Dam Safety Instrumentation with Case Study

Size: px
Start display at page:

Download "Dam Safety Instrumentation with Case Study"

Transcription

1 Dam Safety Instrumentation with Case Study Dr. Rajbal Singh Joint Director Rock Mechanics Discipline Central Soil and Materials Research Station (CSMRS), New Delhi

2 Dam Instrumentation Safety of Dam Construction First Filling Operation Refinement of Design Back Analysis

3 Status of Dam Instrumentation in India 4800 Dams under construction 200 Instrumented Dam (< 5 %) About 50 years ago, instruments were not usually specified in Water Resources ProjectProposalsandinstruments were installed only when problems were encountered during construction and operation of the project. Instrumentation is generally specified in each Project Proposal: Tala, Tehri, NJP, SSP, Indira Sagar.

4 Tala Hydroelectric Project, Bhutan 89 O 40' 89 O 40' TO THIMPHU DAM ROAD TO DAM SITE & ADIT NO. 1 C1 ADIT NO.1 C2 ADIT NO.2 ROAD TO GEDUCHU ADIT NO. 3 ROAD TO PADECHU ADIT NO. 2 KM 7.5 ROAD TO POWER HOUSE C4 ROAD TO KALIKHOLA ADIT NO. 5 C5 POWER HOUSE TAIL RACE TUNNEL ROAD TO MIRICHINGCHU ADIT NO. 4 KM 80 P.T. ROAD C3 HEAD RACE TUNNEL ADIT NO.5 MONITAR ADIT NO.3 ADIT NO.4 KM 45 TO PHUENTSHOLING

5 Layout of Head Race Tunnel Dam Complex RD 0 RD 3456 Takctchu D/s 2244m Thiyomachu D/s m U/s m Thiyomachu (101m) Padechu (268m) RD 9399 D/s m U/s m Geduchu (963m) RD D/s m U/s m AGO Reach Kalikhola (520m) Mirchingchu (320m) RD Mirchingchu D/s m U/s m RD Kalikhola Powerhouse Complex RD By Pass of HRT D/s m U/s m C1 C2 C3 C4 C5 HRT km HRT km HRT km HRT km Excavation of HRT from 11 Faces

6 PROJECT FEATURES Dam on River Wangchu Concrete Dam - 92 m height 130 m length (Located 3 km d/s of Chukha Power House) Diversion Tunnel m diameter 356 m length

7 U/S View of Dam Intake Structures Coffer Dam Diversion Tunnel

8 Dam D/S with Sluices Glacis (HPC) During Construction During Operation

9 Dam U/S & D/S during Operation

10 Instrumentation Programme at THEP Planning Technical Specifications Contractual Arrangement Calibration of Instruments Supply Installation Monitoring

11 Instrumentation Programme at THEP Accuracy of Data Analysis Documentation/Report DAS Attitude/Interest of Project Management Instrumentation Responsibility Cost of Instrumentation [3%]

12 Cost and Power Generation Cost to Completion Rs million Project Fully financed by the Govt. of India Indian Technology Instrumentation Cost Annual Generation million units Cost per unit - Rs per unit (India) - Rs per unit (Bhutan)

13 Instrumentation at Tala Project Quality Control and Instrumentation Contractual Arrangements EnCardio Rite Electronics Ltd., Lucknow Calibration of Instruments Supply Installation Monitoring Reporting of Monitoring Documentation

14 Instruments Installed in Dam S. No Name of Instrument Temperature Meter Pore Pressure Meter Joint Meter/ Crack Meter MPBX Normal Plumb Line Total No. of Instruments Proposed Installed Remarks Monitoring Monitoring Monitoring 9 7 Monitoring 2 2 Monitoring 6 Inverted Plumb Line 1 1 Monitoring Concrete Pressure Cell Vibrating Wire Strain Meter Up Lift Pressure Pipe Strong Motion Accelerograph Sets Sets 20 4 Monitoring Monitoring Monitoring Monitoring 11 Automatic Water Level Recorder 2 2 Monitoring

15 Instruments Installed in Dam Instruments Installed = 282 Nos. Instruments Working = 277 Nos. Instruments Not Working = 5 NOs.

16 U/S View of Dam, Intake Structures Coffer Dam, Diversion Tunnel TYPE: CONCRETE GRAVITY HEIGHT: 92 M NO. OF BLOCKS: 7 UNDERSLUICES: 5 OVER SPILLWAY:

17 LOCATIONS OF INSTRUMENTS IN DAM BLOCK 2

18 Concrete Placement in Tala Dam Concrete Completed- March 2006 EL EL ELEVATOR SHAFT 2500X2400 1NO. OVERFLOW SPILLWAY 1000 PARAPET EL EL EL EL EL NOS. 2 SLUICE CROSS GALLERY SPILLWAY (6500 X 13150) EL EL EL EL EL EL EL EL SUMP WELL EL EL FOUNDATION GALLERY

19 LOCATIONS OF INSTRUMENTS IN DAM BLOCK 5

20 OBSERVATION OF TEMPERATURE METERS 35 B2T2 B2T3 B5T3 B5T7 B5T C 22 0 C 15 1/3/2001 1/4/2001 5/5/ /11/01 1/1/2002 1/2/2002 7/3/2002 2/4/ /11/02 7/1/2003 9/2/2003 9/3/ /4/2003 9/5/2003 Temperature ( o C) Date

21 OBSERVATION OF TEMPERATURE METERS TEMPERATURE METER BLOCK B5T16 B5T17 B5T18 B5T19 B5T20 B5T21 B5T DATE Figure 6A: Observation of Temperature meters B5T16 to B5T22

22 OBSERVATION OF TEMPERATURE METERS New Temperature M eters Of Block B2T19 B2T20 B2T21 B2T22 B2T23 B2T24 DATE Figure 5B : Observat ion of Temperat ure Met ers B2T19 t o B2T24

23 Temperature Meters in Block B2T1 B2T2 B2T3 B2T4 B2T5 B2T6 B2T7 B2T8 B2T9 B2T10 B2T11 B2T12 B2T13 B2T19 B2T14 B2T20 B2T15 B2T21 B2T16 B2T22 B2T17 B2T23 B2T18 B2T24 B2T25 B2T26 B2T27 B2T28 B2T /01/ /04/ /05/ /12/ /01/ /03/ /04/ /01/ /02/ /03/ /04/ /01/ /02/ /04/ /05/ /09/ /10/ /12/ /01/ /02/ /04/ /05/ /06/ /08/ /09/ /11/ /12/ /01/2006 Monitoring Time (Date) Temprature (degree c)

24 Cement Content & Concrete Temperature Cement Content kg/m 3 Temperature of Mass Concrete Remarks ( ) Cracking ( ) Cracking ( ) Cracking ( ) No Cracking ( ) No Cracking ( ) No Cracking ( ) No Cracking

25 60 50 Strength of In-situ Cores with Age and Cement Content Compressive Strength, MPa Compressive Strength Testing Age Cement Content, Kg/m Testing Age, days

26 35 Compressive S trength (MPa) Cube Compressive Strength at Different Testing Age Testing Age (Days) Cement Content = 200 kg/m3 Cement Content = 190 kg/m3 Cement Content = 180 kg/m3 Cement Content = 170 kg/m3 Cement Content = 160 kg/m3 Comp. Strength = 15 MPa after 365 days Comp. Strength = 12.5 MPa after 28 days 31.46

27 Pore Pressure Meters in Block B5P1 B5P2 B5P3 B5P4 B5P5 B5P6 B5P7 B5P8 B5P9 B5P10 B5P11 B5P12 B5P13 B5P14 B5P15 B5P /03/ /04/ /11/ /09/ /02/ /03/ /11/ /01/ /02/ /04/ /09/ /10/ /01/ /02/ /06/ /12/ /11/ /10/ /04/ /11/ /02/ /03/ /05/ /06/ /08/ /09/ /10/ /12/ /01/2006 Monitoring Time (Date) Pore Pressure (kg/cm2)

28 Stress Meters in Block /01/ /04/ /12/ /02/ /04/ /01/ /02/ /04/ /06/ /07/ /08/ /10/ /12/ /01/ /03/ /05/ /09/ /11/ /01/ /05/ /04/ /6/ /09/ /10/ /12/2005 B2S1 B2S2 B2S3 B2S4 B2S5 B2S6 B2S7 B2S8 B2S9 B2S10 Monitoring Time (Date) Stress (kg/cm2)

29 Strain Meters in Dam Block 2 11/02/ /03/ /04/ /05/ /10/ /11/ /12/ /01/ /02/ /06/ /09/ /06/ /08/ /09/ /11/ /12/ /01/2006 B2SN9A B2SN9B B2SN9C B2SN9D B2SN9E B2SN9F Monitoring Time (Date) Strain (micro meter)

30 Report on Instrumentation Monitoring

31 Report on Reprt # 6 Quality Control and Instrumentation for Concrete Gravity Dam of 1020 MW Tala Hydroelectric Project in Bhutan Volume II: Instrumentation Dr. Rajbal Singh Chief Research Officer, Quality Control Engineer-In-Charge, Instrumentation Quality Control Department Tala Hydroelectric Project Authority Gedu, Bhutan October 2006

32 INDEX S. NO. CONTENTS PAGE NO. PREFACE LIST OF TABLES LIST OF FIGURES I v-vi vii-viii 1.0 INTRODUCTION DETAILS OF INSTRUMENTS INSTALLATION OF INSTRUMENTS MONITORING OF INSTRUMENTS CONCLUSIONS 17 ACKNOWLEDGEMENTS 18 REFERENCES 19 TABLES FIGURES ANNEXURES

33 CONCLUSIONS Mass concrete temperature, which was about 10 0 C at the time of placement, has risen up to C and finally settled down between C to C. Due to low ambient temperature (4 0 C) in the month of January, temperature of mass concrete dropped during 3 days from Cto5.2 0 C and increased again up to C. Cement content in mass concrete should be optimized to achieve required strength. High cement content leads to cracking in mass concrete. Temperature readings should be monitored from the time of placement of concrete. Instrument should be calibrated with placement temperature of mass concrete.

34 CONCLUSIONS contd. The pore pressure meters installed have shown pore pressures in the range of 3.2 kg/cm 2 to 4.0 kg/cm 2, in Blocks 2 and 5 respectively. Three joint meters/crack meters installed in blocks 3 and 5 at the cracks, show the increase in crack width in the order of 0.01mm to 0.11 mm. The joint meters installed between two blocks joint have shown insignificant displacement in the range of 0.01mm to 5.40mm.

35 CONCLUSIONS contd. The concrete pressure cells installed in Blocks 2 and 5 have shown pressures in the mass concrete varying from 5.5 kg/cm 2 to 4.4 kg/cm 2 which is 3.8 to 4.76 time lower than theoretically expected stresses of kg/cm 2 and kg/cm 2 based on mass concrete density of 2400 kg/cm 2 and height of blocks 84 m and m above the pressure cells, respectively. However, the pressure cells have shown increasing trend during observations. 9.2 kg/cm 2 & 12.6 kg/cm 2 from FEM The safe design parameters must be made available and may be attached with data acquisition system as alarm for further monitoring the safety of dam.

36 CONCLUSIONS contd. In general, behaviour of all instruments installed in Tala dam was in order with respect to increasing/decreasing trends in observations. A record number of 277 instruments were in working order out of 282. This was possible due to awarding a contract for supply, installation, maintenance and monitoring of instruments before commencement of dam construction.

37 Temperature Meter Instruments Installed Concrete Pressure Cell Pore Pressure Meter Joint Meter/Crack Meter Strain Meter Spider For Strain Rosettes

38 MPBX MULTI POSITION BOREHOLE EXTENSOMETER (MPBX)

39 Instruments Installed READ-OUT UNIT/ DATALOGGER

40 NORMAL & INVERTED PLUMBLINES

41 INSTRUMENTS INSTALLED Uplift pressure Meters Water Level Indicators Surveying Points or Targets

42 INSTRUMENTS INSTALLED SEISMOGRAPH GPS STRONG MOTION ACCELEROMETER SAM

43 INCLINOMETER SYSTEM CASING PROBE CONNECTING CABLE REEL INCLINOMETER DATALOGGER

44 SETTLEMENT MAGNETIC SYST EM DISC/PLATE MAGNET MAGNETIC PROBE SPIDER MAGNET

45 Thank You For your Kind Attention Please

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966 SINCE 1966 Introduction Geotechnical Systems Australia (GSA) was founded in March 1987 to design, manufacture and distribute geotechnical instrumentation for the geotechnical and mining industries. Now

More information

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT A CASE STUDY OF 1200 MW TEESTA-III HEP, SIKKIM Abstract - The Case study brings out the use of IT application in

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs Project: Sorang Hydro Electric Project - 100 MW Overview: M/s.Himachal Sorang Pvt.Ltd., Hyderabad, is developing the Run of the River Sorang Hydro Electric Project (100MW) in Kinnaur District of Himachal

More information

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1 Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...

More information

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING)

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) Bid Title : EPC Bid for Planning, detailed design& engineering, construction/manufacturing of civil, electro-mechanical, hydro- mechanical and switch

More information

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

TUG - Institute of Hydraulic Engineering and Water Resources Management 1 Large Dams Design, Construction and Performance Gerald Zenz Graz - University of Technology 1 Dam Structures & Geotechnique Design Construction / Observation Operation / Monitoring Cooperation & Transfer

More information

WELCOME CHAMERA-I DAM

WELCOME CHAMERA-I DAM WELCOME CHAMERA-I DAM HYDRO POWER A CLEAN, GREEN & SUSTAINABLE POWER LEAST GENERATION OF GREEN HOUSE GASES WATER SECURITY SPINNING RESERVE DEVELOPMENT OF REMOTE AREA OF THE COUNTRY FLOOD MODERATION INCORPORATED

More information

Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India

Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India Vishnugad Pipalkoti Hydropower Project Tehri Hydro Development Corporation Uttarakhand, India World Bank Water Week February 17, 2009 Pyush Dogra (Environmental Specialists) & Daryl Fields (Senior Water

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80

More information

NEELUM JHELUM HYDRO POWER PROJECT TECHNICAL VISIT BY A DELEGATION OF PAKISTAN ENGINEERING CONGRESS ON NOVEMBER, 2011

NEELUM JHELUM HYDRO POWER PROJECT TECHNICAL VISIT BY A DELEGATION OF PAKISTAN ENGINEERING CONGRESS ON NOVEMBER, 2011 NEELUM JHELUM HYDRO POWER PROJECT TECHNICAL VISIT BY A DELEGATION OF PAKISTAN ENGINEERING CONGRESS ON 25-27 NOVEMBER, 2011 A 15 - Members delegation of Pakistan Engineering Congress paid an extensive visit

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. June 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. June 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report June 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development &

More information

Instrumentation for measuring and monitoring geotechnical and geomechanical parameters in tunnels, caverns and underground works.

Instrumentation for measuring and monitoring geotechnical and geomechanical parameters in tunnels, caverns and underground works. TUNNEL MONITORING Instrumentation for measuring and monitoring geotechnical and geomechanical parameters in tunnels, caverns and underground works. SISGEO design and manufacture a comprehensive range of

More information

APPLICATION NOTE AN-9920 May 1999 INSTRUMENTATION FOR MONITORING CONSOLIDATION OF SOFT SOIL 1. Introduction

APPLICATION NOTE AN-9920 May 1999 INSTRUMENTATION FOR MONITORING CONSOLIDATION OF SOFT SOIL 1. Introduction APPLICATION NOTE May 1999 INSTRUMENTATION FOR MONITORING CONSOLIDATION OF SOFT SOIL 1. Introduction Considerable settlement may occur when constructing projects such as highway embankments, bridge approaches,

More information

Design of Concrete Lining for Head Race Tunnel using STAAD

Design of Concrete Lining for Head Race Tunnel using STAAD Design of Concrete Lining for Head Race Tunnel using STAAD Singh Adarsh Department of Civil Engineering, CBS Group of Institutions, Fatehpui, Jhajjar, Haryana, India Affilated to Maharishi Dayanand University,

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

Inovatívne metódy geotechnického monitoringu na stavbách v SR a v zahraničí

Inovatívne metódy geotechnického monitoringu na stavbách v SR a v zahraničí Inovatívne metódy geotechnického monitoringu na stavbách v SR a v zahraničí Arno Thut, Solexperts AG, Switzerland Vladimir Grof, Geoexperts spol. S.r.o., Slovakia 1 Minimizing Risks with Testing and Monitoring

More information

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental

More information

THE SUMMARY OF SAFETY MONITORING AND OPERATION ABOUT RCC GRAVITY DAM IN CHINA

THE SUMMARY OF SAFETY MONITORING AND OPERATION ABOUT RCC GRAVITY DAM IN CHINA COMITÊ BRASILEIRO DE BARRAGENS XXX SEMINÁRIO NACIONAL DE GRANDES BARRAGENS FOZ DO IGUAÇU - PR - 11 A 13 DE MAIO DE 2015 THE SUMMARY OF SAFETY MONITORING AND OPERATION ABOUT RCC GRAVITY DAM IN CHINA Quansheng

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

Assessment of cracks using percolation dye tests in. Rihand concrete dam, Uttar Pradesh, India

Assessment of cracks using percolation dye tests in. Rihand concrete dam, Uttar Pradesh, India www.ipublishing.co.in/jaserindex.html Copyright 2011 - Integrated Publishing Association ijasersubmissions@ipublishing.co.in Research article ISSN 2277 9442 Assessment of cracks using percolation dye tests

More information

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank. Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge

More information

ERDC/GSL TN-14-2 August 2014 Review of Instrumentation and Monitoring for USACE Levees

ERDC/GSL TN-14-2 August 2014 Review of Instrumentation and Monitoring for USACE Levees Review of Instrumentation and Monitoring for USACE Levees By Joseph B. Dunbar, Gustavo Galan-Comas, Lucas A. Walshire, Ronald E. Wahl, Donald Yule, Maureen K. Corcoran, Jose Llopis, and Amber L. Bufkin

More information

DEMONSTRATION OF ONLINE STRUCTURAL HEALTH MONITORING OF EXISTING BRIDGES

DEMONSTRATION OF ONLINE STRUCTURAL HEALTH MONITORING OF EXISTING BRIDGES December 2016 DEMONSTRATION OF ONLINE STRUCTURAL HEALTH MONITORING OF EXISTING BRIDGES 1 Introduction India is covered by a large number of rail and road bridges. They are an important component of transportation

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Progress Report January 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development & Consulting

More information

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd. Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd., Switzerland 1. Introduction The 9.4 km Zimmerberg base tunnel is an important part

More information

FE MODELING AND NUMERICAL SIMULATION FOR DYNAMIC ANALYSIS OF GRAVITY DAM SPILLWAYS

FE MODELING AND NUMERICAL SIMULATION FOR DYNAMIC ANALYSIS OF GRAVITY DAM SPILLWAYS FE MODELING AND NUMERICAL SIMULATION FOR DYNAMIC ANALYSIS OF GRAVITY DAM SPILLWAYS ABSTRACT : Akshay Adya 1 1 Graduate Student, SOE Fellow, Department of Civil & Environmental Engineering, Stanford University

More information

Guide to Geotechnical Instrumentation

Guide to Geotechnical Instrumentation Guide to Geotechnical Instrumentation Copyright 2004 Durham Geo Slope Indicator. All Rights Reserved. This equipment should be installed, maintained, and operated by technically qualified personnel. Any

More information

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng. HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the

More information

North and South Dams Project Overview

North and South Dams Project Overview North and South Dams Project Overview Construction performed by Barnard Pennecon LP Mobilized in late-2015 Anticipated Completion in mid-2019 Major Features of Our Contract Include: Diversion of Churchill

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : January,

More information

SURGE SHAFT EXCAVATION AND CONCRETE LINING WITH SLIPFORM AT PUNATSANGCHHU I HEP, MC # 3 PACKAGE, BHUTAN

SURGE SHAFT EXCAVATION AND CONCRETE LINING WITH SLIPFORM AT PUNATSANGCHHU I HEP, MC # 3 PACKAGE, BHUTAN SURGE SHAFT EXCAVATION AND CONCRETE LINING WITH SLIPFORM AT PUNATSANGCHHU I HEP, MC # 3 PACKAGE, BHUTAN 2 0 1 7 Sangameshwar D. Jeur Head of Hydro electric project HCC Ltd. Mumbai Abstract This paper discusses

More information

Systematic and Early Development of Hydro Projects in Nepal. Development of Projects in Bheri Basin A Case Study

Systematic and Early Development of Hydro Projects in Nepal. Development of Projects in Bheri Basin A Case Study Systematic and Early Development of Hydro Projects in Nepal Development of Projects in Bheri Basin A Case Study 1 RIVER MAP: ORIGIN AND ITS CONFLUENCES Tallo Bheri HEP Thuli Bheri-1HEP NEPAL Bheri-III

More information

CONSTRUCTION SPECIFICATION FOR TUNNELLING

CONSTRUCTION SPECIFICATION FOR TUNNELLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 415 FEBRUARY 1990 CONSTRUCTION SPECIFICATION FOR TUNNELLING 415.01 SCOPE 415.02 REFERENCES 415.03 DEFINITIONS TABLE OF CONTENTS 415.04 SUBMISSION AND

More information

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore Module No. # 07 Lecture No. # 22 Micropiles (Refer Slide Time: 00:30) So, we would be

More information

Determining subsidence of soil layers in the process of building soil embankment

Determining subsidence of soil layers in the process of building soil embankment Vietrock215 an ISRM specialized conference Vietrock215 12-13March 215, Hanoi, Vietnam Determining subsidence of soil layers in the process of building soil embankment Viet Ha NGUYEN a a Hanoi university

More information

BRILLIANT EXPANSION PROJECT

BRILLIANT EXPANSION PROJECT BRILLIANT EXPANSION PROJECT Utilizes power tunnel 120 MW Capacity 500 GWh Energy Transmission link to Brilliant Terminal Station Will reduce TGP downstream Intake Transmission Link Transmission Link Extent

More information

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

MIEL I Hydroelectric Power Plant

MIEL I Hydroelectric Power Plant MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers

More information

Chapter 3 METHODOLOGY ADOPTED

Chapter 3 METHODOLOGY ADOPTED Chapter 3 METHODOLOGY ADOPTED 3.1 INTRODUCTION Concrete mix design is a well established practice around the world. Adapting from developed countries, many developing countries have standardized their

More information

ARHAM VEERAYATAN INSTITUTE OF ENGINEERING, TECHNOLOGY & RESEARCH Haripar (Mota Asambia), Bhuj Mandvi road, Mandvi Tal.

ARHAM VEERAYATAN INSTITUTE OF ENGINEERING, TECHNOLOGY & RESEARCH Haripar (Mota Asambia), Bhuj Mandvi road, Mandvi Tal. ARHAM VEERAYATAN INSTITUTE OF ENGINEERING, TECHNOLOGY & RESEARCH Haripar (Mota Asambia), Bhuj Mandvi road, Mandvi Tal. Kutch (Gujarat) Date: 19/10/2016, Wednesday Duration: 1 Day A FEEDBACK REPORT ON VISIT

More information

REAL WORLD TO THE CITIES SENSORS INTERFACE SOFTWARE

REAL WORLD TO THE CITIES SENSORS INTERFACE SOFTWARE WE CONNECT REAL WORLD SMART CITIES TO THE SMART SENSORS WIRELESS INTERFACE SOFTWARE CLOUD Rev.5 del 23/10/2017 Redatto da: R&D e MKT Approvato da: CEO Smart Cities WIRELESS Interface NI200 are ultra low

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report February 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development

More information

MONITORING AND DEFORMATION ASPECTS OF LARGE CONCRETE FACE ROCKFILL DAMS

MONITORING AND DEFORMATION ASPECTS OF LARGE CONCRETE FACE ROCKFILL DAMS MONITORING AND DEFORMATION ASPECTS OF LARGE CONCRETE FACE ROCKFILL DAMS Anna SZOSTAK_CHRZANOWSKI 1, Nianwu DENG 1,3, and Michel MASSIÉRA 2 1 Canadian Centre for Geodetic Engineering, University of New

More information

PERFORMANCE OF CYLINDRICAL LIQUID STORAGE TANKS IN SILAKHOR, IRAN EARTHQUAKE OF MARCH 31, 2006

PERFORMANCE OF CYLINDRICAL LIQUID STORAGE TANKS IN SILAKHOR, IRAN EARTHQUAKE OF MARCH 31, 2006 173 PERFORMANCE OF CYLINDRICAL LIQUID STORAGE TANKS IN SILAKHOR, IRAN EARTHQUAKE OF MARCH 31, 006 Sassan Eshghi 1 and Mehran S. Razzaghi ABSTRACT Several on-ground cylindrical liquid storage tanks experienced

More information

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID TRANSIT SYSTEM Chi-Te Chang, Ming-Jung Wang, Chien-Tzen Chang, and Chieh-Wen Sun Central District Office, Department of Rapid Transit System, Taipei

More information

CURRICULUM VITAE. Born in Campina Grande, Paraiba- Brazil, on February 19, Public Profile:

CURRICULUM VITAE. Born in Campina Grande, Paraiba- Brazil, on February 19, Public Profile: CURRICULUM VITAE 1. PERSONAL DATA Name: OSCAR MACHADO BANDEIRA Born in Campina Grande, Paraiba- Brazil, on February 19, 1947. E-mail: oscarbandeira@norteenergiasa.com.br Public Profile: www.linkedin.com/in/oscarbandeiracivilengineer

More information

DAMS AND APPURTENANT HYDRAULIC STRUCTURES

DAMS AND APPURTENANT HYDRAULIC STRUCTURES rs-t DAMS AND APPURTENANT HYDRAULIC STRUCTURES LJUBOMIR TANCEV Professor, Faculty of Civil Engineering, Sts Cyril and Methodius University, Skopje, Republic of Macedonia A.A. BALKEMA PUBLISHERS LEIDEN

More information

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No ) Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides

More information

JOURNAL OF ADVANCEMENT IN ENGINEERING AND TECHNOLOGY

JOURNAL OF ADVANCEMENT IN ENGINEERING AND TECHNOLOGY Research Article JOURNAL OF ADVANCEMENT IN ENGINEERING AND TECHNOLOGY Journal homepage: http://scienceq.org/journals/jaet.php Open Access Performance of Francis Turbine and Hydro Electric Governing B.Sandhya

More information

The durability of normal strength concrete: an experimental study

The durability of normal strength concrete: an experimental study Materials Characterisation VII 195 The durability of normal strength concrete: an experimental study V. Patel & N. Shah Civil Engineering Department, Charotar University of Science and Technology, India

More information

Comparative Study on Effect of Cooling Methods on Compressive Strength of Standard And High Strength Concrete Subjected To Real Fire

Comparative Study on Effect of Cooling Methods on Compressive Strength of Standard And High Strength Concrete Subjected To Real Fire American Journal of Engineering Research (AJER) e-issn: 2320-0847 p-issn : 2320-0936 Volume-6, Issue-12, pp-167-172 www.ajer.org Research Paper Open Access Comparative Study on Effect of Cooling Methods

More information

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Structure of Presentation Outline of the Project Development Phases Key Attributes of the Project Environmental Considerations Scheme Layout

More information

Three Dimensional Seepage Analyses in Mollasadra Dam after Its Impoundments

Three Dimensional Seepage Analyses in Mollasadra Dam after Its Impoundments JASEM ISSN 1119-8362 All rights reserved Full-text Available Online at www.bioline.org.br/ja J. Appl. Sci. Environ. Manage. June, 2011 Vol. 15 (2) 241-246 Three Dimensional Seepage Analyses in Mollasadra

More information

LEA_EN_PZL Vibrating Wire Piezometer. Instruments and Systems for Geotechnical and Structural Monitoring

LEA_EN_PZL Vibrating Wire Piezometer.   Instruments and Systems for Geotechnical and Structural Monitoring LEA_EN_PZL1001000 Vibrating Wire Piezometer LEA_EN_PZL1001000 Vibrating Wire Piezometer Description _ Vibrating wire piezometers are instruments of great reliability and high strength, used for measuring

More information

PRISM TEST, FLAT JACK TEST, REBOUND HAMMER, & MECHANICAL PULSE VELOCITY

PRISM TEST, FLAT JACK TEST, REBOUND HAMMER, & MECHANICAL PULSE VELOCITY PRISM TEST, FLAT JACK TEST, REBOUND HAMMER, & MECHANICAL PULSE VELOCITY PRISM TEST(Introduction) It is a laboratory test to calculate the compressive strength of a masonry prism. The prism can be obtained

More information

Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building

Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building Thayapraba M Civil Department, NIT Trichy, (India) ABSTRACT Designers have a huge number of choices

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1 Alberta Environment Page 13-1 13.0 DROP INLET SPILLWAYS 13.1 General The drop inlet spillway is commonly used for providing flood protection for earth dams which have smaller reservoirs and/or smaller

More information

The Rio Grande project - Argentina

The Rio Grande project - Argentina The Rio Grande project - Argentina Introduction The Rio Grande pumped storage project is located on the Rio Grande river near the town of Santa Rosa de Calamucita in the Province of Cordoba in Argentina.

More information

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures Preferred QC/QA Procedures The Federal Highway Administration (FHWA) has provided QC/QA guidance for this technology as noted below. The reference document also contains information about construction

More information

ANALYSIS, DESIGN AND CONSTRUCTION OF TIE-BACK ANCHOR FOR COFFER DAM

ANALYSIS, DESIGN AND CONSTRUCTION OF TIE-BACK ANCHOR FOR COFFER DAM International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 6, November-December 2016, pp. 371 377, Article ID: IJCIET_07_06_040 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=7&itype=6

More information

AGS(HK) Seminar - Tunnelling - Selected Topics Instrumentation for Tunnelling. Practical Aspects of Tunnelling Instrumentation

AGS(HK) Seminar - Tunnelling - Selected Topics Instrumentation for Tunnelling. Practical Aspects of Tunnelling Instrumentation AGS(HK) Seminar - Tunnelling - Selected Topics Instrumentation for Tunnelling Presented by David Sein 13 June 2009 Presentation Outline Practical Aspects of Tunnelling Instrumentation Managing, Interpretation

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

ADVANCES in NATURAL and APPLIED SCIENCES

ADVANCES in NATURAL and APPLIED SCIENCES ADVANCES in NATURAL and APPLIED SCIENCES ISSN: 1995-0772 Published BYAENSI Publication EISSN: 1998-1090 http://www.aensiweb.com/anas 2017 July 11(9): pages 291-296 Open Access Journal Performance Evaluation

More information

THE STUDY OF t-z AND q-z CURVES ON BORED PILE BASED ON THE RESULTS OF INSTRUMENTED PILE LOAD TEST IN MEDIUM AND STIFF CLAYS

THE STUDY OF t-z AND q-z CURVES ON BORED PILE BASED ON THE RESULTS OF INSTRUMENTED PILE LOAD TEST IN MEDIUM AND STIFF CLAYS Proceedings of Pile 2013, June 2-4 th 2013 THE STUDY OF t-z AND q-z CURVES ON BORED PILE BASED ON THE RESULTS OF INSTRUMENTED PILE LOAD TEST IN MEDIUM AND STIFF CLAYS Aswin Lim 1, Aksan Kwanda 2 and Paulus

More information

GEOTECHNICAL CHARACTERIZATION OF MINE WASTE MATERIALS (ZINC/LEAD MINE) FROM RAJPURA DARIBA MINE, UDAIPUR ABSTRACT

GEOTECHNICAL CHARACTERIZATION OF MINE WASTE MATERIALS (ZINC/LEAD MINE) FROM RAJPURA DARIBA MINE, UDAIPUR ABSTRACT GEOTECHNICAL CHARACTERIZATION OF MINE WASTE MATERIALS (ZINC/LEAD MINE) FROM RAJPURA DARIBA MINE, UDAIPUR Noor Shahid 1, Singh Amardeep 2, Chitra R 3. & Gupta M 4. 1 Corresponding Author and Scientist C,

More information

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K)

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K) ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT Project Location State District River Vicinity Latitude Longitude Nearest Railhead; Udhapur (J&K) Hiachal Pradesh Chaba Chenab River Luj village

More information

6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, October 2012

6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, October 2012 6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, 23 25 October 2012 DESIGN AND CONSTRUCTION ADVANTAGES OF HARDFILL SYMMETRICAL DAMS - CASE STUDY: SAFSAF DAM IN EASTERN ALGERIA

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

Lessons learnt from constructing the FE tunnel incl. some monitoring results

Lessons learnt from constructing the FE tunnel incl. some monitoring results LUCOEX conference Oskarshamn, Sweden 3 rd of June 2015, Session 3 Lessons learnt from constructing the FE tunnel incl. some monitoring results Herwig R. Müller, Sven Köhler, Tobias Vogt concrete plug (5m)

More information

Abstract. Construction and commissioning

Abstract. Construction and commissioning Geo-Textile Sand Container Mattresses (GSCM) Lining for Temporary River Diversion Channels Author: Rajendra Deshpande Hindustan Construction Co. Ltd (HCC), India. Abstract HCC (Hindustan Construction Co.

More information

DIVERSION CHANNEL OF BELO MONTE HPP

DIVERSION CHANNEL OF BELO MONTE HPP DIVERSION CHANNEL OF BELO MONTE HPP INTRODUCTION The diversion channel of Belo Monte HPP is an important engineering work which required the engagement of several specialties to be able to address all

More information

FINAL LICENSE APPLICATION Exhibit C Construction History

FINAL LICENSE APPLICATION Exhibit C Construction History FINAL LICENSE APPLICATION Exhibit C Construction History Portland, Oregon April 2004 Copyright 2004 by Reproduction in whole or in part without the written consent of is prohibited. TABLE OF CONTENTS

More information

Geotechnical & Structural Instrumentation

Geotechnical & Structural Instrumentation Geotechnical & Structural Instrumentation quality uk manufacturing & technical support Who we are Geosense Ltd is one of Europe s leading manufacturers and suppliers of instrumentation to the geotechnical,

More information

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL Roger BREMEN Engineer of the Hydraulic Department Lombardi Engineering Limited Via Simen 19 CH 6648 Minusio Switzerland ABSTRACT: A 7.5 km long

More information

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM 1. PROJECT INFORMATION Intoduction: Tamakoshi V Hydroelectric Project The Tamakoshi-V Hydropower Project is a cascade development

More information

BRIHANMUMBAI MAHANAGARPALIKA

BRIHANMUMBAI MAHANAGARPALIKA BRIHANMUMBAI MAHANAGARPALIKA PROJECTS SANCTIONED UNDER JNNURM A] IV Mumbai - Middle Vaitarna Water Supply Project :- Municipal Corporation of Greater Mumbai (MCGM) has undertaken the Middle Vaitarana Water

More information

Workshop. Granada - Spain. CESI RICERCA s numerical modeling of dams affected by ASR: two case-studies. A. Frigerio, G. Mazzà

Workshop. Granada - Spain. CESI RICERCA s numerical modeling of dams affected by ASR: two case-studies. A. Frigerio, G. Mazzà Workshop Granada - Spain CESI RICERCA s numerical modeling of dams affected by ASR: two case-studies A. Frigerio, G. Mazzà 10/2007 Forward Topics of the presentation: problems related to ageing and deterioration

More information

A successful case of water cut-off by ground freezing in the excavation of the shaft DST-1

A successful case of water cut-off by ground freezing in the excavation of the shaft DST-1 A successful case of water cut-off by ground freezing in the excavation of the shaft DST-1 Roberto Bono Chief Engineer, Salini-Impregilo Healy JV, USA. Basilio Giurgola Site Engineer, Salini-Impregilo

More information

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY G.L. Sivakumar Babu 1, B. R.Srinivasa Murthy 2, D.S. N. Murthy 3, M.S. Nataraj 4 ABSTRACT Micropiles have been used effectively in many applications

More information

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction Ö. Özen, H. Küsmez, A. Akman Dam and Tunnel Projects Director, İLCİ Holding & TR COLD Member, Ankara, Turkey

More information

STUDY OF MIX DESIGN FOR HIGH PERFORMANCE CONCRETE

STUDY OF MIX DESIGN FOR HIGH PERFORMANCE CONCRETE STUDY OF MIX DESIGN FOR HIGH PERFORMANCE CONCRETE SACHIN PATIL E-mail: jay40308@rediffmail.com Abstract In present research work a thorough study and analysis of Mix Design of High Performance Concrete

More information

Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah

Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah 1 Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT Steven Bartlett, University of Utah Roadway Widening (I-15 Project) Salt Lake City Utah, USA 2002 Host of

More information

Early age behaviour of fibre reinforced shotcrete

Early age behaviour of fibre reinforced shotcrete Early age behaviour of fibre reinforced shotcrete J. Sustersic, A. Zajc, R. Ercegovic IRMA Institute for Research in Materials and Applications, Ljubljana, Slovenia V. Jovicic Institute for Mining, Geotechnology

More information

Innovation in Instrumented Test Piles in Malaysia: Application of Global Strain Extensometer (GloStrExt) Method for Bored Piles

Innovation in Instrumented Test Piles in Malaysia: Application of Global Strain Extensometer (GloStrExt) Method for Bored Piles Innovation in Instrumented Test Piles in Malaysia: Application of Global Strain Extensometer (GloStrExt) Method for Bored Piles... By: Dr H.M. Abdul Aziz bin K.M Hanifah 1 and Lee Sieng Kai 2 (GIEM) 1

More information

PERFORMANCE OF SHORING WALL IN DEEP EXCAVATION, CORNICHE TOWERS, ABU DHABI: A CASE STUDY

PERFORMANCE OF SHORING WALL IN DEEP EXCAVATION, CORNICHE TOWERS, ABU DHABI: A CASE STUDY International Journal of Advanced Research in Engineering and Technology (IJARET) Volume 9, Issue 4, July August 2018, pp. 281 292, Article ID: IJARET_09_04_029 Available online at http://www.iaeme.com/ijaret/issues.asp?jtype=ijaret&vtype=9&itype=4

More information

Dam Safety and Seismicity

Dam Safety and Seismicity Dam Safety and Seismicity January 13, 2014 Fort St. John, BC John Nunn, P.Eng, M.Sc., M.I.C.E Chief Project Engineer Tim Little, P. Eng. Topics 1. The Practice of Dam Safety in BC Hydro 2. Bennett Dam

More information

Tanahu Hydropower Limited

Tanahu Hydropower Limited Tanahu Hydropower Limited (A subsidiary company of Nepal Electricity Authority) Trade Tower Building, 4th Floor, Thapathali, Kathmandu, Website: http://www.thl.com.np NEWS LETTER - 073/074 06 February,

More information

DAMS AND OTHER HYDRAULIC STRUCTURES

DAMS AND OTHER HYDRAULIC STRUCTURES GAP.2.9.1 A Publication of Global Asset Protection Services LLC DAMS AND OTHER HYDRAULIC STRUCTURES INTRODUCTION The purpose of a dam evaluation is to review the design, construction and performance history

More information

Designing, Commissioning and Monitoring of 40% Scale Bentonite Buffer Test 14260

Designing, Commissioning and Monitoring of 40% Scale Bentonite Buffer Test 14260 Designing, Commissioning and Monitoring of 40% Scale Bentonite Buffer Test 14260 Harri Kivikoski*, Pieti Marjavaara* and Pasi Rantamäki** * VTT Technical Research Centre of Finland, Espoo, Finland ** Posiva

More information

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT General Works Guidelines for Investigation of SHP Projects Sponsor: Ministry of New and Renewable Energy Govt. of India Lead Organization: Alternate

More information

Investigation into Crack Phenomena of Unreinforced Concrete Structures for Aseismic Evaluation of Concrete Dams

Investigation into Crack Phenomena of Unreinforced Concrete Structures for Aseismic Evaluation of Concrete Dams Investigation into Crack Phenomena of Unreinforced Concrete Structures for Aseismic Evaluation of Concrete Dams by Tadahiko Sakamoto 1, Yoshikazu Yamaguchi 2, Takashi Sasaki 3, Kei Takafuji 4, Ken-ichi

More information

Section Gabions Tender No. [ ] Page The following detail drawings are appended hereto and form part of this section.

Section Gabions Tender No. [ ] Page The following detail drawings are appended hereto and form part of this section. Tender No. [ ] Page 1 1.0 GENERAL 1.1 DETAILED DRAWINGS.1 The following detail drawings are appended hereto and form part of this section. Number Title 02374.01 Gabion Basket Assembly Details 02374.02

More information

John Hart Generating Station Replacement Project. October 2017 Community Construction Update Report #52

John Hart Generating Station Replacement Project. October 2017 Community Construction Update Report #52 John Hart Generating Station Replacement Project October 2017 Community Construction Update Report #52 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone Gue See Sew G&P Professionals Sdn Bhd www.gnpgroup.com.my 20 July 2016 CONTENTS INTRODUCTION SOIL PARAMETERS

More information

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering

More information