1 UNC Chapel Hill CIP Process Innovation in Leadership and Oversight in the Capital Improvement Project Process

2 Statement Projects that involve a great deal of moving parts and stakeholders can fail to reach their full potential. Culture Vision Division Non Inclusive

3 Objective A new pedagogy in planning, construction, and operations of facilities on campus had to be developed in order to meet the vision for campus development. Strategies Capital Oversight Process Tool Box Consensus Lessons Learned

4 Presenters Jerry U. Guerrier, RA, LEED AP $1.4 Billion $125 Million Servant, not Celebrity Keith Snead, LEED AP $2.6 Billion $190 Million Form ever follows function L.H. Sullivan

5 Agenda Form follows function, that has been misunderstood. Form and function should be one, joined in a spiritual Union. Frank Lloyd Wright Challenge Culture New Order Shift Next Phase

6 Dynamic UNC CAPITAL PROGRAM

7 Dynamic Staffing Workload At the Peak of the Capital Improvement Project Bond Program (2001 to 2011) FPD managed; 165 projects $2.3 Billion 11 professional staff AVG. = 8.6 projects/staff/yr. Table above does not indicate Repair & Renovation projects UNDER $500,000, Feasibility & Programming Studies, and Pan University activities. National Average AVG. = 8.33 projects/staff/yr.

8 PROJECTS STAFF Dynamic Facilities Planning Staffing Workload Capital Improvement Project (2010 to current fiscal year) FPD manages; 270 projects $3.74 Billion 6.25 professional staff AVG. = 11 projects/staff/yr. Table above does not include Repair & Renovation projects UNDER $500,000, Feasibility & Programming Studies, and Pan University activities. National Average AVG. = 6.3 projects/staff/yr FISCAL YEAR Sum of TOTAL # PROJECTS Sum of # PROJECTS UNDER DESIGN Sum of # TOTAL PROJECTS PER FTE Sum of # DESIGN PROJECTS PER FTE Sum of FAC DESIGN STAFF Sum of PROJECTS ADDED 1 QTR 2015 Non Formal/Non Billable

9 PROJECTS Facilities Services Division 5/1/2015 STAFF Dynamic Facilities Design Staffing Workload Capital Improvement Project (2010 to current fiscal year) FPD manages; 1402 projects $46.8 Million 8.25 professional staff AVG. = 33 projects/staff/yr. Table above does not include Repair & Renovation projects ABOVE $500,000, Feasibility & Programming Studies, and Pan University activities. National Average AVG. = 25 projects/staff/yr FISCAL YEAR Sum of Projects Sum of # Projects/FTE Sum of Staff/Personnel Non Informal/Non Billable

10 PROJECTS STAFF Dynamic Interior Design Staffing Workload Capital Improvement Project (2010 to current fiscal year) FPD manages; 721 projects $23.5 Million 3 professional staff AVG. = 48 projects/staff/yr. Table above does not include Repair & Renovation projects ABOVE $500,000, Feasibility & Programming Studies, and Pan University activities. National Average AVG. = 33 projects/staff/yr FISCAL YEAR Sum of Projects Sum of # Projects/FTE Sum of Staff/Personnel Non Informal/Non Billable Facilities Services Division 5/1/2015

11 Skill Sets CHALLENGE

12 Skill Sets Criticized Tunnel Vision Missed Opportunities Multiple Divisions If you only asked me

13 Skill Sets Change Orders O&M Scheduling Delays Errors & Omissions What were you thinking?

14 Competency CULTURE

15 Competency No Play Book Private sector mode Competing Means & Methods on delivery Limited Review/Input Paper based system static Silo Effect

16 Oversight NEW ORDER

17 Oversight Established Subcommittees Facilities Planning Construction Management Building Services Energy Services Environmental Health & Safety Facilities Services HUB Office Engineering Information Services

18 Oversight Over the coarse of 5 yrs. Updated Design Guidelines CIP Memorandum of Agreement CIP Checklist CIP Budget/Expense CIP Procurement Guidelines Management Reporting DrChecks SPOTS GIS LEED Equivalent (Silver)

19 Tool Box SHIFT

20 Tool Box: University Design Guidelines Web Based Guidelines & Manuals Web Based Design Guidelines 2010/2015 Left Design Guidelines 2003 MS Word Top Right Design Guidelines 2007 MS Word Lower Right

21 Tool Box: Capital Project Team Coordination Procedure Checklist, Team Assignments & Memorandum of Agreement Project Checklist MS Excel Left Capital Project Team List MS Excel Center Memorandum of Agreement MS Word Upper Right

22 Tool Box: Interview Process Guidelines & RFQ Matrix

23 Tool Box: Project Cost/Budgeting Budget & Expenses Worksheet

24 Tool Box: Project Cost /Budgeting Web Based Budget & Expenses System

25 Tool Box: Project Manager Reporting MS Word

26 Tool Box: Project Scheduling Web Based Scheduling & Reporting System

27 Tool Box: Facilities Sit-down Review Owner, Architect and Contractor Submittal Review Meeting To All: A sit-down review is scheduled for January 22 nd with the expectation of receiving written comments on January 29 th from UNC stakeholders through the DrChecks System. The sit-down will be held in the EHS - Big Conference Room 2202A. SIT-DOWN REVIEW SCHEDULE Wednesday, January 22, EHS - Big Conference Room 2202A 2015 Time: Topic: Participating Division & University Representative/Location: 8:00 to 9:00 AM Building Systems (Mechanical) Mechanical; Joe Magura Energy Management:; Chris Martin/Rod Rabold 9:00 to 10:00 AM Building Systems (Electrical) 10:00 to 11:00 AM Building Systems (IT/Telecomm) 11:00 AM to 12:00 PM Building Systems (Life Safety) Electrical; Jeannie Smith IT/Telecom; Lee Edmark/Frank Hall Life Safety; Todd Going/Doug Fleming 12:00 to 1:00 PM LUNCH Time: Topic: Participating Division & University Representative/Location: 1:00 to 2:00 PM Land Planning Grounds; Tom Bythell/Steve Gooch Facilities Planning; Jill Coleman Department of Public Safety; Cheryl Stout/Kurt Stolka/Than Auston/Adrian Naylor EHS; Larry Daw/Mal Donohue/Billy Mitchell/Sharon Myers 2:00 to 2:30 PM Waste & Recycle/Housekeeping 2:30 PM to 3:00 PM Accessibility (Site & Building) 3:00 PM to 5:00 PM Energy Services OWRR; BJ Tipton/Ray Lanier Housekeeping; Herb Richmond Facilities Planning - Accessibility; Michael Pierce Chilled Water; Doug Mullen/Carl Smith Electrical Distribution; Gaylan Bishop/Wayne Sink/Brian Bogie COGEN; Bill Lowery Water; Meg Holton Storm Water: Sally Hoyt

28 Tool Box: Project Submittal Review ProjNet - DrChecks Web Based Review & Submittal Exchange System

29 Tool Box: Project Submittal Review ProjNet - DrChecks Web Based Review & Submittal Exchange System

30 Tool Box: Project Submittal Review ProjNet - DrChecks Web Based Review & Submittal Exchange System

31 Tool Box: The Online Spatial Information System (OSIS) espots Space Planning & Occupancy Tracking System 3.0 Web Based Space Management System

32 Tool Box: The Online Spatial Information System (OSIS) espots Space Planning & Occupancy Tracking System 3.0 Web Based Space Management System

33 Tool Box: The Online Spatial Information System (OSIS) espots Space Planning & Occupancy Tracking System 3.0 Web Based Space Management System

34 Tool Box: The Online Spatial Information System (OSIS) espots Space Planning & Occupancy Tracking System 3.0 Web Based Space Management System

35 Tool Box: The Online Spatial Information System (OSIS) espots Space Planning & Occupancy Tracking System 3.0 Web Based Space Management System

36 Tool Box Outcome Shared Vision Higher Degree Accountability Consensus Interdivision relationships Stronger Cradle to Grave involvement Real time response Better quality, time and cost outcomes

37 The Carolina Way Innovation & Leadership NEXT PHASE

38 Pushing Innovation & Leadership Update Design Guidelines New technology industry standards Incorporate BIM into O&M process Online Facilities Condition Assessment Program (FCAP) Expand DrChecks Triage formal & informal projects at inception Improve AEC Firm Profile Data Base 2.0 Electronic RFQ/RFP submittals only Paperless documentation (e-filing)

39 Resources The Dynamic Decade by David R. Godschalk and Jonathan B. Howes, Amazon.com UNC Facilities Planning & Design A Division of Facilities Services Master Planning, Design Guidelines, Financial Portal, Firm Profile Database, and DrCHECKS Systems FCAP, GIS, Mapping, Plan Room, and SPOTS DrCHECKS by Business Resource Group The Online Spatial Information System Presenters: Jerry U. Guerrier, RA, LEED AP jerry.guerrier@fac.unc.edu Keith Snead, LEED AP keith.snead@fac.unc.edu

Construction Meet & Greet. Wednesday, March 8, 2017 Facilities Management

Construction Meet & Greet. Wednesday, March 8, 2017 Facilities Management Construction Meet & Greet Wednesday, March 8, 2017 Facilities Management http://facilities.uncc.edu/advertisements Agenda Welcome: Phil Jones, PE, AVC, Facilities Management Construction opportunities

More information

Implementing Program Management for Delivery of the City of Fresno s RechargeFresno Program

Implementing Program Management for Delivery of the City of Fresno s RechargeFresno Program Implementing Program Management for Delivery of the City of Fresno s RechargeFresno Program CA-NV AWWA, 2014 Annual Fall Conference, October 21, 2014 Presenters Martin Wendels City of Fresno, DPU, Water

More information

Student Government Office Renovations Design/Construction Administration Services Code Item 305

Student Government Office Renovations Design/Construction Administration Services Code Item 305 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, NC 28223 Telephone: 704-687-0615 PROJECT: UNC Charlotte Student Government Office

More information

Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction

Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction STARTING UP AN ILPD PROJECT Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction As to Disney artwork/properties: Disney Lean

More information

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards I. INTRODUCTION The Los Angeles Community College District is currently undertaking the largest public sector sustainable building effort in the United States, funded by its Proposition A/AA and J Bond

More information

BIM Design & Construction Requirements. Follow-up Seminar. September 10,

BIM Design & Construction Requirements. Follow-up Seminar. September 10, BIM Design & Construction Requirements Follow-up Seminar September 10, 2009 www.indiana.edu/~uao/iubim.html Opening Comments Two years ago Indiana University began the process of embracing the use of Building

More information

Saurabh Gangwar 2018 Project Management Symposium

Saurabh Gangwar 2018 Project Management Symposium Name UMD Project Management Symposium May 10-11, 2018 Slide 1 FROM PEOPLE MANAGEMENT TO INFORMATION MANAGEMENT Impact of technology on project management in the design and construction industry Saurabh

More information

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program

More information

Xavier University s Facility Management BIM Integration A Case Study

Xavier University s Facility Management BIM Integration A Case Study Xavier University s Facility Management BIM Integration A Case Study Andy Burg and Chris Mealy / Messer Construction / 10/10/2012 Agenda Project Background Workflow How XU is leveraging data Best Practices/Lessons

More information

COBIE Implementing Working Together via: SMART, SpecsIntact, Unified Facilities Guide Specifications, ProjNet, & Whole Building Design Guide

COBIE Implementing Working Together via: SMART, SpecsIntact, Unified Facilities Guide Specifications, ProjNet, & Whole Building Design Guide National Institute of Building Sciences COBIE Implementing Working Together via: buildingsmart SMART, SpecsIntact, Unified Facilities Guide Specifications, ProjNet, & Whole Building Design Guide Bill Brodt

More information

APPA Chicago August 2015

APPA Chicago August 2015 Facilities Planning, Design & Construction University of North Texas Integrated University Facilities Project Management Process APPA Chicago August 2015 UNT Factoids: 36,000+ students 172 Buildings including

More information

BIM Design & Construction Requirements Indiana University

BIM Design & Construction Requirements Indiana University BIM Design & Construction Requirements Indiana University AGC BIM Forum - Philadelphia October 9, 2009 www.shp.com Opening Comments Two years ago Indiana University began the process of embracing the use

More information

University of Washington. Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR. UW Fluke Hall Labs and Building Renewal Project Number:

University of Washington. Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR. UW Fluke Hall Labs and Building Renewal Project Number: Capital Projects Office Request For Qualifications for Architectural Design Services University of Washington Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR UW Fluke Hall Labs and Building

More information

Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017

Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017 Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017 Facilities Advisory Committee (FAC) AGENDA FAC focus and framework FPCS Preliminary Design and Construction Schedule Meet our

More information

University Campus Perspective;

University Campus Perspective; University Campus Perspective; C/D Materials Reuse and Recycling Prepared by Sarah Myers and BJ Tipton The campus perspective Residence halls Houses Restaurants & dining halls Medical clinics and hospital

More information

UNC Charlotte. Union Deck Expansion. Pre Submittal Conference June 21, 2016, 2:00 PM CHHS Room 147

UNC Charlotte. Union Deck Expansion. Pre Submittal Conference June 21, 2016, 2:00 PM CHHS Room 147 UNC Charlotte Union Deck Expansion Pre Submittal Conference June 21, 2016, 2:00 PM CHHS Room 147 Meeting Agenda PART I General Welcome Introductions Questions: dschauble@uncc.edu Updates: facilities.uncc.edu/advertisements

More information

The Key to Successful Design and Construction

The Key to Successful Design and Construction The Key to Successful Design and Construction Lower Cost... Fewer Problems... Higher Value ICCCFO Spring Conference April 14, 2011 Sitton Construction Group Owner rep construction managers Primary focus:

More information

Integrated Project Delivery

Integrated Project Delivery NSBA/COSA Copyright 2015 National School Boards Association. All rights reserved. Integrated Project Delivery Code of Hammurabi (circa 1772 BC) 229 If a builder build a house for some one, and does not

More information

FMD Project File Management Procedures

FMD Project File Management Procedures Issued: November 10, 2014 Revised: April 9, 2015 GUIDELINE: Applies to: All Planning, Project Management and Business Office Employees of the Facilities Management Department (FMD) PURPOSE: To establish

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

University Health Network. Energy Management Plan 2014 to Energy & Environment. University Health Network

University Health Network. Energy Management Plan 2014 to Energy & Environment. University Health Network University Health Network Energy Management Plan 2014 to 2019 Energy & Environment University Health Network Originally Published July 2014 Updated July 2017 Background While the links between environmental

More information

Building Information Modeling to Facilities Information Management and Beyond

Building Information Modeling to Facilities Information Management and Beyond Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas

More information

Overview of Capital Projects Division Introduction, Purpose, and Plans

Overview of Capital Projects Division Introduction, Purpose, and Plans Overview of Capital Projects Division Introduction, Purpose, and Plans Presented by: John Haig, Michael Savannah, Keith Reynolds Board of Directors Meeting August 1, 2018 Why A Capital Projects Division?

More information

3D Virtual Master Campus Planning and Management

3D Virtual Master Campus Planning and Management 3D Virtual Master Campus Planning and Management Dr. Thomas Furlani Charles Hixon Best Practices The Eastern Regional Association of Physical Plant Administrators (ERAPPA) is a Registered Provider with

More information

Jackson Miracle Building Plan Outreach Roundtable. February 14, 2017

Jackson Miracle Building Plan Outreach Roundtable. February 14, 2017 Jackson Miracle Building Plan Outreach Roundtable February 14, 2017 $1.8 billion Expanded Footprint Improved Patient Experience World-Class Facilities Innovative, Leading-Edge Care A Stronger, More Competitive

More information

UCF FAIRWINDS Alumni Center Achieves LEED Gold Certification Evaluating the Return on Investment for LEED in an Existing Building

UCF FAIRWINDS Alumni Center Achieves LEED Gold Certification Evaluating the Return on Investment for LEED in an Existing Building UCF FAIRWINDS Alumni Center Achieves LEED Gold Certification Evaluating the Return on Investment for LEED in an Existing Building Prepared for: University of Central Florida Case Study Prepared by: UCF

More information

Cone University Center HVAC Modernization Design and Construction Administration Services Code Item 320

Cone University Center HVAC Modernization Design and Construction Administration Services Code Item 320 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, N.C. 28223-0001 TEL: 704/687-0615 PROJECT: UNC Charlotte Cone University Center

More information

UF Sustainability in Built Environment Implementation Plan

UF Sustainability in Built Environment Implementation Plan Vision In framing the vision for sustainability in the Built Environment, participants envisioned a campus with buildings that would be designed to last 100 years, and to provide a healthy, productive

More information

Exercises supervision over building inspectors, plan reviewers, technicians, and support staff as required or assigned.

Exercises supervision over building inspectors, plan reviewers, technicians, and support staff as required or assigned. Class Title: Department: Village Hall Job Status: Full Time FLSA Classification: Exempt GENERAL PURPOSE: Performs a variety of routine and complex administrative, supervisory and technical work in administering

More information

RECYCLERS OF THE YEAR: MECKLENBURG COUNTY RECOGNIZES ORGANIZATIONS FOR WASTE-CUTTING PROGRAMS

RECYCLERS OF THE YEAR: MECKLENBURG COUNTY RECOGNIZES ORGANIZATIONS FOR WASTE-CUTTING PROGRAMS May 15, 2009 FOR IMMEDIATE RELEASE RECYCLERS OF THE YEAR: MECKLENBURG COUNTY RECOGNIZES ORGANIZATIONS FOR WASTE-CUTTING PROGRAMS Charlotte, N.C. A wide variety of businesses and organizations, and three

More information

NC State University OESAD GUIDELINES Contract Year

NC State University OESAD GUIDELINES Contract Year July 1, 2014 NC State University OESAD GUIDELINES Contract Year 2014-2016 I. Informal Projects A. Preface Based on the North Carolina Administrative Code (NCAC), Title 01, Subchapter 30D Section.0300 Selection

More information

Developing your ZNE Plan: Goals, Targets, Policies & Process

Developing your ZNE Plan: Goals, Targets, Policies & Process Developing your ZNE Plan: Goals, Targets, Policies & Process ZNE Tools for Planning & the ZNE Planning & Policy Workbook ZNE Charrette Process: San Mateo Pilot Heather Flint Chatto, New Buildings Institute

More information

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Olscamp Central Chiller Plant CCP-3 Response

More information

APPLYING THE VALUE METHODOLOGY TO LEED CHARRETTES

APPLYING THE VALUE METHODOLOGY TO LEED CHARRETTES APPLYING THE VALUE METHODOLOGY TO LEED CHARRETTES Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing services in value engineering,

More information

Establishing a Multi-Stakeholder Group and National Secretariat

Establishing a Multi-Stakeholder Group and National Secretariat Construction Sector Transparency Initiative October 2013 / V1 Guidance Note: 4 Establishing a Multi-Stakeholder Group and National Secretariat Introduction An essential feature of CoST is the multi-stakeholder

More information

WESTERN ILLINOIS UNIVERSITY CONSTRUCTION PROJECT PROCEDURES WESTERN ILLINOIS UNIVERSITY CONSTRUCTION POLICY

WESTERN ILLINOIS UNIVERSITY CONSTRUCTION PROJECT PROCEDURES WESTERN ILLINOIS UNIVERSITY CONSTRUCTION POLICY WESTERN ILLINOIS UNIVERSITY CONSTRUCTION PROJECT PROCEDURES WESTERN ILLINOIS UNIVERSITY CONSTRUCTION POLICY Management of all campus construction projects will be provided exclusively through the Facilities

More information

ADDENDUM NO. 1 Issued April, 3, 2014 REQUEST FOR PROPOSALS ( RFP ) FOR ORGANIZATIONAL REVIEW SERVICES

ADDENDUM NO. 1 Issued April, 3, 2014 REQUEST FOR PROPOSALS ( RFP ) FOR ORGANIZATIONAL REVIEW SERVICES ADDENDUM NO. 1 Issued April, 3, 2014 TO REQUEST FOR PROPOSALS ( RFP ) FOR ORGANIZATIONAL REVIEW SERVICES (RFP Number 14-HR-002) (RFP Issued March 17, 2014) Note: Proposers are required to acknowledge this

More information

NACUBO 2010 Smart and Sustainable Campuses

NACUBO 2010 Smart and Sustainable Campuses NACUBO 2010 Smart and Sustainable Campuses Steve Tatge, University of Washington Tim Williams, ZGF Architects Chris Flint Chatto, ZGF Architects Strategies to Reduce the Carbon Footprint of Lab Buildings

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Wide HVAC Upgrades - Steam Lines Response

More information

WELCOME to the 2013 JETC Continuing Education Webinar

WELCOME to the 2013 JETC Continuing Education Webinar WELCOME to the 2013 JETC Continuing Education Webinar Programs Director: Col. Nick Desport, F.SAME, USAF (Ret.), SAME Programs Manager: Belle Febbraro, bfebbraro@same.org Instructors: Karen Courtney, AIA,

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response

More information

1.133 M.Eng. Concepts of Engineering Practice Fall 2007

1.133 M.Eng. Concepts of Engineering Practice Fall 2007 MIT OpenCourseWare http://ocw.mit.edu 1.133 M.Eng. Concepts of Engineering Practice Fall 2007 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. THE ENGINEERING

More information

Facilities Management & Real Property. Strategic and Annual Planning Processes

Facilities Management & Real Property. Strategic and Annual Planning Processes Facilities Management & Real Property Strategic and Annual Planning Processes Typical Planning Practices Typically 2 planning sessions are held each year Environmental Scanning Strategic Plan of the University

More information

Using BIM to Transform Healthcare Operations & Maintenance

Using BIM to Transform Healthcare Operations & Maintenance Using BIM to Transform Healthcare Operations & Maintenance Building information modeling (BIM) has transformed the way that buildings are designed and delivered, particularly when it comes to the construction

More information

DESIGN-BUILD INSTITUTE OF AMERICA LOS ANGELES COMMUNITY COLLEGE DISTRICT David Salazar, Chief Facilities Executive Rob Brykalski, Program Director

DESIGN-BUILD INSTITUTE OF AMERICA LOS ANGELES COMMUNITY COLLEGE DISTRICT David Salazar, Chief Facilities Executive Rob Brykalski, Program Director DESIGN-BUILD INSTITUTE OF AMERICA LOS ANGELES COMMUNITY COLLEGE DISTRICT David Salazar, Chief Facilities Executive Rob Brykalski, Program Director December 6, 2018 www.jacobs.com worldwide LOS ANGELES

More information

JGBNov_a01Muse.qxd 12/19/05 5:43 PM Page 1 I INDUSTRY CORNER

JGBNov_a01Muse.qxd 12/19/05 5:43 PM Page 1 I INDUSTRY CORNER I INDUSTRY CORNER AN INSIDE LOOK AT LEED: EXPERIENCED PRACTITIONERS REVEAL THE INNER WORKINGS OF LEED Ashley Muse, LEED AP 1 Josette M. Plaut, LEED AP 2 INTRODUCTION LEED is leading the building industry

More information

UPCOMING AIM FACILITY PROJECTS

UPCOMING AIM FACILITY PROJECTS UPCOMING AIM FACILITY PROJECTS David Mashburn, Director of Facility Services Airport Infrastructure Management (AIM) AIM - Development January 14, 2015 1 Welcome and Agenda MEP Projects Facilities Projects

More information

Facility Basics for Bond Project Communications

Facility Basics for Bond Project Communications Facility Basics for Bond Project Communications TSPRA Annual Conference February 19, 2013 Presented by: Cathy Brandewie O Connell Robertson Architectural Teams can help with Evaluating / Assessing Facilities

More information

Berlin School RFQ / RFP: Clerk of the Works/Owner s Rep Berlin, Vermont

Berlin School RFQ / RFP: Clerk of the Works/Owner s Rep Berlin, Vermont Request for Qualifications The Berlin School District requests submissions of Qualification Statements and Salary Requirements for the position of Clerk of the Works/Owner s Representative for building

More information

Professional Qualifications Supplement (PQS) Instructions. GENERAL INSTRUCTIONS UF-368, Reitz Union Expansion and Renovation

Professional Qualifications Supplement (PQS) Instructions. GENERAL INSTRUCTIONS UF-368, Reitz Union Expansion and Renovation BUSINESS AFFAIRS www.facilities.ufl.edu FACILITIES PLANNING AND CONSTRUCTION DIVISION Professional Qualifications Supplement (PQS) Instructions GENERAL INSTRUCTIONS UF-368, Reitz Union Expansion and Renovation

More information

ENERGY MANAGEMENT PLAN Revised Version Approved May 26, 2016

ENERGY MANAGEMENT PLAN Revised Version Approved May 26, 2016 A. General Information ENERGY MANAGEMENT PLAN Project Title: ENERGY MANAGEMENT PLAN, Revised Version This charter is a continuation and revision of the initial Energy Management Plan Charter approved by

More information

Critical Construction Industry Trends Influencing Process and Profitability

Critical Construction Industry Trends Influencing Process and Profitability Critical Construction Industry Trends Influencing Process and Profitability Harvey M. Bernstein, F.ASCE, LEED AP Vice President, Industry Insights & Alliances McGraw Hill Construction Agenda General Industry

More information

Organization Efficiency Study

Organization Efficiency Study Val Ruiz Vice President Philip Campos Director Contracting Pre-Submittal Conference Introduction Purpose: Provide information pertaining to SAWS Solicitation No. R-14-001-PC CUSTOMER SERVICE GROUP AND

More information

REQUEST FOR QUALIFICATIONS DESIGN BUILD SERVICES FACILITY IMPROVEMENTS AT MUSIC HALL, AFRICAN AMERICAN MUSEUM & AQUARIUM ANNEX FAIR PARK DALLAS, TEXAS

REQUEST FOR QUALIFICATIONS DESIGN BUILD SERVICES FACILITY IMPROVEMENTS AT MUSIC HALL, AFRICAN AMERICAN MUSEUM & AQUARIUM ANNEX FAIR PARK DALLAS, TEXAS REQUEST FOR QUALIFICATIONS for DESIGN BUILD SERVICES for FACILITY IMPROVEMENTS AT MUSIC HALL, AFRICAN AMERICAN MUSEUM & AQUARIUM ANNE at FAIR PARK DALLAS, TEAS ISSUED: MARCH 8, 2018 DUE: APRIL 6, 2018

More information

Science Technology Engineering and Mathematics (STEM) Initiative

Science Technology Engineering and Mathematics (STEM) Initiative DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and

More information

Request for Qualifications (Criteria Architect/Engineer, Architect/Engineer) State of Ohio Standard Forms and Documents

Request for Qualifications (Criteria Architect/Engineer, Architect/Engineer) State of Ohio Standard Forms and Documents Request for Qualifications (Criteria Architect/Engineer, Architect/Engineer) State of Ohio Standard Forms and Documents Administration of Project: School District Board + OFCC Project Name West Clermont

More information

Request for Qualifications For Master Agreement

Request for Qualifications For Master Agreement Page 1 of 11 Capital Planning & Development Request for Qualifications For Master Agreement University of Washington Request for Qualifications ON-CALL COMMISSIONING AUTHORITY SERVICES Submittal Date:

More information

Commissioning Green Buildings

Commissioning Green Buildings Commissioning Green Buildings Hazem Elzarka, PhD, PE, LEED AP University of Denver Denver, CO, USA Owners are increasingly recognizing building commissioning as an effective means of ensuring quality and

More information

Campus Project Manager Measure CC Management Range: 16

Campus Project Manager Measure CC Management Range: 16 Board Approved: 04/11/2019 P. 1 5 Class specifications are intended to present a descriptive list of the range of duties performed by employees in the class. Specifications are not intended to reflect

More information

Project Management based on the Project Management book of knowledge

Project Management based on the Project Management book of knowledge Project Management based on the Project Management book of knowledge Integration Check parts of your plan are co-ordinated. Make trade off between competing objectives Scope Ensure the project includes

More information

C. Compliance and Audit. Dr. Goyal will report on the committee meeting of April 7, 2017 in the absence of General Moore, chair of the committee.

C. Compliance and Audit. Dr. Goyal will report on the committee meeting of April 7, 2017 in the absence of General Moore, chair of the committee. C. Compliance and Audit Dr. Goyal will report on the committee meeting of April 7, 2017 in the absence of General Moore, chair of the committee. Compliance and Audit Committee Meeting of November April

More information

Build your facility management career on a solid foundation. Enroll in Renton Technical College s FMP Course.

Build your facility management career on a solid foundation. Enroll in Renton Technical College s FMP Course. Build your facility management career on a solid foundation. Enroll in s FMP Course. Why should you pursue the FMP credential? Why should employers support the FMP? The IFMA Seattle Chapter and have joined

More information

Sweetwater Union High School District. Proposition O Performance Audit. March 20, 2012 Board of Education and Citizens Bond Oversight Committee

Sweetwater Union High School District. Proposition O Performance Audit. March 20, 2012 Board of Education and Citizens Bond Oversight Committee Sweetwater Union High School District Proposition O Performance Audit Board of Education and Citizens Bond Oversight Committee Outline of Performance Audit Presentation All parties, District staff and

More information

Design Reviews / Highlights DIA Specifications. Dave Mashburn Director of Facilities Services January 28 th, 2015

Design Reviews / Highlights DIA Specifications. Dave Mashburn Director of Facilities Services January 28 th, 2015 Design Reviews / Highlights DIA Specifications Dave Mashburn Director of Facilities Services January 28 th, 2015 1 Who leads review design Our speakers James Glavin PE MEP Services Michelle Martin PE Civil

More information

KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT. The 7-S for Success Framework

KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT. The 7-S for Success Framework KEY SUCCESS FACTORS FOR MAJOR PROGRAMS THAT LEVERAGE IT The 7-S for Success Framework May 2014 This document sets forth a framework of critical success factors for large scale government IT projects. ACT-IAC

More information

SUSTAINABLE DESIGN & DEVELOPMENT LEED CERTIFICATION PROGRAM 9 EDITION: NOVEMBER 1, 2016 USF FACILITIES MANAGEMENT - DC

SUSTAINABLE DESIGN & DEVELOPMENT LEED CERTIFICATION PROGRAM 9 EDITION: NOVEMBER 1, 2016 USF FACILITIES MANAGEMENT - DC SUSTAINABLE DESIGN & DEVELOPMENT LEED CERTIFICATION PROGRAM 9 EDITION: NOVEMBER 1, 2016 USF FACILITIES MANAGEMENT - DC SUSTAINABLE DESIGN & DEVELOPMENT (SDD) USF LEED CERTIFICATION PROGRAM (LCP) INDEX

More information

Salinas River Watershed Management Coordinator

Salinas River Watershed Management Coordinator Request For Qualifications Salinas River Watershed Management Coordinator Response Due: February 27, 2018 at 5:00pm Contact: Devin Best, Executive Director 65 South Main Street, Suite 107 Templeton, CA

More information

SAN JACINTO COLLEGE DISTRICT Building Committee Meeting September 18, Dan Mims, John Moon, Jr., Marie Flickinger, Erica Davis Rouse

SAN JACINTO COLLEGE DISTRICT Building Committee Meeting September 18, Dan Mims, John Moon, Jr., Marie Flickinger, Erica Davis Rouse SAN JACINTO COLLEGE DISTRICT Building Committee Meeting September 18, 2018 Members Present: Members Absent: Others Trustees Present: Others Present: Dan Mims, John Moon, Jr., Marie Flickinger, Erica Davis

More information

1. CLASSIFICATION AND CATEGORY OF CAPITAL ASSETS:

1. CLASSIFICATION AND CATEGORY OF CAPITAL ASSETS: EAST CAROLINA UNIVERSITY CAPITAL ASSETS GUIDELINES ISSUED - FEBRUARY 2012 UPDATED NOVEMBER 2012 INTRODUCTION These guidelines are being provided by the University s Financial Services Office to promote

More information

CarolinaRed Collaboration Meeting

CarolinaRed Collaboration Meeting CarolinaRed Collaboration Meeting November 18, 2009 Today s Agenda Introductions Collaboration Concept Scope of Collaboration Joint Timeline Implementation Status Proposed Collaboration Structure Chartered

More information

Request for Qualifications for Master Agreement

Request for Qualifications for Master Agreement Page 1 of 10 Request for Qualifications for Master Agreement ON-CALL ARCHITECTURAL SERVICES Submittal Deadline: April 28, 2017 at 3:00 p.m. The University of Washington is soliciting Statements of Qualifications

More information

Herrington Architects PC 101 Richard Arrington Jr. Blvd. S. Birmingham, AL phone fax

Herrington Architects PC 101 Richard Arrington Jr. Blvd. S. Birmingham, AL phone fax Herrington Architects PC 101 Richard Arrington Jr. Blvd. S. Birmingham, AL 35233 phone 205.326.1131 fax 205.326.1164 ADDENDUM #04 PROJECT: Alabama State University Renovations to Life Sciences Building

More information

JOB DESCRIPTION. 1. JOB TITLE: Fitness Facilities Co-ordinator (Maternity cover Chester Campus) 2. ROLE CODE: SFCSSRS (HRMS/12157a)

JOB DESCRIPTION. 1. JOB TITLE: Fitness Facilities Co-ordinator (Maternity cover Chester Campus) 2. ROLE CODE: SFCSSRS (HRMS/12157a) JOB DESCRIPTION 1. JOB TITLE: Fitness Facilities Co-ordinator (Maternity cover Chester Campus) 2. ROLE CODE: SFCSSRS (HRMS/12157a) 3. DEPARTMENT: Facilities Management 4. ORGANISATION CHART: Head of Operations:

More information

Construction Management at Risk

Construction Management at Risk Construction Management at Risk Implementation and Lessons Learned Virginia Water Environment Association Webinar Janelle Wright Okorie Director, Engineering and Technology Programs 21 October 2015 Alexandria

More information

ADDENDUM # 1 TO: FROM:

ADDENDUM # 1 TO: FROM: ADDENDUM # 1 TO: FROM: SUBJECT: DATE: bidders Somsri Bond, RA, LEEDap Assistant Architect for Research, University Architect s Office 20180123 - EA802 - Whitewater Hall - Rms 221,223,225-Interior Finishes

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Agency Project Name Stadium Project Response Deadline 1/9/14 12 pm local time

More information

Clemson, South Carolina Public, land-grant university Established 1889 Current FTE: 26,000 10,000 Acres 3M Cleanable FT2 of building space

Clemson, South Carolina Public, land-grant university Established 1889 Current FTE: 26,000 10,000 Acres 3M Cleanable FT2 of building space Clemson, South Carolina Public, land-grant university Established 1889 Current FTE: 26,000 10,000 Acres 3M Cleanable FT2 of building space Waste & Recycling Services Primarily managed in-house Exceptions:

More information

Campus Energy Plant Tufts University

Campus Energy Plant Tufts University IDEA CampusEnergy2017 Combined Heat and Power to Provide Energy Efficiency to Medium Size Campus February 20-24, 2017 Campus Energy Plant Tufts University Overview Presentation Overview: Campus Introduction

More information

Activation, Transition & Close Out Step 7. July 13, 2012

Activation, Transition & Close Out Step 7. July 13, 2012 Activation, Transition & Close Out Step 7 July 13, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

Campus Master Plan Update. Sustainable Initiatives

Campus Master Plan Update. Sustainable Initiatives Sustainable Initiatives UConn Sustainable Initiatives Appointment - Director of Environmental Policy Embracing a philosophy of conservation and development UConn 21 st Century Benchmark past performance

More information

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents

Request for Qualifications (Architect / Engineer) State of Ohio Standard Forms and Documents Request for Qualifications (Architect / Engineer) Administration of Project: Local Higher Education Project Name Technolgy Building Related Infrastructure Response Deadline Oct. 5, 2018 11:00 am local

More information

HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES:

HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES: Handouts HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: DATE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES: FUNCTIONAL GROUPS PARTICIPATING: SAMPLE 3-1 REQUIREMENTS RECORD

More information

BU21079 Building Information Modeling to Facilities Information Management and Beyond

BU21079 Building Information Modeling to Facilities Information Management and Beyond BU21079 Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, BIM Manager / Carolinas HealthCare System Thomas Koltoniak, BIM Specialist / Carolinas HealthCare System

More information

X470 Project Management UC Berkeley Extension, Business and Management August 2009

X470 Project Management UC Berkeley Extension, Business and Management August 2009 X470 Project Management UC Berkeley Extension, Business and Management August 2009 Anuradha Vaddadi Miguel Rivera Prasada Martala Wayne Harriman Archina Vishen Kiumars Golriz Table of Contents 1. Project

More information

HS2 s approach to BIM and Beyond

HS2 s approach to BIM and Beyond HS2 s approach to BIM and Beyond Britain s New High Speed Railway HS2: the new backbone of Britain s rail network HS2 s Timeline Fast, Frequent & Reliable National College for High Speed Rail Birmingham

More information

Water Resources Protection Program Advisory Committee Report November 15, 2012

Water Resources Protection Program Advisory Committee Report November 15, 2012 Water Resources Protection Program Advisory Committee Report November 15, 2012 SUMMARY REPORT In January 2009, the Charlottesville City Council considered a proposal to implement a stormwater user fee

More information

Research Shared Services:

Research Shared Services: Research Shared Services: A Case Study in Implementation November 19 th, 2015 YOUR MISSION OUR SOLUTIONS Huron Consulting Group Inc. All Rights Reserved. Huron is a management consulting firm and not a

More information

North Carolina Agricultural and Technical State University

North Carolina Agricultural and Technical State University North Carolina Agricultural and Technical State University BOARD OF TRUSTEES HUMAN RESOURCES COMMITTEE MEETING Friday, September 21, 2012 Presiding: Dr. Stanley Allen, Interim Chair Minutes The Human Resources

More information

Integrated Energy Master Plan Summary

Integrated Energy Master Plan Summary Integrated Energy Master Plan Summary January 8, 2013 Adapted from the original Board of Trustees presentation by Eric Utterson, PE, LEED AP Jerry Williams, PE, LEED AP 8760 Engineering, LLC St. Louis,

More information

Science Building Advance Planning/Design Services Code Item 301

Science Building Advance Planning/Design Services Code Item 301 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, N.C. 28223-0001 TEL: 704/687-0615 PROJECT: UNC Charlotte Science Building Advance

More information

BIM for FM Opportunities: Overcoming Challenges and Sharing Lessons Learned

BIM for FM Opportunities: Overcoming Challenges and Sharing Lessons Learned BIM for FM Opportunities: Overcoming Challenges and Sharing Lessons Learned Angela Lewis 1, P.E., PhD, LEED AP; Deke Smith 2, FAIA, Jim Whittaker 1, CFM, P.E. 1 Facility Engineering Associates, 2 buildingsmart

More information

Strategic Planning developing a roadmap to Our Future. May 30, 2001

Strategic Planning developing a roadmap to Our Future. May 30, 2001 Strategic Planning developing a roadmap to Our Future May 30, 2001 Why Strategic Planning? If you don t know where you are going any road will get you there Annon Without Vision the people parish Proverbs

More information

Request for Qualifications Architects CENTRAL UTILITY PLANT SHOP AND POWER CENTER

Request for Qualifications Architects CENTRAL UTILITY PLANT SHOP AND POWER CENTER Request for Qualifications Architects CENTRAL UTILITY PLANT SHOP AND POWER CENTER The University of Arkansas Fayetteville, in accordance with the policies of the Board of Trustees, is soliciting responses

More information

Lean Sigma: Doing More with Less

Lean Sigma: Doing More with Less Lean Sigma: Doing More with Less Problem Assessment The City of Tyler has a long history of innovative, forward-thinking management. The foundation was established in 1997, when the City of Tyler adopted

More information

House Doctor Consulting Services Application Package

House Doctor Consulting Services Application Package Public Facilities Department House Doctor Consulting Services Application Package For FY2013 FY2015 House Doctor Consulting Services Project #7005 City of Boston Thomas M. Menino, Mayor Michael Galvin

More information

Office of Physical Plant

Office of Physical Plant Office of Physical Plant The Pennsylvania State University Physical Plant Building University Park, PA 16802-1118 DATE: August 21 th, 2014 SUBJECT: TO: Integrated Project Delivery (IPD) Engagement RFP

More information

PUBLIC/PRIVATE PARTNERSHIPS

PUBLIC/PRIVATE PARTNERSHIPS UW MEDICINE TITLE OR EVENT SCHOOL OF MEDICINE TRADELINE CONFERENCE PUBLIC/PRIVATE PARTNERSHIPS THE PUBLIC SECTOR PERSPECTIVE & COMPARISON CASE STUDY JILL MORELLI, FAIA, DIRECTOR OF FACILITIES, UW SCHOOL

More information

Business Member Outreach and Liaison Committee Meeting May 21, 2011 ~ ~ 2:00 PM Marriott Memphis ~ ~ Natchez Room. Agenda

Business Member Outreach and Liaison Committee Meeting May 21, 2011 ~ ~ 2:00 PM Marriott Memphis ~ ~ Natchez Room. Agenda Business Member Outreach and Liaison Committee Meeting May 21, 2011 ~ ~ 2:00 PM Marriott Memphis ~ ~ Natchez Room Agenda Welcome and Introductions David Mikoryak Frank DiGiacomo Approval of the minutes

More information

Target Value Design and BIM: Delivering the targets of construction 2025

Target Value Design and BIM: Delivering the targets of construction 2025 Target Value Design and BIM: Delivering the targets of construction 2025 Prof Lauri Koskela, University of Huddersfield Dr Paul Coates, University of Salford Amit Kaushik, MSc, University of Salford Presentation