Alternative Project Delivery Status Update 2013

Size: px
Start display at page:

Download "Alternative Project Delivery Status Update 2013"

Transcription

1 Alternative Project Delivery Status Update 2013 Eric Kahlig Division of Construction Management Alternative Project Delivery Innovative Contracting Manual Separate from Division of Innovative Delivery Traditional Funding Sources DB / Incentive Disincentives / A+B / Etc. Value Engineering Change Proposals LPA Construction Monitoring 1

2 Alternative Project Delivery Two major Initiatives OHIO CMGC Deployment Implementation Team Design Build Background Primary focus Design Build Contracts Background Definition Owner executes a single contract with one entity (design builder) to provide engineering services and construction services. Preliminary authority to enter into Design Build contracts in

3 Design Build Background ODOT currently has the authority to enter into Design Build contracts per ORC effective Min = 2 / year Max = 26 / year (2013) $5 million to $550 million per year 148 projects using the Least Cost Method $725mill FY 2013: $136Mill Design Build Background An amendment to the ORC (6/29/2011) ODOT allowed to combine technical qualifications and competitive bidding elements Value Based DB CUY 90: Cleveland Innerbelt Bridge CCG1 Fra 71/670: Columbus Crossroads Project internally identified issues 3

4 Design Build Background Initially developed Value Based without extensive industry input First 2 VB DBs resulted in litigation CUY90 Innerbelt concerning interpretation of Scope Requirement Dismissed FRA 71/670 Columbus Crossroads Concerning responsiveness to project requirements Stipend Paid Design Build Last 5 years Fiscal Year Total Projects Sold Total Contract $ Total DB Projects Sold DB Total Contract $ % $ of total program $1,223,823, $9,041, % $1,318,291, $13,493, % $1,545,548, $81,710, % $1,556,481, $558,819, % $1,264,950, $114,496, % Note: FY2011 Cleveland Innerbelt Bridge Ph1 and Columbus Crossroads Ph1 both sold. 4

5 Year Design Build Next 5 years # of DB Projects DB Value Total Program % $ of total program $138,731, $ 1,892,817, % $513,402, $ 1,810,499, % $39,793, $ 2,148,813, % $157,153, $ 2,003,443, % $1,043, $ 2,108,204, % FY 2014 include DB Finance CUY90 Adjusted = 12% 7 ODOT 2 FHWA 5 OCA Members 5 ACEC Members 5

6 Task Force Scope: Review existing alternative project delivery techniques, assessing usage and value of each Identify new alternative project delivery techniques Design Build Evaluation, Usage, and potential Improvements in Ohio Low Bid / 2 Step / ATC Process / Standards Every Day Counts Initiative Round 1 Implemented changes: Least Cost Design Builds Projects of value less than $20 million 8 weeks minimum advertising w/ a PreBid Meeting being optional Projects of $20 million or more will be Advertised for 12 weeks with prebid meetings being mandatory 6

7 DB Project Type Changes Signal and Signage projects considered separately Signage projects no longer allowed to be DB projects Signal projects may be DB Noisewall Projects no longer allowed to be DB Simplified project plans to be developed PN124/125 A+B (Price + Time) Considered usage on all: not being implemented Usage to continue to be District decisions no mandatory usage per project type Revised table changes to be addressed: Time portion to be Day for Day. Removal of anticipated weather days for B impacted work 7

8 PN128 Windows Contracts Rename to Flexible Start / Windows Contract Open up allowed contract types. New Bridge / Bridge Replacement allowed Four Lane Resurfacing & Overlays allowed No Major Reconstruction / Major New Note to apply to entire project not just portions Contractor Designed MOT Traffic Engineering Manual: Item 614 Maintaining Traffic The Contractor shall be responsible for designing and maintaining safe and effective traffic control 24 hours a day for the duration of this project. The Contractor shall devise a maintenance of traffic scheme which shall be stamped by a professional engineer, and present it to the Engineer for approval. 8

9 Contractor Designed MOT ODOT District Usage last 5 yrs. Dist. 1, 8, &11 Have used extensively Dist. 3, 4, & 12 Have used some Dist. 2, 5, 6, 7, & 10 Have not used Contractor Designed MOT Pros No Wasted Designer Effort Most Efficient design employed (Contractor controlled) Fast Plan Prep in Design Cons Waste of multiple designs Owner concerns = Safety. Contractor concerns = Safety + Money Unleveled Bidding field Who owns changes? Not controlling overall Design 9

10 Contractor Designed MOT Statewide Consistency a Priority Recommendation: No further usage of Contractor Designed MOT Limited projects within developed will be allowed to continue NO Excuse Incentive NEI The NEI Date shall not be adjusted for any reason, cause or circumstance whatsoever, regardless of the cause of the delay No Claims if Accepted 2 Pilot Project $3.0 Mill Incentive / $1.5 Mill 1 year off both Specifications relaxed on 2 nd implementation 10

11 No Excuse Incentive Feedback Like the Incentives, but DO NOT USE ARBITRARILY!!! Why No Claims? Why So Harsh if missed by 1 day? Re evaluating and reworking Value Based Design Build Shortlisting SOQ Discussion Heavy Weighting on Personnel Potentially Important to Design More weighting should be on Contractor s company Bait and Switch concerns Scoring of SOQ depends on RFQ details Under advisement.. 11

12 Upcoming ATCs in DBB 2 Step DB Not necessarily VB DB Task Order Contract for Ohio Upcoming DB Project Listing Update Monthly onmgt/designbuild/designbuild/forms/dbs.aspx 12

13 Construction Manager / General Contractor Construction Manager / General Contractor CMGC is a project management method which engages a selected Contractor to work with a selected Designer early in the development of a project Quality Based Selection (primarily) 13

14 Construction Manager / General Contractor Overall A Project Team consisting of three components: An Owner A Contract with a Designer A Two Phase Contract with a General contractor Phase one Construction Management consulting contract to help with design Phase two General Contractor Construction Manager / General Contractor Part one: Work with Owner, and Designer to design Project Provide advice on Constructability, Schedule, Materials, Budget When ready, Price the Project Part two: Construction Contract 14

15 Construction Manager / General Contractor Advantages Collaboration Risk Aversion and Risk Assignment Schedule savings Innovation Consultants continue to work for the owner Owner owns the design Gain the Best of All Worlds (potentially) Construction Manager / General Contractor Ohio Hurdles Legislative Policy Project Selection Construction Manager selection Management Strategy 15

16 Construction Manager / General Contractor Ohio Hurdles continued Perception Beauty Contest Limited Competition Shotgun Marriage Project Cost validation Construction Manager / General Contractor Every Day Counts and MAP 21 No longer requiring Special Experimental Project (SEP 14) consideration Still considered Innovative therefore allowed to be 100% federally funded per MAP21 Every Day Counts Initiative Round 2 16

17 OHIO CMGC Deployment Implementation Team OHIO CMGC Deployment Team ODOT/FHWA Co Chairing ODOT Deputy Director Construction Management FHWA Field Operations Team Leader ODOT 8 members OCA 3 members FHWA 2 members ACEC 2 members OHIO CMGC Deployment Implementation Team Preliminary Discussions Should not include a unit price component during CMGC selection Funding will need to be identified and committed 50% self performance requirement Substantial size to judge effectiveness No VECPs after award will be allowed Independent Cost Estimator 17

18 OHIO CMGC Deployment Implementation Team Potential CMGC Selection Evaluation Topics Project Team Capability of the Contractor Project Approach Project Innovations CMGC Design Process formalized Risk Management Model Understanding / Approach Approach to Price Proposal OHIO CMGC Deployment Implementation Team CMGC Pre Construction Services Constructability Reviews CPM Schedule (Design) Material Availability Reviews Identification of Long Lead Items/Issues Ongoing cost estimates Stakeholder Identification Risk Identification / Mitigation Potentials 18

19 OHIO CMGC Deployment Implementation Team Potential Project Selection Criteria Monetary Size $30 $80 mill. Constructability and Technically complex Schedule Issues Third Party Stakeholders Construction Flexibility OHIO CMGC Deployment Implementation Team Proposed Legislative Highlights Single pilot project CMGC for preconstruction fee based services Negotiated fixed price, fixed unit prices, or guaranteed maximum price All estimates within 10% to award construction Independent Cost Estimator Out for bid if negotiated pricing not reached Currently under review by Legislature 19

20 OHIO CMGC Deployment Implementation Team Candidate Project was discussed I 480 Bridge Redecking Difficult Bridge construction Phase Construction sequences Difficult MOT / Construction Access Team Evaluation of Pros/Cons Team Recommendation = Different Project Limited Solutions / Late in Process / Long Construction Timeline Thank You Eric Kahlig ODOT Division of Construction Management eric.kahlig@dot.state.oh.us 20

Ohio Department of Transportation. Conflict of Interest Waiver Process Guidance Concerning Review of Conflict of Interest Waiver Requests

Ohio Department of Transportation. Conflict of Interest Waiver Process Guidance Concerning Review of Conflict of Interest Waiver Requests June 26, 2017 (rev. 9/29/2017) Ohio Department of Transportation Conflict of Interest Waiver Process Guidance Concerning Review of Conflict of Interest Waiver Requests Purpose The purpose of this document

More information

Construction Administration Updates

Construction Administration Updates Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Construction Administration Updates Clint Bishop Construction Administration Updates Construction Administration Updates

More information

Pioneering Alternative Project Delivery in Ohio

Pioneering Alternative Project Delivery in Ohio Pioneering Alternative Project Delivery in Ohio Ali Bahar, PE Principal Engineer Metropolitan Sewer District of Greater Cincinnati Tim Koch, PE, Vice President, Brown and Caldwell 1 Agenda Construction

More information

Design-Build (DB) and Construction Manager / General Contractor (CMGC)

Design-Build (DB) and Construction Manager / General Contractor (CMGC) Design-Build (DB) and Construction Manager / General Contractor (CMGC) IDOT and Industry Preliminary Joint Review for Proposed Legislation December 18, 2012 Welcome Introductions Agenda Purpose Definitions

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

State of Ohio. Department of Transportation ~ Innovative Contracting Manual

State of Ohio. Department of Transportation ~ Innovative Contracting Manual State of Ohio Department of Transportation ~ Innovative Contracting Manual 4/10/2006 Copies of this manual and reference materials may be obtained at: Ohio Department of Transportation Division of Construction

More information

Presented By: Debbie Hunt Florida Department of Transportation District Seven Director of Transportation Development October 16, 2013

Presented By: Debbie Hunt Florida Department of Transportation District Seven Director of Transportation Development October 16, 2013 PROJECT MANAGEMENT IN A DOT ENVIRONMENT Presented By: Debbie Hunt Florida Department of Transportation District Seven Director of Transportation Development October 16, 2013 Mission Safe Transportation

More information

CONSTRUCTRION MANAGEMENT AT RISK ASHE December 13, 2011 Julio Alvarado Construction State Engineer

CONSTRUCTRION MANAGEMENT AT RISK ASHE December 13, 2011 Julio Alvarado Construction State Engineer CONSTRUCTRION MANAGEMENT AT RISK CM@R ASHE December 13, 2011 Julio Alvarado Construction State Engineer 1 Agenda Background What leads DOT s to CMAR? ADOT s Outlook on CMAR Project Updates CMAR Benefits

More information

I-90 Pavement Rehab VE Study

I-90 Pavement Rehab VE Study I-90 Pavement Rehab VE Study Using Value Analysis to Select Project Delivery Method Ken L. Smith, PE, CVS 360-570-4415 The week may have started with a bang But it ended with a success Do not drink and

More information

Agenda. Hugh Tucker, Deputy Chief Procurement Officer Legislation Request for Qualifications/Proposals

Agenda. Hugh Tucker, Deputy Chief Procurement Officer Legislation Request for Qualifications/Proposals August 15, 2016 1 Agenda Welcome & Introduction Design-Build Vision Comprehensive Modernization Projects 2016 Legislation Request for Qualifications/Proposals Proposal Scoring Information Provided By LAUSD

More information

FINAL INSPECTION OF CONSTRUCTION PROJECTS

FINAL INSPECTION OF CONSTRUCTION PROJECTS Approved: Standard Procedure No.: 510-007(SP) Effective Date: January 19, 2010 Responsible Division: Construction Management Supersedes procedure dated June 1, 2009 William H. Lindenbaum, P.E., P.S., Deputy

More information

Ivan Damnjanovic and Stu Anderson

Ivan Damnjanovic and Stu Anderson Selection and Evaluation of Alternative Contracting Methods to Accelerate Project Completion (NCHRP 20-5) Ivan Damnjanovic and Stu Anderson Texas A&M University Texas Transportation Institute August 2008

More information

A Primer Indianapolis, Indiana June 16, 2010

A Primer Indianapolis, Indiana June 16, 2010 Alternative Project Delivery Methods A Primer Indianapolis, Indiana June 16, 2010 Michael Kenig, Holder Construction Company, Past chair of AGC of America s s Project Delivery Committee Jayne O Donnell,

More information

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013)

SH 183 Managed Lanes Project RFQ Q & A MATRIX #2. (June 4, 2013) SH 183 Managed Lanes Project RFQ Q & A MATRIX #2 (June 4, 2013) No. Current language states: Project experience provided by a parent or sister company of the Lead Engineering Firm, Lead Contractor or Lead

More information

CM/GC Contracting Lessons Learned from Portland and San Francisco

CM/GC Contracting Lessons Learned from Portland and San Francisco CM/GC Contracting Lessons Learned from Portland and San Francisco Lance Erz, TriMet Robin M Reitzes, SF City Attorney s Office American Public Transportation Association Legal Affairs Seminar February

More information

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services Kevin Western, MnDOT State Bridge Engineer House Transportation Policy and Finance Committee April 11, 2016 Introduction to Design

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

Alternative Delivery Methods in the Post-Davis World

Alternative Delivery Methods in the Post-Davis World CASBO 2017 Annual Conference April 2017 Alternative Delivery Methods in the Post-Davis World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson

More information

George V. Voinovich Bridge Project

George V. Voinovich Bridge Project George V. Voinovich Bridge Project INVEST Webinar October 27, 2014 David Lastovka, P.E. Ohio DOT District 12 Cleveland Innerbelt Corridor Project Manager ODOT District 12-Cleveland, Ohio Cleveland Innerbelt

More information

VILLAGE OF GLENDALE, OHIO REQUEST FOR QUALIFICATIONS CIVIL ENGINEERING SERVICES JULY 2015

VILLAGE OF GLENDALE, OHIO REQUEST FOR QUALIFICATIONS CIVIL ENGINEERING SERVICES JULY 2015 VILLAGE OF GLENDALE, OHIO REQUEST FOR QUALIFICATIONS CIVIL ENGINEERING SERVICES I. INVITATION JULY 2015 The Village of Glendale requests firms submit proposal and qualifications for ongoing Civil Engineering

More information

INNOVATIVE CONTRACTING GUIDELINES

INNOVATIVE CONTRACTING GUIDELINES Office of Construction and Innovative Contracting INNOVATIVE CONTRACTING GUIDELINES A+B Bidding Lane Rentals Incentives/ Disincentives Liquidated Savings Design-Build Warranties Pay for Performance No

More information

Project Delivery. Rodger Rochelle, PE Technical Services Administrator. Mike Holder, PE Chief Engineer

Project Delivery. Rodger Rochelle, PE Technical Services Administrator. Mike Holder, PE Chief Engineer Project Delivery Rodger Rochelle, PE Technical Services Administrator Mike Holder, PE Chief Engineer NC : Project Delivery - Preconstruction Overview of Project Delivery Process Review of Other States

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Agency Project Name Stadium Project Response Deadline 1/9/14 12 pm local time

More information

ALTERNATIVE PROJECT DELIVERY DIVISION PROGRAM UPDATE

ALTERNATIVE PROJECT DELIVERY DIVISION PROGRAM UPDATE ALTERNATIVE PROJECT DELIVERY DIVISION PROGRAM UPDATE 2018 VTCA VDOT Consultant Forum Shailendra Patel, P.E., DBIA State Engineer APD Division October 2, 2018 Odd Fellows Road Improvements Design-Build

More information

Project: Replacement provision for the Highway Term Service Contract (HTSC)

Project: Replacement provision for the Highway Term Service Contract (HTSC) BUSINESS JUSTIFICATION CASE (BJC) Project: Replacement provision for the Highway Term Service Contract (HTSC) Purpose: To support the Councils Highways Service in the management of highways infrastructure,

More information

Accelerated Construction: A Path Forward by Texas Department of Transportation 512/ All Rights Reserved

Accelerated Construction: A Path Forward by Texas Department of Transportation 512/ All Rights Reserved Accelerated Construction: A Path Forward 2018 by Texas Department of Transportation 512/416-2500 All Rights Reserved Introduction The construction zone is the visible and perhaps only connection between

More information

Project Delivery Systems

Project Delivery Systems Project Delivery Systems National Society of Professional Engineers Alaska Society of Professional Engineers 2011 Western and Pacific Region Annual Meeting and Conference Jeffrey Callahan April 1, 2011

More information

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018 Request for Proposal for GC/CM Consultant Services Ferndale School District Secondary High School GC/CM Program October 19, 2018 The Ferndale School District is requesting proposals for project management,

More information

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011)

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Sec. 153.65. As used in sections 153.65 to 153.73 of the Revised Code: (A)(1)

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

Please note the following policy concerning communication between Consultants and the City of Dublin during the announcement and selection process:

Please note the following policy concerning communication between Consultants and the City of Dublin during the announcement and selection process: 01-08-19 Posting Date FRA-33-3.70 Smart Technology Connected Vehicle Roundabout Application Project PID No. 109356 City of Dublin Response Due Date: 01-24-19 Communications Restrictions Please note the

More information

Texas School for the Blind and Visually Impaired Contract Management Guide

Texas School for the Blind and Visually Impaired Contract Management Guide Texas School for the Blind and Visually Impaired Contract Management Guide TSBVI Contract Management Guide Page 1 of 9 June 2017 TABLE OF CONTENTS Section Title Page No. 1. INTRODUCTION 3 2. PROCUREMENT

More information

REQUEST FOR QUALIFICATIONS CAMP HALL RAILROAD BUILD-IN DESIGN-BUILD PROJECT

REQUEST FOR QUALIFICATIONS CAMP HALL RAILROAD BUILD-IN DESIGN-BUILD PROJECT REQUEST FOR QUALIFICATIONS CAMP HALL RAILROAD BUILD-IN DESIGN-BUILD PROJECT Camp Hall Commerce Park (Camp Hall) Ridgeville, South Carolina March 2, 2018 Addendum 2 March 29, 2018 Comment Sheet 1 of 5 Sheets

More information

Strategic Initiatives 2000 & 2001

Strategic Initiatives 2000 & 2001 Strategic Initiatives 2000 & 2001 Introduction ODOT has worked in recent years to become more efficient and effective in its use of the public tax dollar. Since the early 1990 s the department has increased

More information

Design-Build: the National Perspective

Design-Build: the National Perspective Design-Build: the National Perspective Douglas D. Gransberg, PhD, PE, DBIA University of Oklahoma dgransberg@ou.edu 2007, All rights reserved, Douglas Gransberg, PE 1 Traditional vs. Non-Traditional Traditional

More information

LPA Stewardship and Oversight A Louisiana Perspective

LPA Stewardship and Oversight A Louisiana Perspective LPA Stewardship and Oversight A Louisiana Perspective A Little History FY 2007 FHWA HQ LPA Comprehensive Oversight Program Determination Results (HINT: RED = NOT GOOD) Yes No Yes/No Undetermined NA Getting

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

EXHIBIT 6 Preconstruction Work

EXHIBIT 6 Preconstruction Work EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements

More information

TRANSPARENCY IN STRATEGIC PROJECTS DIVISION

TRANSPARENCY IN STRATEGIC PROJECTS DIVISION TRANSPARENCY IN STRATEGIC PROJECTS DIVISION Scott Spradlin, P.E. Strategic Projects Division, TxDOT Footer Text October 13, 2015 Date INNOVATIVE PROJECT DELIVERY INNOVATIVE PROJECT DELIVERY AUTHORITY AND

More information

Design-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection

Design-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection DESIGN-BUILD Design-Build Authorization Project Selection Criteria Selection/Award Process Warranties Design-Build Construction Engineering and Inspection Materials Acceptance DESIGN-BUILD AUTHORIZATION

More information

Florida Department of Transportation District-Wide DESIGN-BUILD TOPICS PUSH BUTTON Contract

Florida Department of Transportation District-Wide DESIGN-BUILD TOPICS PUSH BUTTON Contract Florida Department of Transportation District-Wide DESIGN-BUILD TOPICS PUSH BUTTON Contract (FEDERAL SAFETY AND STATE FUNDS) Contract Evaluation June 2013 06/18/13 FDOT DBPB Evaluation 1 Jobs Creation

More information

448 INNOVATIVE BIDDING TOOLKIT

448 INNOVATIVE BIDDING TOOLKIT Publication 448 INNOVATIVE BIDDING TOOLKIT 2013 Edition, Change 2 Bureau of Project Delivery, Highway Delivery Division Project Schedules, Specifications and Constructability Section PUB 448 (05-16) This

More information

Proposal for Preconstruction Services CM/GC Services-TMSF Office and Maintenance Building Project

Proposal for Preconstruction Services CM/GC Services-TMSF Office and Maintenance Building Project Equal Opportunity Employer January 5, 2015 Exhibit A Exhibit A CM/CG Preconstruction Services Proposal Diane Morrison, CPPB PW Purchasing Specialist Public Works Department 150 N Capitol Blvd. Boise, Idaho

More information

Design-Build Terminology

Design-Build Terminology Design-Build Terminology This glossary is representative of the terminology used in the design-build community and advocated by the Canadian Design-Build Institute (CDBI). For definitions of contractual

More information

Design-Build and Design-Bid-Build

Design-Build and Design-Bid-Build Design-Build and Design-Bid-Build Comparison of Overall Cost and Time Question: How does the total cost and time to deliver a $55,000,000 and 814 day design-build project compare to using design-bid-build

More information

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS PROJECT: ISSUE DATE: October 22, 2018 ISSUED BY: INQUIRIES: SUBMISSION DEADLINE: SUBMIT TO: City of Delaware, Ohio Public Works Department, Traffic & Engineering Services 440

More information

Topics of Discussion

Topics of Discussion Ohio Department of Transportation Consultant Selection & Agreements Lee Matthes, P.E. District 8 Consultant Contract Manager ta Manager John R. Kasich, Governor Jerry Wray, Director www.transportation.ohio.gov

More information

The Pros and Cons of Construction Delivery Methods Available to Community College Districts

The Pros and Cons of Construction Delivery Methods Available to Community College Districts The Pros and Cons of Construction Delivery Methods Available to Community College Districts Community College Facility Coalition 25 th Annual Conference September 11, 2018 Panel Alan Kroeker - Principal

More information

Table of Contents Local Agency Guidelines Section B August 2011

Table of Contents Local Agency Guidelines Section B August 2011 Table of Contents SECTION B NON-CERTIFIED AGENCY 2 Chapter 10 Design Approval... 2 A. OVERVIEW... 2 B. DESIGN ACCEPTANCE PACKAGE (30 PERCENT)... 2 1. Traffic Data... 3 2. Right of Way... 3 3. Horizontal-

More information

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG

More information

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overview of the Project Development Process Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overall Project Development Process The time it takes to produce a project varies significantly

More information

COMMUNICATIONS RESTRICTIONS:

COMMUNICATIONS RESTRICTIONS: 02-18-18 Posting Date SUM-SR 91 and SR 303/Ravenna Signal and Roadway Improvements PID No. 102692 City of Hudson Engineering Department Response Due Date: Friday, March 16, 2018 The City of Hudson s Engineering

More information

EXHIBIT A. 1) General:

EXHIBIT A. 1) General: 1) General: EXHIBIT A FINDINGS OF FACT FOR EXEMPTION FROM COMPETITIVE BIDDING AND USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) METHOD OF CONTRACTING FOR TILLAMOOK PUD OPERATIONS CENTER AND

More information

Selecting Projects for Accelerated Bridge Construction

Selecting Projects for Accelerated Bridge Construction Selecting Projects for Accelerated Bridge Construction In January of 2017, the Engineering Services and Operations Division Directors issued a memo instructing Districts to consider accelerated bridge

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

Any discussions or marketing activities related to this specific project.

Any discussions or marketing activities related to this specific project. 04-11-19 Posting Date South Sandusky Street Widening and Relocation PID No. Not Assigned City of Mount Vernon Response Due Date: 04-24-19 Communications Restrictions Please note the following policy concerning

More information

Addendum 3 publishes and answers questions related to the Request for Qualifications ( RFQ ) issued on November 24, 2014:

Addendum 3 publishes and answers questions related to the Request for Qualifications ( RFQ ) issued on November 24, 2014: www.dot.state.pa.us Date: December 18, 2014 Subject: Questions and Answers Regarding RFQ Solicitation: CNG Fueling for Transit Agencies Partnership Project SOQ Due Date: No later than 11:00 a.m. Eastern

More information

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016 Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of June 2016 Meeting Minutes Facilitator: Robert

More information

EXHIBIT 1. A. The Construction Manager/General Contractor Project Delivery Method

EXHIBIT 1. A. The Construction Manager/General Contractor Project Delivery Method EXHIBIT 1 FINDINGS OF FACT AND CONCLUSIONS SUPPORTING AN EXEMPTION FROM COMPETITIVE BIDDING REQUIREMENTS AND ALLOWING THE USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) COMPETITIVE SELECTION

More information

Route 29 Solutions. September 11, 2014 Rt. 29 Project Delivery Advisory Panel Meeting

Route 29 Solutions. September 11, 2014 Rt. 29 Project Delivery Advisory Panel Meeting September 11, 2014 Rt. 29 Project Delivery Advisory Panel Meeting Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Viewers:

More information

House Doctor Consulting Services Application Package

House Doctor Consulting Services Application Package Public Facilities Department House Doctor Consulting Services Application Package For FY2013 FY2015 House Doctor Consulting Services Project #7005 City of Boston Thomas M. Menino, Mayor Michael Galvin

More information

2009 Louisiana Transportation Conference February 9, 2009 Session 9. LA DOTD s Design-Build Procurement For the I-12 Widening Project

2009 Louisiana Transportation Conference February 9, 2009 Session 9. LA DOTD s Design-Build Procurement For the I-12 Widening Project 2009 Louisiana Transportation Conference February 9, 2009 Session 9 LA DOTD s Design-Build Procurement For the I-12 Widening Project Jeff Burst, P.E. Project Management Administrator Louisiana Department

More information

RAPID INCIDENT SCENE CLEARANCE (RISC)

RAPID INCIDENT SCENE CLEARANCE (RISC) Approved: Effective: September 18, 2008 Traffic Engineering and Operations Topic No. 750-030-020-a RAPID INCIDENT SCENE CLEARANCE (RISC) PURPOSE: Rapid Incident Scene Clearance (RISC) is a highly innovative

More information

Ohio Department of Transportation - Prebid Questions

Ohio Department of Transportation - Prebid Questions Project No. 120625 Sale Date - 12/14/2012 ATB-76747 - IR-90-7.56, PART 1;ATB-90-13.60, PART 2 12/11/2012 8:03:55 AM Per Addendum 5 Item 184 was reduced drastically. With over 35,000 LF of new guardrail

More information

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract

The Effects of Comparative 4D Models on Schedule Development and Controls. Abstract The Effects of Comparative 4D Models on Schedule Development and Controls Kevin Coyne, P.E. Managing Engineer, Exponent, Inc. Abstract In this paper the argument is made that the use of comparative 4D

More information

Subject: Statement of Qualifications for Public Safety Building Design

Subject: Statement of Qualifications for Public Safety Building Design March 5, 2010 Subject: Statement of Qualifications for Public Safety Building Design The City of Porterville seeks Statements of Qualification (SOQ) from qualified architectural and engineering firms for

More information

Executive Steering Committee Meeting. Department of Revenue Building 1 August 9, 2017

Executive Steering Committee Meeting. Department of Revenue Building 1 August 9, 2017 Executive Steering Committee Meeting Department of Revenue Building 1 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of June 20, 2017 Meeting Minutes Facilitator: Melissa

More information

Request for Qualifications. For. Engineering Services. Industrial Pretreatment Facilities Feasibility Study

Request for Qualifications. For. Engineering Services. Industrial Pretreatment Facilities Feasibility Study Request for Qualifications For Engineering Services Industrial Pretreatment Facilities Feasibility Study Issue Date: March 14, 2018 Response Deadline: April 30, 2018, 3:00 p.m. General In accordance with

More information

Project Planning and Development Process

Project Planning and Development Process Project Planning and Development Process The project development process (PDP) involves hundreds of tasks. Many of these are internal agency activities that help an agency follow a methodical process of

More information

APPLICATION INFORMATION: 1. All five sections of the application must be completed.

APPLICATION INFORMATION: 1. All five sections of the application must be completed. HELP ME GROW SUSTAINABILITY PLANNING CONSULTANT REQUEST FOR QUALIFICATIONS Application Deadline: 5:00 pm on MONDAY, SEPTEMBER 25, 2017 APPLICATION INFORMATION: 1. All five sections of the application must

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION PROJECTS

REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION PROJECTS DEPARTMENT OF TRANSPORTATION Transportation Commission and Office of Transportation Safety REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION

More information

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Internal Audit Report Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division Objective To evaluate the effectiveness and efficiency of the PEPS

More information

REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT

REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT REQUEST FOR QUALIFICATIONS PROFESSIONAL AIRPORT ENGINEERING SERVICES RUNWAY 16R-34L IMPROVEMENTS PROGRAM RENO-TAHOE INTERNATIONAL AIRPORT The Reno-Tahoe Airport Authority (RTAA) Reno, Nevada, is seeking

More information

Stakeholders and project delivery methods

Stakeholders and project delivery methods Stakeholders and project delivery methods CIV-E.1040 Construction Management Lecture II 8 th November 2016 Antti Peltokorpi Assistant Professor Department of Civil Engineering, Aalto University antti.peltokorpi@aalto.fi

More information

EXHIBIT 1. A. The Construction Manager/General Contractor Project Delivery Method

EXHIBIT 1. A. The Construction Manager/General Contractor Project Delivery Method EXHIBIT 1 FINDINGS OF FACT AND CONCLUSIONS SUPPORTING AN EXEMPTION FROM COMPETITIVE BIDDING REQUIREMENTS AND ALLOWING THE USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) COMPETITIVE SELECTION

More information

Florida Department of Transportation DESIGN-BUILD PUSH BUTTON Contract

Florida Department of Transportation DESIGN-BUILD PUSH BUTTON Contract Florida Department of Transportation DESIGN-BUILD PUSH BUTTON Contract (FEDERAL SAFETY AND STATE FUNDS) Presentation to FHWA EDC 3 Systemic Safety Implementation Peer Exchange, Nashville, TN September

More information

ADMINISTRATIVE DIRECTIVE #CS-04

ADMINISTRATIVE DIRECTIVE #CS-04 HILLSBOROUGH COUNTY Office of the County Administrator ADMINISTRATIVE DIRECTIVE #CS-04 SUBJECT: EFFECTIVE DATE: UTILITY COORDINATION PROCEDURES FOR HILLSBOROUGH COUNTY CONSTRUCTION PROJECTS WITHIN COUNTY

More information

NYSDOT DESIGN BUILD. Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview. AGC Conference December 10, 2015

NYSDOT DESIGN BUILD. Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview. AGC Conference December 10, 2015 NYSDOT DESIGN BUILD Design-Build Info/Design-Build Moving forward/roles and Responsibilities 2015 Overview AGC Conference December 10, 2015 Where DOT is currently with Design-Build Websites Under procurement

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE CAYUCOS SANITARY DISTRICT 200 Ash Avenue P.O. Box 333, Cayucos, California 93430-0333 www.cayucossd.org 805-995-3290 REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED

More information

Revenue recognition. Resource guide for construction. plantemoran.com

Revenue recognition. Resource guide for construction. plantemoran.com Revenue recognition Resource guide for construction plantemoran.com Revenue recognition 2 Contents Are you ready for principles-based revenue recognition? 2 The revenue recognition process 3 Timeline and

More information

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS CONSULTANT FEE SCHEDULE FOR LANDSCAPE ARCHITECTURAL CONSULTING SERVICES A GUIDELINE NOV 2008 TABLE OF CONTENTS Table Of Contents... 2 INTRODUCTION...

More information

Construction Project Delivery Methods

Construction Project Delivery Methods Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031

More information

Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017

Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017 Fairview Park City Schools Facilities Advisory Committee Meeting: 4/12/2017 Facilities Advisory Committee (FAC) AGENDA FAC focus and framework FPCS Preliminary Design and Construction Schedule Meet our

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)

More information

Managing a Design-Build vs. Bid-Build Project

Managing a Design-Build vs. Bid-Build Project Managing a Design-Build vs. Bid-Build Project January 30, 2018 Claude Ipock, P.E. SCDOT State Construction Engineer Jay Thompson, P.E. SCDOT State Pavement Design Engineer Contract Documents Bonds Performance

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 6/2/2014 Project 140353 Addendum No. 1 PID No. 86675 MOT IR 75 11.75/11.80

More information

STATEMENTS OF QUALIFICATIONS ARE DUE NO LATER THAN 5:00 P.M. FRIDAY, JUNE 23, 2017

STATEMENTS OF QUALIFICATIONS ARE DUE NO LATER THAN 5:00 P.M. FRIDAY, JUNE 23, 2017 RFQ 13-2017-01 REQUEST FOR QUALIFICATIONS FOR A CRITERIA ENGINEER TO PERFORM CERTAIN PROFESSIONAL SERVICES IN THE REPAIR AND/OR REPLACEMENT OF THE LOWER LAKE DAM AND POTENTIAL REPAIRS TO THE UPPER LAKE

More information

Commonwealth of Virginia

Commonwealth of Virginia Commonwealth of Virginia Alternative Project Delivery Division April 2017 Virginia Department of Transportation TABLE OF CONTENTS INTRODUCTION... 2 1.0 DEFINITIONS... 3 2.0 PRELIMINARY PROJECT SELECTION...

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNIVERSITY OF CALIFORNIA, SAN DIEGO BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSOCIATE VICE CHANCELLOR CAPITAL PROGRAM MANAGEMENT TEL: (858) 534-2177 FAX: (858) 534-4363

More information

STATE OF FLORIDA DEPARTMENT OF CHILDREN AND FAMILIES SUBSTANCE ABUSE AND MENTAL HEALTH

STATE OF FLORIDA DEPARTMENT OF CHILDREN AND FAMILIES SUBSTANCE ABUSE AND MENTAL HEALTH STATE OF FLORIDA DEPARTMENT OF CHILDREN AND FAMILIES SUBSTANCE ABUSE AND MENTAL HEALTH REQUEST FOR QUOTES FOR CONSULTING SERVICES TO IDENTIFY REQUIREMENTS FOR A SAMH FINANCIAL AND SERVICES ACCOUNTABILITY

More information

Report on Contract Management Practices Review. Ministry of Finance. Internal Audit & Advisory Services Ministry of Finance

Report on Contract Management Practices Review. Ministry of Finance. Internal Audit & Advisory Services Ministry of Finance Report on Contract Management Practices Review Ministry of Finance Internal Audit & Advisory Services Ministry of Finance Table of Contents Section Page No. Introduction... 1 Purpose... 2 Scope & Objectives...

More information

TXDOT ALTERNATIVE DELIVERY SUPPORT TOOL

TXDOT ALTERNATIVE DELIVERY SUPPORT TOOL TXDOT ALTERNATIVE DELIVERY SUPPORT TOOL Short Course 2016 October 12, 2016 ENABLING LEGISLATION - Timeline for DB & CDA 72 nd Legislature HB 749 - First Bill that authorized Public-Private Partnership

More information

FACILITY PROJECT BIDDING OPTIONS OVERVIEW

FACILITY PROJECT BIDDING OPTIONS OVERVIEW FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Wide HVAC Upgrades - Steam Lines Response

More information

Recruitment and Appointment Policy Responsible Officer. Executive Director, Human Resources Approved by

Recruitment and Appointment Policy Responsible Officer. Executive Director, Human Resources Approved by Recruitment and Appointment Procedure Related Policy Recruitment and Appointment Policy Responsible Officer Executive Director, Human Resources Approved by Executive Director, Human Resources Approved

More information