Case Study: TallWood House at Brock Commons The University of British Columbia
|
|
- Caitlin Armstrong
- 5 years ago
- Views:
Transcription
1 Case Study: TallWood House at Brock Commons The University of British Columbia Presented on January 25, 2017 by Robert Jackson Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board.
2 The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES), Provider #G516. Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-aia members are available upon request. This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
3 Course Description When completed in the spring of 2017, the 18-story TallWood House at Brock Commons will be the tallest contemporary mass wood building in the world. An exceptional example of the advantages of timber prefabrication, this project aspires to be the model for a future that includes extraordinarily ordinary mass wood buildings. This presentation will introduce the project, discuss the various design approaches considered and explain the process used to arrive at the final solution. While providing a focused discussion on the structural design and unique engineering challenges, the presenter will also provide an introduction to the fire/life safety approach, construction methods and project coordination.
4 Learning Objectives 1. Review the structural system in the context of design challenges and how/why the project team arrived at the final solution. 2. Understand the fire design approach for TallWood House. 3. Discuss the methods employed to deliver a highly prefabricated mass timber project and related construction benefits. 4. Review the cost and quality of the final solution, as well as lessons learned.
5 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
6 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
7 DESIGN TEAM Kamps Engineering Limited PROJECT BACKGROUND
8 TIMELINE 10 Months Dec Sept Aug Oct May 2016 Sept Summer 2017 Project Contemplation NRC Funding Announced Design Team Selected SSR Completed Tender Construction Start Concrete Complete, Timber Install Start Superstructure Complete Project Complete PROJECT BACKGROUND
9 EXTERNAL FUNDING National Resources Canada (NRCan) Forestry Innovation Investment Ministry of Forests, Lands, And Natural Resource Operations Binational Softwood Lumber Council PROJECT BACKGROUND
10 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
11 LOCATION/CLIMATE DESIGN CONTEXT
12 LOCATION/CLIMATE DESIGN CONTEXT
13 LOCATION/CLIMATE DESIGN CONTEXT
14 LOCATION/CLIMATE DESIGN CONTEXT
15 COST DESIGN CONTEXT
16 BUILDING CODES & MATERIAL STANDARDS BRITISH COLUMBIA BUILDING CODE 2012 ENGINEERING DESIGN IN WOOD DESIGN CONTEXT
17 PROCUREMENT DESIGN CONTEXT
18 SUPPLIERS DESIGN CONTEXT
19 SUPPLIERS CAPACITY NLT GLT STARTING POINT CLT LVL LSL = 3640 m 3 OF MASS TIMBER DESIGN CONTEXT
20 SUPPLIERS CAPABILITY DESIGN CONTEXT
21 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
22 DESIGN APPROACH KEEP IT SIMPLE DESIGN APPROACH CREDIT: SEAGATE
23 DESIGN APPROACH DESIGN APPROACH
24 DESIGN APPROACH DESIGN APPROACH
25 DESIGN APPROACH DESIGN APPROACH
26 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
27 SUPERSTRUCTURE BUILDING OVERVIEW CREDIT: CADMAKERS
28 SUPERSTRUCTURE - LATERAL BUILDING OVERVIEW CREDIT: CADMAKERS
29 SUPERSTRUCTURE - LATERAL BUILDING OVERVIEW CREDIT: SEAGATE
30 SUPERSTRUCTURE - GRAVITY BUILDING OVERVIEW CREDIT: CADMAKERS
31 SUPERSTRUCTURE - GRAVITY BUILDING OVERVIEW CREDIT: KK LAW
32 SUPERSTRUCTURE - GRAVITY BUILDING OVERVIEW CREDIT: SEAGATE
33 PANEL SUPERSTRUCTURE LAYOUT - GRAVITY BUILDING OVERVIEW
34 ARCHITECTURE SUPERSTRUCTURE - GRAVITY BUILDING OVERVIEW CREDIT: ACTON OSTRY
35 ARCHITECTURE SUPERSTRUCTURE - GRAVITY BUILDING OVERVIEW CREDIT: ACTON OSTRY
36 ENVELOPE BUILDING OVERVIEW CREDIT: ACTON OSTRY
37 ENVELOPE BUILDING OVERVIEW CREDIT: ACTON OSTRY
38 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Superstructure Overview Key Analysis / Design Issues Construction Conclusion
39 BUILDING CODES & MATERIAL STANDARDS BCBC 2012 limited to 6-storeys UBC an Independent Jurisdiction British Columbia Safety Standards Branch Site Specific Regulation Building Permit KEY ANALYSIS/DESIGN ISSUES
40 BUILDING CODES & MATERIAL STANDARDS NBCC 2015 BCBC 2012 Vancouver Sa(2.0) = SEISMIC ACCELLERATIONS INCREASED BY 53% NBCC 2015 Vancouver Sa(2.0) = KEY ANALYSIS/DESIGN ISSUES
41 BUILDING CODES & MATERIAL STANDARDS PEER REVIEWS Merz Kley Partners Austria Timber Focused Read Jones Christofferson Vancouver Seismic Focused KEY ANALYSIS/DESIGN ISSUES
42 BUILDING CODES & MATERIAL STANDARDS KEY ANALYSIS/DESIGN ISSUES MICHAEL GREEN ARCHITECTURE
43 FIRE KEY ANALYSIS/DESIGN ISSUES
44 FIRE KEY ANALYSIS/DESIGN ISSUES
45 FIRE KEY ANALYSIS/DESIGN ISSUES
46 FIRE KEY ANALYSIS/DESIGN ISSUES
47 FIRE KEY ANALYSIS/DESIGN ISSUES
48 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
49 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
50 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
51 POINT POINT SUPPORTED SUPPORTED CLT CLT KEY ANALYSIS/DESIGN ISSUES
52 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
53 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
54 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
55 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
56 POINT SUPPORTED CLT KEY ANALYSIS/DESIGN ISSUES
57 COLUMN TO COLUMN CONNECTIONS KEY ANALYSIS/DESIGN ISSUES
58 COLUMN TO COLUMN CONNECTIONS KEY ANALYSIS/DESIGN ISSUES
59 COLUMN TO COLUMN CONNECTIONS KEY ANALYSIS/DESIGN ISSUES
60 AXIAL COLUMN SHORTENING Δ1 Δ2 TIIMBER COLUMNS CONCRETE CORE TIIMBER COLUMNS Δ1 (CONCRETE) Δ2 (TIMBER) = SHRINKAGE + ELASTIC SHORTENING + CREEP = SHRINKAGE + ELASTIC SHORTENING + CREEP + JOINT SETTLEMENT KEY ANALYSIS/DESIGN ISSUES
61 AXIAL COLUMN SHORTENING Dead Load Axial Live Load Axial Longitudinal Shrinkage Creep and Joint Settlement KEY ANALYSIS/DESIGN ISSUES
62 AXIAL COLUMN SHORTENING TIME OF INSTALL MECHANICAL SHIM PACKAGE KEY ANALYSIS/DESIGN ISSUES
63 AXIAL COLUMN SHORTENING SOME TIME LATER MECHANICAL SHIM PACKAGE KEY ANALYSIS/DESIGN ISSUES
64 AXIAL COLUMN SHORTENING KEY ANALYSIS/DESIGN ISSUES
65 LATERAL DESIGN KEY ANALYSIS/DESIGN ISSUES
66 LATERAL DESIGN RdRo = 3.5 * 1.6 DUCTILE COUPLED CONCRETE SHEARWALLS ~R=5.6 MODE 1 = E/W ORTHOGONAL, T=2.0 SEC. MODE 2 = N/S ORTHOGONAL, T = 1.65 SEC. MODE 3 = TORSIONAL, T= 1.30 SEC. EQ = 4.5% OF WEIGHT KEY ANALYSIS/DESIGN ISSUES
67 CAPACITY DESIGN CAPACITY DESIGN NO YIELDING DESIGN DIAPHRAGM TO FLEXURAL CAPACITY OF CORES DESIGN CONNECTIONS, DRAGS, CHORDS, COLLECTORS WITH OVERSTRENGTH CAPACITY YIELDING KEY ANALYSIS/DESIGN ISSUES
68 CAPACITY DESIGN KEY ANALYSIS/DESIGN ISSUES
69 DIAPHRAGM DESIGN KEY ANALYSIS/DESIGN ISSUES
70 DIAPHRAGM DESIGN KEY ANALYSIS/DESIGN ISSUES
71 DIAPHRAGM DESIGN KEY ANALYSIS/DESIGN ISSUES
72 DIAPHRAGM DESIGN KEY ANALYSIS/DESIGN ISSUES
73 DIAPHRAGM DESIGN KEY ANALYSIS/DESIGN ISSUES
74 DIAPHRAGM DESIGN KEY ANALYSIS/DESIGN ISSUES
75 DYNAMIC WIND ACCELERATIONS KEY ANALYSIS/DESIGN ISSUES
76 DYNAMIC WIND ACCELERATIONS DAMPING? β= 1% to 3% KEY ANALYSIS/DESIGN ISSUES
77 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
78 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
79 INFORMATION FLOW DESIGN TEAM CADMAKERS (3D COORDINATOR) STRUCTURLAM (TIMBER SUPPLIER) 3D (.SAT and.ifc) models provided by CadMakers supplies general geometry including all mechanical penetrations. Use of a coordinated single model saved time and reduced confusion between the multiple parties. KEY ANALYSIS/DESIGN ISSUES
80 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
81 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
82 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
83 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
84 PRE-FABRICATION ~0.95 mmfbm in 2 months time. KEY ANALYSIS/DESIGN ISSUES
85 PRE-FABRICATION KEY ANALYSIS/DESIGN ISSUES
86 PRE-FABRICATION Fabrication arranged in a linear process for just in time delivery. Loads arranged on trucks to perfectly match installation sequence o Requires ample preplanning on the part of the project team KEY ANALYSIS/DESIGN ISSUES
87 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
88 MOCK-UP CONSTRUCTION
89 MOCK-UP CONSTRUCTION
90 MOCK-UP CONSTRUCTION
91 MOCK-UP PRECAST SIP WOOD FRAME/ METAL PANEL STEEL STUD/ METAL PANEL CONSTRUCTION
92 SEQUENCING CONSTRUCTION
93 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
94 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
95 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
96 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
97 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
98 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
99 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
100 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
101 CONSTRUCTION CONSTRUCTION
102 CONSTRUCTION CONSTRUCTION
103 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
104 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
105 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
106 CONSTRUCTION CONSTRUCTION CREDIT: SEAGATE
107 CONSTRUCTION CONSTRUCTION
108 CONSTRUCTION CONSTRUCTION
109 CONSTRUCTION CONSTRUCTION
110 CONSTRUCTION CONSTRUCTION CREDIT: ACTON OSTRY
111 CONSTRUCTION CONSTRUCTION CREDIT: ACTON OSTRY
112 TALLWOOD HOUSE AT BROCK COMMONS Project Background Design Context Design Approach Building Overview Key Analysis / Design Issues Construction Conclusion
113 PROGRESS TO DATE CONCLUSION CREDIT: NATURALLY WOOD
114 ACHIEVEMENTS WOOD VOLUME ESTIMATE 3600m 3 ACHIEVED 2233m 3 COST 192 $/ft 2 (2014) TBD TIMBER INSTALL ~2 FLOORS / WEEK 2 FLOORS / WEEK RAIN A LITTLE A LOT! TOLERANCES +/- 1mm +/- 1mm CONCLUSION
115 LESSONS LEARNED Efficient system suitable for student residences, microapartments or hotels Wider column grid possible with wider panels Keep things simple. Involve your trades early. 3D coordination paid off. Kit-Of-Parts prefabrication has advantages. CONCLUSION
116 Questions? This concludes The American Institute of Architects Continuing Education Systems Course Robert Jackson Fast + Epp Structural Engineers rjackson@fastepp.com
designing the tallest mass timber building in the world
designing the tallest mass timber building in the world Fast + Epp structural engineers Tanya Luthi, P.E. Northeast Mass Timber Symposium November 16, 2017 Disclaimer: This presentation was developed by
More informationFast + Epp structural engineers Tanya Luthi, P.E.
Fast + Epp structural engineers Tanya Luthi, P.E. Seattle Wood Solutions Fair April 25, 2017 Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood
More informationstructural design of mass timber framing systems
structural design of mass timber framing systems nwwood design symposium -seattle davin lewis, p.e., p.eng. fast +epp july19, 2018 Disclaimer: This presentation was developed by a third party and is not
More informationstructural design of mass timber framing systems
structural design of mass timber framing systems midwest wood solutions fair tanya luthi, p.e. fast +epp Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the
More informationstructural design of mass timber framing systems
structural design of mass timber framing systems northeast wood design symposium tanya luthi, p.e. fast +epp september26, 2018 Disclaimer: This presentation was developed by a third party and is not funded
More informationMassive but Lean: How Design + Construction Efficiency Led One Mass Timber Project to Success
Massive but Lean: How Design + Construction Efficiency Led One Mass Timber Project to Success Presented by: W illiam Silva Disclaimer: This presentation was developed by a third party and is not funded
More informationThe Tallest Wood Building in the World UBC Brock Commons Student Residence Base 3D Model to Product Delivery
The Tallest Wood Building in the World UBC Brock Commons Student Residence Base 3D Model to Product Delivery Kris Spickler, P.E. Principal Heavy Timber Group Inc Granite Bay, California Nicholas Sills,
More informationBROCK COMMONS TALLWOOD HOUSE DESIGN MODELLING. innovation in hybrid mass timber construction
BROCK COMMONS TALLWOOD HOUSE DESIGN MODELLING innovation in hybrid mass timber construction KK Law introduction Located on a large forested peninsula on the west side of Vancouver, the University of British
More informationBROCK COMMONS PHASE 1: CODE COMPLIANCE
innovation in hybrid mass-timber construction DESIGN AND PRECONSTRUCTION OF A TALL WOOD BUILDING BROCK COMMONS PHASE 1: CODE COMPLIANCE Acton Ostry Architects Inc. 2 introduction Located on a large forested
More informationCLT in the U.S. Manufacturing and Applications
CLT in the U.S. Manufacturing and Applications Presented by Quinn Guerrero Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. The
More informationExposed Wood in Fire Resistive Applications
Please add relevant logo here Exposed Wood in Fire Resistive Applications David Barber, Arup Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood
More informationBROCK COMMONS PHASE 1
University of British Columbia Vancouver, B.C., Canada BROCK COMMONS PHASE 1 Brock Commons Phase 1 is an innovative tall wood student residence under construction at the University of British Columbia
More informationTowards Earthquake-Proof Wood Buildings
Towards Earthquake-Proof Wood Buildings Full-scale shake table test of a two-story mass timber building Presented by Shiling Pei, Ph.D. P.E. Colorado School of Mines Disclaimer: This presentation was developed
More informationTall Timber Americas Challenges & Solutions. Dmitri Jajich, Director, Skidmore, Owings & Merrill LLP
Tall Timber Americas Challenges & Solutions Dmitri Jajich, Director, Skidmore, Owings & Merrill LLP SOM Research and Testing Survey of Recent North American Projects Future Timber Tower Research Project
More informationThe Wood Products Council and AIA/CES. Concept, Performance and. Learning Objectives. FPInnovations - Background
The Wood Products Council and AIA/CES www.fpinnovations.ca Midply Shearwall System: Concept, Performance and Code Implementation C. Ni, M. Popovski FPInnovations, Building Systems The Wood Products Council
More informationCASE STUDY: AN 18 STOREY TALL MASS TIMBER HYBRID STUDENT RESIDENCE AT THE UNIVERSITY OF BRITISH COLUMBIA, VANCOUVER
CASE STUDY: AN 18 STOREY TALL MASS TIMBER HYBRID STUDENT RESIDENCE AT THE UNIVERSITY OF BRITISH COLUMBIA, VANCOUVER Paul Fast 1, Bernhard Gafner 2, Robert Jackson 3, Jimmy Li 4 ABSTRACT: This article outlines
More informationCross-Laminated Timber in the Capital
Cross-Laminated Timber in the Capital A Case Study: Washington Latin Public Charter School Gymnasium Presented by Ann Neeriemer, AIA, LEED AP Disclaimer: This presentation was developed by a third party
More informationSignificant Changes to AWC s Special Design Provisions for Wind and Seismic
Significant Changes to AWC s Special Design Provisions for Wind and Seismic Michelle Kam-Biron, PE, SE, SECB Director of Education American Wood Council Copyright Materials This presentation is protected
More informationCross-Laminated Timber (CLT) in California: Guidelines, Testing and Recommendations
Cross-Laminated Timber (CLT) in California: Guidelines, Testing and Recommendations Presented by Scott Breneman, PhD, PE, SE Senior Technical Director Scott.Breneman@woodworks.org 1 The Wood Products Council
More informationMid-Rise Engineering Considerations for Engineered Wood Products
Mid-Rise Engineering Considerations for Engineered Wood Products Presented by Frank Powell, P.E. Presented by [ Presenter s Name ] Please add relevant logo here Disclaimer: This presentation was developed
More informationAn Engineering Perspective on Mass Timber Design in the Southeast
An Engineering Perspective on Mass Timber Design in the Southeast Graham Montgomery, PE Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber
More information6-Story Wood Frame Committee
6-Story Wood Frame Committee Fourth (A) Draft Report March 14 th 2009 1. INTRODUCTION 1.1 PURPOSE This technical bulletin provides basic guidance on structural, fire protection and building envelope engineering
More informationWood Solutions Fair, 2014, Toronto
Overview of Changes to CSA O86-2014 & Structural Design Provisions for Mid-Rise in OBC Wood Solutions Fair, 2014, Toronto Jasmine Wang, Ph.D., P.Eng. Canadian Wood Council Copyright Materials This presentation
More informationCopyright Materials. R. Jonkman, P.Eng, A. Robertson, P.Eng 1
Robert Jonkman, P.Eng. November 12, 2013 Adam Robertson, P.Eng. Toronto Wood Solutions Fair Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution,
More informationOverview of the New Mid-Rise Handbook Alberta Wood Solutions Fair
Overview of the New Mid-Rise Handbook Alberta Wood Solutions Fair Conroy Lum, P.Eng. Research Leader Structural Performance Group Advanced Building Systems February 12, 2015 Calgary Copyright Materials
More informationFire Safety of Tall Wood Buildings: A Research Review. Copyright Materials. Course Description. This presentation is protected by US and
Fire Safety of Tall Wood Buildings: A Research Review Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation
More informationDesign Opportunities Michigan Mass Timber
A presentation to: The Michigan Forest Bioeconomy Conference Design Opportunities Michigan Mass Timber Brian K. Craig, AIA, LEED AP Director Master of Architecture Kendall College of Art and Design Ferris
More informationEngr. Thaung Htut Aung M. Eng. Asian Institute of Technology Deputy Project Director, AIT Consulting
Engr. Thaung Htut Aung M. Eng. Asian Institute of Technology Deputy Project Director, AIT Consulting Selection of Structural systems Load paths Materials Approximate sizing of members Primary mechanisms
More informationDISTRICT 03: EASTERN CANADA'S FIRST 6- STOREY CLT BUILDING DAVID MIZRAHI, ENG. (ENSTIB, M.S.) DESIGN ENGINEER, NORDIC. Copyright Materials
: EASTERN CANADA'S FIRST 6- STOREY CLT BUILDING DAVID MIZRAHI, ENG. (ENSTIB, M.S.) DESIGN ENGINEER, NORDIC Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction,
More informationWORKSHOP Progressive Multi- Family Design: New Opportunities for Light Frame Mid-Rise Structures
WORKSHOP Progressive Multi- Family Design: New Opportunities for Light Frame Mid-Rise Structures February 14 16, 2017 San Diego, Long Beach, San Francisco The Wood Products Council is a Registered Provider
More informationStructural Design for Wind Loads: An Overview of Engineering Considerations for Wood
Structural Design for Wind Loads: An Overview of Engineering Considerations for Wood Lori Koch, PE Manager, Educational Outreach American Wood Council Buildings Copyright Materials This presentation is
More informationCross-Laminated Timber (CLT) in California:
Cross-Laminated Timber (CLT) in California: Guidelines, Testing and Recommendations Erik Kneer, SE, LEED AP BD+C Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks
More informationBROCK COMMONS TALLWOOD HOUSE: CONSTRUCTION OVERVIEW
CONSTRUCTION OF A TALL WOOD BUILDING BROCK COMMONS TALLWOOD HOUSE: CONSTRUCTION OVERVIEW innovation in hybrid mass-timber construction naturally:wood front cover Acton Ostry Foresty Innovation Investment
More informationStage: A Case Study. Course Description. Learning Objectives
Arena Stage: A Case Study Brought to Lifeto The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES), Provider #G516. Credit(s)
More informationUBC BROCK COMMONS PROJECT
Disclaimer: This Presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. UBC BROCK COMMONS PROJECT Karla Fraser Senior Project Manager Outline Project Description
More informationRiver Beech Tower: A Tall Timber Experiment
Architecture/Design River Beech Tower: A Tall Timber Experiment Authors Jeff Sanner, Project Architect Todd Snapp, Design Principal Perkins+Will 410 N. Michigan Avenue, Suite 1600 Chicago, IL 60611, United
More informationStructural Composite Lumber (SCL)
Prefabricated Wood I-Joists Structural Composite Lumber (SCL) Laminated Veneer Lumber (LVL) Parallel Strand Lumber (PSL) Laminated Strand Lumber (LSL) Oriented Strand Lumber (OSL) Other EWP Products Plywood
More informationCopyright Materials 11/8/2012. Learning Objectives
Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited.
More informationDesign Opportunities - Exploring Wood
A presenta*on to: The Michigan Forest Bioeconomy Conference Design Opportunities - Exploring Wood Brian K. Craig, AIA, LEED AP Director Master of Architecture Kendall College of Art and Design Ferris State
More informationDESIGN AND PRECONSTRUCTION OVERVIEW
BROCK COMMONS TALLWOOD HOUSE DESIGN AND PRECONSTRUCTION OVERVIEW innovation in hybrid mass timber construction Early version of the design. Render by Acton Ostry Architects Inc. At the end of the day,
More informationA 21st Century Iconic Glulam Structure: Cathedral of Christ the Light
A 21st Century Iconic Glulam Structure: Cathedral of Christ the Light Paul C. Gilham, P.E., S.E. Chief Engineer Western Wood Structures, Inc. Disclaimer: This presentation was developed by a third party
More informationTall Wall Applications Challenges. Products Design Considerations Framing Details Fire Assemblies Innovative Solutions. Residential Construction
Wood Framed Tall Walls July 2010 AIA Course WoodWorks is a Registered Provider with the American Institute of Architects t Continuing i Education Systems. Credit earned on completion of this program will
More informationStructural Timber Systems
BUILDING SOLID! UTILIZING NEW WOOD TECHNOLOGIES San Francisco Wood Solutions Fair March 16, 2011 The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing
More informationMore with Less: An Overview of the 1 st CLT Hotel in the U.S. Jeff Morrow Northwest Wood Solutions Fair Portland, OR April 26, 2016 AIA #16NW04
More with Less: An Overview of the 1 st CLT Hotel in the U.S. Jeff Morrow Northwest Wood Solutions Fair Portland, OR April 26, 2016 AIA #16NW04 Disclaimer: This presentation was developed by a third party
More informationChecker Building Structural Analysis and Design
Checker Building Structural Analysis and Design Zhiyong Chen 1, Minghao Li 2, Ying H. Chui 1, Marjan Popovski 3, Eric Karsh 4, and Mahmoud Rezai 4 1 Univ. of New Brunswick, 2 Univ. Canterbury, 3 FPInnovations,
More informationIntroducing the Design Guide for Nail-Laminated Timber Architectural Considerations SUBTITLE
NAILED IT! Introducing the Design Guide for Nail-Laminated Timber Architectural Considerations SUBTITLE Presented by Alex Minard, Architect AIBC, MRAIC, LEED AP BD+C, CPHD Disclaimer: This presentation
More informationCE 549 Building Design Project Spring Semester 2013
CE 549 Building Design Project Spring Semester 2013 Instructor: Farzad Naeim, Ph.D., S.E., Esq. E-Mail: naeim@usc.edu Syllabus Overview: We will design a mid-rise office building using a team-approach
More informationThe Mass Timber Prospective: Tall Wood, Code Changes, and Forest Resource Impacts
The Mass Timber Prospective: Tall Wood, Code Changes, and Forest Resource Impacts Presented September 2018, Kathryn Fernholz Disclaimer: This presentation was developed by a third party and is not funded
More informationThe Mass Timber Prospective: Tall Wood, Code Changes, and Forest Resource Impacts
The Mass Timber Prospective: Tall Wood, Code Changes, and Forest Resource Impacts Presented October 2018, Kathryn Fernholz Disclaimer: This presentation was developed by a third party and is not funded
More informationProgressive Multi-Family Design: New Opportunities for Light Frame Mid-Rise Structures. Workshop
Progressive Multi-Family Design: New Opportunities for Light Frame Mid-Rise Structures Workshop The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education
More informationCopyright Materials. Learning Objectives
Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited.
More informationStructural CLT Floor and Roof Design
Structural CLT Floor and Roof Design Scott Breneman, PhD, PE, SE Senior Technical Director Project Resources and Solutions Division WoodWorks Wood Products Council Photo Ema Peter Photography The Wood
More informationCANADIAN DESIGN GUIDE TO TALL WOOD BUILDINGS
CANADIAN DESIGN GUIDE TO TALL WOOD BUILDINGS M. Mohammad, FPInnovations/NRCan Journée technique sur le bois: Projet NE WBuildS de 20 étages et atelier sur les techniques d assemblages Nov. 12, 2014, Montreal
More informationCE 549 Building Design Project Spring Semester 2010
CE 549 Building Design Project Spring Semester 2010 Instructor: Farzad Naeim, Ph.D., S.E., Esq. E-Mail: naeim@usc.edu Syllabus Overview: We will design a mid-rise office building using a team-approach
More informationCopyright Materials TIMBER TOWER RESEARCH PROJECT BY SOM. Learning Objectives
The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES
More informationDESIGN OF HIGH-RISE CORE-WALL BUILDINGS: A CANADIAN PERSPECTIVE
DESIGN OF HIGH-RISE CORE-WALL BUILDINGS: A CANADIAN PERSPECTIVE Perry Adebar Professor, Dept. of Civil Engineering, The University of British Columbia, Vancouver, Canada Email: adebar@civil.ubc.ca ABSTRACT
More informationContinuing Education Course and Credits
Canadian Wood Council G063 The Mid-Rise Wood-Frame Construction Handbook: Overview and Structural Design Aspects Marjan Popovski, Ph.D., P. Eng. Principal Scientist, FPInnovations Adjunct Professor, University
More informationDetailing For Wood Shrinkage
Detailing For Wood Shrinkage Presented to: 2014 Texas Wood Solutions Fair Presented by: Doug Steimle Schaefer Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks
More informationImplementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and
More informationChecker Building Structural Analysis and Design
Checker Building Structural Analysis and Design Zhiyong Chen 1, Minghao Li 2, Ying H. Chui 1, Marjan Popovski 3, Eric Karsh 4, and Mahmoud Rezai 4 1 Univ. of New Brunswick, 2 Univ. Canterbury, 3 FPInnovations,
More informationLearning Objectives. Eden Project The Core Cornwall, England
The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES
More information* https://www.rethinkwood.com/tall-wood-mass-timber/tall-wood-gallery
Mass Timber elements, including Cross-laminated timber (CLT), are allowed outright for certain applications in the 2015 International Building Code (IBC), which has been adopted by Washington State. The
More informationLearning Objectives. Copyright Materials. This presentation is protected by US and International Copyright laws. Reproduction,
The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES
More informationMass Plywood Panels: Designing with the Newest Mass Timber Structural Product
Mass Plywood Panels: Designing with the Newest Mass Timber Structural Product Presented by Eric Ortiz, Freres Lumber Co., Inc. Disclaimer: This presentation was developed by a third party and is not funded
More informationAISC Live Webinars. Thank you for joining our live webinar today. We will begin shortly. Please standby.
AISC Live Webinars Thank you for joining our live webinar today. We will begin shortly. Please standby. Thank you. Need Help? Call ReadyTalk Support: 800.843.9166 Today s audio will be broadcast through
More informationBROCK COMMONS TALLWOOD HOUSE PERFORMANCE OVERVIEW. innovation in hybrid mass timber construction
BROCK COMMONS TALLWOOD HOUSE PERFORMANCE OVERVIEW innovation in hybrid mass timber construction Brock Commons Tallwood House is a shining star within UBC s overall inventory of student housing facilities.
More informationToday s agenda 1/30/2017. Mass timber What is it products Why use it appeal How does it work design topics Where is it used case studies What s next?
Please add relevant logo here Introduction to Mass Timber Buildings Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use
More informationFULL-SCALE SHAKE TABLE TESTING OF A TWO- STORY MASS TIMBER BUILDING WITH RESILIENT ROCKING WALL LATERAL SYSTEM
EXECUTIVE REPORT FULL-SCALE SHAKE TABLE TESTING OF A TWO- STORY MASS TIMBER BUILDING WITH RESILIENT ROCKING WALL LATERAL SYSTEM Prepared for Softwood Lumber Board by: NHERI Tall Wood Project Team Shiling
More informationMass Timber: Knowing Your Options
Mass Timber: Knowing Your Options Presentation to the Architectural Institute of BC & the American Institute of Architects 24 October, 2013 Ian Boyle P.Eng., Struct.Eng., P.E., S.E. Bernhard Gafner P.Eng.,
More informationMass(Timber(Building(Systems:( Understanding(the(Op:ons(
Mass(Timber(Building(Systems:( Understanding(the(Op:ons( & Fast&+&Epp& & & & Presented&on&December&9 th,&2015&by&ian&boyle& P.Eng.,&Struct.Eng.,&PE,&SE& & Disclaimer: This presentation was developed by
More informationSeismic Design of Building Structures
Seismic Design of Building Structures A Professional's Introduction to Earthquake Forces and Design Details Ninth Edition Michael R. Lindeburg, PE with Kurt M. McMullin, PE '.The Power to Pass www.ppi2pass.com
More informationLecture 5 Building Irregularities
1 Lecture 5 Building Irregularities Course Instructor: Dr. Carlos E. Ventura, P.Eng. Department of Civil Engineering The University of British Columbia ventura@civil.ubc.ca Short Course for CSCE Calgary
More informationSolid Wood: New Trends in Mass Timber Architecture, Technology and Design
Solid Wood: New Trends in Mass Timber Architecture, Technology and Design Joe Mayo, AIA, LEED AP Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood
More informationSeismic Steel Design 12/9/2012
Chapter 8 Design of Seismic-Resistant Steel Building Structures: A Brief Overview SEISMIC STEEL DESIGN IN CANADA and the USA Instructor: Dr. Carlos E. Ventura, P.Eng. Department of Civil Engineering The
More informationBiobehavioral Health Building
Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor Heather Sustersic Location: The Pennsylvania State University University Park, PA Project Size: 5
More informationeqcanada.com 1. Identifying the advantages and disadvantages of a variety of 2. Acquire current status of the joint Canada/US code
CLT Conference Solid Panel Construction and Design for Cost Effectiveness Seattle February 28, 2013 The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing
More informationCWC Publications, Software and Tools
CWC Publications, Software Kevin Rocchi, MASc., E.I.T. October 27 th 2015 Vancouver, BC Canadian Wood Council G063 CWC Publications, Software Kevin Rocchi, MASc., E.I.T. Technical Service Specialist Canadian
More informationFraming Techniques for Builders: Lessons Learned and Best Practices
Framing Techniques for Builders: Lessons Learned and Best Practices Gary Schweizer, PE Weyerhaeuser April 25, 2018 Disclaimer: This presentation was developed by Weyerhaeuser and is not funded by WoodWorks
More informationTimber Office Buildings: Everything Old is New Again. Image:
Timber Office Buildings: Everything Old is New Again Image: Brock Commons Vancouver, completed 2017 Acton Ostry Fast+Epp 18 storeys (17 wood +1 concrete); 54 metres; 162,700 sqft. Time for Canadian & U.S.
More informationMass Timber & Tall Wood Buildings
Mass Timber & Tall Wood Buildings XXII WESTFORD SYMPOSIUM - SUMMER CAMP, AUGUST 8, 2018 GRAHAM FINCH, MASC, P.ENG PRINCIPAL, SENIOR BUILDING SCIENCE SPECIALIST 1 Overview What is Mass Timber? Why Tall
More informationTECHNICAL NOTE. Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006 IBC. On Cold-Formed Steel Construction INTRODUCTION
TECHNICAL NOTE On Cold-Formed Steel Construction 1201 15th Street, NW, Suite 320 W ashington, DC 20005 (202) 785-2022 $5.00 Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006
More informationDanielle Shetler - Structural option Courtyard by Marriott Lancaster, PA
Structural Analysis Overview: During the structural analysis of the in Lancaster, Pa, a redesign of the lateral and gravity system from masonry bearing and shear walls to a staggered truss system was performed.
More informationSeismic Performance of Residential Buildings with Staggered Walls
Seismic Performance of Residential Buildings with Staggered Walls Hyungoo Kang and Joonho Lee Graduate Student, Department of Architectural Engineering, Sungkyunkwan University, Suwon, Korea Jinkoo Kim
More informationBy Denis Mitchell and Patrick Paultre Seismic Design
11 By Denis Mitchell and Patrick Paultre Seismic Design 11.1 Introduction... 11 3 11.2 Seismic Design Considerations... 11 5 11.3 Loading Cases... 11 5 11.4 Design of a Six-Storey Ductile Moment-Resisting
More informationTOWARD TALLER WOOD BUILDINGS
NATIONAL SYMPOSIUM : TOWARD TALLER WOOD BUILDINGS November 6-7, 2014 Chicago, IL Earn 12 AIA/CES LUs (HSW) or PDH credits Register at woodworks.org Photo: Lawrence Anderson, www.lawrenceanderson.net Put
More informationCopyright Materials. Learning Objectives. Design is in the Details: Solutions to Common to Mid Rise Design. Challenges
Design is in the Details: Solutions to Common to Mid Rise Design Challenges The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES).
More informationWOODWORKS WEBINAR - JUNE 14, 2012
W HAT W HEN W HY WOODWORKS WEBINAR - JUNE 14, 2012 Catherine Marx Kaake, P.E, CFM Senior Director, Engineered & Framing Markets Special Thanks to: WoodWorks SPIB AWC SBCA NAHB Anthony Forest Products Weyerhaeuser
More informationLooking Forward: Leading Edge Solutions through Applied Research in Wood Building Systems
Looking Forward: Leading Edge Solutions through Applied Research in Wood Building Systems Weichiang Pang, Ph.D. Associate Professor Glenn Department of Civil Engineering Dustin Albright, Assistant Professor
More informationSTRUCTURAL DESIGN OF POST-FRAME BUILDINGS: A CONCEPTUAL PRESENTATION
STRUCTURAL DESIGN OF POST-FRAME BUILDINGS: A CONCEPTUAL PRESENTATION The Wood Products Council is a Registered Provider with The$ American$Ins.tute$of$Architects$Con.nuing$Educa.on$Systems$(AIA/CES). Credit(s)
More informationRich Denio, Supervising Structural Engineer Ron LaPlante, Supervising Structural Engineer
Designing Wood Schools in California: A Perspective from DSA October 4, 2017 Rich Denio, Supervising Structural Engineer Ron LaPlante, Supervising Structural Engineer Richard.Denio@dgs.ca.gov Disclaimer:
More informationBuilding Bigger, Taller and Smarter with Wood. Iain Macdonald TallWood Design Institute
Building Bigger, Taller and Smarter with Wood Iain Macdonald TallWood Design Institute Outline Mass timber what and why? European origins Worldwide growth Mass timber in the US The future TallWood Design
More informationAdvances in Mass Timber Buildings
Advances in Mass Timber Buildings Peter Lister, MASc, PEng. Research & Innovation Executive and Forestry Sector Advocate Pacific NorthWest Economic Region - 26 th Annual Summit July 17-21, 2016 Calgary,
More informationResponse of TBI case study buildings
Response of TBI case study buildings ANALYSIS OF STEEL BUILDING Pierson Jones & Farzin Zareian May 7 th, 2010 Introduction Three 40-story Building BRBF Systems building Structural and Earthquake Engineering
More informationModular Wood Framing Goes Vertical
Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported
More informationPEER/CSSC Tall Building Design Case Study Building #1. J. Andrew Fry John Hooper Ron Klemencic Magnusson Klemencic Associates
PEER/CSSC Tall Building Design Case Study Building #1 J. Andrew Fry John Hooper Ron Klemencic Magnusson Klemencic Associates Building Information Located in Los Angeles 42-Story 410 ft Tall 108 ft X 107
More informationCROSS LAMINATED TIMBER
CROSS LAMINATED TIMBER Bridging the Designer-Manufacturer Gap Presented By: Allison Standiford November 2, 2017 Southeast Wood Solutions Fair Disclaimer: This presentation was developed by a third party
More informationDESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY
DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY ABSTRACT Jugesh Kapur, PE, SE 1 The seismic design and detailing of bridges made of precast prefabricated members
More informationMass$Timber$Building$Systems:$ Understanding$the$Op9ons$
Mass$Timber$Building$Systems:$ Understanding$the$Op9ons$ Presented(on(January(27 th,(2015(by(bernhard(gafner( P.Eng.,(MIStructE,(C.Eng.,(Dipl.Ing.(FH/STV( ( Disclaimer: This presentation was developed
More informationNew Innovative Wood Products Challenges and Opportunities
New Innovative Wood Products Challenges and Opportunities Dr Keith Crews Professor of Structural Engineering Associate Dean Faculty of Engineering & IT University of Technology Sydney 1 Background A number
More information