1 Building Enclosure Pre-construction Meeting Melissa Payne, BECxP, CxA+BE, CDT Miller Engineering, P.C.
2 Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members are available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
3 Learning Point #1 Understand where in the specifications the BE pre-construction meeting should be specified and what divisions should be referenced.
4 Learning Point #2 Understand what trades should be present and why.
5 Learning Point #3 Understand how to coordinate the building envelope components and why it s important to coordinate them.
6 Learning Point #4 Understand how to resolve compatibility and installation issues that may arise out of a preconstruction meeting.
7 Learning Point #5 Understand what specific details to look for and why they should be discussed at the preconstruction meeting.
8 70% of the our Building Enclosure Consulting services is Forensic Work
9
10 Why is this Happening? Incomplete Design and Construction Documents Time Crunch Design and Construction Skilled Labor The Dying Craft Lack of Inspections Q/A & Q/C Lack of Coordination and Collaboration
11 Not Designed Per Code Clearances, states 4 minimum clearance above earth.
12 Not Designed Per Code Use of gypsum board as a backing board. gypsum board shall not be used as backing for cement plaster.
13 Water Intrusion & Condensation
14 Water Intrusion
15 Environmental Hazards
16 Poor Workmanship
17 Poor Workmanship
18 Poor Workmanship
19 Water Management
20 Water Management
21 Water Damage
22 Lack of Skilled Labor
23 Lack of Inspection
24 Lack of Inspection
25 Lack of Onsite Observation
26 Lack of Collaboration & Communication
27 Lack of Testing & Quality Assurance
28 Pre-Con Meeting Planning Starts in the project manual By specifying a building enclosure pre-construction meeting, the construction team is presented with an opportunity to walk through the project with the design team and the owner. Pre-Design Phase Design Phase Pre- Construction Phase Construction Phase Occupancy Phase
29 Specifications Quality Requirements Design Team Responsibilities Construction Team Responsibilities Pre-Construction Meetings Quality Control and Assurance Plan Functional Performance Testing Inspection and Testing Requirements Mockup Vs. In-Place Air and Water infiltration Thermal Performance Material Performance Properties Pre-Installation Meetings Non-Conformance
30
31
32 14 page specification
33 Related Specifications The Quality Requirements specification should note the following under Part 1 under the Related Documents: Division 03 through 14 Sections for building envelope work required in each Section Also, each section should specify that the installer be present and participate in the pre-construction and preinstallation meetings.
34 Reducing RFI s Experience has shown us that when preconstruction meetings conducted on projects, a reduction in RFI s is realized.
35 Completeness of Submittals Completeness of the building enclosure in the submittal process by requiring the preconstruction meeting occur prior to submittal of product data sheets and shop drawings. If you do not specify it, it will not happen!
36 Pre-Construction Meeting Construction Team Q/C Opportunity Building Enclosure Pre-Construction meeting should be conducted prior to the preparation of product submittal and shop drawings. Pre-Design Phase Design Phase Pre- Construction Phase Construction Phase Occupancy Phase
37 Team Buy-in and Ownership Contractors and trades have an opportunity to provide input and become empowered by having a voice, resulting in project Ownership.
38 What should be covered? Define the project team responsibilities GC and Trades to discuss envelope details to identify the by others Discuss sequencing Compatibility concerns Discuss inspections Cover testing requirements
39 Enclosure Construction Team Owner The Owner representative Design Team Architect/Engineers/Consultants involved in the design of the enclosure Contractor General Contractor s Project Manager and Project Superintendents Subcontractors Concrete Foreman, Carpenter Lead, Weatherproofing Installer, Roofing Lead, Mason Lead, Metal Panel Installer, Glazer Lead, Door Installer, and any trade who constructs or penetrates the building envelope. Manufacturer Rep The product representative of enclosure components.
40 Why all these trades? Any penetration through the control layers becomes a weak point in the enclosure.
41
42
43
44
45
46
47
48
49
50
51 Why should architects care? This process will minimize their risks and it will allow the opportunity to discuss details that may no have been included in the construction drawings. If you specify it, make sure it happens!
52 Architect s Role
53 Architect s Role Budget time to attend and participate in the Pre- Construction Meeting Empowerment and opportunity to address construction concerns early on when changes can be made on paper rather than when the construction is in progress Provide clarification on building enclosure transition and penetration details to ensure that the owner truly gets the building performance he or she expects and paid for Ultimately provide the Owner with a functional, durable, efficient building which is constructible and sustainable
54
55
56 Contractor s Role
57 Contractor s Role To interpret the construction documents and coordinate the subcontractors/trades to do the installation Project Management Construction contract administration, contractor project manager, site coordinator, and phasing schedule coordinator Architectural and engineering understanding Understand the role of each construction participant and be sensitive to the expectations each participant has of the other trades Environmental, Safety, and Health Oversight Facility Operation, Maintenance, and Surveillance Quality Assurance Communicator
58
59 Subcontractor s Role Get in, get out, get paid, and make it to the end of their 1 yr. warranty?
60 Subcontractor s Role The subcontractor is the trade expert providing the labor to perform the work and provide the installation warranty. Typically the contractors are certified by the manufacturers as a qualified installer. When certified as specialist in the trade, they understand the requirements of the manufacturer for installation and means of construction which are acceptable by their selected manufacturer. As the trade specialist, they should take ownership of the installation and offer feedback to the contractor on scheduling, compatibility, and construction requirements.
61 Subcontractor s Role The subcontractor is the trade expert providing the labor to perform the work and provide the installation warranty. Typically the contractors are certified by the manufacturers as a qualified installer. When certified as specialist in the trade, they understand the requirements of the manufacturer for installation and means of construction which are acceptable by their selected manufacturer. As the trade specialist, they should take ownership of the installation and offer feedback to the contractor on scheduling, compatibility, and construction requirements.
62
63 Pre-Installation Meeting Contractor s Quality Control Pre-Installation meetings give everyone a chance to discuss installation in order to ensure the transitions happen per the shop drawings and meet the Owner s project expectations. Pre-Design Phase Design Phase Pre- Constructio n Phase Construction Phase Occupancy Phase
64 All Fun Aside General Contractors, Subcontractors and Manufacturers are great resources!
65 Tribute to Bill Nash May Zelda s Fortune always be in your favor!
66 Melissa I. Payne Building Enclosure Consultant Forensic Investigator Phone: (417) Visit our website at: Millerstructures.com
67 ThankYou!
Air Barrier and shelf angle design, detailing, and lessons learned
Air Barrier and shelf angle design, detailing, and lessons learned Corey S Zussman, AIA, NCARB, ALA, REWC, RWC, RRO, CDT, CQM, LEED AP BD+C Pepper Construction Company Air Barrier Association of America
More informationThe Air Barrier Pre-Installation Meeting
The Air Barrier Pre-Installation Meeting Corey S Zussman, AIA, NCARB, ALA, REWC, RWC, RRO, CDT, CQM, LEED AP BD+C Pepper Construction Company Air Barrier Association of America (ABAA) is a Registered Provider
More informationAudio Sessions. Session 5 MEETINGS. Construction Contract Administration Education Program
Audio Sessions Session 5 MEETINGS Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org This presentation
More informationPractices for Installing
Quality Management Best Practices for Installing Self-Adhering Sheet Air Barriers Chris Bubser, AIA, LEED AP BD+C Mortenson Construction Air Barrier Association of America (ABAA) is a Registered Provider
More informationSuccess Via Vigilance Breaks
National Institute of Building Sciences Provider Number: G168 BECx, Construction, and the Kick-Off Meeting Success Via Vigilance Breaks Alex Connor, David Meyers, & Nick Thornsbury Course Number Date Credit(s)
More informationBECx Design Phase Specification Review Workshop. Design Phase. Construction Risk Management. Building Enclosure Coordination Process
BECx Design Phase Specification Review Workshop Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by William R. Nash Design Phase Pre Design
More informationUse of Commissioning for LEED Projects. H. Jay Enck President Commissioning & Green Building Solutions, Inc.
Use of Commissioning for LEED Projects H. Jay Enck President Commissioning & Green Building Solutions, Inc. AIA Quality Assurance Learning Objectives 1. Use of the commissioning process for more efficient
More informationCommissioning the Building Envelope
Thank you to our Conference Sponsors! Silver Sponsors Bronze Sponsor Commissioning the Building Envelope Brian H. Neely, AIA, NCARB, CDT March 27,2014 Gale Associates, Inc. E n g i n e e r s a n d P l
More informationAudio Presentation. Session 3 DESIGN. Project Delivery Education Program. Construction Document Technology (CDT) Preparatory Course
Audio Presentation Session 3 DESIGN Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 www.csinet.org This presentation is protected by US and International
More informationROLES AND RESPONSIBILITIES
Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationLeveraging Brute Force. Steve Cook // The Walsh Group // 03 November 2011
Leveraging Brute Force Steve Cook // The Walsh Group // 03 November 2011 The Associated General Contractors of America (AGC) is a Registered Provider with The American Institute of Architects Continuing
More informationCodes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS
Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute
More informationSECTION CONTRACTOR QUALITY CONTROL
SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationBuild it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning
Build it Right the First Time: Building Envelope Commissioning/ Retro-Commissioning NFMT 2016 T. Stephen Kisielnicki, RWC, LEED AP, BECxP March 24, 2016 About Gale Building Envelope Technology Roof, walls,
More informationGuideline for Building Envelope Commissioning: New Buildings
Guideline for Building Envelope Commissioning: New Buildings Introduction Building envelope failures may arise from inadequacies in the design, construction and operation of buildings and appear to be
More informationSECTION QUALITY REQUIREMENTS
SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.
More informationIndustry Updates. Ryan Dalgleish. Air Barrier Association of America
Industry Updates Ryan Dalgleish Air Barrier Association of America Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute of Architects Continuing Education Systems.
More informationDeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT
DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationChapter 3 Other Stakeholders Duties
Chapter 3 Other Stakeholders Duties Everyone involved in the special inspection process has a responsibility to perform their agreed upon duties correctly and in a timely fashion during the project. In
More informationCONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION
PHASE 1: PRE-CONSTRUCTION Schematics Phase Based upon program requirements and design parameters, D&J will establish conceptual budget and preliminary schedule for the project, which will highlight specific
More informationWe met at the parapet and it was transition at first sight. Christine Cronin, Building Science Corporation
We met at the parapet and it was transition at first sight Christine Cronin, Building Science Corporation Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute
More informationAddendum #2 B14/9830. East Campus Student Life/Business Services/DSR Renovation
September 25, 2013 Addendum #2 B14/9830 East Campus Student Life/Business Services/DSR Renovation SPECIFICATIONS for East Campus Student Life/Business Services/DSR Renovation Dated: September 5, 2013 This
More informationQUALITY REQUIREMENTS
SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationSECTION QUALITY CONTROL
SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.
More informationImplementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and
More informationPRE-INSTALLATION MEETING RECORD
Meeting Date: Meeting Location: Description of Work To Be Discussed: Attendees (in most cases must include the trade contractor s foreman who will actually be out in the field doing the work): NAME POSITION
More informationFull-Scope Commissioning for High-Quality Buildings
Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building
More informationAir Barrier Considerations for Roof/Wall Intersections. Presented by Laverne Dalgleish Air Barrier Association of America
Air Barrier Considerations for Roof/Wall Intersections Presented by Laverne Dalgleish Air Barrier Association of America Credit(s) earned on completion of this course will be reported to AIA CES for AIA
More informationUNDERSTANDING DIFFICULT CRITICAL TRANSITIONS OF AVB SYSTEMS
UNDERSTANDING DIFFICULT CRITICAL TRANSITIONS OF AVB SYSTEMS COREY S ZUSSMAN AIA, NCARB, ALA, REWC, RWC, RRO, CDT, CQM, LEED AP BD+C PEPPER CONSTRUCTION Air Barrier Association of America (ABAA) is a Registered
More informationDesigning and Constructing a High-Performance Building Envelope for Multi-Unit Affordable Housing
Designing and Constructing a High-Performance Building Envelope for Multi-Unit Affordable Housing Jeffrey Davis, AIA, LEED AP FortyEighty Architecture Debbie Clark, NCARB, LEED AP FortyEighty Architecture
More informationMeasuring the Impact of BIM in Design-Bid-Build
Measuring the Impact of BIM in Design-Bid-Build A Case Study Dace A. Campbell, AIA, LEED AP // BNBuilders // 2 November 2011 The Associated General Contractors of America (AGC) is a Registered Provider
More informationBuilding Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506
AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationThermal Bridging Solutions. Improving Building Envelope Performance
Thermal Bridging Solutions Improving Building Envelope Performance AIA Best Practices Armatherm sponsors this program provided by Hanley Wood, a Registered Provider with the American Institute of Architects
More informationLATERAL DRIFT DESIGN IN COLD FORMED STEEL WALL SYSTEMS
1 LATERAL DRIFT DESIGN IN COLD FORMED STEEL WALL SYSTEMS Thomas Castle, S.E. 2 This presentation is published by the Cold-Formed Steel Engineers Institute ( CFSEI ). The information herein shall not constitute
More informationCONSTRUCTION DOCUMENTS Part 1
Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationDIVISION 1- GENERAL REQUIREMENTS
DIVISION 1- GENERAL REQUIREMENTS This division contains the following elements: 1.1 General 1.2 Summary of Work 1.3 Administration 1.4 Quality 1.5 Temporary Facilities 1.6 Products 1.7 Execution 1.8 Closeout
More informationCompliance for Continuous Insulation, Water Resistive Barriers & NFPA-285 What you need to Know
Compliance for Continuous Insulation, Water Resistive Barriers & NFPA-285 What you need to Know www.dryvit.com 800-556-7752 1 AIA / CES Dryvit Systems, Inc. is a Registered Provider with The American Institute
More informationOwner s Representative SCOPE OF SERVICES
Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,
More informationAvoiding Specification Pitfalls!
1 Continuing Education This program is a registered provider with The American Institute of Architects Continuing Education Systems. Credit Earned on completion of this program will be reported to CES
More informationQuestions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
AIA Honolulu is a Registered Provider with the American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members.
More information150/ G Versus 150/ H Contractor Quality Control Program
AC 150/5370-10G AC 150/5370-10H 1 Part 1 of General Provisions Part 2 of General Construction Items 2 Section 100 Item C-100 3 Quality Control Program (CQCP) 4 100-01 General. When the specification requires
More informationBULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL PRACTICE
200-4010 Regent Street Burnaby BC V5C 6N2 Canada Telephone: (604) 430-8035 Toll Free Canada-wide: 1-888-430-8035 Facsimile: (604) 430-8085 BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL
More informationAttachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #
UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial
More informationBUILDING ENCLOSURE COMMISSIONING EDUCATION
BUILDING ENCLOSURE COMMISSIONING EDUCATION Building Enclosure Technology and Environment Council - BETEC Wagdy Anis, FAIA, LEED AP Lead Instructor Building Enclosure Technology and Environment Council
More informationThoughts on Managing Site Visits
Hanover Architects & Engineers Advantage Thoughts on Managing Site Visits Construction phase services are an important element of any design contract involving construction. Design documents cannot be
More informationC. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.
SECTION 01400 QUALITY CONTROL SERVICES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification
More informationBuilding Enclosure Commissioning of a Student Athletic Facility
Building Enclosure Commissioning of a Student Athletic Facility Presented by: Paul Totten, PE, Senior Project Manager BEST3 Conference Atlanta, Georgia 3 April 2012 www.sgh.com Presentation Outline Section
More informationCOMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202
COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning
More informationCommissioning the Project Schedule
Commissioning the Project Schedule Matthew S. Malinosky, PE, LEED AP BD+C, CCP Mechanical Engineer Molly B. Meyer, PE, LEED AP BD+C, CEM Mechanical Engineer AIA Quality Assurance The Building Commissioning
More informationQA/QC Program Overview. November, 2015
QA/QC Program Overview November, 2015 Quality Roles on the Project Construction Management Oversight (CMO-Turner) functions as the TJPA s eyes and ears. Construction Manager/General Contractor (CM/GC-
More informationStudent Services & Classroom Addition
SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services
More informationSECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS
SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.
More informationFL200 13/4 x41/2 GUIDE SPECIFICATION. Non-Thermal Storefront
Manufacturer: Coral Architectural Products 3010 Rice Mine Road Tuscaloosa, AL. 35406 Voice: (800) 772-7737 Fax: (800) 443-6261 SECTION 08410 ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS This suggested guide
More informationRFP for Building Enclosure Consulting Services Proposal Request No Answers to Questions Asked as of 11/01/2017
RFP for Building Enclosure Consulting Services Proposal Request No. 17-0137 Answers to Questions Asked as of 11/01/2017 1. What extent of project documents will be available for the building enclosure
More information2008 Questions & Solutions Engineering, Inc.
BNP Media is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates
More informationFL550T 21/2 x5. GUIDE SPECIFICATION Series FL550T Thermal (21/2 x 5 ) Impact-Resistant Storefront. Thermal Impact-Resistant Storefront
Series FL550T Thermal (21/2 x 5 ) Impact-Resistant Storefront Manufacturer: Coral Architectural Products 3010 Rice Mine Road Tuscaloosa, AL. 35406 Voice: (800) 772-7737 Fax: (800) 443-6261 SECTION 08410
More informationCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.
More informationProjectwide ROI. A team approach to gaining BIM Benefits (Arizona State University ISTB IV) Dan Russell / Sundt Construction / November 2, 2011
Projectwide ROI A team approach to gaining BIM Benefits (Arizona State University ISTB IV) Dan Russell / Sundt Construction / November 2, 2011 The Associated General Contractors of America (AGC) is a Registered
More informationKeene Building Products
Keene Building Products Keene Building Products is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported
More informationFlooring Contractor QA/QC Plan Sample Selected pages (not a complete plan)
Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact:
More informationCommunications Contractor QA/QC Plan Sample
Communications Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Communications Standards & Inspection Forms Contact: Ed Caldeira
More information-TESTING AND COMMISSIONING
MEP CONSTRUCTION DESIGN STAGE -CONSTRUCTION PHASE -TESTING AND COMMISSIONING Consultant Project Management Team refer also to Consultant or Site Consultant They do Site Supervision-surveillance or official
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationCode Compliant Fire- Resistance Design for Wood Construction
Code Compliant Fire- Resistance Design for Wood Construction (BCD220-2) Paul Coats, PE, CBO Southeast Region Manager American Wood Council The American Wood Council is a Registered Provider with The American
More information(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet
(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:
More informationMSBA OWNERS PROJECT MANAGER ROUNDTABLE
MSBA OWNERS PROJECT MANAGER ROUNDTABLE September 12, 2018 Winchester High School Winchester, MA AGENDA 9:00 A.M. Welcome and Introduction 9:05 A.M. Presentation Commissioning Experiences on MSBA Projects
More informationIntegrated Air & Water Barrier Systems
Integrated Air & Water Barrier Systems Presented by [ Jeff Presenter s Key, Georgia-Pacific Name ] Wood Products AIA Course: GP-FF-WRBAB Credit Designation: LU HSW Please add relevant logo here Disclaimer:
More informationCopyright Materials 11/8/2012. Learning Objectives
Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited.
More informationInvolving Stakeholders in the Professional s Design and Construction Process
Involving Stakeholders in the Professional s Design and Construction Process Presented By: Peter Trozze, AIA Managing Director of Middle Eastern Operations Continuing Education The Middle East Chapter
More informationEnergy-Efficient Facilities: Building Envelope Design. Wall Systems. Copyright Materials. Course Description
Energy-Efficient Facilities: Building Envelope Design Steve Easley steve@steveeasley.com Wall Systems www.steveeasley.com Copyright Materials This presentation is protected by US and International Copyright
More informationTransit Center Waterproofing Systems. December 2015
Transit Center Waterproofing Systems December 2015 Agenda Waterproofing Systems Overview Roof Level Waterproofing Systems Physical Glass Monitoring Jar System Electronic Leak Monitoring Mesh System Fountain
More informationDRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL
1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (November 2016) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 00.00 10 (February 2010) UNIFIED FACILITIES GUIDE
More informationOccupational Outlook Handbook, Edition
Page 1 of 6 Occupational Outlook Handbook, 2006-07 Edition U.S. Department of Labor Bureau of Labor Statistics Bulletin 2600 Construction Managers Nature of the Work Working Conditions Training, Other
More informationWorking with roof consultants can be beneficial, but there are
30 www.professionalroofing.net JULY 2013 During the 2013 International Roofing Expo, I moderated an NRCA panel that explored the relationships between roofing contractors and roof consultants. Although
More informationOBTAINING LEED CERTIFICATION FOR TOILET PARTITIONS. By AMPCO Products, LLC
OBTAINING LEED CERTIFICATION FOR TOILET PARTITIONS By AMPCO Products, LLC AMPCO PRODUCTS is a registered provider with The American Institute of Architects Continuing Education Systems. Credit earned on
More informationJanitorial QA/QC Manual Sample
Janitorial QA/QC Manual Sample Selected pages (not a complete plan) Reporting Forms Inspection Forms Contact: Ed Caldeira 410-451-8006 Pat [Pick the date] [CompanyName] Janitorial Services Operating Policies
More informationEnergy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort
Please add relevant logo here Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort Presented by: Peter J. Arsenault, FAIA, NCARB, LEED-AP Disclaimer: This presentation was developed by
More informationFinding Value in Building Enclosure Commissioning
Finding Value in Building Enclosure Commissioning Brian S. Rose, P.E. Technical Staff Jeffrey D. Kerr, P.E. Senior Project Manager 12 March 2015 www.sgh.com Course Description This presentation will outline
More informationThe construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.
L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally
More informationREQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components
REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro
More informationIntroduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1
Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:
More informationCardinal Commercial Products ALUMINUM STOREFRONT SYSTEM SERIES CF450 GUIDE SPECIFICATIONS SECTION ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS
Cardinal Commercial Products ALUMINUM STOREFRONT SYSTEM SERIES CF450 GUIDE SPECIFICATIONS SECTION 08410 ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS This suggested guide specification has been developed using
More informationPerformance Testing for Quality Assurance and Commissioning
BEST 4 Conference: April 13, 2015, Kansas City, MO Performance Testing for Quality Assurance and Commissioning Fiona Aldous Principal The most benefit to a project is obtained during the Design Phase -
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 20 (February 2010) Changed 1-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02.10 (November 2008) UNIFIED FACILITIES
More informationEx AC. Examination for Architects in Canada Examen des architectes du Canada
Ex AC Examination for Architects in Canada Examen des architectes du Canada General and Specific Objectives Theme 1 general objective specific objectives rogramming 1.1 Understand the process for the preparation
More informationCHAPTER 3: Modern Methods of Construction (MMC)
CONTENTS 3.1.1 INTRODUCTION 3.1.2 SUITABILITY OF SYSTEMS AND COMPONENTS 3.1.3 TYPES OF MODERN METHODS OF CONSTRUCTION (MMC) 3.1.4 SUITABILITY OF SYSTEMS TO MEET WARRANTY REQUIREMENTS FUNCTIONAL REQUIREMENTS
More informationVILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information
VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction
More informationISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal
More informationMy Role and Background
Provider #: K054 VS02: 60 Sites, 50 Miles and 5 Key Lessons Learned How One School District Made the Move to IP Video Surveillance Brian Johnson Escambia County School District April 10, 2013 My Role and
More informationBUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P
BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P Provider Number:404108121 Darek Brandt, PE Chief Engineer, Building Science Solutions AIA CES DISCLAIMER Credit(s) earned on completion
More informationFacilities Planning and Construction (FP&C)
Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:
More informationConstruction Documents Education Program
PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected
More informationStage: A Case Study. Course Description. Learning Objectives
Arena Stage: A Case Study Brought to Lifeto The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES), Provider #G516. Credit(s)
More informationSTUDY GUIDE. For the REGISTERED EXTERIOR WALL OBSERVER (REWO ) EXAM. Prepared By REWO Examination Development Committee
STUDY GUIDE For the REGISTERED EXTERIOR WALL OBSERVER (REWO ) EXAM Prepared By REWO Examination Development Committee RCI, Inc. 1500 Sunday Drive Ste 204 Raleigh, NC 27607 800-828-1902 919-859-0742 FAX
More informationSTANDING SEAM METAL ROOFING. Presented by MBCI Credit: 1 AIA LU/HSW AIA course number: SSRLU2B
STANDING SEAM METAL ROOFING Presented by MBCI Credit: 1 AIA LU/HSW AIA course number: SSRLU2B Credit earned on completion of this course will be reported to AIA CES for AIA members. To receive a certificate
More informationPW251 21/2 x7 GUIDE SPECIFICATION. Curtain Wall
Manufacturer: Coral Architectural Products 3010 Rice Mine Road Tuscaloosa, AL. 35406 Voice: (800) 772-7737 Fax: (800) 443-6261 SECTION 08900 ALUMINUM CURTAIN WALL This suggested guide specification has