ELECTRICAL SAFETY INSPECTION REPORT

Size: px
Start display at page:

Download "ELECTRICAL SAFETY INSPECTION REPORT"

Transcription

1 ELECTRICAL SAFETY INSPECTION REPORT AG s APPARELS LIMITED. Plot No. A/1&2 Block-B, BSCIC I/A Fouzderhat, Sagarika Road, Dhaka-1207, Bangladesh Factory List: 1. AG s Apparels Limited. Inspected by: Sherub Tenzin Report Generated by: Sherub Tenzin Inspected on July 22 th 2014

2 SUMMARY factory building was constructed in 1983 and started production in The six (G+5) storied building was constructed as an industrial structure with total floor area of 90,000sq.ft and 21 meters tall. Factory is established in first and second floor, and the building is fully occupied by the factory from first floor to roof. There are no separate sheds other than the main building. There were 350 workers in the factory during the inspection. The building was approved for industrial purpose and the factory during survey, had about 4,446 Workers working on regular basis The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd. (WEC). The purpose of the survey was to identify significant electrical safety issues and to provide recommendations for remediation based on applicable standards specified by the Accord. The scope of this initial electrical safety inspection was limited to the review and identification of major electrical safety issues. The inspection did not include identification of minor deficiencies, which will be further addressed as part of follow-up inspections. Table below summarizes the major electrical safety issues identified during the inspection. Recommendations have been provided to address each issue. An implementation schedule shall be developed by the factory to remediate each of the findings. The Specific timing of improvements, including any requested extensions due to design / installation Constraints shall be submitted to the Accord for approval. Page 2 of 13

3 FINDINGS AND RECOMMENDATIONS FINDING NO: E- 1 CATEGORY: DESIGN, DRAWINGS & RECORDS 1. As-built electrical SLD, wiring layout designs and drawings, machine layouts are prepared 2. Thermo graphic scanning of the entire electrical system has not been performed 3. Insulation resistance test of electrical equipment is not performed 4. Electric safety program is not initiated 1. Any changes in load, protection system, conductors, Generation and supply system must be reflected in the As-built SLD and drawings. 2. Thermo graphic scanning of the entire electrical system must be performed on tri-annual basis and recorded 3. Insulation resistant test of all the cables must be performed once every 5 year cycle and recorded 4. Electrical safety training and awareness program for the electrical personal and workers must be initiated and recorded REMEDIATION TIMEFRAME: 10 WEEKS FINDING NO: E- 2 CATEGORY: SERVICE LINE Drop out fuse replaced by wire. Cartridge fuse unit must be fitted with cartridge fuses only. Fix the transformer properly on its frame and fix with nuts and bolts. FINDING NO: E- 3 CATEGORY: DISTRIBUTION PANEL Page 3 of 13

4 Cables are not supported and arranged haphazardly. Cable tray and riser with protective metal cover must be installed to support the cables laid haphazardly. Fix the panel enclosure to protect the control devices inside the panel. Rearrange the cables in tray and riser through proper route. REMEDIATION TIMEFRAME: 5 WEEKS Broken panel door with cables laid on the floor.. FINDING NO: E- 4 CATEGORY: DISTRIBUTION PANEL Inadequate space between the panels. Remove the obstacles and make clearance of at least 1 meter in front of the panel for regular inspection and maintenance work. Reorient the panel location for cable route and support. Inadequate space between the REMEDIATION TIMEFRAME: 3 WEEKS FINDING NO: E- 5 CATEGORY: DISTRIBUTION PANELS Panel baseplate not installed to allow cable entry. Page 4 of 13

5 Install base plate of the panel and make hole into it then fit cable gland (required sized) for cable entry and exit to the panel and seal all the unused openings by suitable means to make the panel dust and vermin proof. Install cable tray/riser with rigid cover for cables exiting from the panel. Install base plate with supporting accessories for cable. Dust and lint deposited inside the trench and keep the trench clean.. REMEDIATION TIMEFRAME: 3 WEEKS Cable haphazardly arranged while exiting the panel FINDING NO: E- 6 CATEGORY: SWITCHBOARD & PANEL Cables and capacitors inside the PFI panel not arranged and supported properly. Install cable tray along the side frame of the panel and arrange cable in it with proper dressing and terminate to the busbar. Re-route the cable terminated to busbar. Remove the wooden support for the capacitor at the base and install base plate for support and rigid fixture of capacitor. Page 5 of 13

6 Ply board replacing the baseplate and supporting capacitor installed inside the panel. FINDING NO: E- 7 CATEGORY: SWITCHBOARD & PANEL Inadequate working space around panels. Every item of installation shall be arranged so as to facilitate its operation, inspection, maintenance & access. Access of the DB must be kept obstacle free for easy operation & maintenance. REMEDIATION TIMEFRAME: 5 WEEKS Panels installed inside the congested main distribution room. FINDING NO: E- 8 CATEGORY: SWITHBOARD & PANEL Cable trench filled by sand. Remove the sand from trench and install checkered plate to cover the opening. Arrange the cables with support and install gland while entering the panel. PRIORITY: P3 Page 6 of 13

7 Cable trench filled by sands in main distribution room. FINDING NO: E- 9 CATEGORY: SWITCHBOARD & PANEL Base plate and to cover removed for cable entry. Install base plate and top cover with provision for installing gland for cable. Use required size of gland for cable to avoid stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. PRIORITY: P3 Cables and panels without adequate space inside the main distribution room. Page 7 of 13

8 FINDING NO: E- 10 CATEGORY: DISTRIBUTION PANELS Neutral conductor bypassed. Install TPN (Triple pole Neutral) MCCB to connect the neutral conductor at MCCB terminal. Neutral conductor must pass through the control device to be controlled. Neutral conductor bypassed and jointed with nuts and bolts. FINDING NO: E- 11 CATEGORY: CABLE & SUPPORTS Cables supported in sanitary pipes partially exposed. The PVC pipe must be used for surface wiring which should be continuous through-out its length and properly supported (clamped with saddle, at regular interval of 600 mm). The conduit shall run vertically or horizontally, shall never at angle. PRIORITY: P3 REMEDIATION TIMEFRAME: 3 WEEKS Feeder line protected in sanitary pipe and dropped in main distribution room. Page 8 of 13

9 FINDING NO: E- 12 CATEGORY: CABLE & SUPPORTS Cables and wires exiting through the wall are not supported and protected. Install cable tray to support the cables exiting from wall. Provide non-combustible cover to protect cable from mechanical and physical injury. Cables and wires should be properly arranged inside the cable tray for maintenance and rewiring. REMEDIATION TIMEFRAME: 7 WEEKS Cables exiting to production floor are not supported and protected. FINDING NO: E- 13 CATEGORY: GENERATOR ROOM Generator battery placed on the concrete floor. Generator Battery bank should be placed inside the steel frame (battery rack) with protective cover. Relocate the battery in safer place. REMEDIATION TIMEFRAME: 1 WEEKS Generator and battery installed in front of the door. Page 9 of 13

10 FINDING NO: E- 14 CATEGORY: CABLE & SUPPORTS Panel base plates are open and cables not supported. Panel base plates must be installed and cable(s) entering panel must be firmly fixed with cable gland. Cable terminating at Generator output terminal box must be supported on covered cable tray installed on at safe location. REMEDIATION TIMEFRAME: 1 WEEKS Generator output cables terminated without baseplate and support. FINDING NO: E- 15 CATEGORY: CABLE & SUPPORT Generator output cable protected in flexible pipe without support. Rewiring must be done with proper cable layout. Cables must be supported on tray/riser with protective cover. Cables may be protected in rigid conduit laid over the floor. The conduit shall run vertically or horizontally, shall never at angle. Cable without support entering production floor. Cable exiting the wall without sealing and protective support. Page 10 of 13

11 FINDING NO: E- 16 CATEGORY: CABLE & SUPPORT Wires supported on the wooden tray. Wooden tray must be replaced by aluminum/gi tray or duct. Wires supported on the tray must be arranged inside the duct and covered properly to protect from mechanical injury and dust. Combustible storage materials must be relocated in safer place. PRIORITY: P1 Wooden duct wiring done in the storage room without proper support and protection for wires laid haphazardly and tied to the duct. REMEDIATION TIMEFRAME: 7 WEEKS FINDING NO: E- 17 CATEGORY: CABLE & SUPPORT Cables from distribution panel are protected in wooden cable duct. Remove and replace the wooden cable duct and install non-combustible duct to protect and support the cables running to various floors. Lighting fixtures must be independently supported on the supporting structure with seismic bracing. REMEDIATION TIMEFRAME: 5 WEEKS PFI panel placed temporarily on floor in substation room Page 11 of 13

12 FINDING NO: E- 18 CATEGORY: CABLE & SUPPORT Lighting fixture tied to aluminum channel for support. Re-fix the lighting fixture to the supporting structure rigidly by removing the tie. Supporting structure may be installed independently for light with seismic bracing. Lighting supporting frame tied to aluminum channel for support. FINDING NO: E- 19 CATEGORY: SWITCHBOARD & PANEL Control devices fixed on the wall without enclosure. Replace the semi enclosed re-wire able fuses with MCB and put inside the metallic enclosure. PRIORITY: P1 PFI panel placed temporarily on floor in substation room FINDING NO: E- 20 CATEGORY: SWITCHBOARD & PANEL Inadequate spacing in front of panel. (less than 1m) Every item of installation shall be arranged so as to facilitate its operation, inspection, maintenance & access. Access of the DB must be kept obstacle free for easy operation & maintenance. REMEDIATION TIMEFRAME: 5 WEEKS Inadequate space in front of the panel inside the production floor. Page 12 of 13

13 FINDING NO: E- 21 CATEGORY: COMPRESSOR ROOM Compressor machine supported on wheel. Compressor machine mounted on wheel must be anchored or wheel must be locked to prevent from trolling. Remove the combustible material store inside the room. Combustible materials stored near the machine. REMEDIATION TIMEFRAME: 3 WEEKS Machine supported on the wheel. FINDING NO: E- 22 CATEGORY: SWITCHBOARD & PANEL Inadequate spacing in front of panel. (less than 1m) Every item of installation shall be arranged so as to facilitate its operation, inspection, maintenance & access. Access of the DB must be kept obstacle free for easy operation & maintenance. Panel installed inside the storage room with inadequate space at rear and side of the panel. REMEDIATION TIMEFRAME: 5 WEEKS Page 13 of 13

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT M/S. PROUD TEXTILE Plot 31/A, BSCIC Industrial Estate, Fatullah, Narayanganj, Bangladesh Factory List: 1. Inspected by: Pema Wangdi Report Generated by: Pema Wangdi

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ABIR FASHIONS Kutubail, Fatullah (Post Office Road), Narayangonj, Bangladesh Factory List: 1. Inspected by: Pema Wangdi & Mamun Report Generated by: Pema Wangdi Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FIRST WEAR LMITED 68/Y, Sagarika Road, Pahartoli, Chittagong, Bangladesh Factory List: 1. Inspected by: Moin Hasan Report Generated by: Moin Hasan Inspected on August

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT Zirabo Bazar, Ashulia, Savar, Dhaka, Bangladesh Factory List: 1. Inspected by: Khan & Tapu Report Generated by: Khan Inspected on Feb 6 th 2015 SUMMARY factory building

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. SREERAMPUR, DHAKA, BANGLADESH Factory List: Graphics Textiles Limited Inspected on May 20, 2014 SUMMARY Graphics Textiles Limited is located in Sreerampur, Dhaka. Reportedly,

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. Plot # B-32,BSCIC I/E,Tongi,Gazipur Factory List: 1. Kento Asia Limited. Inspected on May 15, 2014 SUMMARY Kento Asia Ltd. factory is established in a rented premises

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT BOVS APPARELS LTD. JAMUR MUCHIPARA, HEMAYETPUR, SAVAR, DHAKA, BANGLADESH Factory List: 1. BOVS APPARELS LTD. Inspected on April 13, 2014 SUMMARY The Bovs Apparels Ltd

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ACTIVE COMPOSITE MILLS LTD. Dewan Idris Road, Zirabo, Ashulia, Savar, Dhaka, Bangladesh Factory List: 1. Active Composite Mills Ltd. Inspected by: Hemlal Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT K.L FASHION LTD. 75/1, Mudafa West, Master Bari, Tongi, Gazipur, Bangladesh Factory List: 1. Inspected by: Jobair Ibna Abdul Alim Report Generated by: Jobair Ibna Abdul

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SINCERE KNIT GARMENTS LIMITED UNIT-1 East Isdair, Chandmari, Fatullah, Narayangonj, Bangladesh Factory List: 1. Unit-1 2. Fakir Knit Ltd. Inspected by: Sherab Dorji

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FRESH FASHION WEAR LTD. 638, Sharifpur, P.O-National University, Gazipur Sadar, Bangladesh Factory List: 1. Passion Apparels and Wears Ltd. 2. Inspected by: Jobair Ibna

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT LIBAS TEXTILES LTD., Mouchak, Kaliakoir, Gazipur, Bangladesh Factory List: 1. Libas Textiles Ltd. Inspected on April 6, 2014 SUMMARY The Libas Textiles Ltd., factory

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. Sumilpara, Adamjee Nagar, Shiddirgonji, Narayangonj, Bangladesh Factory List: 1. Moonlux Kinit Garments Limited. 2. West knit Wear Limited. 3. West Fashion. 4. Moonlus

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. KAROTOA APPARELS LTD., TATKHANA ROAD, DHAKA, BANGLADESH. Factory List: 1. Inspected on May 14, 2014 ELECTRICAL SAFETY INSPECTION REPORT. KAROTOA APPARELS LTD., TATKHANA

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT TARATEX (BD) LTD. Plot 23/1, Sataish Road, Tongi, Gazipur, Bangladesh Factory List: 1) Taratex (BD) Ltd. 2) S. P. M Design Ltd. Inspected by : Luv Kumar Chhetri Report

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AKH APPARELS LIMITED 128 Hemayetpur, AKH Tower, Savar, Dhaka-1340, Bangladesh. Factory List: 1. AKH Apparels Limited Inspected by: Deonarayan Khatiwara Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADHUNIK POSHAK SHILPA LIMITED Civil Engineer Tower, Mirpur, Dhaka, Bangladesh Factory List: 1. Adhunik Poshak Shilpa Ltd. 2. Crazy Fashions Ltd. 3. Kazipur Fashion Ltd.

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT METRO KNITTING & DYEING MILLS LTD.(FACTORY-02), CHARBAG, ASHULIA, SAVAR, DHAKA, BANGLADESH Factory List: 1. Inspected by: Younten Report Generated by: Das Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT MAHID APPAREL LTD. Nowpara, Madhabdi, Narsingdi, Bangladesh Factory List: 1. MAHID APPAREL LTD. Inspected by: Nazmul Huda Report Generated by: Nazmul Huda Inspected

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FASHION FORUM LTD. 53-54, Diakhali, Zamgara, savar, Dhaka, Bangladesh. Factory List: 1. Fashion Forum Ltd. 2. IDS Washing Ltd. Inspected by: Karma Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. House 8 & 10, Road 3, Section 7, Mirpur Industrial Area, Dhaka, Bangladesh Factory List: 1. Alliance Garments Ltd. Inspected on May 5, 2014 ELECTRICAL SAFETY INSPECTION

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT AHMED FASHIONS 34/1, Darus Salam Road (Technical), Mirpur-1, Dhaka, Bangladesh. Factory List: 1. Inspected by: Yang Generated by: Yang Inspected on 06 March 2015 SUMMARY

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ALIF GARMENTS Ltd, Dhaka, Bangladesh Prepared for: JANUARY 14, 2014 Alif Garments Ltd. PAGE 1 SUMMARY The seven-story factory housing Alif Textiles Ltd. & Hexa Garments

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT (1ST FLOOR BOTH WINGS) CHITTAGONG EXPORT PROCESSING ZONE SOUTH HALISHAHAR, CHITTAGONG Factory List: 1. 2. Regency Garments Ltd. 3. ABC Camp Inspected on May 10, 2014

More information

ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH

ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH ELECTRICAL SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH January 14, 2013 Redpoint Jackets Ltd. PAGE 1 SUMMARY The four-story factory housing Redpoint Jackets Ltd. located in Dhaka Export

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th) Factory Name Address Shashongaon, Plot - S, A-646, Enayet nagar, Fatullah,Narayanganj Factory ID 9468 Electrical Safety dates Initial Date 07/07/2014 20/09/2016 Date of 5 th Follow Up Report Received Date

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT, SOUTH VANGNAHATI, SREEPUR, GAZIPUR, BANGLADESH. Factory List: 1. Hams Garments Ltd. Inspected on April 03, 2014 ELECTRICAL SAFETY INSPECTION REPORT, GAZIPUR, BANGLADESH

More information

ELECTRICAL SAFETY INSPECTION REPORT.

ELECTRICAL SAFETY INSPECTION REPORT. ELECTRICAL SAFETY INSPECTION REPORT. ANTIM KNIT COMPOSITE LTD., Barpa, Rupshi, Rupgonj, Narayangonj, Bangladesh. Factory List: 1. Antim Knit Composite Ltd. 2. Antim Knitting & Finishing Ltd. Inspected

More information

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th)

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (4th) Factory Name Address Joyna Bazer Road, Jamirdia, Valuka Factory ID 9504 Electrical Safety dates Initial Date 06/07/2014 Date of 5 th Follow Up Report Received Date 07/27/2015 Date of 6 th Follow Up Date

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Details of technical leaflets/write-up on various pieces of equipment.

Details of technical leaflets/write-up on various pieces of equipment. Details of technical leaflets/write-up on various pieces of equipment. (1) Insulator Designs: The insulators are provided in one, two, three, or four insulator designs per location and spaced to provide

More information

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS DAIMLERCHRYSLER MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS ISSUE DATE: 5/1/90 EFFECTIVE DATE: 2/4/92 REVIEW DATE:

More information

SECTION GROUNDING

SECTION GROUNDING SECTION 16450 GROUNDING PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies general grounding and bonding requirements of electrical and telecommunication installations for personnel safety, equipment

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 48 (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.01 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for

More information

ANY SPECIFICATION DRAWINGS OR DATED PRIOR TO SEPTEMBER 2015 WILL NOT BE HONORED.

ANY SPECIFICATION DRAWINGS OR DATED PRIOR TO SEPTEMBER 2015 WILL NOT BE HONORED. November 30, 2015 Dear STEMC Member and Contractors, Over the years, STEMC has made many changes to its member requirements for new services and specifications associated with those requirements. As a

More information

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016 Method Statement BLOCK WORK Civil Works 6/26/2016 The purpose of this Work Method Statement for Block Works (Concrete Masonry Units) is to outline and describe in detail the procedure such as setting and

More information

SEISMIC RESTRAINT SYSTEM

SEISMIC RESTRAINT SYSTEM 1. GENERAL 1.1. Description: SECTION 16012 SEISMIC RESTRAINT SYSTEM 1.1.1. This specification covers design and installation of seismic bracing and anchorage required for conduit, cable tray, bus duct,

More information

NEUTRAL GROUNDING TRANSFORMERS INSTALLATION AND MAINTENANCE INSTRUCTIONS

NEUTRAL GROUNDING TRANSFORMERS INSTALLATION AND MAINTENANCE INSTRUCTIONS 1 Table of Contents SECTION 1 Unpacking... 3 1.1 Shipping... 3 1.2 Receiving... 3 SECTION 2 Installation... 3 SECTION 3 Inspection... 4 SECTION 4 Connection... 4 4.1 Neutral Lead... 5 4.2 Ground Lead...

More information

T. SUNDUPALLI BRANCH (04427)

T. SUNDUPALLI BRANCH (04427) STATE BANK OF INDIA T. SUNDUPALLI BRANCH (04427) REGION 2, KADAPA RURAL TIRUPATI (A.O) ELECTRICAL WORK BILL OF QUANTITIES SL. NO. DESCRIPTION QTY. UNIT RATE AMOUNT Rs. Rs. 1 Supply, installation, testing

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF SIGN LUMINAIRES

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF SIGN LUMINAIRES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 612 SEPTEMBER 1984 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF SIGN LUMINAIRES 612.01 SCOPE 612.02 REFERENCES 612.03 Not Used 612.04 Not Used

More information

Cutouts and Fuse Links Equipment to protect against faults and over-current conditions on power distribution systems. Open-Type Cutouts Linkbreak Cutouts Loadbreak Cutouts Cutout-Arrester Combinations

More information

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC).

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC). SECTION 16111 CONDUITS PART 1 - GENERAL 1.01 DESCRIPTION A. General: Provide conduits, complete, as shown, specified or required per Contract Documents. Principal items include: 1. Rigid aluminum conduit.

More information

SECTION BUSWAYS

SECTION BUSWAYS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 25 11 BUSWAYS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable to the section and

More information

PREPARING RESIDENTIAL PROPERTY FORTHE HOUSING HABITABILITY INSPECTION

PREPARING RESIDENTIAL PROPERTY FORTHE HOUSING HABITABILITY INSPECTION CITY OF LOS ANGELES HOUSING DEPARTMENT HABITABILITY INSPECTION PROGRAM CODE ENFORCEMENT UNIT 3550 Wilshire Boulevard, 15 th Floor Los Angeles, CA 90010 PREPARING RESIDENTIAL PROPERTY FORTHE HOUSING HABITABILITY

More information

OVERHEAD SERVICES - SECONDARY

OVERHEAD SERVICES - SECONDARY OVERHEAD SERVICES - SECONDARY Contents - Overhead Services... O-1 General Requirements for Overhead Service... O-2 Names of Parts for Overhead Service... O-3 Service Attachment on an Unguyed Service Mast...

More information

SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR

SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR FINANCIAL BID Item DSR Item Description Qty Units No No. Total 1.1.1 Excavating trenches of

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

SECTION EARTHING AND EARTH FAULT PROTECTION

SECTION EARTHING AND EARTH FAULT PROTECTION SECTION 16660 PART 1 - GENERAL 1.01 DESCRIPTION A. The work to be performed includes, but is not necessarily limited to, all work involved with the construction and assembly of a complete electrical earthing

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

Duke Energy Carolinas Distribution Construction Standards Reference Guide

Duke Energy Carolinas Distribution Construction Standards Reference Guide Duke Energy Carolinas Distribution Construction Standards Reference Guide The Duke Energy Carolinas (DEC) Distribution Construction Standards are available on the My Duke Energy Contractor Portal. Access

More information

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein. 16470 PANELBOARDS ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 26 24 16 An optional keynote to

More information

SECTION I -- IRONWORK

SECTION I -- IRONWORK SECTION I -- IRONWORK CONTENTS PAGE 1. GENERAL... I-2 1.1. Introduction... I-2 2. REQUIREMENTS... I-2 2.1. General... I-2 2.2. Auxiliary Framing... I-2 2.3. High Seismic Risk Zone Requirements... I-3 2.4.

More information

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment

More information

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION E11 : General Electrical Earthing and LIGHTNING Protection PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION 1 2009-05-12 Review of Mechanical / Electrical and Control

More information

CHAPTER 5 METERING REQUIREMENTS

CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS 5.1 General 1. All installations connected to, or intended to be connected to HK Electric s supply of electricity must comply with HK Electric

More information

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. AFC Cable Systems, Inc. Product Specification This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. SECTION 260519.13 METAL CLAD CABLE-MC

More information

TEMPORARY METER POLE INSTALLATION

TEMPORARY METER POLE INSTALLATION TEMPARY METER POLE INSTALLATION MEMBER PROVIDED Location to be made by REMC within 50' of our transformer or existing service Temporary pole to be properly braced 24" 3 wire weatherhead (located 24" from

More information

Price Bid Estimate of,electrification Voice, Data cabling works for B.O.I VARACHHA Branch Item Amount Electrification Voice & Data Cabling Works Total amount RS RS. RS./- Estimate. for electrification

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin March 2014 CEC-12 [rev-6] Page 1 of 6 CANADIAN ELECTRICAL CODE SUBJECT: Section 12 Wiring Methods Conductors General Insulation Thickness on Conductors Used in Ungrounded

More information

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard PART 1 GENERAL 1.1 Scope A. The intent of this specification is to provide power control for the parallel operation of generator

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS SECTION 26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Kaf-Tech Product Specification

Kaf-Tech Product Specification Kaf-Tech Product Specification This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. SECTION 260519.13 METAL CLAD CABLE-LUMINARY CABLE

More information

Rate (Rs.) Description Unit Qty PART I : REMOVING & RESHIFTING OF EXISTING. Amount (Rs.) INSTALLATION

Rate (Rs.) Description Unit Qty PART I : REMOVING & RESHIFTING OF EXISTING. Amount (Rs.) INSTALLATION REVISED BOQ FOR ELECTRICAL WORK FOR ESTABLISHMENT OF MUSEUM AT BANK'S BUILDING AT 70/80, M.G. ROAD, FORT, MUMBAI Note : The rates quoted shall include supply, installation, testing, commissioning of complete

More information

8. REVENUE METERING. Operational Excellence Model. 8.1 Introduction

8. REVENUE METERING. Operational Excellence Model. 8.1 Introduction 8. 8.1 Introduction The purpose of this section is to outline requirements of the customer, as set forth herein by PSEG Long Island, as they pertain to Electric Revenue Metering at Primary and Secondary

More information

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID

ELECTRICAL WORKS RELATED TO AC & UPS OF CMP GOC & IAD, LINGAMPALLY, HYDERABAD IN TWO BID SYSTEM THROUGH E-TENDER PRICE BID SBI INFRA MANAGEMENT SOLUTIONS PVT.LTD. 3 rd Floor, Local Head Office,Bank Street, Koti, Hyderabad- 500095 On behalf of On behalf of On behalf of Cash Management Product GOC (CMP GOC) & Internal Audit

More information

OVERHEAD SERVICE. Table of Contents - Section 400

OVERHEAD SERVICE. Table of Contents - Section 400 OVERHEAD SERVICE Table of Contents - Section 400 PARAGRAPH 400.0 OVERHEAD SERVICES (0-600 VOLTS)... 1 400.1 GENERAL 1 400.2 IDENTIFICATION OF CONDUCTORS. 1 400.3 MAXIMUM SERVICE ENTRANCE CONDUCTOR SIZE

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: ARCHITECT/ENGINEER ADDRESS:

More information

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents DIVISION 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN Contents 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION 13 00 60 LIST OF FIGURES... 6 Page 1 of 6 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN 1. General

More information

AS/NZS 3000: 2018 Changes to Wiring Rules Standard

AS/NZS 3000: 2018 Changes to Wiring Rules Standard BUILDING SERVICES Ref: BCA 19-01 Current at January 2019 AS/NZS 3000: 2018 Changes to Wiring Rules Standard The new edition of AS/NZS 3000 Wiring Rules Standard (Electrical Installations) was published

More information

UNDP / PAPP OFFICE BUILDING RAMALLAH HVAC WORKS

UNDP / PAPP OFFICE BUILDING RAMALLAH HVAC WORKS UNDP / PAPP OFFICE BUILDING RAMALLAH WORKS Bill of Quantities July 2008 ENGINEERING UNIT Project: system The contractor shall, when pricing the rates of this bill take into consideration including and

More information

Electric Service Requirements. Residential Overhead. Engineering Specification T002. February

Electric Service Requirements. Residential Overhead. Engineering Specification T002. February Electric Service Requirements Residential Overhead Engineering Specification T002 February 2017 0362-16 ENG. SPEC. T002 REV. 3 RESIDENTIAL OVERHEAD INSTALLATIONS page 1 of 12 Table of Contents 1 GENERAL

More information

Residential Electric Policy

Residential Electric Policy Residential Electric Policy 7/19/16 1 Table of Contents General Information..3 Construction.3 Ownership....3 Underground Service...3 Apartments/Multi-Unit Dwellings..3 Modular and Manufactured Homes...3

More information

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING

More information

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1- GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 48-05 Van Dam Street Long Island City, NY 11101 ELECTRIC METER SHOP DEPARTMENT METER ENGINEERING SPECIFICATION MES-350 REVISION 3 June 2016 EFFECTIVE DATE

More information

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT

EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT EQUIVALENT INITIAL STRUCTURAL SAFETY ASSESSMENT Plot No.: 74-77, Sector -02, Karnaphuli EPZ North Patenga, Chittagong Chittagong Chittagong Bangladesh The Alliance for Bangladesh Worker Safety Page 1/11

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. Kaf-Tech Product Specification This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update. SECTION 260519 METAL CLAD CABLE - MC-PLUS Neutral

More information

Telecommunication Spaces

Telecommunication Spaces Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137

More information

Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER

Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER PART 1 - GENERAL 1.1 SUMMARY SECTION 26 13 16 MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER A. The scope of this section includes providing and assembling materials and equipment for the dead-front, medium voltage

More information

QUOTATION FOR THE ELECTRICAL WORK OF BANK OF INDIA, CHERTHALA BRANCH.

QUOTATION FOR THE ELECTRICAL WORK OF BANK OF INDIA, CHERTHALA BRANCH. QUOTATION FOR THE ELECTRICAL WORK OF BANK OF INDIA, CHERTHALA BRANCH. PART-B Date:- Sl.No Description Qty Unit Rate Amount I METER BOX II Supply,installation,testing & commisioning of dust & vermine proof

More information

CENTRE FOR DEVELOPMENT OF IMAGING TECHNOLOGY (C-DIT) Chitranjali Hills, Thiruvallam P.O., Thiruvananthapuram

CENTRE FOR DEVELOPMENT OF IMAGING TECHNOLOGY (C-DIT) Chitranjali Hills, Thiruvallam P.O., Thiruvananthapuram CENTRE FOR DEVELOPMENT OF IMAGING TECHNOLOGY (C-DIT) Chitranjali Hills, Thiruvallam P.O., Thiruvananthapuram 695 027 No. C-DIT/CG-Elec/18-19/T044 Date: 19.07.2018 TENDER NOTICE Sealed tenders are invited

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section

More information

PT. Swd Engineering Consultant

PT. Swd Engineering Consultant Spec.No.1525017/E/JICT LEVEL 2ND & HELPDESK LEVEL GROUND/V/2015 Page 1 CONTENTS SECTION DESCRIPTION Page No. SECTION : 1 - GENERAL 2 SECTION : 2 - TESTING AND COMMISSIONING 5 SECTION : 3 - MAINTENANCE

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES...

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES... DIVISION 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN Contents 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION 13 00 60 LIST OF FIGURES... 6 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN 1. General Requirements

More information

Signage Code. H101.2 Signs exempt from permits. The following signs are exempt from the requirements to obtain a permit before erection:

Signage Code. H101.2 Signs exempt from permits. The following signs are exempt from the requirements to obtain a permit before erection: Signage Code ICC Code: Appendix H: Signs SECTION H101 GENERAL H101.1 General. A sign shall not be erected in a manner that would confuse or obstruct the view of or interfere with exit signs required by

More information

LIST OF DRAWINGS PLAN TITLE

LIST OF DRAWINGS PLAN TITLE LANDFILL SITE [CLOSED 00] PLAN.... 5. TITLE LIST OF DRAWINGS EXISTING PROCESS DIAGRAM PROPOSED PROCESS DIAGRAM EXISTING EQUIPMENT LAYOUT PLAN PROPOSED EQUIPMENT LAYOUT PLAN ELEVATION D AND DETAILS TREATMENT

More information

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 27 Communication 0528 Pathways. Page 1 of 6

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 27 Communication 0528 Pathways. Page 1 of 6 1 General 1.1 Scope of work 1.1.1 The Contractor is held responsible to be familiar with the provisions contained herein and with other Sections of this Specification as applicable to the completion of

More information

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL WARNING Before digging or trenching... Call 811 Indiana Underground Protection Service 1-800-382-5544 AVOID BURIED POWER CABLES 4901 East Park 30 Drive P.O.

More information