ATTACHMENT A Sanitary Sewage Line Replacement Columbia County, Roadside Rest Site# 38, I-80 WB Project# Roadside Rest Grounds# 031R380

Size: px
Start display at page:

Download "ATTACHMENT A Sanitary Sewage Line Replacement Columbia County, Roadside Rest Site# 38, I-80 WB Project# Roadside Rest Grounds# 031R380"

Transcription

1 I. Base Bidding Requirements This is not a base bid project. II. Work Included The following items are site specific requirements of the project. Contractor to repair, replace and install the necessary materials to complete the work identified below. Remove and replace approximately 625 ft. of existing 6-inch diameter vitrified clay sanitary sewer pipe with 6 SDR 35 PVC sewer pipe from manhole No. 5 (located 10 out from rest area building) to manhole No. 3. Remove existing clay pipe at three (3) manholes, core bore if required and install flexible boot style connectors for the new PVC sew pipe installation. Reestablish vegetative ground cover in all areas of lawn disturbance. Materials o Sewer Pipe Polyvinyl chloride (PVC) with integral-bell gasketed joints, conforming to ASTM D-3034, SDR 35. o Fittings Conforming to the same applicable ASTM Specification requirements as specified for the pipe. o Joints Push-on with elastomeric gasket, ASTM D 3212, and ASTM F477 for gasket specifications. o Pipe Bedding Material AASHTO No. 8 (Penn DOT No. 1B) coarse aggregate conforming to PennDOT Publication 408, Section o Pipe-Manhole Connectors Sewer pipe to manhole connections shall be flexible, resilient, watertight connectors meeting the requirements of ASTM C-923, Resilient Connectors Between Reinforced Concrete Manhole Structures and Pipes. Connectors may be any of the following types: Flexible, watertight, banded-boot and compression type connectors with stainless steel expander ring/sleeve, similar to NPC Kor-N-Seal as manufactured by Trelleborg Pipe Seals Milford, Inc.: PS: Direct Drive by Press Seal Gasket Corporation or a Department approved equal. Waterstop grouting rings similar to NPC-Waterstop Grouting Ring as manufactured by Trelleborg Pipe Seals Milford, Inc.; WS-30 Waterstop by Press Seal Gasket Corporation or a Department approved equal. Page 1 of 8 08/23/2012

2 o Bonding Agent Two-component, 100% solids, moisture tolerant epoxy resin grouting/bonding agent similar to Sikadur Hi-Mod as manufactured by Sika Corporation; F 752 HydroEster by Fox Industries; Sonobond by Sonneborn Building Products or Department approved equal. o Non-Shrink Grout BASF Masterflow 713; Master Builders s Embeco 636; SiksGrout 212 by Sika Corporation or Department approved equal. Sanitary Sewer Construction o Take precaution to protect the public and property by furnishing and maintaining temporary fencing, barricades, lights, and other appurtenances as necessary. o Excavated material not reused for backfill shall become the property of the Contractor and be removed from the construction area and legally disposed. o Provide shoring as required in compliance with all applicable Occupational Safety & Health Administration (OSHA) regulations and safety provisions for excavation and trenching operations. Remove all shoring from excavations before backfilling. o The Contractor is solely responsible for the conditions and results of the excavation work. Disposition of Underground Utilities o Contractor is responsible to identify any overhead or underground utilities including all utility company owned or Department owned utilities. o Before beginning work, ascertain the existing underground utilities which may be encountered during trenching operations and verify their depth and location. Take precautions to protect and clear any such utilities within the work area. o Be advised of the following underground utility lines that are in close proximity to and parallel alignment with the existing sewer line. Primary electrical line to rest area building transformer Secondary electrical distribution line from rest area building to sewage treatment plant. Telephone service. o Comply with Pennsylvania Underground Utility Line Protection Law, PA Act 287 by telephoning Pennsylvania One Call System, Inc. at least three days prior to the start of excavation. o Adequately repair or replace any utilities damaged during the course of construction. Page 2 of 8 08/23/2012

3 Trench Excavation o Excavate the pipe trench true in alignment with that of the existing sanitary sewer line so as to permit the new pipe to be laid in the approximate center of the trench. Ensure the trench is wide enough to provide a free working space on each side of the pipe. Trench width from the trench bottom to a point 12 inches above the top of the outside barrel to the pipe shall not exceed 24 inches. o Remove the existing vitrified clay pipe and excavate to a depth of 6 inches below the pipe to allow for the placement of bedding material. If the trench foundation is yielding, over excavate and stabilize the trench. o Keep the trench free from water during installation operations. Pipe Bedding o Provide the replacement sewer pipe with a crushed stone aggregate bedding foundation placed on the bottom of the trench to a minimum depth of 6 inches and along the sides of the pipe to a depth on one-half the pipe diameter. o Bedding material shall provide adequate and uniform support under the pipe. Ensure that sufficient granular bedding material is worked under the haunching of the pipe to provide adequate side support. Pipe Installation o Construct the new 6 inch diameter sewer along the same uniform line and grade as that of the existing sewer line. Lay pipe with a firm and even bearing along the barrel of the pipe. o Commence laying the pipe beginning at the low point of system and proceeding upgrade with smooth, unbroken continuity of invert. Lay pipe with bell end upgrade. o Maintain the existing manhole inlet and outlet invert elevations. o Do not lay the pipe in water or when trench conditions or weather conditions are unsuitable for such work. Manhole Connections o Ensure the watertight connection of replacement sewer pipe to existing manholes. o Pipe-to-manhole connector installation: Install banded-boot and compression type connectors by core drilling the manhole in strict accordance with the manufacturer s specifications. Recore the manhole using a larger diameter hole to accept the required connector size recommended by the manufacturer for use with the new pipe. Page 3 of 8 08/23/2012

4 Position the water-stop grouting ring around the outside diameter of the pipe so that the ring will be in the middle of the manhole s wall thickness. Secure the ring to the pipe with stainless steel take-up pipe clamps in accordance with the manufacturer s specifications. Prepare the opening by thoroughly cleaning and applying a high-quality bonding agent to the opening. Apply and compact non-shrink grout around the water-stop and between pipe and opening, taking care to fill all voids. o All pipes are to be flush with the inside face of the manhole wall. Do not allow the pipe to protrude into the manhole trough. o Reshape the bottom of the manhole as necessary to accommodate the invert of the new sewer pipe and maintain the manhole channel flow line as a smooth continuation of the pipe. Testing o Before backfilling, inspect and test the sewer line. After each manhole-tomanhole section of sanitary sewer is replaced, plug the pipe manhole and perform a low pressure air test. o Tests shall be performed in accordance with the current provision of ASTM F using the time-pressure drop method. All 6 inch pipe sections tested shall not exceed a0.5 psig air pressure drop (from 3.5 to 3.0 psig) for a minimum of 2 minutes and 50 seconds. o All pipe sections failing the test shall be repaired or replaced and retested. Backfill o Backfill the pipe only after is it inspected, tested and accepted. o Use the same granular pipe bedding material for the initial backfill from the bedding (centerline of the pipe) to a depth of 12 inches above the top of the pipe. o Place the initial granular material backfill in uniform 6-inch layers and, using mechanical methods, thoroughly tamp and compact to eliminate the possibility of settlement, pipe misalignment, or damage to joints. o Backfill from 12 inches above the top of the pipe to the surface with suitable excavated trench material. o Use mechanical tampers to compact trench backfill material and consolidate the backfill in such a manner as to ensure minimal possible settlement. Page 4 of 8 08/23/2012

5 Topsoil, Seeding and Soil Supplements o Material Topsoil In accordance with Section of PennDOT Publication 408 Specifications. Seed Formula B in accordance with Section 804.2(b) of PennDOT Publication 408 Specifications. Soil Supplements Pulverized agricultural limestone and fertilizer in accordance with Section of PennDOT Publication 408 Specifications. o Seeding Operations Place and spread topsoil on the prepared areas to a uniform 4-inch depth. Rake topsoil and remove debris, foreign material and stones larger than 2 inches in any dimension. Final grade shall be reasonably free from rocks, roots and other debris. Do not place topsoil in a wet or frozen condition. Prepare areas for seeding by uniformly applying supplements. Blend the initial supplements into the soil as least 2 inches on top-soiled areas, by raking, disking, harrowing, or other acceptable methods. Apply soil supplements in accordance with Section 804.3(c) Publication 408 Specifications. Apply seed at the specified rates and sow uniformly on the prepared areas by broadcasting or hand seeding methods. Place mulch uniformly in a continuous blanket immediately after seeding is completed. END OF SECTION Page 5 of 8 08/23/2012

6 Submittals and final Deliverable items o The Department will provide the awarded contractor a complete breakdown of the required submittals based off of the System identified, I.E. Roofing System o Contractor to provide three (3) copies of the entire project documentation in three (3) ring Binders. o Binders to include the following items: Bid Documents & Specifications All project meeting minutes (pre-bid, pre-job, Interim, and Final inspection) Correspondence Submittals L&I approved Engineered Drawings (Paper/CD) L&I Building Permits, Inspection Logs, Occupancy Permit, Other-File Number is Certifications Certified Payrolls (Prevailing Wage rates) Waste receipts Photos Before, during and after o A sufficient amount of Photos is required for all phases of construction. Operation and Maintenance manuals Contractors Warranty Manufactures Warranty I. SUBMITTAL PROCEDURE A. Submit Two (2) copies of all items shown on submittal schedule except for "samples". B. Identify project number, project name and location, and contractor's name and address on all submittals. C. Provide space for review stamps of Contractor and Department. Put contractor stamp of approval on each item submitted. D. Revise and resubmit submittals as required, identify all changes made since previous submittal. Page 6 of 8 08/23/2012

7 E. No work shall be performed until all submittals are approved by the Department. Work performed prior to submittal approval is performed at the Contractor's risk and may be subject to repair, replacement or other corrective measures as deemed necessary by the Department with no additional contract time or money. F. Review of shop drawings will be general and for the limited purpose of checking for general conformance with the design; and shall not relieve the Contractor from the responsibility for proper fitting and construction of the work, nor from furnishing materials and work required by the Contract which may not be indicated on the shop drawings when reviewed. G. The submittals required by this contract are subject to reproduction for the Department's internal use only. By signature on this bid proposal, both the Contractor and the equipment manufacturer authorize the Department to reproduce any materials including printed literature and training aids, submitted in fulfillment of this contract. II. MANUFACTURER'S INSTRUCTIONS A. When specified in individual specification sections, submit manufacturer's printed instructions for delivery, storage, assembly, installation, start-up, adjusting and finishing, and maintenance, in quantities specified for product data. B. Identify conflicts between manufacturer's instructions and contract documents. III. MANUFACTURER'S CERTIFICATES A. When specified in individual specification sections or on submittal schedule, submit manufacturer's certificates to for review. B. Indicate that material or product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits and certifications as appropriate. C. Certificates may be recent or previous test results on material or product, but in all cases must be acceptable to Department. Page 7 of 8 08/23/2012

8 IV. SUBMITTAL SCHEDULE A. Abbreviations: SoSu - Source of Supply DeDa - Descriptive Data or Catalog Cuts ShDr - Shop or Installation Drawings CoCh - Color Chart Cert - Certificates Samp Samples B. Schedule: Description of items to be submitted SoSu DeDa ShDr CoCh Samp Cert 1. Line Item Cost Breakdown 2. Work Schedule 3. Aggregate Material (Bedding and Backfill) 4. Pipe and Fittings 5. Pipe to Manhole Connectors 6. Seeding & Soil Supplements 7. L & I Permit Documents 8. Waste Receipts 9. Digital Photos 10. Final Deliverables 3 ring binder Page 8 of 8 08/23/2012

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

SECTION STORM DRAIN

SECTION STORM DRAIN PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract

More information

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE SECTION 02632 POLYVINYL CHLORIDE (PVC) WATERLINE PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required, and install polyvinyl chloride (PVC) waterline,

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.

More information

***************************************************************************************************************

*************************************************************************************************************** 02735 WASTE WATER DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 22 14 00 ***************************************************************************************************************

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation

SECTION STORM DRAINAGE UTILITIES. B. Section : Site Restoration and Rehabilitation SECTION 33 40 00 STORM DRAINAGE UTILITIES 1. PART 1 GENERAL 1.1 RELATED WORK A. Section 31 23 00: Excavation and Fill B. Section 32 00 01: Site Restoration and Rehabilitation C. Special Conditions for

More information

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation. SECTION 312333 TRENCHING AND BACKFILLING PART 1 - GENERAL 1.1 SUMMARY A. Excavate trenches for new electric and telephone conduits, gas lines, and their appurtenances from at least 5 feet outside the building

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

D. Removal of existing storm sewerage pipe and drainage structures.

D. Removal of existing storm sewerage pipe and drainage structures. SECTION 33 40 00 - PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including General and Supplemental Conditions, Division B and other Division 1 Specifications

More information

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS. SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION STORM DRAINAGE AND STORMWATER MANAGEMENT

SECTION STORM DRAINAGE AND STORMWATER MANAGEMENT SECTION 322 - STORM DRAINAGE AND STORMWATER MANAGEMENT 322.01 DESCRIPTION Work includes all labor, material and equipment to construct storm drain systems and stormwater management facilities, including

More information

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction 1.00 DESCRIPTION 1.01 WORK INCLUDED: This work shall include the furnishing of all labor, equipment and materials necessary

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

SECTION UTILITY MANHOLES AND STRUCTURES

SECTION UTILITY MANHOLES AND STRUCTURES SECTION 33 05 14 UTILITY MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Precast reinforced concrete manholes and structures with tongue-and-groove joints with masonry transition

More information

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections. SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity

More information

INDUSTRIAL PIPE FITTINGS, LLC

INDUSTRIAL PIPE FITTINGS, LLC Page 1 of 9 SPIROLITE MUNICIPAL AND INDUSTRIAL ODOR CONTROL PIPING Municipal wastewater treatment plants, industrial processes and composting facilities can be assured of trouble free transport of foul

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

Summary of the 2011 Changes

Summary of the 2011 Changes The following is a list of amendments to the Residential Site Improvement s, N.J.A.C. 5:21, adopted in 2011. The Notice of Adoption of these changes appeared in the New Jersey Register on May 16, 2011.

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

Overview. Advanced Dual Wall Profile Construction. Superior Polypropylene Material

Overview. Advanced Dual Wall Profile Construction. Superior Polypropylene Material HP Storm Pipe 12 60 HP STORM pipe 12 60 FOR Storm applications Overview An addition to our proven line of pipe products, HP (High Performance) Storm is a high-performance polypropylene (PP) pipe for gravity-flow

More information

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation)

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) PART 1 GENERAL SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) 1.01 SCOPE This specification includes the materials and procedures required for the internal sealing of the frame-chimney

More information

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS SECTION 334100 - STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY Section Includes: 1. Pipe and fittings. 2. Drain Basin. 3. De-chlorination tablet feeder. 4. Non-pressure transition couplings.

More information

SECTION RIPRAP, BOULDERS, AND BEDDING

SECTION RIPRAP, BOULDERS, AND BEDDING SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and

More information

CHAPTER 6. Sanitary Sewer

CHAPTER 6. Sanitary Sewer CHAPTER 6 Sanitary Sewer A. Introduction All proposed developments, subdivisions, and buildings must have a properly designed and constructed sanitary sewer collection system. The system shall provide

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS

CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS Storm Sewer System: 1. Detention/retention of stormwater runoff shall be provided in accordance with the requirements of the DuPage County Countywide Stormwater

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES January 18, 2013 811.01 Conduit Description 811.02 Conduit Materials 811.03 Conduit Definitions

More information

901 - PIPE SEWERS COMPLETE IN PLACE

901 - PIPE SEWERS COMPLETE IN PLACE 901 - PIPE SEWERS COMPLETE IN PLACE 901.01 Description 901.02 Materials and Material Handling 901.03 Excavation 901.04 Limits as to Width of Trench 901.05 Unauthorized Excavation 901.06 Subgrade 901.07

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction. General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting

More information

TRENCH EXCAVATION AND BACKFILL

TRENCH EXCAVATION AND BACKFILL SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction Section 300 - Trench Excavation and Backfill TRENCH EXCAVATION AND BACKFILL PART - GENERAL.0 SECTION INCLUDES A. Trench Excavation

More information

Chapter 8 TECHNICAL SPECIFICATIONS FOR CONVEYANCE SYSTEMS

Chapter 8 TECHNICAL SPECIFICATIONS FOR CONVEYANCE SYSTEMS Chapter 8 8.01 General Provisions 8.02 Manholes and Structures 8.02.1 Materials 8.02.2 Workmanship on Manholes 8.02.3 Types of Connections 8.03 Catch Basins and Inlets (Storm only) 8.03.1 Materials 8.03.2

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

Special Provision No. 405F03 March 2005

Special Provision No. 405F03 March 2005 PIPE SUBDRAINS - Item No. VIDEO CAMERA INSPECTION Item No. Special Provision No. 405F03 March 2005 OPSS 405, February 1990, Construction Specification for Pipe Subdrains is deleted in its entirety and

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following: SEGMENTAL BLOCK RETAINING WALLS PART 1 - GENERAL 1.01 SECTION INCLUDES Segmental Block Retaining Walls 1.02 DESCRIPTION OF WORK Constructing segmental block retaining walls. 1.03 SUBMITTALS Comply with

More information

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and

More information

SECTION XXXX POLYMER CONCRETE PUMP STATIONS

SECTION XXXX POLYMER CONCRETE PUMP STATIONS SECTION XXXX POLYMER CONCRETE PUMP STATIONS PART 1 GENERAL 1.1 SUMMARY A. This specification shall govern for the furnishing of all work necessary for installation of polymer concrete pump stations to

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer

More information

ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION

ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION NEW CASTLE COUNTY DEPARTMENT OF LAND USE ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION For Permanent Structures, pursuant to Delaware Pond Code 378 and Delaware Sediment and

More information

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated.

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated. SECTION 221316 SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

ONE PIPE LENGTH MAX (REFER TO 1/4"/FT SLOPE (MIN) 5'-0" (MIN) OR 4" LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4"x6" REFER TO TYPICAL EXCAVATION,

ONE PIPE LENGTH MAX (REFER TO 1/4/FT SLOPE (MIN) 5'-0 (MIN) OR 4 LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4x6 REFER TO TYPICAL EXCAVATION, VENT CAP (MUSHROOM TYPE) SOLID CAP EXIST GRADE MIN BUILDING REFER TO NOTE #4 MIN CONCRETE SIDEWALK CURB OR EDGE OF SIDEWALK STREET CLEANOUT (REFER TO NOTE #3) VENT PIPE 4" PVC 6" PVC CLEANOUT CONCRETE

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 33 3400 STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

GWINNETT COUNTY STORM SEWER PIPE STANDARDS

GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.0 Standard Specifications GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.1 Unless otherwise specifically set forth herein or in the Gwinnett County Standard Drawings, all of the materials, methods of the

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

GENERAL CONSTRUCTION SPECIFICATIONS

GENERAL CONSTRUCTION SPECIFICATIONS GENERAL CONSTRUCTION SPECIFICATIONS PREPARED BY: CITY OF VALPARAISO ENGINEERING DEPARTMENT 166 LINCOLNWAY VALPARAISO, IN 46383 219-462-1161 Last Revision December 18, 2008 These specifications are intended

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

Section 1I-3 - Bioswales

Section 1I-3 - Bioswales BIOSWALES (Numbering pending) These specifications compliment the bioswale design portion of the Iowa Stormwater Management Manual in Chapter 2, Section 2I-3. Sections of the following documents, as referenced

More information

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1. Table of Contents Section 300 - Trench Excavation and Backfill Page No. Part - General.0 Section Includes.02 Description of Work.03 Submittals.04 Substitutions.05 Delivery, Storage, and Handling.06 Scheduling

More information

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 1.0 EXCAVATION AND FILL 1.1 GENERAL.1 The excavation or fill shall be made to provide proper grade, lines and crosssection for the laying of

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

SOLID WALL PVC SEWER PIPE

SOLID WALL PVC SEWER PIPE INSTALLATION GUIDE FOR SOLID WALL PVC TABLE OF CONTENTS INTRODUCTION: Introduction 3 Receiving 4 Unloading and Handling 5-6 Storage 7 Trenching 8 De-Watering 9 Field Cutting 10 Lowering Pipe into the Trench

More information

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert.

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert. SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION q Item meets

More information

SOLID WALL PVC SEWER PIPE

SOLID WALL PVC SEWER PIPE INSTALLATION GUIDE FOR SOLID WALL PVC SEWER PIPE TABLE OF CONTENTS Introduction 3 Receiving 4 Unloading and Handling 5-6 Storage 7 Trenching 8 De-Watering 9 Field Cutting 10 Lowering Pipe into the Trench

More information

SECTION FOUNDATION DRAINAGE

SECTION FOUNDATION DRAINAGE SECTION 33 41 13 SPEC WRITER NOTES: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

Section 401. PIPE CULVERTS

Section 401. PIPE CULVERTS 401.02 Section 401. PIPE CULVERTS 401.01. Description. This work consists of constructing pipe culverts of the size and class required, including excavation and backfill. 401.02. Materials. Provide materials

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

SECTION BITUMINOUS CONCRETE PAVEMENT

SECTION BITUMINOUS CONCRETE PAVEMENT SECTION 321216 BITUMINOUS CONCRETE PAVEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

SECTION WATER DISTRIBUTION

SECTION WATER DISTRIBUTION SECTION 33 10 00 WATER DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY 1.02 CODES A. Section Includes: 1. Underground water service piping, watermains and appurtenances. A. All work shall comply with the most

More information

A.2.a Random Riprap... Table

A.2.a Random Riprap... Table 3601 RIPRAP MATERIAL 3601.1 SCOPE Provide stone and filter layer material for use in random or hand-placed riprap, gabion, and revet mattress construction. 3601.2 REQUIREMENTS A Stones A.1 Quality Provide

More information

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 401 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING TABLE OF CONTENTS 401.01 SCOPE 401.02 REFERENCES 401.03 DEFINITIONS

More information

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The Work of this Section shall be all labour, materials, equipment and supervision necessary

More information

Michigan State University Construction Standards EARTHWORK PAGE SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS

Michigan State University Construction Standards EARTHWORK PAGE SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS PAGE 312300-1 SECTION 312300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014 1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,

More information

KANSAS CITY METROPOLITAN CHAPTER OF THE AMERICAN PUBLIC WORKS ASSOCIATION

KANSAS CITY METROPOLITAN CHAPTER OF THE AMERICAN PUBLIC WORKS ASSOCIATION KANSAS CITY METROPOLITAN CHAPTER OF THE AMERICAN PUBLIC WORKS ASSOCIATION CONSTRUCTION AND MATERIAL SPECIFICATIONS Section 2400 Seeding and Sodding DIVISION II CONSTRUCTION AND MATERIAL SPECIFICATIONS

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations. DURA-CRETE S-SERIES PRECAST CONCRETE WALL SPECIFICATIONS PART 1 GENERAL 1.01 SECTION INCLUDES A. Concrete Screen Wall Description: Work under this item shall consist of furnishing and erecting a wall in

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 852 SANITARY SEWER MANHOLES

San Antonio Water System Standard Specifications for Construction ITEM NO. 852 SANITARY SEWER MANHOLES San Antonio Water System Standard Specifications for Construction ITEM NO. 852 SANITARY SEWER MANHOLES 852.1 DESCRIPTION: This item shall govern the construction of standard sanitary sewer manholes complete

More information

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE SUGGESTED STANDARD SPECIFICATION January, 2012 Prepared by International Pipe Bursting Association Thanks to the following participants for the development

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

SANITARY GRAVITY SEWER LINES. A. Sanitary sewer lines, manholes, fittings, accessories, and bedding

SANITARY GRAVITY SEWER LINES. A. Sanitary sewer lines, manholes, fittings, accessories, and bedding PART 1 GENERAL 1.1 SECTION INCLUDES A. Sanitary sewer lines, manholes, fittings, accessories, and bedding B. Municipal sewer service connections and clean-out access C. Bore and jack casing D. Creek crossing

More information