REPORT TO US. DEPARTMENT OF THE INTERIOR AND STATE OF IDAHO FAILURE OF TETON DAM INDEPENDENT PANEL TO REVIEW CAUSE OF TETON DAM FAILURE DECEMBER 1976
|
|
- Cecil Rice
- 6 years ago
- Views:
Transcription
1 REPORT TO US. DEPARTMENT OF THE INTERIOR AND STATE OF IDAHO ON FAILURE OF TETON DAM BY INDEPENDENT PANEL TO REVIEW CAUSE OF TETON DAM FAILURE DECEMBER 1976
2 SUMMARY AND CONCLUSIONS The Independent Panel to Review Cause of Teton Dam Failure has completed its task, as charged by the Secretary of the United States Department of the Interior and the Governor of the State of Idaho in letters from Secretary Kleppe, dated June 11, 23, and 30, The Panel submits its report herewith. These pages present a summary and conclusions. Teton Dam failed on June 5, 1976, when the reservoir was at El , 3.3 ft below the spillway sill. Although downstream warnings are believed to have been timely, deaths of 14 persons and property damage estimated variously from 400 million to one billion dollars have been attributed to the failure. Construction of Teton Dam was authorized on September 7, 1964, by Public Law The dam is situated on the Teton River, three miles northeast of Newdale, Idaho. Prior to 1963, the proposed dam was known as Fremont Dam. Teton Dam and its reservoir were principal features of the Teton Basin Project, a multipurpose project embodying flood control, power generation, and supplemental irrigation water supply. The S dam was a central-core zoned earthfill structure, with a height of 305 ft above the riverbed and 405 ft above the lowest point in the foundation. Provisions for seepage control included a key trench in the foundation rock above El and a cutoff trench to foundation rock below that elevation. A grout curtain extended below these trenches. investigations of site possibilities for a dam on the Teton River commenced as early as 1904 and continued at various times until bids for construction of Teton Dam were invited on July 22, A construction contract was awarded on December 13, The embankment was topped out November 26, Filling of the reservoir commenced October 3, 1975, and continued until the failure on June 5, The Panel's approach to its assignment has been to: (1) obtain, analyze and evaluate all relevant information which could be obtained in document form from the United States^Bureau of Reclamation, the United States Geological Survey, the c / -, / (- / construction contractor, and any other available and knowledgeable source regarding the regional and ** site geology, pre-siting investigations, siting decisions, pre-design investigations, design, contract specifications and drawings; construction practices, progress and inspections; in-progress changes, it any; pre-failure operation; mechanism of failure, including sworn eyewitness accounts; and actions of respective authorities during and immediately following failure; (2) supplement the documentary information by such further inquiry, including public hearings, as became necessary; (3) make (a) detailed studies of the post-failure condition of the dam, its auxiliary structures and its foundation, by inspection, dissection and subsurface drilling; (b) special tests on foundation materials; (c) detailed geologic maps and joint surveys; (d) tests of remnant materials; (e) detailed stress analyses; (0 studies of photographs for comparison of post-failure conditions with pre-construction and construction conditions; (g) measurements of post-failure geodetic positions of surface and subsurface points, as determined before failure and before filling of the reservoir; (4) contract with various organizations for special studies required by the Panel;
3 (5) evaluate relevant data in order to sort out those of greatest significance in determining cause; (6) complete a report of the results of the foregoing activities prior to January 1,1977. Hie approach was initiated by telegrams, dated June 11 and June 14, 1976, to the Director, Engineering and Construction, U.S. Bureau of Reclamation, Denver, and by setting the Panel's first working session and its inspection of conditions at the site for the week of June 28-July 2, The telegrams requested information concerning (l)site geology in plan and sections with any test results on foundation materials; (2) site exploration with detail of drill logs, exploration trenches, borrow materials and tests; (3) grout records in detail showing non-average takes by location and depths, the patterns used and records of any interconnections; (4) foundation preparation showing both before and after conditions; (5) design memoranda for embankment, spillway, diversion structures and outlets; (6) basic drawings and technical specifications; (7) any outside report regarding the site or designs; (8) construction history of borrow pits, material preparation placement, progress, inspection, in-place tests; (9) seepage measurements or observations; (10) eyewitness accounts on progress of failure; (11) hydrology of the site; (12) seismicity of the site; (13) drain designs and drainage observations; (14) post-failure changes in spillway or auxiliary outlet structures; (15) any changes in precise level or horizontal control survey points; (16) changes in topography up and downstream; (17) photos of the foundation as approved at the start of embankment placement, particularly in the key trench and the cutoff trench; (18) record of any seeps or springs in the cutoff and core contact area; and (19) records of cofferdam seepage and pumpage from the foundation area. Prior to the Panel's convening for its first session, the Department of the Interior had recorded sworn testimony of 37 eyewitness observers of pre-failure and during-failure conditions, of whom 14 were Bureau of Reclamation staff and employees, 13 were employees of the construction contractor, and 10 were from the general public. In parallel with these eyewitness accounts, there became available several excellent photographic sequences in still and later in motion picture form. In order to supplement these eyewitness accounts with any available observations of failure-related, but pre-failure conditions, a public call was issued, and two public hearings were held in Idaho Falls on July 21, During its first working session, the need for professional staff and technical and administrative support was recognized. To fill this need, the services of Robert B. Jansen, as Executive Director, were secured through the cooperation of the Governors of Idaho and California. Also, the services of Clifford Cortright, Staff Engineer, and Larry James, Staff Geologist, and Frank Sherman, also a staff geologist, were secured within a few days of Mr. Jansen's appointment. Through the excellent cooperation of the Office of the Secretary, Department of the Interior, supporting properties, services, technicians and administrative assistance have been made available to the Panel through various bureaus of the Department. Because of the importance of determining existing embankment and foundation conditions, the Panel early addressed the Director, Design and Construction, USBR, Denver, requesting specific work on the right abutment to permit detailed examination of the remnant there, and excavation to uncover both the auxiliary outlet tunnel for internal inspection and the site of the large, lower spring observed early on June 5, Response was prompt, and on July 16, 1976, the Bureau of Reclamation awarded its Contract No. DC-7232 to Gibbons and Reed, Salt Lake City, to cover the required work. Actual dissection of the right remnant of the dam started July 26, This excavation proceeded expeditiously, in five-foot vertical increments, to El. 5200, with trenching in each incremental level to allow taking of samples as VI
4 well as inspection of the core remnant for any evidence of water channeling, or cracking, and of the manner in which the key trench was excavated, sealed, filled and compacted. The Bureau's response to the Panel's request for records, data and descriptions was also prompt. A large volume of information was furnished. Many of these records have been supplemented by others furnished to the Panel's staff at the site in response to oral and written requests. Further information was sought on the manner in which the grout curtains were closed and in which the core was built into the key trench. This information was desired both from the Bureau of Reclamation as designers and construction engineers of the dam, and of the contractor, who implemented that construction. Accordingly, a questionnaire was directed concurrently to the Director, Design and Construction, USBR, and to the Chief Executive Office of Morrison-Knudsen, as the sponsoring member of the constructing contractor, Morrison-Knudsen-Kiewit. The USBR response was quite complete. The contractor's response is in two parts. One is from the prime contractor per se, and the other is from the grouting sub-contractor, McCabe Bros., Inc. The prime contractor's answer was rather general. Staff investigations started immediately upon appointment of the various staff members. Their efforts have been interested, diligent, competent, and tireless. They have greatly expedited the completion of the Panel's task and the compilation of its report. The Panel met in Denver on June 28 and 29 to organize and initiate its inquiry through information presentations by the Bureau of Reclamation. A site inspection was made on June 30. Information meetings were held with the Bureau engineers at the site during the following day. Working sessions were continued in Denver on July 2. The Panel met again in working session in Idaho Falls August 3 through 5, again October 5 through 7, November 1 through 3, and December 7 through 10. Between its working sessions, individual Panel members worked with the staff, and independently on assignments from the Panel. Frequent individual visits were made to the site exploratory work. Careful study was made of all eyewitness accounts of their observations prior to the breach. All available photographs of the failure events were studied and arranged in chronologic sequence. All available relevant documentary records have been reviewed for significant content. Continuous professional examination was conducted of all trenching in the right abutment embankment remnant. Detailed mapping of the bedrock joints and fractures in and adjacent to the right abutment key trench was conducted between Stas and Laboratory testing of undisturbed samples of Zone 1 (core) material was carried out. Subsurface water loss tests were conducted at many locations near the centerline right abutment grout curtain. Surface ponding tests were conducted at the key trench invert at prominent joints crossing the invert. Hydraulic fracturing tests were made in drill holes in the left abutment core remnant. Analytic studies were made to assess the stress conditions on sections of the embankment and key trench in the zone of failure. * The Panel's conclusions are summarized below: 1. The records show that the pre-design site selection and geological studies were appropriate and extensive. The pilot grouting program carried out in 1969 forecast the difficulties to be experienced in construction of the final grout curtain. 2. The design followed USBR practices, developed over a period of many years from experience I with other Bureau projects, but without sufficient consideration of the effects of differing and > unusually difficult geological conditions at the Teton Damsite. Every embankment can be said to > vii *
5 have its own personality requiring individual design consideration and construction treatment. Treatment of such individualities produces most of the continuing advances in dam design and construction technology. 3. The volcanic rocks at the Teton Damsite are highly permeable and moderately to intensely jointed. Water was therefore free to move with almost equal ease in most directions, except locally where the joints had been effectively grouted. Thus during reservoir filling, water was able to move rapidly to the foundation of the dam. Open joints existed in the upstream and downstream faces of the right abutment key trench, providing potential conduits for ingress or egress of water. 4. The wind-deposited nonplastic to slightly plastic clayey silts used for the core and key trench fill are highly erodible. The Panel considers that the use of this material adjacent to the heavily jointed rock of the abutment was a major factor contributing to the failure. 5. Construction of the project was carried out by competent contractors under formal contracts administered in accord with well-accepted practices. Controversy between the contractors and Bureau of Reclamation officials which might have affected the quality of the work seems not to have occurred. Construction activities conformed to the actual design in all significant aspects except scheduling. 6. One construction condition which affected the Bureau's ability to control the rate of filling of the reservoir was the delay that occurred in completion of the river outlet works. However, the Panel believes that the conditions which caused the piping and consequent failure of the dam were not materially affected by the fact that the reservoir was filled at a more rapid rate than had been originally planned. A slower rate of filling would have delayed the failure but, in the judgment of the Panel, a similar failure would have occurred at some later date. 7. The records show that great effort was devoted to constructing a grout curtain of high quality, and the Panel considers that the resulting curtain was not inferior to many that have been considered acceptable on other projects. Nevertheless, the Panel's on-site tests and other field investigations showed that the rock immediately under the grout cap, at least in the vicinity of Stas to 15+00, was not adequately sealed, and that additional unsealed openings may have existed at depth in the same locality. The leakage beneath the grout cap was capable of initiating piping in the key trench fill, leading to the formation of an erosion tunnel across the base of the fill. The Panel considers that too much was expected of the grout curtain, and that the design should have provided measures to render the inevitable leakage harmless. 8. The geometry of the key trenches, with their steep sides, was influential in causing transverse arching that reduced the stresses in the fill near the base of the trenches and favored the development ot cracks that would open channels through the erodible fill. Arching in the longitudinal direction, due to irregularities in the base of the key trenches, and arching adjacent to minor irregularities and overhangs, undoubtedly added to the reduction of stress. 9. Stress calculations by the finite element method indicated that, at the base of the key trench near Stas and 15+00, the arching was great enough that the water pressure could have exceeded the sum of the lateral stresses in the impervious fill and the tensile strength of the fill material. Tims, cracking by hydraulic fracturing was a theoretical possibility and may have led to flow of water in the base of the key trench between Stas and 15+00, and erosion of the key trench fill. Vlll
6 10. Close examination of the interior of the auxiliary outlet tunnel showed no distress of any kind such as would be expected had the right abutment, through which the tunnel passes, been subjected to significant settlement or other structural change. Geodetic resurveys showed only minor surface movements as a result of reservoir filling and emptying. Accordingly, differential movements of the foundation are not considered to have contributed to the failure. 11. The Panel found no evidence that seismicity was a factor in failure of the dam. 12. The dam and its foundations were not instrumented sufficiently to enable the Project Construction Engineer and his forces to be informed fully of the changing conditions in the embankment and its abutments. 13. Following its first working session, the Panel reported that it then seemed apparent that the failure resulted from piping, a process by which embankment material is eroded internally and transported by water flowing through some channel in the embankment section. That conclusion remains valid. The Panel's investigations since that time have been directed particularly to determining the most probable manner in which such piping erosion started. The Panel believes that two mechanisms are suspect. Either could have worked alone or both could have worked together. One is the flow of water against the highly erodible and unprotected key trench filling, through joints in the unsealed rock immediately beneath the grout cap near Sta and the consequent development of an erosion tunnel across the base of the key trench fill. The other is cracking caused by differential strains or hydraulic fracturing of the core material filling the key trench. This cracking would also result in channels through the key trench fill which would permit rapid internal erosion. In either case, leakage occurring through the key trench ultimately initiated further erosion along the downstream contact of the core and the abutment rock. Since the core material was both easily erodible and strong, any erosion channels in the core, along the contact with the rock, readily developed into large tunnels or pipes before becoming visible along the downstream parts of the dam. It should be noted that this description of the failure mechanism does not provide a final answer to the specific cause of failure of Teton Dam. Clearly many aspects of the site and the embankment design contributed to the failure, but because the failed section was carried away by the flood waters, it will probably never be possible to resolve whether the primary cause of leakage in the vicinity of Sta was due to imperfect grouting of the rock below the grout cap, or cracking in the key trench fill, or possibly both. There is evidence to support both points of view. Nevertheless, while the specific cause may be impossible to establish, the narrowing of the possibilities to these two aspects of design and construction is likely to serve as an important but tragic lesson in the design and construction of future projects of this type. 14. The fundamental cause of failure may be regarded as a combination of geological factors and design decisions that, taken together, permitted the failure to develop. The principal geologic factors were (1) the numerous open joints in the abutment rocks, and (2) the scarcity of more suitable materials for the impervious zone of the dam than the highly erodible and brittle windblown soils. The design decisions included among others (1) complete dependence for seepage control on u combination of deep key trenches filled with windblown soils and a grout curtain; (2) selection of a geometrical configuration for the key trench that encouraged arching, cracking and hydraulic fracturing in the brittle and erodible backfill; (3) reliance on special compaction of the impervious IX
7 materials as the only protection against piping and erosion of the material along and into the open joints, except some of the widest joints on the face of the abutments downstream of the key trench where concrete infilling was used; and (4) inadequate provisions for collection and safe discharge of seepage or leakage which inevitably would occur through the foundation rock and cutoff systems. The difficult conditions of the site called for basing the design on the most unfavorable assumptions compatible with the geologic conditions concerning the behavior of the water and its possible effect on the embankment. Instead of placing so much dependence on the key trenches and grout curtain, measures should have been developed to render harmless whatever water did pass, irrespective of the reasons. In final summary, under difficult conditions that called for the best judgment and experience of the engineering profession, an unfortunate choice of design measures together with less than conventional precautions was taken to ensure the adequate functioning of the Teton Dam, and these circumstances ultimately ted to its failure.
BLOCKING AND FILLING SURFACE DRAINAGE DITCHES
MINNESOTA WETLAND RESTORATION GUIDE BLOCKING AND FILLING SURFACE DRAINAGE DITCHES TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-1 Publication Date: 10/14/2015 Table of Contents Introduction Application
More informationMr. Paul Dunlap, California Department of Water Resources
Memorandum To: From: Mr. Paul Dunlap, California Department of Water Resources Oroville Dam Spillway Incident Independent Forensic Team Date: September 5, 2017 Re: Interim Status Memorandum Introduction
More informationConduits through Embankment Dams
Conduits through Embankment Dams Best Practices for Design, Construction, Problem Identification and Evaluation, Inspection, Maintenance, Renovation, and Repair L-266/September 2005 Introduction Conduits
More informationPonds: planning, design, and construction
Ponds: planning, design, and construction Ponds for many purposes: Fish Production Recreation Water Supply Esthetics Wildlife Habitat Natural ponds: Formed in natural depressions in the landscape Not man-made
More informationCBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park
CBC Case Study-1212 1 of 5 CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park More Than Geotechnical Engineering DAYTON 125 Westpark Road Centerville, OH 45459 Phone: 937-428-6150 HAZARD
More informationThe Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments
HOOVER DAM Need arose to control the Colorado River flow and the cycles of flood and drought. Responsibility fell on the Department of the Interior s Bureau of Reclamation Colorado River Compact History
More informationAMERICAN ELECTRIC POWER (SWEPCO)
2016 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-16-163 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION
More informationImportant Role of Filters in Hydraulic Soil Structures Hamid Fallah Apr. 19, 2013
11 th PURDUE GEOTECHNICAL SOCIETY WORKSHOP Important Role of Filters in Hydraulic Soil Structures Hamid Fallah Apr. 19, 2013 Outline Introduction Brief history of evolution of filter design criteria Design
More informationCHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS
CHAPTER 8 SEEPAGE CONTROL IN EMBANKMENTS 8-1. General. All earth and rock-fill dams are subject to seepage through the embankment, foundation, and abutments. Seepage control is necessary to prevent excessive
More informationDistribution Restriction Statement Approved for public release; distribution is unlimited.
CECW-ED Regulation No. 1110-2-8152 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design PLANNING AND DESIGN OF TEMPORARY COFFERDAMS AND BRACED EXCAVATIONS
More informationAMERICAN ELECTRIC POWER (SWEPCO)
2015 DAM & DIKE INSPECTION REPORT ASH PONDS GERS-15-034 WELSH POWER PLANT AMERICAN ELECTRIC POWER (SWEPCO) CASON, TEXAS NATIONAL INVENTORY NO. TX4357 PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION
More informationLimited Visual Dam Safety Inspections OA Wahiawa Dam. Oahu, Hawaii
Limited Visual Dam Safety Inspections OA00017 Wahiawa Dam Oahu, Hawaii Prepared by: U.S. ARMY CORPS OF ENGINEERS HONOLULU DISTRICT STATE OF HAWAII DEPARTMENT OF LAND AND NATURAL RESOURCES May 2006 Dam
More informationSuccessful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam
Successful Foundation Preparations in Karst Bedrock of the Masonry Section of Wolf Creek Dam David M. Robison, P.G. Geotechnical and Dam Safety Section, Louisville District, U.S. Army Corps of Engineers
More informationATTACHMENT A STATEMENT OF WORK RAGGED MOUNTAIN DAM PROJECT
PROEJECT UNDERSTANDING Background ATTACHMENT A STATEMENT OF WORK RAGGED MOUNTAIN DAM PROJECT The purpose of this work scope is to develop feasible alternatives for raising the existing Lower Ragged Mountain
More informationTSAILE DAM MODIFICATION PROJECT Unearthing a Safer Dam
TSAILE DAM MODIFICATION PROJECT Unearthing a Safer Dam Bureau of Indian Affairs Navajo Regional Safety of Dams Program Stephen G. Brown, PE Kleinfelder Acknowledgements C. Scott Goss BIA Chief Safety of
More information378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE
378-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION 378 - POND I. SCOPE The work shall consist of constructing an earthfill embankment and appurtenances to the lines, grades,
More informationWELCOME TO POND 101 OREGON WATER RESOURCES DAM SAFETY SECTION. John Falk, PE
WELCOME TO POND 101 OREGON WATER RESOURCES DAM SAFETY SECTION John Falk, PE MISCONCEPTION 101 This is my own property..so I guess it s really none of your %*&^`!# business if I want to build a pond. R
More informationThe Problem. Embankment Dams on Karstic Limestone, Soluble and Erodible Foundations: Challenges and Solutions GEOSYSTEMS, L.P.
Embankment Dams on Karstic Limestone, Soluble and Erodible Foundations: Challenges and Solutions Donald A. Bruce, Geosystems, L.P. Keith Ferguson, Kleinfelder, Inc. GEOSYSTEMS, L.P. The Problem Centerhill
More informationWater Control Structures Selected Design Guidelines Alberta Environment Page 13-1
Alberta Environment Page 13-1 13.0 DROP INLET SPILLWAYS 13.1 General The drop inlet spillway is commonly used for providing flood protection for earth dams which have smaller reservoirs and/or smaller
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationVolume II: Hazard Annex Dam Failure
Volume II: Hazard Annex Dam Failure Causes and Characteristics of Dam Failure Dam Characteristics Dams are impervious structures that block the flow of water in a river or stream, capturing water behind
More informationDAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety
DAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety NAME OF DAM: Milltown Dam DEPDAMNO.: 15-146 LOCATION: Municipality: East Goshen Township
More informationVisual Inspection Checklist
APPENDIX Q. Visual Inspection Checklist Thispageintentionallyleftblank. VISUAL INSPECTION CHECKLIST CITY OF AUBURN PUBLIC WORKS DEPARTMENT INSPECTION YEAR: TYPE OF INSPECTION: (Informal, Regular, Formal):
More informationPonds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.
POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made
More informationCONSTRUCTION PLAN CHECKLIST
CONSTRUCTION PLAN CHECKLIST The design engineer is responsible for ensuring that plans submitted for city review are in accordance with this checklist. It is requested that the executed checklist be submitted
More informationEarth Brickwork Concrete Plain Radial Drum Roller Flap. fixed. Weirs Barrages. mobile. rockfills. Gravity butress Arch Arch-gravuty Cupola.
Dams type 1 Weirs Barrages fixed mobile Earth Brickwork Concrete Plain Radial Drum Roller Flap embankment Earthfills rockfills Dams Concrete gravity Arch Gravity butress Arch Arch-gravuty Cupola 2 Dams
More informationREMOVING/RELOCATING DRAINAGE LIFT STATIONS
MINNESOTA WETLAND RESTORATION GUIDE REMOVING/RELOCATING DRAINAGE LIFT STATIONS TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-5 Publication Date: 10/14/2015 Table of Contents Introduction Application
More informationSanta Clara Valley Water District Page 1 of 4
Santa Clara Valley Water District File No.: 17-0256 Agenda Date: 4/28/2017 Item No.: 6. BOARD AGENDA MEMORANDUM SUBJECT: Discussion on the Anderson Dam Seismic Retrofit Project. RECOMMENDATION: A. Receive
More informationKeeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement
Keeyask Generation Project Environmental Impact Statement Supporting Volume Physical Environment June 2012 KEEYASK GENERATION PROJECT SUPPORTING VOLUME EFFECTS OF THE ENVIRONMENT ON THE PROJECT June 2012
More informationCreated by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq
Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure
More informationLyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual
Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This
More informationWater Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4
Water Resources By Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4 High Aswan Dam Project 1. Location The High Aswan Dam (HAD) location was determined to fit the topographical features of the
More informationWater Control Structures Selected Design Guidelines Alberta Environment Page 14-1
Alberta Environment Page 14-1 14.0 LOW LEVEL OUTLET WORKS 14.1 General In general, a low level outlet structure can be used to provide one or more of the following functions: Supply adequate water to meet
More informationTable of Contents 5.1 GENERAL Overview Investigation and Engineering Information
Table of Contents Section Page 5.1 GENERAL... 5.1-1 5.1.1 Overview... 5.1-1 5.1.2 Investigation and Engineering Information... 5.1-2 5.2 PRELIMINARY GEOTECHNCIAL REPORTS... 5.2-1 5.2.1 Preliminary Geotechnical
More informationAPPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011
APPENDIX A EARTHEN EMBANKMENT VERSION 1.0 March 1, 2011 SECTION A-1: DESCRIPTION OF PRACTICE An earthen embankment is a raised impounding structure made from compacted soil. The embankment is the feature
More informationMcElroy s Run Impoundment Structural Stability Assessment Report
Allegheny Energy Supply Company, LLC A FirstEnergy Company Pleasants Power Station Pleasants County, West Virginia October 2016 Prepared for: Allegheny Energy Supply Company, LLC A FirstEnergy Company
More informationCategory 1 Waste Rock Stockpile Groundwater Containment System
Memorandum To: Jennifer Saran, Poly Met Mining Inc. Project: 23690862.00-042-008 1.0 Introduction The Co-Lead Agencies have requested a summary of the four containment systems that are planned for the
More informationFailure Consequence Classification
Failure Consequence Classification Audience: Dam Safety Officers (DSO) Owners of small dams Community emergency preparedness coordinators Introduction This document provides an overview of failure consequence
More informationReview of the 2014 Annual Dam Safety Inspection Report, 2-North Pit Tailings Disposal Facility, Quinsam Coal Mine
November 24, 2014 Quinsam Coal Corporation Hillsborough Resources Limited PO BOX 5000 Campbell River BC V9W 8A3 ISSUED FOR USE FILE: V15103102-01 via Email: gbg@hillsboroughresources.com Attention: Subject:
More informationDry structural excavation is usually done with front-end loaders, bulldozers or backhoes.
1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined
More informationMEMORANDUM. Norm Evenstad, Water Resources Program Coordinator, Natural Resources Conservation Service (NRCS), Salt Lake City, Utah
MEMORANDUM To: From: Norm Evenstad, Water Resources Program Coordinator, Natural Resources Conservation Service (NRCS), Salt Lake City, Utah Dennis Hawkins, PN Regional Diving Officer (PN-3425), Boise,
More informationBig Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill Annual Inspection Report
January 15, 2016 Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill Annual Inspection Report CCR Landfill Information Name: Operator:
More informationPHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe
PHASE I ERNEST MINE COMPLEX Project Objectives The objective of the project was to develop an economically feasible, safe method of diverting all flows from the Ernest Mine Complex to a central discharge
More informationMD Exhibit MD1 SMALL POND DESIGN CHECKLIST. ProjectName. Engineering Firm Date Submitted. Vicinity Map Pond Summary Sheet (MD-ENG-14) Pond Class
MD501.06 Exhibit MD1 SMALL POND DESIGN CHECKLIST ProjectName Engineering Firm Date Submitted Vicinity Map Pond Summary Sheet (MD-ENG-14) Pond Class REVIEW INDEX R (required, not submitted) NA (not applicable)
More informationCCR Rule Annual Inspection Report 2
Inspection Description An ARCADIS team performed the Trimble County Gypsum Storage Pond (GSP) 2015 annual inspection by a qualified professional engineer. The overall goal of the inspection was to ensure
More informationSEEPAGE FAILURE, EVALUATION AND REMEDIATION OF PENN FOREST DAM
SEEPAGE FAILURE, EVALUATION AND REMEDIATION OF PENN FOREST DAM by W. B. Bingham, P.E.l R. E. Holderbaum, P,E.* W. S. Sherman, P,E,3 ABSTRACT Penn Forest Dam is a large earthfill embankment dam that impounds
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationHISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY
HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY (i) Site Name and Ownership Information: Site Name: Plant Hammond Site Location: Site Address:
More information2. SCOPE OF WORK Evolution of Plan of Study Hydrology ALASKA ENERGY AUTHORITY AEA ENGINEERING FEASIBILITY REPORT
2. SCOPE OF WORK 2.1. Evolution of Plan of Study The purpose of this feasibility study is to define all aspects of the Project in sufficient detail to support the State s decision process regarding project
More informationSupplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania
Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Project Authorization USDA's Small Watershed Program is carried out under the
More informationUSACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED
USACE LEVEE RISK ASSESSMENT PROCESS LESSONS LEARNED 1 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56
More informationGRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION
CHAPTER 23.105 GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION Sections 23.105.101 General... 1 23.105.102 Definitions... 1 23.105.103 Permits required... 3 23.105.104 Hazards.... 4 23.105.105 Permit
More informationA Brief History of Dams in Iraq. The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE
A Brief History of Dams in Iraq The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE Dams in General Definition of a Dam: A dam is a barrier made of soil, concrete
More information2017 ANNUAL DAM AND DIKE INSPECTION REPORT
2017 ANNUAL DAM AND DIKE INSPECTION REPORT ASH PONDS WELSH POWER PLANT CASON, TEXAS November, 2017 Prepared by: American Electric Power Service Corporation 1 Riverside Plaza Columbus, OH 43215 GERS-17-067
More informationSection 8 Minimum Horizontal and Vertical Setback Distances
Section 8 Minimum Horizontal and Vertical Setback Distances 1. Horizontal Distances a. Horizontal distances from the various components of a system to pertinent terrain features, including streams, lakes,
More informationAppendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS
Appendix 3-G SWM AND BMP CONSTRUCTION INSPECTIONS Table of Contents APPENDIX SECTION HEADINGS 3-G.1.0 INTRODUCTION 3-G-2 3-G.1.1 Construction Inspections 3-G-2 3-G.1.2. As-Built Survey and Plan 3-G-2 3-G.1.2.1
More informationStorm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
More information(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08
(b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including
More informationThe Afton TSF, situated approximately 12 km west of Kamloops, BC has been under care and maintenance since 1997.
November 27, 2014 KGHM Ajax Mining Inc. Ajax Project Suite 200-124 Seymour Street Kamloops, BC V2C 2E1 ISSUED FOR USE FILE: V15103098-01 via Email: kate.parsons@kghm.com Attention: Subject: Kate Parsons,
More informationENGINEERING AND CONSTRUCTION STANDARD FOR CULVERT BRIDGES AND RELATED STRUCTURES ORIGINAL EDITION JULY 1997
ENGINEERING AND CONSTRUCTION STANDARD FOR CULVERT BRIDGES AND RELATED STRUCTURES ORIGINAL EDITION JULY 1997 This standard specification is reviewed and updated by the relevant technical committee on Jun.
More informationCCR Rule Operating Criteria Closure Plan
CCR Rule Operating Criteria 257.102 Closure Plan FGD Pond 2 Jim Bridger Plant Point of Rocks, Wyoming PREPARED FOR PacifiCorp 1407 West North Temple Salt Lake City, UT 84116 (801) 521-0376 Fax (801) 220-4748
More informationDraft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS
SECTION 10.1 GENERAL 10.1.1 SCOPE This part of the Manual covers the structural design and installation of reinforced concrete pipe for railway culverts. Pipe geometry may be circular, arch, or elliptical.
More informationUnited States Army Corps of Engineers. Addicks and Barker Dam Safety Update
United States Army Corps of Engineers Addicks and Barker Dam Safety Update COL Richard P. Pannell District Commander, Galveston District U.S. Army Corps of Engineers March 9, 2016 US Army Corps of Engineers
More informationDAMS AND OTHER HYDRAULIC STRUCTURES
GAP.2.9.1 A Publication of Global Asset Protection Services LLC DAMS AND OTHER HYDRAULIC STRUCTURES INTRODUCTION The purpose of a dam evaluation is to review the design, construction and performance history
More informationChapter 1 INTRODUCTION
Chapter 1 Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 1.1 Introduction... 1 1.2 Preconstruction Division... 1 1.2.1 Regional Production Groups... 2 1.2.2 Preconstruction
More informationNUMERICAL ANALYSIS AND INVESTIGATION OF PIPING IN AN EARTH DAM FOUNDATION BY SOFTWARE SEEP / W (CASE STUDY OF KERMANSHAH EZGELEH EARTH DAM)
NUMERICAL ANALYSIS AND INVESTIGATION OF PIPING IN AN EARTH DAM FOUNDATION BY SOFTWARE SEEP / W (CASE STUDY OF KERMANSHAH EZGELEH EARTH DAM) *Seyyed Hossein Naghmehkhan Dahandeh Civil Engineering, Hydraulic
More informationSECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...
SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...
More informationCASE STUDY: SURFACE IMPOUNDMENT FAILURE AND RECONSTRUCTION
CASE STUDY: SURFACE IMPOUNDMENT FAILURE AND RECONSTRUCTION The April 2002 Geotechnical Fabrics Report (GFR) contained a case study on the failure of a liner system for a surface impoundment. A follow-up
More informationEvaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair
Memorandum Number MERL 2011-34 Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair Missouri River Basin Project Solomon Division Glen Elder Unit - Kansas
More informationGreen CCR Landfill. Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2017 Annual Inspection Report
Green CCR Landfill Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2017 Annual Inspection Report January 11, 2018 Prepared By: Project ID: 170138B Big Rivers
More informationSPECIFICATIONS FOR STRUCTURAL EXCAVATION
SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition
More informationVICINITY MAP AND SITE MAP. Page 1 of 9
INTRODUCTION... 2 1. Background Information of West Bottom Ash Pond (BAP)... 2 1.1 Facility Location Description...2 1.2 Description of West BAP CCR Unit...2 1.2.1 Embankment Configuration...2 1.2.2 Construction
More informationConstruction Inspection Checklists
III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments
More informationMechanical and Hydraulic Behavior of Cut off-core Connecting Systems in Earth Dams
Mechanical and Hydraulic Behavior of Cut off-core Connecting Systems in Earth Dams Zakaria Zoorasna Graduate Student Faculty of Engineering, Tarbiat Moallem University, Tehran, Iran z_zoorasna@yahoo.com
More informationAnnex V Concrete Structures Removal Plan
Appendix D Annex V Concrete Structures Removal Plan Figure V1 Lower Granite Sequences of Concrete Removal and Cofferdam Figure V2 Little Goose Sequence of Concrete Removal and Cofferdam Figure V3 Lower
More informationAppendix E. Coordinating Erosion and Sediment Control With Low-Impact Development Planning
Appendix E Appendix E. Coordinating Erosion and Sediment Control With Low-Impact Development Planning E.1 Introduction It is essential to coordinate post-construction stormwater planning with the design
More informationChapter 4. Main problems in a canal network 4.1 INTRODUCTION
Canals 21 Chapter 4 4.1 INTRODUCTION This chapter looks at problems which are frequently encountered in irrigation canal systems. Some of these are described in detail. The last section of this chapter
More informationTravers Reservoir Rehabilitation Project Irrigation Technical Conference Lethbridge, AB June 2, 2010
Travers Reservoir Rehabilitation Project 2010 Irrigation Technical Conference Lethbridge, AB June 2, 2010 Location Plan Western Irrigation District Headworks CALGARY Eastern Irrigation District Headworks
More informationManure Storage for Environmental Management Systems
WiMStor01 MStor Manure Storage for Environmental Management Systems Key: 1)Low Risk 2)Low-Moderate Risk 3)Moderate-High Risk 4)High Risk Location of Manure Storage Are the manure storage facilities in
More informationCOLD WEATHER AND HIGH ALTITUDE DAM CONSTRUCTION
COLD WEATHER AND HIGH ALTITUDE DAM CONSTRUCTION CASE STUDY TWIN LAKES DAM ENLARGEMENT PROJECTS DANIEL JOHNSON, AECOM DAN HERTEL, ENGINEERING SOLUTIONS TED FELDSHER, AECOM PURPOSE / HISTORY Remove two dams
More informationEast Branch. April 11, Johnsonburg, Pa BUILDING STRONG
East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 11, 2013 Johnsonburg, Pa 1 WHY WE ARE HERE Communicate actions to improve dam safety What s The Problem What s Been Done The
More informationLessons Learned from Dam Incidents and Failures Lessons Learned Identified
Lessons Learned from Dam Incidents and Failures Lessons Learned Identified Seepage along penetrations through embankment dams should be controlled using a filter diaphragm instead of antiseep collars.
More informationRemedial grouting works to two dams in Hong Kong
Remedial grouting works to two dams in Hong Kong D. GALLACHER, AECOM, Edinburgh, UK SYNOPSIS. Tai Tam Upper and West Col Dams in Hong Kong had experienced substantial leakage over an extended period. Recommendations
More information2017 Annual Dam and Dike Inspection Report
2017 Annual Dam and Dike Inspection Report Bottom Ash Pond Complex Mitchell Plant Wheeling Power Company & Kentucky Power Company Marshall County, West Virginia October 20, 2017 Prepared by: American Electric
More informationPeter Lighthall, P.Eng. Consulting Geotechnical Engineer
Peter Lighthall, P.Eng. Consulting Geotechnical Engineer Cassiar Gold Corp. China Minerals Mining Corporation Suite 1100 1111 Melville Street Vancouver, BC V6E 3V6 Attn: Re: Ms. Patricia Fong Independent
More informationWater Control Structures Selected Design Guidelines Alberta Environment Page 12-1
Alberta Environment Page 12-1 12.0 CHUTE SPILLWAYS 12.1 General Reinforced concrete chute spillways are the most frequently used type of service spillway for providing flood protection for earthfill dams,
More information3.2 INFILTRATION TRENCH
3.2 INFILTRATION TRENCH Type of BMP Priority Level Treatment Mechanisms Infiltration Rate Range Maximum Drainage Area LID Infiltration Priority 1 Full Retention Infiltration, Evapotranspiration (when vegetated),
More informationWater Control Structures Selected Design Guidelines Alberta Environment Page 17-1
Alberta Transportation Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 17.0 MAIN CANAL CONVEYANCE STRUCTURES 17.1 General Conveyance structures typically employed on main
More informationHISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116
(i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:
More informationCCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0
Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 47708 Submitted by AECOM 9400 Amberglen Boulevard Austin, Texas 78729 257.83
More informationDam Safety and Seismicity
Dam Safety and Seismicity January 13, 2014 Fort St. John, BC John Nunn, P.Eng, M.Sc., M.I.C.E Chief Project Engineer Tim Little, P. Eng. Topics 1. The Practice of Dam Safety in BC Hydro 2. Bennett Dam
More informationDeep Foundations Institute Fall 2004 Fall 2004
Fall 2004 Treviicos/Rodio JV using Wirth Reverse Circulation Drill Rig to install Secant Wall Piles for Walter F. George Dam Deep Cut-Off Fall 2004 DEEP FOUNDATIONS 5 The Deep Cut-Off at the Walter F.
More information2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio
Prepared for: FirstEnergy Generation, LLC 76 South Main St Akron, Ohio 44308 2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio Prepared by: 10211 Wincopin Circle, Floor 4 Columbia,
More informationChapter 3: Summaries of Case Histories
Chapter 3: Summaries of Case Histories This chapter presents summaries of 30 case studies on the performance of seepage barriers in dams that were reviewed for this study. Information was collected on
More information2016 ANNUAL DAM AND DIKE INSPECTION REPORT. Bottom Ash Ponds. Rockport Plant Spencer County, Indiana. December 6 th, 2016
2016 ANNUAL DAM AND DIKE INSPECTION REPORT Bottom Ash Ponds Rockport Plant Spencer County, Indiana December 6 th, 2016 Prepared for: Indiana Michigan Power Company Rockport Plant 2791 North US 231 Rockport,
More informationCCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0
Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 47708 Submitted by AECOM 9400 Amberglen Boulevard Austin, Texas 78729 257.83
More informationApplication for a Dam Permit Ash Basin No. 1
Application for a Dam Permit Ash Basin No. 1 for the Sunbury Generating Station Shamokin Dam, Pennsylvania submitted to Commonwealth of Pennsylvania Department of Environmental Protection Bureau of Waterways
More informationCONSTRUCTION SPECIFICATION
CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES GENERAL C220 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C220 ISSUE: NO:3 July 2018 TABLE OF CONTENTS CLAUSE CONTENTS PAGE GENERAL...
More informationMangla Dam Raising: Effectiveness of Seepage Reduction Measures for Sukian Dyke
Mangla Dam Raising: Effectiveness of Seepage Reduction Measures for Sukian Dyke Jehan Zeb, Sr. Geotechnical Engineer, GT&GE Division NESPAK, Lahore, Pakistan; email: jazy930@hotmail.com Tahir M. Hayat,
More informationGeneral Groundwater Concepts
General Groundwater Concepts Hydrologic Cycle All water on the surface of the earth and underground are part of the hydrologic cycle (Figure 1), driven by natural processes that constantly transform water
More information