1 New York State Code Rule 56 Requirements & Changes in the Asbestos Code Rule Presented by Peter DeLucia AAC Contracting, Inc. 8/3/2012 AAC Contracting, Inc. 1

2 8/3/2012 AAC Contracting, Inc. 2

3 What is Asbestos? Commercial designation for mineral products that possess: High tensile strength Flexibility Chemical and thermal resistance High electrical resistance And can be woven 8/3/2012 AAC Contracting, Inc. 3

4 Uses-Ancient 8/3/2012 AAC Contracting, Inc. 4

5 Uses-Everyday 80% cotton and 20% asbestos 8/3/2012 AAC Contracting, Inc. 5

6 Uses-bizarre 8/3/2012 AAC Contracting, Inc. 6

7 Uses-Pop Culture 8/3/2012 AAC Contracting, Inc. 7

8 Uses-Why? Last updated November 27, :41 p.m. PT 8/3/2012 AAC Contracting, Inc. 8

9 8/3/2012 AAC Contracting, Inc. 9

10 Outline Multi-employer responsibilities Project Records Cleanup of Uncontrolled Disturbances Surveys Proposed Changes 8/3/2012 AAC Contracting, Inc. 10

11 Revised 2006 To comply with OSHA & EPA Clarification Include existing AVs User Friendly Continual Corrections in State Register 3/21/07 Guidance Documents New revision 8/3/2012 AAC Contracting, Inc. 11

12 Guidance Document 8/3/2012 AAC Contracting, Inc. 12

13 Multi-employer Worksites: Demolition Renovation, Remodeling and Repair Asbestos Abatement Contractor Shall inform all employers on site Nature of work PACM & ACM Disturbance prohibited by non-licensed contractor Elevated air samples Work stoppage Barrier inspections 8/3/2012 AAC Contracting, Inc. 13

14 Multi-employer Worksites: Demolition Renovation, Remodeling and Repair Non-Asbestos Contractors Notify building owner or representative Upon discovery of PACM Within 24 hours Quantity and location Activities cease Until assessed/handled by licensed contractor 8/3/2012 AAC Contracting, Inc. 14

15 Multi-employer Worksites: Demolition Renovation, Remodeling and Repair Building owner or representative Prior to commencement Inform all employers of PACM and ACM within their portion of building impacted by project Presence Location Quantity 8/3/2012 AAC Contracting, Inc. 15

16 Multi-employer Worksites: Demolition Renovation, Remodeling and Repair General Contractors Shall prohibit Disturbance of PACM and ACM Shall require Asbestos contractors under their control and supervision to be in compliance 8/3/2012 AAC Contracting, Inc. 16

17 Multi-employer - OSHA (d)(5) All general contractors on a construction project which includes work covered by this standard shall be deemed to exercise general supervisory authority over the work covered by this standard, even though the general contractor is not qualified to serve as the asbestos "competent person" as defined by paragraph (b) of this section. As supervisor of the entire project, the general contractor shall ascertain whether the asbestos contractor is in compliance with this standard, and shall require such contractor to come into compliance with this standard when necessary. 8/3/2012 AAC Contracting, Inc. 17

18 8/3/2012 AAC Contracting, Inc. 18

19 Project Record- Owner Responsibility Required on-site with the owner for active projects Copies of: Licenses for all involved entities Supervisor and handler certificates Notifications and variances Including amendments and re-openings 8/3/2012 AAC Contracting, Inc. 19

20 Project Record- Owner Responsibility Required on-site with the owner for active projects Copies of: Air sample log Air sample results Project Monitor s daily log 8/3/2012 AAC Contracting, Inc. 20

21 Project Record- Owner Responsibility Required on-site with the owner for active projects Copies of: Supervisor s daily log Entry/exit logs Inspection, surveys and bulk sample data The building/structure owner can rely upon his authorized representative(s) during the active portion of the asbestos project to maintain these required records. PROJECT NUMBER: PROJECT NAME : PROJECT ADDRESS : ENTRY/EXIT LOG SHEET page DATE: DAY: PLEASE READ BEFORE SIGNING ALL PERSONS WHO ENTER THE WORK AREA / ENCLOSURE SHALL SIGN IN. BY SIGNING THE ENTRY / EXIT LOG SUCH PERSONS HAVE ACKNOWLEDGED THAT THEY HAVE REVIEWED AND UNDERSTAND ALL REGULATIONS, PERSONAL PROTECTIVE REQUIREMENTS, WORK AREA ENTRY / EXIT PROCEDURES AND EMERGENCY PROCEDURES. SIGNATURE IN OUT IN OUT IN OUT INT. of 8/3/2012 AAC Contracting, Inc. 21

22 8/3/2012 AAC Contracting, Inc. 22

23 Responsibility for Cleanup of Uncontrolled Disturbances Upon discovery Property Owner must Contract with licensed asbestos contractor For immediate isolation and cleanup Prior to cleanup Must be assessed by Inspector Incidental Disturbance- Quantity not determined by the amount of asbestos disturbed, but the square feet of contaminated surfaces. 8/3/2012 AAC Contracting, Inc. 23

24 Responsibility for Cleanup of Uncontrolled Disturbances Incidental vs. Historic Incidental Disturbance considered an emergency project, regardless of quantity. More than a Minor requires a SSV. 8/3/2012 AAC Contracting, Inc. 24

25 SURVEYS are ALWAYS REQUIRED 8/3/2012 AAC Contracting, Inc. 25

26 Asbestos Survey Owner must have an Asbestos survey in the affected portion of the building prior to Before Demolition Remodeling Renovation Repair 8/3/2012 AAC Contracting, Inc. 26

27 Inspection & Survey AHERA Basis OSHA must inspect those materials or areas that will be disturbed AHERA protocols/accreditation for compliance EPA-NESHAPS Prior to demolition or renovation activities Accredited inspectors May involve destructive sampling 8/3/2012 AAC Contracting, Inc. 27

28 Survey Pitfalls Scope not communicated to inspector Lack of experience Insufficient samples Not compliant with all regulations Outdated Done during phase IAplanning & design 8/3/2012 AAC Contracting, Inc. 28

29 NEW YORK STATE ASBESTOS / FIBERS FREQUENTLY ASKED QUESTIONS Listed below are the most frequently asked questions (FAQs) regarding asbestos /fibers that are commonly received by the New York State Department of Health s (NYS DOH) Environmental Laboratory Approval Program (ELAP) and Bureau of Occupational Health (BOH), as well as, the NYS Department of Labor (DOL). FAQ # 5: Which types of samples does my laboratory need to gravimetrically reduce? In March 2011, the ELAP Certification Manual was updated to include more detail regarding which types of materials must be gravimetrically reduced. Manual Item describes the laboratory-approved method for Friable bulk samples that may not require gravimetric reduction, while Manual Item describes the approved method for Non-Friable Organically Bound (NOB) bulk samples that must be gravimetrically reduced. It is recommended that friable samples, which contain matrices that interfere with optical properties (e.g., large percentage of aggregate glass or "milky way effect"), or when asbestos concentrations are near the one percent level, be gravimetrically reduced (Item 198.1, Section 4.3). Meanwhile, NOB building materials embedded in flexible-to-rigid organic matrices including asphalt or vinyl must be gravimetrically reduced according to either Item or (Section 4). Refer to Table 1 below, which is also included in Items 198.1, 198.4, and /3/2012 AAC Contracting, Inc. 29

30 8/3/2012 AAC Contracting, Inc. 30

31 Vermiculite 70% Of Vermiculite from Libby, MT 8/3/2012 AAC Contracting, Inc. 31

32 Vermiculite-Loose Fill EPA & NYS No approved method to determine if asbestos present Treated as ACM 8/3/2012 AAC Contracting, Inc. 32

33 Vermiculite-as a component Per NYSDOH If < 10 % Vermiculite may be tested by PLM If > or = 10 % Vermiculite considered ACM 8/3/2012 AAC Contracting, Inc. 33

34 Asbestos Survey Survey to assess Locations Quantities Friability Condition To include visual inspections All suspect materials considered asbestos Unless bulk sample proves otherwise GD- Regardless of construction date Survey Contents.pptx 8/3/2012 AAC Contracting, Inc. 34

35 Asbestos Survey Survey shall be kept on-site throughout Abatement and Renovation, repair, remodeling, demolition 8/3/2012 AAC Contracting, Inc. 35

36 Asbestos Survey Pre-demolition surveys Submitted to ACB Submit all asbestos surveys To local government office in charge of permit issuance Demolition: The wrecking or removal of any loadsupporting structural member of a building or structure 8/3/2012 AAC Contracting, Inc. 36

37 Asbestos Still in Use 80+% of US imports from Canada Last US mine closed in 2002 Partial ban TSI Spray- 1973/78 No new products after 1989 Chrysotile cement pipes-manufactured in Pakistan 8/3/2012 AAC Contracting, Inc. 37

38 US Asbestos Consumption 8/3/2012 AAC Contracting, Inc. 38

39 8/3/2012 AAC Contracting, Inc. 39

40 8/3/2012 AAC Contracting, Inc. 40

41 8/3/2012 AAC Contracting, Inc. 41

42 Mineral Forms Serpentine Amphiboles Chrysotile Amosite Crocidolite Actinolite Anthophyllite Tremolite 8/3/2012 AAC Contracting, Inc. 42

43 8/3/2012 AAC Contracting, Inc. 43

44 GD Question 121: Regardless of Code Rule 56 requirements regarding surveys/inspections, as per Section (d) "No exemption to this requirement to conduct an asbestos survey shall exempt any person, asbestos contractor, property owner or business entity from the inspection or asbestos survey requirements of EPA, OSHA ". Thus, if federal regulations mandate various materials installed on January 1, 1974 or after to be treated as ACM, Code Rule 56 does not grant relief from that requirement. Regardless of construction date, Building Owner due diligence is always required for identification and assessment of ACM, as per OSHA requirements 8/3/2012 AAC Contracting, Inc. 44

45 (k)(1) If the employer/building owner has actual knowledge, or should have known through the exercise of due diligence, that other materials are asbestos-containing, they too must be treated as such. 8/3/2012 AAC Contracting, Inc. 45

46 EPA-Inspections (a) Prior to commencement of the demolition or renovation, thoroughly inspect the affected facility or part of the facility where the demolition or renovation operation will occur for the presence of asbestos Regardless of construction date Exemption Residential 4 or fewer dwellings 8/3/2012 AAC Contracting, Inc. 46

47 OSHA: Materials <1% asbestos (a)Scope and application. This section regulates asbestos exposure in all work as defined in 29 CFR (b) Competent person Exposure assessments Recordkeeping If < PELs Wet methods Prompt cleanup No prohibited methods 8/3/2012 AAC Contracting, Inc. 47

48 Cementitious Products 8/3/2012 AAC Contracting, Inc. 48

49 Cementitious Products Transite Acoustical Panels (music rooms, auditoriums) Transite Roofing Panels 8/3/2012 AAC Contracting, Inc. 49

50 Cementitious Products 8/3/2012 AAC Contracting, Inc. 50

51 Asbestos Electrical Insulation "AF wire (asbestos fiber) 8/3/2012 AAC Contracting, Inc. 51

52 Fire Door Asbestos Textiles Asbestos Insulation 8/3/2012 AAC Contracting, Inc. 52

53 ACM plaster topcoat Mastic hockey pucks 8/3/2012 AAC Contracting, Inc. 53

54 Flooring and flooring mastics & backing 8/3/2012 AAC Contracting, Inc. 54

55 Spray Applied Acoustical Plaster Surfacing Materials Spray Applied Fireproofing 8/3/2012 AAC Contracting, Inc. 55

56 Thermal System Insulation 8/3/2012 AAC Contracting, Inc. 56

57 Thermal System Insulation 8/3/2012 AAC Contracting, Inc. 57

58 Mastics and Glues 8/3/2012 AAC Contracting, Inc. 58

59 Asbestos Gaskets & Ropes 8/3/2012 AAC Contracting, Inc. 59

60 Roofing Products 8/3/2012 AAC Contracting, Inc. 60

61 Asbestos Tape and Expansion Cloth 8/3/2012 AAC Contracting, Inc. 61

62 Flooring Topcoat Finishing Materials Joint Compound Asbestos Paint 8/3/2012 AAC Contracting, Inc. 62

63 Caulking & Glazing Compounds Fire-stopping 8/3/2012 AAC Contracting, Inc. 63

64 TSI Refractory Brick Oven Insulation 8/3/2012 AAC Contracting, Inc. 64

65 Proposed Changes to CR56 8/3/2012 AAC Contracting, Inc. 65

66 Proposed Changes to CR 56 Fire & Life Safety enforceable now as part of NYS UFBC State register Summer 2012????? Effective end of 2012????? Clarify disturbance cleanup requirements Include existing AV s Other Mechanical fastening Buried NF piping Commercial re-usable tents 8/3/2012 AAC Contracting, Inc. 66

67 Demolition Change definition Load bearing & nonload bearing members and/or components Done by abatement contractor as part of project 8/3/2012 AAC Contracting, Inc. 67

68 Survey or Certificate of Survey Submitted to local entity (CEO) To obtain permits (demo, reno, etc.) If no permit required To town/city clerk 8/3/2012 AAC Contracting, Inc. 68

69 Project Completion Certificate Submitted to local entity (CEO) To obtain permits for continuation of work If no permit required To town/city clerk 8/3/2012 AAC Contracting, Inc. 69

70 Accessible Means of Egress Marked inside and out maintained throughout the project No alterations will be allowed to the existing means of egress in occupied buildings Including exit signage and illumination 8/3/2012 AAC Contracting, Inc. 70

71 Unoccupied buildings Construction or preparation for demolition > 50 ft. or 4 or more stories must have At least one lighted stairway with adequate exit signage, including directionality 8/3/2012 AAC Contracting, Inc. 71

72 Pre-demolition asbestos projects at a vacant building Existing standpipes maintained in an operational condition one floor below the project 8/3/2012 AAC Contracting, Inc. 72

73 Exits from abatement work areas shall be Maintained Have appropriate signage prominently displayed clearly indicate the direction of the exits Inspected daily by the supervisor for blockage or impediments. 8/3/2012 AAC Contracting, Inc. 73

74 Hardwall Barriers Fire-retardant No OSB or wallboard ASTM D-2898 UL 723 ASTM E84 NFPA 255 8/3/2012 AAC Contracting, Inc. 74

75 Existing fire protection systems Maintained throughout asbestos project Per the NYS Uniform Fire Prevention and Building Code (UFPBC) requirements These systems cannot be removed or modified Without the approval of the Code Enforcement Official (CEO) 8/3/2012 AAC Contracting, Inc. 75

76 8/3/2012 AAC Contracting, Inc. 76

77 Active system components Smoke heads, alarms, sensors, sprinkler heads, etc. Not considered fixed objects and shall not be covered with plastic. In lieu of plasticizing these components subject to cleaning by wet methods and/or HEPA-vacuuming. 8/3/2012 AAC Contracting, Inc. 77

78 Pre-fire plans (for the asbestos project) On site Copies provided to Fire Chief Code Enforcement Official The owner shall designate a person to be the Fire Prevention Program Superintendent. The fire prevention program superintendent shall develop and maintain an approved prefire plan in cooperation with the fire chief Fire safety and evacuation plans shall be reviewed or updated annually or as necessitated by changes in staff assignments, occupancy, or the physical arrangement of the building 8/3/2012 AAC Contracting, Inc. 78

79 Emergency evacuation maps Posted Decontamination unit The ground floor lobby or comparable location At all exits from each work area 8/3/2012 AAC Contracting, Inc. 79

80 8/3/2012 AAC Contracting, Inc. 80

81 If variation from NYS UFPBC or local regulations is required due to the asbestos project, Permits obtained by a NYS registered design professional. If not required, the written approval of the variation must be obtained from the pertinent agency and made part of the project record. Documentation on-site Copies of approved variations Fire Chief & CEO, prior to implementing Variance from ICR 56 Relief from section /3/2012 AAC Contracting, Inc. 81

82 If an asbestos project covers the entire floor or is greater than 15,000 SF on any floor A negative air ventilation system disconnect switch Located on the floor below Or a secure location in the ground floor lobby Location coordinated with the Fire Chief Notice of the location of the switch posted in the ground floor lobby or similar location 8/3/2012 AAC Contracting, Inc. 82

83 A Code Enforcement Official or Registered Design Professional Review the project documents & provide a written acceptance Compliance with ALL federal, state and local building and fire codes. Part of the Project Record. DOL notification - individual providing written acceptance Name NYS certification/professional license and registration number Phone number Design Professional= Architect or Engineer 8/3/2012 AAC Contracting, Inc. 83

84 Variance petition submissions seeking relief from ICR 56 Include a written statement by NYS Registered Design Professional Or CEO Compliant with NYS UFPBC and local regulations for fire or life safety issues in regards to the asbestos project. 8/3/2012 AAC Contracting, Inc. 84

85 Information required for submission to the design professional to obtain written acceptance of the work plan as required for NYS notifications or variance from CR 56. Written detailed work plan Copy of the variance petition (if needed) Plans/Drawings for the floor or building depicting Regulated work areas Decon and neg air locations Fire extinguisher locations Hard wall locations Means of egress Must be unobstructed (vertical and horizontal) & without alteration Exit locations marked (signage and illumination required) Evacuation routes marked Location and means to maintain existing fire protection systems 8/3/2012 AAC Contracting, Inc. 85

86 In Summary Protect Health Prohibit disturbance Asbestos contractor oversight Surveys NO safe date OSHA & NYS Due diligence EPA- Identify Cross reference prior to work Inform all of presence, location and quantity Controls for <1% asbestos Recordkeeping Fire and Life Safety Considerations 8/3/2012 AAC Contracting, Inc. 86

87 Health Effects 8/3/2012 AAC Contracting, Inc. 87

88 Mesothelioma 8/3/2012 AAC Contracting, Inc. 88

89 Need a Trunk Monkey? 8/3/2012 AAC Contracting, Inc. 89

90 8/3/2012 AAC Contracting, Inc. 90

91 8/3/2012 AAC Contracting, Inc. 91

92 Resources NYSDOL Transition Web Site DOSH_CODE_RULE_56_TRANSITION.shtm AAC Contracting, Inc. Kevin Cannan: , ext. 119 Peter DeLucia: , ext 129 8/3/2012 AAC Contracting, Inc. 92

93 Disclaimer: This information should be used as a resource and is not a substitute for an individual or an entity from pursuing their own due diligence with regards to regulatory and legal compliance. The author has merely collected information and is not responsible for the compliance or non-compliance of the readers in regards to the information provided.

Asbestos Management Program April 27, 2017

Asbestos Management Program April 27, 2017 Asbestos Management Program April 27, 2017 1. INTRODUCTION 1.1. Purpose Indiana University Environmental Health and Safety (IUEHS) has developed this Program to identify practices and procedures for the

More information

Project Monitoring & Air Sampling

Project Monitoring & Air Sampling Project Monitoring & Air Sampling 1. Qualifications of Air Sampling Personnel. The project air sampling shall be conducted by an asbestos project air sampling technician who has been trained in the selected

More information

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22 Page 1 of 22 Asbestos Survey Project Summary Pursuant to your request; Environmental, Inc., has performed an Asbestos Building Survey on 8/13/2014 and limited to the above referenced location. The Interior/Exterior/Roof

More information

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 Department Title: Safety Department Page: 2 Department Title: Safety Department Page:

More information

Asbestos. Asbestos is a naturally occurring fibrous mineral that is mined from the earth and

Asbestos. Asbestos is a naturally occurring fibrous mineral that is mined from the earth and Asbestos What is asbestos? Asbestos is a naturally occurring fibrous mineral that is mined from the earth and found in many parts of the world. Its composition is such that it can be separated into smaller

More information

Washington University Asbestos Operations and Maintenance Plan

Washington University Asbestos Operations and Maintenance Plan 1. Purpose 2. Asbestos Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to

More information

HERRON Enterprises USA, Inc.

HERRON Enterprises USA, Inc. Phone (303) 763 9639 To: City of Montrose / Mr. Mark Armstrong HERRON Project No.: 1120145 Job No.: Verbal Location: Multiple Buildings, 950 and 970 Chipeta Rd., Montrose, CO 81403 Dates of Service: November

More information

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager Asbestos Management Plan Program originated: 02/2000 Last updated: 6/2015 Wendel Reece University Safety Manager TABLE OF CONTENTS I. Introduction II. Purpose III. Operations and Maintenance Asbestos Related

More information

Asbestos Awareness OSHA Class IV

Asbestos Awareness OSHA Class IV Asbestos Awareness OSHA Class IV Stacy Kahatapitiya, CHMM, LEED GA & Peter Nketia-Akonnor Characteristics Naturally occurring mineral found in rock formations Most ACM mined/produced in Canada Comes from

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

WILLIAM PATERSON UNIVERSITY ASBESTOS MANAGEMENT PLAN

WILLIAM PATERSON UNIVERSITY ASBESTOS MANAGEMENT PLAN WILLIAM PATERSON UNIVERSITY ASBESTOS MANAGEMENT PLAN 1. INTRODUCTION 1.1 OBJECTIVES Asbestos-containing materials (ACM) have been used widely in the construction industry. Although use of ACM in buildings

More information

Limited Asbestos Demolition Survey

Limited Asbestos Demolition Survey Limited Asbestos Demolition Survey Limited Asbestos Demolition Survey Former Fire Station Facility 25 to 45 S. Orlando Avenue Cocoa Beach, Florida Client: City of Cocoa Beach Public Works Department 1600

More information

ASBESTOS AWARENESS. What is Asbestos? Asbestos

ASBESTOS AWARENESS. What is Asbestos? Asbestos ASBESTOS AWARENESS 1of 63 What is Asbestos? Asbestos is the name for a group of naturally occurring minerals that separate into very fine fibers that are very durable and extremely heat resistant. Because

More information

Office of Design & Construction State University Plaza Albany, New York

Office of Design & Construction State University Plaza Albany, New York Instructions: Consultant should meet with the Campus and Fund at the work area(s) prior to completing this Checklist. At least two (2) meetings are required, one prior to Schematic Phase submission and

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.10/22/08, 10/15/09 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information

ASBESTOS ASSESSMENT Cartier Court Memorial University of Newfoundland St. John s, NL

ASBESTOS ASSESSMENT Cartier Court Memorial University of Newfoundland St. John s, NL Project #: 13916 ASBESTOS ASSESSMENT Cartier Court Memorial University of Newfoundland St. John s, NL Prepared for: Sheila Miller Director, Department of Health and Safety Memorial University of Newfoundland

More information

November 12, Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California

November 12, Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California November 12, 2014 Mr. Derek Sandgren Helm Properties 1520 Butte House Road, Suite 400 Yuba City, California 95993-2240 RE: Pre-Renovation Asbestos Survey Report 5862 Rupert Avenue, Marysville, California

More information

ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps)

ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps) Los Rios Community College District Sacramento City College ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps) GENERAL This addendum forms a part

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

Guide for Asbestos Management

Guide for Asbestos Management Guide for Asbestos Management May 2017 TABLE OF CONTENTS Introduction...2 Regulatory Information...5 Asbestos Management...7 1. Asbestos Inventory...8 2. Asbestos Control Plan...16 3. Training...24 4.

More information

Asbestos Elevator Industry Workshop November 25, 2015

Asbestos Elevator Industry Workshop November 25, 2015 Asbestos Elevator Industry Workshop November 25, 2015 BOB SWING CONTACT INFO EMAIL: Bob.Swing@ThyssenKrupp.com Phone: 604-499-5714 SOME ASBESTOS-CONTAINING MATERIALS Cement Pipes Cement Wallboard Cement

More information

FACILITY ASBESTOS MANAGEMENT PLAN

FACILITY ASBESTOS MANAGEMENT PLAN WASHINGTON ADVENTIST UNIVERSITY DEPARTMENT OF PUBLIC SAFETY DIVISION FACILITY ASBESTOS MANAGEMENT PLAN TAKOMA PARK CAMPUS REVIEWED and APPROVED BY: Patrick Farley WAU- V.P. of Finance Steven Lapham WAU-Executive

More information

Asbestos Awareness Program

Asbestos Awareness Program Safety Manual 1 of 9 Safety Manual Sect: 1.0 Purpose 2.0 Scope Rel. Date: Last Review: This program covers Ardent policy related to asbestos, either discovered or suspected in the workplace. Ardent recognizes

More information

TSI SAMPLE. Asbestos Producing Countries. Asbestos Uses. Asbestos Consuming Countries. Asbestos Uses. Training Services International, Inc

TSI SAMPLE. Asbestos Producing Countries. Asbestos Uses. Asbestos Consuming Countries. Asbestos Uses. Training Services International, Inc www.training.com Operations & Maintenance (OSHA Class III) Asbestos Training Course What questions will be answered? What is? Serpentine Chrysotile Where is found? How is used? Is banned? P.1 www.training.com

More information

Asbestos Management. Asbestos Health and Safety Training Environmental. (and other dutyholder responsibilities)

Asbestos Management. Asbestos Health and Safety Training Environmental. (and other dutyholder responsibilities) Asbestos Health and Safety Training Environmental Asbestos Management (and other dutyholder responsibilities) Presentation No.: BECL A058 Birmingham Wakefield Blackpool St Asaph (N. Wales) Matt Dawes CoCA

More information

Asbestos Management Program and Procedures

Asbestos Management Program and Procedures Asbestos Management Program and Procedures Department of Environmental Health and Safety Northern Illinois University 11/23/15 Review and Updates Date Reviewed by Changes Made 11/23/15 Mary Schlagel Annual

More information

Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016

Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016 Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016 1.0 Purpose This written program is intended to comply with both state and federal asbestos regulations. Asbestos containing

More information

Asbestos is the generic name that refers to six unique minerals: Chrysotile Amosite Crocidolite Anthophyllite Tremolite Actinolite PPT-SM-A 2018

Asbestos is the generic name that refers to six unique minerals: Chrysotile Amosite Crocidolite Anthophyllite Tremolite Actinolite PPT-SM-A 2018 Asbestos Asbestos is the generic name that refers to six unique minerals: Chrysotile Amosite Crocidolite Anthophyllite Tremolite Actinolite 2 These naturally occurring mineral fibers were widely used in

More information

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY ASBESTOS CONTROL PROGRAM September 22, 2006 Table of Contents 1.0 Introduction... 4 2.0 Purpose and Applicability... 4 3.0 Roles and Responsibilities... 5 3.1

More information

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 1 July 2014 Approved Plan Jon Fahie This, the University

More information

ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

ASBESTOS OPERATIONS & MAINTENANCE PROGRAM NEW MEXICO MILITARY INSTITUTE 101 WEST COLLEGE BOULEVARD ROSWELL, NM 88201 ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Pursuant to Asbestos standards OSHA: 29CFR1926.1101 Construction; & 1910.1001 General

More information

CLASS I AND II ABATEMENT PROJECT SUBMITTALS

CLASS I AND II ABATEMENT PROJECT SUBMITTALS 5.1 Pre-Work Submittals CLASS I AND II ABATEMENT PROJECT SUBMITTALS Abatement contractors shall submit the following in a bound notebook to AU or our designated representative at the mandatory pre-construction

More information

PRE-DEMOLITION ASBESTOS INSPECTION REPORT FOR VACANT RESIDENCE 326 NE 7 TH TERRACE OCALA, FLORIDA. Prepared for

PRE-DEMOLITION ASBESTOS INSPECTION REPORT FOR VACANT RESIDENCE 326 NE 7 TH TERRACE OCALA, FLORIDA. Prepared for ENVIRONMENTAL SERVICES, LLC PRE-DEMOLITION ASBESTOS INSPECTION REPORT FOR VACANT RESIDENCE 326 NE 7 TH TERRACE OCALA, FLORIDA Prepared for CITY OF OCALA REVITILIZATION STRATEGIES-CODE ENFORCEMENT DIVISION

More information

NARRATIVE REPORT 1.0 BUILDING INFORMATION 2.0 ASBESTOS SURVEY INFORMATION

NARRATIVE REPORT 1.0 BUILDING INFORMATION 2.0 ASBESTOS SURVEY INFORMATION NARRATIVE REPORT 1.0 BUILDING INFORMATION Bentson Bunker Fieldhouse was originally constructed in 1931; the building has had several renovations, notably, a 1976-1980 multi-phase renovation throughout

More information

ASBESTOS INSPECTION REPORT Completed in accordance with 40 CFR, and (a)(4)

ASBESTOS INSPECTION REPORT Completed in accordance with 40 CFR, and (a)(4) ASBESTOS INSPECTION REPORT Completed in accordance with 40 CFR, 763.86 and 763.85(a)(4) Assessment Completed for Clint Moore, ASLA Planning, Research and Development City of Florence 324 West Evans Street

More information

FINAL Asbestos Management Program University of Windsor 401 Sunset Avenue, Windsor, Ontario

FINAL Asbestos Management Program University of Windsor 401 Sunset Avenue, Windsor, Ontario FINAL Asbestos Management Program University of Windsor 401 Sunset Avenue, Windsor, Ontario Prepared for: University of Windsor 401 Sunset Avenue Windsor, Ontario, N9B 3P4 Attn: Danny A. Castellan, P.Eng.

More information

Asbestos Management Plan

Asbestos Management Plan Asbestos Management Plan Management Plan Statement The following management plan has been produced and will be implemented so that the risks associated with known or presumed asbestos containing materials

More information

Asbestos Code of Practice

Asbestos Code of Practice Revised date: 2010-06-26 Asbestos Code of Practice Issued date: 2009-07-21 Version: 1.0 Creator: Occupational Health 1.0 Purpose Custodian: H&S Programs & Projects The purpose of the Asbestos Code of Practice

More information

Asbestos-Containing Material and Hazardous Material Survey Summary Report

Asbestos-Containing Material and Hazardous Material Survey Summary Report Asbestos-Containing Material and Hazardous Material Survey Summary Report Site: Haas Park Fieldhouse PS1757 2404 North Washtenaw Street Chicago, Illinois 60647 Survey Date: January 15, 2010 PBCC Project

More information

ASBESTOS PROGRAM. C. Asbestos Containing Materials (ACM) are defined as any material or product which contains more than 1% (by weight) asbestos.

ASBESTOS PROGRAM. C. Asbestos Containing Materials (ACM) are defined as any material or product which contains more than 1% (by weight) asbestos. PAGE: 1 OF 14 I. PURPOSE ASBESTOS PROGRAM The Lake Charles Asbestos Program has been developed to establish work practices, engineering controls, training programs, industrial hygiene monitoring, and medical

More information

Asbestos / Lead Paint Management Plan

Asbestos / Lead Paint Management Plan Asbestos / Lead Paint Management Plan 2017 http://www.dshs.state.tx.us/asbestos/rules.shtm http://www.dshs.state.tx.us/elp/rules.shtm Prepared by the Environmental, Health and Safety Department 6300 Ocean

More information

ASBESTOS BUILDING INSPECTION

ASBESTOS BUILDING INSPECTION ASBESTOS BUILDING INSPECTION LOCATION: BURT HALL 2651 SW ORCHARD AVENUE CORVALLIS, OREGON 97331 NOVEMBER 28, 2008 FORENSIC ANALYTICAL PROJECT NO. PJ6263 PREPARED FOR: OREGON STATE UNIVERSITY 127 OAK CREEK

More information

Test Report: Asbestos Analysis of Bulk Materials by PLM via the NY State ELAP Method

Test Report: Asbestos Analysis of Bulk Materials by PLM via the NY State ELAP Method 031214474 Phone: (518) 453-0146 Received: 05/11/12 9:59 AM Analysis Date: Project: Test Report: Analysis of Bulk Materials by PLM via the NY State ELAP 198.1 Method Non- Sample Description Appearance %

More information

Asbestos Awareness Training Handout For Custodial/Housekeeping Workers and Class IV Asbestos Workers

Asbestos Awareness Training Handout For Custodial/Housekeeping Workers and Class IV Asbestos Workers This handout is provided to meet the requirements of the OSHA asbestos awareness refresher training for custodial and housekeeping workers and Class IV asbestos workers. This training allows you to: HEPA

More information

Asbestos Inspection Cover Letter

Asbestos Inspection Cover Letter Asbestos Inspection Cover Letter Date Issued: January 27, 2016 Site Name/Location Residential Structure 4 Cauthen Street Rock Hill, South Carolina Asbestos Inspection Performed For Hank Williams Right

More information

APPROACH FOR IMPLEMENTION OF HUD S LEAD SAFE HOUSING RULE REGULATIONS (24 CFR Part 35, Subpart H, )

APPROACH FOR IMPLEMENTION OF HUD S LEAD SAFE HOUSING RULE REGULATIONS (24 CFR Part 35, Subpart H, ) January 16, 2008 Mississippi Development Authority Homeowner Elevation Grant Program and Small Rental Assistance Program in Hancock, Harrison, Jackson, and Pearl River Counties, Mississippi APPROACH FOR

More information

Asbestos Management Plan. Approved by TRCA Strategy Committee: May 19, 2016

Asbestos Management Plan. Approved by TRCA Strategy Committee: May 19, 2016 Asbestos Management Plan Approved by TRCA Strategy Committee: May 19, 2016 Table of Contents 1.Objectives... 3 1.1 Purpose and Scope... 3 1.2 Elements of the Asbestos Management Plan... 4 1.3 Roles and

More information

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL 1st Edition January 2007 RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL GUIDANCE ON COMPLYING WITH THE OCCUPATIONAL HEALTH AND SAFETY (ASBESTOS) REGULATIONS 2003 The information presented in Recycling

More information

OSHA s Enforcement of Asbestos Standards in the Construction Industry

OSHA s Enforcement of Asbestos Standards in the Construction Industry Open Journal of Safety Science and Technology, 2014, 4, 157-165 Published Online December 2014 in SciRes. http://www.scirp.org/journal/ojsst http://dx.doi.org/10.4236/ojsst.2014.44017 OSHA s Enforcement

More information

OAK GROVE SCHOOL DISTRICT ASBESTOS PLAN

OAK GROVE SCHOOL DISTRICT ASBESTOS PLAN Authority and Scope Regulation: 29 CFR 1910.1001 Asbestos OAK GROVE SCHOOL DISTRICT ASBESTOS PLAN Scope: This Plan establishes the requirements for handling, maintenance, use, removal, and disposal by

More information

AHERA ASBESTOS INSPECTION & MANAGEMENT PLAN. for. Grounds Building 3644 Lee Road Shaker Heights, Ohio

AHERA ASBESTOS INSPECTION & MANAGEMENT PLAN. for. Grounds Building 3644 Lee Road Shaker Heights, Ohio AHERA ASBESTOS INSPECTION & MANAGEMENT PLAN for Grounds Building 3644 Lee Road Shaker Heights, Ohio March 2017 CONTENTS OF INSPECTION REPORT AND MANAGEMENT PLAN PART I BUILDING INSPECTION/REINSPECTION

More information

ASBESTOS REMOVAL CONTROL PLAN

ASBESTOS REMOVAL CONTROL PLAN APPROVED CODE OF PRACTICE // MANAGEMENT AND REMOVAL OF ASBESTOS ASBESTOS REMOVAL CONTROL PLAN This Appendix is a template of an asbestos removal control plan. It is designed to incorporate the elements

More information

Asbestos Survey Report

Asbestos Survey Report Asbestos Survey Report Downtown Duluth Old City Hall Block Buildings for renovation 3087 Main Street, 3097 Main Street, New Dawn Theater, 3530 W. Lawrenceville Street, Old City Hall/Church Duluth, Georgia

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

Asbestos/Lead Paint Survey

Asbestos/Lead Paint Survey Asbestos/ Survey At: Camp Lejeune Bldg. 500 Repair Indoor Physical Fitness Center Prepared for: The Walker Group Architecture Inc. PO Box 541 New Bern, NC 28563 PEI Project No.: Walker Group Project No.:

More information

CSBP Asbestos Management Plan

CSBP Asbestos Management Plan A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: CSBP ASBESTOS MANAGEMENT PLAN CSBP-GM-11-031-20 Version Number: 12.0.0 Date Revised:

More information

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 CONTENTS A. PURPOSE B. DESIGNATED RESPONSIBILITIES C. DEFINITIONS D. PROJECT SUBMITTAL PROCEDURE E. REQUIREMENTS

More information

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278 PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278 PREPARED FOR: Mr. Roberto Aguirre City of San Francisco DPW, SAR, BCM 1680 Mission Street San Francisco, California PREPARED

More information

What is Asbestos? Asbestos was also used in household items, such as: oven gloves ironing board pads simmer mats for stoves fire blankets.

What is Asbestos? Asbestos was also used in household items, such as: oven gloves ironing board pads simmer mats for stoves fire blankets. All About Asbestos Read this booklet to learn more about: identifying asbestos-containing material in your home the health risks of asbestos what you can do about asbestos. What is Asbestos? Asbestos is

More information

Asbestos Containing Materials Assessment 631 Fulton Avenue Spartanburg, South Carolina

Asbestos Containing Materials Assessment 631 Fulton Avenue Spartanburg, South Carolina Asbestos Containing Materials Assessment 631 Fulton Avenue Spartanburg, South Carolina Prepared for: Northside Development Group 410 Magnolia Street Spartanburg, South Carolina Prepared by: Apex Environmental

More information

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS 1. DESCRIPTION OF WORK: ATTACHMENT A RFP # 024-0-2016BH ASBESTOS ABATEMENT REQUIREMENTS The work includes pre-cleaning, repair and/or removal and disposal of friable and non-friable asbestos containing

More information

ASBESTOS MANAGEMENT PLAN PROCEDURE

ASBESTOS MANAGEMENT PLAN PROCEDURE ADMINISTRATIVE PROCEDURE Approval Date January 2011 Review Date 2016 Contact Person/Department Superintendent of Business Replacing All Previous Procedures Page 1 of 6 Identification BU-3565 ASBESTOS MANAGEMENT

More information

INTRODUCTION TO THE PROGRAM

INTRODUCTION TO THE PROGRAM INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information

More information

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f:

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f: VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA 02189 www.vertexeng.com p: 781.952.6000 f: 781.335.3543 EZRA BAKER ELEMENTARY SCHOOL/GYMNASIUM ASBESTOS ABATEMENT WORK PLAN ASBESTOS CONTAINING

More information

Report of. Asbestos Survey

Report of. Asbestos Survey Report of Asbestos Survey of Curtis Block and Marlowe Buildings 14501, 14505, 14509, 14511 & 14515 Detroit Avenue and 1412 Marlowe Avenue Lakewood, Ohio 44107 Prepared for City of Lakewood 12650 Detroit

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM California Institute of Technology ASBESTOS MANAGEMENT PROGRAM Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727 Fax: 626.577.6028

More information

Common Household Contaminants: The Hazards and the Laws

Common Household Contaminants: The Hazards and the Laws The National Center for Healthy Housing (NCHH) developed this summary to serve as a short guide for health and housing professionals on common household contaminants. It is not comprehensive. As a guide,

More information

Tim Nelson, Facilities Management's Asbestos Coordinator, 400 Donhowe Building Dan Allen, Associate Director, Recreation Sports, 108 Cooke Hall

Tim Nelson, Facilities Management's Asbestos Coordinator, 400 Donhowe Building Dan Allen, Associate Director, Recreation Sports, 108 Cooke Hall July 3, 2007 REPORT: Full Building Survey TO: Tim Nelson, Facilities Management's Asbestos Coordinator, 400 Donhowe Building Dan Allen, Associate Director, Recreation Sports, 108 Cooke Hall FROM: Bryan

More information

Comparison of the life safety elements of the 1997 UBC and the IBC 2000.

Comparison of the life safety elements of the 1997 UBC and the IBC 2000. Comparison of the life safety elements of the 1997 UBC and the IBC 2000. Introduction The Building Performance Research Institute s mission is primarily one of education on building safety and performance.

More information

PRE-DEMOLITION ASBESTOS SURVEY Curtis Park Ballpark and Pool 1901 NW 24 Avenue Miami, FL 33125

PRE-DEMOLITION ASBESTOS SURVEY Curtis Park Ballpark and Pool 1901 NW 24 Avenue Miami, FL 33125 PRE-DEMOLITION ASBESTOS SURVEY Curtis Park Ballpark and Pool 1901 NW 24 Avenue Miami, FL 33125 Prepared For: City of Miami Capital Improvements & Transportation Program 444 SW 2 nd Avenue, 8 th Floor Miami,

More information

The Building Codes A.R.E. Building Design and Construction Exam Prep

The Building Codes A.R.E. Building Design and Construction Exam Prep Know Thy Codes! The Building Codes Building Codes The Code of Hammurabi 4000bc Developed 19 th and 20 th c. Codes define what you can and can t do Allowable area and height based on degree of danger Fire

More information

CHAPTER 26 PLASTIC SECTION BC 2601 SECTION BC 2603 GENERAL FOAM PLASTIC INSULATION

CHAPTER 26 PLASTIC SECTION BC 2601 SECTION BC 2603 GENERAL FOAM PLASTIC INSULATION CHAPTER 26 PLASTIC SECTION BC 2601 GENERAL 2601.1 Scope. These provisions shall govern the materials, design, application, construction and installation of foam plastic, foam plastic insulation, plastic

More information

Bioscience Research Building

Bioscience Research Building Bioscience Research College Park, Maryland Presentation Agenda and Construction Features Analysis Analysis Research Features Presentation Agenda Construction Features: CM at Risk 2 year schedule (July

More information

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843)

Assessment Completed by: Asbestos Inspections, LLC 4686 Pee Dee Highway Conway, South Carolina (843) ASBESTOS INSPECTION REPORT 1814 PRINCE STREET 2-STORY Georgetown, South Carolina Asbestos Inspections, LLC Project # 2017-48 Performed in general accordance with SCDHEC regulation 61-86.1 along with OSHA

More information

780 CMR CHAPTER 34 EXISTING BUILDINGS STRUCTURES

780 CMR CHAPTER 34 EXISTING BUILDINGS STRUCTURES 780 CMR CHAPTER 34 EXISTING BUILDINGS STRUCTURES SECTION 3401 GENERAL 3401.1 Scope. Chapter 34 of the International Building Code 2009 is deleted in its entirety. The provisions of the International Existing

More information

Asbestos in the Home

Asbestos in the Home Asbestos in the Home This document will help you understand asbestos: what it is, its health effects, where it is in your home, and what to do about it. What Is Asbestos? Asbestos is a mineral fiber. It

More information

If the address on this form is different than the address of the building, submit a written explanation.

If the address on this form is different than the address of the building, submit a written explanation. ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: CHICAGO SCHOOL DIST 299 SCHOOL ID NUMBER: 14-016-2990-2270

More information

INTERIOR FINISHES CHAPTER 8

INTERIOR FINISHES CHAPTER 8 CHAPTER 8 INTERIOR FINISHES SECTION 801 GENERAL 801.1 Scope. Provisions of this chapter shall govern the use of materials used as interior finishes, trim and decorative materials. 801.2 Interior wall and

More information

International Proficiency Module Syllabus. IP405 - Management of Asbestos in Buildings

International Proficiency Module Syllabus. IP405 - Management of Asbestos in Buildings International Proficiency Module Syllabus IP405 - Management of Asbestos in Buildings Aim To provide candidates with practical knowledge and skills to manage asbestos in buildings and to provide a basic

More information

Building Codes and Ordinances ARC 227

Building Codes and Ordinances ARC 227 Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction 03.02.10 Instructor: Rick Staub, AIA Email: staub@pointonearchitects.com Phone: 860-434-7707 Fire Resistive Construction Passive

More information

Asbestos Survey. Site: Prepared for: Edmundson Elementary School Grayland Avenue, Norwalk, CA 90650

Asbestos Survey. Site: Prepared for: Edmundson Elementary School Grayland Avenue, Norwalk, CA 90650 Asbestos Survey Site: Edmundson Elementary School 15121 Grayland Avenue, Norwalk, CA 90650 Prepared for: Norwalk-La Mirada Unified School District 12820 Pioneer Boulevard, Norwalk, CA 90650 October 24th,

More information

ASBESTOS, PCB CAULKING & UNIVERSAL WASTE SURVEY REPORT

ASBESTOS, PCB CAULKING & UNIVERSAL WASTE SURVEY REPORT ASBESTOS, PCB CAULKING & UNIVERSAL WASTE SURVEY REPORT HUNTER COLLEGE - Hunter High School and Hunter Elementary School (The Campus Schools) HVAC UPGRADE 71 EAST 94 th STREET NEW YORK, N.Y. 10128 PREPARED

More information

Pre-Renovation Asbestos Survey

Pre-Renovation Asbestos Survey Pre-Renovation Asbestos Survey L640 Level 2 Remodel College Complex Los Medanos College Pittsburg, California November 23, 2016 Terracon Project No. R1167D98 Prepared for: Contra Costa Community College

More information

If the address on this form is different than the address of the building, submit a written explanation.

If the address on this form is different than the address of the building, submit a written explanation. ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: SCHOOL ID NUMBER: ADDRESS OF SCHOOL: CITY: CHICAGO

More information

HERRON Enterprises USA, Inc.

HERRON Enterprises USA, Inc. Phone (33) 763 9639 HERRON Enterprises USA, Inc. Fax (33) 763 9686 E-Mail Lennie.Herron@comcast.net Hazardous Materials*Mold*Asbestos*Lead Paint www.herron-enterprises.com Environmental Services*Industrial

More information

Crothers Environmental Group, LLC

Crothers Environmental Group, LLC , LLC Morrisville, Vermont 05661 Phone 802-888-1936 info@crothersiaq.com June 26, 2009 Mr. Joe Aja, Project Engineer State of Vermont - Department of Buildings & General Services 5 Perry Street, Suite

More information

Infrastructure. Asbestos Management Plan

Infrastructure. Asbestos Management Plan Infrastructure Asbestos Management Plan Contents... 1 Introduction... 3 Identification... 3 Asbestos Registers... 4 Risk management... 4 Training... 5 Removal or Disturbance... 5 Records Management...

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

Learn Charter School Excel Campus

Learn Charter School Excel Campus ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: SCHOOL ID NUMBER: ADDRESS OF SCHOOL: CITY: CHICAGO

More information

Asbestos Survey Report

Asbestos Survey Report > This report was produced in 5 seconds with PocketSurvey How long does it take you? Handheld Systems Ltd Your Address Your Town County, Post Code Email: youremail@yourdomain.com

More information

Limited Hazardous Materials Survey Report

Limited Hazardous Materials Survey Report Limited Hazardous Materials Survey Report Contra Costa Community College Applied Arts Building Chiller Replacement Project 2600 Mission Bell San Pablo, California RGA Project No: R1167404 June 29, 2016

More information

TRB Summer Conference June 15-18, 2008 Baltimore, Maryland DOT Practices for the Identification and Abatement of Asbestos in Bridges - TxDOT

TRB Summer Conference June 15-18, 2008 Baltimore, Maryland DOT Practices for the Identification and Abatement of Asbestos in Bridges - TxDOT TRB Summer Conference June 15-18, 2008 Baltimore, Maryland DOT Practices for the Identification and Abatement of Asbestos in Bridges - TxDOT Rodney Concienne, P.G. Terry Dempsey, P.G. Pollution Prevention

More information

HOW TO SAFELY REMOVE ASBESTOS

HOW TO SAFELY REMOVE ASBESTOS HOW TO SAFELY REMOVE ASBESTOS Code of Practice DECEMBER 2011 Safe Work Australia is an Australian Government statutory agency established in 2009. Safe Work Australia consists of representatives of the

More information

LIMITED ASBESTOS-CONTAINING BUILDING MATERIALS SURVEY. Wal-Mart # Highway 51 North Ripley, TN ATC Project Number

LIMITED ASBESTOS-CONTAINING BUILDING MATERIALS SURVEY. Wal-Mart # Highway 51 North Ripley, TN ATC Project Number LIMITED ASBESTOS-CONTAINING BUILDING MATERIALS SURVEY Wal-Mart #0097 628 Highway 51 North Ripley, TN 38063 ATC Project Number 30.75300.0612 Prepared for: Wal-Mart Stores, Inc. Ms. Vicki Ingram Store Planning

More information

1. Sign-in sheet from the Pre-Proposal Conference on April 19, 2017 at Atherton Elementary.

1. Sign-in sheet from the Pre-Proposal Conference on April 19, 2017 at Atherton Elementary. DATE: April 20, 2017 ARLINGTON INDEPENDENT SCHOOL DISTRICT 1203 W. Pioneer Parkway Arlington, Texas 76013 ADDENDUM II FROM: Tammy Craig Director Purchasing RE: CSP 17-79 Amos & Atherton Elementary Renovations

More information

Minimum Standards for Building Occupancy. Safety Resources

Minimum Standards for Building Occupancy. Safety Resources Minimum Standards for Building Occupancy 2017 Safety Resources Contents 1 Purpose... 1 2 Applicable To... 1 3 Scope... 1 4 Definitions... 1 5 Training... 2 6 Safety... 2 7 Equipment and Materials... 2

More information

Level 3 Award in Asbestos Air Monitoring and Clearance Procedures (HSG248 Sampling, Analysis and Clearance Procedures)

Level 3 Award in Asbestos Air Monitoring and Clearance Procedures (HSG248 Sampling, Analysis and Clearance Procedures) Level 3 Award in Asbestos Air Monitoring and Clearance Procedures (HSG248 Sampling, Analysis and Clearance Procedures) January 2016 Guided Learning Hours 30 Total Qualification Time 91 Ofqual Qualification

More information

UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT PLAN

UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT PLAN UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 1 15-02-05 First Issue Ian Oram HSMT 2 02-03-09 Revised to incorporate Control of Asbestos

More information

TABLE OF CONTENTS 4. PREPARATION, COMMUNICATIONS, AND CONTROLS

TABLE OF CONTENTS 4. PREPARATION, COMMUNICATIONS, AND CONTROLS TABLE OF CONTENTS SECTION PAGE NO. 1. INTRODUCTION... 1-1 1.1 Background... 1-1 1.2 Conceptual Site Model... 1-1 1.3 Plan Organization... 1-2 1.4 Certification... 1-3 2. SAMPLE COLLECTION, ANALYSIS, AND

More information

DP ASBESTOS MANAGEMENT

DP ASBESTOS MANAGEMENT DP 057 1997-12-03 ASBESTOS MANAGEMENT Table of Contents 1. Background 2. Policy 3. Scope 4. Definitions 5. Roles and Responsibilities 6. Guidelines 1. Implementation 2. Monitoring 7. Procedures 8. Compliance