Cork Institute of Technology. Summer 2008 Process Plant Design (Time: 3 Hours)

Size: px
Start display at page:

Download "Cork Institute of Technology. Summer 2008 Process Plant Design (Time: 3 Hours)"

Transcription

1 Cork Institute of Technology Bachelor of Science (Honours) in Process Plant Technology Award (EPPTN_8_Y4) (EPPTN_8_Y5) (EPPTE_8_Y4) Instructions: Answer FIVE questions. Answer at least TWO questions from each section. All questions carry equal marks. Use separate answer books for each section. Summer 2008 Process Plant Design (Time: 3 Hours) Examiners: Dr. Francis Murphy Section A Mr. William Bateman Section B Mr. N. Kingston Mr. J. Phelan Item Support Material Details Question Location 1. Steam Pipeline Sizing Chart Pressure Drop Q5 (with paper) 2. Vapour Pressure V s Water Temperature. Q7 (with paper) 3. CIBSE Table C Velocity press loss factors. Q7, Q8 (with paper) 4. CIBSE Table C4.11, Page Water 75 C Medium Grade steel. Q7 (with paper) 5. Lowara Pump HTF Data Sheet 04195D Q7 (with paper) 6. CIBSE Table C4.16, Page Water 10 C Heavy Grade Steel. Q8 (with paper) 7. n/a

2 Section A: Process Plant Design Q1. Determine the reinforcement requirements for a 300 mm diameter opening in a cylindrical pressure vessel 1 m in diameter subjected to an internal pressure of 5 MPa. The shell and nozzle allowable stress is 120 MPa. The shell and nozzle thickness are 25 mm and 32 mm, respectively. The reinforcement scheme is shown in Figure (Question 1). (20 marks) Figure (Question 1): FORMULAE: (based on the ASME design philosophy) PR The minimum required shell thickness is given by: t rs = s S 0.6P Reinforcement limit parallel to shell surface is the larger of t s +t n +0.5d or d. Reinforcement limit normal to the shell surface is the smaller of 2.5t s or 2.5t n SYMBOLS: P = Design Pressure R s = Shell Radius S = Allowable Stress d = opening diameter 2

3 Q2. In the great Boston molasses flood, which took place during the year of 1919, a tank failed by shear killing 21 and injuring more than 150 people. Seven steel sheets (joined to make cylindrical tubes) were stacked to form the tank. Single riveted lap joints (single shear) joined the horizontal seams between the tubes. Butt joints (double shear) and splice plates joined the vertical seam of the bottom tube. For each tube above the first (bottom) tube, six columns of lap joints fastened the steel sheet to form cylindrical tubes. Keeping the basic facts and using the data given below, design a similar storage tank, 90 ft (27.4 m) diameter, 58 ft (17.7 m) tall, to hold 2.5 million gallons of molasses. DATA: 1 US gallon = 3.8 x 10-3 m 3 ; Density of standard blackstrap molasses = 12 lb/gal ( kg/m 3 ) A36 structural steel yield stress = 36 ksi (248.3 MPa); Recommended safety factor = 3; Rivet strength: 25 mm diameter kips (52.42 kn) single shear; Rivet strength: 35 mm diameter kips (63.14 kn) single shear. FORMULAE: Pressure = ρgh + atmospheric pressure. Hoop stress, σ H = pr/t Longitudinal stress, σ L = pr/2t Force per unit length (vertical seam) F v = σ H t Force per unit length (horizontal seam) F H = σ L t SYMBOLS: ρ = density, g = acceleration due to gravity, h = height, p = pressure, t = thickness, r = radius, 3

4 Determine: (a) The height of molasses in the tank. (b) The pressure at the bottom of the tank. (c) The size and thickness of the seven steel sheets required. (d) The hoop stress and longitudinal stress in the tank walls. (e) The size/number of rivets required for both horizontal and vertical seams (4 marks) (4 marks) (4 marks) (4 marks) (4 marks) Q3. (a) Determine the proper lengths of weld, L 1 and L 2, for the connection of a 76 x 51 x 11.1 mm steel angle to steel plate, as shown in Figure (Question 3). The connection is to develop the full strength in the angle uniformly stressed to 140 MPa. Use 10 mm fillet welds, whose strength per AWS specification is 1020 newtons per linear millimetre. Figure (Question 3) (15 marks) 4

5 (b) Using Table (Question 3) and the same allowable stress, determine the lengths L 1 and L 2 for the connection of a 203 x 152 x 19 mm steel angle to steel plate. Use 12 mm fillet welds, whose strength is 1224 newtons per mm. (5 marks) Table (Question 3) 5

6 Q4. It is required to store 50,000 m 3 of natural gas, such that there will be a releasable volume of this amount of gas from the storage system at peak periods. A number of vessels at a storage pressure of 20 bar may be used. (a) Giving reasons, select the type of vessel that you consider suitable. (b) Select the number of vessels required again giving reasons. (c) Calculate the overall dimensions of the vessels. (d) Devise a management system that will ensure that the vessels are designed and manufactured to an appropriate safe standard. (3 marks) (3 marks) (4 marks) (10 marks) 6

7 Section B Process Plant Services. Q5 a) Compare and contrast the construction and operating characteristics of a Fire Tube Boiler with those of a Water Tube Boiler. [5 marks] b) Why is boiler feed water pre-treatment necessary. [5 marks] c) Why does TDS build up inside a steam boiler. What negative effects can high TDS have on boiler operation. How are TDS levels controlled within a steam boiler. [5 marks] d) Steam is generated at 10 Bar g pressure inside the boiler house. A new process 65m from the boiler house required 5000 kg/h at a minimum supply pressure of 9.0 bar g. Using the steam pipe sizing chart provided suggest the most suitable pipe diameter and calculate the actual pressure available at the point of use. NB design for a maximum pressure drop of 0.1 Bar / 100m. [5 marks] Reference:- Steam Pipeline Sizing Chart Pressure Drop Q5 (with paper) Q6 a) Describe with the aid of a neat sketch a typical refrigeration circuit. Label the four major components. Use arrows to indicate the direction of flow. Indicate relative pressures and liquid / gas phases after each of the four major components. [5 marks] b) Cooling towers are often used in conjunction with large refrigeration systems. With the aid of a neat sketch show a cross section through a cross draft cooling tower showing how the water flow and return can be connected to a refrigeration system with a water cooled condenser. Label all major components. [5 marks] c) Problems can occur due to continuous recirculation with partial evaporation of water inside a cooling tower. List two possible problems and describe the maintenance needed to prevent them. [5 marks] d) Plate Heat Exchangers and Shell and Tube Heat Exchangers are commonly used for heating and cooling of fluids. List five differences which might be considered when selecting either heat exchanger for a given application. [5 marks] 7

8 Q7 a) The following diagram shows a reactor vessel working under vacuum. The pump is Model HTF , manufactured by Lowara. Data sheet 04195D. Determine if the pump shown will cavitate under the operating conditions shown. Stainless Steel pipe connecting vessel to pump. No CIBSE charts for stainless steel pipe. Use charts for mild steel pipe and welded mild steel elbows Pressure Gauge Reading 5000 Pa 3 No. Air Operated Diaphram Valves w/d = 1.0. For CIBSE Table C No. In-line strainer zeta = 3.0 Pump Details Lowara HTF rpm Q=20 cubic m/h PG N2 blanket 3 m Water 60 Deg 3 m 1 m b) The production personnel predict a situation where the water temperature in the tank may increase to 85 Deg C on some occasions. Neglecting any change in flow velocity due to the higher water temperature, clarify if the change in vapour pressure alone would cause the pump cavitate. [5 marks] Vapour Pressure V s Water Temperature. Q7 (with paper) CIBSE Table C Velocity press loss factors. Q7 (with paper) CIBSE Table C4.11, Page Water 75 C Q7 (with paper) Medium Grade Steel. Lowara Pump HTF Data Sheet 04195D Q7 (with paper) 8

9 Q8 (a) Pump and pipe work required to transfer 90 m 3 /h of effluent from a waste water storage tank to an effluent treatment tank. Cold water 10 Deg C. Effluent to be distributed in equal volumes to each of 6 injection points. All effluent injection points require a minimum of 10m residual head pressure to facilitate mixing once the effluent enters the treatment tank. Use heavy grade steel pipe and welded fittings. 24hrs/day, 7 days/wk operation. Use 1m/s flow velocity to minimise delta P. Estimate the pipe diameter for each section of pipe. [10 marks] Specify overall flow and pressure requirements for the pump. [10 marks] References:- CIBSE Table C Velocity press loss factors for pipe work Q8 (with paper) CIBSE Table C4.16, Page 4-35, Water 10 C Heavy Grade Steel. Q8 (with paper) 9

10 10

11 11

12 12

13 13

14 14

15 15

16 16

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION

PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF CONSTRUCTION CONTENTS Foreword... xv Statements of Policy... xvii Personnel... xix Preamble... xxxi Summary of Changes... xxxiii List of Changes in BC Order... xxxvi PART PG GENERAL REQUIREMENTS FOR ALL METHODS OF

More information

VVER-440/213 - The reactor core

VVER-440/213 - The reactor core VVER-440/213 - The reactor core The fuel of the reactor is uranium dioxide (UO2), which is compacted to cylindrical pellets of about 9 height and 7.6 mm diameter. In the centreline of the pellets there

More information

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET 1. A vessel of volume 0.04m 3 contains a mixture of saturated water and steam at a temperature of 250 0 C. The mass of the liquid present is 9 kg. Find the pressure, mass, specific volume, enthalpy, entropy

More information

ChE 455 Fall 2001 Major 1. Ethylene Oxide Production

ChE 455 Fall 2001 Major 1. Ethylene Oxide Production 10/19/01 ChE 455 Fall 2001 Major 1 Ethylene Oxide Production Ethylene oxide is a chemical used to make ethylene glycol (the primary ingredient in antifreeze). It is also used to make poly(ethylene oxide),

More information

PAPER-I (Conventional)

PAPER-I (Conventional) 1. a. PAPER-I (Conventional) 10 kg of pure ice at 10 ºC is separated from 6 kg of pure water at +10 O C in an adiabatic chamber using a thin adiabatic membrane. Upon rupture of the membrane, ice and water

More information

ES230 Strength of Materials Exam 6 - Compilation Prof. Kurtz, ES230 STRENGTH OF MATERIALS Exam 6 Wednesday, April 26, 2017, 7pm

ES230 Strength of Materials Exam 6 - Compilation Prof. Kurtz, ES230 STRENGTH OF MATERIALS Exam 6 Wednesday, April 26, 2017, 7pm Given Formulae Bending M/EI = 1/ = -y/ =My/I = E Beam Shear Stress = VQ/It q = VQ/I q = F/s Torsion I = ( /4)r 4 for a solid, circular shape of radius r Pressure Vessels hoop = Pr/t long = Pr/2t ES230

More information

SEA Certified Piping Design Engineer

SEA Certified Piping Design Engineer SEA Certified Piping Design Engineer Certification Course Course Title Eligibility Criteria : SEA CERTIFIED PIPING DESIGN ENGINEER : Mechanical Engineer, Chemical & Petroleum Engineer Duration of Course

More information

Supplemental Plan Check List for Concrete Special Moment Resisting Frame

Supplemental Plan Check List for Concrete Special Moment Resisting Frame Plan Check / PCIS Application Number: Your feedback is important, please visit our website to complete a Customer Survey at /LADBSWeb/customer-survey.jsf. If you have any questions or need clarification

More information

Methodology for design of earthquake resistant steel liquid storage tanks

Methodology for design of earthquake resistant steel liquid storage tanks Earthquake Resistant Engineering Structures V 699 Methodology for design of earthquake resistant steel liquid storage tanks M. A. Haroun & M. A. Al-Kashif University of California, Irvine, and American

More information

Problems at the Cumene Production Facility, Unit 800

Problems at the Cumene Production Facility, Unit 800 Problems at the Cumene Production Facility, Unit 800 Background Cumene (isopropyl benzene) is produced by reacting propylene with benzene. During World War II, cumene was used as an octane enhancer for

More information

Task 5. Christopher Mack Zack Kaldy MET 330 Fluid Mechanics November 8, Purpose

Task 5. Christopher Mack Zack Kaldy MET 330 Fluid Mechanics November 8, Purpose Purpose Task 5 Christopher Mack Zack Kaldy MET 330 Fluid Mechanics November 8, 2015 For the fifth task of this project we are asked to specify the layout of the piping system, the material type and sizes

More information

COOLING TOWER DESIGN FOR CENTRAL GENERATORS OF CUET, BANGLADESH. Mohammad Sharif Khan, Golam Mainuddin, Abu Sadat Mohammad Sayem, Nadeem Nafis

COOLING TOWER DESIGN FOR CENTRAL GENERATORS OF CUET, BANGLADESH. Mohammad Sharif Khan, Golam Mainuddin, Abu Sadat Mohammad Sayem, Nadeem Nafis Proceedings of the 4 th BSME-ASME International Conference on Thermal Engineering 7-9 December, 008, Dhaka, Bangladesh COOLING TOWER DESIGN FOR CENTRAL GENERATORS OF CUET, BANGLADESH. Mohammad Sharif Khan,

More information

KEYSTONE SWING TYPE WAFER CHECK VALVE FIGURE 86

KEYSTONE SWING TYPE WAFER CHECK VALVE FIGURE 86 High capacity, spring loaded swing type wafer check valve FEATURES Lightweight, wafer type check valve with face-to-face dimensions according ISO 5752, table 5 long High flow capacity featuring a special

More information

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Styrene

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Styrene Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Styrene The feasibility of constructing a new, grass-roots, 100,000 tonne/y, styrene plant is being investigated. As part of

More information

FE Review Mechanics of Materials

FE Review Mechanics of Materials 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1. T he element is subjected to the plane stress condition shown. a-x = - 140 M Pa a- y = 205 M Pa Txy = 100 M Pa What is t

More information

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Ethylbenzene

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Ethylbenzene Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Ethylbenzene We continue to investigate the feasibility of constructing a new, grass-roots, 80,000 tonne/y, ethylbenzene facility.

More information

DESIGN, FABRICATION AND PERFORMANCE EVALUATION OF CONTINUOUS OPERATING AUTOCLAVE

DESIGN, FABRICATION AND PERFORMANCE EVALUATION OF CONTINUOUS OPERATING AUTOCLAVE Proceedings of the 3 rd International Conference on Civil Engineering for Sustainable Development (ICCESD 2016), 12~14 February 2016, KUET, Khulna, Bangladesh (ISBN: 978-984-34-0265-3) DESIGN, FABRICATION

More information

1/58 Components of solar systems

1/58 Components of solar systems 1/58 Components of solar systems storage heat exchangers safety and protection devices air vents, check valve control & measurement Thermosiphon circulation system 2/58 circulation induced by buoyancy

More information

SYNTHESIS GAS COOLER DOWNSTREAM OF PARTIAL OXIDATION OF OIL OR NATURAL GAS

SYNTHESIS GAS COOLER DOWNSTREAM OF PARTIAL OXIDATION OF OIL OR NATURAL GAS SYNTHESIS GAS COOLER DOWNSTREAM OF PARTIAL OXIDATION OF OIL OR NATURAL GAS BORSIG 1 About BORSIG Process Heat Exchanger GmbH BORSIG Process Heat Exchanger GmbH, a member of the BORSIG Group, is the international

More information

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS p 1 of 6 UF-1 UF-12 PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGING the test temperature be higher than 20 F ( 29 C). Certification is required. An ultrasonic examination shall be made

More information

7018 MR. Conformances

7018 MR. Conformances STICK (SMAW) ELECTRODE Excalibur 7018 MR Mild Steel, Low Hydrogen AWS Improved coating integrity Extreme bendability 60% less moisture pickup vs. competition Reduction of arc starting porosity Clear puddle

More information

Geothermal Power Plant

Geothermal Power Plant Geothermal Power Plant The Tokyo Electric Power Co., Inc., Japan Hachijo-jima Geothermal Power Plant 3,300kW 0A3-E-009 Outline All equipment and system except for the civil work and geothermal wells were

More information

MTBE Production. Process Description. Possibility of Changing Process Feed Conditions

MTBE Production. Process Description. Possibility of Changing Process Feed Conditions Production You work in a facility that produces about 100,000 tonne/y of methyl tertiary butyl ether (). is an oxygenated fuel additive that is blended with gasoline to promote CO 2 formation over CO formation

More information

Keystone swing type wafer check valve Figure 86

Keystone swing type wafer check valve Figure 86 High capacity, spring loaded swing type wafer check valve Features Lightweight, wafer type check valve with face-to-face dimensions according ISO 5752, table 5 long High flow capacity featuring a special

More information

9. VACUUM TANK 9. VACUUM TANK

9. VACUUM TANK 9. VACUUM TANK 9. VACUUM TANK This system constitutes the external part of the solenoid cryostat. The vacuum tank, made of stainless steel, is cantilevered from the central ring of the barrel yoke. It houses and supports

More information

ENGINEERING INFORMATION Hot water and steam service

ENGINEERING INFORMATION Hot water and steam service ENGINEERING INFORMTION Hot water and steam service What is steam? Like other substances, water can exist in the form of a solid, when we call it ice; as a liquid when we call it water or as a gas when

More information

Calculate the Costs of Piping System Elements

Calculate the Costs of Piping System Elements Calculate the Costs of Piping System Elements by Ray Hardee, Engineered Software, Inc. Last month s column described the process of creating an energy cost balance sheet for a piping system (see Figure

More information

BORSIG SYNTHESIS GAS COOLER DOWNSTREAM OF PARTIAL OXIDATION OF OIL OR NATURAL GAS PROCESS HEAT EXCHANGER. A Member of KNM Group Berhad

BORSIG SYNTHESIS GAS COOLER DOWNSTREAM OF PARTIAL OXIDATION OF OIL OR NATURAL GAS PROCESS HEAT EXCHANGER. A Member of KNM Group Berhad BORSIG PROCESS HEAT EXCHANGER SYNTHESIS GAS COOLER DOWNSTREAM OF PARTIAL OXIDATION OF OIL OR NATURAL GAS A Member of KNM Group Berhad 1 About BORSIG Process Heat Exchanger GmbH BORSIG Process Heat Exchanger

More information

GREEN THREAD Piping Systems

GREEN THREAD Piping Systems Bulletin No. A1300 February 15, 2006 SMITH FIBERCAST GREEN THREAD Piping Systems PRODUCT GREEN THREAD pipe is filament wound using an amine cured epoxy resin and fiberglass and has a resin-rich liner reinforced

More information

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Ammonia Your assignment is to continue evaluating the details of a process to produce 50,000 tonne/y of ammonia from a syngas

More information

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa.

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa. Chapters 5, 6, and 7 Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa. 5-1. Steam enters a steady-flow device at 16 MPa and 560 C with

More information

Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project. Production of Ethanol

Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project. Production of Ethanol Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project Production of Ethanol Your assignment is to continue evaluating the details of a process to produce 30,000 tonne/y of ethanol from ethylene.

More information

Design of Diesel Storage Tank in Consonance with Requirements of American Petroleum Institute (API) Standard 650

Design of Diesel Storage Tank in Consonance with Requirements of American Petroleum Institute (API) Standard 650 Design of Diesel Storage Tank in Consonance with Requirements of American Petroleum Institute (API) Standard 650 Abstract Okpala, Alexander N.* and Jombo, P.P., Department Of Mechanical Engineering, Faculty

More information

flow work, p. 173 energy rate balance, p. 174 nozzle, p. 177 diffuser, p. 177 turbine, p. 180 compressor, p. 184 (4.4b) p. 166

flow work, p. 173 energy rate balance, p. 174 nozzle, p. 177 diffuser, p. 177 turbine, p. 180 compressor, p. 184 (4.4b) p. 166 0 Chapter 4 Control Volume Analysis Using Energy The use of mass and energy balances for control volumes at steady state is illustrated for nozzles and diffusers, turbines, compressors and pumps, heat

More information

REINFORCING PRODUCT CATALOGUE MESH PRODUCT CATALOGUE MESH JAN 2013 S&T025

REINFORCING PRODUCT CATALOGUE MESH PRODUCT CATALOGUE MESH JAN 2013 S&T025 S&T025 JAN 2013 PRODUCT CATALOGUE MESH PRODUCT CATALOGUE MESH REINFORCING INDEX Introduction 1 NZ Standards relating to Steel Wire Fabric 2 Sheet Sizes 3 & 4 Standard Meshes, Wire Size, Pitch, Mass and

More information

Sample Questions for Welding Engineering Examinations

Sample Questions for Welding Engineering Examinations Sample Questions for Welding Engineering Examinations AWS Welding Engineer Revision 2 August 2003 Part 1 Basic Fundamentals of Science Examination Mathematics 1. Determine the acute angle _ when tan 63

More information

AMCOT COOLING TOWER CORPORATION LRC-H & LRC-LNS CROSS FLOW COOLING TOWER OPERATIONS AND MAINTAINENCE MANUAL

AMCOT COOLING TOWER CORPORATION LRC-H & LRC-LNS CROSS FLOW COOLING TOWER OPERATIONS AND MAINTAINENCE MANUAL AMCOT COOLING TOWER CORPORATION LRC-H & LRC-LNS CROSS FLOW COOLING TOWER 1. Preface OPERATIONS AND MAINTAINENCE MANUAL 1-800-444-8693 Operation and Maintenance Manual For Amcot LRC-H Cooling Tower & LRC-LNS

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT SECTION 220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION A. The General Conditions, Special Conditions and Division 1 through Division 22 as set forth in

More information

VENTURI FLOWMETERS. Your First Choice in Intelligent Flow Management...

VENTURI FLOWMETERS. Your First Choice in Intelligent Flow Management... VENTURI FLOWMETERS Your First Choice in Intelligent Flow Management... VENTURI FLOWMETERS Preso s complete line of Venturis offer reduced operating costs, proven accuracy, and great rangeability. Low permanent

More information

St.MARTIN S ENGINEERING COLLEGE

St.MARTIN S ENGINEERING COLLEGE St.MARTIN S ENGINEERING COLLEGE Dhulapally, Secunderabad-500 014 Subject: STRENGTH OF MATERIALS - II Class : Civil II Part-A (Short Answer Questions) UNIT-I 1 Define a) Torque b) Torsional moment of resistance

More information

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT UNIT 47: Engineering Plant Technology Unit code: F/601/1433 QCF level: 5 Credit value: 15 OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT 2 Be able to apply the steady flow energy equation (SFEE) to plant and equipment

More information

Application nr. 6 (Connections) Strength of welded connections to EN (Eurocode 3, Part 1.8)

Application nr. 6 (Connections) Strength of welded connections to EN (Eurocode 3, Part 1.8) Application nr. 6 (Connections) Strength of welded connections to EN 1993-1-8 (Eurocode 3, Part 1.8) PART 1: Design of a fillet weld connection in shear Initial data of the problem: Given two overlapping

More information

Fluid Mechanics. The Energy Equation [7] Dr. Mohammad N. Almasri

Fluid Mechanics. The Energy Equation [7] Dr. Mohammad N. Almasri 1 Fluid Mechanics The Energy Equation [7] Dr. Mohammad N. Almasri http://sites.google.com/site/mohammadnablus/home 2 Introduction There are various types of devices and components that are utilized in

More information

Design and Analysis of Hydraulic Oil Cooler by Application of Heat Pipe

Design and Analysis of Hydraulic Oil Cooler by Application of Heat Pipe Design and Analysis of Hydraulic Oil Cooler by Application of Heat Pipe Abstract Heat pipe is an essentially passive heat transfer device having high thermal conductivity. In hydraulic power pack use of

More information

Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard

Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard Introduction SRU s (Sulfur Recovery Units) are critical pieces of equipment in refineries and gas plants. SRUs remove sulfur compounds from certain

More information

ASME BPVC SECTION 1 - RULE FOR CONSTRUCTION OF POWER BOILERS

ASME BPVC SECTION 1 - RULE FOR CONSTRUCTION OF POWER BOILERS LAST UPDATED 15-12-2016 ASME BPVC SECTION 1 - RULE FOR CONSTRUCTION OF POWER BOILERS COURSE DURATION: 5 DAYS REACH US Today for Greater Safety, Quality, Reliability, Productivity, Profitability HRD Approved

More information

1.15 Chemical Tanker Longitudinal corrugated bulkhead (vertical type).

1.15 Chemical Tanker Longitudinal corrugated bulkhead (vertical type). Table A.1 corrugated bulkhead s Case Ship Type Damage Location 1.1 Chemical Tanker Longitudinal corrugated bulkheads (horizontal type) in way of mid cargo area. 1.2 Product Tanker Transverse corrugated

More information

DIVISION: METALS SECTION: STEEL DECKING REPORT HOLDER: EPIC METALS CORPORATION 11 TALBOT AVENUE RANKIN, PENNSYLVANIA 15104

DIVISION: METALS SECTION: STEEL DECKING REPORT HOLDER: EPIC METALS CORPORATION 11 TALBOT AVENUE RANKIN, PENNSYLVANIA 15104 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2047 Reissued 07/207 This report is subject to renewal 07/209. DIVISION: 05 00 00

More information

CENTRIFUGE DECANTER AND HOW IT WORKS

CENTRIFUGE DECANTER AND HOW IT WORKS CENTRIFUGE DECANTER AND HOW IT WORKS DECANTER CENTRIFUGE In a decanter there s a continuous mechanical separation of suspended solids from a liquid or liquids You could see a centrifuge decanter like a

More information

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13 Table of Contents Scope... 845 References... 845 Governmental... 845 EQT Midstream Publications... 845 Industry Standards... 846 Computer Programs... 846 1 Manufactured Branch Connections... 846 1.1 Extruded

More information

COMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.

COMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31. April 2012 Process Industry Practices Piping PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.3 Metallic Piping PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost

More information

Does Your Application Call for an F-Shell Heat Exchanger?

Does Your Application Call for an F-Shell Heat Exchanger? Heat Transfer Does Your Application Call for an F-Shell Heat Exchanger? Rajiv Mukherjee Consultant If the process has a temperature cross or a low flowrate, an F shell might prove beneficial. S EVERAL

More information

A class of its own JUMAG STEAM BOILER COMPACT INFORMATION STEAM BOILER WATER SUPPLY MODULES BLOW DOWN VESSEL COMPACT STEAM SYSTEM.

A class of its own JUMAG STEAM BOILER COMPACT INFORMATION STEAM BOILER WATER SUPPLY MODULES BLOW DOWN VESSEL COMPACT STEAM SYSTEM. A class of its own JUMAG STEAM BOILER COMPACT INFORMATION STEAM BOILER WATER SUPPLY MODULES BLOW DOWN VESSEL COMPACT STEAM SYSTEM www.jumag.de OIL OR GAS FIRED STEAM BOILER A class of its own Steam within

More information

Eng Thermodynamics I: Sample Final Exam Questions 1

Eng Thermodynamics I: Sample Final Exam Questions 1 Eng3901 - Thermodynamics I: Sample Final Exam Questions 1 The final exam in Eng3901 - Thermodynamics I consists of four questions: (1) 1st Law analysis of a steam power cycle, or a vapour compression refrigeration

More information

CHAPTER 12 TRICKLING FILTER PLANTS

CHAPTER 12 TRICKLING FILTER PLANTS CHAPTER 12 TRICKLING FILTER PLANTS TM 5-814-3/AFM 88-11, Volume III 12-1. General considerations. Trickling filter plants have been justified by their low initial cost, low operating and maintenance costs,

More information

Conventional Paper II (a) Draw a crank rocker mechanism and identify all instantaneous centers.

Conventional Paper II (a) Draw a crank rocker mechanism and identify all instantaneous centers. Conventional Paper II-2014 1. Answer of the following (Each part carries 4 marks): (a) Draw a crank rocker mechanism and identify all instantaneous centers. (b) A steel tube 2.5 cm external diameter and

More information

Design and Analysis of Multilayer High Pressure Vessels and Piping Tarun Mandalapu 1 Ravi Krishnamoorthy. S 2

Design and Analysis of Multilayer High Pressure Vessels and Piping Tarun Mandalapu 1 Ravi Krishnamoorthy. S 2 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 02, 2015 ISSN (online): 2321-0613 Design and Analysis of Multilayer High Pressure Vessels and Piping Tarun Mandalapu 1

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT SECTION 220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

DCV Wafer check valves

DCV Wafer check valves V Wafer check valves V wafer check valves to prevent reverse flow... The Spirax Sarco range of V wafer check valves provides an effective minimal maintenance free solution for the prevention of reverse

More information

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 13686.00 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 230529-1 SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 1.1 SUMMARY A. Section Includes: 1. Metal pipe hangers and supports.

More information

we move more than fluids Plate Heat Exchangers Type XPS + safe + smart + efficient LASER WELDED

we move more than fluids Plate Heat Exchangers Type XPS + safe + smart + efficient LASER WELDED we move more than fluids Plate Heat Exchangers safe smart efficient LASER WELDED The XPS for use under hard processing conditions. Our answer to the questions and challenges from the market for heat exchangers

More information

Product Test Report Solon Rd. December 2015 Solon, Ohio U.S.A. Page 1 of 5

Product Test Report Solon Rd. December 2015 Solon, Ohio U.S.A. Page 1 of 5 Solon, Ohio 44139 U.S.A. Page 1 of 5 TITLE Rotary Flexure Test of Alloy 825 Tubing with Stainless Steel Swagelok Tube Fittings PRODUCT TESTED Samples Tested Alloy 825 Tubing Size OD Wall in. Tubing Hardness

More information

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: )

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: ) QUIZ TEST-1 Q.1. In a stage of an impulse turbine provided with a single row wheel, the mean diameter of the blade ring is 80cm and the speed of the rotation is 3000rpm. The steam issues from the nozzle

More information

2. TECHNICAL DESCRIPTION OF THE PROJECT

2. TECHNICAL DESCRIPTION OF THE PROJECT 2. TECHNICAL DESCRIPTION OF THE PROJECT 2.1. What is a Combined Cycle Gas Turbine (CCGT) Plant? A CCGT power plant uses a cycle configuration of gas turbines, heat recovery steam generators (HRSGs) and

More information

Reactors and Separations Design Project. Phthalic Anhydride Production

Reactors and Separations Design Project. Phthalic Anhydride Production Reactors and Separations Design Project Phthalic Anhydride Production We are continuing our evaluation of process alternatives for the production of Phthalic Anhydride via the catalytic oxidation of o-xylene.

More information

PV Newsletter Monthly Publication from CoDesign Engineering Academy

PV Newsletter Monthly Publication from CoDesign Engineering Academy Volume 2012, Issue 6 June 15, 2012 PV Newsletter Monthly Publication from CoDesign Engineering Academy Tall Vertical Pressure Vessels Introduction Tall pressure vessels are generally defined as those where

More information

ANNALS of Faculty Engineering Hunedoara

ANNALS of Faculty Engineering Hunedoara ANNALS of Faculty Engineering Hunedoara International Journal of Engineering Tome XII [2014] Fascicule 4 [November] ISSN: 1584 2673 [CD Rom, online] a free access multidisciplinary publication of the Faculty

More information

CONTROL VOLUME ANALYSIS USING ENERGY. By Ertanto Vetra

CONTROL VOLUME ANALYSIS USING ENERGY. By Ertanto Vetra CONTROL VOLUME ANALYSIS USING ENERGY 1 By Ertanto Vetra Outlines Mass Balance Energy Balance Steady State and Transient Analysis Applications 2 Conservation of mass Conservation of mass is one of the most

More information

Section 906. STRUCTURAL STEEL

Section 906. STRUCTURAL STEEL 906.01 Section 906. STRUCTURAL STEEL 906.01. General Requirements. Finished rolled shapes must be free from imperfections that affect strength and durability in accordance with ASTM A 6. Rolled shapes

More information

Peerless Pump Company Handbook of Engineering Data

Peerless Pump Company Handbook of Engineering Data Peerless Pump Company Handbook of Engineering Data Brochure EM77 DEFINITION OF PUMP TERMS A.1 A line shaft vertical turbine pump is a vertical-shaft centrifugal or mixed-flow pump with rotating impeller

More information

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant International Journal of Engineering and Technology Volume 3 No. 1, January, 2013 Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant Wordu, A. A, Peterside, B Department

More information

Feedwater Heaters (FWH)

Feedwater Heaters (FWH) Feedwater Heaters (FWH) A practical Regeneration process in steam power plants is accomplished by extracting or bleeding, steam from the turbine at various points. This steam, which could have produced

More information

Storage Tank Piping (79720-PS-002) Stress Analysis

Storage Tank Piping (79720-PS-002) Stress Analysis Author(s): Scott Kaminski Page 1 of 25 Storage Tank Piping (79720-PS-002) Stress Analysis Revision History: Revision Date Released Description of Change - May 11, 2017 Original release, Issued for Project

More information

Grain Silo Strengthening South Dakota. Prepared for Vector Construction Group

Grain Silo Strengthening South Dakota. Prepared for Vector Construction Group Grain Silo Strengthening South Dakota Prepared for Vector Construction Group May 20, 2002 Table of Contents General...3 nalysis...4 Vertical...4 Horizontal...4 Crack Control...6 Strengthening...7 Vertical...8

More information

VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur

VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK VII SEMESTER ME 6008-WELDING TECHNOLOGY Regulation 2013 Academic Year 2017 18 Prepared

More information

HYSYS WORKBOOK By: Eng. Ahmed Deyab Fares.

HYSYS WORKBOOK By: Eng. Ahmed Deyab Fares. HYSYS WORKBOOK 2013 By: Eng. Ahmed Deyab Fares eng.a.deab@gmail.com adeyab@adeyab.com Mobile: 002-01227549943 - Email: adeyab@adeyab.com 1 Flash Separation We have a stream containing 15% ethane, 20% propane,

More information

[4163] T.E. (Mechanical) TURBO MACHINES (2008 Pattern) (Common to Mech. S/W) (Sem. - II)

[4163] T.E. (Mechanical) TURBO MACHINES (2008 Pattern) (Common to Mech. S/W) (Sem. - II) Total No. of Questions : 12] P1061 SEAT No. : [Total No. of Pages : 7 [4163] - 218 T.E. (Mechanical) TURBO MACHINES (2008 Pattern) (Common to Mech. S/W) (Sem. - II) Time : 3 Hours] [Max. Marks :100 Instructions

More information

AWS B1.10:1999 An American National Standard. Guide for the Nondestructive Examination of Welds

AWS B1.10:1999 An American National Standard. Guide for the Nondestructive Examination of Welds AWS B1.10:1999 An American National Standard Guide for the Nondestructive Examination of Welds Key Words Guide, eddy current examination, magnetic particle examination, nondestructive examination, penetrant

More information

YARWAY HANCOCK CONTINUOUS BLOWDOWN GLOBE VALVE SERIES 5505

YARWAY HANCOCK CONTINUOUS BLOWDOWN GLOBE VALVE SERIES 5505 Advanced construction features of this high pressure drop angle globe valve provide quality and long service life. FEATURES GENERAL APPLICATION In addition to continuous blowdown service, the Yarway high

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Stainless Steel Sluice Gates C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Stainless Steel Sluice Gates C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 11294 - Stainless Steel Sluice Gates C O N T E N T S PART 1 - GENERAL... 1 1.01 SUMMARY... 1 1.02 REFERENCES... 1 1.03 DEFINITIONS... 1 1.04 DESIGN REQUIREMENTS...

More information

Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland, WA, USA

Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland, WA, USA THROUGH WELD INSPECTION OF WROUGHT STAINLESS STEEL PIPING USING PHASED ARRAY ULTRASONIC PROBES Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland,

More information

COLUMNS 1- Definition: The Egyptian code defines columns as : 2- Types of concrete columns

COLUMNS 1- Definition: The Egyptian code defines columns as : 2- Types of concrete columns COLUMNS 1- Definition: Columns are vertical compression members which carry primarily axial compression load; the axial load may be associated with bending moments in one or two directions, as shown in

More information

1.2 ACTION AND INFORMATIONAL SUBMITTALS.1 Provide submittals in accordance with Section Submittal Procedures.

1.2 ACTION AND INFORMATIONAL SUBMITTALS.1 Provide submittals in accordance with Section Submittal Procedures. BID OPPORTUNITY NO. 253-2011 PAGE 1 OF 7 PART 1 GENERAL 1.1 REFERENCES.1 American Society of Mechanical Engineers (ASME).1 ASME B31.1, Power Piping, B31.3 Process Piping, B31.9 Building Services Piping..2

More information

STAINLESS STEEL SHEETS

STAINLESS STEEL SHEETS STAINLESS & NICKEL ALLOY CHATHAM STEEL CORPORATION 59 STAINLESS STEEL SHEETS TYPE 04, 04L, 6, 6L No. 2B Finish Cold Rolled, Annealed *No. 2D Finish No. Finish Polished One Side No. 4 Finish Polished One

More information

Design study of ship LNG storage and engine feeding system. Gerasimos Theotokatos NAOME, University of Strathclyde

Design study of ship LNG storage and engine feeding system. Gerasimos Theotokatos NAOME, University of Strathclyde Design study of ship LNG storage and engine feeding system Gerasimos Theotokatos NAOME, University of Strathclyde Introduction This study focuses on the design of the LNG storage and feeding system of

More information

Item 442 Metal for Structures

Item 442 Metal for Structures Item 442 Metal for Structures 1. DESCRIPTION 2. MATERIALS Provide structural steel, high-strength bolts, forgings, steel castings, iron castings, wrought iron, steel pipe and tubing, aluminum castings

More information

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights 1 Exam Prep Placing Reinforcing Bars Tabs and s These 1 Exam Prep Tabs are based on the CRSI Placing Reinforcing Bars Recommended Practices, 9 th Edition. Each 1 Exam Prep tabs sheet has five rows of tabs.

More information

ST7008 PRESTRESSED CONCRETE

ST7008 PRESTRESSED CONCRETE ST7008 PRESTRESSED CONCRETE QUESTION BANK UNIT-I PRINCIPLES OF PRESTRESSING PART-A 1. Define modular ratio. 2. What is meant by creep coefficient? 3. Is the deflection control essential? Discuss. 4. Give

More information

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors) 1.3.2016 Prof.Dr. Böck Technical University Vienna Atominstitut Stadionallee 2, 1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at

More information

Proceedings of the ASME nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013 June 9-14, 2013, Nantes, France

Proceedings of the ASME nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013 June 9-14, 2013, Nantes, France Proceedings of the ASME 2013 32nd International Conference on Ocean, Offshore and Arctic Engineering OMAE2013 June 9-14, 2013, Nantes, France OMAE2013-10684 A COMPARISON STUDY OF PRESSURE VESSEL DESIGN

More information

Cutting-Edge Pumping Solutions for the Concentrated Solar Power Generation

Cutting-Edge Pumping Solutions for the Concentrated Solar Power Generation Cutting-Edge Pumping Solutions for the Concentrated Solar Power Generation The Sulzer Advantage Taking on new challenges Around the world, the power industry is taking on the challenge to produce clean,

More information

INSPECTION ACCESSORIES

INSPECTION ACCESSORIES Date : 01-01- 2015 Page : 1 / 7 THE TWI WELD GAUGE An essential tool for rapidly checking the dimensions of weld preparations, butt welds and fillet welds: * angle of preparation * misalignment * fillet

More information

BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS

BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS Slide No. 1 Bending of In the previous discussion, we have considered only those beams that are fabricated from a single material such as steel. However, in

More information

Screening, Definition: The unit involved is called a screen.

Screening, Definition: The unit involved is called a screen. Screening, Definition: Screening is a unit operation that separates materials in and/or on water (found in different sizes) from water and from entering water treatment facilities and mains. The unit involved

More information

Fragility Curves for Seismically Retrofitted Concrete Bridges

Fragility Curves for Seismically Retrofitted Concrete Bridges Fragility Curves for Seismically Retrofitted Concrete Bridges S.-H. Kim Department of Civil and Environmental Engineering, University of California, Irvine, USA. ABSTRACT: This study presents the development

More information

Steel Pipe and Tube. Section 13

Steel Pipe and Tube. Section 13 Steel Pipe and Tube Section 13 13-1 INFORMATION - STEEL PIPE AND TUBE GENERAL INFORMATION Rigid hydraulic tubing offers intrinsic bene ts when installing uid transfer lines in both xed and mobile plant

More information

Bioreactor System ERT 314. Sidang /2012

Bioreactor System ERT 314. Sidang /2012 Bioreactor System ERT 314 Sidang 1 2011/2012 Chapter 3:Types of Bioreactors Week 4-5 Handouts : Chapter 13 in Doran, Bioprocess Engineering Principles Background to Bioreactors The bioreactor is the heart

More information

Overview. We will not study pipe systems in detail as these are always solved with software. Wednesday, September 01, :21 PM.

Overview. We will not study pipe systems in detail as these are always solved with software. Wednesday, September 01, :21 PM. Ch4 Page 1 Overview Wednesday, September 01, 2010 4:21 PM We will not study pipe systems in detail as these are always solved with software EGL, HGL Wednesday, September 01, 2010 3:51 PM Energy drives

More information

6. PUMPS AND PUMPING SYSTEM

6. PUMPS AND PUMPING SYSTEM 6. PUMPS AND PUMPING SYSTEM Syllabus Pumps and Pumping System: Types, Performance evaluation, Efficient system operation, Flow control strategies and energy conservation opportunities 6.1 Pump Types Pumps

More information

FUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie

FUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie FUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie The BWR reactor vessel spray(core spray) and feed water spray systems are designed to inject water into

More information