The River Runs Through It : Rehabilitation of the Harvie Passage Project. Chuck Slack, P.Eng., Principal, Manager Water Resources & Civil Projects

Size: px
Start display at page:

Download "The River Runs Through It : Rehabilitation of the Harvie Passage Project. Chuck Slack, P.Eng., Principal, Manager Water Resources & Civil Projects"

Transcription

1 The River Runs Through It : Rehabilitation of the Harvie Passage Project Chuck Slack, P.Eng., Principal, Manager Water Resources & Civil Projects

2 1. Project Background 2. June 2013 Flood Harvie Passage: Presentation Agenda 3. Rehabilitation of Harvie Passage 4. Project Team 5. Project Schedule 6. Biophysical Impact Assessment, Regulatory Applications and Approval Process 7. Work Restrictions 8. Care of Water 9. Construction 10. Questions

3 1. Project Background Since its construction in 1908 the Western Headworks (WH) Weir claimed over 20 lives. The weir incorporated an ogee weir profile which utilized a circulating hydraulic to reduce energy. This circulating hydraulic was named the Drowning Machine because once in the hydraulic swimmers and boaters had extreme difficulty to get out. Primary objective of the Harvie Passage was to enable river passage for non-motorized boats and enhance upstream fish passage while maintaining water delivery to the Western Headworks canal. This was achieved by constructing a series of pools and drop structures (riffles) that backflooded the weir; thereby eliminating the dangerous hydraulics. Photo Courtesy Discovery Channel s Daily Planet

4 1. Project Background (Cont d) The energy created through the drop structures allowed for the creation of recreational hydraulics for river users while maintaining upstream fish passage. The Low Water Channel (LWC) on river right consisted of five concreted boulder structures and five constructed pools to provide a bypass channel for novice boaters to pass downstream and fish to pass upstream and downstream. The High Water Channel (HWC) consists of five concreted boulder structures and three constructed pools to provide whitewater play areas for more experienced boaters and for fish to pass upstream and downstream.

5 1. Project Background (Cont d) Low Water Channel High Water Channel

6 1. Project Background (Cont d) Construction started in November General construction contractor was DeGraaf Excavating Ltd. Fishway wall extension was constructed between November 2008 and April HWC Drops #3L, #3R, and #4 were constructed between August and November HWC Drop #1 constructed between October 2009 and November Cofferdam

7 1. Project Background (Cont d) LWC and HWC Drops #1, #2L, and #2R constructed between April 2010 and November 2010.

8 Project was completed in June Project Background (Cont d)

9 Project Commissioning

10 2. June 2013 Flood

11 2. June 2013 Flood 2013 Flood Damages: HWC Divide Island Right Abutments of HWC Drop #2R and #3R Scour Downstream of HWC Drop #2L River Levels Downstream of HWC Drop #4 are Significantly Lower at Lower River Discharges Resulting in Unsafe Hydraulics and Compromised Upstream Fish Passage

12 2. June 2013 Flood 2013 Flood Damages: LWC LWC Pools #3 to #5 and LWC Drops #4 to #6 Buried in Gravel and Cobbles Left Bank of LWC Pool #2/right side of HWC Pool #1 Breached. LWC Drop #3 Damaged Eroded Channel along Right Bank of River

13 3. Rehabilitation of Harvie Passage Fall 2016 HWC Extend downstream end of HWC Drop #4 to accommodate lower tailwater levels. Rehabilitate HWC Drops #3L and #3R. Rehabilitate Divide Island. Riprap revetment on left riverbank downstream of sluiceway structure. Place boulders downstream of HWC Drop #2L.

14 3. Rehabilitation of Harvie Passage Landscaping including cuttings, shrubs, trees, boulders, stone benches, stairs, and ramps. NEW LWC Includes: 5 pools 7 concreted boulder offset deflectors (groynes) 3 concreted boulder drop structures Bio-engineering including vegetated riprap and vegetated soil wrap.

15 Alberta Transportation Carl Wirzba Project Manager Sanjaya Pradhan Assistant Project Manager Alberta Environment and Parks Clayton Weiss, Italo Colistro, and Rick Freidl City of Calgary Deighen Blakely and Jon Slaney 4. Project Team

16 4. Project Team (Cont d) Consultants Prime Consultant: Klohn Crippen Berger Landscape Designer: O2 Planning+Design Recreational Hydraulics: SG1 Water Consultants Recreation Engineering & Planning Physical Hydraulics: Northwest Hydraulics Consultants First Nations: Dockland Specialists Ltd. Safety: Charlie Walbridge Surveys: Challenger Geomatics Ltd. Concrete Testing: McIntosh Lalani Engineering Ltd.

17 5. Project Schedule Project condition assessment completed in July and August Emergency repairs completed in September Conceptual design completed in 2014 (AMEC). Stakeholder consultation consisting of project newsletters issued to stakeholders in April 2015, January 2016, September 2016, and January 2017, 3 river user workshops, and meetings Preliminary and final design completed in 2015 and Landscape design by O2 Planning + Design completed in Submitted regulatory applications in February First Nations consultation from May 2016 to July 2016.

18 5. Project Schedule (Cont d) Received all regulatory approvals by August Construction contract awarded to Bluebird Contracting Services Inc. in August Construction started in August Substantial Performance of the Work: April 30, 2018 Total Performance of the Work: June 1, 2018

19 6. BIA, Regulatory Applications and Approval Process Biophysical Impact Assessment Soils and Terrain Salvage and import topsoil, seed, ECB Heritage Resources Clearance from ACT Hydrology and River Morphology Navigation NPA approval Vegetation Tree compensation Wildlife and Wildlife Habitat Bird nesting season Fish and Fish Habitat

20 6. BIA (Continued) Fish and Fish Habitat Bio-engineering slope treatment Reinstate upstream portage side channel fish habitat Net fish habitat gain not accounting for reinstating upstream fish passage BIA provided an assessment of temporary and residual effects and proposed mitigations. BIA presented a rating of residual effects and their relative significance. Identified cumulative effects. BIA presented proposed environmental monitoring during, and after, construction and commissioning.

21 6. BIA, Regulatory Applications and Approval Process Regulatory Applications and Approvals Met with AEP and DFO in February 2016, prior to submitting application, to discuss fisheries. Submitted regulatory applications to AEP, DFO, Transport Canada in February Met with AEP in April 2016 to present Issued for Tender Drawings, BIA, and review Water Act Application. Received Historical Resources Clearance in June Received Navigation Protection Program approval in August Received AEP Water Act Approval in August Received DFO Authorization in August 2016.

22 6. BIA, Regulatory Applications and Approval Process Construction started in August 2016 and is to be completed by June Water Act Approval is 156 pages long! Collaborative approach for construction contractor to prepare ECO Plan, Care of Water Plan, Turbidity Monitoring plan, Tree Protection Plan, etc. KCB s environmental scientist supporting construction for environmental compliance.

23 7. Work Restrictions Hours of work: 7 am to 7 pm Monday to Saturday. 9 am to 7 pm on Sundays and statutory holidays. Do not perform instream work activities between May 1 and July 15 and September 16 and April 5 of any year. Do not interfere with Western Headworks operation. AEP opens the sluiceway gates from October 1 to April 20 each year. Gates closed from April 21 to October 1. If requested, AEP will operate the sluiceway gates to divert river flows through the sluiceway and not over the weir. Schedule construction activities such that no more than 2 LWC offset deflectors or 2 LWC drop structure foundations and adjacent LWC pools are dewatered at a time.

24 7. Work Restrictions Complete HWC Drops #3L, #3R, and #4 on or before April 5, Complete the new LWC, except for placing boulder concrete at locations specified in the Contract Documents by August 1, Initial commissioning of the new LWC scheduled from August 1 to 15, Pathways within the Site Limits will not be closed during construction. Traffic accommodation strategy to facilitate construction access across and on pathways.

25 8. Care of Water Detailed care of water plans were required. The temporary river diversion channel was included in the construction drawings and paid under unit prices. Proposed isolation plans (i.e. temporary river diversion channel and cofferdam sequence) were included in the Water Act Application. Minimum top of cofferdam elevations were specified to aid contractors in preparing their bids. Contractor required to prepare an EPP for major runoff events and cofferdam overtopping. Contractor to perform turbidity monitoring required during construction (maximum allowable TSS is <25 mg/l above background). Placement of Bedding 5B, Riprap (all zones) in restricted depths of non-flowing (i.e. standing) water is permitted. Placement of Riprap 6C and Boulders 7B in HWC Pool #2 in flowing water is permitted.

26 Isolation Plans August 2016 to April 2017 Contractor could propose changes to the isolation plans but an amendment to the Water Act Approval would be required at no cost to the Minister. April 2017 to April 2018

27 Instream Construction Temporary River Diversion Drone video footage courtesy of Bluebird Contracting Services Ltd.

28 Temporary River Diversion Channel

29 Drone video footage courtesy of Bluebird Contracting Services Ltd. Isolation and Fish Rescue

30 HWC Drop #4 Construction Drone video footage courtesy of Bluebird Contracting Services Ltd.

31 10. Questions?

COTTON CREEK CULVERT REPLACMENT

COTTON CREEK CULVERT REPLACMENT COTTON CREEK CULVERT REPLACMENT Integrating Mobility with Environmental Innovation Located along a scenic section of Highway 3/95 in British Columbia, Moyie Bluffs, a 6.5 km stretch of inland highway had

More information

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California Final Report September 2005 Prepared by Center for Ecosystem Management and Restoration, Oakland,

More information

Appendix D. Fisheries and Oceans Canada (DFO) Letter of Advice

Appendix D. Fisheries and Oceans Canada (DFO) Letter of Advice The City of Winnipeg Bid Opportunity No. 851-2017 Template Version: C420170317 - RW Appendix D Fisheries and Oceans Canada (DFO) Letter of Advice Fisheries and Oceans Canada Pêches et Océans Canada 103-1800

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Table D1: WC-R1 to WC-R3 (Wilket Creek Park)

Table D1: WC-R1 to WC-R3 (Wilket Creek Park) APPENDIX D Table D1: WC-R1 to WC-R3 (Wilket Creek Park) Category of Consideration Criteria Alternative 1 Do Nothing Alternative 2 Local Improvements Alternative 3 Channel Realignment Natural Geomorphic

More information

Strategies to Mitigate Scour Critical Structures

Strategies to Mitigate Scour Critical Structures U.S. Department of Transportation Federal Highway Administration Strategies to Mitigate Scour Critical Structures Dan Ghere Hydraulics Engineer (708) 283-3557 dan.ghere@dot.gov Support Material HEC 23,

More information

Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 DRAFT. Draft Feasibility Study Report with Integrated Environmental Assessment

Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 DRAFT. Draft Feasibility Study Report with Integrated Environmental Assessment Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 Draft Feasibility Study Report with Integrated Environmental Assessment St. Paul District U.S. Army Corps of Engineers March 2018

More information

Temporary Watercourse Crossing: Fords

Temporary Watercourse Crossing: Fords Temporary Watercourse Crossing: Fords DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Amisk Hydroelectric Project Update

Amisk Hydroelectric Project Update Amisk Hydroelectric Project Update AHP Development Corporation (AHP) is providing an update on the Amisk Hydroelectric Project ( Amisk /the Project ). Amisk is a proposed run-of-river hydroelectric project,

More information

FORM B: DAMMING AND DIVERSION OF WATER

FORM B: DAMMING AND DIVERSION OF WATER APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan

More information

Calgary River Users Alliance

Calgary River Users Alliance Calgary River Users Alliance A review of designated boat ramps Current Designated Boat Launches West Baker Park Shouldice Park Cushing Bridge / 17 Ave. Se Graves Bridge / Glenmore Trail Quarry Park Fish

More information

Wetted Perimeter Assessment Shoal Harbour River Shoal Harbour, Clarenville Newfoundland. Submitted by: Submitted to: January 8, 2003 TF05205

Wetted Perimeter Assessment Shoal Harbour River Shoal Harbour, Clarenville Newfoundland. Submitted by: Submitted to: January 8, 2003 TF05205 Shoal Harbour, Clarenville Newfoundland Submitted by: James H. McCarthy AMEC Earth & Environmental Limited 95 Bonaventure Ave. St. John s, NL A1C 5R6 Submitted to: Mr. Kirk Peddle SGE-Acres 45 Marine Drive

More information

ADDENDUM #1. PROJECT: Montrose Water Sports Park Construction BID NO: FROM: Scott Murphy DATE: August 15, 2014

ADDENDUM #1. PROJECT: Montrose Water Sports Park Construction BID NO: FROM: Scott Murphy DATE: August 15, 2014 ADDENDUM #1 PROJECT: BID NO: 14-038 FROM: Scott Murphy DATE: Questions and Answers 1. Is angular or rounded rock wanted for this project? Answer: All foundation and pool armoring rock shall be angular.

More information

Beaver Creek Hydrology, LLC. Franklin, Tennessee

Beaver Creek Hydrology, LLC. Franklin, Tennessee Beaver Creek Hydrology, LLC. Franklin, Tennessee The Harpeth River Blueway Problems with Harpeth River EPA s 303(d) Listed for siltation, habitat alteration, nutrient enrichment and low dissolved oxygen

More information

2013 BARGE ALLISION AT MARSEILLES LOCK AND DAM MARSEILLES, ILLINOIS

2013 BARGE ALLISION AT MARSEILLES LOCK AND DAM MARSEILLES, ILLINOIS 2013 BARGE ALLISION AT MARSEILLES LOCK AND DAM MARSEILLES, ILLINOIS 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 1 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

JOINT PUBLIC NOTICE. ATTN: Jeff Smaka 800 Municipal Drive Farmington, New Mexico 87401

JOINT PUBLIC NOTICE. ATTN: Jeff Smaka 800 Municipal Drive Farmington, New Mexico 87401 Albuquerque District JOINT PUBLIC NOTICE Application Number: SPA-2015-00366-ABQ Date: October 19, 2015 Comments Due: November 19, 2015 SUBJECT: The U.S. Army Corps of Engineers, Albuquerque District, (Corps)

More information

Application for Paragraph 35(2)(b) Fisheries Act Authorization for Workforce Accommodation Centre Revision 1, November 2015

Application for Paragraph 35(2)(b) Fisheries Act Authorization for Workforce Accommodation Centre Revision 1, November 2015 Application for Paragraph 35(2)(b) Fisheries Act Authorization for Workforce Accommodation Centre The copyright of this document is vested in LNG Canada Development Inc. All rights reserved. 8. FISH HABITAT

More information

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Project Authorization USDA's Small Watershed Program is carried out under the

More information

Public Information Centre September 19 th, 2017

Public Information Centre September 19 th, 2017 Public Information Centre September 19 th, 2017 WELCOME! Public Information Centre for the Maple Hill Creek Rehabilitation Class Environmental Assessment Please take the time to sign our sign in sheet

More information

30-DAY PUBLIC NOTICE EMERGENCY STREAMBANK PROTECTION PROJECT Connecticut River Lyme, New Hampshire

30-DAY PUBLIC NOTICE EMERGENCY STREAMBANK PROTECTION PROJECT Connecticut River Lyme, New Hampshire 696 Virginia Road Concord, MA 01742-2751 Public Notice In Reply Refer to: Mr. Michael Narcisi nae-pn-nav@usace.army.mil Planning Division Date: January 17, 2019 Comment Period Closes: February 15, 2019

More information

Travers Reservoir Rehabilitation Project Irrigation Technical Conference Lethbridge, AB June 2, 2010

Travers Reservoir Rehabilitation Project Irrigation Technical Conference Lethbridge, AB June 2, 2010 Travers Reservoir Rehabilitation Project 2010 Irrigation Technical Conference Lethbridge, AB June 2, 2010 Location Plan Western Irrigation District Headworks CALGARY Eastern Irrigation District Headworks

More information

Ceresco Dam Removal Project. Michigan Watershed Summit March 25, 2015 Luke Trumble, P.E., MDEQ-WRD Jay Wesley, MDNR-Fisheries

Ceresco Dam Removal Project. Michigan Watershed Summit March 25, 2015 Luke Trumble, P.E., MDEQ-WRD Jay Wesley, MDNR-Fisheries Ceresco Dam Removal Project Michigan Watershed Summit March 25, 2015 Luke Trumble, P.E., MDEQ-WRD Jay Wesley, MDNR-Fisheries Outline Overview of Ceresco Dam History Public Process Funding Dam Removal Ecosystem

More information

ENVIRONMENTAL RESOURCE PERMIT APPLICATION

ENVIRONMENTAL RESOURCE PERMIT APPLICATION ENVIRONMENTAL RESOURCE PERMIT APPLICATION SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT 2379 BROAD STREET, BROOKSVILLE, FL 34604-6899 (352) 796-7211 OR FLORIDA WATS 1 (800) 423-1476 SECTION E INFORMATION

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information

REQUEST FOR CONSTRUCTION BIDS February 22, 2010

REQUEST FOR CONSTRUCTION BIDS February 22, 2010 REQUEST FOR CONSTRUCTION BIDS February 22, 2010 Roaring Branch Channel and Floodplain Restoration Project 1.0 Project Background Roaring Branch (watershed area ~ 41 square miles) flows generally west through

More information

Oatka Creek Stream Stabilization and Habitat Restoration Project Narrative

Oatka Creek Stream Stabilization and Habitat Restoration Project Narrative Oatka Creek Stream Stabilization and Habitat Restoration Project Narrative This project was started from a previous Great Lakes Grant to identify concerns in the Oatka and Black Creek watersheds. Through

More information

Conceptual-Level Cost Estimates Arkansas River Corridor Dam Improvement and River Bank Stabilization Projects

Conceptual-Level Cost Estimates Arkansas River Corridor Dam Improvement and River Bank Stabilization Projects TECHNICAL MEMORANDUM Conceptual-Level Cost Estimates Arkansas River Corridor Dam Improvement and River Bank Stabilization Projects TO: COPIES: PREPARED BY: Tulsa County File CH2M HILL DATE: September 2,

More information

STUDY 7.0 FISH PASSAGE

STUDY 7.0 FISH PASSAGE STUDY 7.0 FISH PASSAGE STUDY 7.0 FISH PASSAGE... 7-1 1. GOALS AND OBJECTIVES OF STUDY... 7-1 2. RELEVANT RESOURCE MANAGEMENT GOALS... 7-2 3. BACKGROUND AND EXISTING INFORMATION... 7-2 4. PROJECT NEXUS...

More information

GUIDE TO THE CODE OF PRACTICE FOR WATERCOURSE CROSSINGS, INCLUDING GUIDELINES FOR COMPLYING WITH THE CODE OF PRACTICE

GUIDE TO THE CODE OF PRACTICE FOR WATERCOURSE CROSSINGS, INCLUDING GUIDELINES FOR COMPLYING WITH THE CODE OF PRACTICE GUIDE TO THE CODE OF PRACTICE FOR WATERCOURSE CROSSINGS, INCLUDING GUIDELINES FOR COMPLYING WITH THE CODE OF PRACTICE May 2000 Revised April 2001 TABLE OF CONTENTS Page 1. Introduction 3 2. Topics in the

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

ROLE OF THE FIRM IN THE PROJECT

ROLE OF THE FIRM IN THE PROJECT PROJECT DESCRIPTION Lake Loramie Dam is a Class I dam located in Lake Loramie State Park in Minster, Ohio. Lake Loramie originally served as the high feeder water supply for the Miami-Erie Canal that began

More information

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM U.S. ARMY CORPS OF ENGINEERS, NEW ENGLAND DISTRICT CONCORD, MA PROJECT: Northfield Brook Dam, Naugatuck River

More information

RIVER RIPARIAN CONNECTIVITY & HABITAT SECTION 506 CHICAGO, IL

RIVER RIPARIAN CONNECTIVITY & HABITAT SECTION 506 CHICAGO, IL CHICAGO DISTRICT LEADERS IN CUSTOMER CARE RIVER RIPARIAN CONNECTIVITY & HABITAT SECTION 506 CHICAGO, IL Civil Engineering Appendix Preliminary Submittal ATR Review 11 January 2016 CELRC-Civil Engineering

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 NOVEMBER 2012 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp Geneva Dam Design of a Steep, Temporary, Riprap Ramp A Run-of of-river Dam Analysis for Geneva Dam Credit to: Yu-Chun Su, Ph.D., P.E., CFM David T. Williams. Ph.D., P.E, CFM Presentation Purpose History

More information

Transportation Association of Canada Environmental Achievement Award Nomination Submission:

Transportation Association of Canada Environmental Achievement Award Nomination Submission: Transportation Association of Canada Environmental Achievement Award Nomination Submission: Highway 26 New Wildlife Passage and Enhancements Ontario Ministry of Transportation, Central Region Nominees:

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

General Construction

General Construction General Construction Terms and Conditions: 1. Flagging sensitive areas. The action area will be flagged to identify sensitive resource areas, such as the extent of herbicide buffers, areas below ordinary

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

TENDER NO TABULATION OF TENDERS INFRASTRUCTURE AND TRANSPORTATION SUMMARY OF PRICES CONTRACTOR SECTION 1 SECTION 2 BID TOTAL

TENDER NO TABULATION OF TENDERS INFRASTRUCTURE AND TRANSPORTATION SUMMARY OF PRICES CONTRACTOR SECTION 1 SECTION 2 BID TOTAL FOR: Bridge Construction (Structures) ROAD NO.: 345 & 445 BRIDGE SITE NO.: 0534-10, 1350-10 SUMMARY OF PRICES CONTRACTOR SECTION 1 SECTION 2 BID TOTAL Armcon Ltd 893,542.68 2,135,575.82 3,029,118.50 M.D.

More information

Meeting with PRRD Board

Meeting with PRRD Board Received DC Office May 11/17 Site C Project Peace River Channel Contouring and Side Channel Enhancement Meeting with PRRD Board Background - The Peace River has fluctuating water levels which can cause

More information

Milestones: September 4 NTP

Milestones: September 4 NTP September September 30, 2018 : Mobilization to site Install Erosion Control Early shop drawing review Material Procurement o Obermeyer Gates o Rip Rap & Boulders o Pedestrian Bridges o Rapid Blocks o Debris

More information

Interesting Solutions for a Culvert Rehabilitation Project in a Sensitive Urban Watershed

Interesting Solutions for a Culvert Rehabilitation Project in a Sensitive Urban Watershed Interesting Solutions for a Culvert Rehabilitation Project in a Sensitive Urban Watershed Jason Stahl, P. Eng., Project Engineer, Amec Foster Wheeler David Sinke, P. Eng., Principal, Transportation Engineering,

More information

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 CONSTRUCTION GUIDELINES

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 CONSTRUCTION GUIDELINES OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 CONSTRUCTION GUIDELINES APRIL 2011 MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 19 - CONSTRUCTION GUIDELINES TABLE OF CONTENTS

More information

Detailed Options Evaluation

Detailed Options Evaluation Appendix F Detailed Options Evaluation 06 Google Category & Criterion Description Measure/Indicator Natural Environment Rating Scale for Measuring Impacts Comparative Evaluation Score Comparative Evaluation

More information

Swan Lake Wetland Mitigation: Restoration/Enhancement Concept Ducks Unlimited Canada August 2017

Swan Lake Wetland Mitigation: Restoration/Enhancement Concept Ducks Unlimited Canada August 2017 Swan Lake Wetland Mitigation: Restoration/Enhancement Concept Ducks Unlimited Canada August 2017 Background: DUC has been contracted by MOTI to compensate for 2,500 m 2 (0.62 ac) of disturbed cattail marsh

More information

Upper Mississippi River Basin Environmental Management Program Workshop

Upper Mississippi River Basin Environmental Management Program Workshop Presentation to the Upper Mississippi River Basin Environmental Management Program Workshop by Kara Mitvalsky Environmental Engineer US Army Corps of Engineers, Rock Island District August 18, 2005 Engineering

More information

Green River Diversion Rehabilitation

Green River Diversion Rehabilitation USDA Natural Resources Conservation Service-Utah Wallace F. Bennett Federal Building 125 S. State Street Room 4010 Salt Lake City, UT 84138-1100 Green River Diversion Rehabilitation National Environmental

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information

Site C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017

Site C Clean Energy Project. Monthly Environmental Monitoring Summary Report - February 2017 Site C Clean Energy Project Monthly Environmental Monitoring Summary Report - February 2017 Prepared by BC Hydro Submitted May 8, 2017 Page 1 of 17 Table of Contents Introduction... 4 Project Progress...

More information

TOLEDO BEND PROJECT FERC NO DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES

TOLEDO BEND PROJECT FERC NO DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES TOLEDO BEND PROJECT FERC NO. 2305 DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES May 2011 Copyright 2011.Sabine River Authority of Texas and Sabine River

More information

Special Provision - Turbidity

Special Provision - Turbidity 1. DEFINITIONS Special Provision - Turbidity Instream Construction Activity Isolated Construction Activity Site Isolation Visually Conspicuous Plume Accidental Occurrence Any planned instream construction

More information

Step-Pool Creation to Restore Fish Passage and Riparian Health

Step-Pool Creation to Restore Fish Passage and Riparian Health Step-Pool Creation to Restore Fish Passage and Riparian Health Jenny Kindig Water Resources Engineer Denny Mengel, Senior Environmental Scientist Steve Miller, Water Resources Engineer Gloria Beattie,

More information

Temporary Stream Crossing

Temporary Stream Crossing Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Temporary Stream Crossing

Temporary Stream Crossing Temporary Stream Crossing NS-4 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution

More information

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT SASKATCHEWAN WATER CORPORATION BUFFALO POUND NON-POTABLE WATER SUPPLY SYSTEM EXPANSION PROJECT Introduction

More information

Eco-engineering on the Edge:

Eco-engineering on the Edge: Eco-engineering on the Edge: Decision Making for Stream Restoration and Stabilization in High Profile or Risk Environments Dan Salas, Ecologist Cardno JFNew Types of Risk Physical/Structural = Property

More information

What is the Terms of Reference?

What is the Terms of Reference? What is the Terms of Reference? Framework for content of the Environmental Assessment Certificate Application Provides the scope of technical studies and consultation processes with the public and First

More information

Channel stability and capacity considerations Ensure that vertical and lateral channel stability is adequate.

Channel stability and capacity considerations Ensure that vertical and lateral channel stability is adequate. Selecting an appropriate design Stream form and function Diversions should accommodate natural stream geometry and channel dynamics. Evaluate stream width-to-depth ratio, and match these dimensions if

More information

Memorandum BACKGROUND AND PURPOSE

Memorandum BACKGROUND AND PURPOSE COTTONWOOD WETLANDS Memorandum William P. Ruzzo, PE, LLC 6641 West Hamilton Drive, Lakewood, Colorado 80227 (303) 985-1091 (303) 989-6561 fax bill.ruzzo@comcast.net To: Chuck Reid, Manager, CCBWQA Cc:

More information

Summary of Relief Sought by Transpower New Zealand Limited

Summary of Relief Sought by Transpower New Zealand Limited Summary of Relief Sought by Transpower New Zealand Limited Relief sought in Transpower s further submission and supported by evidence The following consolidates the amendments to the Proposed Southland

More information

CREEK RESTORATION/EROSION PROTECTION WORKS. General Submission Requirements

CREEK RESTORATION/EROSION PROTECTION WORKS. General Submission Requirements COMPLETE APPLICATION CHECKLIST Jan 2016 CREEK RESTORATION/EROSION PROTECTION WORKS The following checklist has been compiled to assist the applicant in preparing their application for approval pursuant

More information

Fish Passage Planning and Design

Fish Passage Planning and Design Fish Passage Planning and Design Culvert Fishway Planning and Design Guidelines Part A About These Guidelines Ross Kapitzke James Cook University School of Engineering and Physical Sciences April 2010

More information

Mill Pond Dam Modifications Feasibility Study

Mill Pond Dam Modifications Feasibility Study May 1, 2013 Mill Pond Dam Modifications Feasibility Study Village of Goodrich, MI Table of Contents 1. Background...1 1.1 Michigan Department of Environmental Quality (MDEQ) Regulation Dam Safety Unit

More information

Environmental, geotechnical and hydrotechnical services PIPELINE SERVICES

Environmental, geotechnical and hydrotechnical services PIPELINE SERVICES Environmental, geotechnical and hydrotechnical services PIPELINE SERVICES KCB offers excellent quality, service and rates and have consistently remained either on or under budget. Their reports are clear,

More information

Construction of Dariali HEPP. Reinstatement Plan

Construction of Dariali HEPP. Reinstatement Plan Construction of Dariali HEPP Reinstatement Plan 2016 Table of Content 1. Introduction... 3 2. Site Clean-up... 4 3. Headwork Site Reinstatement... 4 4. Reinstatement Of The Pipeline Corridor.9 5. Cable

More information

Public Notice: Application for Permit

Public Notice: Application for Permit U.S. ARMY CORPS Of Engineers Walla Walla District 201 North Third Avenue Walla Walla, WA 99362-1876 Public Notice: Application for Permit APPLICATION NO.: NWW-2014-00446 WATERWAY: Snake River APPLICANT:

More information

Arkansas River Corridor Projects

Arkansas River Corridor Projects T E C H N I C A L M E M O R A N D U M Arkansas River Corridor Projects Concept Alternatives for Gates, Dam Spillway, Whitewater and Roughened Channel Fish Passage TO: Tulsa County COPIES: FROM: File McLaughlin

More information

Labrador Iron Mines Holdings Limited

Labrador Iron Mines Holdings Limited Labrador Iron Mines Holdings Limited Rehabilitation and Closure May 10, 2016 Re-establishing Flow to the Un-named Tributary Evolution of the Un-named Tributary James Mine Dewatering was required to lower

More information

498 AVE BRIDGE HYDRAULICS INVESTIGATION OF IMPACTS RELATED TO TOWN OF HIGH RIVER FLOOD MITIGATION WORKS

498 AVE BRIDGE HYDRAULICS INVESTIGATION OF IMPACTS RELATED TO TOWN OF HIGH RIVER FLOOD MITIGATION WORKS 498 AVE BRIDGE HYDRAULICS INVESTIGATION OF IMPACTS RELATED TO TOWN OF HIGH RIVER FLOOD MITIGATION WORKS Submitted to: M.D. of Foothills No. 31 High River, Alberta Submitted by: Amec Foster Wheeler Environment

More information

SEDIMENT MANAGEMENT PLAN

SEDIMENT MANAGEMENT PLAN SEDIMENT MANAGEMENT PLAN DRAFT October 2012 October 2012 POINTE DU BOIS SPILLWAY REPLACEMENT PROJECT Sediment Management Plan DRAFT Report Prepared for October 2012 October 2012 PREFACE Manitoba Hydro

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW

COON CREEK WATERSHED DISTRICT PERMIT REVIEW 16-054 Woodland Creek Wetland Banking Restoration Project, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 11 FILE NUMBER: 16-054 ITEM: Woodland Creek

More information

Reclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template

Reclamation Manual Design Data Collection Guidelines Chapter 5 Typical Design Data Package Template Reclamation Manual The Introduction (Chapter 1) for these design data collection guidelines contains additional information concerning: preparing a design data collection request, design data collection

More information

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CECW-ED Regulation No. 1110-2-8152 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design PLANNING AND DESIGN OF TEMPORARY COFFERDAMS AND BRACED EXCAVATIONS

More information

Project Alternatives: The Parsons Sill Project History

Project Alternatives: The Parsons Sill Project History Project Alternatives: The Parsons Sill Project History Project Impetus Over the past 150 years, human actions have altered the tidal, freshwater, and sediment processes that are essential to support and

More information

Substation Developments Environmental Guidelines Checklist for Applicants

Substation Developments Environmental Guidelines Checklist for Applicants Substation Developments Environmental Guidelines Checklist for Applicants Effective date: February 1, 2016 These guidelines are intended to be used in conjunction with the flowchart in Figure 1 which conceptually

More information

404(b)(1) EVALUATION

404(b)(1) EVALUATION 404(b)(1) EVALUATION SECTION 404(b)(1) EVALUATION DETAILED PROJECT REPORT AND ENVIRONMENTAL ASSESSMENT POMEROY SECTION 14 EMERGENCY STREAMBANK PROTECTION PROJECT POMEROY, OH I. INTRODUCTION As required

More information

SPECIAL PROVISIONS WATERWAY PERMITS CONDITIONS PID: Date: 3/8/18 C-R-S: UNI-TR

SPECIAL PROVISIONS WATERWAY PERMITS CONDITIONS PID: Date: 3/8/18 C-R-S: UNI-TR SPECIAL PROVISIONS WATERWAY PERMITS CONDITIONS C-R-S: UNI-TR 0308-00.57 PID: 99910 Date: 3/8/18 Special Provisions: UNI-TR 0308-00.57, PID 99910 Page 2 of 7 1. Waterway Permits Time Restrictions: USACE

More information

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012 Bridge Planning Updates Bridge Planning Practitioners Workshop April 2012 Bridge Website Bridge Website Bridge Website Bridge Website BPG 11 Stormwater Management at Rural Bridges Released July 2010 Documents

More information

Golf Course and Recreational Facilities Best Management Guidelines. Regional Official Plan Guidelines

Golf Course and Recreational Facilities Best Management Guidelines. Regional Official Plan Guidelines Golf Course and Recreational Facilities Best Management Guidelines Regional Official Plan Guidelines Halton Region Official Plan Guidelines The Regional Official Plan (ROP) is Halton s guiding document

More information

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Version 1.0 April 2008 This document is available from the Yukon Placer Secretariat, Yukon

More information

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION 1 Contents Introduction 3 Delegation to the NEB 3 Assessments and regulatory guidance 4 Provincial requirements

More information

Ducks Unlimited M&T Ranch / Llano Seco Intake Project Final Alternatives

Ducks Unlimited M&T Ranch / Llano Seco Intake Project Final Alternatives Ducks Unlimited M&T Ranch / Llano Seco Intake Project Final Alternatives M&T Ranch / Llano Seco Intake Project Final Alternatives Draft Engineering Analysis Technical Memorandum Ducks Unlimited September,

More information

D EROSION AND SEDIMENT CONTROL. Table of Contents

D EROSION AND SEDIMENT CONTROL. Table of Contents Table of Contents D1. GENERAL... 1 D2. OBJECTIVE... 1 D3. REFERENCE MATERIAL... 1 D4. REGULATORY REQUIREMENTS... 1 D5. EROSION AND SEDIMENT CONTROL (ESC) PLANS... 2 D5.1 Goals and Objectives:... 2 D5.2

More information

STANDARDS TO ADDRESS THE ENVIRONMENTAL FACTORS

STANDARDS TO ADDRESS THE ENVIRONMENTAL FACTORS 94-412 SACO RIVER CORRIDOR COMMISSION Chapter 103: STANDARDS TO ADDRESS THE ENVIRONMENTAL FACTORS SUMMARY: All projects approved must show no unreasonable a) degradation of water and water quality, b)

More information

Mike Jastremski, CFM Watershed Conservation Director

Mike Jastremski, CFM Watershed Conservation Director Planning for Flood Resilient and Fish Friendly Road-Stream Crossings in CT s Northwest Hills Mike Jastremski, CFM Watershed Conservation Director Presentation Outline Project area Climate threats Field

More information

SITE C14: H771:04 Slide and Culvert Distress

SITE C14: H771:04 Slide and Culvert Distress SITE C14: H771:04 Slide and Culvert Distress LEGAL LOCATION: NW34-45-1-W5 REFERENCE LOCATION ALONG HIGHWAY: UTM COORDINATES (NAD 83): N 5,868,192 E 696,622 AT FILE: H771:04 AT PLAN & PROFILE: Date of Initial

More information

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat S.R. 4007, Section 14B PADEP Environmental Assessment Form Description of Aquatic Habitat Cresheim Creek is the only water resource that exists within the project area. No jurisdictional wetlands were

More information

Annex Q Potlatch Corporation Water Intake Modification Plan

Annex Q Potlatch Corporation Water Intake Modification Plan Annex Q Potlatch Corporation Water Intake Modification Plan Figure Q1 Figure Q2 Site Plans Johnson Screen Installations H:\WP\1346\Appendices\FEIS\D - Drawdown\CamRdy\App_D.doc Annex Q: Potlatch Corporation

More information

Our reference BGS-0003-c. Direct line +31(0)

Our reference BGS-0003-c. Direct line +31(0) Deltares Enabling Delta Life,J Alberta Environment and Parks Resilience and Mitigation Attn. Mr. A. Wilson 4th Floor, 9920-108 Street EDMONTON, AB T5K 2M4 Canada 7 October 2015 From Hans van Duijne Our

More information

Irrigation Structures 1

Irrigation Structures 1 CHAPTER 8 Irrigation Structures 1 Dr. M. R. Kabir Professor and Head, Department of Civil Engineering University of Asia Pacific (UAP), Dhaka LECTURE 20 Diversion Head Works Definition: The works, which

More information

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below.

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below. SEDIMENT CONTROL NOTES 1.0 GENERAL 1.1 The Developer and Contractor shall comply with the requirements of all regulatory authorities, federal, provincial and municipal government departments including

More information

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project

More information

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Version 1.3 November 2010 This document is available from: Yukon Placer Secretariat, 206B

More information

Proposed Maplewood Marine Restoration Project Discussion guide and feedback form

Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Vancouver Fraser Port Authority Habitat Enhancement Program Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Public consultation September 24 October 12, 2018 Feedback form

More information

Alberta Transportation. Environmental Protection Plan for the Planning and Construction of Water and Transportation Projects

Alberta Transportation. Environmental Protection Plan for the Planning and Construction of Water and Transportation Projects Alberta Transportation Environmental Protection Plan for the Planning and Construction of Water and Transportation Projects January 9, 2009 INFTRA Table of Contents Page Table of Contents... i 1.0 INTRODUCTION...1

More information

NS-5 CLEAR WATER DIVERSION. Objectives

NS-5 CLEAR WATER DIVERSION. Objectives CLEAR WATER DIVERSION NS-5 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management - WM DESCRIPTION

More information

Honeysuckle Reservoir decommissioning

Honeysuckle Reservoir decommissioning Honeysuckle Reservoir decommissioning Christopher Dwyer Earth Tech, PO Box 165 Wangaratta, 3676. Web: www.earthtech.com.au, Email: chris.dwyer@earthtech.com.au Abstract Often significant investment is

More information

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C90593066 PARTNERS Alabama Department of Environmental Management Cawaco

More information