CERA s Programme Management Office

Size: px
Start display at page:

Download "CERA s Programme Management Office"

Transcription

1 CERA s Programme Management Office Published 18 April 2016 Canterbury Earthquake Recovery Authority The Government established the Canterbury Earthquake Recovery Authority (CERA) in March 2011 to lead and coordinate the on-going recovery effort after the major earthquakes of September 2010 and February 2011 in greater Christchurch. To support this role, CERA established its Programme Management Office (PMO) to set up a suitable framework, methodology, reporting and governance structure to help manage and deliver its many programmes. The PMO was established in August 2011 after a public tender process was won by a consultancy group. Portfolio, programme and project framework The PMO had to establish programme and project controls while emergency response was in full swing and at a time when a strategic direction had not yet been set for the organisation. To enable this, the Senior Leadership Team (SLT) approved the PMO recommendation to establish a programme and project oriented organisation. A portfolio, programme and project (PPP) framework was a logical way to structure the work that CERA was already delivering and would continue to deliver over its lifespan. The six recovery components identified in the Recovery Strategy for Greater Christchurch (Recovery Strategy) were ideal portfolio groupings for CERA s work programme. At CERA s peak, the six portfolios were made up of 24 programmes and 137 projects. 1

2 Strategy Strategic objectives which are documented in the Recovery Strategy for Greater Christchurch CERA s components of recovery: Economic, Social, Natural, Cultural, Built, Community Each component of recovery has a specific strategic objective or goal Portfolios A group of programmes primarily focused on the delivery of strategic goals Translates the six components of recovery into tangible initiatives, or Portfolios CERA s portfolios: Economic, Social, Natural, Cultural, Built, Leadership and Integration Programmes A group of large scale, complex projects managed together, due to their strong links and dependencies, to deliver objectives A coordinated approach ensuring consistent management, no overlaps or gaps Must follow CERA s mandated five step lifecycle approach Initiation, Definition, Planning, Execution, Close-out Projects Individual efforts executing a set of activities to deliver specific outputs Have a start and end date; a finite life Must follow CERA s mandated five step lifecycle approach Initiation, Definition, Planning, Execution, Close-out The framework and model were consistent with best practice for the successful delivery of a broad, but interrelated, set of outcomes. In CERA s case, a large majority of those outcomes all related to the successful delivery of the Recovery Strategy. Programme and project lifecycle Drawing its methodology from Projects in Controlled Environments (PRINCE2) and the Project Management Book of Knowledge (PMBOK), the PMO adopted a five-phase lifecycle over which each programme and project was to deliver its outcomes. Each programme or project had to develop key documents at the beginning or end of each of its phases. As an example, at the end of phase 3 [the planning phase] a completed Implementation Plan was required. After the sponsor approved that document and then the governance group in CERA s case, the Programme Management Steering Committee (PMSC) considered it, the programme or project would move into the next phase. In a disaster response environment, a key challenge was that projects had very little or no formalised planning before they started. This was a direct result of the fact that CERA was in an emergency response phase working at pace, the organisation was lean, the workload was significant and intense, and time pressures were high. Staff had a genuine desire to just get on with it and to do the work needed to support and deliver recovery. Key documents were not always completed or approved before the project moved through the delivery lifecycle. From time to time, this did result in missed milestones, changes in scope, and unclear expectations for project teams and stakeholders. 2

3 Recovery programmes Deliver, Enable, Support As the leader and coordinator of recovery, CERA had to keep an overview of all recovery programmes underway. With SLT agreement, the PMO introduced a model to help CERA prioritise and resource the different types of work involved, and labelled its programmes and projects as Deliver, Enable or Support. With delivering programmes of work, CERA was responsible for leading them and was accountable for the budget. With enabling programmes of work, CERA was partially responsible for leading them and/or was accountable for part of the budget. With supporting programmes of work, other organisations were leading them, but CERA was responsible for making sure the programmes were consistent with the Recovery Strategy and for bringing a strategic, all of recovery view to the individual programmes. Categories CERA Delivering CERA Enabling CERA Supporting Programmes and projects that CERA is responsible for leading and/or is the budget owner. Programmes and projects that CERA is partially responsible for leading and/or is the partial budget owner. Programmes and projects that CERA is not responsible for leading and not the budget owner. Criteria These programmes have: These programmes have: These programmes have: - Key, externally communicated milestones - Strong interest from Public and Government - Significant budget - Significant resourcing - Minimal externally communicated milestones - Some interest from Public and Government - Led externally - Monitored by CERA CERA helps resolve issues impeding delivery, and ensures alignment with other programmes. Embedding the PMO and project management framework within CERA In October 2011, the PMO released a programme and project management manual, outlining the framework, tools and processes for programme managers to use to ensure programmes and projects were undertaken in a consistent way. Not all staff had a government background or had worked in a PMO environment before and there was little time to get up to speed and understand how it worked. Consequently, the manual was not well embedded across the organisation until a refresh and focused roll-out occurred in The PMO had to be established very quickly in an organisation which was new and evolving. Some felt that the PMO framework was too mature for a new organisation like CERA. The ideal model of project and programme delivery is not something that you can just impart into an immature organisation and expect compliance and adherence and the cogs of the machine to go around seamlessly. In the early stages of CERA, the PMO needed to stay close to leaders and recognise their different operating styles so that it could understand where it could add value. As CERA evolved the Senior Leadership Team (SLT) requested more formality around processes. The PMO responded by implementing robust programme and project controls. In 2012, the Recovery Strategy Planning and Policy team, together with the PMO, developed a Recovery Programme Guidance document. The purpose of this guide was to ensure programmes followed a consistent methodology, were integrated with other programmes and were consistent with the Recovery Strategy. 3

4 By this stage, a range of tools had also been developed internal reporting, weekly status updates to the Minister for Canterbury Earthquake Recovery, programme concept papers and project briefs. CERA management requested information around timelines, deliverables, funding and capacity and some programme managers felt that they were providing the same information in a range of different tools. It remained difficult to put robust structures and timelines into programmes because CERA s work was constantly moving and shifting. In 2013 the Senior Leadership Team mandated and promoted the PMO s model and processes with the result that CERA s activities became more integrated. Programme Managers were held accountable for completing programme concept papers and project briefs and for providing accurate and timely reports. Across CERA, staff became significantly more engaged with and gained a better understanding of the PMO s role and function. Programme offices I ve seen fail time and time again because they lack executive sponsorship or ownership of the accountability at a governance level. My piece of advice for anyone setting up a programme office is to initially make sure it s right-sized for the organisation and it s doing the right things and, secondly, if you haven t got top-down executive sponsorship for it, don t bother. Establishing the Programme Management Steering Committee In 2013, the PMSC was established to oversee and manage the delivery of CERA s work programme. The PMSC was comprised of all programme managers (General Manager level) from across CERA. It reported formally on progress each month to the Senior Leadership Team through a consolidated report. The PMSC was an effective way to share information across the organisation, with its helicopter view across all programmes. Its meetings provided programme managers with an opportunity to talk about dependencies, themes and issues that were arising, and to provide key programme updates. In early 2014, the PMO focused on meeting with programme managers, developing a detailed programme and project inventory, bringing templates and processes up to date and working directly with different programme areas. The Risk and Assurance team In 2012, the Risk and Assurance (R&A) team was set up within the Finance team to undertake risk management. The R&A team facilitated risk workshops to capture risk information and provided advice and training on risk management across all areas of CERA. Typically, risk and issue functions are carried out together. As the PMO was responsible for the issue management process, this separation created difficulties with reporting. Risks 1 You can t really separate them: you ve got a risk, it becomes an issue, the issue gets dealt with, it goes back to being a risk and yet we ve got two different teams reporting on them so there wasn t that synergy. In the beginning, risk management at the programme and project level was often seen as a compliance exercise. Effort was made to shift the risk management culture so that managers took ownership of their risks. Strategic risks were managed at the SLT level. A document known as CERA s Top 10 Risks was updated on a quarterly basis by incorporating a risk session into the SLT strategy days. 1 A risk is an event that has not yet occurred but that could have a negative effect on project objectives if it were to occur. 4

5 Due to the diversity of work, it was difficult to have one refined risk management framework. A senior risk advisor recommends having a flexible approach. For example, where CERA was leading a programme that had high time pressures, changing priorities and ministerial involvement, the senior risk advisor had to be more closely involved to ensure accurate information was reported. In other cases, this wasn t necessary. An Audit and Risk Committee (ARC) was established with three independent professional directors to act as advisors to the Chief Executive. They met quarterly and were responsible for endorsing CERA s financial accounts and recommending for chief executive approval. Issues 2 Although issue registers were made available to programmes early on, they were not being used. In 2014, the PMO developed an issue management process and agreed with the R&A team to cover issues at risk workshops. Through this approach, new issues were identified and suitable actions were taken to resolve them. The PMO also introduced a combined register to record both risks and issues in a more streamlined process. Structure of the PMO and skills required The size and structure of the PMO changed a lot over CERA s lifespan. In 2011, CERA brought in external consultants with specialist skills in cost control, planning, reporting and scheduling. During the immediate response phase, some of these skills were useful and some were not because CERA was not yet delivering a large capital works programme. Over the next two years, as the PMO continued to evolve, the roles transferred from external consultants to CERA employees until, in 2014, CERA was leading the PMO with its own staff. From this time, the team remained a manageable size with a PMO manager, senior advisors, advisors, a reporting advisor and a programme support advisor. Programme coordinators were also working in programmes across the organisation. They were responsible for reporting and for supporting the programme managers in developing documentation. In this way, they performed a helpful role to the PMO as the key liaison point between the PMO and recovery programme managers. In some cases, other staff in programmes were also heavily involved in producing documentation and reporting. Christchurch Central Development Unit Programme Support Office In 2012, the Government established the Christchurch Central Development Unit (CCDU) as part of CERA, with the specific role of leading the recovery of the central city. When CERA was set up, it wasn t envisaged that it would manage a large capital works programme. However, in 2014 the CCDU needed additional resources and the right skills to drive and manage the anchor projects. In September 2014, the CCDU Programme Support Office was set up with the appropriate skills, processes, systems and experience to enable best-practice, construction-focused programme management. Its mixed resourcing model used existing CERA resource, heavily supported by external consultants. The PMO s helicopter view across all recovery programmes included the anchor projects. Its reporting requirements to the Senior Leadership Team were integrated with those of the CCDU. A summary of CERA s programme of work including its key achievements and milestones from April 2011 to April 2016 is available on the 2 An issue is an event that has already occurred and that is delaying the project, increasing its cost or impacting on its quality, or is affecting the overall delivery of the programme or project. 5

6 Lessons identified about a Programme Management Office Outlined below are important lessons identified from CERA s experience over its five-year existence. Every disaster and recovery organisation is different: the first decision is whether or not a PMO is necessary in the particular circumstances and, if so, whether it should be a separate function or part of an existing function. In CERA s case, having a standard PMO framework in a new disaster recovery organisation was a key challenge. It was difficult to apply a one size fits all framework across the many CERA programmes. It was challenging for supporting programmes as they had no control over budget and milestones, which caused frustration for project staff. Flexibility was necessary for these programmes so in 2014 the PMO modified documentation requirements to meet the needs of support programmes. When setting up a PMO in a disaster recovery organisation, the following provides a range of questions and guidelines to consider based on CERA s identified PMO lessons. Systems and processes What is the type of PMO needed? A corporate/reporting management office is different to a field delivery management office and may require different skills. Set up the PMO as soon as practical to establish a clear and consistent framework including methodology, governance, reporting, processes and templates. Ensure that the PMO has a good understanding of what the recovery organisation is tasked to do. As the role of the recovery organisation evolves including its activities a PMO can support change. Use existing project management tools from government agencies and recovery organisations but recognise that any disaster recovery environment is complex and a one size fits all model and approach will need to be tailored. Have a PMO that supports both risk and issue management. These functions should not be separated. Think about whether the PMO will need a finance function to track programme and project costs. Having accurate project costs will help manage programmes and projects effectively. As the recovery organisation evolves, think about whether the PMO is evolving with it. Templates and processes need to be the right fit for the organisation s level of maturity. A programme that has low risk and low cost does not need the same level of project management as a programme that has high risk, high costs and demanding timeframes. Programme management skills Resource the PMO with appropriately skilled and experienced staff, including people with: o a thorough understanding of portfolio, programme and project management and the ability to implement disciplines such as risk management and scheduling o strong analytical skills and experience in capturing and interpreting data o communications and relationship management skills if an organisation includes non-believers in the PMO system, they need to be brought along on the journey and shown its value o specialist skills in cost control, planning, reporting and scheduling, particularly if the recovery organisation is managing a large capital programme o experience in relevant projects for example, in construction and infrastructure projects for those working in demolitions and operations. 6

7 Consider embedding PMO staff in programme and project teams to provide targeted support. Have a training plan in place. People joining the recovery organisation might be subject matter experts but not experienced in project management. Communications Having a strong sponsor and support from the chief executive and senior leadership team is critical. It is important that senior leaders advocate for the PMO and all staff understand the value it adds. Consider holding regular meetings with those in coordinator/support roles to share information. These people can be the glue for their programmes and projects and the link between the PMO and recovery programme managers. Have communication channels in place to provide projects with the same level of information as programmes. CERA s PMO was initially more focused on programmes but better visibility and control was needed for the projects as well. Establish high-level commitment from, and accountabilities to, senior leaders. 7

Tusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018

Tusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018 Tusla Programme Management (PMO) Design and Establishment Fergal Collins 20 th September 2018 1 Contents Tusla Overview Executive Summary. Choosing an operating model for the PMO. 3 PMO Models to choose

More information

Peak Performance Coaching at SCIRT

Peak Performance Coaching at SCIRT Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

NHSScotland Procurement Review

NHSScotland Procurement Review NHSScotland Procurement Review Project Initiation Document QuEST Portfolio Office Contents 1. Document Control 3 1.1 Programme Details 3 1.2 Version Control 3 2. Purpose of the Document 4 3. Context and

More information

Response to the Report of the National Assembly for Wales Public Accounts Committee Report on Regeneration Investment Fund for Wales

Response to the Report of the National Assembly for Wales Public Accounts Committee Report on Regeneration Investment Fund for Wales Response to the Report of the National Assembly for Wales Public Accounts Committee Report on Regeneration Investment Fund for Wales We welcome the findings of the report and offer the following response

More information

Chartered Institute of Internal Auditors. The above areas are addressed by the sections identified below:

Chartered Institute of Internal Auditors. The above areas are addressed by the sections identified below: 22 March 2018 Projects Chartered Institute of Internal Auditors Internal audit can play a significant role in helping an organisation achieve its strategic objectives in relation to project management.

More information

Coordinating other recovery work: Lessons identified from CERA s support programmes

Coordinating other recovery work: Lessons identified from CERA s support programmes Coordinating other recovery work: Lessons identified from CERA s support programmes Published 18 April 2016 Canterbury Earthquake Recovery Authority Disaster recovery is made up of many moving parts that

More information

How to implement PPM Technology to Improve Your Organisational Maturity. Guy Jelley, CEO, Project Portfolio Office

How to implement PPM Technology to Improve Your Organisational Maturity. Guy Jelley, CEO, Project Portfolio Office How to implement PPM Technology to Improve Your Organisational Maturity Guy Jelley, CEO, Project Portfolio Office Let technology guide your journey What is Maturity? Project management maturity refers

More information

At Revolution IT, one goal sets the tone for all our portfolio and project management: achieving strong investment returns for clients.

At Revolution IT, one goal sets the tone for all our portfolio and project management: achieving strong investment returns for clients. Revolution IT >>Portfolio & Project Management At Revolution IT, one goal sets the tone for all our portfolio and project management: achieving strong investment returns for clients. Unwanted surprises

More information

Audit of Human Resources Planning

Audit of Human Resources Planning Health Canada Santé Canada Final Audit Report Audit of Human Resources Planning March 2012 Table of Contents Executive summary... i 1. Introduction... 1 1.1 Background... 1 1.2 Audit objective... 2 1.3

More information

ESTABLISHING AN EFFECTIVE PMO

ESTABLISHING AN EFFECTIVE PMO ESTABLISHING AN EFFECTIVE PMO Michelle Griffiths, University of Oxford Simon Hogg, Oxford Brookes University Sally Jorjani, Edinburgh Napier University Why are we here? Brief overview of Institutional

More information

Procurement Functional Leadership Progress Report October 2015 to March 2016

Procurement Functional Leadership Progress Report October 2015 to March 2016 Office of the Minister for Economic Development The Chair Cabinet State Sector Reform and Expenditure Control Committee Procurement Functional Leadership Progress Report October 2015 to March 2016 Proposal

More information

Sunil Kapur, Assistant Director, Quality Assurance and Continuous Improvement,

Sunil Kapur, Assistant Director, Quality Assurance and Continuous Improvement, Agenda item: 11 Report title: Report by: Action: Quality Assurance update Sunil Kapur, Assistant Director, Quality Assurance and Continuous Improvement, sunil.kapur@gmc-uk.org 0161 923 6654 To consider

More information

Tailoring PRINCE2 to the project environment

Tailoring PRINCE2 to the project environment 1. The adoption of PRINCE 2 across an organisation is known as: A. Adapting B. Embedding C. Tailoring D. Reporting 2. Tailoring PRINCE 2 appropriately is: A. Implementing a portion of the method as the

More information

Cascading change throughout an organisation

Cascading change throughout an organisation Cascading change throughout an organisation Author Melanie Franklin Director Agile Change Management Limited Introduction Organisations all over the world are experiencing high volumes of change as a result

More information

Ministerial Review Terms of Reference. Better responses to natural disasters and other emergencies in New Zealand

Ministerial Review Terms of Reference. Better responses to natural disasters and other emergencies in New Zealand Ministerial Review Terms of Reference Better responses to natural disasters and other emergencies in New Zealand 1. Purpose This review will provide advice to the Minister of Civil Defence on the most

More information

Falcon Training PMP & CAPM Exam Preparation Course

Falcon Training PMP & CAPM Exam Preparation Course Falcon Training PMP & CAPM Exam Preparation Course Chapter 1-3: Project Framework Review Questions 1. What is the primary role of the portfolio manager? A. To deliver the unique product, service, or result

More information

Business Planning for 2014/15

Business Planning for 2014/15 Business Planning for 2014/15 Proposed approach and timeframe Authors: John Willshere and Steve Bruggenwirth Date: 14/10/13 1 Copyright 2013, Health and Social Care Information Centre. Contents Contents

More information

JOB DESCRIPTION & PERSON SPECIFICATION

JOB DESCRIPTION & PERSON SPECIFICATION JOB DESCRIPTION & PERSON SPECIFICATION HIAL AMSL DAL 1. JOB DETAILS JOB HOLDER JOB TITLE REPORTS TO Vacant ICT Advisor Head of ICT and Digital Transformation 2. JOB PURPOSE The Air Traffic Management 2030

More information

Employment relationships

Employment relationships Employment relationships Published 18 April 2016 Canterbury Earthquake Recovery Authority The Canterbury Earthquake Recovery Authority (CERA) was set up in March 2011 to lead and coordinate the recovery

More information

About AITSL. Position Overview. Who are we looking for? Position Description. AITSL classification range: Remuneration range:

About AITSL. Position Overview. Who are we looking for? Position Description. AITSL classification range: Remuneration range: At AITSL, we believe every Australian child deserves a quality education. This relies on quality teaching and effective school leadership. We drive effective and inspiring teaching and school leadership,

More information

The Executive Board had already put in place a number of critical elements to achieve the new strategic plan, including:

The Executive Board had already put in place a number of critical elements to achieve the new strategic plan, including: Case Studies Regional Power Company (becoming part of a pan European energy group) Following a change in ownership in 2009, this market leading Dutch utility Company needed a company-wide transformation

More information

Job Description. No of Direct Reports : Titles of Direct Reports: Budget Responsibility (direct) : Revenue Responsibility (direct) :

Job Description. No of Direct Reports : Titles of Direct Reports: Budget Responsibility (direct) : Revenue Responsibility (direct) : Job Description Job Title : Department : Senior Portfolio Analyst Portfolio Management Office Reporting to (Job Title) : Senior Portfolio Manager No of Direct Reports : None Titles of Direct Reports: Size

More information

Head of Programmes and Performance Improvement

Head of Programmes and Performance Improvement Job details Job title: Head of Programmes & Performance Responsible to: Director of Business Effectiveness Responsible for: Posts in the Project Management Team and the Performance Team Location: Liverpool

More information

MSP : The Basics. Kenn Dolan, Consultant, FPMS. AXELOS.com. APMG International 2010

MSP : The Basics. Kenn Dolan, Consultant, FPMS. AXELOS.com. APMG International 2010 Kenn Dolan, Consultant, FPMS AXELOS.com White Paper May 2010 Contents Background/history 3 Why would an organization use MSP? 3 Who uses MSP? 3 What are the benefits of using MSP? 3 An overview of the

More information

Job description and person specification

Job description and person specification Job description and person specification Position Job title Knowledge Management Facilitator Directorate Operations and Information Pay band AFC Band 8a Responsible to NHS RightCare Knowledge Management

More information

Significant Service Contracts Framework

Significant Service Contracts Framework 1 Significant Service Contracts Framework The Significant Service Contracts Framework is delivered by New Zealand Government Procurement (NZGP). NZGP delivers on the Ministry of Business Innovation and

More information

Guidelines for policy making: promoting good governance in policy development (278 KB)

Guidelines for policy making: promoting good governance in policy development (278 KB) Guidelines for policy making: promoting good governance in policy development (278 KB) Item type Authors Rights Report Heslin, Caitriona NEHB Downloaded 7-Jun-2018 09:46:45 Link to item http://hdl.handle.net/10147/43611

More information

Change and project management

Change and project management Change and project management www.first.com What gets measured, gets d! -Change leader Change and Project Management Change and project management Prince 2, PMI and PCI When projects fail in an organisation,

More information

SO Think P30 Make Up 14/11/08 11:15 Page 1 1 Introduction

SO Think P30 Make Up 14/11/08 11:15 Page 1 1 Introduction SO Think P30 Make Up 14/11/08 11:15 Page 1 Introduction 1 3 1 Introduction People have been talking about programmes and projects for many years, and there are lots of books, guidance, qualifications,

More information

Chapter One PROJECT MANAGEMENT OVERVIEW

Chapter One PROJECT MANAGEMENT OVERVIEW Chapter One PROJECT MANAGEMENT OVERVIEW Project management itself is not a new concept. It has been practiced for hundreds, even thousands of years. Any large undertaking requires a set of objectives,

More information

Director Procurement & Value Delivery

Director Procurement & Value Delivery Position Reports to Direct Reports Band Director Procurement & Value Delivery Chief Executive Heads of Procurement (3), Sustainability Officer (1), Head Procurement Operations (1), Head Clinical Engagement

More information

Ministerial Review - Better Responses to Natural Disasters and Other Emergencies in New Zealand. Submission by the Engineering Leadership Forum

Ministerial Review - Better Responses to Natural Disasters and Other Emergencies in New Zealand. Submission by the Engineering Leadership Forum Ministerial Review - Better Responses to Natural Disasters and Other Emergencies in New Zealand Introduction Submission by the Engineering Leadership Forum 7 July 2017 1. Thank you for the opportunity

More information

Board Meeting: 20 June Change and Transition Report. HS Paper 17/18

Board Meeting: 20 June Change and Transition Report. HS Paper 17/18 HS Paper 17/18 Board Meeting: 20 June 2018 We are working towards all our publications being available in an accessible format. In the meantime if you require this paper in a more accessible format, please

More information

OPM The Missing Link. Jane Betterton, BS,ChE., PMP PMIRGC JaneBetterton.com/ BTSResults.com

OPM The Missing Link. Jane Betterton, BS,ChE., PMP PMIRGC JaneBetterton.com/ BTSResults.com OPM The Missing Link Jane Betterton, BS,ChE., PMP PMIRGC 11-2-18 Jane@BTSResults.com JaneBetterton.com/ BTSResults.com Presentation Overview In this session you will learn how PMI s latest foundational

More information

OPM The Missing Link

OPM The Missing Link OPM The Missing Link Jane Betterton, BS,ChE., PMP PMIRGC 11 2 18 Jane@BTSResults.com JaneBetterton.com/ BTSResults.com Presentation Overview In this session you will learn how PMI s latest foundational

More information

SAI Performance Measurement Framework Implementation strategy

SAI Performance Measurement Framework Implementation strategy SAI Performance Measurement Framework Implementation strategy 2017-19 24 September 2016 Draft SAI PMF strategy, 2017-19 Page 1 SAI PMF Strategy 2017-2019 1. Introduction 1.1 What is the SAI PMF? The SAI

More information

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference:

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference: Inland Revenue Transformation Programme Sourcing Workstream PROCUREMENT PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 28/06/2013 v1.0 FINAL Reference: 2013050 Document Control File

More information

Business Partnering Skills and Capabilities Model Electrocomponents - Case Study

Business Partnering Skills and Capabilities Model Electrocomponents - Case Study Business Partnering Skills and Capabilities Model Electrocomponents - Case Study Summary This case study examines the introduction of a finance business partnering skills and capabilities model designed

More information

Auckland Transport HS08-01 Safety In Design

Auckland Transport HS08-01 Safety In Design Auckland Transport HS08-01 Safety In Design (Procedure uncontrolled when printing) Relating to Standard: HS08 Safety In Design December 2016 Health and Safety-Procedure-HS08-01 Safety In Design Contents

More information

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED NOT PROTECTIVELY MARKED Meeting Audit Committee Date 24 July 2018 Location Pacific Quay, Glasgow Title of Paper Internal Audit Organisational Change Report Item Number 5.5 Presented By Campbell McLundie,

More information

NHS Highland. Procurement Strategy

NHS Highland. Procurement Strategy NHS Highland Procurement Strategy 2016-21 NHS Highland Procurement Strategy 2016-21 1 Introduction Recognising that effective and efficient procurement will positively support the Board in achieving its

More information

Developing Role-Based Change Competencies In an ECM Framework

Developing Role-Based Change Competencies In an ECM Framework P e o p l e. C h a n g e. R e s u l t s. Developing Role-Based Change Competency in an ECM Framework Prosci Webinar Developing Role-Based Change Competencies In an ECM Framework Copyright 2017 Prosci.

More information

Program/Project Management

Program/Project Management PROCEDURE OVERVIEW PROGRAM/PROJECT MANAGEMENT PROCEDURE defines the project management infrastructure, reporting relationships and project management activities within SDLC.com. Project Managers, Program

More information

Architecture Planning Adding value to projects with Enterprise Architecture. Whitepaper. September By John Mayall

Architecture Planning Adding value to projects with Enterprise Architecture. Whitepaper. September By John Mayall Adding value to projects with Enterprise Architecture Whitepaper September 2007 By John Mayall W O R L D C L A S S A R C H I T E C T U R E Architecture Planning Introduction We are often asked what an

More information

Delivering change, sustaining benefits

Delivering change, sustaining benefits pwc.com.pg pwc.com.au Delivering change, sustaining benefits Projects Consulting Service Catalogue 2013 version . Project Consulting Capabilities Portfolio Management Project Services PMO Management Project

More information

Open Information Purpose of the Report

Open Information Purpose of the Report Meeting Date 15 March 2018 Agenda Item 2c Report Title Financial Governance Review Report Author Liz Stauber, Committee Services Manager Report Sponsor Pam Wenger, Director of Corporate Governance Presented

More information

Internal Audit of ICT Governance in WFP. Office of the Inspector General Internal Audit Report AR/15/11

Internal Audit of ICT Governance in WFP. Office of the Inspector General Internal Audit Report AR/15/11 Fighting Hunger Worldwide Internal Audit of ICT Governance in WFP Office of the Inspector General Internal Audit Report AR/15/11 Contents Page I. Executive summary 3 II. Context and scope 5 III. Results

More information

Programme Manager / Senior Project Manager, Strategy and Planning. Salary: Grade 8 ( 39,992 47,722 p.a. with flexibility to appoint up to 52,132)

Programme Manager / Senior Project Manager, Strategy and Planning. Salary: Grade 8 ( 39,992 47,722 p.a. with flexibility to appoint up to 52,132) CANDIDATE BRIEF Programme Manager / Senior Project Manager, Strategy and Planning Salary: Grade 8 ( 39,992 47,722 p.a. with flexibility to appoint up to 52,132) Two Year Fixed Term Contract (due to particular

More information

Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011

Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011 Audit of Mobile Telecommunication Devices June 21, 2012 Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011 Presented to the Audit Committee on November 21, 2016

More information

Programme Manager - Strategic Initiatives

Programme Manager - Strategic Initiatives Programme Manager - Strategic Initiatives Location: [Global] Category: Project Management *Position location to be determined by home country of successful candidate in a jurisdiction (country of US state)

More information

PROJECT MANAGEMENT OVERVIEW

PROJECT MANAGEMENT OVERVIEW Chapter One PROJECT MANAGEMENT OVERVIEW Project management itself is not a new concept. It has been practiced for hundreds, even thousands of years. Any large undertaking requires a set of objectives,

More information

Topic for today: From tactical to strategic the journey of a PMO

Topic for today: From tactical to strategic the journey of a PMO Topic for today: From tactical to strategic the journey of a PMO The Start-up PMO Structure Chief Executive Officer Director: Strategy Group Executive: Strategic Projects Project Administrator Portfolio

More information

University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives

University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives Updated: October 2017 1. Introduction This procedure exists to ensure operational adherence with

More information

White Paper. PDC Taxonomy

White Paper. PDC Taxonomy PDC Taxonomy This White Paper is designed to provide some clarity in the terms used to describe Portfolio, Program and Project management (a PPP Taxonomy) and their key governance, support and oversight

More information

Ōtākaro Limited Statement of Intent

Ōtākaro Limited Statement of Intent Ōtākaro Limited Statement of Intent For Financial Years 2018 to 2022 INTRODUCTION This Statement of Intent (SOI) is submitted by the Board of Directors of Ōtākaro Limited (Ōtākaro), pursuant to the Crown

More information

Discussion Paper: Shared Services

Discussion Paper: Shared Services Discussion Paper: Shared Services 23 November 2016 Overview This discussion paper presents an overview of the opportunities for the delivery of professional services for Western Sydney University (the

More information

Job Description Overall Purpose of Role:

Job Description Overall Purpose of Role: Job Description Job Title : Department : Programme Analyst Demand Management / IT Reporting to (Job Title) : Portfolio Manager No of Direct Reports : 0 Titles of Direct Reports: N/A Size of Department:

More information

Driving integration and innovation at the point of service delivery Outcome-based homecare

Driving integration and innovation at the point of service delivery Outcome-based homecare COMMISSIONING THE FUTURE: WORKSHOP 3 Driving integration and innovation at the point of service delivery Outcome-based homecare Facilitator s Notes, July 2012 Commissioning The Future Workshop materials

More information

Design Management Plan

Design Management Plan Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

Job Description. No of Direct Reports : 0. Titles of Direct Reports: varied number in seconded project team. Budget Responsibility (direct) :

Job Description. No of Direct Reports : 0. Titles of Direct Reports: varied number in seconded project team. Budget Responsibility (direct) : Job Description Job Title : Department : Project Analyst Portfolio Management / IT Reporting to (Job Title) : Portfolio Manager No of Direct Reports : 0 Titles of Direct Reports: N/A Size of Department:

More information

Evaluation, Not Just a Matter of Training or Resources. but a Cultural Change. J. Hanwright and S. Makinson Queensland, Australia

Evaluation, Not Just a Matter of Training or Resources. but a Cultural Change. J. Hanwright and S. Makinson Queensland, Australia Evaluation, Not Just a Matter of Training or Resources but a Cultural Change J. Hanwright and S. Makinson Queensland, Australia DETA adopted its current Program Evaluation Strategy in August 2005. The

More information

Senior Advisor, Privacy, Te Ara Manaaki

Senior Advisor, Privacy, Te Ara Manaaki Senior Advisor, Privacy, Te Ara Manaaki Te Ara Manaaki, Service Delivery and Operations The senior advisor privacy will work as part of the Policy & Privacy team to foster positive privacy outcomes in

More information

Simplification of work: Knowledge management as a solution within the European Institutions

Simplification of work: Knowledge management as a solution within the European Institutions Simplification of work: Knowledge management as a solution within the European Institutions Second line optional lorem ipsum B Subhead lorem ipsum, date quatueriure 2 Content 4 Simplification of work:

More information

Lisa Hodges Owner/Principal Consultant

Lisa Hodges Owner/Principal Consultant Lisa Hodges Owner/Principal Consultant Cornerstone Service Management unless otherwise stated. ITIL is a registered trademark of Axelos Limited. PRINCE2 is a registered trademark of Axelos Limited. PMBoK

More information

TA Corporate Risks - Ethical Business Practice and Modern Compliance Framework Technical Annex. September 2018 Version 1.0

TA Corporate Risks - Ethical Business Practice and Modern Compliance Framework Technical Annex. September 2018 Version 1.0 TA 7.2 - Corporate Risks - Ethical Business Practice and Modern Compliance Framework Technical Annex September 2018 Version 1.0 Navigation: TA 7.2 Modern Compliance Framework and Ethical business practice

More information

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102 INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102 Audit of the United Nations Conference on Trade and Development arrangements for initiation, review and clearance of technical cooperation projects Overall

More information

Job PLAN INTERNATIONAL UK JOB PROFILE

Job PLAN INTERNATIONAL UK JOB PROFILE Job PLAN INTERNATIONAL UK JOB PROFILE Job Title Department Unit (if appropriate) Consortium Manager (Education) and Partnership Development Unit Grade 2 Salary Contract type Reporting to Responsible for

More information

Programme & Project Planning and Execution

Programme & Project Planning and Execution Portfolio, LEADING THE WAY IN PROJECTS Programme & Project Planning and Execution Caravel Group - Project Management with a total focus on value THE SPECIALIST FOR LARGE COMPLEX MULTI-DISCIPLINED PROJECTS

More information

White Paper. Seven Secrets of Successful PMOs

White Paper. Seven Secrets of Successful PMOs White Paper Seven Secrets of Successful PMOs Introduction Establishing a PMO is a popular approach taken by many organizations to facilitate project portfolio management or project management capability

More information

The Ministry. Project XYZ. Assurance Plan V.02 July Document Approval. Approved by Senior Responsible Officer

The Ministry. Project XYZ. Assurance Plan V.02 July Document Approval. Approved by Senior Responsible Officer The Ministry Project XYZ Assurance Plan V.02 July 2014 Document Approval Name / Title Sign-off Date Approved by Senior Responsible Officer Endorsed by the Project Board Endorsed by Chief Executive Endorsed

More information

BUSINESS CONTINUITY MANAGEMENT

BUSINESS CONTINUITY MANAGEMENT Loss Control BUSINESS CONTINUITY MANAGEMENT Preparing for the Unexpected Preparing your organization for a disaster can be an overwhelming task, but the risk of being unprepared can be even more devastating.

More information

CUSTOMERS AND OUR ENERGY NETWORKS.

CUSTOMERS AND OUR ENERGY NETWORKS. CUSTOMERS AND OUR ENERGY NETWORKS. ActewAGL Distribution Customer Engagement Strategy Stage 2 December 2016 Message from the CEO. Community is important to us. In 2015 we celebrated 100 years of providing

More information

POSITION DESCRIPTION TEAM LEADER, COMMUNICATIONS, ENGAGEMENT AND COMMUNITY RELATIONS

POSITION DESCRIPTION TEAM LEADER, COMMUNICATIONS, ENGAGEMENT AND COMMUNITY RELATIONS Team Classification Position Objective Communications Western Water Enterprise Agreement Band 7 Level A Level D FIXED TERM ROLE Hands-on leadership role. Coordination, development and delivery of business

More information

HDA Coaching Culture Survey Results 2011

HDA Coaching Culture Survey Results 2011 HDA Coaching Culture Survey Results 2011 HDA is a Human capital consultancy that has worked in the area of coaching for 17 years, developing a reputation for a highly successful, outcomes-focused approach

More information

JOB DESCRIPTION. Manager Service Management Technical Systems & Proposed band. Job family

JOB DESCRIPTION. Manager Service Management Technical Systems & Proposed band. Job family Job title Job family Manager Service Management Technical Systems & Proposed Delivery band E Job purpose The Manager, Service Management is responsible for leading a functional team in one of the specialist

More information

Principal Continual Service Improvement Manager Technical Systems & Grade Grade 9 Delivery

Principal Continual Service Improvement Manager Technical Systems & Grade Grade 9 Delivery Job title Job family Principal Continual Service Improvement Manager Technical Systems & Grade Grade 9 Delivery Job purpose The Continual Service Improvement (CSI) manager is responsible for leading a

More information

Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value

Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value SAP Thought Leadership Value Realization Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value The Business Transformation Services group of SAP

More information

Head of marketing production

Head of marketing production Head of marketing production Role Brief Directorate Base location Marketing and communications Bristol Grade B 18 Date September 2016 Reports to Group marketing director Responsible for Production events

More information

ROLE DESCRIPTION. VISION To make Sydney and NSW one of the world s most successful tourism and events destinations.

ROLE DESCRIPTION. VISION To make Sydney and NSW one of the world s most successful tourism and events destinations. ROLE DESCRIPTION Senior Research Business Analyst Division: Corporate Services Location: Sydney, Australia Grade Equivalent:9/10 Kind of Employment: Permanent ANZSCO Code: Date of Approval: Agency Website:

More information

The Five Stages of a Successful Agile Transformation

The Five Stages of a Successful Agile Transformation White Paper The Five Stages of a Successful Agile Transformation Providing you with: An understanding of Agile s key principles and processes Advice on defining an effective transformation strategy Tips

More information

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 POLICY NUMBER P15/2 VERSION 1.0 CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 AUTHORISED BY Trust ISSUED DATE 10/08/2015 DISTRIBUTION External REVIEW DATE

More information

Moving Upmarket: New Roles for Old PMOs

Moving Upmarket: New Roles for Old PMOs Moving Upmarket: New Roles for Old PMOs G J Rankins CPPD MApplSc MBA This paper was presented at the Australian Institute of Project Management National Conference, 7-10 October 2007, Hobart, Tasmania,

More information

Job description and person specification

Job description and person specification Job description and person specification Job title Business Process Lead - NHS RightCare System Programme Management& Governance Position Directorate Midlands & East Region Pay band AFC Band 8c Responsible

More information

SACN Strategic Evaluation: Organisational Implications Report. SACN Strategic Evaluation Organisational Implications Report Version 1 i

SACN Strategic Evaluation: Organisational Implications Report. SACN Strategic Evaluation Organisational Implications Report Version 1 i SACN Strategic Evaluation: Organisational Implications Report SACN Strategic Evaluation Organisational Implications Report Version 1 i EXECUTIVE SUMMARY Introduction This report provides an overview of

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

National Development Programs Manual

National Development Programs Manual National Development Programs Manual August 2014 V5 For further information, please contact: Diabetes Australia GPO Box 3156 Canberra ACT 2601 Fax: (02) 6230 1535 Email: admin@diabetesaustralia.com.au

More information

PRINCE Update. Changes to the manual. AXELOS.com. April 2017 PUBLIC

PRINCE Update. Changes to the manual. AXELOS.com. April 2017 PUBLIC PRINCE2 2017 Update s to the manual AXELOS.com April 2017 2 PRINCE2 2017 Update Contents 1 Introduction 3 2 Summary of changes 4 PRINCE2 2017 Update 3 1 Introduction This document provides a list of the

More information

GREATER MANCHESTER HEALTH AND SOCIAL CARE PARTNERSHIP STRATEGIC PARTNERSHIP BOARD

GREATER MANCHESTER HEALTH AND SOCIAL CARE PARTNERSHIP STRATEGIC PARTNERSHIP BOARD NHS Bury CCG Governing Body Paper 6 appendix 6a 5ci GREATER MANCHESTER HEALTH AND SOCIAL CARE PARTNERSHIP STRATEGIC PARTNERSHIP BOARD Date: 29 April 2016 Subject: The Transformation Fund Report of: Katy

More information

Introduction This is a presentation about the introduction of Project, Programme and Change Management disciplines into a global company. It aims to s

Introduction This is a presentation about the introduction of Project, Programme and Change Management disciplines into a global company. It aims to s Project, Programme and Change Management in British American Tobacco: A 5 Year Story in 30 minutes. Introduction This is a presentation about the introduction of Project, Programme and Change Management

More information

Collaboration within the public sector

Collaboration within the public sector Collaboration within the public sector presented by SenateSHJ February 2014 We literally knocked the wall down between the two of us and that massively changed things. Our staff are doing what they ve

More information

Action to date: Recommendation 2: Response: Action to date:

Action to date: Recommendation 2: Response: Action to date: ANNEX C 360 Assurance Report Urgent and Emergency Care Centre Project 3rd Project Governance Assurance Report Response to recommendations Background: 360 Assurance were appointed by the CCG to provide

More information

POSITION DESCRIPTION SENIOR ENGINEER

POSITION DESCRIPTION SENIOR ENGINEER POSITION DESCRIPTION SENIOR ENGINEER Position Title: Classification: Department: Position Type: Organisational Context: Senior Engineer SGW Enterprise Agreement - SEO Infrastructure and Planning Team Full

More information

Become A Change Champion

Become A Change Champion Become A Change Champion By Mark Williams Head Of Training MTD Training Web: www.mtdtraining.com Telephone: 0800 849 6732 1 MTD Training, 5 Orchard Court, Binley Business Park, Coventry, CV3 2TQ Web: www.mtdtraining.com

More information

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED NOT PROTECTIVELY MARKED MEETING TITLE Audit Committee Public Session DATE 23 August 2017 PAPER TITLE IT Service Delivery ITEM NO 6.5 PREPARED BY Gary Devlin PURPOSE This paper presents our final report

More information

GRIP for Programmes Release 1 (DRAFT) April Network Rail GRIP for Programmes Page 1 of 104

GRIP for Programmes Release 1 (DRAFT) April Network Rail GRIP for Programmes Page 1 of 104 GRIP for Programmes Release 1 (DRAFT) April 2015 Network Rail GRIP for Programmes Page 1 of 104 Network Rail GRIP for Programmes Page 2 of 104 Forward Purpose This document provides an overview and guidance

More information

Horizontal audit of the Public Services and Procurement Canada investigation management accountability framework

Horizontal audit of the Public Services and Procurement Canada investigation management accountability framework Final Report Horizontal audit of the Public Services and Procurement Canada investigation October 11, 2017 Office of Audit and Evaluation Table of contents Background... 1 About the audit... 2 Audit observations...

More information

White Paper Realising benefits: How to plan for success

White Paper Realising benefits: How to plan for success Realising benefits: How to plan for success UK Government departments are currently facing significant challenges prioritising their initiatives effectively under increased resource constraints. Robust

More information

Define and Initiate SubPhase

Define and Initiate SubPhase Project Management Methodology Project Management Methodology Training Define and Initiate SubPhase Course Purpose Familiarize team members with the Start Project Sub-Phase processes. Understand process

More information

Role Description Team Leader, Policy & Program Animal Biosecurity

Role Description Team Leader, Policy & Program Animal Biosecurity Role Description Team Leader, & Program Animal Biosecurity Cluster Industry Agency Department of Primary Industries Division/Branch/Unit DPI Biosecurity & Food Safety / Animal Biosecurity Location Orange/

More information

Implementing a Project Infrastructure

Implementing a Project Infrastructure The PROJECT PERFECT White Paper Collection Overview Implementing a Project Infrastructure eville Turbit In working with a client recently, proved an interesting experience. The way in which the organisation

More information