1 JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015
2 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation of JOC Concept Competitive Bidding Process Procedures for Developing a Job Order Benefits of Job Order Contracting
3 WHO WE ARE The Gordian Group Provides Construction Procurement Services To Facility and Infrastructure Owners Public and Private Owners from Every Sector Our Mission To Support Organizations Pursuing Efficient and Effective Construction Procurement and Information Solutions with a Variety of Products and Services Built on Three Pillars 1. Data 2. Software 3. Expertise The Gordian Group is not a contractor We are a consultant specializing in innovative procurement solutions, based on our unique capabilities with construction data, software and expertise.
4 INTRODUCTION TO JOC Our Most Widely-used Procurement Solution is Job Order Contracting (JOC) Job Order Contracting Provides: A Means to Accomplish a Substantial Number of Individual Projects with a Single Competitively Bid Contract On-Call Contractors Ready to Perform a Series of Projects at Different Locations for Competitively Bid Prices Types of Work to be Completed: Straightforward, Renovation, Upgrade, Replacement in Kind Projects Focus on Projects that Exceed Competitive Bidding Threshold JOC is an innovative method of procurement, but construction is delivered in the typical way
5 JOC - BACKGROUND Introduced In the United States in 1985 Dept. of Defense, NASA, etc. Over 1,000 Contracts in Use Over $1.5 Billion of Construction Placed Annually Implemented by States, Counties, Major Cities, Universities & Private Owners New York State Office of General Services United States Postal Service Los Angeles Unified School District City of Chicago Department of General Services New York City Department of Education Florida Power & Light The Pennsylvania State University New Jersey Department of Transportation Georgetown University
6 SAMPLE STATEWIDE PROGRAMS Statewide Programs are Shared Among Many Users, and often Referred to as Cooperative Purchasing. Connecticut Capitol Region Council of Governments Pennsylvania Keystone Purchasing Network Maryland, Virginia, and District of Columbia - NJPA Georgia Department of Administrative Services Ohio Department of Administrative Services Michigan - NJPA Minnesota NJPA Texas Texas Buy Board Arizona Department of Administrative Services New Jersey Middlesex Regional Education Services Commission
7 WHY JOB ORDER CONTRACTING? Traditional Bid System can be Slow and Costly Months (Sometimes Years) from Project Identification to Contract Prepare Full Set of Bid Documents, Advertise, Conduct Pre-bids and Bid Openings, and Formally Award Contracts Owner May not be Happy with Low Bidder; Contractor Reputation and Quality is Meaningless Adversarial Relationship Between Owner and Contractor Administrative, Pricing and Scheduling Issues with Change Orders JOC Offers a Cost Effective & Efficient Alternative Faster Response; Days or Weeks instead of Months Traditional Bid Process Conducted Once, Not Over and Over. Well Defined, Goal Oriented Administration Owner and Contractor Work in Partnership No Negotiation of Change Orders; Prices are Known Upfront Transparent, Documented Process Fully Auditable Performance Based System Rewards High-Quality Contractors
8 UNION CONTRACTING, JOC AND GORDIAN JOC is Simply a Procurement Method Like Design-Bid-Build, Design-Build, T&M, etc. JOC Neither Favors Nor Harms Union Construction The Gordian Group Does Support Union Construction Safety, Efficiency, Productivity and Availability of Workforce High-Quality, High-Efficiency Contractors with Reputation of Success The Gordian Group Supports Increased Bidder Standards Around the Country Pre-qualification of Bidders, Best-Value Selection of Contractors, OSHA 30-Hour Workforce Training, Apprenticeship Where Authorized by Law, Gordian Recommends these tools to Clients Where Not Authorized by Law, Gordian is Working with Interested Partners in the Construction Community to Authorize these Provisions Gordian Wants a Partnership with Carpenters and Carpenter Contractors
9 GORDIAN S JOC DELIVERY MODEL
10 JOC CONTRACT DOCUMENTS 1. Front End Documents Information for Bidders Bid Forms Scope of Work General Conditions Insurance Requirements Defines Geographic Area Estimated Annual Values
11 JOC CONTRACT DOCUMENTS 2. Construction Task Catalog Catalog of over 275,000 Pre-Priced Tasks Based on Local Prevailing Wage Rates, Local Material & Equipment Costs Customized task description, unit of measurement, and unit price
12 JOC CONTRACT DOCUMENTS 3. Technical Specifications Specifies Quality of Materials and Workmanship Corresponds with Tasks in the Construction Task Catalog 12
13 OPTIONS FOR JOC CONTRACTS JOC for Different Trades: GC, HVAC, Electric, Plumbing: Separate Regions, or Building Types, or Departments
14 PRE-BID GUIDANCE TO CONTRACTORS Review Construction Task Catalog in Detail Present Examples of Price Proposals Prior to Bidding Owner Does Not Commit to: Any Specific Project Any Specific Quantities or Tasks Owner Does Commit to: Fixed Contract Term e.g., one year, two years. Fixed Geographic Area Guaranteed Minimum Value of Work $10,000, $25,000, $50,000, etc. Estimated Annual Value or Maximum Contract Value $1,000,000, $5,000,000, etc., Depending on Trade and Region
15 JOC BIDDING PROCESS Public Owners Award Based on Competitive Bid Contractors Bid Adjustment Factors to be Applied to the Preset Unit Prices in the Construction Task Catalog Normal Working Hours: 7:00 am to 4:00 pm Monday Friday Other Than Normal Working Hours: 4:00 pm to 7:00 am Monday Friday, and all day Saturday, Sunday and Holidays Adjustment Factors Apply to All Tasks in the Task Catalog Each Adjustment Factor is Weighted and Combined Lowest Combined Adjustment Factor From a Responsive, Responsible Bidder Wins! Private Owners and some Public Owners can Award JOC Contracts Based on Other Factors Best Value or Qualification Based Selection Process Bid to a Prequalified Group of Contractors
16 PRICE PROPOSAL FORMULA JOC is not a Time and Materials Contract Contractors Paid for Each Task Performed Importance of Adjustment Factors Determines Winning Bidder AND Used to Price Individual Job Orders Price Proposal Total = Lump Sum Job Order Price
17 Joint Scope Meeting Review Detailed Scope of Work Discuss Schedule Request for Proposal Contractor Develops Proposal Selects Tasks and Quantities Basic Work Schedule Subcontractor Plan Contractor s Proposal Reviewed Owner Reviews Proposal Contractor Makes Required Changes Owner Issues Lump Sum Job Order JOC EXECUTION PROCESS
18 JOC MANAGEMENT SOFTWARE Internet Based Software Provided with Contract egordian Software Automates the Proposal Process Generates all Forms and Management Reports 18
19 ADMINISTERING JOC CONTRACTS Owner Holds all Contracts with JOC Contractors Owner Can Manage JOC Process with In-House Staff Joint Scope Meetings Prepare Detailed Scopes of Work Review Price Proposals Manage Construction Owner Can Engage Construction Manager to Manage JOC Process, or Certain Portions of Process Owner Can Engage A/E Professionals to Prepare Detailed Scopes of Work
20 CONTRACT DETAILS Payment and Performance Bonds Can be Required at Award for Full Contract Value, or for each Job Order Alternatively, Owner may not Require Bonds Can be Included in Adjustment Factor or Reimbursed for each Job Order Differing Site Conditions Priced from Construction Task Catalog No Negotiated Change Orders Developed Just Like Original Job Order Joint Scope Meeting, Detailed Scope of Work, RFP and Price Proposal Filings and Permits Fees Paid for All Permits; Reimbursed 100% Subcontracting Requirements Owner may Incorporate MBE/WBE Requirements
21 WHY JOC WORKS JOC Addresses a Series of Individual Projects with a Single Competitively Bid Contract Contractor Has a Continuing Financial Incentive To Provide: Responsive Services Accurate Price Proposals Deliver Quality Work on Time Future Job Orders Tied to Contractor Performance No Obligation To Award Specific Projects Contractor not Guaranteed Specific Volume of Work High-Quality Contractors are Rewarded with More Projects Not Restrictive; Owner Can Use All Other Methods to Complete Work
22 JOC SAVES TIME & MONEY Los Angeles Unified School District Calculated cost savings of 9.26% for 2,587 JOC projects reviewed. New York State University Construction Fund Found an average cycle time for a JOC project from Project Initiation to Job Authorization is 15 days compared to 95 days for a traditional construction project, a savings of 80 days. New Jersey Department of Transportation Found JOC contracts are 12% more cost effective than Time & Material contracts Chicago Board of Education Average cost savings of 8.6% for all City JOC contracts. New York City Board of Education Discovered the average duration from project identification to issuance of the Job Order is 42 days, compared with an average duration of approximately seven (7) months under the traditional system, an 80% time savings. City of Miami Beach JOC tripled the volume of projects completed, decreased procurement time by 89%, and eliminated change orders, protests and litigation. Won the Best of the Best Award from the National Institute of Governmental Purchasing (NIGP)
23 SUMMARY JOC is a Proven System with a 30-Year Track Record of Success Over $1.5 Billion of Construction Completed Each Year Enables Owners to Complete a Series of Individual Projects with a Single Competitively Bid Contract Fixed Pricing for all Work Eliminates the Need to Negotiate Change Orders JOC Saves Money JOC Saves Time Increases Options for Owner to Complete More Work Gordian wants to partner with you Lobby to Improve Bidder Standards Encourage More Carpenter Contractors to Bid JOC Contracts
JOB ORDER CONTRACTING INFORMATIONAL SEMINAR. Monday, June 27, 2016
JOB ORDER CONTRACTING INFORMATIONAL SEMINAR Monday, June 27, 2016 2 AGENDA JOC Overview JOC Process JOC RFPQ Documents Benefits of JOC to Contractors Questions 3 JOC OVERVIEW Job Order Contracting is an
More informationJob Order Contracting Industry Information Session
Job Order Contracting Industry Information Session DECEMBER 9, 2013 1 Agenda JOC Overview Benefits of JOC to Contractors JOC Contract Documents JOC Process JOC Management Software Understanding the CTC
More informationPresenters Benjamin Huff, NYCDEP Paul R. Schreyer, The Gordian Group
JOC Case Study: New York City's Toilet Replacement Project Presenters Benjamin Huff, NYCDEP Paul R. Schreyer, The Gordian Group Agenda Part 1: The Problem Part 2: Job Order Contracng Overview Part 3: The
More informationJob Order Contracting (JOC) ITB JE Overview August 2016
Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.
More informationMaintenance, Repair, and Operations JOC Program
Maintenance, Repair, and Operations JOC Program Pre-Proposal Meeting CSP #16-11-07 Building Automation Systems CSP #16-11-08 Glass and Glazing Service CSP #16-11-09 HVAC / Mechanical CSP #16-11-10 Plumbing
More informationCalifornia State University Regional General
California State University Regional General JOB ORDER CONTRACTING Pre-Bid Meeting December 15, 2015 DISCLAIMER Nothing written in this presentation, or said during this pre-bid webcast supersedes what
More informationJOB ORDER CONTRACTING INFORMATIONAL PRESENTATION
JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION FOR PROSPECTIVE SANDAG CONTRACTORS March 2, 2016 1 WELCOME & INTRODUCTIONS 2 AGENDA Overview of Job Order Contracting (JOC) SANDAG s JOC Program SANDAG
More informationCalifornia State University Immediate Response
California State University Immediate Response JOB ORDER CONTRACTING Pre Bid Meeting November 19, 2015 Disclaimer Nothing written in this presentation, or said during this pre bid webcast supersedes what
More informationJOB ORDER CONTRACTING / JOC A LEAN Best Management Practice for Efficient Construction Project Delivery
JOB ORDER CONTRACTING / JOC A LEAN Best Management Practice for Efficient Construction Project Delivery All product and company names are trademarks or registered trademarks of their respective holders.
More informationJOB ORDER CONTRACTING (JOC)
JOB ORDER CONTRACTING (JOC) A LEAN Best Management Practice for Efficient Construction Project Delivery All product and company names are trademarks or registered trademarks of their respective holders.
More informationJOB ORDER CONTRACTING INFORMATIONAL PRESENTATION
JOB ORDER CONTRACTING INFORMATIONAL PRESENTATION FOR PROSPECTIVE SANDAG CONTRACTORS April 21, 2016 1 WELCOME & INTRODUCTIONS 2 AGENDA Overview of Job Order Contracting (JOC) What is the process for a JOC
More informationConstruction Needs On Renovation, Remodeling & Repair 02/21/07 1
Job Order Contracting Responsive Solution for Facility Owners Construction Needs On Renovation, Remodeling & Repair Projects 02/21/07 1 In the Beginning i Initial Concept Developed Department of Army Army
More informationPublic Building Commission of Chicago Terms and Tools for Public Capital Development and Financing
Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan
More informationCHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS
CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical
More informationRick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative
Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative This presentation will cover: What is JOC? JOC contracting terms JOC experience Types
More informationYou Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements
You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG
More informationJim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide
Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide array of design, construction, construction administration,
More informationAdvance Collaborate Enrich
Job Order Contracting 101 A Facilities Management Tool Sponsored by the Center for Job Order Contracting Excellence and The National Association of State Facilities Administrators Job Order Contracting
More informationConstruction Back-Log Solution Begins With Proposal Stage
Construction Back-Log Solution Begins With Proposal Stage Developing the Job Order Contract Request for Proposal (RFP) By: Vince Duobinis, Senior Market Development Manager Kelvin King, Director, Market
More informationConstruction Contracts
Construction Contracts By Dr. Ibrahim Assakkaf Construction Contracts By Dr. Ibrahim Assakkaf 1 The Need Web-based Contracts Supporting scheduling Controlling Regulating Analyzing Auditing the procurement
More informationJOB ORDER CONTRACTS (JOC) PROGRAM
City and County of San Francisco Department of Public Works JOB ORDER CONTRACTS (JOC) PROGRAM JOC-J23 General Building Services (ID NO. JCC14023) B-License JOC-J24 General Engineering Services (ID NO.
More informationPUBLIC CONTRACT CODE SECTION
PUBLIC CONTRACT CODE SECTION 22160 22169 22160. (a) The Legislature finds and declares that the design build method of project delivery, using a best value procurement methodology, has been authorized
More informationPublicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build
1 Leigh Sata, Santa Rosa Junior College Kelle Lynch McMahon, Peralta Community College Mark Kelley, Dannis Woliver Kelley Deidree Sakai, Dannis Woliver Kelley 2 1 Publicly Bid: Design-Bid-Build Multiple-Prime
More informationWEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES
1. Introduction WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES The Town of West Yellowstone (Town) is seeking a qualified
More informationCommittee Meeting. Procurement Processes for Professional Services and Contractors
Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional
More informationLB 889 The Political Subdivisions Construction Alternatives Act
1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.
More informationReport on Effectiveness of the Construction Manager at Risk Project Delivery Method
Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to
More informationDesign-Build (DB) and Construction Manager / General Contractor (CMGC)
Design-Build (DB) and Construction Manager / General Contractor (CMGC) IDOT and Industry Preliminary Joint Review for Proposed Legislation December 18, 2012 Welcome Introductions Agenda Purpose Definitions
More informationMore Construction Projects Completed + Less Burden On Staff = Job Order Contracting. Job Order Contracting (JOC) 3 Identifying Features
More Construction Projects Completed + Less Burden On Staff = Job Order Contracting Construction Management Tuesday, August 19, 2008 2:30 p.m. - 3:30 p.m. Room 343 Job Order Contracting (JOC) A contracting
More informationProject Labor Agreements. September 18, 2012
Project Labor Agreements September 18, 2012 Project Labor Agreements - Definitions Pre-Hire Collective Bargaining Agreement Used on Large Complex Construction Projects Employing Multiple Trades Terms and
More informationLease-Leaseback Project Delivery Method
Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,
More informationPennsylvania Public Private Transportation Partnership Board
Pennsylvania Public Private Transportation Partnership Board Friday, September 27, 2013 511PA /Traveler Information System Request for Information (RFI) issued jointly by PennDOT & Pennsylvania Turnpike
More informationREQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES For the renovation of existing apartment buildings August 15, 2016 INVITATION Bath Housing Development Corporation is soliciting proposals for
More informationALTERNATIVE PROJECT DELIVERY METHODS
ALTERNATIVE PROJECT DELIVERY METHODS Capital Contracting Office April 2016 1 This Class will Cover Overview of Contracts Focus on CMR and JOC Contracting Opportunities Contract Tool Box: Choosing the right
More informationConstruction Documents Education Program
PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected
More informationProcurement Policies and Procedures
Center for Economic and Social Development Procurement Policies and Procedures 1. Purpose of procurement standards. The purpose of these standards is to establish procedures for the Center for Economic
More informationAlternative Delivery Methods in the Post-Davis World
CASBO 2017 Annual Conference April 2017 Alternative Delivery Methods in the Post-Davis World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson
More informationCollaboration Today: Better Buildings Tomorrow
Collaboration Today: Better Buildings Tomorrow ith technological innovation a constant, the construction industry is in a perpetual state of evolution, continually in flux. This is the way it has always
More informationDesign Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright
Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development
More informationPROFESSIONAL PRACTICE 544
PROFESSIONAL PRACTICE 544 April 20, 2015 Contracting Methods Alternative Project Delivery Methods Michael J. Hanahan, Esq. Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com
More informationFACILITY PROJECT BIDDING OPTIONS OVERVIEW
FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationProject Delivery Breakthroughs for Improving Energy Efficiency
Tuesday, June 11, 2013 8:30 am 9:45 am, Garden Salon One, 2nd Fl. Presented by: Kenneth R. Downes, Architect/Engineer, United States Postal Service Matt Peterson, Contract Manager, National Joint Powers
More informationREQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE
REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE Proposals Solicited by: City of Nanticoke 15 East Ridge Street Nanticoke, PA 18634 C:\Users\jim\Desktop\Nanticoke City\07222013professionalengservices\Engineer
More informationNeighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
More informationConnoisseur Solutions Project Procurement Management
Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes
More informationCRISP Azure Migration Consulting Services. All responses due no later than Friday, July 21 st, at 5pm EST
Request for Quote CRISP Azure Migration Consulting Services Friday, July 7th, 2017 All responses due no later than Friday, July 21 st, at 5pm EST 1 Request for Quote RFQ TO ALL RESPONDERS CRISP Azure Migration
More informationTime to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO
Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from
More informationChapter 4 State Requirements for Educational Facilities Section 4.1
providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,
More informationProfessional Practice 544
Spring Semester 2017 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights
More informationThe Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents
The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents CCDC Standard Construction Documents CCDC 2-1994 Stipulated Price Contract Standard prime contract between
More informationProfessional Practice 544
Spring Semester 2018 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights
More informationEJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center
EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationALTERNATE FORMS OF PROJECT DELIVERY
ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors
More informationAdministration Bldg. #9 Purchasing Department- Ground Floor Suite 12 One College Drive, Toms River, New Jersey 08753
ADDENDUM 1 BID- Background Check Screening Services Reference 13/14 B46 New due date: Location: December 20, 2013 10:00 a.m. Ocean County College Administration Bldg. #9 Purchasing Department- Ground Floor
More informationNOTICE TO BIDDERS FOR
CITY OF SAN LEANDRO STATE OF CALIFORNIA ENGINEERING AND TRANSPORTATION DEPARTMENT NOTICE TO BIDDERS FOR MONARCH BAY DRIVE BRIDGE REPAIR PROJECT NO. 12-144-38-324 BID NO. 12-13.013 1. BID OPENING: The bidder
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationConstruction Project Delivery Methods
Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031
More informationNeighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
Subrecipient Administrative Training (SAT) Meeting NJEDA Office, Trenton, NJ December 18, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
More informationStriking While the Climate is Hot: New Program Design for Accelerated Delivery of Energy Retrofit Projects
Striking While the Climate is Hot: New Program Design for Accelerated Delivery of Energy Retrofit Projects Christine Vance and Terry O Sullivan, City and County of San Francisco Leslie Kramer, HDR, Inc.
More informationConstruction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119
Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts
More informationCCA Contract Forms Type Members Non-Members
To order CCA documents and/or seals please email planroom@saskatoonconstruction.ca CCA Contract Forms Type Members Non-Members CCA 1-2008 Stipulated Price Subcontract Electronic $52.00 $67.00 Seals $6.00
More informationALTERNATIVE CONTRACTING METHODS
ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional
More informationLM032: Advanced Tendering Procedures & Bid Evaluation
LM032: Advanced Tendering Procedures & Bid Evaluation LM032 Rev.001 CMCT COURSE OUTLINE Page 1 of 6 Training Description: The engagement and management of contractors and suppliers is a vital part of the
More informationHow to Respond to Bids issued by Miami-Dade County Public Schools ( M-DCPS )
How to Respond to Bids issued by Miami-Dade County Public Schools ( M-DCPS ) Presented by: Melody Thelwell, MPA Chief Procurement Officer Procurement Management Services Bids?? What s that? Where does
More informationLEVEL I PREQUALIFICATION DOCUMENTS
Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,
More informationSellwood Bridge Replacement Slayden Sundt JV. Diversity Plan
Sellwood Bridge Replacement Slayden Sundt JV Diversity Plan A. Diversity Plan Objectives Slayden-Sundt shares in the County s commitment to diversity in all aspects of the Sellwood Bridge Replacement project.
More informationHow to Increase Business Opportunities by Responding to Bids from Miami Dade County Public Schools ( M DCPS )
How to Increase Business Opportunities by Responding to Bids from Miami Dade County Public Schools ( M DCPS ) Presented by: Melody Thelwell, MPA Chief Procurement Officer Procurement Management Services
More informationRESPONSES TO QUESTIONS RFP for Security Guard Services at Veterans Memorial Complex RFP #1614
DATE: November 11, 2016 QUESTION 1: Is it only for "as needed" security services and not full time officers assigned continually at the site? RESPONSE 1: Senior Center There are set weekly daytime hours
More informationHow to Do Business with The Orlando Utilities Commission
How to Do Business with The Orlando Utilities Commission 5971 Pershing Ave Orlando, FL 32822 Phone: 407-434-4080 Fax: 407-434-4338 Website: www.ouc.com PREFACE Welcome Suppliers to Orlando Utilities Commission.
More informationOFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, CT BUILDING RFP NO.: RFP OPENING DATE: APRIL 16, 3:00 PM ADDENDUM #4.
OFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, RFP NO.: 618-009 RFP OPENING DATE: APRIL 16, 2018 @ 3:00 PM ADDENDUM #4 April 9, 2018 THIS ADDENDUM IS TO PROVIDE ANSWERS TO THE FOLLOWING QUESTIONS: NOTE:
More informationConstruction Project Delivery Methods Overview and Comparison. Operations Division
Construction Project Delivery Methods Overview and Comparison Operations Division 1 Four Types of Delivery Methods Design/Bid/Build (CM Multi-Prime) CM at Risk Design/Build Lease/Leaseback 2 Considerations
More information5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods
PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are
More informationConstruction Family of Documents
Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications
More informationWhat You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President
What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives
More informationPROJECT PROCUREMENT MANAGEMENT. 1 Powered by POeT Solvers Limited
PROJECT PROCUREMENT MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited CONDUCT PROCUREMENT PROCESSES BY PROCESS GROUP Planning Executing Monitoring and controlling Closing 12.1 12.2 12.3 12.4
More informationProcurement 101. Tom Blaine Senior Research Associate, Public Procurement Research Center NASPO Honorary Member CPPO, FCPM, FCPA
Procurement 101 Monica Wilkes NASPO Honorary Member and Procurement Consultant CPPO, CPPB Universal Public Procurement Certification Council (UPPCC) Board of Directors Tom Blaine Senior Research Associate,
More informationREQUEST FOR PROPOSALS. Request for Proposals for Classification Pay and Benefits Study (A )
CITY OF TUSCALOOSA ) STATE OF ALABAMA ) REQUEST FOR PROPOSALS TO: FROM: RE: Qualified Firms The City of Tuscaloosa, Alabama Request for Proposals for Classification Pay and Benefits Study (A17-0172) DATE
More informationHow to Respond to Bids issued by Miami Dade County Public Schools ( M DCPS )
How to Respond to Bids issued by Miami Dade County Public Schools ( M DCPS ) Presented by: Melody Thelwell, MPA Chief Procurement Officer Procurement Management Services Bids?? What s that? Where does
More informationProject Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP
Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction
More informationStacey Camillo, Contract Administration. As-Needed Construction Contracting
Stacey Camillo, Contract Administration As-Needed Construction Contracting November 3, 2016 Why we are here Agenda Introductions Methods of getting construction work in San Francisco New As-Needed Construction
More informationREQUEST FOR QUALIFICATIONS
Issue Date: August 11, 2013 Title: Issuing Agency & Address Location of Work: RFQ#: SWaM-2013-15 Pre-Qualified Contractors Term Small, Women, and Minority Owned (SWaM) Contractors for Renovation, Replacement
More informationUNDP Procurement. UNDP Angola Procurement
UNDP Procurement The term procurement refers to the process of acquiring goods, works and services. The process spans the whole cycle from identification of needs, choosing the adequate procurement methods,
More informationINVITATION FOR BID NUMBER AEPA IFB #010-B-SPORTS/HEALTH SUPPLIES SPORTS / HEALTH EQUIPMENT AND SUPPLIES CATALOG PART B SPECIFICATIONS
INVITATION FOR BID NUMBER AEPA IFB #010-B-SPORTS/HEALTH SUPPLIES SPORTS / HEALTH EQUIPMENT AND SUPPLIES CATALOG PART B SPECIFICATIONS TABLE OF CONTENTS 1. IFB Goal...1 2. IFB Intent...1 3. Scope of Bid...3
More informationTopics of Discussion 10/7/2010 1
Topics of Discussion California s employment picture. Green jobs snapshot. California s green jobs formula. Administration priority. Budget priority. Capitol. Green jobs results. Follow the progress. 10/7/2010
More informationBEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND
BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND IN THE MATTER OF THE COMMISSION S ) INVESTIGATION INTO DEFAULT SERVICE ) CASE NO: 0 FOR TYPE II STANDARD OFFER SERVICE ) CUSTOMERS ) IN THE MATTER OF THE
More informationProcurement Under the New Requirements 1
Requirements 1 Procurement under the New Requirements 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between
More informationJOC 101. Questions and Answers
JOC 101 Questions and Answers Prepared by the Center for Job Order Contracting Excellence for The National Association of State Facilities Administrators 10-2009 2 Background JOC Questions and Answers
More informationBALTIMORE COUNTY PUBLIC SCHOOLS
BALTIMORE COUNTY PUBLIC SCHOOLS OFFICE OF PURCHASING SUPPLIER GUIDE 2018 Developing lifelong learners through literacy TABLE OF CONTENTS Supplier Guide ABOUT US.....3 SUPPLIER REGISTRATION......4 SOLICITATIONS.
More informationLabor Compliance Department Los Angeles Unified School District
October 2017 1 Labor Compliance Department Los Angeles Unified School District LAUSD has been monitoring its construction sites since February 1985. The LAUSD Labor Compliance Program was enacted on January
More informationREQUEST FOR QUALIFICATIONS DESIGN BUILD SERVICES FACILITY IMPROVEMENTS AT MUSIC HALL, AFRICAN AMERICAN MUSEUM & AQUARIUM ANNEX FAIR PARK DALLAS, TEXAS
REQUEST FOR QUALIFICATIONS for DESIGN BUILD SERVICES for FACILITY IMPROVEMENTS AT MUSIC HALL, AFRICAN AMERICAN MUSEUM & AQUARIUM ANNE at FAIR PARK DALLAS, TEAS ISSUED: MARCH 8, 2018 DUE: APRIL 6, 2018
More informationNORTHEAST TEXAS PUBLIC HEALTH DISTRICT (NET HEALTH) REQUEST FOR PROPOSALS (RFP)
NORTHEAST TEXAS PUBLIC HEALTH DISTRICT (NET HEALTH) REQUEST FOR PROPOSALS (RFP) PROJECT: SERVER REPLACEMENT November 28, 2016 OVERVIEW 1. Project Background and Description The Northeast Texas Public Health
More informationTEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL
TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II El Paso, Texas EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL for the BUILDING CONCRETE GLASS AND GLAZING FIRE SPRINKLER MECHANICAL
More informationSelection of Contractor Step 5. June 2013
Selection of Contractor Step 5 June 2013 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement of Contractor
More informationConsensusDocs. Catalog. Updated Docs Inside
ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even
More informationGLOSSARY OF TRAINING TERMS
Section 3 Terms and Definitions GLOSSARY OF TRAINING TERMS THESE ARE GENERAL DEFINITIONS AND NOT NECESSARILY APPLICABLE TO PARTICULAR SITUATIONS Arbitration: A method of dispute resolution involving one
More informationParticipating AEPA States
Participating AEPA States California Colorado Connecticut Florida Indiana Iowa Kansas Kentucky Michigan Minnesota Missouri Wyoming Montana Nebraska New Jersey New Mexico North Dakota Ohio Oregon Pennsylvania
More informationSEPARATED PROJECT DELIVERY SYSTEMS
SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer
More informationICOC Procurement Briefing
ICOC Procurement Briefing How we acquire goods and services Overview Procurement of Professional Services Engineering, architecture, design build, construction manager Projects < $2 million use continuing
More informationComparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013
Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should
More information