BUILDING ASSESSMENT REPORT for NMSU GREENHOUSES at NEW MEXICO STATE UNIVERSITY LAS CRUCES, NEW MEXICO

Size: px
Start display at page:

Download "BUILDING ASSESSMENT REPORT for NMSU GREENHOUSES at NEW MEXICO STATE UNIVERSITY LAS CRUCES, NEW MEXICO"

Transcription

1 BUILDING ASSESSMENT REPORT for NMSU GREENHOUSES at NEW MEXICO STATE UNIVERSITY LAS CRUCES, NEW MEXICO July 14, 2014 Prepared By: 6501 Americas Parkway NE, Suite 550 Albuquerque, New Mexico (505) ph ~ (505) fax

2 TABLE OF CONTENTS SECTION ONE SECTION TWO SECTION THREE SECTION FOUR APPENDIX REPORT SUMMARY EXISTING CONDITIONS RECOMMENDATIONS COST ANALYSIS SITE SURVEY PHOTOGRAPHS TOC - 1

3 SECTION ONE REPORT SUMMARY Huitt-Zollars prepared this facility conditions assessment report for the two hundred and ten (210) existing greenhouses located south of the NMSU campus. The 30 acre parcel of land the greenhouses are sited on is owned by NMSU and leased to Aldershot (grower). The assessment report includes the evaluation of the exterior and interior building finishes, structural system and mechanical and electrical systems. The overall condition of the buildings was assessed to determine: 1.) The cost of upgrades and repairs. 2.) The cost to demolish the greenhouses and return the site to predevelopment conditions. 3.) The cost to dismantle, recycle steel structure and return the site to predevelopment conditions. The report will also investigate the site to determine if there are likely environmental contamination issues that may require remediation. An environmental assessment is not included in this report. Code deficiencies were also identified. Project Team: NMSU ~ Office of Facilities and Services Glen Haubold Leo Lucero Associate Vice President Project Manager Huitt-Zollars John Jarrard Joe Gallegos Project Manager Architect Page 1 of 11

4 SECTION TWO EXISTING CONDITIONS The existing greenhouse complex (GH) is located on an approximately 30.5 acre site south of the NMSU Main Campus, on land leased to the plant grower by NMSU. The complex consists of 210 units. Units are grouped in rows of 21 greenhouses per group for a total of 10 groups. The size of each unit is 24 wide x 200 long, for a total overall size of 500 x 200 per group. The units are prefabricated lightweight galvanized steel structures with sheet vinyl roofs and semi rigid plastic walls. The galvanized structure appears to be in overall good condition, with only minor rust near the footings. The footing appears to be about 12 diameter concrete piers. The floors of the GH are mostly dirt with a gravel surface. Concrete walks are located on the south side of each group for access through the units. Some of the units have concrete walkways between the plant racks, others are gravel over earth. Each group of 21 units is connected to a common central corridor. Contained in the common corridor are planting materials, potting materials, herbicide and pesticide containers, irrigation and HVAC equipment and irrigation controls. Each group is cooled by an evaporative unit on the south wall. Exhaust fans on the north side of the building draw cool air across the units. Heating is provided by several propane fired blast heaters with in each group of greenhouses. Supplemental heat is provided to the plants by a radiant heating system located above and below the plants. This report does not include a detailed assessment of the heating system, however it is likely the hot water is provided from one boiler with in the common corridor and piped to each unit in one or two zones with thermostatic controls. A motorized shading device is located above each plant rack. This device can be adjusted to provide various amounts of shade depending on the type of plant being grown. Lighting in the GH units is overhead light strings with exposed bulbs and make shift reflectors. Plants are set up on racks that run the full length of the building. The eastern half of the greenhouses has movable racks that can accommodate a greater number of pots. The western half has fixed racks. The plants are watered by a drip irrigation system that is feed from galvanized piping running below each rack. In addition to the greenhouses, the complex also houses a large warehouse and shipping building, a small hazardous material storage building and a caretaker s mobile home. Eight loading docks are located on the south side of the warehouse. Employee and visitor parking is provided on the south and east side of the complex, in unpaved areas. Page 2 of 11

5 There are some condition issues with the greenhouses. Numerous wall panels have deteriorated due to sun exposure or have been damaged by other means. The roofing membrane is sheet vinyl and has ripped or separated from the steel structure in numerous areas. Much of the plumbing in the GH buildings is rusted and / or scaled and is leaking. Some of the evaporative coolers are leaking and scaled and need servicing. The doors are sliding barn type doors and are in fair condition, but some do not latch easily or close completely. Page 3 of 11

6 SECTION THREE RECOMMENDATIONS GREENHOUSE BUILDINGS The building steel structure is sound and in overall good condition. The exterior wall panels should be replaced in most, if not all areas. The roof membrane requires replacing every year due to the UV degradation and wind damage to this very thin material. The roof membrane is held in place with galvanized steel battens that require manual removal and reinstallation. The roof membrane extends the full length on each unit from the ridge line to the gutters or one half of the roof area. The barn doors will need to be adjusted and others may need to be replaced in some areas of the GH complex. The plant racks are in overall good condition and do not require maintenance at present. The moveable racks should be lubricated and adjusted as needed. The evaporative cooling system should be thoroughly maintained, including replacement of the cooling medium, repairs of leaks and servicing of the exhaust fans. The heating system was not operational at the time of the site visit, but appears to be in good working order. The lighting does not meet code and should be replaced with appropriate industrial fixtures. Also, due to the use of chemical pesticides and other chemical products, a preliminary environmental assessment should be conducted to determine if hazardous materials are present and the extent of the contamination if found. The cost to repair or demolish the greenhouses is shown in Section Four of this report. If the University decides to relocate or reuse only a portion of the greenhouses a separate cost for this will need to be prepared depending on number of greenhouses and location(s) to be moved. It should be noted however, that if only a portion of these are reused or relocated, a new heating system may be required, pending the condition and size of the existing boiler system. WAREHOUSE / SHIPPING BUILDING The warehouse / shipping building is a pre-engineered structure that is in good condition. The building systems appear to functioning properly and appropriate for the type facility. HAZARDOUS MATERIAL STORAGE BUILDING This building houses pesticides, herbicides and other chemical products. The design team did not have access to this structure at the time of the site visit. The CMU structure appears to be in overall fair condition, however, it is recommended that an environmental assessment be conducted within and around the building to determine if hazardous materials or chemicals are present that may require remediation. SITE IMPROVEMENTS The parking areas and drives around the complex are unpaved. It is recommended that these areas be paved and drainage swales and / or ponds be constructed to retain / detain runoff. It was also noted that dead plants are dumped in a large depression on the southwest side to the warehouse building. If these plants contain harmful chemicals an environmental restoration will likely be required. As noted above, it is recommended that a preliminary environmental assessment be conducted to determine if this is required. Page 4 of 11

7 SECTION FOUR COST ANALYSIS COST TO UPGRADE / REPAIR EXISTING GREENHOUSES The following is a cost estimate to repair or replace damaged or deficient items within the complex 1. Replace Exterior Envelope at Greenhouses a. Wall Area 77,000 SF x $2.00 / SF = $154, b. Roof Area 100,000 SF x $1.50 / SF = $150, Repair / Replace Building Systems a. Maintain Evap. Coolers 210 Units x $ 800 / Unit = $168, b. Replace Lighting 210 Units x $1200 / Unit = $252, c. Replace / Repair Doors 20 Doors x $500 / Door = $ 10, Pave Parking Area / Access Roads a. 6 Acres x $25, / Acre = $150, TOTAL ESTIMATED COST OF UPGRADES $ 884, COST TO DEMOLISH GREENHOUSES & CHEMICAL STORAGE BUILDING (Warehouse to Remain) The following is a cost estimate to demolish the greenhouses and chemical storage building and to restore that portion of the site to desert conditions. Note: Costs do not include environmental remediation. 1. Demolish Greenhouse Buildings & Chemical Storage Building a. 210 Buildings x $ / Building = $252, b. Demo Chemical Building = $ 6, c. Haul and Dispose $ / Ton = $ 37, Regrade and Reseed Site a. 30 Acres x $ / Acre = $114, TOTAL ESTIMATED DEMOLITION COST $ 410, Page 5 of 11

8 COST TO DISMANTLE AND RECYCLE GREENHOUSE STRUCTURES The following is a cost estimate to dismantle and recycle steel from the greenhouses and demolish chemical storage building and to return that portion of the site to desert conditions. Dismantling costs include cutting and separating of steel from other materials as required for acceptance by recycler. Note: Costs do not include environmental remediation. 2. Dismantle Greenhouse Structures b. 210 Buildings x $ / Building = $ 462, c. Demo Chemical Building = $ 6, d. Haul $50.00 / Ton = $ 7, Recycled Value of Steel Structure a. 150 tons x $ 150 / ton = $ - 22, Regrade and Reseed Site a. 30 Acres x $ / Acre = $ 114, TOTAL ESTIMATED COST $ 567, Page 6 of 11

9 APPENDIX Page 7 of 11

10

11 TYPICAL INTERIOR W/ NO PLANTS TYPICAL EXTERIOR TYPICAL EXTERIOR VIEW AT COMMON CORRIDOR TYPICAL EXHAUST FANS TYPICAL INTERIOR W/ PLANTS Page 8 of 11

12 TYPICAL IRRIGATION SYSTEM WAREHOUSE / LOADING DOCKS COMMON CORRIDOR STORAGE CHEMICAL STORAGE BUILDING COMMON CORRIDOR LOOKING NORTH PIPING IN COMMON CORRIDOR Page 9 of 11

13 WAREHOUSE AREA MECH AREA IN COMMON CORRIDOR MECHANICAL EQUIPMENT AREA TYPICAL EVAP. COOLERS WAREHOUSE / CARETAKER HOME TYPICAL FOOTING Page 10 of 11

14 WAREHOUSE INTERIOR TYPICAL BLAST HEATER TYPICAL EVAP. COOLING SECTIONS PLANT DUMPING AREA Page 11 of 11

National Property Inspections

National Property Inspections National Property Inspections Anywhere, USA (325) 382-8754 Property Location 9375 Burt Street Anywhere USA Prepared for John Investor Consultant Al Standard (325) 382-8754 Page 1 of 27 TABLE OF CONTENTS

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072

More information

MCER Study for Little Powder K-8

MCER Study for Little Powder K-8 MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Quantity Estimated Mobilization 1 LS

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Quantity Estimated Mobilization 1 LS 010100-01 Mobilization 1 LS 010500-01 Construction Surveying 1 LS 015000-01 Temporary Construction Fence 1 LS 029100-01 Tree Retention and Protection 1 LS 015150-01 Erosion and Sediment Control 1 LS Division

More information

WILKINSON ELEMENTARY SCHOOL

WILKINSON ELEMENTARY SCHOOL INITIAL YEAR BUILT 1976 BUILDING AREA 144,900 SF CURRENT PROGRAM CAPACITY 508 ENROLLMENT 2008 451 WARD 8 PROPOSED PROGRAM CAPACITY 600 Site Plan WILKINSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Appendix J - Custom Uniformat for EDU Migration

Appendix J - Custom Uniformat for EDU Migration Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations

More information

National Property Inspections

National Property Inspections Monday, August 22, 2011 Inspector Joe Smith 548-254-3658 Page 1 of 33 GENERAL INFORMATION GENERAL CONDITIONS AT TIME OF INSPECTION : No Property Occupied : Property Faces : North South East þ West Year(s)

More information

School Assessment Report

School Assessment Report School Assessment Report School: Humphries Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:35:17 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

Stevens High School Pre Bond Presentation Claremont, NH

Stevens High School Pre Bond Presentation Claremont, NH Stevens High School Pre Bond Presentation Claremont, NH Existing Conditions Existing Conditions Existing Conditions Existing Conditions Proposed site features New main entry that is ADA accessible New

More information

School Assessment Report

School Assessment Report School Assessment Report School: KIPP Vision Report: Dec 15, 14 Condition Assessment: Suitability Assessment: Generated: 12/15/14 12:33:33 PM Final School Assessment Report - Charter Schools, KIPP Vision

More information

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT Report Clayville Elementary School October 2016 3 George Washington Highway, Clayville, RI 02815 Clayville Elementary School Summary of Findings On behalf of the School Building Authority at Rhode Island

More information

FOR ADDITIONS and REMODELS Before filling out this application, read Green Building & Green Points Guideline Booklet for more in-depth information.

FOR ADDITIONS and REMODELS Before filling out this application, read Green Building & Green Points Guideline Booklet for more in-depth information. City of Boulder Residential Building Guide Green Building & Green Application Resource Conservation Ordinance 7565 www.bouldergeenpoints.com FOR ADDITIONS and REMODELS Before filling out this application,

More information

0B MAGNOLIA HALL. Scale: 1:110. Date: Feb Time: 7:40 pm. User: brady. 10 ft

0B MAGNOLIA HALL. Scale: 1:110. Date: Feb Time: 7:40 pm. User: brady. 10 ft 0B 2 m 1:110 7:40 pm. 01 5 m 1:230 7:38 pm. 02 5 m 1:230 7:38 pm. 03 5 m 1:230 7:45 pm. Facility Profile ( FP-1 ) City: State: Country: Address: Stories: Attic: Basement: Glassboro New Jersey United States

More information

School Assessment Report

School Assessment Report School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School

More information

Lake Highlands North Recreation Center Summary

Lake Highlands North Recreation Center Summary Lake Highlands North Recreation Center Summary Address Building Purpose 9940 White Rock Trail Dallas, TX 75238 Recreation Center Original Year of Construction 1971 Building Area 33,036 SF Inspection Date

More information

Priority 1 Maintenance Projects Total Investment Needed: $54,875,317. Elementary Schools

Priority 1 Maintenance Projects Total Investment Needed: $54,875,317. Elementary Schools Priority 1 Maintenance Projects Total Investment Needed: $54,875,317 Appleton Elementary Elementary Schools Total Priority 1 Need: $1,513,280 * Replace roofing in 3 areas * Add air handling units in cafeteria,

More information

Horse Farm, Livestock Office, and Horticulture Shed Cost Evaluation Report, Revised to address comments

Horse Farm, Livestock Office, and Horticulture Shed Cost Evaluation Report, Revised to address comments November 4, 2014 Heidi Hubble Facilities and Services MSC 3545 New Mexico State University P.O. Box 30001 Las Cruces, NM 88003 Re: Horse Farm, Livestock Office, and Horticulture Shed Cost Evaluation Report,

More information

Repair methods of the roofing structures. Mon

Repair methods of the roofing structures. Mon Repair methods of the roofing structures Mon 29.02.2016 Course Content Introduction & Conservation The use of ICT for condition assessment of structures Repair of fire damage Repair methods of the roofing

More information

Mills Elementary School Site Summary

Mills Elementary School Site Summary 1 Mills Elementary School Site Summary Address 6201 Davis Lane Austin, TX 78749 Number of Permanent Campus Facilities 1 Original Year of Construction 1998 Total Campus Building Area (combined) 81,368 SF

More information

Columbia County Health Care Center Added Amenities

Columbia County Health Care Center Added Amenities Columbia County Health Care Center Added Amenities Columbia County Board Meeting on January 16th, 2013 Building Exterior Added Amenities 1. Upgraded nail-base roofing insulation to 3 thickness on Center

More information

What is NUFORM HOUSE KIT?

What is NUFORM HOUSE KIT? Introduction Nuform Building Technologies Inc. (NUFORM ) is creating a better way to deliver affordable housing the NUFORM HOUSE KIT is a solution for creating neighborhoods where people live with pride

More information

Commercial & Hobby. Greenhouses

Commercial & Hobby. Greenhouses Commercial & Hobby Greenhouses Single Source Responsibility Greenhouse Design Greenhouses Greenhouse Equipment Greenhouse Construction Page 2 To Order Call: 1-888-281-9337 Commercial Greenhouses Structures

More information

CIBL Categories of Work Classification Guidelines

CIBL Categories of Work Classification Guidelines 11 May 06 CIBL Categories of Work Classification Guidelines The following is provided as guidelines for classifying design, engineering and construction work. Project examples are provided for reference

More information

Site Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks

Site Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks Site Bldg Fiscal Yr System Sub-System Site site 2014/15 Parking Paving Site site 2014/15 Sidewalks Skill Center L 2015/16 Architectural Partitions Site Site 2015/16 Parking Striping Arc Center M 2014/15

More information

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION

More information

FREMONT UNIFIED. Thornton Middle School Conversion S C H O O L D I S T R I C T. Quattrocchi Kwok Architects. Sept 26, 2018

FREMONT UNIFIED. Thornton Middle School Conversion S C H O O L D I S T R I C T. Quattrocchi Kwok Architects. Sept 26, 2018 FREMONT UNIFIED S C H O O L D I S T R I C T Thornton Middle School Conversion Quattrocchi Kwok Architects Sept 26, 2018 1 Transforming Thornton Incoming 6 th graders in year 2021/22 Student population

More information

School Assessment Report

School Assessment Report School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment

More information

Size: length ft., bay width ft., number of bays: Square feet of floor space: Sq. ft. of bench/floor space covered by crops:

Size: length ft., bay width ft., number of bays: Square feet of floor space: Sq. ft. of bench/floor space covered by crops: Greenhouse Energy Conservation Checklist/Audit (Adapted by A.J. Both, Rutgers University, and Paul Fisher, University of Florida from a checklist developed by John W. Bartok Jr., Professor Emeritus, University

More information

PROPERTY SUMMARY Noakes St, Commerce, CA 90023

PROPERTY SUMMARY Noakes St, Commerce, CA 90023 4000 Noakes St, Commerce, CA 90023 PROPERTY SUMMARY Anthony Dedeaux Senior Associate anthonyd@raginc.com 545 South Figueroa Street, 12th Floor, Los Angeles, California 90071 (213) 892-8881 FAX: (213) 627-6526

More information

Inspection Report. Prepared for: Yossi Berg. Property Address: 4925 Diggers Way Sugar Hill, GA. Date: July 20, 2011

Inspection Report. Prepared for: Yossi Berg. Property Address: 4925 Diggers Way Sugar Hill, GA. Date: July 20, 2011 Inspection Report Prepared for: Yossi Berg Property Address: Sugar Hill, GA. Date: July 20, 2011 Inspector: Charles Mann (770) 594-2222 www.edificeinspections.com Page 1 INSPECTION CONDITIONS CLIENT &

More information

Facility Assessment Report, Montgomery Independent School District

Facility Assessment Report, Montgomery Independent School District NATATORIUM CAMPUS DATA NATATORIUM 22628 Hwy 105 West, Montgomery TX 77356 Year Built 2009 Approx. Total Square Footage Grades Served 30,420 n/a Current Enrollment n/a Building Levels 1 1 MASTER PLAN 2

More information

LEWIS ELEMENTARY SCHOOL

LEWIS ELEMENTARY SCHOOL INITIAL YEAR BUILT 1962 BUILDING AREA 49,500 SF CURRENT PROGRAM CAPACITY 550 ENROLLMENT 2008 288 WARD 1 PROPOSED PROGRAM CAPACITY 450 Site Plan LEWIS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Uniform Construction Code

Uniform Construction Code Uniform Construction Code When the UCC Requires Permits and Inspections (A Zoning Certificate may be required even though the project does not require a UCC Building Permit.) As a general rule, the UCC

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

KEARNEY REGIONAL AIRPORT NEW HANGAR KEARNEY, NEBRASKA 1238

KEARNEY REGIONAL AIRPORT NEW HANGAR KEARNEY, NEBRASKA 1238 ADDENDUM # KEARNEY REGIONAL AIRPORT NEW HANGAR KEARNEY, NEBRASKA Wilkins Hinrichs Stober Architects, L.L.C. Date Issued: March, 0 908 West 9 th Street, Suite A Kearney, Nebraska 88 Bid Date: April, 0 08--8

More information

A UCC Building permit is not required for the exceptions listed below for COMMERCIAL application: (403.42): Building construction for the following:

A UCC Building permit is not required for the exceptions listed below for COMMERCIAL application: (403.42): Building construction for the following: New buildings or renovations to existing buildings for which an application for a permit was made to the Department or a municipality before April 9, 2004. New buildings or renovations to existing buildings

More information

APPENDIX 3C DOMINION HOTEL SPECIFICATIONS

APPENDIX 3C DOMINION HOTEL SPECIFICATIONS APPENDIX 3C DOMINION HOTEL SPECIFICATIONS 1. GENERAL 1.1 Refer to Section 2.1 of Schedule 3 [Design and Construction Specifications] regarding compliance with Schedule 3 and this Building Specification.

More information

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017 Chenango Bridge Elementary School Phase 1 Asphalt Pavement Reconstruction Reconstruct asphalt parking located on west side of building including access drive. Sidewalk Replacement Replace cracked sections

More information

School Assessment Report

School Assessment Report School Assessment Report School: Morningside Elementary School Report: Dec 15, 2014 Condition Assessment: Suitability Assessment: Generated: 12/15/2014 12:11:31 PM FOR OFFICIAL USE ONLY Final School Assessment

More information

Choosing a Greenhouse. Prof. Emeritus William Roberts Former Director, Center for Controlled Environment Agriculture (CCEA) Rutgers University

Choosing a Greenhouse. Prof. Emeritus William Roberts Former Director, Center for Controlled Environment Agriculture (CCEA) Rutgers University Choosing a Greenhouse Prof. Emeritus William Roberts Former Director, Center for Controlled Environment Agriculture (CCEA) Rutgers University Greenhouse Crop Production and Engineering Design Short Course

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

186 TH AIR REFUELING WING KEY FIELD, MERIDIAN, MS ADDENDUM #1 PERFORMANCE WORK STATEMENT

186 TH AIR REFUELING WING KEY FIELD, MERIDIAN, MS ADDENDUM #1 PERFORMANCE WORK STATEMENT 186 TH AIR REFUELING WING KEY FIELD, MERIDIAN, MS PROJECT NUMBER MDVL092051 Renovate Vehicle Maintenance Facility Bldg 200 23 June 2017 ADDENDUM #1 PERFORMANCE WORK STATEMENT 1.0 SCOPE. This addendum to

More information

Property Condition Assessment. Summary Report

Property Condition Assessment. Summary Report www.real-estate-inspections.com Property Condition Assessment Summary Report Subject Property Prepared for: Client in Detroit File Number: 05-15-005 Inspector: Craig Milliken, PE CPM Real Estate Inspections,

More information

Timberglen Recreation Center Summary

Timberglen Recreation Center Summary Timberglen Recreation Center Summary Address Building Purpose 3810 Timberglen Road Dallas, TX 75287 Recreation Center Original Year of Construction 2003 Building Area 15,000 SF Inspection Date August 2,

More information

ROOF INSPECTION AND ANALYSIS PROCEDURE QUINLAN ASSOCIATES, LLC. 166 SHORE DRIVE BURR RIDGE, ILLINOIS

ROOF INSPECTION AND ANALYSIS PROCEDURE QUINLAN ASSOCIATES, LLC. 166 SHORE DRIVE BURR RIDGE, ILLINOIS ROOF INSPECTION AND ANALYSIS PROCEDURE QUINLAN ASSOCIATES, LLC. INSPECTION AND ANALYSIS PROCEDURE CONDUCTED ON: QUINLAN ASSOCIATES, LLC. INSPECTION CONDUCTED FOR: MS. CHERYL QUINLAN QUINLAN ASSOCIATES,

More information

HUGHES STADIUM CONTROLLED MAINTENANCE THROUGH 2020 Description of Projects on Facilities Management List September 18, 2014

HUGHES STADIUM CONTROLLED MAINTENANCE THROUGH 2020 Description of Projects on Facilities Management List September 18, 2014 HUGHES STADIUM CONTROLLED MAINTENANCE THROUGH 2020 Description of Projects on Facilities Management List September 18, 2014 1. Upgrade Video Security and Surveillance Systems - Replace with New a. Existing

More information

2018 FRENGER FOOD COURT ROOFING PROJECT

2018 FRENGER FOOD COURT ROOFING PROJECT For: Facilities and Services, NMSU Main Campus, New Mexico State University, Las Cruces, NM : 01/XX/2018 - ISSUED FOR RFP #: CONSULTANTS: ARCHITECT: WILLIAMS AVE. FRENGER FOOD CRT. McFIE CIRCLE PROJECT

More information

Appendix A. Stormwater Pollutant Sources/Source Controls Checklist

Appendix A. Stormwater Pollutant Sources/Source Controls Checklist Appendix A. Stormwater Pollutant Sources/Source Controls Checklist How to use this worksheet (also see instructions on page -6 of the Stormwater Technical Guide):. Review Column and identify which of these

More information

Yardmen Arena Expansion & Renovation Project Update

Yardmen Arena Expansion & Renovation Project Update For Immediate Release 25, September,2017 Yardmen Arena Expansion & Renovation Project Update BELLEVILLE ON With 33 days until puck drop of the home opening game of the American Hockey League s Belleville

More information

SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA EDWARD TUCKER ARCHITECTS, INC.

SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA EDWARD TUCKER ARCHITECTS, INC. SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA WHAT DOES IT MEAN TO BE GREEN? Sustainable of, or relating to, or being a method of harvesting or using a resource so that the resource is not depleted

More information

2 Main Building BLDG-959A Building Purpose Building Area Bus Terminal 14,890 SF Inspection Date August 18, 2016 Inspection Conditions Facility Conditi

2 Main Building BLDG-959A Building Purpose Building Area Bus Terminal 14,890 SF Inspection Date August 18, 2016 Inspection Conditions Facility Conditi 1 Site Summary Address 7105 Berkman Drive Austin, TX 78752 Number of Permanent Campus Facilities 1 Original Year of Construction 1995 Total Campus Building Area (combined) 14,890 SF Introduction is located

More information

COUNTY OF NEVADA BUILDING DEPARTMENT POLICIES

COUNTY OF NEVADA BUILDING DEPARTMENT POLICIES COUNTY OF NEVADA BUILDING DEPARTMENT POLICIES Original Policy: March, 2006 Revised: January 30, 2007 Policy Number: BD-CSC-07-004 Over-The-Counter Permits (Mechanical, Plumbing, Building and Electrical)

More information

Edmonton Public School District No. 7

Edmonton Public School District No. 7 EXECUTIVE SUMMARY 1. Overall Impressions The 1966 non-core school has actively pursued an ongoing maintenance and upgrade program to improve a number of past problem areas within the school. Extensive

More information

43. CONSERVATORY. Conservatory. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle

43. CONSERVATORY. Conservatory. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle Classification: Cluster: Location: Total Area: No. of Stories Acreage Owned: Acquired: 1904 Most Recent Improvements: THE CONSERVATORY Conservatory Close to junction of Inselrhue and Loiter Way, Belle

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

HEAVY STEEL CONSTRUCTION

HEAVY STEEL CONSTRUCTION HEAVY STEEL CONSTRUCTION PRE-ENGINEERED PRE ENGINEERED STEEL BUILDINGS Prismatic Constructions Work Shops, Storage Buildings etc. Figure 1 Figure 2 Prismatic steel constructions can be manufactured as

More information

TERMINAL BUILDING EVALUATION

TERMINAL BUILDING EVALUATION TERMINAL BUILDING EVALUATION 1.0 INTRODUCTION This report evaluates the existing Terminal Building at Frederick Municipal Airport (FDK) to determine the suitability of the building for continued use as

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

Deficiency ID Qty UoM Priority. Concrete Walks Are Damaged And Require Replacement ,000 SF 3

Deficiency ID Qty UoM Priority. Concrete Walks Are Damaged And Require Replacement ,000 SF 3 School and Site Level Deficiencies Site Concrete Walks Are Damaged And Require Replacement 5539 4,000 SF 3 Bus drop-off area does not have a canopy. 14005 250 LF 5 Paved Play Requires Recoating And Resurfacing

More information

NYC Department of Education

NYC Department of Education NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S. 81 ANNEX (OLD 75) - QUEENS, 511 SENECA AVENUE, New York, 11385 Inspection Id Inspection Type Time In

More information

G R E E N H O U S E D E S I G N M A N U F A C T U R I N G FEATURED GREENHOUSE PACKAGES

G R E E N H O U S E D E S I G N M A N U F A C T U R I N G FEATURED GREENHOUSE PACKAGES S t u ppy, Inc. G R E E N H O U S E D E S I G N M A N U F A C T U R I N G FEATURED GREENHOUSE PACKAGES STUPPY, INC. BRINGING STRUCTURE TO A NATURAL WORLD S t u p p y, I n c. G r e e n h o u s e d e s i

More information

RAYMOND EDUCATION CAMPUS

RAYMOND EDUCATION CAMPUS INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

3 CUMULATIVE METHODS AND PROJECTS

3 CUMULATIVE METHODS AND PROJECTS 3 CUMULATIVE METHODS AND PROJECTS 3.1 INTRODUCTION This chapter is an introduction to the cumulative impacts analysis contained within each respective environmental impact category subsection of Chapter

More information

Deficiency ID Qty UoM Priority. K Play Area Requires Impact Resistant Material Ea. 2

Deficiency ID Qty UoM Priority. K Play Area Requires Impact Resistant Material Ea. 2 School and Site Level Deficiencies Site K Play Area Requires Impact Resistant Material 1320 1 Ea. 2 Exterior Basketball Goals Are Damaged And Require Replacement 1322 1 Ea. 4 Bus drop-off area does not

More information

FACILITY COMPONENTS - MIDDLE SCHOOL

FACILITY COMPONENTS - MIDDLE SCHOOL SITE AREAS Parking and Access - Buses 2.0 2.0 0.30 Parking and Access - Serv. / Delivery 3.0 1.0 0.22 Parking and Access - Staff 4.0 3.0 0.89 Parking and Access - Visitors 1.0 3.0 0.22 Four fewer stalls

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 X DATE: March 27-29, 2018 ****************************************************************************** SUBJECT USD North Commons Renovation

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Spy Hill Complex - Southern Alberta Forensic Psychiatry Centre B6238B Calgary Report run on: March 28, 214 2:36 PM Building Name: Address: Location: Building Id: Gross

More information

School Without Walls

School Without Walls INITIAL YEAR BUILT 1938 BUILDING AREA 59,400 SF CURRENT PROGRAM CAPACITY 304 ENROLLMENT 2008 276 WARD 1 PROPOSED PROGRAM CAPACITY 400 SCHOOL WITHOUT WALLS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

1. Before selective demolition, Owner will remove the following items:

1. Before selective demolition, Owner will remove the following items: SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected

More information

EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN. Category #1: Work that must be done to cure dangerous and hazardous conditions

EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN. Category #1: Work that must be done to cure dangerous and hazardous conditions EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN Category #1: Work that must be done to cure dangerous and hazardous conditions identified by the City. This work must begin immediately upon receiving

More information

SUMMARY 792 Youngfield Ct., Lakewood CO Frank Oz January 13, 2018

SUMMARY 792 Youngfield Ct., Lakewood CO Frank Oz January 13, 2018 SUMMARY 792 Youngfield Ct., Lakewood CO 80228 Frank Oz January 13, 2018 Christopher Grabbe internachi Certified Professional Inspector FirePower Inspections 7204645889 info@firepowerinspections.com 2.1.1

More information

Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home

Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home Designed and built by New Mexico landscape architect John Mosely for his own Santa Fe home. The solar greenhouse shown

More information

55 Bishop Long Log Cabin Planning Zone 3

55 Bishop Long Log Cabin Planning Zone 3 55 Bishop Long Log Cabin Planning Zone 3 9385 Pardee Road Visit Date: September 2016 St. Louis County Parks Master Plan Page 1 Description: The Bishop Long Log Cabin site is 2.19 acres of woodlands with

More information

TRIAD ENGINEERING CONSULTANTS, INC.

TRIAD ENGINEERING CONSULTANTS, INC. TRIAD ENGINEERING CONSULTANTS, INC. 2638 Willard Dairy Rd Providing High Point, NC Suite 100 Plumbing, Mechanical and 27265 (336) 454-0225 Electrical Engineering Services Since 1984 admin@triadengmep.com

More information

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project: RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Two stalls fewer than minimum standard. Parking and Access - Service / Delivery 2.0 1.0 0.16 Parking and Access - Staff 1.0 3.0 0.24 Thirty-seven stalls

More information

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28- 1 Metz Elementary School Site Summary Address 84 Robert Martinez Jr. Austin, TX 78702 Number of Permanent Campus Facilities 1 Original Year of Construction 1993 Total Campus Building Area (combined) 61,905

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: P.S.372 ANNEX - K, 215 FIRST STREET, New York, 11215 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2018-03-06

More information

CITY OF NOVI. Police Department

CITY OF NOVI. Police Department CITY OF NOVI Police Department Indoor Gun Range and Training Facility Assessment Analysis with Master Plan for Novi Police Department at Community Build Out Field Services Complex Facility Needs Master

More information

PROPERTY OVERVIEW PROPERTY HIGHLIGHTS. 2,340 SF Convenience Store. 3,508 SF Three Unit Strip Center. U-Haul Business. Sunoco Branded Gas Station

PROPERTY OVERVIEW PROPERTY HIGHLIGHTS. 2,340 SF Convenience Store. 3,508 SF Three Unit Strip Center. U-Haul Business. Sunoco Branded Gas Station RETAIL FOR SALE 5990 Asheville Highway, Hendersonville, NC 28791 OFFERING SUMMARY SALE PRICE: $1,350,000 LOT SIZE: 0.75 Acres YEAR BUILT: 1980 BUILDING SIZE: 5,848 SF RENOVATED: 2018 C-2 Commercial ZONING:

More information

FACILITY COMPONENTS - ELEMENTARY SCHOOL

FACILITY COMPONENTS - ELEMENTARY SCHOOL SITE AREAS Parking and Access - Buses 1.0 2.0 0.16 Five fewer bus stalls than minimum standard. Parking and Access - Service / Delivery 1.0 1.0 0.08 No delivery parking adjacent to delivery entrance. Parking

More information

10 tips from your Architect

10 tips from your Architect 10 tips from your Architect Within the context of the national week of Energy Efficiency, in collaboration with the Energy Efficiency Management Office, the Mauritius Association of Architects offers you

More information

STUART-HOBSON MIDDLE SCHOOL

STUART-HOBSON MIDDLE SCHOOL INITIAL YEAR BUILT 1927 BUILDING AREA 105,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 399 WARD 6 PROPOSED PROGRAM CAPACITY 450 Site Plan STUART-HOBSON - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

CEFPI Monthly Meeting

CEFPI Monthly Meeting CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type

More information

Introduction to Integrated Sustainable Design

Introduction to Integrated Sustainable Design Introduction to Integrated Sustainable Design Prepared by Ar.Joshima V.M. Reference: Beyond Interior Design; ASID publications. Building Design Because of the complexities of different building components

More information

RESIDENTIAL PROJECT INFORMATION

RESIDENTIAL PROJECT INFORMATION Community Development Building and Inspection Services 2100 Ridge Avenue Evanston, Illinois 60201-2798 T 847.448.4311 FAX 847.448.8020 www.cityofevanston.org RESIDENTIAL PROJECT INFORMATION The Community

More information

PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT

PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT Prepared for: GATTER ARCHITECTS 111 MAIN ST. PHILMONT, NY 12565 Prepared by: TACONIC ENGINEERING, DPC PO BOX 272 CHATHAM, NY 12037 TACONIC

More information

For Sale/For Lease Refrigerated Warehouse 4602 Domain Drive Menomonie, WI 54751

For Sale/For Lease Refrigerated Warehouse 4602 Domain Drive Menomonie, WI 54751 4602 Domain Drive Menomonie, WI 54751 Beautifully-maintained building formally used for beverage distribution Building fully outfitted with refrigeration systems Part of Menomonie s well-known industrial

More information

For Sale by Owner Chicago Ave., Riverside, Calif. Contact: Mark Brinkman Phone:

For Sale by Owner Chicago Ave., Riverside, Calif. Contact: Mark Brinkman Phone: For Sale by Owner 1717 Chicago Ave., Riverside, Calif. 36,000 SF of Offices and High Quality work areas plus 3,500 SF covered bldg services and loading dock and 500 SF covered employee entrance patio.

More information

COLUMN SPACING TRUCK ACCESS/DOORS EAVE HEIGHT UTILITIES PARKING & DRIVES

COLUMN SPACING TRUCK ACCESS/DOORS EAVE HEIGHT UTILITIES PARKING & DRIVES LOCATION & ACCESS Akron Business Centre I and II 4.2 acre site at Opportunity Parkway (Wooster Avenue) & Pier Drive Located in Downtown Akron Adjacent to Innerbelt Expressway (Route 59) and just north

More information

ROOF OWNER'S OPERATION AND MAINTENANCE MANUAL

ROOF OWNER'S OPERATION AND MAINTENANCE MANUAL ROOF OWNER'S OPERATION AND MAINTENANCE MANUAL Table of Contents Section Title Page Section 1.0 General Maintenance Statement 2 Section 2.0 Safety 2 Section 3.0 Inspections 2-4 Section 4.0 Repairs 4 Section

More information

This section applies to service areas and loading docks for new construction and major renovations.

This section applies to service areas and loading docks for new construction and major renovations. Basis of Design This section applies to service areas and loading docks for new construction and major renovations. Programming Minimum requirements: Defined custodial area, service area and loading docks

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

NYC Department of Education

NYC Department of Education Asset: Building Assessment Survey 2017-2018 PRE-K CENTER @ 132-10 JAMAICA AVENUE - QUEENS, 132-10 JAMAICA AVENUE, New York, 11418 Inspection Id Inspection Type Time In Last Edited SA : Architectural -

More information

Thesis Proposal for Berks Classroom and Lab Building

Thesis Proposal for Berks Classroom and Lab Building Thesis Proposal for Berks Classroom and Lab Building Berks Classroom and Lab Building Berks Campus Reading, PA Authored by Julia Broskey Mechanical Option Prepared for Dr. William P. Bahnfleth PE 11 January

More information