XU CAMPUS ACTION PLAN ENERGY AND INFRASTRUCTURE SECTION

Size: px
Start display at page:

Download "XU CAMPUS ACTION PLAN ENERGY AND INFRASTRUCTURE SECTION"

Transcription

1 TABLE OF CONTENTS A. BACKGROUND AND OBJECTIVES Objectives Historical Usage Utility Rates GHG Emission Factors Capital Investment Projects vs. Purchased GHG Credits Existing Initiatives...4 B. BUILDING ENERGY REDUCTION POTENTIAL Overview Building Inventory Campus Energy Use Building Energy Use Subsystem Energy Use Energy Savings Percentages and Payback Periods Accuracy of Calculations...9 C. EMISSION REDUCTION STRATEGIES Energy Conservation Measures (ECMs) Considered Strategies Not Developed Constraints to Applying Energy Conservation Measures Future Technologies and Costs Future-Building Strategies Benchmarking Implementation Methods...15 D. RESULTS Existing Buildings Existing + Future Buildings...16 E. CONCLUSIONS AND RECOMMENDATIONS

2 A. BACKGROUND AND OBJECTIVES 1. Objectives XU CAMPUS ACTION PLAN ENERGY AND INFRASTRUCTURE SECTION There are five paths to reduce the GHG emissions from purchased electricity and stationary fuel sources: Retrofit and operate existing buildings to lower their energy use. Design and construct new buildings to use significantly less energy than the codes allow (recognizing that any use greater than zero increases the campus carbon footprint). Install renewable energy systems to take the place of purchased electricity and stationary fuel uses in campus buildings. Purchase GHG offset credits or renewable energy credits for the campus energy use that remains. Make an investment in non-campus (e.g., community) buildings or forestry projects and claim the GHG emission reduction. The objective of this section of the Campus Action Plan is to suggest the most economical and effective paths to reach the goal of zero GHG emissions, considering the mix of buildings, available and future technologies, capital investment requirements, and the impact of market forces. 2. Historical Usage The FY 2008 GHG emissions were calculated by XU to be 19,500,000 kg/year for purchased electricity and 4,200,000 kg/year for stationary fuel sources. The site-energy use of a typical campus building is 50% electric energy and 50% natural gas. GHG emissions are about 80% due to electric energy and 20% due to natural gas. This suggests that a larger impact can be made by focusing on reductions in electricity usage. On a site-btu basis, purchased electricity has over three times the GHG emissions of natural gas, even after accounting for combustion losses. 3. Utility Rates The electric rate used in the calculations is $0.065/kWH. This is a blended rate that includes an energy charge of $0.06/kWH and a demand charge of $3.40/kW. The campus is under contract to First Energy until mid-2012 at this rate. 2

3 The natural gas rate used in the calculations is $7.60/mmBTU. This rate reflects a $6.00/mmBTU commodity charge and a $1.60/mmBTU transportation charge. The rate fluctuates according to market conditions. 4. GHG Emission Factors The GHG emission factors used by XU in the inventory report and in this Campus Action Plan are #CO2e per MMBTU of gas burned and #CO2e per kwh. The purchased electricity factor is an egrid regional factor. The factors for Duke Energy (the local Cincinnati utility) and First Energy (the present campus electricity supplier) are higher (~ #CO2e per kwh). Higher factors would result in a need to purchase greater amounts of credits in order to achieve zero emissions. The State of Ohio has legislation to require public utilities to provide up to 20% of their electricity from renewable sources. The utility companies could adopt other technologies to produce electricity (e.g., nuclear). Over a year period, this could lower the GHG purchased electricity factor applicable to the campus. We have not taken this into account in the analysis. 5. Capital Investment Projects vs. Purchased GHG Credits The campus can reduce GHG emissions by investing in on-campus energy-saving or renewable-energy projects, investing in off-campus projects, buying green power, or buying GHG credits directly or through a commodity exchange. Ideally, an energy-saving capital investment project should achieve an annual return-oninvestment (ROI) that meets XU's requirement. We assume that the desired ROI is ~10%/year. This corresponds to a target discounted payback period of 10 years, assuming a 20-year project life, 2% annual utility cost increase, and no tax relief. This means any project that has a simple payback period of less than 10 years meets the XU ROI requirement. Investment in on-campus energy-saving projects produces monetary savings for XU and offsets the purchase GHG credits to achieve zero emissions. As the payback period for energy-saving projects increases, a point is reached where the ROI target is no longer met. Longer payback projects still earn a ROI that is better than buying GHG credits, which have no ROI. For projects that save electric energy and electric demand charges, we calculate that the target discounted payback period ranges from 10 years if there is no cost for credits, up to 11.6 years if credits cost $20/ton/year. For projects that save gas, we calculate that the target discounted payback period ranges from 10 years if there is no cost for credits, up to 11.5 years if credits cost $20/ton/year. Energy-saving investments that have a payback period beyond years (depending on the cost of credits) present three alternatives: Accept a lower ROI and implement the project Defer the project until the payback becomes more favorable (due to technology developments, new product offerings, higher utility rates) 3

4 Reject the project and invest in a renewable-energy system when it becomes cost effective (meaning the payback period is better than available energy-saving projects) Purchase GHG credits or renewable-energy credits, which are a pure cost and have no savings stream. Investment in off-campus energy-saving projects does not produce monetary savings for XU but avoids the need to buy GHG credits to achieve zero emissions. For projects that save electric energy, we calculate that the maximum target discounted payback period ranges from zero years if there is no cost for credits, up to 1.2 years if credits cost $20/ton/year. For projects that save gas, we calculate that the maximum target discounted payback period ranges from zero years if there is no cost for credits, up to 1.5 years if credits cost $20/ton/year. The conclusion is that XU should invest in on-campus projects or purchase GHG credits if the simple payback period is more than a few months for any off-campus project. Since these types of short-payback projects seldom exist in any magnitude, off-campus investment is not an economical path to GHG emission reductions. Green power can be purchased at a premium (over the normal cost) by buying power from a biomass plant, wind farm, solar farm, etc. We calculate that the maximum economical premium cost of a kwh ranges from $0 if there is no cost for credits, up to $0.010 if credits cost $20/ton/year. Locally, Duke Energy presently offers renewable energy at a premium cost of about $0.01/kWH. The market price is about $0.005 to $0.01 per kwh at the present time. Green power is not an economical path unless the premium cost is less than 1% for every dollar per ton per year that a GHG credit costs (if credits cost $20/ton/year, green power is economical at up to 20% more than normal utility power). 6. Existing Initiatives The XU campus has already made wide-spread use of several energy-reduction strategies and operating procedures including: Lighting retrofits to T8 fluorescent lamps with electronic ballasts. Compact fluorescent lamps. Sporadic use of occupancy sensors. Networked Building Management System in ~15 of the largest East Campus buildings to control HVAC systems, exterior lighting, chiller and boiler plants. This system is being upgraded to a web-based interface as part of the construction of four new campus buildings. Dedicated outdoor air systems on one of the existing residence halls and on the new residence hall presently being designed. New buildings designed to meet the LEED Silver status including submetering, 3rd party commissioning, sophisticated control strategies, lighting controllers, occupancy sensors, demand-controlled ventilation, high-performance envelopes, variable-flow HVAC systems, condensing water heaters, condensing boilers, high-efficiency variable-speed chillers. 4

5 Control strategies that turn off all boilers, chillers, and pumps during unoccupied periods when weather conditions are favorable. Use of LCD terminals for most computers. Variable-speed drives on fans and pumps. Reduced bathroom exhaust flow during unoccupied periods. Low-flow showers and faucets in high usage areas. The candidate ECMs outlined in this document to further reduce GHG emissions continue to build on these campus strategies. 5

6 B. BUILDING ENERGY REDUCTION POTENTIAL 1. Overview Based on the analysis presented above, the most economical path to reduce GHG emissions is to first exhaust all on-campus capital investment opportunities that meet the target ROI, and then purchase GHG credits or renewable energy credits for the remaining emissions. There was insufficient time and resources that could be devoted to a detailed building-by-building analysis of individual energy-reduction opportunities. This section describes a simplified model that was created to determine the economical emissions-reduction potential in existing and future campus buildings. The steps of the analysis were: Use campus master plan information to document the existing building areas and to estimate the future building areas. Use historical metered gas and electric utility data and building area to estimate the annual energy consumption of each building (not all buildings are submetered). Use industry building-profile data to estimate the baseline system energy use within each building by building type (education, food service, lodging, office, public assembly, service, storage) and subsystem (space heating, space cooling, ventilation, water heating, lighting, cooking, refrigeration, office equipment, computers, other). Identify typical energy conservation measures (ECMs) that would apply to each subsystem. Identify other ECMs that are of a broader nature, which would reduce the energy use of multiple buildings (e.g., central plant projects). Based on the experience of the engineers or from custom calculations, estimate the percent energy savings that may be achieved for each ECM in each building. From the baseline energy use and the percent savings, for each ECM calculate the units of energy savings, the dollar savings, and the GHG emission reduction. Based on the experience of the engineers, assign a likely simple payback period to each type of ECM. From the annual dollar savings and the simple payback period, for each ECM calculate the capital investment required. Total all of the energy savings, capital investments, and GHG emission reductions. 2. Building Inventory The area of the existing campus buildings is 1,769,000 SF. Campus master plan estimates that more buildings will be constructed to accommodate more students and expanded academic programs. At the time of this report, the first four are under construction. 6

7 Building Area, SF Central Utility Plant (CUP) 20,000 Learning Commons 85,000 Williams College of Business 80,000 New Residence Hall and Dining Facility 240,000 Residence Hall Facility North of Cintas 200,000 Residence Hall Facility West of Cintas 70,000 Residence Hall Facility South of Cintas 70,000 East Campus 600,000 Hailstones Addition 10,000 Williams College of Business Addition 40,000 New Buildings 180,000 Campus Expansion to the South 100,000 Total 1,700,00 0 If all of these facilities are constructed, the new buildings represent a 100% increase in the footprint of the campus. Even with aggressive energy-reduction strategies, GHG emissions will increase when these buildings are constructed. 3. Campus Energy Use Electric energy is distributed to the campus buildings by the utility company via six master meters and numerous individual-account meters. Natural gas is distributed to the campus buildings by the utility company via three master meters and numerous individual-account meters. Many of the buildings served from the master meters are not submetered. One of the ECMs is to provide gas and electric submeters that are read by the campus Building Management System for every building. While this will not save energy directly, meters are essential to measuring ECM performance, spotting wasteful practices, and benchmarking within the campus and to similar building types. There are two central utility plants on the campus that provide hot and chilled water to other buildings. A third plant is under construction. The existing central plants are metered for the electricity and gas used but not for the hot and chilled water delivered to the buildings. The new central plant will have hot and chilled water energy meters for every building that it serves. 4. Building Energy Use Where buildings do not have submeters, usage by each building for electricity, gas, and hot/chilled water was estimated based on the master meter data and each building's area. The existing buildings average 102,000 site BTU/SF/year as a whole. For reference, per the EPA Energy Star database, "average" K-12 school buildings use 51,000 BTU/SF/year and "average" residence halls use 87,000 BTU/SF/year. Buildings that qualify for Energy Star 7

8 certification use 40,000 and 62,000 BTU/SF/year, respectively. A 2004 survey of Midwest Association of Physical Plant Administrators (Higher Education Facilities) shows the campus average energy use is ,000 BTU/SF/year. The buildings under construction and the future buildings were assumed to be more energy efficient than the average of the existing buildings. While the buildings under construction will conform to LEED Silver standards, have higher-quality envelopes and more sophisticated controls and energy systems, they will also have higher ventilation rates, tighter temperature control, better filtration, better humidity control, and more glass area all of which increase energy use compared to the average existing building. Energy modeling results performed by the design engineer for one of the new academic buildings estimated consumption to be 60,000 BTU/SF/year but the model appeared to be overly optimistic. Generally, we assumed a factor of 70-75% of the campus average for the new buildings. This would put the site energy use for new buildings at 70-75,000 BTU/SF/year. GHG emissions will increase by about 70% due to the construction of new buildings if no action is taken to reduce energy use or decrease the energy use of the new buildings. 5. Subsystem Energy Use Energy use within each building was estimated from Commercial Building Energy Consumption Survey data for similar building types (education, food service, lodging, office, public assembly, service, storage). The subsystems included space heating, space cooling, ventilation, water heating, lighting, cooking, refrigeration, office equipment, computers, and other. For buildings served from central plants, the space heating and cooling was assumed to be the energy used by the central plant. 6. Energy Savings Percentages and Payback Periods The energy savings percentages were estimated for each ECM and each building. For example, to convert from single-pane to double-pane windows, an estimate must be made as to what portion of the building envelope energy is due to the windows and then what portion of that energy would be saved by the conversion. The simple payback period for each ECM was estimated from experience. Adjustments were made for individual buildings where knowledge of the building suggested a more appropriate value. Some of the values were based on previous calculations done for XU for particular ECMs. Adjustments were made for interaction between ECMs. If there were mutually exclusive ECMs (e.g., adding window film and replacing single-pane windows with double-pane), one of them was eliminated. Once the electric and gas energy savings was determined, the dollar savings was computed. The result was combined with the simple payback to determine the capital investment. 8

9 7. Accuracy of Calculations The methodology used in the analysis is not as accurate as if individual ECM savings and cost calculations had been performed based on measured field data and hourly computer simulation models. The estimates likely have accuracy in the range of +/-25-30%. However, they do provide a perspective on the magnitude of emissions reductions that can be economically achieved. 9

10 C. EMISSION REDUCTION STRATEGIES 1. Energy Conservation Measures (ECMs) Considered The following general types of ECMs were included in the analysis where appropriate to a building or system. Envelope improvements: Window films Infiltration reduction methods Reflective roofing / re-roofing Additional wall insulation Adding another window pane to single or double pane units Shading devices to reduce solar gains during the cooling season Electric appliances, computer equipment: Power management, such as automatically powering down office equipment, vending machines, computer equipment when not in use Energy Star appliances, equipment such as residence hall equipment, laundry equipment, food service equipment Lighting: Occupancy sensors Compact fluorescent lamps in place of incandescent T8/T5 fluorescent lamps and electronic ballasts in place of T12 or metal halide fixtures LED fixtures in place of fluorescent Daylighting strategies to reduce the use of artificial lighting HVAC: Recommissioning of building systems to restore the original operation, fix defects, improve control sequences Variable speed drives on pumps and fans High efficiency motor replacements when motors burn out, use of electricallycommutated motors in place of fractional-horsepower motors Lower coil/duct/filter velocities, eliminate sound attenuators Revised air filter program to lower pressure drop Control strategies, temperature resets, demand controlled ventilation Ventilation energy recovery Chilled beam systems (as part of a major renovation) in conjunction with dedicated outdoor air systems to reduce fan power Food service refrigerator heat recovery Pool upgrades: improved heating, pool cover Central energy systems: Academic Mall underground piping replacement Logan plant decommission - transfer to the new Central Utility Plant (CUP) Replace Residence Hall central plant equipment Replace Brockman central plant equipment 10

11 Replace Alumni Center boilers Replace one Cintas chiller with a higher efficiency unit CUP boiler condensing economizer when the new, larger, non-condensing boilers are installed for future buildings CUP boiler in-stack economizer Solar water heating on individual buildings Submetering on all individual buildings for electric power, gas (and ideally, hot water and chilled water) Water conservation measures - low flow heads to reduce hot water use Open-loop geothermal coupled with heat recovery chillers for heating and cooling Natural gas fuel cells to produce electricity Cogeneration systems to produce electricity and hot water from burning natural gas onsite Next-level future buildings: Super insulation and envelopes Integrated photovoltaic systems (generation capability built into exterior finishes) Substantially better performance than energy code Renewable-energy systems: Photovoltaic arrays to generate electricity from solar energy Wind turbines Digester using campus waste 2. Strategies Not Developed The following types of opportunities were not analyzed in detail. Low-cost operations and maintenance items some of these savings opportunities fall under the recommissioning task or will be achieved through educational programs and existing Physical Plant initiatives. Alternatives to utility power such as fuel cells, photovoltaic, wind, electrolysis/hydrogen fuel, etc. Due to their long payback periods at the present time, these opportunities are viewed as "future technologies" that may be able to make up the difference between conservation and zero emissions after all economical ECMs are implemented in the campus buildings. See the discussion on future technologies, below. 3. Constraints to Applying Energy Conservation Measures Difficulties will be encountered in trying to implement every proposed ECMs in every building. For example, shading devices may not be suitable for the décor, physical space doesn't exist for heat recovery equipment, occupants are resistant to the changes (e.g., using a pool cover), occupancy sensors aren't practical in as many rooms as estimated. Some ECMs are not practical to do unless the entire building is being gutted for renovation (e.g., chilled beams). 11

12 The analysis results were interpreted to be conservative so as to not overstate the retrofit potential or understate the implementation cost. 4. Future Technologies and Costs The ECMs included in the analysis are those that are available, practical, and viable today or are likely to reach such status in the next years. For example, LED lighting was included with a simple payback period of 10 years. The payback period today is closer to years but it is expected to improve. This technology would only be adopted once the life-cycle economics are favorable, much like the application of T8 lamps over the last decade. This is one of the largest opportunities in the existing buildings. Some ECMs, like motor replacement or roof insulation, are only economical when the component must be replaced. While a short payback period may have been used, it is for the premium cost to upgrade to a more energy-efficient level, not to replace the entire component. Working motors can't be economically replaced if they are still working. Roof insulation can't be economically upgraded until the roof membrane must be replaced. Many technologies, such as wind turbines, fuel cells, and photovoltaics also have long payback periods at the present time. These fall in the category of "alternatives to utility power" and would be used as cleaner sources of electricity once all other economical means to reduce campus consumption are exhausted. Whether they ever become viable will depend on market forces and technology developments. Even if they do become viable, they may be deployed more economically by third parties or the utility companies, rather than by the individual end users. If a developing technology, like photovoltaics, suddenly becomes very cost effective (e.g., 5 year simple payback), then it would trump all other ECMs that have a longer payback. At that time, it would be best to invest in the technology. It is not very likely that there would be a huge price break-through. Market forces and the need to recoup development costs will likely keep prices high compared to present energy costs. 5. Future-Building Strategies The future buildings being proposed could double the area of the campus under roof. No building can be made net-zero (without the inclusion of renewable-energy systems). They will only increase the carbon footprint of the campus. If the goal of the campus is to be carbon neutral, it is a given that the future buildings must be as efficient as economically possible. Even with that strategy, renewable energy systems or GHG credits will still be required to make up the difference. A major issue is how to adopt new energy efficiency philosophies within traditional funding, design, and construction management mindsets. Suggestions to improve the end result include the following: Budgeting / financing The cost of new buildings are traditionally benchmarked against buildings of similar function and size that other entities have built. Budgets are usually 12

13 set early in the project and the entire design and construction team works to meet that cost-per-sf, cost-per-bed, or cost-per-classroom-seat budget. We are in a transition period. Most historical cost data is from buildings that were not energy efficient or only make modest attempts to be more efficient. Addition investments to drive energy performance can be the first to be cut or "value engineered" out of the project when budget ceilings are hit. To make major strides in reducing energy consumption, a different financing model must be developed and adopted. Perhaps this involves benchmarking the construction cost to a base building performance concept then adding incremental funding to support "super efficient" concepts. This incremental funding could come from a different University budget, outside donors (naming rights for the energy systems?), third-party investors who would finance the incremental investment over time. Augment the LEED process Based on the energy system selection and design details of the four new Hoff Academic Quad buildings, the LEED process alone does not go far enough to insure the lowest economical GHG emissions are achieved. Energy points are only a small portion of the total points needed. Designing to a LEED Silver level does little to inspire imaginative concepts. We are left with systems that have been routine over the last 20 years. LEED points are earned for the percentage cost reduction that the proposed building is expected to achieve compared to a base building, as defined by ASHRAE Standard Depending on the type of building and the utility sources, Standard 90.1 is an inconsistent benchmarking tool. For example, o o o o o o If a building is served from a central plant, both the proposed and the base building must assume the same central plant is used. Small proposed buildings are allowed to be compared to less efficient base buildings, making the percent savings appear higher even though the BTU/SF/year is no better than a large building would achieve. No credit can be earned for passive solar features or improved building massing. There is no baseline performance for fume hoods, IT equipment, and electrical equipment. As Standard 90.1 is revised, the base building performance will be increasing, making comparison of proposed buildings designed several years apart less meaningful. The comparisons are made based on utility cost, not GHG emissions or energy. Thus, a proposed design may be more cost efficient but have higher GHG emissions due to greater reliance on electricity. Ways of improving the process would be to set BTU/SF/year targets, use the Energy Star points system, or use the ASHRAE EQ Rating System, rather than a single percentage-reduction benchmark. Enhanced modeling Most building and energy system modeling is done after the concepts are established, to verify that the building meets code and to see how many 13

14 LEED points can be earned. Modeling should be done early in the design process to examine dozens of variables and concepts, while changes can still be easily made. A single building simulation tool, like equest or EnergyPlus (popular with LEED modelers), is incapable of modeling every design aspect of a project. The design team must have access to many specialized programs to optimize component performance. For example: o o A particular fan selection could beat the Standard 90.1 minimum requirements but multiple iterations of a vendor equipment selection program, coupled with pricing information, could greatly lower the fan power from the base case. Perhaps the noise level would also be reduced in the process, such that the cost and pressure loss of a sound attenuator could be eliminated. A duct system could be sized by manual calculations such that the fan power meets the minimum requirement. A computerized duct sizing program could be used to iterate the duct design, saving both first cost and the fan power. Equal marginal performance One goal of the modeling and design effort should be to insure that every component and subsystem is sized and selected to operate at the margin. That is, if the desired ROI is 10%/year, the efficiency of every component and subsystem should be improved until the ROI limit is reached. For example: o o o o The R-values of the walls and roof should be increased until the last increment (the last R-value) has a 10% ROI. The glazing systems should be enhanced until the last pane or the last coating has a 10% ROI. The duct/coil/filter/pipe velocities should decrease until the last size increment has a 10% ROI. The chiller and boiler efficiency should be increased until the incremental cost and savings between two models has a 10% ROI. The overall ROI for improvements made to a component or system will be much higher than the target, since every increment prior to the last will inherently perform better. State the cost of achieving net zero emissions Require the design team to calculate the life-cycle cost of the proposed design, including purchasing renewable energy credits or GHG credits to offset all purchased energy. The life cycle cost would equal the building first cost + the net present value of [the annual utility costs + the annual cost of GHG credits + the annual cost of maintenance]. This would insure that the building optimization process includes all future costs, in line with the University s environmental goals. 6. Benchmarking Enhanced energy metering is one of the proposed ECMs that were included in the analysis. While not a direct energy saver, metering can provide valuable information on where attention and investment should be focused. It can help spot anomalies and wasteful practices, guide 14

15 facility policies, and allow charge-back of energy costs to the end users (to incentivize conservation). The metering program can include automatic data gathering, organization of the data, real-time dashboards and periodic reports that are easy to understand. 7. Implementation Methods Several methods are available to implement long-term GHG-emission-reduction programs. They include: Self-manage The University could continue with its present strategy of guiding and directing all aspects of the program. Existing or additional Physical Plant staff would manage the analysis and design engineers, write requests to obtain internal funding, hire contractors, manage the construction, and pursue grants. Third-party partnerships A company is hired to manage portions of the program as an extension of the in-house staff. The goal is to allow the University to defer hiring additional permanent skilled staff members by off-loading some of the management activities, such as directing engineers, developing financial justifications, writing requests for funding, pursuing grants, developing PR, bidding and managing projects, and monitoring the results. These relationships are usually more open than ESCOs. They still require significant management participation and retain control by the University. Energy Service Companies (ESCOs) A company is hired, usually with no upfront cost, to conduct energy analyses, recommend opportunities, implement and manage the projects, and possibly provide project financing. Guaranteed savings may or may not be included. The University pays based on the savings achieved or at a set rate. No costs are incurred for projects that do not come to fruition. Overall costs tend to be significantly higher than self-managed or partnerships due to the high overhead burdens that these firms have. Line-item details of project economics are usually not shared, leading to higher-than-necessary costs. Results may occur faster since the ESCO has an incentive to complete projects in order to begin to receive payments. Contract Energy Provider A company enters into an agreement with the University to install an energy system on the campus, such as a fuel cell, photovoltaic array, heatrecovery chiller, cogeneration system, at no upfront cost. The University pays for the power produced at an agreed-upon rate over the life of the contract. The Provider owns and maintains the system. 15

16 D. RESULTS 1. Existing Buildings The proposed ECMs for the existing buildings were arranged in order of increasing simple payback period and plotted against cumulative GHG emissions. Future technologies, such as LED lights and fuel cells, and central utility technologies, such as geothermal and photovoltaic, were not included. Figure 1 shows that about 20% of the existing building emissions can be cost-effectively reduced (<~10 year simple payback period). To get to 25% requires extending the allowable simple payback period to about 25 years. The 10-year simple payback period cut-off excludes two longer-payback projects that should be included despite the economics improved utility metering and replacement of the Academic Mall underground piping system. The metering is valuable to allow monitoring of building performance. The Mall piping replacement is necessary from a maintenance and reliability need. Figure 2 shows the cumulative capital investment as the GHG emission reduction increases. A $2.5mm capital investment would be required to achieve a 20% reduction. Figure 3 shows the net present value of the capital investments, energy savings, and GHG credit costs. It was assumed that GHG credits would be purchased to offset all emissions remaining after the ECMs are implemented and that the credits cost $3/ton/year. The optimum net present value is at the 20% GHG reduction level. Beyond this point, the further investment in ECMs does save enough to justify the savings of purchasing GHG credits. If less than the optimum is invested, the cost of purchasing increasing amounts of credits drags down the net present value. If the cost of GHG credits is assumed to be higher, the optimum GHG reduction percentage remains the same. The curve is merely shifted downward. 2. Existing + Future Buildings The proposed ECMs for all buildings were arranged in order of increasing simple payback period and plotted against cumulative GHG emissions. Included were three major future technologies, LED lights, next level new buildings, and a campus-wide geothermal heating system. Figure 4 shows that about 40% of the projected future emissions can be costeffectively reduced (<~10 year simple payback period). About 25% of the reduction in the total emissions was due to these three technologies. Due to the uncertainty of these items, there could be considerable variation in the actual cost-effective outcome. Figure 5 shows the cumulative capital investment as the GHG emission reduction increases. A $15mm capital investment would be required to achieve a 40% reduction. Figure 6 shows the net present value of the capital investments, energy savings, and GHG credit costs at the same $3/ton/year credit cost. The optimum net present value is at the 40% GHG reduction level. If the cost of GHG credits is assumed to be higher, the optimum GHG reduction percentage remains the same. The curve is merely shifted downward. 16

17 Figure 7 shows the net present value of the capital investments, energy savings, and cost of purchasing green power. It was assumed that green power at $0.01/kWH would be purchased for all purchased electricity remaining after the ECMs are implemented. The optimum net present value is at the same 40% GHG reduction level. At higher costs for green power, the geothermal system is not cost effective, since it increases electric usage so much in exchange for a reduction in gas usage. The optimum net present value is at ~33% GHG reduction level. 17

18 E. CONCLUSIONS AND RECOMMENDATIONS This portion of the Campus Action Plan determined the approximate cost-effective levels of GHG emission reduction that can be achieved by retrofitting existing buildings and constructing new buildings to higher standards. Based on the range of expected costs for renewable energy credits and GHG offset credits, about 20% of the existing building emissions and 40% of the existing + future building emissions can reduced via conservation efforts. The reduced emission levels are dependent on certain technologies becoming cost effective over time. To achieve zero emissions, the remainder will have to come from credits purchased on the open market. The recommended course of action for achieving zero GHG emissions includes the following: Continue to identify and implement high-value ECM projects in the existing buildings and central utility plants. Refine the calculation methodology used in this analysis based on individual ECM investigations on a building-by-building and system-by-system basis. Follow the development and commercialization of new technologies that would be applicable to XU, including more effective lighting, better control algorithms, renewableenergy systems. Be flexible in the program direction based on changing energy price signals, particularly higher electric rates that would make electrical savings more valuable. GHG emissions are strongly impacted by electricity use. Take advantage of incentive programs and grants. Recently, Duke Energy adopted their Save-A-Watt campaign in Ohio which pays for part of the cost of energy analyses and is integrated with their prescriptive and custom incentive (rebate) programs. Implement enhanced building and system metering. Organize the data streams using automated tools, dashboards, and smart reporting. Communicate performance to all participants (building occupants, Physical Plant, academic departments). Set higher energy design standards for new and renovated buildings. Go beyond LEED as the benchmark. Include more rigorous system modeling requirements. Require equal marginal performance analyses for all systems and components. Develop mechanisms for financing the energy improvements. Insure that the construction cost benchmarks adapt to the GHG emission reduction goals and that the design and construction teams are incentivized to respond appropriately. Expand the campus construction standards to give better guidance on energy performance, system design techniques, and long-term University energy-system goals. Make life-cycle costing the foundation of all energy system decisions. Track the costs, commodity markets, and suppliers of renewable energy credits and GHG offset credits. A timeline for achieving reduced target levels should be developed. The aggressiveness of the targets will depend on how much and how quickly the University wants to achieve a GHG emission reduction. 18

19 Figure 1 Simple Payback vs. GHG Emission Reduction In Existing Buildings 35% 30% Cumulative GHG Reduction, % of Existing Building Emissions 25% 20% 15% 10% 5% 0% Simple Payback, Years

20 Figure 2 GHG Emissions Reduction vs. Capital Cost in Existing Buildings $9,000,000 $8,000,000 $7,000,000 $6,000,000 Cumulative Capital Cost $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $0 0% 20% 40% 60% 80% 100% Cumulative GHG Reduction

21 $2,500,000 Figure 3 GHG Emission Reduction vs. Net Present Value (Energy Savings - Capital Cost - Credits) (GHG Credits Purchased for All Remaining Emissions) $2,000,000 $1,500,000 Cumulative Net Present Value $1,000,000 $500,000 $0 -$500,000 -$1,000,000 -$1,500,000 -$2,000,000 0% 20% 40% 60% 80% 100% Cumulative GHG Reduction

22 Figure 4 Simple Payback vs. GHG Emissions Reduction in Existing + Future Buildings 60% 50% 40% Cumulative GHG Reduction 30% 20% 10% 0% Simple Payback, Years

23 Figure 5 GHG Emissions Reduction vs. Capital Cost in Existing + Future Buildings $30,000,000 $25,000,000 $20,000,000 Cumulative Capital Cost $15,000,000 $10,000,000 $5,000,000 $0 0% 20% 40% 60% 80% 100% Cumulative GHG Reduction

24 $10,000,000 Figure 6 GHG Emissions Reduction vs. Net Present Value (Energy Savings - Capital Cost - Credits) (GHG Credits Purchased for All Remaining Emissions) $8,000,000 Cumulative Net Present Value $6,000,000 $4,000,000 $2,000,000 $0 -$2,000,000 0% 20% 40% 60% 80% 100% Cumulative GHG Reduction

25 $5,000,000 Figure 7 GHG Reduction vs. Net Present Value (Energy Savings - Capital Cost - Green Power Cost) (Green Power Purchased for All Remaining kwh) $4,000,000 $3,000,000 $2,000,000 Cumulative Net Present Value $1,000,000 $0 -$1,000,000 -$2,000,000 -$3,000,000 -$4,000,000 -$5,000,000 0% 20% 40% 60% 80% 100% Cumulative GHG Reduction

Energy Auditing for Schools. Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007

Energy Auditing for Schools. Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007 Energy Auditing for Schools Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007 Schools Consumption breakdown 19% 6% 9% Space Heating 46% Water Heating Lighting Cooling 20%

More information

South Carolina Society for Hospital Engineers

South Carolina Society for Hospital Engineers South Carolina Society for Hospital Engineers Selecting Energy Partners: Criteria & Pitfalls and the Top 10 Ways to Reduce Energy in a Hospital Presented by Jon Dierking, PE, CEM, LEED AP Director of Energy

More information

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT Report Clayville Elementary School October 2016 3 George Washington Highway, Clayville, RI 02815 Clayville Elementary School Summary of Findings On behalf of the School Building Authority at Rhode Island

More information

Colorado Mountain College: Sustainable Design Standards

Colorado Mountain College: Sustainable Design Standards Colorado Mountain College: Sustainable Design Standards Objective: Design and build to the highest energy and water standards in order to meet the College s Carbon Neutrality Objective in the most cost-effective

More information

Energy Efficiency in Multi-Tenant Office Buildings

Energy Efficiency in Multi-Tenant Office Buildings Energy Efficiency in Multi-Tenant Office Buildings Presented by David Herman, PE, LEED AP Principal, EnerG Associates, LLC 3/10/2015 1 Learning Objectives 1. List the principal sources and uses of energy

More information

What s My Baseline? ASHRAE

What s My Baseline? ASHRAE 2010 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions (2010, vol 116,part 2). For personal use only. Additional reproduction,

More information

University of Minnesota Duluth Civil Engineering Building

University of Minnesota Duluth Civil Engineering Building Energy Data Attachment University of Minnesota Duluth Civil Engineering Building LEED Energy Modeling The energy modeling for LEED NC 2.2 was performed against ASHRAE 9.1-24 Appendix using equest version

More information

Fifteen Year Plan for Energy Efficiency and Conservation Projects

Fifteen Year Plan for Energy Efficiency and Conservation Projects Fifteen Year Plan for Energy Efficiency and Conservation Projects Presented to the Board of Trustees of the Northeastern Ohio Universities Colleges of Medicine and Pharmacy, December, 2008, in accordance

More information

College of Lake County Sustainability Center

College of Lake County Sustainability Center ~ 1 ~ Climate Action Plan College of Lake County College of Lake County Sustainability Center ~ 2 ~ Table of Contents I. Introduction...3 A. CLC s Climate Commitment... 3 B. Executive Summary... 4 C. CLC

More information

Energy Efficiency Solutions for Multifamily Housing. Clark Energy Group LLC

Energy Efficiency Solutions for Multifamily Housing. Clark Energy Group LLC Energy Efficiency Solutions for Multifamily Housing Clark Energy Group LLC 1 Agenda About Clark Energy Group Energy Service Company (ESCO) Overview ESCO Services Utility Rate Forecasts Making the Decision

More information

GreenStep Cities Workshop Xcel Energy Rebates: Commercial Program Overview

GreenStep Cities Workshop Xcel Energy Rebates: Commercial Program Overview GreenStep Cities Workshop Xcel Energy Rebates: Commercial Program Overview Mike Meyers, Xcel Energy Commitment from Leadership Our energy conservation programs are especially valuable because they give

More information

Grunenwald Science and Technology Building

Grunenwald Science and Technology Building Grunenwald Science and Technology Building Clarion University- Clarion, PA AE 482 Mechanical Project Proposal: Proposal for Alternative Designs Shane Helm The Pennsylvania State University Architectural

More information

SUSTAINABILITY An Energy & Emissions Case Study

SUSTAINABILITY An Energy & Emissions Case Study SUSTAINABILITY An Energy & Emissions Case Study 1 Energy & Emissions Case Study WASHINGTON UNIVERSITY IN ST. LOUIS has a history of responsibly investing resources to increase the efficiency of our operations

More information

CREDIT COMPLIANCE (Please complete the color coded criteria(s) based on the option path selected)

CREDIT COMPLIANCE (Please complete the color coded criteria(s) based on the option path selected) (Responsible Individual) (Company Name) I,, from verify that the information provided below is accurate, to the best of my knowledge. CREDIT COMPLIANCE (Please complete the color coded criteria(s) based

More information

Deep Energy Retrofit Modeling and Cost Effectiveness Study: A Technical Policy Brief. January 2013

Deep Energy Retrofit Modeling and Cost Effectiveness Study: A Technical Policy Brief. January 2013 Deep Energy Retrofit Modeling and Effectiveness Study: A Technical Policy Brief January 2013 Table of Contents EXECUTIVE SUMMARY... 3 INTRODUCTION... 4 BUILDING 1... 7 BUILDING 2... 9 BUILDING 3... 11

More information

BETA OPTION 1: PERFORMANCE RATING METHOD. Section General Information

BETA OPTION 1: PERFORMANCE RATING METHOD. Section General Information LEED-CS 2. Certification Submittal Template OPTION 1: PERFORMANCE RATING METHOD I confirm that the energy simulation software used for this project has all capabilities described in EITHER section `G2

More information

Energy Strategies That Work

Energy Strategies That Work Energy Strategies That Work Emmy Presenter s Riley, Building name Professional Energy Specialist Title (eg. architect/energy Illini Center specialist..) 10-10-12 Smart Energy Design Assistance Center (SEDAC),

More information

OSU Cascades Net Zero Campus. Recommendations

OSU Cascades Net Zero Campus. Recommendations OSU Cascades Net Zero Campus Recommendations February 20, 2017 Viable Net Zero Options Building Energy Efficiency Better 30% better than code Best 50% better than code Electrical energy Photovoltaic energy

More information

2014 ENERGY REPORT. Mark J. Ferguson, P.E. Campus Operations & Plant Manager

2014 ENERGY REPORT. Mark J. Ferguson, P.E. Campus Operations & Plant Manager 2014 ENERGY REPORT Mark J. Ferguson, P.E. Campus Operations & Plant Manager Table of Contents Executive Summary... 2 Utilities Overview... 3 Avoided Cost... 4 Our Carbon Footprint... 5 Benchmarking...

More information

Multifamily Net Zero Retrofit Market: Technical and Cost Benchmarks for San Francisco

Multifamily Net Zero Retrofit Market: Technical and Cost Benchmarks for San Francisco Multifamily Net Zero Retrofit Market: Technical and Cost Benchmarks for San Francisco 1 Table of Contents Acronym Key Analysis Process Retrofit Economics Technical Analysis Details 6 Unit Building Analysis

More information

IFMA Central Pennsylvania Chapter August 20, 2014

IFMA Central Pennsylvania Chapter August 20, 2014 IFMA Central Pennsylvania Chapter August 20, 2014 Facility Managers Roundtable: Sustainability Practices Alan Brunner, Project Manager for the Financer Department, PSECU Michele Sinadinos, Facility Manager,

More information

DGS worked with the GGGC (Governors Green

DGS worked with the GGGC (Governors Green Energy Management Success Story DGS worked with the GGGC (Governors Green Government Council), DOC (Department t of Corrections), and NAESCO (National Association of Energy Service Companies) to develop

More information

2013 ENERGY REPORT MARK J. FERGUSON, P.E. CAMPUS ENERGY MANAGER 1125 GLEN AVENUE COLORADO SPRINGS, CO 80905

2013 ENERGY REPORT MARK J. FERGUSON, P.E. CAMPUS ENERGY MANAGER 1125 GLEN AVENUE COLORADO SPRINGS, CO 80905 2013 ENERGY REPORT MARK J. FERGUSON, P.E. CAMPUS ENERGY MANAGER 1125 GLEN AVENUE COLORADO SPRINGS, CO 80905 CC 2013 Energy Report Table of Contents Executive Summary... 2 Utilities Overview... 3 Avoided

More information

OPTION 1: PERFORMANCE RATING METHOD

OPTION 1: PERFORMANCE RATING METHOD OPTION 1: PERFORMANCE RATING METHOD I confirm that the energy simulation software used for this project has all capabilities described in EITHER section `G2 Simulation General Requirements' in Appendix

More information

New Jersey Board of Public Utilities Clean Energy Program Incentives and Proposed Hurricane Sandy Storm Response

New Jersey Board of Public Utilities Clean Energy Program Incentives and Proposed Hurricane Sandy Storm Response New Jersey Board of Public Utilities Clean Energy Program Incentives and Proposed Hurricane Sandy Storm Response Energy Efficient Equipment and Building Upgrades February 2013 Program Goals Save energy

More information

Georgetown University New Science Center

Georgetown University New Science Center Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical

More information

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal

Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal Example LEED-NC v2.1 Energy & Atmosphere Credit 1 Submittal The following documentation provides an example submittal for the LEED-NC v2.1 Energy & Atmosphere Credit 1 (EAc1). This sample EAc1 submittal

More information

Reducing Costs with Energy Efficiency

Reducing Costs with Energy Efficiency Reducing Costs with Energy Efficiency Presented to Pennsylvania Demand Side Response Working Group February 9, 2007 2/9/2007 1 Austin Energy Municipally-owned 700,000 population Area > 400 sq. miles Generation

More information

Energy Efficiency Planning. June 30, 2009

Energy Efficiency Planning. June 30, 2009 Energy Efficiency Planning at Genzyme June 30, 2009 Genzyme - A Global Corporation >11,000 employees worldwide Helping patients in 100 countries 17 manufacturing sites 9 genetic testing lab sites 19 major

More information

Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits

Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits AEP Ohio Customer Seminar Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits Presented by: Julie Birchfield Customer Manager Energy Optimizers, USA May, 2018 Test your Energy IQ 11

More information

Energy Modeling Applications for Existing Buildings

Energy Modeling Applications for Existing Buildings Energy Modeling Applications for Existing Buildings Presented by: Clark Denson PE, CEM, BEMP, LEED AP BD+C 4/27/12 Learning Objectives 1. List available methods and tools for energy modeling 2. Explain

More information

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Hotels and Restaurants October 18, 2012

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Hotels and Restaurants October 18, 2012 Pepco & Delmarva Power Commercial & Industrial Energy Savings Program Hotels and Restaurants October 18, 2012 Housekeeping The presentation will be emailed to you after the webinar. If you have technical

More information

Italcementi Center for Research and Innovation

Italcementi Center for Research and Innovation Italcementi Center for Research and Innovation Bergamo, Italy LEED-NC v2.1 EAc1 A. Project Narrative (Viridian) analyzed the energy use of the proposed Italcementi Center for Research and Innovation located

More information

White Paper ENVELOPE-FIRST APPROACH TO NET-ZERO ENERGY BUILDINGS

White Paper ENVELOPE-FIRST APPROACH TO NET-ZERO ENERGY BUILDINGS BOULDER CHICAGO NASHVILLE SALT LAKE CITY SAN FRANCISCO SPRINGFIELD, MO WASHINGTON, DC 2540 Frontier Avenue, Suite 100 Boulder, Colorado 80301 303.444.4149 White Paper ENVELOPE-FIRST APPROACH TO NET-ZERO

More information

Energy Conservation and Finances Using NYPA Performance Contracts. SUNY Sustainability Conference September 19-20, 2011

Energy Conservation and Finances Using NYPA Performance Contracts. SUNY Sustainability Conference September 19-20, 2011 Energy Conservation and Finances Using NYPA Performance Contracts SUNY Sustainability Conference September 19-20, 2011 By The Numbers Acres......... 476 Buildings...... 76 Square Feet.... 2.6M + Student

More information

Hawaii Energy Policy Forum and Energy Industries Energy by Example Audit Awards Status Report October 2006-November 2007

Hawaii Energy Policy Forum and Energy Industries Energy by Example Audit Awards Status Report October 2006-November 2007 Hawaii Energy Policy Forum and Energy Industries Energy by Example Audit Awards Status Report October 2006-November 2007 Introduction In August 2006, the Hawaii Energy Policy Forum (Forum) invited over

More information

BGSU Construction Standards Office of Design & Construction Bowling Green State University

BGSU Construction Standards Office of Design & Construction Bowling Green State University TABLE O CONTENTS: ENERGY MANAGEMENT GUIDELINE... 1 PURPOSE... 1 REERENCES... 1 GENERAL... 1 1. ENERGY CONSERVATION GOALS... 1 2. ENERGY MODELING & ANALYSIS.... 3 3. MEASUREMENT AND VERIICATION (M&V)...

More information

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available?

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available? Why an Energy Efficiency Program? Business Solutions Energy Efficiency Incentive Program MPSC 21st Century Electric Energy Plan More electricity is needed as soon as practicable. One way of achieving this

More information

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity Energy Accounting & Education Energy Managers Kermit King School District of La Crosse John Daily School District of Holmen 1 Topics (Electricity) Creating electricity Defining degree days Customer charges

More information

Energy. Efficiency Guide. for Minnesota Colleges and Universities. Tips to make you even smarter about saving energy

Energy. Efficiency Guide. for Minnesota Colleges and Universities. Tips to make you even smarter about saving energy Energy Efficiency Guide for Minnesota Colleges and Universities Tips to make you even smarter about saving energy Building on strong energy knowledge Along with technologies and scientific breakthroughs

More information

Application of Advanced Energy Technologies

Application of Advanced Energy Technologies GLOBALCON 2002 Philadelphia, Pennsylvania March 27, 2002 Application of Advanced Energy Technologies Michael K. West, Ph.D., P.E. Building Systems Scientist Advantek Consulting, Inc. www.advantekinc.com

More information

179D Tax Deductions for Architects & Engineers

179D Tax Deductions for Architects & Engineers 179D Tax Deductions for Architects & Engineers Presented by: CJ Aberin, CCSP, Electrical Engineer Senior Manager 877-525-4462 x148 cj@kbkg.com www.kbkg.com Overview History Section 179D Energy Efficient

More information

Dynamic simulation of buildings: Problems and solutions Università degli Studi di Trento

Dynamic simulation of buildings: Problems and solutions Università degli Studi di Trento Dynamic simulation of buildings: Problems and solutions Università degli Studi di Trento Paolo BAGGIO The basic problem To design (and operate) energy efficient buildings, accurate modeling tools are needed.

More information

Better By Design Energy Efficiency in Needham s Public Construction Projects

Better By Design Energy Efficiency in Needham s Public Construction Projects Better By Design Energy Efficiency in Needham s Public Construction Projects Green Needham Monday, November 26 th, 2012 7:00PM Needham Public Library Energy Efficiency in Town Projects Presenters tonight

More information

2. Chilled Water Storage: A 4.4-million gallon chilled water storage tank improves Cornell s ability to meet peak cooling needs.

2. Chilled Water Storage: A 4.4-million gallon chilled water storage tank improves Cornell s ability to meet peak cooling needs. SECTION 018130 ENERGY MODELING GUIDELINES APPENDIX A Modeling the District Heating and Cooling Systems of Cornell University for LEED Projects PART 1: GENERAL 1.01 PURPOSE A. Cornell is continually improving

More information

A. Cornell s district energy systems include the following components:

A. Cornell s district energy systems include the following components: SECTION 018130 ENERGY MODELING GUIDELINES APPENDIX A Modeling the District Heating and Cooling Systems of Cornell University for LEED Projects PART 1: GENERAL 1.01 PURPOSE A. Cornell is continually improving

More information

Matt Gudorf Campus Energy Manager. Page 1

Matt Gudorf Campus Energy Manager. Page 1 Matt Gudorf Campus Energy Manager Page 1 Quick Facts About UCI 7.4 Million Square Feet of Conditioned Space District High Temp and Chilled Water Campus 12kV owned and operated grid 4.5 Million Gallon Thermal

More information

PECO Smart Ideas for Your Business

PECO Smart Ideas for Your Business PECO Smart Ideas for Your Business April 2015 Agenda PECO Smart Ideas incentive programs Program measures and process Tools and Trade Allies 2 1 PECO Smart Ideas PA Act 129 Program incentives designed

More information

Exhibit A Program Descriptions, Historical Changes and Proposed Changes

Exhibit A Program Descriptions, Historical Changes and Proposed Changes Exhibit A Program Descriptions, Historical Changes and Proposed Changes Exhibit A Program Descriptions, Historical Changes and Changes Reflected in Forecasts Home Energy Savings The Home Energy Savings

More information

2018 ENERGY REPORT. Mark J. Ferguson, P.E. Campus Operations & Plant Manager

2018 ENERGY REPORT. Mark J. Ferguson, P.E. Campus Operations & Plant Manager 2018 ENERGY REPORT Mark J. Ferguson, P.E. Campus Operations & Plant Manager Table of Contents Executive Summary... 2 Utilities Overview... 3 Avoided Cost... 4 Carbon Footprint... 5 Benchmarking Colorado

More information

ENERGY MODELING GUIDELINES. D. Section Building Automation and Control System Guidelines

ENERGY MODELING GUIDELINES. D. Section Building Automation and Control System Guidelines 018130 ENERGY MODELING GUIDELINES PART 1: GENERAL 1.01 RELATED SECTIONS A. Section 018110 Green Building Guidelines B. Section 230000 Basic HVAC Requirements C. Section 230540 Laboratories D. Section 230900

More information

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses SMART HVAC & LIGHTING SYSTEMS Savings From Two Major C&I End Uses September 21, 2016 PRESENTATION OVERVIEW Why this focus? Significant savings potential Smart controls coupled with more efficient technologies

More information

Identifying Strong ROI Opportunities for Green Upgrades and Engaging your Entire Portfolio on Incremental Change

Identifying Strong ROI Opportunities for Green Upgrades and Engaging your Entire Portfolio on Incremental Change Identifying Strong ROI Opportunities for Green Upgrades and Engaging your Entire Portfolio on Incremental Change Presented by: Ryan Delliacono, AGPM, LLD DeeAnne McClenahan, Greystar Kelly Thompson, HD

More information

LOGO. Trivium Level II Energy Audit

LOGO. Trivium Level II Energy Audit LOGO Trivium Level II Energy Audit Submission Date: 9/16/2016 Table of Contents 1.0 EXECUTIVE SUMMARY 3 2.0 SITE ENERGY CONSUMPTION 5 3.0 BACKGROUND INFORMATION 6 3.1 Description of the Client 6 3.2 Description

More information

Energy Efficiency, GeoExchange Systems and Renewable Energy MiAPPA Winter 2010

Energy Efficiency, GeoExchange Systems and Renewable Energy MiAPPA Winter 2010 GETTING TO NET-ZERO Energy Efficiency, GeoExchange Systems and Renewable Energy MiAPPA Winter 2010 Jan Culbertson, AIA, LEED AP Sr. Principal A3C Collaborative Architecture James Hardin, P.E. Sr. VP of

More information

Building Control Strategies That Work to Improve Your Energy Bottom Line

Building Control Strategies That Work to Improve Your Energy Bottom Line Building Control Strategies That Work to Improve Your Energy Bottom Line William D. (Skip) Milton MBA, CEM, CEA Assistant Director of Facilities Operations Texas Children s Hospital Objective: Learn how

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.1 OVERVIEW This document has been prepared for as a. This document is the culmination of a comprehensive analysis of the current and future use and production of energy and water on campus. The purpose

More information

Pepco C&I Energy Savings Program. AOBA Briefing April 27, 2011

Pepco C&I Energy Savings Program. AOBA Briefing April 27, 2011 Pepco C&I Energy Savings Program AOBA Briefing April 27, 2011 Program Eligibility Pepco s Maryland commercial and industrial customers are eligible for CASH incentives for projects that reduce electric

More information

Lambton Kent District School Board

Lambton Kent District School Board Lambton Kent District School Board Management and Demand Management Plan June 24, 2014 1 Table of Contents Table of Contents Conservation and Demand Management Plan... 3 Introduction... 3 The Green Act...

More information

ENERGY AUDIT REPORTS SUMMARY

ENERGY AUDIT REPORTS SUMMARY Steven Winter Associates, Inc. 293 Route 18, Suite 330 Telephone (866) 676-1972 Building Systems Consultants East Brunswick, NJ 08816 Facsimile (203) 852-0741 www.swinter.com February 16, 2011 Sussex Community

More information

LEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering

LEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering LEED Commissioning and Actual Energy Use John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering AIA Quality Assurance Learning Objectives 1. Why Best Practice and Fundamental Commissioning are

More information

International Certification Scheme 1.0

International Certification Scheme 1.0 CEM International Certification Scheme Page 1 of 9 International Certification Scheme 1.0 Scope The Certified Energy Manager (CEM ) is an individual who optimizes the energy performance of a facility,

More information

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business FirstEnergy s Pennsylvania Utilities Energy Efficiency Programs for Business 2018 TODAY S AGENDA Introduction to Sodexo Summary of Pennsylvania Act 129 Overview of program website Overview of Application

More information

Local Government Energy Audit: Energy Audit Report

Local Government Energy Audit: Energy Audit Report Local Government Energy Audit: Energy Audit Report Panzer Athletic Center Copyright 2017 TRC Energy Services. All rights reserved. Reproduction or distribution of the whole, or any part of the contents

More information

Energy Reduction Strategy Through 2020

Energy Reduction Strategy Through 2020 Through 2020 Revised: August 2017 Executive Summary Auburn University is a land, sea and space grant university established in 1856. The university consists of 11,629,000 square feet on 1,840 acres and

More information

DCAS Energy Management. August 15, 2014 Ellen Ryan & Mike Dipple

DCAS Energy Management. August 15, 2014 Ellen Ryan & Mike Dipple DCAS Energy Management August 15, 2014 Ellen Ryan & Mike Dipple DCAS Energy Management Mission DCAS Energy Management (DEM) serves as the hub for City government s energy management. DEM provides energy

More information

DTE Energy Commercial & Industrial Energy Optimization Program. Trade Ally Meeting. Guardian Plumbing & Heating January 20, 2011

DTE Energy Commercial & Industrial Energy Optimization Program. Trade Ally Meeting. Guardian Plumbing & Heating January 20, 2011 DTE Energy Commercial & Industrial Energy Optimization Program Trade Ally Meeting Guardian Plumbing & Heating January 20, 2011 Agenda Introduction DTE Energy Your Energy Savings Program Overview 2011 Program

More information

DIGITAL AND ENVIRONMENTAL SKILLS FOR FACILITIES MANAGEMENT

DIGITAL AND ENVIRONMENTAL SKILLS FOR FACILITIES MANAGEMENT DIGITAL AND ENVIRONMENTAL SKILLS FOR FACILITIES MANAGEMENT O3 A1 Learning unit 2 Energy efficiency and energy management in buildings Project Start Date - October 1st, 2016 Project End Date - March 31,

More information

Consumers Energy Business Solutions. Commercial and Industrial Energy Efficiency Program January 15, 2013

Consumers Energy Business Solutions. Commercial and Industrial Energy Efficiency Program January 15, 2013 Consumers Energy Business Solutions Commercial and Industrial Energy Efficiency Program January 15, 2013 1 David MacDonald Senior Marketing Manager TODAY S PRESENTER 2 3 Today s Topics Program Summary

More information

Minnesota Conservation

Minnesota Conservation Program Information MN Minnesota Conservation Programs Summary We offer solutions for business customers in a suite of energy conservation and energy management products that will help you increase your

More information

Incentives. After work is complete:

Incentives. After work is complete: SAVE your WAY Create your own Energy Demand Savings with OUC s Commercial & Industrial Custom Incentive Program Overview OUC is committed to helping your business become more energy efficient. We understand

More information

A GUIDE TO ENERGY MANAGEMENT. U.S. Environmental Protection Agency ENERGY STAR

A GUIDE TO ENERGY MANAGEMENT. U.S. Environmental Protection Agency ENERGY STAR A GUIDE TO ENERGY MANAGEMENT U.S. Environmental Protection Agency ENERGY STAR 1 Agenda ENERGY STAR Overview Energy Management Guidelines ENERGY STAR Tools & Resources Building Upgrade Manual Energy Performance

More information

UNIFIED FACILITIES CRITERIA (UFC)

UNIFIED FACILITIES CRITERIA (UFC) UNIFIED FACILITIES CRITERIA (UFC) ENERGY CONSERVATION APPROVED FOR PUBLIC RELEASE: DISTRIBUTION UNLIMITED UNIFIED FACILITIES CRITERIA (UFC) ENERGY CONSERVATION Any copyrighted material included in this

More information

Energy Savings Performance Contracting What is Performance Contracting? How Does It Work? How Are Savings Calculated?

Energy Savings Performance Contracting What is Performance Contracting? How Does It Work? How Are Savings Calculated? Energy Savings Performance Contracting What is Performance Contracting? How Does It Work? How Are Savings Calculated? ABMA Annual Meeting January 15, 2011 About the Energy Services Coalition Public-private

More information

Wakulla Chamber of Commerce July Place your cover photo here. Size and crop it to 4 high x 9.6 wide. Presented by Derick Farfan

Wakulla Chamber of Commerce July Place your cover photo here. Size and crop it to 4 high x 9.6 wide. Presented by Derick Farfan Wakulla Chamber of Commerce July 2017 Commercial Energy Efficiency Programs Place your cover photo here. Size and crop it to 4 high x 9.6 wide. Presented by Derick Farfan Energy Efficiency Incentives Question:

More information

Chapter 6:Energy & Atmosphere

Chapter 6:Energy & Atmosphere Chapter 6:Energy & Atmosphere Category with highest number of points 1 Learning Objectives Fundamental & Enhanced commissioning and verification Minimum & Optimize energy performance Building-level & Advanced

More information

Green Star Shopping Centre Design PILOT Energy Calculator Guide

Green Star Shopping Centre Design PILOT Energy Calculator Guide Green Star Shopping Centre Design PILOT Energy Calculator Guide Prepared by: Advanced Environmental Green Building Council of Australia Page 1 of 29 EXECUTIVE SUMMARY The Green Star Shopping Centre Design

More information

U.S. Chamber of Commerce

U.S. Chamber of Commerce U.S. Chamber of Commerce Energy Efficiency through Performance Contracts John Mahoney Senior Vice President Chevron Energy Solutions A Division of Chevron U.S.A. Inc. April 21, 2011 Long-Term Global Energy

More information

WAKE TECHNICAL COMMUNITY COLLEGE SUSTAINABLE ENERGY PLAN. Energy Plan

WAKE TECHNICAL COMMUNITY COLLEGE SUSTAINABLE ENERGY PLAN. Energy Plan Energy Plan 1 EXECUTIVE SUMMARY SCORECARD RESULTS An assessment of current energy management efforts was performed; current performance falls into all categories on the SEP-Performance Scorecard (Appendix

More information

The Greenest Little Schools in the Midwest

The Greenest Little Schools in the Midwest The Greenest Little Schools in the Midwest And what we can do to get there Andy Robinson LEED AP, Energy Engineer Smart Energy Design Assistance Center Overview Introduction A Little About SEDAC The Language

More information

SCHAEDLER YESCO ENERGY EFFICIENT TECHNOLOGIES

SCHAEDLER YESCO ENERGY EFFICIENT TECHNOLOGIES SCHAEDLER YESCO ENERGY EFFICIENT TECHNOLOGIES Topics: Energy Usage and Types Energy Conservation Measures Implementation of Energy Retrofit Projects Incentives to Conserve Energy Electrical Energy Efficient

More information

Local Government Energy Audit:

Local Government Energy Audit: Local Government Energy Audit: Energy Audit Report Abbott and Costello Center Copyright 2017 TRC Energy Services. All rights reserved. Reproduction or distribution of the whole, or any part of the contents

More information

Farm Energy IQ. Farms Today Securing Our Energy Future. Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station

Farm Energy IQ. Farms Today Securing Our Energy Future. Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station Farm Energy IQ Farms Today Securing Our Energy Future Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station Farm Energy IQ Farm Energy Efficiency Principles Tom Manning,

More information

Commercial & Industrial Energy Optimization Programs

Commercial & Industrial Energy Optimization Programs SP Energy and Water Work Group Breakfast Meeting Commercial & Industrial Energy Optimization Programs May 2, 2011 Agenda Introduction DTE Energy Your Energy Savings Program Overview 2011 Program Changes

More information

Energy Efficiency and Reduction. Tribal Lands and Environment Forum August 15, 2016

Energy Efficiency and Reduction. Tribal Lands and Environment Forum August 15, 2016 Energy Efficiency and Reduction Tribal Lands and Environment Forum August 15, 2016 Energy Efficiency versus Energy Conservation Energy Conservation using less of an energy service Examples include: Turning

More information

Summary of Greening of State Government Executive Orders

Summary of Greening of State Government Executive Orders Summary of Greening of State Government Executive Orders Energy Management By Fiscal Year 2011-2012 achieve at least a 20% reduction in energy consumption of state facilities below fiscal year 2005-2006

More information

ENERGY INVESTIGATION. Energy Investigation Organization

ENERGY INVESTIGATION. Energy Investigation Organization Energy Investigation Organization A. Building Information, Energy Costs, and Energy Sources This section includes general questions about the school building, as well as questions about energy costs and

More information

Farm Energy IQ. Farm Energy Efficiency Principles 2/16/2015. Farm Energy Efficiency. Basic Energy Principles

Farm Energy IQ. Farm Energy Efficiency Principles 2/16/2015. Farm Energy Efficiency. Basic Energy Principles Farm Energy IQ Farm Energy IQ Farms Today Securing Our Energy Future Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station Farm Energy Efficiency Principles Tom Manning,

More information

Auburn Facilities Energy Reduction Plan

Auburn Facilities Energy Reduction Plan Auburn Facilities Energy Reduction Plan Revision 2: May 2012 Overall Plan: Auburn University Facilities will work to reduce energy usage, utility consumption, energy costs, and the University s carbon

More information

CSIRO Energy Centre Newcastle, New South Wales, Australia

CSIRO Energy Centre Newcastle, New South Wales, Australia CSIRO Energy Centre Newcastle, New South Wales, Australia Trevor Moody BE, BEc Commonwealth Scientific and Industrial Research Organisation (CSIRO), Australia. PO Box 227 Dickson ACT 2602 Australia. Telephone:

More information

Design Standard Sustainability

Design Standard Sustainability Design Standard Sustainability Purpose Educational institutions have the ability to influence the ideals and principles of our future decision makers; as such, East Side Union High School District (ESUHSD)

More information

Integrated Energy Master Plan Summary

Integrated Energy Master Plan Summary Integrated Energy Master Plan Summary January 8, 2013 Adapted from the original Board of Trustees presentation by Eric Utterson, PE, LEED AP Jerry Williams, PE, LEED AP 8760 Engineering, LLC St. Louis,

More information

is consciousness and action

is consciousness and action Kaua`i Renewable Energy Conference Miles Kubo President/COO September 8, 28 Energy Conservation is consciousness and action Turn off a light Walk a flight of stairs Shut down computers Unplug phantom loads

More information

Local Government Energy Audit:

Local Government Energy Audit: Local Government Energy Audit: i Energy Audit Report Lift Station #1, 3, 5, 6, 7, 8, and 9 Copyright 2018 TRC Energy Services. All rights reserved. Reproduction or distribution of the whole, or any part

More information

Connecticut Housing Finance Authority. Construction Guidelines: Energy Conservation 2019

Connecticut Housing Finance Authority. Construction Guidelines: Energy Conservation 2019 Connecticut Housing Finance Authority Construction Guidelines: Energy Conservation 2019 These Guidelines are effective I. Energy Conservation Guidelines Energy efficiency is strongly encouraged. An objective

More information

The Low Hanging Fruit Energy Efficient Lighting

The Low Hanging Fruit Energy Efficient Lighting The Low Hanging Fruit Energy Efficient Lighting John Noel, President Energy & Environment, LLC 2121-B Hollywood Rd., NW Atlanta, GA 30318 p.404.794.2023 john@energyandenvironment.com www.energyandenvironment.com

More information

Applying Energy Code to Existing Buildings

Applying Energy Code to Existing Buildings Applying Energy Code to Existing Buildings Massachusetts Energy Code Technical Support Program 1 Who Is Mass Save? Mass Save is an initiative sponsored by Massachusetts gas and electric utilities and energy

More information

Measurement & Verification for Performance Contracts Through Rebuild Colorado. January Rebuild Colorado

Measurement & Verification for Performance Contracts Through Rebuild Colorado. January Rebuild Colorado Measurement & Verification for Performance Contracts Through Rebuild Colorado January 2005 Rebuild Colorado A Program of the Governor's Office of Energy Management and Conservation 225 East 16th Avenue

More information

Applying Geothermal Technology for Large Scale Projects

Applying Geothermal Technology for Large Scale Projects Jeff Urlaub, PE MEP Associates, LLC jeffu@mepassociats.com 715.832.5680 Engineering Future Focused Solutions Applying Geothermal Technology for Large Scale Projects Breakout Session Category (e.g. Residential)

More information

SYRACUSE UNIVERSITY ENERGY CONSERVATION

SYRACUSE UNIVERSITY ENERGY CONSERVATION SYRACUSE UNIVERSITY ENERGY CONSERVATION 1955-2009 PREVIOUS TO 1955 Previous to 1955, most of our campus buildings were steam-heated from our coal fired Steam Plant located to the west of Campus on Burt

More information