1 INS 310 Water Supply and Sewerage Water Transmission and Distribution Systems Dr. A. Ozan Celik Monday, April 8,

2 Components of water supply systems: Municipal water systems generally comprise (a) collection works, (b) purification works, (c) transmission works, and (d) distribution works. 2

3 Transmission systems Supply conduits, or aqueducts, transport water from the source of supply to the community and, hence, form the connecting link between collection works and distribution systems. The location of the source determines whether conduits are short or long, and whether transport is by gravity or pumping. 3

4 Transmission systems The hydraulic design of supply conduits is concerned chiefly with (a) resistance to flow in relation to available and needed heads or pressures and (b) required and allowable velocities of flow relative to cost, scour, and sediment transport. In long supply lines, frictional or surface resistance offered by the pipe interior is the dominant element. In short transport systems, on the other hand, form resistance (minor losses) may be of controlling importance. 4

5 Transmission systems Multiple parallel pipes may be better than a single pipe for transmission lines: (a) when the maximum pipe size of manufacture is exceeded; 36 in. (900 mm) in the case of centrifugal cast-iron pipe, (b) when possible failure would put the line out of commission for a long time, and (c) when pipe location presents special hazards floods, ice, and ships anchors endangering river crossings or submarine pipes and cave-ins rupturing pipe lines in mining areas, for example. 5

6 Transmission systems Structurally, closed conduits must resist a number of different forces singly or in combination: 1. Internal pressure equal to the full head of water to which the conduit can be subjected 2. Unbalanced pressures at bends, contractions, and closures 3. Water hammer or increased internal pressure caused by sudden reduction in the velocity of the water by the rapid closing of a gate or shutdown of a pump, for example 4. External loads in the form of backfill and traffic 5. Their own weight between external supports (piers or hangers) 6. Temperature-induced expansion and contraction. 6

7 Transmission systems Important considerations for the transmission pipe lines are: 1. Depth of cover 2. Strength of material 3. Durability 4. Safety 5. Transportation 6. Leakage 7

8 Water distribution systems Water distribution systems have three major components: pumping stations, distribution storage, and distribution piping. Water Resources Engineering, 2nd Edition ISBN-13: , by Mays, Larry W 8

9 Water distribution systems Two distribution patterns emerge from the street plan: (a) a branching pattern in which ribbon development follows the primary arteries of roads and (b) a gridiron pattern within the built-up portions of the community where streets crisscross and water mains are interconnected Most common pipe system appurtenances: Gate valves Air valves Check valves Blowoffs Pressure reducing valves Flow control valves 9

10 Water distribution systems To determine the operating point of a pump system, the pump headcharacteristic curve (H-Q curve of the pump) and a system-head-capacity curve (H-Q curve of the piping system) are required. The pump operating point is the single point on these two H-Q curves where they intersect. Water Resources Engineering, 2nd Edition ISBN-13: , by Mays, Larry W 10

4A General Information A. Concept... 1 B. Conditions... 1

4A General Information A. Concept... 1 B. Conditions... 1 Design Manual Chapter 4 - Water Mains Table of Contents TOC Table of Contents Chapter 4 - Water Mains 4A General Information 4A-1---------------------------------General Information A. Concept....... 1

More information

Task 5. Christopher Mack Zack Kaldy MET 330 Fluid Mechanics November 8, Purpose

Task 5. Christopher Mack Zack Kaldy MET 330 Fluid Mechanics November 8, Purpose Purpose Task 5 Christopher Mack Zack Kaldy MET 330 Fluid Mechanics November 8, 2015 For the fifth task of this project we are asked to specify the layout of the piping system, the material type and sizes

More information

Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11)

Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11) بسم هللا الرحمن الرحيم Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11) A sewer that drops below the hydraulic gradient to pass under an obstruction, such as a railroad cut,

More information

Water supply components

Water supply components Water supply components Water sources structures (Dams, wells, reservoirs) Surface water Groundewater Pipelines from source Water treatment plant components Pumping stations Storage (elevated tanks) Distribution

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

ENGINEERING REPORT ANALYSIS OF CLOSURES. HOUSATONIC RIVER and NAUGATUCK RIVER FLOOD PROTECTION PROJECTS SECTION 1. ANSONIA and DERBY, CONNECTICUT

ENGINEERING REPORT ANALYSIS OF CLOSURES. HOUSATONIC RIVER and NAUGATUCK RIVER FLOOD PROTECTION PROJECTS SECTION 1. ANSONIA and DERBY, CONNECTICUT ENGINEERING REPORT ANALYSIS OF CLOSURES HOUSATONIC RIVER and NAUGATUCK RIVER FLOOD PROTECTION PROJECTS SECTION 1 ANSONIA and DERBY, CONNECTICUT December 2010 MMI #1560-119 and #3118-03 Prepared for: City

More information

Minimum grade (%) Velocity at full flow (m s 1 )

Minimum grade (%) Velocity at full flow (m s 1 ) 1.6 Pipes Effluent can be conveyed by channels or pipes under gravity or in dedicated pipelines under pressure. If pipes are used, pressure rating, water-hammer and excessive friction losses must be considered

More information

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable

More information

Piping layout for fire sprinkler system: An overview

Piping layout for fire sprinkler system: An overview Piping layout for fire sprinkler system: An overview Kshitiz Vishnoi Abstract In today s times, the designing of piping systems has become an important field. With increased urbanization, and construction

More information

Hydraulics Laboratory Experiment Report

Hydraulics Laboratory Experiment Report Hydraulics Laboratory Experiment Report Name: Ahmed Essam Mansour Section: Title: "1", Monday 2-5 pm Centrifugal Pumps Date: 27 November, 2006 Objectives: To study the performance of a centrifugal pumps

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7: Hydraulic Design of Sewers and Storm Water Drains 7.0 HYDRAULIC DESIGN OF SEWERS AND STORM WATER DRAINS 7.1 General Consideration

More information

Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES

Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES A. GENERAL 1. The following water system design guidelines are based on Federal, State and local health requirements and the Hilton Head No. 1 Public

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 Alberta Transportation Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 17.0 MAIN CANAL CONVEYANCE STRUCTURES 17.1 General Conveyance structures typically employed on main

More information

Session 2 Pump Selection. Mark Markham, P.E. Gresham, Smith and Partners September 14, 2017

Session 2 Pump Selection. Mark Markham, P.E. Gresham, Smith and Partners September 14, 2017 Session 2 Pump Selection Mark Markham, P.E. Gresham, Smith and Partners September 14, 2017 Quick Refresh System Curves graphically show the relationship between flow rates and associated total dynamic

More information

City of Wentzville. Standard Specifications and Construction Details Amendment List

City of Wentzville. Standard Specifications and Construction Details Amendment List Amendment No. 1 Standard Specifications and Construction Details Amendment List Date: September 21, 2009 Subject: SCD 700.23 - Residential Entrance Layout and drawing revised to more clearly show the location

More information

10.0 Storm Sewer Systems

10.0 Storm Sewer Systems October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and

More information

Variable Speed Waste Water Pumping

Variable Speed Waste Water Pumping Variable Speed Waste Water Pumping Challenges & Opportunities Kristel Zaman Marketing & Business Development Manager Flygt Large Systems Xylem North America Background VFDs have become common during the

More information

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System INSTRUCTIONS: This form shall be completed and submitted (in duplicate)

More information

Overview. We will not study pipe systems in detail as these are always solved with software. Wednesday, September 01, :21 PM.

Overview. We will not study pipe systems in detail as these are always solved with software. Wednesday, September 01, :21 PM. Ch4 Page 1 Overview Wednesday, September 01, 2010 4:21 PM We will not study pipe systems in detail as these are always solved with software EGL, HGL Wednesday, September 01, 2010 3:51 PM Energy drives

More information

Module 3. Irrigation Engineering Principles. Version 2 CE IIT, Kharagpur

Module 3. Irrigation Engineering Principles. Version 2 CE IIT, Kharagpur Module 3 Irrigation Engineering Principles Lesson 8 Conveyance Structures for Canal Flows Instructional objectives On completion of this lesson, the student shall learn the following: 1. The need for structures

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Environmental Engineering-I

Environmental Engineering-I Environmental Engineering-I Prof. Dr. Muhammad Zulfiqar Ali Khan Engr. Muhammad Aboubakar Farooq Water Distribution Systems & Analysis 1 Water Distribution Systems & Analysis References Water Supply &

More information

The purpose of distribution system is to deliver water to consumer with appropriate quality, quantity and pressure. Distribution system is used to

The purpose of distribution system is to deliver water to consumer with appropriate quality, quantity and pressure. Distribution system is used to Water Distribution System INTRODUCTION The purpose of distribution system is to deliver water to consumer with appropriate quality, quantity and pressure. Distribution system is used to describe collectively

More information

SECTION 4 RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS

SECTION 4 RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS 4.1 General SECTION 4 RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS Distribution system improvements, which have been organized and prioritized in this section, are forecasted and intended to be completed

More information

SAWEA Workshop 2010 Innovative Water and Wastewater Networks Presented by Greg Welch, AECOM

SAWEA Workshop 2010 Innovative Water and Wastewater Networks Presented by Greg Welch, AECOM SAWEA Workshop 2010 Innovative Water and Wastewater Networks Presented by Greg Welch, AECOM Basic Hydraulic Principles Open channel flow Closed conduit / pressurized flow systems Orifices, weirs and flumes

More information

Sewer Audit - Design Checklist Gravity sewers, sewage pumping stations and pressure sewers

Sewer Audit - Design Checklist Gravity sewers, sewage pumping stations and pressure sewers Question Relevant Clauses Design checked? Do the drawings show an appropriate revision history, and is 1.1 the design complete, checked and effectively ready for construction? 1.2 Has the whole catchment

More information

The Montreal Water Supply*

The Montreal Water Supply* The Montreal Water Supply* C. J. DESBAILLETS Chief Engineer, Montreal Water Board, Montreal, Canada N the year 1800, The Montreal Aqueduct was formed and received a 50-years franchise for the installation

More information

Concrete Pressure Pipe

Concrete Pressure Pipe Concrete Pressure Pipe AWWA MANUAL M9 Third Edition Contents List of Figures, vii List of Tables, xi Acknowledgments, xiii Chapter 1 Purpose and Scope............................................... 1 Chapter

More information

Environmental Engineering-I

Environmental Engineering-I Environmental Engineering-I Prof. Dr. Muhammad Zulfiqar Ali Khan Engr. Muhammad Aboubakar Farooq Department of Civil Engineering The University of Lahore 1 Water Supply Pipes Valves Fire Hydrants 2 Water

More information

INTRODUCTION. PVC PRESSURE PIPE SPECIFICATIONS The SANS 966 is a two-part specification.

INTRODUCTION. PVC PRESSURE PIPE SPECIFICATIONS The SANS 966 is a two-part specification. 1 INTRODUCTION DPI Plastics (Pty) Ltd is a leading manufacturer of PVC and HDPE water reticulation and drainage pipe and fitting systems with two ISO 9001 certified South African factories based in Johannesburg

More information

7. Allowable Fittings.

7. Allowable Fittings. 7. Allowable Fittings. a. General Requirements. 1) The fittings listed in this section are generally the allowable fittings for the design of DIP and PVC pipe. For steel pipe and fittings, see Part One,

More information

WATER SUPPLY CODE. of Australia. WSA Version 2.3

WATER SUPPLY CODE. of Australia. WSA Version 2.3 WATER SUPPLY CODE of Australia WSA 03-2002 Version 2.3 Water Supply Code of Australia WSA 03 2002 Second Edition Version 2.3 Previous edition WSA 03: 1999 CONTENTS PREFACE 6 INTRODUCTION 9 PART 0: GLOSSARY

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

Introduction to Water Supply System OUTLINE

Introduction to Water Supply System OUTLINE Introduction to Water Supply System PDH: 4.0 hours 1 OUTLINE Water Supply System Objectives Elements of Water Supply System Source of Supply Collections System Treatment System Distribution System Planning

More information

Aqueducts and Water Pipes

Aqueducts and Water Pipes Aqueducts and Water Pipes - Conveyance and distribution : Water, whether it be drawn from surface or ground suppliers, must be conveyed to the community and distributed to the users. Conveyance from the

More information

Module 9 : Sewage And Storm water Pumping Stations. Lecture 11 : Sewage And Storm water Pumping Stations

Module 9 : Sewage And Storm water Pumping Stations. Lecture 11 : Sewage And Storm water Pumping Stations 1 P age Module 9 : Sewage And Storm water Pumping Stations Lecture 11 : Sewage And Storm water Pumping Stations 2 P age 9.1 Introduction There are certain locations where it is possible to convey sewage

More information

Pumps, Turbines, and Pipe Networks. Ch 11 Young

Pumps, Turbines, and Pipe Networks. Ch 11 Young Pumps, Turbines, and Pipe Networks Ch 11 Young Chapter Topics Types of pumps and turbines Moment of momentum review Pump and turbine theory Energy and power Pump selection Pump-pipe networks Use of pipe

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Irrigation Structures 2. Dr. M. R. Kabir

Irrigation Structures 2. Dr. M. R. Kabir CHAPTER 9 Irrigation Structures 2 Dr. M. R. Kabir Professor and Head, Department of Civil Engineering University of Asia Pacific (UAP), Dhaka LECTURE 22 What is Cross Drainage Works? In an irrigation project,

More information

SECTION FACILITY POTABLE WATER DISTIBUTION

SECTION FACILITY POTABLE WATER DISTIBUTION PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 22 11 00 FACILITY POTABLE WATER DISTIBUTION A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification

More information

Design and Construction Standards SECTION POTABLE WATER SYSTEMS

Design and Construction Standards SECTION POTABLE WATER SYSTEMS SECTION 15410 POTABLE WATER SYSTEMS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections,

More information

Polyethylene Piping for Underground Fire Main Systems

Polyethylene Piping for Underground Fire Main Systems Polyethylene Piping for Underground Fire Main Systems Bulletin: PP 504 Factory Mutual Approvals DRISCOPLEX Polyethylene Piping for Underground Fire Main Systems Factory Mutual Approvals DRISCOPLEX Polyethylene

More information

SEA Certified Piping Design Engineer

SEA Certified Piping Design Engineer SEA Certified Piping Design Engineer Certification Course Course Title Eligibility Criteria : SEA CERTIFIED PIPING DESIGN ENGINEER : Mechanical Engineer, Chemical & Petroleum Engineer Duration of Course

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

Learning objectives. Upon successful completion of this lecture, the participants will be able to: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to: Describe and perform the required step for designing sewer system networks Outline Design

More information

PAPERWORK REDUCTION ACT A. GENERAL

PAPERWORK REDUCTION ACT A. GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY - FEDERAL EMERGENCY MANAGEMENT AGENCY RIVERINE STRUCTURES FORM O.M.B No. 1660-0016 Expires: 12/31/2010 PAPERWORK REDUCTION ACT Public reporting burden for this form

More information

1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings

1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings SECTION 33 34 00 SANITARY FORCE MAIN PART 1 GENERAL 1.1 SCOPE OF WORK A. This section specifies the requirements for furnishing and installing sanitary force main and appurtenances. The pipe shall be of

More information

Project Alignment Appendix A

Project Alignment Appendix A Project Alignment Appendix A Fargo Moorhead Metropolitan Area Flood Risk Management Project EA Document This page is intentionally left blank Project Alignment Appendix A Table of Contents 1 BACKGROUND...

More information

Pipe Stress Analysis Where Do I Start?

Pipe Stress Analysis Where Do I Start? Pipe Stress Analysis Where Do I Start? This is a step-by-step logic guideline for the data collection effort that should occur prior to beginning to model a piping system for a stress analysis: TRIFLEX

More information

SECTION 18. AMERICAN General Index

SECTION 18. AMERICAN General Index SECTION 18 AMERICAN General Index General Index A Abbreviations Organizations...1-1 Standard, American...17-23 Abrasion Resistant Pipe...12-12 Accessories (See Joint Materials) American Flow Control Valves

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

B. Brunone University of Perugia C. Chiesa Metropolitana Milanese M. Ferrante - University of Perugia

B. Brunone University of Perugia C. Chiesa Metropolitana Milanese M. Ferrante - University of Perugia MM http://www.global- TEA leakagesummit-2013.com/ B. Brunone University of Perugia C. Chiesa Metropolitana Milanese M. Ferrante - University of Perugia Outline MM pipe system What do we know about leak

More information

CE2304 Environmental Engineering I PART A 1. Define the term potable water. 2. State the causes for water pollution. 3. Write the advantage of sub-surface sources 4. What are the uses of nomograms? 5.

More information

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS DESIGN STANDARDS SECTION 2 INDEX ITEM DESCRIPTION 2.00 GENERAL STATEMENT 2.01 WATER DISTRIBUTION

More information

Army Base Treatment Plant

Army Base Treatment Plant Army Base Treatment Plant Norfolk Berthed at Nauticus, the Battleship Wisconsin is one of the largest and last battleships ever built by the U.S. Navy. 3Q Army Base AB010000 AB010500 3Q Legend Army Base

More information

CURRENT NORTH LAS VEGAS ADDENDA

CURRENT NORTH LAS VEGAS ADDENDA SECTION 1 Section 1.01.73 Fire Service Meter ADD: Type I is not approved for installation in the City of North Las Vegas service area. Section 1.01.107 Pressure Reducing Valve (PRV) or Pressure Regulator

More information

BOSfluids. The Flow Simulation Tool of Choice. Services Introduction Input, Output, and Analysis Features Features and Example System and Training

BOSfluids. The Flow Simulation Tool of Choice. Services Introduction Input, Output, and Analysis Features Features and Example System and Training BOSfluids The Flow Simulation Tool of Choice 1 Services Introduction Input, Output, and Analysis Features Features and Example System and Training 2 BOSfluids Introduction BOSfluids is an interactive computer

More information

CULINARY WATER SYSTEMS

CULINARY WATER SYSTEMS CULINARY WATER SYSTEMS I. Water system size determination A. The minimum water line size is 8 inch for distribution lines in a residential subdivision. 1. Subdivisions that have a school or church will

More information

Sustainable, Simple, Innovative and Effective

Sustainable, Simple, Innovative and Effective Sustainable, Simple, Innovative and Effective Ryan Flickinger KCI Technologies, Inc. Nicky Davis KCI Technologies, Inc. Russ Brown-Utility Service Group 1 What is Ice Pigging? A patented innovative sustainable

More information

INCIDENT AT YERING GORGE PUMPING STATION. HOW WHAT YOU DON T KNOW CAN HURT YOU. John deboer. Melbourne Water

INCIDENT AT YERING GORGE PUMPING STATION. HOW WHAT YOU DON T KNOW CAN HURT YOU. John deboer. Melbourne Water INCIDENT AT YERING GORGE PUMPING STATION. HOW WHAT YOU DON T KNOW CAN HURT YOU Paper Presented by: John deboer Author: John deboer, Operations Specialist, Water Supply Operations, Melbourne Water 79 th

More information

WASTEWATER SYSTEM STANDARDS

WASTEWATER SYSTEM STANDARDS 8.1 SCOPE Wastewater pipelines and appurtenances shall be provided as shown on the plans and as specified herein. Clearing, grubbing, trench excavation and backfill, pipe material, valves, cutting and

More information

Chapter 11 Culverts and Bridges

Chapter 11 Culverts and Bridges Chapter 11 Culverts and Bridges Contents 1.0 Introduction... 1 2.0 General Design... 1 2.1 Design Criteria... 1 2.2 Design Flows... 1 2.3 Permitting and Regulations... 1 2.4 Aesthetics and Safety... 2

More information

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT CHAPTER Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 19 By Dr. Ibrahim

More information

National Hydropower Association Operational Excellence Event Report. Environmental

National Hydropower Association Operational Excellence Event Report. Environmental 1) Submitting Organization: Redacted 2) Name of Preparer, Phone & Email: Redacted 3) Report Number (OE Internal Use): To Be Supplied Later 4) Date & Time of Event: 5) Duration of Event: 6) Functional Area:

More information

Calculate the Costs of Piping System Elements

Calculate the Costs of Piping System Elements Calculate the Costs of Piping System Elements by Ray Hardee, Engineered Software, Inc. Last month s column described the process of creating an energy cost balance sheet for a piping system (see Figure

More information

NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs

NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN INSTRUCTIONS: This notice shall be completed and submitted by persons proposing to construct projects permitted under the "General

More information

PART VII - WATER SYSTEM DESIGN CRITERIA

PART VII - WATER SYSTEM DESIGN CRITERIA PART VII - WATER SYSTEM DESIGN CRITERIA A. Water Distribution, General 1. The water system layout shall be approved by the City Engineer. The fire hydrant layout shall be approved by the Redwood City Fire

More information

بسم هللا الرحمن الرحيم

بسم هللا الرحمن الرحيم بسم هللا الرحمن الرحيم )ملحقات شبكة الصرف الصحي( Class Sewer Appurtenances- 3 rd Dr. Sataa Al-Bayati (10-11) 1. Manholes They are used for inspection & cleaning. They placed when: 1. Intervals between

More information

SECTION 8 WATER SUPPLY SYSTEMS

SECTION 8 WATER SUPPLY SYSTEMS SECTION 8 WATER SUPPLY SYSTEMS Contents Page 8-1 INTRODUCTION... 1 8-2 INTENT OF WATER SYSTEM IMPROVEMENT STANDARDS... 1 8-3 DEFINITIONS... 1 8-4 APPLICABLE STANDARDS... 1 8-5 IMPROVEMENT AND LANDSCAPE

More information

DIVISION 5 STORM DRAINAGE CRITERIA

DIVISION 5 STORM DRAINAGE CRITERIA DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the

More information

APPENDIX G HYDRAULIC GRADE LINE

APPENDIX G HYDRAULIC GRADE LINE Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING Question Bank CE2354 - ENVIRONMENTAL ENGINEERING - II Prepared By: Year: 3rd year Semester: 6th Semester R.THENMOZHI / A.P.Civil J.SHANMUGAPRIYA

More information

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards 2.9. WATER SYSTEM DESIGN Ivins City Standard Specifications for Design and Construction All culinary water mains and appurtenances shall be designed to provide for adequate future service for all contiguous

More information

PERFORMANCE PIPE DRISCOPLEX 4000/4100 Pipe Water and Wastewater Piping Systems

PERFORMANCE PIPE DRISCOPLEX 4000/4100 Pipe Water and Wastewater Piping Systems PERFORMANCE PIPE DRISCOPLEX 4000/4100 Pipe Water and Wastewater Piping Systems Corrosion Resistant Leak Proof Fused Joints Ideal for Trenchless Applications Flexible Hydraulically Efficient Will Not Tuberculate

More information

Chapter 8. Inlets. 8.0 Introduction. 8.1 General

Chapter 8. Inlets. 8.0 Introduction. 8.1 General . Introduction This chapter provides criteria and design guides for evaluating and designing storm sewer inlets in the City of Centennial. The review of all planning submittals will be based on the criteria

More information

Fire Protection Underground Piping. ASCE Meeting 12/17/14 Columbia, SC

Fire Protection Underground Piping. ASCE Meeting 12/17/14 Columbia, SC Fire Protection Underground Piping Columbia, SC What We ll Cover Today 2 Applicable NFPA standards Shop Drawing Requirements State Fire Marshal s Review Sprinkler Act Fire Sprinkler System Specification

More information

NZQA registered unit standard version 4 Page 1 of 5

NZQA registered unit standard version 4 Page 1 of 5 Page 1 of 5 Title Describe drinking-water supply reticulation systems Level 5 Credits 8 Purpose People credited with this unit standard are able to describe: the reticulated services found on public and

More information

Pipe Bursting Services. pipe bursting. services

Pipe Bursting Services. pipe bursting. services Pipe Bursting Services pipe bursting services We have decades of experience solving the really big problems. Concern over the condition of the nation s infrastructure has caused government, municipalities,

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

ONTARIO CENTRE FOR MUNICIPAL BEST PRACTICES 200 University Ave., Suite 801, Toronto, Ontario, M5H 3C6. BEST PRACTICE SUMMARY REPORT February, 2008

ONTARIO CENTRE FOR MUNICIPAL BEST PRACTICES 200 University Ave., Suite 801, Toronto, Ontario, M5H 3C6. BEST PRACTICE SUMMARY REPORT February, 2008 ONTARIO CENTRE FOR MUNICIPAL BEST PRACTICES 200 University Ave., Suite 801, Toronto, Ontario, M5H 3C6 BEST PRACTICE SUMMARY REPORT February, 2008 Water and Wastewater WATER LOSS MANAGEMENT CATHODIC PROTECTION

More information

GREEN THREAD Piping Systems

GREEN THREAD Piping Systems Bulletin No. A1300 February 15, 2006 SMITH FIBERCAST GREEN THREAD Piping Systems PRODUCT GREEN THREAD pipe is filament wound using an amine cured epoxy resin and fiberglass and has a resin-rich liner reinforced

More information

Guidelines for Construction of Pipe Distribution Network (PDN) for Irrigation

Guidelines for Construction of Pipe Distribution Network (PDN) for Irrigation Guidelines for Construction of Pipe Distribution Network (PDN) for Irrigation Mr. Sandesh B. Kulavmode 1, Dr.S.S.Valunjkar 2 1P.G. Student, Dept. of Civil Engineering, Government College of Engineering,

More information

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE SECTION 02632 POLYVINYL CHLORIDE (PVC) WATERLINE PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required, and install polyvinyl chloride (PVC) waterline,

More information

CHAPTER 12 TRICKLING FILTER PLANTS

CHAPTER 12 TRICKLING FILTER PLANTS CHAPTER 12 TRICKLING FILTER PLANTS TM 5-814-3/AFM 88-11, Volume III 12-1. General considerations. Trickling filter plants have been justified by their low initial cost, low operating and maintenance costs,

More information

Plan Name Plan No. Submitting Firm Contact Engineer. Review Date ESI Team ENGINEERS AND SURVEYORS INSTITUTE PEER REVIEW CHECKLIST CITY OF ALEXANDRIA

Plan Name Plan No. Submitting Firm Contact Engineer. Review Date ESI Team ENGINEERS AND SURVEYORS INSTITUTE PEER REVIEW CHECKLIST CITY OF ALEXANDRIA EROSION AND SEDIMENT CONTROL CHECKLIST (E&S) VIRGINIA EROSION AND SEDIMENT CONTROL HANDBOOK (1 of 2) Item # Description OK NO N/A 1 Limits of clearing and grading match on all appropriate sheets 2 Construction

More information

SECTION HANGERS AND SUPPORTS PART 1 - GENERAL. A. Drawings and Division 1 Specification Sections, apply to this Section.

SECTION HANGERS AND SUPPORTS PART 1 - GENERAL. A. Drawings and Division 1 Specification Sections, apply to this Section. 1.01 RELATED DOCUMENTS SECTION 15060 HANGERS AND SUPPORTS PART 1 - GENERAL A. Drawings and Division 1 Specification Sections, apply to this Section. 1.02 SUMMARY A. This Section includes hangers and supports

More information

PART I DESIGN STANDARDS AND PROCEDURES FOR WATER DISTRIBUTION AND SANITARY SEWER SYSTEMS PRINCE GEORGE COUNTY, VIRGINIA

PART I DESIGN STANDARDS AND PROCEDURES FOR WATER DISTRIBUTION AND SANITARY SEWER SYSTEMS PRINCE GEORGE COUNTY, VIRGINIA PART I DESIGN STANDARDS AND PROCEDURES FOR WATER DISTRIBUTION AND SANITARY SEWER SYSTEMS PRINCE GEORGE COUNTY, VIRGINIA May 2008 1 THIS PAGE INTENTIONALLY LEFT BLANK 2 TABLE OF CONTENTS DESIGN PAGE General

More information

Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary.

Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary. Report Engineering Services Group Capital Investment Plan (CIP) Quarterly Report for the period ending September 2012 Summary This report provides a summary of fiscal year accomplishments, capital expenditures

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and

More information

Table D-1. Montour County Hazard Mitigation Projects - Municipalities Affected. Structural Projects

Table D-1. Montour County Hazard Mitigation Projects - Municipalities Affected. Structural Projects Table D-1 Montour County Hazard Mitigation Projects - Municipalities Affected Structural Projects Project Description Mitigation Objective Hazard Municipality(s) Affected Pursue re-mapping of the 100-year

More information

On Wave-Defect Interaction in Pressurized Conduits

On Wave-Defect Interaction in Pressurized Conduits IAHR-HK Student Research Forum, November 17, 2012 On Wave-Defect Interaction in Pressurized Conduits Moez LOUATI, Prof. Mohamed S. GHIDAOUI Department of Civil and Environmental Engineering, Hong Kong

More information

ONE PIPE LENGTH MAX (REFER TO 1/4"/FT SLOPE (MIN) 5'-0" (MIN) OR 4" LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4"x6" REFER TO TYPICAL EXCAVATION,

ONE PIPE LENGTH MAX (REFER TO 1/4/FT SLOPE (MIN) 5'-0 (MIN) OR 4 LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4x6 REFER TO TYPICAL EXCAVATION, VENT CAP (MUSHROOM TYPE) SOLID CAP EXIST GRADE MIN BUILDING REFER TO NOTE #4 MIN CONCRETE SIDEWALK CURB OR EDGE OF SIDEWALK STREET CLEANOUT (REFER TO NOTE #3) VENT PIPE 4" PVC 6" PVC CLEANOUT CONCRETE

More information

STANDARDS FOR WATER FACILITIES

STANDARDS FOR WATER FACILITIES STANDARDS FOR WATER FACILITIES October 2009 200 South Ivy Street - Room 177 Medford, Oregon 97501 Phone: (541) 774-2430 Fax: (541) 774-2555 Standards For Water Facilities Board of Water Commissioners Cathie