1 UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS ARCHITECTURAL AND ENGINEERING SERVICES FOR COBURN HALL ADDITION AND RENOVATION THE UNIVERSITY OF MASSACHUSETTS LOWELL UMBA #16-L1 December 23, 2016 Proposals Due: January 12, 2017 at 2:00pm

2 University of Massachusetts Building Authority UMass Lowell Coburn Hall Addition & Renovation RFP for Architectural and Engineering Services Addendum No. 1 ADDENDUM NO. 1 NOTICE TO RESPONDENTS In accordance with the Request for Proposals (the RFP ) issued by the University of Massachusetts Building Authority (the Authority ) on December 14, 2016 for Architectural and Engineering Services for the Coburn Hall Addition & Renovation at the University of Massachusetts Lowell (the Project ), the Authority is issuing this Addendum No. 1, which includes modifications to the RFP, answers to questions received in response to the RFP and the Pre-Proposal Conference sign-in sheet. Except as specifically modified by the information contained in this Addendum No. 1, the RFP remains unchanged. A. Attachment A to this addendum contains additional narrative to assist designers in aligning their proposals to the anticipated project scope. The four paragraph narrative provides additional language to the RFP on page 6 of 15. The language of Attachment A shall be inserted in Part V, Section B. Architectural and Building Systems Upgrades and Improvements following the paragraph beginning The study and schematic design phases. B. Attachment B to this addendum contains the questions received in response to the RFP and Pre-Proposal Briefing. Answers are provided accordingly. C. Attachment C to this addendum contains the sign-in sheets from the Pre-Proposal Briefing. END OF ADDENDUM NO. 1

3 University of Massachusetts Building Authority UMass Lowell Coburn Hall Addition & Renovation RFP for Architectural and Engineering Services Addendum No. 1 Attachment A to Addendum 1 Language to be inserted into Project Description of the RFP

4 RFP page 6 of 15: The following language shall be inserted in Part V, Section B. Architectural and Building Systems Upgrades and Improvements following the paragraph beginning The study and schematic design phases The proposed Coburn project has evolved from the project that was envisioned at the time of the SMMA study in two important ways. First, the overall project budget and scope has increased significantly, enabling the campus to contemplate a more substantial initiative than the infrastructure pod addition that was under consideration at that time. Second, the overall program requirements are better understood and it is unlikely that a program addition would exceed 20,000 SF (as opposed to the 30,000 SF previously contemplated). The University is currently developing a program in-house as part of a larger master planning effort to facilitate the growth of the South Campus colleges and desired academic adjacencies. It is expected that the results of this programming effort will be provided to the selected designer at the start of the project in February. This information is expected to identify the academic department(s) and college dean(s) offices which will be housed in the renovated Coburn Hall. It is also expected to identify the number of faculty offices, department suites, and the component spaces desired in department suites and deans suites. The designer will be expected to confirm this program and extrapolate code-mandated upgrades, plumbing fixture counts, etc. The objective of the study and schematic design phases of the project will be to identify and evaluate multiple options for how to accommodate the program, address the code and accessibility deficiencies of the building, retain a maximum number of existing teaching spaces, and implement some renovation scope within the available budget using differing combinations of renovation and added square footage. Each option should consider costs, code implications, space efficiencies, building systems improvements required and realized, and schedule / constructability, among other factors. The campus will develop a project Steering Committee including the Dean(s) and Chair(s) of the departments which will ultimately be housed in the renovated Coburn, which will be engaged as part of the project. The campus will also work with the designers and OPM to host open house(s) for the faculty who will ultimately be housed in the renovated Coburn to obtain their input during the study and design phases of the project. This project is NOT simply an infrastructure pod project. It is also NOT simply a historic preservation rehabilitation project. Although historic preservation is important for this signature building and appropriate standards and practices should be employed to protect and celebrate the architectural character and features of the building, the primary objectives are to modernize the building to accommodate the intended uses.

5 University of Massachusetts Building Authority UMass Lowell Coburn Hall Addition & Renovation RFP for Architectural and Engineering Services Addendum No. 1 Attachment B to Addendum 1 Q 1 A 1 The minimum criteria in Section X, Item C - the UMBA is requiring submitting firms to put forward experience on at least 2 higher education projects within the last 7 years with a construction cost greater than $25M. Would the UMBA be willing to accept projects within the last 7 years with a construction cost greater than $25M which are not necessarily academic but include similar planning, design, and historic restoration experience? Delete the language of Section X, Item C and replace with the following: Responding firm and key project members (PIC, PM and Project Architect) significant prior experience on at least two (2) Higher Education projects, each successfully completed within the last seven (7) years of similar size, type, scope and complexity, to that proposed for this Project, with a construction cost of greater than $20,000, In lieu of the above, UMBA is willing to accept at least two (2) relevant and comparable projects (retrofit / addition / renovation) successfully completed within the last seven (7) years of similar size, type, scope and complexity, to that proposed for this Project, with a construction cost of greater than $20,000, AND Higher Education experience on 3 to 5 projects with construction cost greater than $10,000, Q 2 A 2 Q 3 Is there structural information available for this building? UML has a variety of background information on the building which it will share with the selected designer. A 2007 schematic design package for renovations that included structural drawings to support the renovations was prepared but not implemented. However, the campus has not been able to locate any then-existing structural conditions assessment or documentation. The campus does not possess original construction documents for Coburn Hall. The list of sub-consultant disciplines is inconsistent between J Sub-consultant Firms (on pages 11 12) and the Attachment B List of Architect s Consultants included in the Agreement for Professional Services between Owner and Architect. Can you please clarify whether the additional disciplines listed in Attachment B of the contract are required for this project? A 3 Submit per RFP, Section XI, Item J.

6 University of Massachusetts Building Authority UMass Lowell Coburn Hall Addition & Renovation RFP for Architectural and Engineering Services Addendum No. 1 Q 4 A 4 In vetting our sub team, we have a person in one discipline who was recently part of a much larger firm but is now independent. Although the person s new firm does not have Commonwealth experience, could recent individual work with the former firm count toward their qualification? Yes, provided that person actually has direct project experience and had a major role in preparing the documents on Commonwealth of Massachusetts projects.

7 University of Massachusetts Building Authority UMass Lowell Coburn Hall Addition & Renovation RFP for Architectural and Engineering Services Addendum No. 1 Attachment C to Addendum 1 Sign in Sheets from Pre-Proposal Conference December 19, 2016

8 It

9

10

UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY

UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS OWNER S PROJECT MANAGER SERVICES FOR MCGUIRK STADIUM, UPGRADES FOR THE UNIVERSITY OF MASSACHUSETTS AMHERST UMBA PROJECT

More information

BUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION

BUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION I. PURPOSE BUCKNELL UNIVERSITY PROCEDURES FOR RENOVATIONS AND NEW CONSTRUCTION To ensure the proper process to request and obtain approval for all renovation or new construction projects within Bucknell

More information

Career Center Advance Planning/Design Services Code Item 321

Career Center Advance Planning/Design Services Code Item 321 The University of North Carolina at Charlotte Temporary Office Space Facilities Management - Capital Projects Hickory Building (Building #536 on Campus Map) 9316 Mary Alexander Road Charlotte, NC 28223

More information

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018 Question & Answer: #1 The RFP calls for a survey of the building to gain a comprehensive understanding of the existing building, utilities, building systems, occupancies and all existing conditions as

More information

Science Building Advance Planning/Design Services Code Item 301

Science Building Advance Planning/Design Services Code Item 301 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, N.C. 28223-0001 TEL: 704/687-0615 PROJECT: UNC Charlotte Science Building Advance

More information

ADDENDUM NO. 1 REQUEST FOR CLARIFICATIONS/INTERPRETATIONS FOR. RFQ No. 16P3

ADDENDUM NO. 1 REQUEST FOR CLARIFICATIONS/INTERPRETATIONS FOR. RFQ No. 16P3 ADDENDUM NO. 1 REQUEST FOR CLARIFICATIONS/INTERPRETATIONS FOR RFQ No. 16P3 CHAFFEY COMMUNITY COLLEGE DISTRICT ARCHITECTURAL DESIGN SERVICES MEASURE L PROJECT RANCHO CUCAMONGA, CA July 30, 2015 CHAFFEY

More information

UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY

UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY UNIVERSITY OF MASSACHUSETTS BUILDING AUTHORITY ADDENDUM NO. 1 TO REQUEST FOR QUALIFICATIONS TRADE CONTRACTORS CM AT RISK G.L. C. 149A 8 FOR RENOVATION OF EXISTING ACADEMIC BUILDINGS (REAB) FOR THE UNIVERSITY

More information

Student Government Office Renovations Design/Construction Administration Services Code Item 305

Student Government Office Renovations Design/Construction Administration Services Code Item 305 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, NC 28223 Telephone: 704-687-0615 PROJECT: UNC Charlotte Student Government Office

More information

Minnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation

Minnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation Minnesota State Colleges and Universities South Central College Request for Proposals for Commissioning Agent STEM and Healthcare Renovation Date: 12/18/2017 ADDENDUM #1 1. The Sign-In sheet for the voluntary

More information

ADDENDUM NO. 1 November 16, Bid# CL16-GN-0030, Tririga Work Order Implementation Services Project for the University of Massachusetts Lowell

ADDENDUM NO. 1 November 16, Bid# CL16-GN-0030, Tririga Work Order Implementation Services Project for the University of Massachusetts Lowell ADDENDUM NO. 1 November 16, 2015 To all Bidders on the Project Titled: Bid# CL16-GN-0030, Tririga Work Order Implementation Services Project for the University of Massachusetts Lowell UNIVERSITY OF MASSACHUSETTS

More information

NOTICE OF ADDENDUM TO RFQ DOCUMENTS ADDENDUM NO. 01 August 29, 2018 ENGINEERING SERVICES FOR VARIOUS KERN COMMUNITY COLLEGE DISTRICT PROJECTS

NOTICE OF ADDENDUM TO RFQ DOCUMENTS ADDENDUM NO. 01 August 29, 2018 ENGINEERING SERVICES FOR VARIOUS KERN COMMUNITY COLLEGE DISTRICT PROJECTS Construction & Facilities Planning Dept. Bakersfield College, 1801 Panorama, Bakersfield, CA 93305 Program Office: (661) 395-4254 NOTICE OF ADDENDUM TO RFQ DOCUMENTS ADDENDUM NO. 01 August 29, 2018 ENGINEERING

More information

Residence Hall Phase XVI Code Item 308 Code Item 312 Advanced Planning

Residence Hall Phase XVI Code Item 308 Code Item 312 Advanced Planning The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, N.C. 28223-0001 TEL: 704/687-0558 PROJECT: UNC Charlotte Residence Hall Phase

More information

The Lothian Residence Hall Building System Infrastructure Analysis project will develop a phased strategy that will include the following elements:

The Lothian Residence Hall Building System Infrastructure Analysis project will develop a phased strategy that will include the following elements: UNIVERSITY OF CALIFORNIA, RIVERSIDE REQUEST FOR PROPOSAL PRE-DESIGN AND PRE-ENGINEERING PROGRAMMING LOTHIAN RESIDENCE HALL BUILDING SYSTEM INFRASTRUCTURE AND SEISMIC ANALYSIS Introduction The University

More information

RENEWAL/MODERNIZATION FACILITIES REYNOLDS BUILDING #1 COLLEGE OF DESIGN

RENEWAL/MODERNIZATION FACILITIES REYNOLDS BUILDING #1 COLLEGE OF DESIGN Prime DESIGN PHASE SERVICES FOR RENEWAL/MODERNIZATION FACILITIES REYNOLDS BUILDING #1 COLLEGE OF DESIGN Project Scope: $34,000,000 INTRODUCTION The is requesting the services of an ARCHITECTURAL FIRM to

More information

Science Technology Engineering and Mathematics (STEM) Initiative

Science Technology Engineering and Mathematics (STEM) Initiative DEPARTMENT of FACILITIES DESIGN December 17, 2013 and CONSTRUCTION REQUEST for PROPOSAL Science Technology Engineering and Mathematics (STEM) Initiative PRE-CONSTRUCTION SERVICES Facilities Design and

More information

ACEC/MA 15th Annual State Markets Conference

ACEC/MA 15th Annual State Markets Conference University of Massachusetts Building Authority ACEC/MA 15th Annual State Markets Conference April 6, 2017 1 University of Massachusetts Building Authority General Overview 2 Designer Procurement Process

More information

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No.

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No. ADDENDUM NO. 1 Date: January 11, 2017 for RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College BID No. 332 South Orange County Community College District General-All

More information

Project Information. Nominations of Artists. University of Houston

Project Information. Nominations of Artists. University of Houston UNIVERSITY OF HOUSTON SYSTEM SYSTEM WIDE ART ACQUISTION COMMITTEE AGENDA ITEM ITEM: UH University Center Transformation Project Artwork-Artists Nominations DATE PREVIOUSLY SUBMITTED: NA SUMMARY: Nominations

More information

Questions received on Creedmoor PC Major Renovation for Outpatient Residence, Building 70 and DASNY s responses:

Questions received on Creedmoor PC Major Renovation for Outpatient Residence, Building 70 and DASNY s responses: Questions received on Creedmoor PC Major Renovation for Outpatient Residence, Building 70 and DASNY s responses: 1. Will Building 70 be an Article 28 DOH compliant facility? 2. Are the clients/patients

More information

Strategic Planning Consultant Proposal No. P13/9824 Date: July 17, 2013

Strategic Planning Consultant Proposal No. P13/9824 Date: July 17, 2013 Answers to Vendor Questions - Questions are in black, answers are in red. 1. In reference to Section 7 Agreement Page 15 are we to include a copy of this within our returned proposal or will this be executed

More information

Construction Management/Construction Inspection Services

Construction Management/Construction Inspection Services DELAWARE RIVER JOINT TOLL BRIDGE COMMISSION ADMINISTRATION BUILDING 110 WOOD & GROVE STREETS MORRISVILLE, PA 19067 ADDENDUM NO. 1 This Addendum No. 1 gives additional information in connection with the

More information

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards I. INTRODUCTION The Los Angeles Community College District is currently undertaking the largest public sector sustainable building effort in the United States, funded by its Proposition A/AA and J Bond

More information

City of Frederick PURCHASING DEPT.

City of Frederick PURCHASING DEPT. ADDENDUM #4 RFP #12-D CITY OF FREDERICK WWTP ENR UPGRADE March 12, 2012 TO: SUBJECT: REF: All Potential Proposers RFP #12-D, CITY OF FREDERICK WWTP ENR UPGRADE Revised Proposal Closing Date, Submitted

More information

Ohio Public Employees Retirement System. Request for Proposal

Ohio Public Employees Retirement System. Request for Proposal Ohio Public Employees Retirement System For: Consulting Services for Development of the Business Intelligence & Analytics Office Date: 9/11/2017 Project Name: Business Intelligence & Analytics Program

More information

CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS

CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS I. INTRODUCTION The East Rutherford School District is planning to hold a referendum on December 12, 2017 that incorporates facility

More information

Orange Education Center Project Update. Board Of Trustees Meeting November 9, 2015

Orange Education Center Project Update. Board Of Trustees Meeting November 9, 2015 Orange Education Center Project Update Board Of Trustees Meeting November 9, 2015 1 PROJECT BACKGROUND Existing building is 85,130 g.s.f., concrete tilt-up industrial building on 6.37 acres of land. Built

More information

Orange Education Center Project Update. Board of Trustees Meeting February 25, 2019

Orange Education Center Project Update. Board of Trustees Meeting February 25, 2019 Orange Education Center Project Update Board of Trustees Meeting February 25, 2019 1 ORANGE EDUCATION CENTER 2 Topics 1. Need for Adult Education (AE) in Orange 2. Location of AE Center 3. Fiscal Feasibility

More information

KENTUCKY STATE UNIVERSITY

KENTUCKY STATE UNIVERSITY KENTUCKY STATE UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2004-2006 1 Hathaway Hall Renovation Phase II $11,200,000

More information

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register

More information

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN EL CAMINO COLLEGE Facilities Master Plan Report November 2008 PROJECTS IN DESIGN I. Math, Business & Allied Health Building (MBA) The scope of this building is the construction of a new building at the

More information

Program Orientation: Part 2 October 27, :00-2:30 p.m.

Program Orientation: Part 2 October 27, :00-2:30 p.m. Program Orientation: Part 2 October 27, 2017 1:00-2:30 p.m. Cole Forstedt, MS Student Ambassador Program Manager Carly Smith Civic Engagement Specialist Participating Colleges Using Zoom To submit questions,

More information

ADDENDUM NO. 1 Questions and Answers

ADDENDUM NO. 1 Questions and Answers ADDENDUM NO. 1 Questions and Answers Addendum to the Indianapolis Bond Bank RFQ-LJF-2017-004 Request for Qualifications Design and Design Criteria Consulting Services for the Indianapolis-Marion County

More information

Historic Structure Reports. 15 December 2009

Historic Structure Reports. 15 December 2009 St. Elizabeth West Campus Historic Structure Reports and Building Preservation Plans Status t Report 15 December 2009 Wiss, Janney, Elstner Associates, Inc. Work Process and Status Report Archival research

More information

Information Technology Infrastructure Upgrades Advance Planning, Design, & Construction Administration Services Code Item 303

Information Technology Infrastructure Upgrades Advance Planning, Design, & Construction Administration Services Code Item 303 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, N.C. 28223-0001 TEL: 704-687-0615 PROJECT: UNC Charlotte Information Technology

More information

RFP SA 1704 Quality Improvement Consultant - Malcolm Baldrige Excellence Framework. 1. Attachment A: Answers to Questions from Prospective Offerors

RFP SA 1704 Quality Improvement Consultant - Malcolm Baldrige Excellence Framework. 1. Attachment A: Answers to Questions from Prospective Offerors Procurement Department P.O. Box 2266 Woodbridge, Virginia 22195-2266 Fax (703) 335-7954 September 13, 2016 RFP SA 1704 Quality Improvement Consultant - Malcolm Baldrige Excellence Framework Addendum #1

More information

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department ADDENDUM No. 2 DATED JULY 2, 2013 TO THE PROJECT MANUAL and PLANS

More information

CCMS. Construction Cost Management Services. Celebrating 27 Years.. Construction Cost Estimating Expertise

CCMS. Construction Cost Management Services. Celebrating 27 Years.. Construction Cost Estimating Expertise CCMS Construction Cost Management Services Celebrating 27 Years.. Construction Cost Estimating Expertise Credibility and Confidence at Each Stage of the Planning and Design Process CCMS CCMS ensures that

More information

European Union Field School & Internship Program An activity of the Network for European Studies (Canada)

European Union Field School & Internship Program An activity of the Network for European Studies (Canada) INTERNSHIP PROGRAM APPLICATION FOR GRADUATE STUDENTS Applicant s Last Name Applicant s Given Name(s) Home University Department/Faculty INSTRUCTIONS General Information on the Internship Program (graduate

More information

Cone University Center HVAC Modernization Design and Construction Administration Services Code Item 320

Cone University Center HVAC Modernization Design and Construction Administration Services Code Item 320 The University of North Carolina at Charlotte Capital Projects Facilities Management 9201 University City Blvd. Charlotte, N.C. 28223-0001 TEL: 704/687-0615 PROJECT: UNC Charlotte Cone University Center

More information

Bronx Community College. Five-Year Capital Plan FY through FY

Bronx Community College. Five-Year Capital Plan FY through FY Five-Year Capital Plan FY 2019-20 through FY 2023-24 Projects in priority order / costs in $ thousands Project Name FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 (B) Campus-Wide Fire Alarm Replacement DC

More information

WolfWare Standard Operating Practices/Procedures (SOPs) North Carolina State University

WolfWare Standard Operating Practices/Procedures (SOPs) North Carolina State University WolfWare Standard Operating Practices/Procedures (SOPs) North Carolina State University Feature Requests, SOP.WW-WolfWare.002 Authority: Vice Provost for Distance Education and Learning Technology Applications

More information

Addendum 3 publishes and answers questions related to the Request for Qualifications ( RFQ ) issued on November 24, 2014:

Addendum 3 publishes and answers questions related to the Request for Qualifications ( RFQ ) issued on November 24, 2014: www.dot.state.pa.us Date: December 18, 2014 Subject: Questions and Answers Regarding RFQ Solicitation: CNG Fueling for Transit Agencies Partnership Project SOQ Due Date: No later than 11:00 a.m. Eastern

More information

Addendum No. 2 February 19, 2014 City University Construction Fund Engineering Design Services Requirements Contracts RFQ Project No.

Addendum No. 2 February 19, 2014 City University Construction Fund Engineering Design Services Requirements Contracts RFQ Project No. Facilities Planning, Construction, and Management Office of Financial Management Procurement Services 555 West 57 th Street 16 th Floor New York, NY 10019 Tel: 646-664-2700 Addendum No. 2 February 19,

More information

DRAFT September 26th, 2003

DRAFT September 26th, 2003 Harrelson Hall Renovation and Replacement Study DRAFT September 26th, 2003 Summary of Renovation Issues As part of the 2000 Capital Bond Program, funds were allocated for the renovation of Harrelson Hall

More information

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School.

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School. WINDOW REPLACEMENT FOR ARCHITECT'S NO. 2638 NORWOOD ELEMENTARY SCHOOL DOCUMENT 00 9113A - ADDENDUM NO. 1 1.1 PROJECT INFORMATION A. Project Name: Window Replacement for Norwood Elementary School. B. Owner:

More information

PROJECT SPECIFIC QUALIFICATION STATEMENT REQUIREMENTS for CONSTRUCTION MANAGEMENT SERVICES

PROJECT SPECIFIC QUALIFICATION STATEMENT REQUIREMENTS for CONSTRUCTION MANAGEMENT SERVICES PROJECT SPECIFIC QUALIFICATION STATEMENT REQUIREMENTS for CONSTRUCTION MANAGEMENT SERVICES Kraus Edward Henry Building Renovation and Addition U-M Project Number P00011092 Submittal Deadline: April 12,

More information

Amendment 01. Issued: August 18, For. RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School

Amendment 01. Issued: August 18, For. RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School Amendment 01 Issued: August 18, 2017 For RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School Academy District 20 Proposals Due: August 25, 2017 by 2:00pm MST Issued by:

More information

Exploring Options for Departmental Structures and Developing a Concept Document

Exploring Options for Departmental Structures and Developing a Concept Document Exploring Options for Departmental Structures and Developing a Concept Document One of the features of the CALS Organizational Redesign is considering new structures for departments. As part of this redesign,

More information

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together

New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together The New York State Contract Reporter NYS' official source of contracting opportunities Bringing business and government together This document printed Friday, 04/15/2016 Contracting Opportunity Title:

More information

REQUEST FOR QUALIFICATIONS FOR DESIGN SERVICES FLOWING SEAWATER LABORATORY RENOVATION AND INFRASTRUCTURE UPGRADES.

REQUEST FOR QUALIFICATIONS FOR DESIGN SERVICES FLOWING SEAWATER LABORATORY RENOVATION AND INFRASTRUCTURE UPGRADES. SECTION I: SUMMARY REQUEST FOR QUALIFICATIONS FOR DESIGN SERVICES FLOWING SEAWATER LABORATORY RENOVATION AND INFRASTRUCTURE UPGRADES December 26, 2017 The University of Maine (UMaine), located in Orono,

More information

West Zone & Site. October 7, Portland Community College Rock Creek Campus Bond Program Implementation Rock Creek Campus opsis architecture

West Zone & Site. October 7, Portland Community College Rock Creek Campus Bond Program Implementation Rock Creek Campus opsis architecture West Zone & Site October 7, 2011 Portland Community College Rock Creek Campus opsis architecture Agenda Introduction Committee focus for Fall and beyond Review where we left off Bond build-out schedule

More information

CAMPUS MASTER PLAN Appendix D Oregon State University neighborhood Charter Statement

CAMPUS MASTER PLAN Appendix D Oregon State University neighborhood Charter Statement CAMPUS MASTER PLAN 2004-2015 Appendix D Oregon State University neighborhood Charter Statement Oregon State University Neighborhood Charter Statement Oregon State University is a major, comprehensive

More information

Acknowledgement of Addendum 1 Issued August 28, 2018, by and posted to the website.

Acknowledgement of Addendum 1 Issued August 28, 2018, by  and posted to the website. Acknowledgement of Addendum 1 Issued August 28, 2018, by email and posted to the website. Addendum 1 The written questions submitted on or before August 20, 2018. Firm Name: Date: Signature: Title: Typed/Printed

More information

Administrative Review - Stephen Herbert - Personal Statement

Administrative Review - Stephen Herbert - Personal Statement Administrative Review - Stephen Herbert - Personal Statement (This document was developed for a review of my administrative activity.) Associate Dean, Agricultural Research and Outreach, College of Natural

More information

PLANNING PROCESS FOR PARISHES. NEW CONSTRUCTION, RENOVATIONS, REPAIRS and MAINTENANCE

PLANNING PROCESS FOR PARISHES. NEW CONSTRUCTION, RENOVATIONS, REPAIRS and MAINTENANCE PLANNING PROCESS FOR PARISHES NEW CONSTRUCTION, RENOVATIONS, REPAIRS and MAINTENANCE I. PLANNING PHASE (Identify a Project) 1. The pastor establishes a Parish Planning and Building Committee (PPBC). The

More information

TO MEMBERS TO THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM UNIVERSITY SEISMIC SAFETY POLICY AND UPDATE ON PROGRAM FOR SEISMIC IMPROVEMENTS

TO MEMBERS TO THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM UNIVERSITY SEISMIC SAFETY POLICY AND UPDATE ON PROGRAM FOR SEISMIC IMPROVEMENTS Office of the President GB3 TO MEMBERS TO THE COMMITTEE ON : For Meeting of DISCUSSION ITEM UNIVERSITY SEISMIC SAFETY POLICY AND UPDATE ON PROGRAM FOR SEISMIC IMPROVEMENTS EXECUTIVE SUMMARY This discussion

More information

As indicated above, the Department s responses are not final, official or binding.

As indicated above, the Department s responses are not final, official or binding. Please note that the Department s responses are not final, official or binding. Violation of section 287.057(23) of the Florida Statutes, by a respondent to a solicitation, or persons acting on their behalf,

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

Clemson University Capital Project and Space Assignment Approval Policy

Clemson University Capital Project and Space Assignment Approval Policy Clemson University Capital Project and Space Assignment Approval Policy University Facilities Policy 15 Effective Date: 8/14/17 Last Modified Date: Approved by: Executive Leadership Team Purpose This policy

More information

April 14, 2015 Rev Rev

April 14, 2015 Rev Rev Thomas Fydenkevez Section Head Utilities Mechanical Physical Plant University of Massachusetts 360 Campus Way Amherst, MA 01003-9248 Tel.: 413-545-3231 tfydenke@facil.umass.edu April 14, 2015 Rev. 1 41415

More information

As a state agency, the College administration is required to develop procedures for Construction Manager selection.

As a state agency, the College administration is required to develop procedures for Construction Manager selection. COLLEGE of CENTRAL FLORIDA ADMINISTRATIVE PROCEDURE Title: Construction Management Selection Process Page 1 of 2 Implementing Procedure For F.S. 1013.45 Date Approved: 09/11/02 Division: Administration

More information

APPENDIX E: SECRETARY OF THE INTERIOR'S STANDARDS FOR THE TREATMENT OF HISTORIC PROPERTIES

APPENDIX E: SECRETARY OF THE INTERIOR'S STANDARDS FOR THE TREATMENT OF HISTORIC PROPERTIES 442 APPENDIX E: SECRETARY OF THE INTERIOR'S STANDARDS FOR THE TREATMENT OF HISTORIC PROPERTIES () The information contained in this appendix is provided solely for informational purposes due to the fact

More information

ADDENDUM No. 1 for. Leadership & Management Development Program RFP

ADDENDUM No. 1 for. Leadership & Management Development Program RFP OFFICE OF PROCUREMENT SERVICES 2039 KENNEDY BOULEVARD, ROOM# H-111 JERSEY CITY, NEW JERSEY TELEPHONE NO. (201) 200-3159 FAX NO. (201) 200-3238 ADDENDUM No. 1 for Leadership & Management Development Program

More information

State of Florida Department of Financial Services. Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System

State of Florida Department of Financial Services. Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System State of Florida Department of Financial Services Invitation to Negotiate DFS RM ITN 13/14-07 For Insurance Management System Addendum #2 Modifications to the ITN documentation ITN, Section 2.2, Schedule

More information

Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization Program Funded by Measure B Project Report Facilities Modernization Program Funded by Measure B Project Report April 2015 Learning Resource Center- B100 Learning Resource Center Architect: Construction Manager: Contractor: Steinberg Architects

More information

TASKSTREAM AMS PLANNING SESSION

TASKSTREAM AMS PLANNING SESSION TASKSTREAM AMS PLANNING SESSION OBJECTIVES Log on to Taskstream Access Tasktream AMS (Assessment Management System) Access corresponding workspace and planning template Enter 2016-2017 Administrative Goals

More information

Erie County Medical Center Corporation. Addendum Number 1 to RFP # 21728

Erie County Medical Center Corporation. Addendum Number 1 to RFP # 21728 Erie County Medical Center Corporation RFP # 21728 Addendum Number 1 Erie County Medical Center Corporation Addendum Number 1 to RFP # 21728 ARCHITECTURAL / ENGINEERING SERVICES FOR: MEP SYSTEMS / ELEVATOR

More information

Lawrence R. Behan. Executive Profile

Lawrence R. Behan. Executive Profile Lawrence R. Behan Executive Profile Seasoned administration and finance executive with solid higher education, non-profit and private sector experience. Solutions-oriented leader with established record

More information

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA REQUEST FOR PROPOSALS FOR Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA City of Coralville Iowa Coralville, IA Page 1 of 6 Please review and provide response to this letter

More information

ACKNOWLEDGMENT OF RECEIPT OF ADDENDUM NO.

ACKNOWLEDGMENT OF RECEIPT OF ADDENDUM NO. Philadelphia Regional Port Authority 3460 North Delaware Ave. 2 nd Floor Philadelphia, PA 19134 February 19, 2019 To: All Bidders From: Kate Bailey Director of Procurement Re: ADDENDUM NO. 4 Project 19-011.3

More information

INSTRUCTIONS TO PREPARERS

INSTRUCTIONS TO PREPARERS For Completion of the DESIGN PROFESSIONAL CONTRACT BETWEEN DESIGN PROFESSIONAL AND OWNER TO BE USED WITH GEORGIA STATE FINANCING AND INVESTMENT COMMISSION DBB CONSTRUCTION CONTRACT GEORGIA STATE FINANCING

More information

APPLICATION FOR EMPLOYMENT

APPLICATION FOR EMPLOYMENT A m a r i l l o C o l l e g e P O B o x 4 4 7 A m a r i l l o, T X 7 9 1 7 8-0 0 0 1 ( 8 0 6 ) 3 7 1-5040 Date / / APPLICATION FOR EMPLOYMENT Position Which days are you available to work? (Check all that

More information

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS (August 28, 2018) PIERCE HALL IMPROVEMENTS PROJECT NO. 950511-950532 UNIVERSITY OF CALIFORNIA, RIVERSIDE PREQUALIFICATION PROCESS ALL

More information

BID ADDENDUM #1 September 24, 2010

BID ADDENDUM #1 September 24, 2010 BID ADDENDUM #1 September 24, 2010 To: Prospective Bidders/Planholders For: Science 1 Seismic Retrofit & Renovation California State University Stanislaus One University Circle, Turlock, CA 95382 Bid /

More information

RFP # B-SUPPLEMENTAL #2-TEACHER AND STAFF DEVELOPMENT- INSTRUCTIONAL

RFP # B-SUPPLEMENTAL #2-TEACHER AND STAFF DEVELOPMENT- INSTRUCTIONAL Please attach a copy of Appendix A in TAB 5 Appendix A Individual or Company Name Address City, State and Zip Code Telephone Number E-mail address Web address **Attach a copy of any certification as the

More information

North Middlesex Regional High School

North Middlesex Regional High School North Middlesex Regional High School Ashby, Pepperell, Townsend Schematic Design Kick-Off BUILDING COMMITTEE MISSION STATEMENT We will proactively work with the OPM, design team and the community, to develop

More information

Quick Reference: Writing and Revising the Position Description (PD)

Quick Reference: Writing and Revising the Position Description (PD) Position Description Overview: The position description (PD) is a multi-functional tool that serves as a foundation for the job classification, compensation, hiring and performance management processes

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

FACADE IMPROVEMENT PROGRAM Program Guidelines & Application

FACADE IMPROVEMENT PROGRAM Program Guidelines & Application Mission Statement To encourage, enhance and promote a viable, social and economic downtown district FACADE IMPROVEMENT PROGRAM Program Guidelines & Application Purpose of the DWP Façade Improvement Program

More information

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date:

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: 20130524 AMSC Number: N9379 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:

More information

Purchasing and Property Services AOC East Fowler Avenue Tampa, Florida (813)

Purchasing and Property Services AOC East Fowler Avenue Tampa, Florida (813) Purchasing and Property Services AOC 200 4202 East Fowler Avenue Tampa, Florida 33620 (813) 974-2481 Web Address: http://usfweb.usf.edu/purchasing/purch2.htm May 7, 2015 Invitation to Negotiate No. 15-01-STP

More information

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California.

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California. REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE SPARTAN COMPLEX SEISMIC UPGRADE PROJECT SAN JOSE STATE UNIVERSITY ONE WASHINGTON SQUARE, SAN JOSE, CA 95192-0010 The Trustees of

More information

DEPARTMENT OF PROCUREMENT SERVICES CITY OF CHICAGO. January 2, 2018 ADDENDUM NO. 1 FOR

DEPARTMENT OF PROCUREMENT SERVICES CITY OF CHICAGO. January 2, 2018 ADDENDUM NO. 1 FOR DEPARTMENT OF PROCUREMENT SERVICES CITY OF CHICAGO January 2, 2018 ADDENDUM NO. 1 FOR Median and Boulevard Landscape Maintenance and Services North Region This document contains: Specification No. 220844

More information

Business Services Procurement University of North Texas University of North Texas Health Science Center University of North Texas at Dallas

Business Services Procurement University of North Texas University of North Texas Health Science Center University of North Texas at Dallas DATE: September 25, 2018 TO: FROM: SUBJECT: Potential Proposers Denise Harpool Senior Buyer Addendum 1Answers to Questions RFP763-19-133521DH CMAR-UNTHSC East Parking Garage Renovation Clarification to

More information

Request for Proposal Complete Interior Design for 2- Story Historic Building into Collaborative Innovation Space Proposals are due: December 6, 2014

Request for Proposal Complete Interior Design for 2- Story Historic Building into Collaborative Innovation Space Proposals are due: December 6, 2014 The Bakery, LLC 910 N. Main Avenue Sioux Falls SD 57104-5910 605-310- 4259 Request for Proposal Complete Interior Design for 2- Story Historic Building into Collaborative Innovation Space Proposals are

More information

ADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION)

ADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION) ADVERTISEMENT FOR BIDS (AFTER PREQUALIFICATION) Subject to conditions prescribed by the University of California, San Francisco (the University or UCSF ), bids for a Construction Manager at Risk Agreement

More information

Request for Proposals Historic Structure Report Hennepin History Museum

Request for Proposals Historic Structure Report Hennepin History Museum Request for Proposals Historic Structure Report Hennepin History Museum Date: January 24, 2018 Primary Contact: Kristin Kaspar, Project Manager, Hennepin History Museum 612-870-1329, ext. 3# kristin.kaspar@hennepinhistory.org

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER SERVICES AT RISK WITH GUARANTEED MAXIMUM PRICE Memphis Cook Convention Center Renovation City of Memphis, Department of Housing and Community Development

More information

STATE OF ALASKA RFP NUMBER AMENDMENT NUMBER 1

STATE OF ALASKA RFP NUMBER AMENDMENT NUMBER 1 Department of Natural Resources Division of Support Services 550 W. 7 th Avenue, Suite 1230 Anchorage, AK 99501 THIS IS NOT AN ORDER DATE AMENDMENT ISSUED: Nov. 6, 2017 RFP TITLE: ASTAR Project Consulting

More information

Mott Community College Job Description

Mott Community College Job Description Title: Assistant Vice President - Academic Affairs Department: Academic Affairs Reports To: Vice President - Academic Affairs Date Prepared/Revised: July 2018 Purpose, Scope & Dimension of Job: The Assistant

More information

Mott Community College Job Description

Mott Community College Job Description Title: Department: Office of Physical Plant Reports To: Chief Financial Officer Date Written/Revised: September 22, 2006; Revised July 3, 2017, March 13, 2018 Purpose, Scope and Dimension of Job: Purpose:

More information

House Doctor Consulting Services Application Package

House Doctor Consulting Services Application Package Public Facilities Department House Doctor Consulting Services Application Package For FY2013 FY2015 House Doctor Consulting Services Project #7005 City of Boston Thomas M. Menino, Mayor Michael Galvin

More information

Agenda (Items may be taken out of order)

Agenda (Items may be taken out of order) I. ROLL CALL LOS ANGELES COMMUNITY COLLEGE DISTRICT BOARD OF TRUSTEES FACILITIES MASTER PLANNING & OVERSIGHT COMMITTEE Educational Services Center Board Room 770 Wilshire Boulevard Los Angeles, CA 90017

More information

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE HILTON COLISEUM IMPROVEMENTS 1999 PROJECT WILL BE MADE AT THE MARCH BOARD MEETING MEMORANDUM

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE HILTON COLISEUM IMPROVEMENTS 1999 PROJECT WILL BE MADE AT THE MARCH BOARD MEETING MEMORANDUM A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE HILTON COLISEUM IMPROVEMENTS 1999 PROJECT WILL BE MADE AT THE MARCH BOARD MEETING ISU B-1 MEMORANDUM To: From: Subject: Board of Regents Board Office Register

More information

1. Is it possible that each site will become divided into its own project contract? The projects will not be divided into separate contracts.

1. Is it possible that each site will become divided into its own project contract? The projects will not be divided into separate contracts. Ferry Landings Resilience Upgrades Project 6727 / Contract 67270001 Questions & Answers June 20, 2017 1. Is it possible that each site will become divided into its own project contract? The projects will

More information

INCLUSIVE SEARCH AND RECRUITMENT TOOLKIT AN EMERGING BEST PRACTICE. Dr. Sherri L. Sanders Associate Vice President for Inclusion and Equity

INCLUSIVE SEARCH AND RECRUITMENT TOOLKIT AN EMERGING BEST PRACTICE. Dr. Sherri L. Sanders Associate Vice President for Inclusion and Equity INCLUSIVE SEARCH AND RECRUITMENT TOOLKIT AN EMERGING BEST PRACTICE Dr. Sherri L. Sanders Associate Vice President for Inclusion and Equity OVERVIEW Inclusive Faculty Search and Recruitment Toolkit Importance

More information

Request for Qualifications for Architectural Services

Request for Qualifications for Architectural Services Page 1 of 17 Capital Planning & Development Request for Qualifications for Architectural Services University of Washington Request for Qualifications ARCHITECTURAL PREDESIGN SERVICES FOR Health Sciences

More information

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12 3.01 GENERAL A. Design the project to meet the authorized scope, budget, and schedule. B. Upon initiation of the project, arrange to review with the Owner the service and administrative requirements as

More information

'Tlie Commonwea[tli of9v1assacliusetts

'Tlie Commonwea[tli of9v1assacliusetts Deval L. Patrick GOVERNOR Timothy P. Murray LIEUTENANT GOVERNOR Richard K. Sullivan Ir. SECRETARY 'Tlie Commonwea[tli of9v1assacliusetts ~cutive Office ofcenergy andcenvironmenta{jiffairs 100 cam6ritfge

More information

University of Washington. Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR. UW Fluke Hall Labs and Building Renewal Project Number:

University of Washington. Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR. UW Fluke Hall Labs and Building Renewal Project Number: Capital Projects Office Request For Qualifications for Architectural Design Services University of Washington Request for Qualifications ARCHITECTURAL DESIGN SERVICES FOR UW Fluke Hall Labs and Building

More information