MISO-SPP Coordinated System Plan Study Report

Size: px
Start display at page:

Download "MISO-SPP Coordinated System Plan Study Report"

Transcription

1 MISO-SPP Coordinated System Plan Study Report June 30, 2015

2 Table of Contents 1 Executive Summary Introduction Stakeholder Involvement Third Party Coordination Scope Future Development Sensitivities Model Development Economic Model Reliability Models Dynamics Constraint Assessment Cost Estimates Economic Evaluation Issues Identification Historical Congestion Analysis Projected Congestion Analysis Economic Transmission Solution Development APC Methodology Screening Process Benefit-to-Cost Analysis Potential Interregional Projects for Recommendation Sensitivity Analysis Reliability Assessment Steady State Contingency Analysis Issues Assessment Reliability Assessment Solutions Development Solution Evaluation Dynamic Assessment Review of Regional Projects... 29

3 9.4 No-harm Test on Economic Projects Conclusions Economic Reliability Dynamics Interregional Cost Allocation IPSAC and Joint Planning Committee Recommendation IPSAC Recommendation Joint Planning Committee Recommendation Regional Review Process Southwest Power Pool Project Review Process SPP Regional Cost Allocation Midcontinent Independent System Operator Project Review Process MISO Regional Cost Allocation Appendix A Appendix B Table 1: MISO-SPP Coordinated System Plan Tasks... 4 Table 2: Regional Business as Usual Future Major Assumptions... 5 Table 3: MISO-SPP Coordinated System Plan Hurdle Rates... 8 Table 4: MISO-SPP Coordinated System Plan Economic Issues List Table 5: Results of Benefit-to-Cost Analysis Table 6: Sensitivity Analysis Results Table 7: Steady - State Thermal and Voltage Issues Table 8: Areas modeled in Dynamics Assessment Table 9: Results of Fast Fault Screen Table 10: Selected Disturbances Table 11: Combined Project Results Table 12: Interregional Cost Allocation for Potential MISO-SPP Interregional Projects Table 13: Congested Flowgate Analysis Table 14: MISO Congested Flowgate Analysis... 41

4 Figure 1: Elm Creek to Mark Moore 345 kv Project Figure 2: Elm Creek NSUB (Tap of Mark Moore - Pauline 345 kv) 345 kv Figure 3: New Series Reactor on Alto Swartz 115 kv Figure 4: S. Shreveport Wallace Lake 138 kv Rebuild Figure 5: Map of Steady - State Thermal and Voltage Issues Figure 6: Map of Fisher - Rodemacher 230 kv Project Figure 7: Map of Gobbler Knob - Datto 161 kv Project Figure 8: Rotor Angle Response Laramie River Figure 9: Voltage Response - Laramie River Figure 10: Rotor Angle Response Arkansas Nuclear One Figure 11: Voltage Response Arkansas Nuclear One Figure 12: Rotor Angle Response Turk Figure 13: Voltage Response Turk Figure 14: Rotor Angle Response Center Figure 15: Voltage Response Center... 40

5 1 Executive Summary The 2014 MISO-SPP Coordinated System Plan (CSP) was performed to evaluate the combined MISO & SPP transmission systems in an effort to identify mutually beneficial transmission improvements. The study was an 18-month effort that began in January MISO and SPP staff focused efforts on two primary sets of analyses - an economic evaluation and a reliability assessment. For the economic assessment, a 2024 joint model was built specifically for this study. SPP and MISO staff evaluated the congestion resulting from the 2024 model to identify a list of economic needs. Based on those needs, both staff and stakeholders collaborated to propose potential projects to solve the identified issues, which were then tested for Adjusted Production Cost (APC) and other benefits. Based on those results, SPP and MISO identified three projects for consideration as an Interregional Project: Elm Creek to NSUB 345 kv; Alto Series Reactor; and South Shreveport Wallace Lake 138 kv Rebuild. Each of these projects individually demonstrate benefit to both SPP and MISO as well as APC benefit that exceeds the cost of the project over the initial 20 years of the project life. These projects were then recommended by MISO and SPP to the Interregional Planning Stakeholder Advisory Committee (IPSAC) for endorsement to move from the interregional portion of the study onto the regional review process. Both the MISO and SPP portion of the IPSAC endorsed the projects with no opposition. Based on that recommendation the Joint Planning Committee (JPC) voted in favor for approving all three projects for review in both the MISO and SPP regional processes. To accomplish the reliability assessment, a 2024 joint power flow model reflecting generation dispatch utilized in MISO and SPP s respective regional planning processes was built specifically for the reliability assessment. MISO and SPP staff also performed an ACCC assessment on the joint power flow model to determine a list of reliability needs. Similar to the economic assessment, those needs were reviewed by staff and stakeholders to develop potential projects addressing the issues. The projects that were tested were compared to MISO and SPP regional projects that also fixed the corresponding needs to determine if the potential Interregional Projects were more cost effective than the regional solutions. Based on the results of the study, SPP and MISO did not identify any Interregional Projects for the sole purpose of resolving reliability issues more cost effectively than MISO and SPP regional solutions. 2 Introduction The FERC-filed MISO-SPP Joint Operating Agreement (JOA) establishes a JPC comprised of representatives of both MISO and SPP. The JPC is the decision-making body for coordinated interregional transmission planning and is responsible for all aspects of coordinated interregional transmission planning, including the development of a CSP. The JPC is charged with verifying that the

6 results of the study are accurate and meet the expectations of the JPC and IPSAC based on the study scope. The IPSAC was formed to provide an opportunity for stakeholders to review the development of the CSP study and to provide guidance and recommendations to the JPC. IPSAC participation is open to all stakeholders. On an annual basis, MISO and SPP have agreed to review potential transmission issues identified by each RTO or any stakeholder, in response to the RTO s request, at an IPSAC meeting as part of an Annual Issues Review process. The Annual Issues Review is administered by the JPC in coordination with the IPSAC to determine whether there is a need for MISO and SPP to perform a CSP study. When MISO and SPP determine a CSP study is warranted, the Order 1000 interregional coordination procedures outlined in the MISO-SPP JOA will be used to guide the CSP study process. The purpose of the MISO-SPP CSP study is to jointly evaluate seams transmission issues and identify transmission solutions that efficiently address the identified issues to the benefit of both MISO and SPP. This study incorporates an evaluation of economic seams transmission issues and an assessment of potential reliability violations. At the completion of the CSP study, the JPC shall produce a draft report documenting the study, including transmission issues evaluated, studies performed, solutions considered, and if applicable, the recommended Interregional Projects with the associated interregional cost allocation. The draft report will be made available for stakeholder review. Taking into consideration the recommendation of the IPSAC, the JPC shall meet and vote whether to recommend any Interregional Project(s) and the associated interregional cost allocation identified in the CSP study report to both MISO s and SPP s respective regional processes for review and approval by the respective Board of Directors. The Annual Issues Review IPSAC meeting was held on January 21, 2014, in Dallas, TX. Multiple stakeholders, along with MISO and SPP staff, presented proposed transmission issues that were considered for evaluation in the CSP. The issues ranged from reliability issues, economic issues, and issues identified due to the sub-regional power balance constraint between MISO North\Central and MISO South. The feedback from stakeholders at this meeting indicated that there was a strong consensus for moving forward with a CSP starting in Following the IPSAC, the JPC held a meeting where it was formally decided to perform a CSP starting in The schedule for the 2014 SPP-MISO CSP study would be no longer than 18 months and would be scheduled to conclude in June Stakeholder Involvement

7 The MISO-SPP IPSAC is the joint stakeholder group which is utilized to provide stakeholders an opportunity to comment on the CSP Study. The IPSAC s role is to provide input and review on the following items in the CSP Study: i. study scope and analysis approach; ii. joint planning models and input assumptions; iii. identified seams transmission issues or opportunities; iv. proposed transmission solutions and alternatives; v. recommendation on transmission solutions; and vi. CSP report. The IPSAC met on multiple occasions throughout the CSP Study both in person and via conference calls. The IPSAC met on the following dates: i. November 6, 2013; ii. January 21, 2014; iii. April 8, 2014; iv. May 12, 2014; v. October 7, 2014; vi. February 24, 2015; vii. May 6, 2015; and viii. June 18, The IPSAC meetings were facilitated jointly by MISO and SPP staff, and the meetings were hosted by one RTO or the other on an alternating basis. All meeting materials are maintained on each RTO s respective IPSAC webpage. 3.1 Third Party Coordination In addition to coordination between the RTOs and the stakeholders within each RTO, there were opportunities to work with third party stakeholders. As an example, there were some projects which could potentially provide value to Associated Electric Cooperatives, Inc. (AECI), which is a cooperative located in Missouri. Due to AECI s location it is possible that they would be interested in certain projects identified in the CSP. If it was determined that a project could provide value to a third party, that party was contacted to determine if there was any interest in that party participating in that project along with MISO and SPP. While there were a few projects where this took place, as you will see below, none of those projects were identified as being more cost effective or efficient than other Interregional Projects or regional solutions.

8 4 Scope At the first IPSAC meeting held in November 2013, stakeholders proposed 34 transmission issues in preparation for the start of the Annual Issues Review process. The submitted issues were reviewed by the JPC for consideration to be evaluated in the CSP. The selected issues to be evaluated in the CSP study were used to identify and evaluate potential Interregional Projects that may provide benefits to MISO and SPP. A broad range of issues were proposed, including the following: congestion; integration of the MISO South region; expanded market operation by SPP; real-time operational issues; reliability issues; and public policy requirements 1. During the development of the CSP study scope the JPC took into consideration those proposed issues. A high-level overview of the scope of the CSP study is shown in the table below: Table 1: MISO-SPP Coordinated System Plan Tasks MISO-SPP CSP Tasks Scope Development Develop and finalize scope document for CSP study Develop detailed schedule for CSP study Economic Evaluation and Reliability Assessment Economic Evaluation Reliability Assessment Future and Model Development Historical and Projected Congestion Analysis Perform steady-state reliability assessment using jointly developed power flow models Test system stability using scenario(s) appropriate for studying dynamics. Solution Development Determine if there are interregional alternatives to proposed regional solutions Solution Evaluation and Evaluate potential 1 It should be noted that while there was not a specific assessment focused on public policy issues, all approved public policy mandates and targets were included in the models used for the economic and reliability assessment.

9 Robustness Testing transmission solutions, as needed, based on identified issues. Reliability Analysis Determine interregional cost allocation Draft Coordinated System Plan study report Regional Evaluation and Cost Allocation (if needed) 5 Future Development The CSP study future was a Business as Usual (BAU) Future, developed from the 2015 MISO Transmission Expansion Plan (MTEP15) and the 2015 SPP Integrated Transmission Plan 10-Year Assessment (ITP10) BAU Futures. MISO s MTEP 15 BAU Future captures all current policies and trends in place at the time of futures development and assumes they continue, unchanged, throughout the duration of the study period. All applicable Environmental Protection Agency (EPA) regulations governing electric power generation, transmission and distribution are modeled. Demand and energy growth rates are modeled at a level equivalent to the 50/50 forecasts submitted into the Module E Capacity Tracking (MECT) tool. All current state-level Renewable Portfolio Standard (RPS) and Energy Efficiency Resource Standard (EERS) mandates are modeled. To capture the expected effects of environmental regulations on the coal fleet, 12.6 GW of coal unit retirements are modeled. SPP s 2015 ITP10 BAU Future-(F1) utilizes inputs provided by SPP stakeholders to develop the modeling inputs based on the assumption that policy requirements will remain constant. Stakeholders provide to SPP their anticipated level of renewable resources to meet all required mandates and targets. Renewable resources include 3.3 GW of new wind and 20.5 MW of new solar. Less than 1 GW of coal unit retirements are modeled in the 2015 ITP10. The load forecast used in the 2015 ITP10 BAU (F1) is a 50/50 load forecast. Table 2: Regional Business as Usual Future Major Assumptions Regional BAU Futures Demand and Energy Growth Retirements Natural Gas Price (2014$) RPS (10-year incremental GW) MISO 0.8% 12.6 GW Coal $ GW wind/ 1.1 GW Solar SPP 1.3% < 1 GW Coal $ GW Wind/ 20.5 MW Solar CO₂ Price DSM (annual demand reduction in year 10 for EE/DR) None 6,000 GWh/ 12 MW None Embedded in Load

10 5.1 Sensitivities In additional to the BAU future described above, MISO and SPP agreed, based on stakeholder feedback, to also perform three sensitivities. These sensitivities were used to evaluate the impacts of a carbon price, higher natural gas price forecast, and the Sub-Regional Power Balance Constraint (SRPBC) between MISO /Central and South impacts on congestion between the two planning regions. 2 For the carbon price sensitivity, a carbon price of $64 dollars was used. This was derived from the MISO MTEP 15 Public Policy Future. The carbon price is applied to the model year 2024 in an effort to capture changes in generation dispatch and market economics assuming a carbon tax. The natural gas price sensitivity is used to evaluate the impact of rising natural gas prices on the performance of the Interregional Projects. The natural gas prices used were derived from an SPP 2015 ITP10 sensitivity. The Sub-Regional Power Balance Constraint sensitivity is an attempt to replicate the power transfer limits and constraints between the two MISO sub-regions (North/Central and South) consistent with the operation of the current MISO Market. The effect of the SRPBC on MISO s market dispatch is currently the subject of a dispute and settlement discussions between MISO and SPP 3. Pending the outcome of those discussions, it is unknown how this constraint will be utilized in the future, and this sensitivity is only meant to reflect one possibility which is consistent with how the MISO Market is currently being operated. The SRPBC sensitivity models the difference between generation and load in the MISO South Region with an adjustment for interchange transactions with the balancing authority areas connected to the MISO South sub-region. Additionally, the SRPBC is modeled to reflect the following market criteria: hurdle rate of 9.57 $/MWh for transfers above 1000 MW; and maximum transfer limit of 2000 MW 4. Sensitivities were used to further evaluate the potential Interregional Projects. This evaluation utilizing the sensitivities provides additional information that the JPC can use in determining whether or not to propose an Interregional Project to the respective RTOs. 5 2 The Sub-Regional Power Balance Constraint as used in this report refers to the 1000 MW contract path between Ameren, AECI, and Entergy. 3 FERC dockets Docket Nos. EL14-21, EL14-31, ER , EL This sensitivity was designed prior to increasing the Operational Reliability Coordination Agreement (ORCA) transfer limit to 3,000 MW which is the current limit. 5 It is not a requirement that a project perform well in the sensitivities in order to be recommended to the RTOs.

11 6 Model Development 6.1 Economic Model Two economic models were built: a 2019 model and a 2024 model. As the CSP Study is focused on the 10 th year of the study horizon, the 2024 model was the primary model used for issues evaluation, screening, and project development. The 2019 model was utilized for the 20-year financial analysis to extrapolate data points beyond the 2024 model year. Both MISO and SPP utilize Ventyx s PROMOD model in their respective regional planning processes for their economic evaluations. In a similar manner, PROMOD was used in the CSP Study. The PROMOD model was built starting with the base data provided by Ventyx. Ventyx creates and compiles this data from publicly available information and their proprietary sources and processes. In each RTO s regional processes MISO and SPP then update the model with data specific to the MISO and SPP regions through their own respective stakeholder processes. As a starting point for the CSP Study the applicable respective regional PROMOD models were merged. Data for the SPP region and for the Associated Electric Cooperatives, Inc. (AECI) region was pulled from the SPP regional PROMOD model. Data for the MISO region and all regions east of MISO was pulled from the MISO regional PROMOD model. Modeling Footprint The joint CSP economic model footprint included: MISO, SPP, AECI, Manitoba Hydro, MRO, PJM, SERC, and TVA. The SPP footprint and balancing authority was modeled to include the Integrated System as a member of the SPP RTO 6. Transmission Topology The transmission topology used in the 2019 and 2024 models was created using the latest MISO MTEP 15 and SPP 2015 ITP10 power flow models. Note that PJM, SERC, TVA, and Manitoba Hydro areas were based on MISO s MTEP modeling of external areas that is largely based on the Eastern Reliability Assessment Group (ERAG) Multi-regional Modeling Working Group (MMWG) series models; unless specific regions have provided MISO updated information. The AECI region was enhanced from the ERAG model to include AECI s approved firm construction plan and any updates as included in the 2015 ITP10 model. Existing DC interconnections between the Eastern Interconnection and the Western Interconnection and ERCOT were modeled using profiles from SPP s 2015 ITP10 study. Load Forecasts The load forecasts for the MISO and SPP region were the forecasts used in the MISO MTEP 15 BAU Future and SPP 2015 ITP10 BAU Future. The load forecasts utilized reflect a 50/50 case. The load shape 6 The Integrated System (IS) was included as a part of the SPP System. The IS is comprised of Western Area Power Administration Upper Great Plains Region (WAPA), Basin Electric Cooperatives (Basin), and Heartland Consumer Power District (Heartland). The IS members are joining SPP as transmission owning members in October 2015.

12 profiles are from the same year as the wind profiles to ensure synchronization. Demand response and energy efficiency were modeled consistent with how each planning region models it in their respective regional BAU Futures. Generation The existing resource mix came from the SPP 2015 ITP10 and MISO MTEP 15 models for their respective regions. Retirements were modeled based on each RTO s BAU assumptions. New generation, including siting, came from each planning region s current BAU resource expansion plan. The resource expansion plan was incorporated into the model using the same process as the rest of the modeling data. Data from the SPP 2015 ITP10 F1 was utilized for the SPP and AECI regions. All other data was sourced from the 2015 MISO MTEP. The hourly profiles for renewables were developed using data from NREL and were time-synchronized with load shapes. The hourly profiles were based on data for 2005, except for the MISO South region and portions of SERC which used data from Fuel Prices Coal, oil, and uranium fuel prices were provided by Ventyx. After comparing the natural gas prices from the respective MISO and SPP BAU futures and noting that no significant difference exists between the two, the JPC agreed to use the natural gas prices from MISO s MTEP 15 BAU future. Hurdle Rates The CSP study used the hurdle rates from MISO s MTEP15 BAU future for the following areas: 1) where only MISO is interconnected (e.g., MISO-PJM, MISO-TVA, MISO-MHEB); and 2) AECI-TVA, TVA-PJM, PJM- SERC, SERC-TVA, SERC-AECI. MISO and SPP developed and agreed to the hurdle rates between MISO- SPP, MISO-AECI, and SPP-AECI. The specific values used for the hurdle rates in the study were provided to the IPSAC. Table 3: MISO-SPP Coordinated System Plan Hurdle Rates Hurdle Dispatch Commit MISO to SPP $7.55 $10.00 SPP to MISO $5.09 $10.00 MISO to AECI $7.55 $10.00 AECI to MISO $8.29 $10.00 SPP to AECI $1.50 $10.00 AECI to SPP $10.00 $10.00 Stakeholder Review After staff concluded the initial efforts on developing the model, the consolidated economic model was provided to stakeholders for their review and suggested edits. These suggested edits were reviewed by MISO and SPP staff and included in the final economic models as appropriate. Throughout the study the economic model was refined to address modeling errors as they were identified.

13 6.2 Reliability Models A 2024 summer peak power flow model was built for the CSP reliability assessment. The model utilizes generation dispatch consistent with both MISO and SPP regional study processes. As a starting point the 2014 MISO MTEP power flow model was merged with the 2015 SPP ITP10 power flow model. The MTEP model provided the most current MISO topology and dispatch and the ITP10 model provided the same for the SPP footprint. The MISO footprint used a Local Balancing Authority (LBA) dispatch and includes all approved MTEP14 Appendix A projects. The SPP footprint used a Consolidated Balancing Authority Security Constrained Economic Dispatch (CBA-SCED) and excluded all 2015 ITP10 projects approved in January 2015 by the SPP Board of Directors. The modeling footprint and transmission topology are consistent with what was described in Section 7.1 for the economic model. The following steps were taken to accomplish the merge of the MTEP and ITP power flow models: extracted SPP with ties from the MTEP model; pulled SPP from the 2015 ITP10 model and applied it to the MTEP model; applied SPP ties from the MTEP; and verified MISO and SPP Interchange was unchanged. Stakeholder Review After staff concluded the initial efforts on developing the model, the consolidated power flow model was provided to stakeholders for their review. Throughout the study the issues were refined to address modeling errors as they were identified Dynamics The dynamics assessment also included a jointly developed model consisting of the MISO MTEP14 model, the SPP 2015 MDWG model, and the 2013 MMWG series for the external footprint. The dynamics assessment was run using a 2019 light load case. As a starting point, the 2014 MISO MTEP model was merged with the 2015 ITP10 reliability model in order to utilize the generation dispatch that is consistent with both MISO and SPP regional models. The MTEP model provided the most current MISO topology and dispatch and the ITP10 model provided the same for SPP. 6.3 Constraint Assessment The NERC book of flowgates was used as the initial source in the selection of the flowgates for use in the event file. MISO and SPP evaluated the additional flowgates used in the current MTEP and ITP10 studies and identified a mutually agreed upon list of constraints to use for the MISO-SPP CSP study.

14 7 Cost Estimates Cost estimates were developed utilizing the assumptions MISO and SPP respectively use in their regional planning processes. If the project was geographically located within MISO s footprint, MISO s project cost estimates were utilized. If the project was geographically located within SPP s footprint, SPP s project cost estimates were utilized. SPP applied the SPP region-wide average of 17% for the Net Plant Carrying Charge Rate (NPCC) and approximately 8% for the Discount Rate. MISO applied the MISO region-wide average of 17.4% for the NPCC Rate and approximately 8% for the Discount Rate. Two separate cost estimate methodologies were utilized. The first was for project screening. In the CSP these estimates are called the conceptual cost estimates. These estimates are derived by using generic data which is used by each RTO in their respective region. That data is compiled based on historical data for projects previously constructed in each region and stakeholder feedback. While the actual values used in the cost estimates may vary between the RTOs, this is a reasonable assumption as costs associated with transmission development vary by region. MISO and SPP s cost estimation processes are consistent in the process that is used to develop a cost estimate at this stage of the study. The assumptions used by MISO and SPP for these cost estimates were reviewed with the IPSAC. The second cost estimate is called the study estimate in the CSP. The study estimate was developed for those projects which are being considered by the JPC for recommendation as an Interregional Project. This estimate is expected to be a +/- 30% level estimate. MISO utilizes their internal staff in the Transmission Developer Qualification Selection group to develop the study level estimate. SPP contracts with a consultant to develop the study level estimate. While MISO and SPP have their own processes for calculating this estimate, both RTOs target a cost estimate that is within +/-30%. 8 Economic Evaluation 8.1 Issues Identification As previously stated, the JPC reviewed 34 transmission issues submitted by stakeholders for consideration to be included in this study scope. In addition to the submitted transmission issues, the JPC included in the study scope an evaluation to review economic congestion utilizing historical top congested flowgates from market reports and projected congestion resulting from the joint economic model developed for this study effort Historical Congestion Analysis The purpose of the historical congestion analysis is to identify congested flowgates based on current and past market activity. The historically congested flowgates were evaluated to determine whether similar congestion is occurring in the 2024 CSP Study economic model. If there is congestion on that flowgate in the model to a sufficient degree, then it will be evaluated to determine if there is an efficient and cost effective interregional solution. If that historically congested flowgate does not show up in the 2024 CSP Study model, MISO and SPP staff reviewed to determine the reason.

15 MISO and SPP reviewed the MISO and SPP market reports and identified flowgates along the MISO SPP seam. After identifying the applicable flowgates, MISO and SPP staff reviewed the CSP model to determine if the model reflected similar congestion as to what is described in the respective market reports. If the flowgate is not congested in the CSP model, staff reviewed to confirm that the issue was resolved through a MISO or SPP previously approved regional project. The results are shown in Appendix B. These results demonstrate that the seams flowgates that are described in the respective market reports as being congested are either shown as being congested in the CSP model or they are not congested in the CSP model because the congestion is expected to be mitigated by a previously approved planned project Projected Congestion Analysis The projected congestion analysis involved identifying the top congested flowgates based on the 2024 CSP Study model. The flowgates were ranked using the following indicators: 1. Binding Hours number of hours in a year the flowgate is binding 2. Shadow Price reduced production cost for 1 MW increase of thermal rating on the flowgate 3. Congestion Costs flowgate shadow price times MW flow on the flowgate Table 4: MISO-SPP Coordinated System Plan Economic Issues List Issue Constraint Name Contingency Id M-1 Frederick Town AECI - Frederick Town AMMO 161 kv Lutesville - St Francois 345kV S-2 North East - Charlotte 161 kv Iatan Stranger 345 kv M-5 Blue Earth - Winnebago 161kV Lakefield Junction - Lakefield 345kV M-6 Wapello 161/69 kv Transformer T1 Wapello 161/69 kv Transformer T2 M-9 Prairie 345/230kV Transformer T2 Prairie 345/230kV Transformer T1 M-10 Swartz - Alto 115kV Baxter Wilson - Perryville 500 kv M-11 Reed - Dumas 115kV Sterlington - El Dorado 500kV S-12 Essex - Idalia 161 kv Essex - New Madrid 345 kv M-13 Grimes Mt Zion 138 kv Grimes Ponderosa 230 kv S-14 South Shreveport Wallace Lake 138 kv Dolet Hills 345/230 kv Transformer 8.2 Economic Transmission Solution Development The historical and projected congestion analysis, combined with the issues submitted by stakeholders, guided the development of transmission solution ideas that were evaluated as potential MISO-SPP Interregional Projects. The solution development and evaluation were focused on the set of identified congested flowgates that captured a majority of congestion costs (e.g., greater than 70%).

16 Each respective RTO staff and stakeholders were able to propose transmission solutions to address the identified transmission issues. Solutions were solicited through the MISO-SPP IPSAC meetings. MISO and SPP staff solicited a request for stakeholders to submit potential projects addressing congestion identified in the issues list presented at the October 7, 2014 IPSAC meeting. Stakeholders submitted a total of 39 projects addressing approximately 75% of the issues posted. In addition to stakeholder submissions, staff submitted 15 additional projects for consideration APC Methodology As stated in the MISO-SPP JOA, MISO and SPP agreed to jointly evaluate the benefits to the combined MISO-SPP region and to each region individually, using an agreed upon APC metric over a multi-year analysis. The APC is calculated for each simulated year and benefits for intermediate years between simulated years will be based on interpolation. Benefits for years beyond the last simulated year will be based on extrapolation. The total project benefit was determined by calculating the present value of annual benefits for the first 20 years of project life after the projected in-service date. The APC benefit metric is based upon the impact of the project on adjusted production cost, which is adjusted to account for purchases and sales. Both MISO and SPP s APC represents the summation of the APC for the defined areas in each region. Each area s production cost was adjusted for purchases and sales as follows: For each simulation hour in which an area is selling interchange, the APC was calculated by multiplying the interchange sales MW times the area s generation-weighted LMP and then subtracting this value from the area s production cost; and For each simulation hour in which an area is purchasing interchange, the APC was calculated by multiplying the interchange purchase MW times the area s load-weighted LMP and then adding this value to the area s production cost Screening Process A preliminary screening analysis was performed on all proposed transmission solution ideas to determine the solution ideas that have the most potential and warrant further evaluation. All consolidated transmission solution ideas and all transmission solution ideas which have potential value were evaluated for APC benefits to MISO and SPP. If there were projects which appeared to be duplicates, only one of the projects was evaluated. The screening index was calculated by using results of one model year 2024 of APC benefits compared to one model year 2024 costs. If the screening index was at least.5 and the project provided significant benefits to both MISO and SPP, the project was considered to have passed screening. Projects passing the screening process include: St Francois Fletcher 345 kv; St Francois Taum Sauk Fletcher 345 kv;

17 Walker Tap Rivtrin 138 kv; Series Reactor on Alto Swartz 115 kv; S Shreveport Wallace Lake 138 kv; Elm Creek Mark Moore 345 kv; and Elm Creek NSUB 345 kv Benefit-to-Cost Analysis To calculate an indicative benefit to cost ratio for proposed transmission solutions, a 20-year net present value calculation of benefits and costs was used 7. Benefits were calculated by the change in adjusted production cost with and without the proposed Interregional Project. The adjusted production cost was adjusted to account for purchases and sales. The APC benefit metric was calculated for the simulated years 2019 and Benefits for intermediary years were calculated using interpolation and years beyond 2024 using extrapolation. The period covered by the benefit and cost calculation was 20 years starting with the project s in-service year 8. The annual costs were calculated using an average carrying cost of existing Transmission Owners in MISO and SPP. The present value calculation assumed an 8% discount rate. Table 5: Results of Benefit-to-Cost Analysis Project Description NPV Project Cost (2015-M$) B/C Ratio Benefit: MISO% Benefit: SPP% Walker Tap - Rivtrin 138kV $ % -17% St Francois - Fletcher 345kV $ % 12% Elm Creek Mark Moore 345kV $156.3* % 93% Elm Creek NSUB 345kV $133.8* % 80% Series Reactor on Alto Swartz 115kV $5.4* % 14% S Shreveport - Wallace Lake 138kV $17.7* % 20% *Denotes study level cost estimates (+/- 30%) Potential Interregional Projects for Recommendation Elm Creek Mark Moore 345 kv The proposed Interregional Project Elm Creek Mark Moore 345 kv is a new transmission project heading north from an Elm Creek 345 kv substation in North Central Kansas (Cloud County) to the current Mark Moore 345 kv in Southeastern Nebraska (Lancaster County) with a length of approximately 100 miles. The Elm Creek 345 kv substation is being built as a part of the SPP Elm Creek Summit 345 kv project that was approved in the 2012 SPP ITP10. That project has an expected in-service date of There is not a B/C ratio requirement in the CSP study. 8 Initially MISO and SPP have made the assumption that the in-service date for all projects is 2024.

18 Figure 1: Elm Creek to Mark Moore 345 kv Project This project was proposed to relieve congestion on the Northeast to Charlotte 161 kv flowgate. MISO and SPP s analysis shows that relieving the congestion on this flowgate provides benefit to both Parties. This project relieves 23% 9 of the congestion on the Northeast to Charlotte 161 kv flowgate. The number of binding hours is reduced from 1,802 hours with the project to 1,307 with the project. However, in addition to the relief to the Northeast to Charlotte 161 kv flowgate, this project also addresses congestion on the Fairport Osborn 230 kv which is a north-south flowgate east of the Kansas City area. Congestion on this flowgate is reduced by 29%. While the Gentleman Red Willow 345 kv flowgate is a north-south flowgate geographically located in western Nebraska, it is a flowgate that can constrain both the MISO and SPP markets. This flowgate is relieved by 10%. Additional congestion was relieved or mitigated throughout the combined system, primarily along the north-south corridor. 9 This value is calculated by comparing the congestion scores with and without the project. The congestion score is calculated by multiplying the binding hours times the average shadow price.

19 SPP estimated an engineering and construction (E&C) study-level cost estimate of approximately $164.4 million 10 with an assumed in-service date of The $164.4 million E&C cost results in a 20-year present value of $156.3 million 11. MISO and SPP s 20-year benefit analysis shows that over the first 20 years of the project s life MISO and SPP are estimated to receive $161.8 million 12 in APC benefit resulting in a B/C ratio of Of the $161.8 million of APC benefit, SPP is estimated to receive $150.4 million with MISO receiving $11.3 million. Since the proportion of cost paid by MISO and SPP is based on the proportion of benefits, both MISO and SPP s B/C ratio is Elm Creek NSUB (Tap of Mark Moore - Pauline 345 kv) 345 kv The proposed Interregional Project Elm Creek NSUB 345 kv is a new transmission project heading north from an Elm Creek 345 kv substation in North Central Kansas (Cloud County) to a new 345 kv substation that taps the existing Mark Moore Pauline 345 kv line. This project has an estimated length of 78 miles. The Elm Creek 345 kv substation is being built as a part of the SPP Elm Creek Summit 345 kv project that was approved in the 2012 SPP ITP10. That project has an expected in-service date of dollars 11 The 20-year present value cost number is calculated using SPP s 17% NPCC, factoring in depreciation, and discounting at 8%. 12 The 20-year present value benefit number is calculate using a discount rate of 8%.

20 Figure 2: Elm Creek NSUB (Tap of Mark Moore - Pauline 345 kv) 345 kv This project was proposed to relieve congestion on the Northeast to Charlotte 161 kv flowgate and is mutually exclusive of the Elm Creek - Mark Moore 345 kv project discussed above. MISO and SPP s analysis shows that relieving the congestion on this flowgate provides benefit to both Parties. This project relieves 19% 13 of the congestion on the Northeast to Charlotte 161 kv flowgate. The number of binding hours is reduced from 1,802 hours with the project to 1,413 with the project. However, in addition to the congestion relief to the Northeast to Charlotte 161 kv flowgate, this project also addresses congestion on the Fairport Osborn 230 kv which is a north-south flowgate east of the Kansas City area. Congestion on this flowgate is reduced by 23%. While the Gentleman Red Willow 345 kv flowgate is a north-south flowgate geographically located in western Nebraska it is a flowgate that can constrain both the MISO and SPP markets. This flowgate is relieved by 13%. Additional congestion was relieved or mitigated throughout the combined system, primarily along the north-south corridor. 13 This value is calculated by comparing the congestion scores with and without the project. The congestion score is calculated by multiplying the binding hours times the average shadow price.

21 SPP estimated an engineering and construction (E&C) cost estimate of approximately $140.6 million 14 with an assumed in-service date of The $140.6 million E&C cost results in a 20-year present value of $133.8 million 15. MISO and SPP s 20-year benefit analysis shows that over the first 20 years of the project s life MISO and SPP are estimated to receive $165 million 16 in APC benefit resulting in a 20-year B/C ratio of Of the $165 million of APC benefit, SPP is estimated to receive $132 million with MISO receiving $33 million. Since the proportion of cost paid by MISO and SPP is based on the proportion of benefits both MISO and SPP s B/C ratio is New Series Reactor on Alto Swartz 115 kv The proposed Interregional Project New Series Reactor on Alto Swartz 115 kv proposes to add a 10% reactor on 100 MVA base in series with the Alto-Swartz 115 kv line. The reactor is to be normally bypassed, and un-bypassed post-contingency for critical contingencies such as a loss of Baxter Wilson Perryville 500 kv. The Alto-Swartz 115 kv line with which the reactor would be placed in series is located in North Central - Northwest Louisiana. Figure 3: New Series Reactor on Alto Swartz 115 kv dollars 15 The 20-year present value cost number is calculated using SPP s 17% NPCC, factoring in depreciation, and discounting at 8%. 16 The 20-year present value benefit number is calculated using a discount rate of 8%.

22 This project was proposed to relieve congestion on the Swartz Alto 115 kv flowgate. MISO and SPP s analysis shows that relieving the congestion on this flowgate provides benefit to both MISO and SPP. This project completely mitigates the congestion on the Swartz Alto 115 kv flowgate. Without the reactor this flowgate is projected to be binding 292 hours with an average shadow price of approximately $382. While the primary value from this project is addressing the congestion on Swartz Alto 115 kv, additional congestion is mitigated on other flowgates though in a smaller magnitude. MISO estimated an engineering and construction (E&C) cost estimate of approximately $5.3 million 17 with an assumed in-service date of The $5.3 million E&C cost results in a 20-year present value of $5.4 million 18. MISO and SPP s 20-year benefit analysis shows that over the first 20 years of the project life s MISO and SPP are estimated to receive $23.4 million 19 in APC benefit resulting in a 20-year B/C ratio of Of the $23.4 million of APC benefit MISO is estimated to receive $20.1 million with SPP receiving $3.3 million. Since the proportion of cost paid by MISO and SPP is based on the proportion of benefits both MISO and SPP s B/C ratio is S. Shreveport Wallace Lake 138 kv Rebuild The proposed Interregional Project South Shreveport Wallace Lake 138 kv rebuild proposes rebuilding the existing 11 mile South Shreveport to Wallace Lake 138 kv line with CSRT/TW conductor along with upgrades at the South Shreveport and Wallace Lake substations. The South Shreveport Wallace Lake 138 kv line is located in Northwestern Louisiana dollars 18 The 20-year present value cost number is calculated using MISO s 17.4% NPCC, factoring in depreciation, and discounting at 8%. 19 The 20-year present value benefit number is calculated using a discount rate of 8%.

23 Figure 4: S. Shreveport Wallace Lake 138 kv Rebuild This project was proposed to relieve congestion on the South Shreveport Wallace Lake 138 kv flowgate. MISO and SPP s analysis show that relieving the congestion on this flowgate provides benefit to both MISO and SPP. This project completely mitigates the congestion on the South Shreveport Wallace Lake 138 kv flowgate. Without the rebuild this flowgate is projected to be binding 941 hours with an average shadow price of approximately $120. While the primary value from this project is addressing the congestion on the South Shreveport Wallace Lake 138 kv, additional congestion is mitigated on other flowgates though in a smaller magnitude. SPP estimated an engineering and construction (E&C) cost estimate of approximately $18.5 million 20 with an assumed in-service date of The $18.5 million E&C cost results in a 20-year present value of $17.6 million 21. MISO and SPP s 20-year benefit analysis shows that over the first 20 years of the dollars 21 The 20-year present value cost number is calculated using MISO s 17.4% NPCC, factoring in depreciation, and discounting at 8%.

24 project s life MISO and SPP are estimated to receive $46.1 million 22 in APC benefit resulting in a 20-year B/C ratio of Of the $46.1 million of APC benefit MISO is estimated to receive $36.8 million with SPP receiving $9.2 million. Since the proportion of cost paid by MISO and SPP is based on the proportion of benefits both MISO and SPP s B/C ratio is Sensitivity Analysis As previously described in Section 6, additional analyses were performed on projects being considered for recommendation by the JPC using the three sensitivities. The proposed Interregional Projects that are identified in the assessment utilizing the BAU Future were evaluated using the three sensitivities to determine how the projects perform under these scenarios. After receiving input from stakeholders, the study scope included a high natural gas price, carbon price, and modeling of the Sub-Regional Power Balance Constraint as sensitivities. With input from the IPSAC, the JPC set the high natural gas price to $8.66/MMBtu for 2024 and the carbon price to $64/ton in The table below demonstrates the potential change in APC benefit for each project. These are the results of a one-year analysis utilizing the 2024 model. As an example, the High Natural Gas Price Sensitivity indicated that the benefits attributed to the project Series Reactor on Alto Swartz would increase by 43% if the gas price was set to $8.66/MMBtu. Table 6: Sensitivity Analysis Results % Change in APC Benefits (MISO and SPP combined) Project Description High Natural Gas Carbon Tax SRPBC Price Series Reactor on Alto Swartz 115kV +43% +37% +73% S Shreveport - Wallace Lake 138kV -79% -58% -39% New Elm Creek Mark Moore 345kV +52% -62% -7% New Elm Creek NSUB 345kV +54% -67% -7% 9 Reliability Assessment The reliability assessment in this scope included multiple studies. This multi-faceted approach has allowed MISO and SPP to evaluate various transmission issues near the MISO-SPP seam. The phases of the reliability assessment included in the CSP study are: 1. Review of reliability projects that were identified in the respective regional planning processes of MISO and SPP that are located near the seam to determine if there were 22 The 20-year present value benefit number is calculated using a discount rate of 8%.

25 interregional alternatives to the currently proposed transmission solutions that should be evaluated through the respective regional planning processes; 2. A steady state assessment was conducted using jointly developed power flow models consistent with reliability processes used by each region; and 3. A dynamics assessment to test system stability using a light load power flow case. Solutions to address the identified reliability issues were developed and reviewed in coordination with the respective regional planning processes. These solutions, which may include alternative projects that more effectively mitigate identified issues, were submitted by: respective RTO staff; stakeholders through regional planning processes; and stakeholders through MISO-SPP IPSAC meetings Transmission solutions to address identified reliability issues were evaluated to determine the most efficient and cost-effective method to address the identified constraints. Projects addressing reliability issues were also evaluated for potential economic benefits to MISO and SPP. The projects identified as addressing the identified reliability issues were not found to provide substantial economic benefit to MISO or SPP in the context of this study scope. 9.1 Steady State Contingency Analysis An N-1 contingency analysis was conducted using the Study models described in Section 6.2. Topology details can be found in Section Issues Assessment Criteria used to determine the potential violations were as follows: Monitored o Facilities 100kV and above in the MISO and SPP footprints o Thermal Overloads over 100% o Base Case Voltages below.95pu o Contingency Voltages below.90pu o Or more stringent local planning criteria Contingencies o Full N-1 o MISO and SPP Category B contingencies submitted by stakeholders The process that was followed to jointly develop the final issues list which was posted and made available for stakeholders was as follows: MISO and SPP performed separate contingency analyses and compared and verified that each other s results were consistent;

26 issues were reviewed on each respective transmission system; and MISO and SPP used engineering judgement to filter out issues not electrically close to the seam. MISO and SPP jointly performed separate base case (N-0) and contingency (N-1) analysis that provided a list of potential thermal and voltage violations. The results were compared and verified. Engineering judgment was used to filter out issues not electrically close to the seam. This initial issues list was provided to stakeholders along with a request for potential solutions to address the potential violations. After stakeholder feedback and additional validation was completed a final issues list was created. The table below summarizes the number of potential reliability issues. The map below is an overview of all the issues identified. Table 7: Steady - State Thermal and Voltage Issues Needs Overall Unique MISO System SPP System Overloads Low Voltages

27 Figure 5: Map of Steady - State Thermal and Voltage Issues Reliability Assessment Solutions Development The issues list and reliability power flow model were made available to stakeholders. MISO and SPP requested stakeholders submit any potential solutions that could address any of the listed issues. Staff received 12 project submissions from four different study participants. In addition to stakeholdersubmitted projects, MISO and SPP Staff leveraged previously identified regional projects from the MTEP and ITP processes, respectively. MISO and SPP analyzed these regional projects to determine if they addressed the issues identified in the CSP: SPP ITP Projects o Evaluated 1401 projects from 2015 ITP10 o Evaluated 531 projects from 2015 ITPNT MISO MTEP Projects o Reviewed 578 projects from Appendix B and Target Appendix A o Evaluated 8 projects from MTEP 15 In addition to all the projects listed above, staff also worked to create numerous potential solutions addressing the issues specific to this study. Additionally, staff evaluated all potential projects identified

28 in the economic portion of the CSP. The CSP economic projects were evaluated to see if they provided any reliability benefit in addition to the economic benefit Solution Evaluation MISO and SPP evaluated projects to determine: if benefit was provided to both MISO and SPP; if thermal overloads were solved to under 100%; if base case voltages were solved to within applicable planning criteria; if contingency voltages were solved to within applicable planning criteria; and if interregional solutions were more cost effective than MISO and SPP regional projects. Two projects were highlighted throughout the process as being mutually beneficial to both MISO and SPP Fisher to Rodemacher 230 kv Fisher to Rodemacher is a proposed new 50 mile 230 kv line addressing issues identified in the study located in west Louisiana. The project addresses thermal overloads in both MISO and SPP. The conceptual cost of the project was estimated to be approximately $46M.

29 Figure 6: Map of Fisher - Rodemacher 230 kv Project MISO and SPP determined this project was not cost effective as both RTO s could address the overloads with regional projects for approximately $10M each Gobbler Knob Datto 161 kv Gobbler Knob to Datto is a proposed new 20 mile 161 kv line addressing issues identified in the study located in northeast Arkansas. The project addresses both thermal overloads and low voltages on the MISO system. The project also addresses low voltages on the SPP transmission system, specifically on portions of Southwestern Power Administration (SPA). The conceptual cost of the project was estimated to be approximately $25M 23. The project potentially replaces $44M of regional upgrades on the MISO system and $3M of upgrades on the SPA system. 23 This estimate is a conceptual level cost estimate which was proposed by a stakeholder. If this project was deemed to be a viable Interregional Project MISO and SPP would have developed a study level cost estimate which could change the cost estimate.

30 Figure 7: Map of Gobbler Knob - Datto 161 kv Project MISO and SPP determined the project will not be recommended as a part of the MISO-SPP CSP due to the limited participation of SPA in SPP s planning region. However the project will continue to be evaluated in the MISO regional process as an alternative to the MISO Targeted Appendix A project Jim Hill to Datto rebuild. SPP will continue to work with SPA and will be available to provide any coordination needed between SPP and others regarding SPA s interest in this project. 9.2 Dynamic Assessment The dynamics assessment utilized a joint model developed from MISO and SPP s regional models as described in section of this report. A 2019 light load case was developed in an effort to highlight seasonal transient instability issues most likely to occur. MISO and SPP selected areas to be monitored that were adjacent to the MISO-SPP seam shown in Table 8: Areas modeled in Dynamics Assessment below.

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN MISO SPP Interregional Stakeholder Advisory Committee April 8 th, 2014 Carmel, IN 1 Agenda Introductions Discussion on Draft Coordinated System Plan (CSP) Study Scope Lunch Continue Discussion on Draft

More information

SPP at a Glance. Located in Little Rock. Approximately 600 employees

SPP at a Glance. Located in Little Rock. Approximately 600 employees SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment

More information

INTEGRATED TRANSMISSION PLANNING MANUAL

INTEGRATED TRANSMISSION PLANNING MANUAL INTEGRATED TRANSMISSION PLANNING MANUAL Published on July 20, 2017 Pending FERC approval of Tariff language By SPP staff REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 10/13/2010

More information

2750 Monroe Blvd Audubon, PA

2750 Monroe Blvd Audubon, PA 2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

Methodology PLG-METH-0002-V1

Methodology PLG-METH-0002-V1 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V1 Title: Transmission Planning Assessment Practices Issue Date: September 27, 2012 Previous Date: Nov. 18, 2011

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008)

Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008) Interregional Agreements --> MISO-JOA Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008) Effective Date: 5/30/2016

More information

Draft Whitepaper to Platte River Board of Directors

Draft Whitepaper to Platte River Board of Directors Draft Whitepaper to Platte River Board of Directors Report on Organized Power Markets RTOs and ISOs Presented for the October 2016 Board Meeting Overview This report on the potential formation of a regional

More information

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans ENTERGY GULF STATES LOUISIANA, L.L.C. & ENTERGY LOUISIANA, LLC LPSC DOCKET NO. I-33014 DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans This version

More information

Power Sector Transition: GHG Policy and Other Key Drivers

Power Sector Transition: GHG Policy and Other Key Drivers Power Sector Transition: GHG Policy and Other Key Drivers JENNIFER MACEDONIA ARKANSAS 111(D) STAKEHOLDER MEETING MAY 28, 214 5/23/14 POWER SECTOR TRANSITION: GHG POLICY AND OTHER KEY DRIVERS 2 Purpose

More information

MTEP18 Futures. Planning Advisory Committee June 14, 2017

MTEP18 Futures. Planning Advisory Committee June 14, 2017 MTEP18 Futures Planning Advisory Committee June 14, 2017 Overview Objective: Present final MTEP18 Futures and an overview of stakeholder feedback Key Takeaways: Four Futures to be used in MTEP18 to consider

More information

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria MISO-PJM Interface Pricing Post Implementation Metrics and Criteria Contents 1 Introduction... 2 2 Real-Time Market Interchange Price Signal Effectiveness Metrics... 2 2.1 Post Implementation Pricing Monitoring

More information

ATTACHMENT K TRANSMISSION PLANNING PROCESS

ATTACHMENT K TRANSMISSION PLANNING PROCESS ATTACHMENT K TRANSMISSION PLANNING PROCESS 1.0 Introduction This Attachment K addresses the rights and obligations of Transmission Customers, relevant stakeholders and the Transmission Provider related

More information

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN Prepared by Scott Harvey and Susan Pope March 5, 2010 (Updated April 15, 2010) 1 TABLE OF CONTENTS I. Introduction...

More information

ATTACHMENT P. Transmission Planning Process

ATTACHMENT P. Transmission Planning Process ATTACHMENT P Transmission Planning Process Overview of Western s Transmission Planning Processes The Western Area Power Administration (Western) is a Federal agency under the Department of Energy that

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

2016 ANNUAL VRL ANALYSIS

2016 ANNUAL VRL ANALYSIS 2016 ANNUAL VRL ANALYSIS Published on 08/01/2016 By Ops Market Support/Forensics Chris Davis Ricky Finkbeiner REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 7/11/2016 Ricky

More information

Entergy Gulf States Louisiana, L.L.C. and Entergy Louisiana, LLC

Entergy Gulf States Louisiana, L.L.C. and Entergy Louisiana, LLC 2015 Integrated Resource Plan Entergy Gulf States Louisiana, L.L.C. and Entergy Louisian na, LLC LPSC Docket No. I 33014 Draft Report: Filed January 30, 2015 Draft Report Revision 1: Filed Aprill 15, 2015

More information

ORLANDO UTILITIES COMMISSION Open Access Transmission Tariff Original Sheet 91 SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service The Transmission Customer shall compensate

More information

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th 2016 DRAFT Proposal only Formal stakeholder review will begin August 24 th and remain open through September 12

More information

Generation Technology Assessment & Production Cost Analysis

Generation Technology Assessment & Production Cost Analysis SPO Planning Analysis Generation Technology Assessment & Production Cost Analysis EAI Stakeholder Meeting July 31, 212 Technology Life Cycle Technology Deployment Over Time Conceptual Research & Development

More information

Eastern Wind Integration and

Eastern Wind Integration and Eastern Wind Integration and Transmission Study Overview NCSL Transmission Policy Institute Denver, CO June 17-18, 2010 Dave Corbus National Renewable Energy Laboratory NREL is a national laboratory of

More information

Fred Stoffel. Tri-State Generation and Transmission Association, Inc. May 19, Utility Resource Planning Fundamentals

Fred Stoffel. Tri-State Generation and Transmission Association, Inc. May 19, Utility Resource Planning Fundamentals Fred Stoffel Tri-State Generation and Transmission Association, Inc. May 9, 202 Tri-State Overview Tri-State is a not-for-profit, wholesale power supplier owned by 44 electric cooperatives and public power

More information

Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration

Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration Technical Appendix October 2015 Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration

More information

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection DRAFT For Discussion Purposes Only V 4.0 December 19, 2016 Table of Contents

More information

System Impact Study E001 Moon Lake 230 kv 200 MW Plant

System Impact Study E001 Moon Lake 230 kv 200 MW Plant System Impact Study E001 Moon Lake 230 kv 200 MW Plant Prepared by: Midcontinent Independent System Operator Independent Coordinator of Transmission 720 City Center Drive Carmel, IN 46032 Rev Issue Date

More information

MISO s Analysis of EPA s Final Clean Power Plan Study Report

MISO s Analysis of EPA s Final Clean Power Plan Study Report MISO s Analysis of EPA s Final Clean Power Plan Study Report July 2016 MISO Policy & Economic Studies Department i Contents Executive Summary... 4 1 Introduction... 8 2 Near-Term Analysis... 9 2.1 Sensitivity

More information

S P P 2016 TPL a n d FA C

S P P 2016 TPL a n d FA C S P P 2016 TPL-001-4 a n d FA C - 014-2 C o m p l i a n c e A s s e s s m e n t C o m p r e h e n s i v e R e p o r t 12/15/2016 Compliance and Advanced Studies Southwest Power Pool, Inc. Revision History

More information

Methodology PLG-METH-0002-V4

Methodology PLG-METH-0002-V4 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V4 Title: Transmission Planning Assessment Practices Issue Date: August 3, 2015 Previous Date: December 10, 2014

More information

The Virtues of A Virtual RTO

The Virtues of A Virtual RTO The Virtues of A Virtual RTO Jim Mayhew Mirant September 26, 2003 Harvard Electricity Policy Group 1 A Virtual RTO? An Organization That is a RTO in All but Name? Minimum Attributes? Regional Security

More information

PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal

PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal March 2, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com 2 P age Contents Executive Summary 6 Introduction and

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017 MISO 2018 Series Dispatch Update MOD-032 Users Group October 3, 2017 1 Objective MTEP17 Dispatch Process MTEP18 Dispatch Updates Reminder Station Service Load Modeling Enhancements Wind Capacity Credit

More information

Best Practices in Conducting Grid Integration Studies

Best Practices in Conducting Grid Integration Studies GREENING THE GRID Best Practices in Conducting Grid Integration Studies ENHANCING CAPACITY FOR LOW EMISSION DEVELOPMENT STRATEGIES (EC-LEDS) Agenda and Learning Objectives Part 1: Why conduct a grid integration

More information

Mid-C Seminar July 16 th, 2014

Mid-C Seminar July 16 th, 2014 NWPP Members Market Assessment and Coordination Initiative Mid-C Seminar July 16 th, 2014 Dan Williams, LC Chair, Portland General Electric Slides not reviewed or approved by MC Members 1 Agenda History

More information

the most promising locations for new renewables in the Imperial CREZ.

the most promising locations for new renewables in the Imperial CREZ. March 3, 2016 Imperial Irrigation District (IID) appreciates the opportunity to comment on the California Independent System Operator (CAISO) presentation during its 2/18/16 Stakeholder meeting discussing

More information

BEFORE THE PUBLIC SERVICE COMMISSION STATE OF MISSOURI

BEFORE THE PUBLIC SERVICE COMMISSION STATE OF MISSOURI BEFORE THE PUBLIC SERVICE COMMISSION STATE OF MISSOURI In the Matter of the Application of Ameren ) Transmission Company of Illinois for Other Relief, ) or, in the Alternative, a Certificate of Public

More information

Business Practice Manual for the Transmission Planning Process

Business Practice Manual for the Transmission Planning Process Business Practice Manual for the Transmission Planning Process Order 890 Compliance Version 76.0 September 15,February 11, 2010 TABLE OF CONTENTS Order 890 Compliance... i 1. Introduction... 6 1.1 Purpose

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

MOD Data for Power System Modeling and Analysis

MOD Data for Power System Modeling and Analysis MOD-032-1 Data for Power System Modeling and Analysis A. Introduction 1. Title: Data for Power System Modeling and Analysis 2. Number: MOD-032-1 3. Purpose: To establish consistent modeling data requirements

More information

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO This Proposal outlines the terms and conditions in a proposed Appendix to the Southwest Power Pool's ("SPP's") Membership Agreement

More information

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3

More information

2016 Long-Term Reliability Assessment

2016 Long-Term Reliability Assessment 2016 Long-Term Reliability Assessment December 2016 NERC Report Title Report Date I Table of Contents Preface... v Introduction... vi Executive Summary... vii Chapter 1: Reliability Issues... 1 Resource

More information

2011 Congestion Assessment and Resource Integration Study

2011 Congestion Assessment and Resource Integration Study 2011 Congestion Assessment and Resource Integration Study Comprehensive System Planning Process CARIS Phase 1 Final Report March 20, 2012 NYISO System Resources and Planning staff can be reached at 518-356-6000

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

2014 Summer Reliability Assessment

2014 Summer Reliability Assessment 2014 Summer Reliability Assessment May 2014 NERC Summer Reliability Assessment 2013 i of 45 Preface NERC is an international regulatory authority established to evaluate and improve the reliability of

More information

Wes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED

Wes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED Ramapo Phase Angle Regulator Cost Recovery Wes Yeomans Vice President Operations Management Committee May 31, 2017 Agenda Background Benefits of Two Ramapo Phase Angle Regulators Annual Cost Projections

More information

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

More information

EIPC Roll-Up Powerflow Model

EIPC Roll-Up Powerflow Model EIPC Roll-Up Powerflow Model Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG Meeting November 25, 2013 2013 New York Independent System Operator, Inc. All Rights

More information

DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890

DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890 DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890 OVERVIEW AND PURPOSE This strawman proposes enhancements to NYISO s existing reliability and economic planning processes

More information

Energy Markets - The Basics

Energy Markets - The Basics Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

The Husker Power Plan: A New Energy Plan for Nebraska

The Husker Power Plan: A New Energy Plan for Nebraska The Husker Power Plan: A New Energy Plan for Nebraska By Sommer Energy, LLC Anna Sommer President Tel. 315-386-3834 anna@sommerenergy.com Applied Economics Clinic Elizabeth A. Stanton, PhD Director and

More information

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges. SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become

More information

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to

More information

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents

More information

June 28, Sw. Power Pool, Inc., 141 FERC 61,048 (2012) ( October 18 Order ), order on reh g, 142 FERC 61,205 (2013) ( March 21 Order ).

June 28, Sw. Power Pool, Inc., 141 FERC 61,048 (2012) ( October 18 Order ), order on reh g, 142 FERC 61,205 (2013) ( March 21 Order ). June 28, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No. ER13- -000 Compliance

More information

2014 State of the Market

2014 State of the Market 2014 State of the Market 24 August 2015 SPP Market Monitoring Unit Disclaimer The data and analysis in this report are provided for informational purposes only and shall not be considered or relied upon

More information

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE

Tucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE Tucson Electric Power 2017 Integrated Resource Plan Southern Arizona Regional Solar Partnership Jeff Yockey, PE May 2017 Integrated Resource Plan (IRP) Overview Just a Plan Additional steps for specific

More information

ISO New England Available Transfer Capability. Implementation Document. Version 1.0

ISO New England Available Transfer Capability. Implementation Document. Version 1.0 ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6

More information

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017 TSR Modeling in Reliability Planning Planning Subcommittee October 17, 2017 1 Objective TSR Modeling in MISO Series Base Models TSR Modeling in Reliability Planning Studies 2 TSR Modeling in MISO Series

More information

Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project

Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project A Proposal To: PJM June 28, 2013 Page 1 of 69 Table of Contents 1. Table of Contents 1. Table of Contents... 2 2. Introduction

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

High Voltage Direct Current

High Voltage Direct Current High Voltage Direct Current And Large Scale Wind Integration Iowa State University April 2014 Wayne Galli, Ph.D., P.E. Executive Vice President Transmission and Technical Services Clean Line Energy Partners

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Market Monitoring Unit. State of the Market Summer 2017

Market Monitoring Unit. State of the Market Summer 2017 State of the ket 20 published ober 20, 20 TABLE OF CONTENTS List of figures... i 1. ket performance highlights... 1 2. Prices, mitigation, and market costs... 4 3. Demand, generation and unit commitment...

More information

05/23/14. Power Sector Transition: GHG Policy and Other Key Drivers

05/23/14. Power Sector Transition: GHG Policy and Other Key Drivers 5/23/14 Power Sector Transition: GHG Policy and Other Key Drivers JENNIFER MACEDONIA, BLAIR BEASLEY, MEGHAN MCGUINNESS, STUART ILER MAY 214 5/23/14 POWER SECTOR TRANSITION: GHG POLICY AND OTHER KEY DRIVERS

More information

Southwest Power Pool CRITERIA

Southwest Power Pool CRITERIA Southwest Power Pool CRITERIA LATEST REVISION: April 28, 2015 FOREWORD... i INTRODUCTION... ii 1.0 LOAD AND ENERGY FORECASTS...1-1 2.0 CAPACITY MARGIN...2-1 2.1 Definitions...2-1 2.1.1 Load Serving Member...2-1

More information

Two Settlement PJM /06/2016

Two Settlement PJM /06/2016 Two Settlement PJM 2016 Objectives Describe Two-Settlement process Day-Ahead Market Balancing Market Explain Virtual Transactions and their settlement Inc Offers Dec Bids Up-to Congestion Transactions

More information

VALUE OF YOUR WIND PPA

VALUE OF YOUR WIND PPA ROCKY MOUNTAIN IN STIT U TE TRANSMISSION INVESTMENTS AFFECT THE VALUE OF YOUR WIND PPA INSIGHT BRIEF March 2017 IIIII Anthony D. Teixeira ateixeira@rmi.org HIGHLIGHTS The Trend: Two-thirds of corporate

More information

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016 Portland General Electric 2016 Integrated Resource Plan OPUC Public Meeting December 20, 2016 Agenda Process and Compliance Approach and Summary Analysis Action Plan Next steps 2 2013 IRP Order Resource

More information

Dynamic Transfers Revised Draft Final Proposal

Dynamic Transfers Revised Draft Final Proposal Dynamic Transfers Revised Draft Final Proposal Provided in Support of 2009-2011 Stakeholder Process to Consider Expansion of Dynamic Transfer Services in ISO Tariff Revised February 18, 2011 CAISO/M&ID/Dynamic

More information

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh) For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY The 2016 SD Electricity Supply Resource Procurement Plan The 2016 South Dakota Electricity Supply Resource Procurement Plan ( Plan ) evaluates NorthWestern Energy s ( NorthWestern

More information

PJM Manual 37: Reliability Coordination Revision: 14 Effective Date: April 1, Prepared by Systems Operation Division

PJM Manual 37: Reliability Coordination Revision: 14 Effective Date: April 1, Prepared by Systems Operation Division PJM Manual 37: Reliability Coordination Revision: 14 Effective Date: April 1, 2017 Prepared by Systems Operation Division PJM 2017 Table of Contents Table of Contents Approval...4 Current Revision...5

More information

Risk-Based Registration Technical Justification. August 26, 2014

Risk-Based Registration Technical Justification. August 26, 2014 Risk-Based Registration Technical Justification August 26, 2014 Table of Contents Preface and NERC Mission... iv Executive Summary... v Introduction...1 Background...1 Functional Entities Considered...1

More information

Functional Entity Roles and Responsibilities

Functional Entity Roles and Responsibilities Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...

More information

2012 Integrated Resource Plan

2012 Integrated Resource Plan 2012 Integrated Resource Plan Entergy System This document describes the Entergy System s Integrated Resource Plan for the period 2012 2031. The Integrated Resource Planning Process results in a Preferred

More information

PJM Regional Transmission Expansion Plan BOOK 1. RTEP in Review February 28, Book 2 Input Data and Process Scope

PJM Regional Transmission Expansion Plan BOOK 1. RTEP in Review February 28, Book 2 Input Data and Process Scope BOOK 1 PJM 2014 RTEP in Review February 28, 2015 Book 2 Book Book Input Data and Process Scope 3 Baseline and Market Efficiency Results 4 Scenario and Interregional Results Book 5 State RTEP Summaries

More information

PJM M2M Market Flow Proposal. October 2014

PJM M2M Market Flow Proposal. October 2014 PJM M2M Market Flow Proposal October 2014 Table of Contents 1. Introduction... 1 2. M2M Market Flow... 1 3. Real-Time Balancing Congestion and M2M payments... 3 4. Firm Flow Entitlement Impact of Market

More information

Job Descriptions. Title & Job Functions: Transmission Function Employees

Job Descriptions. Title & Job Functions: Transmission Function Employees Job Descriptions In accordance with its Standards of Conduct Implementation and Compliance Procedures, City Utilities of Springfield, Missouri will post on these pages the job titles and job descriptions

More information

Generation Contingency Analysis

Generation Contingency Analysis Generation Contingency Analysis PJM 2016 Objectives Identify the procedure for redispatching generation to alleviate an overloaded monitored transmission line caused by a contingency PJM 2016 2 Agenda

More information

Utility Scale Integration of Wind and Solar Power

Utility Scale Integration of Wind and Solar Power Utility Scale Integration of Wind and Solar Power Charles Reinhold WestConnect Project Manager Southwest Renewable Energy Conference Flagstaff, AZ Presentation Overview WestConnect Background Area Control

More information

December 11, 2013 VIA ELECTRONIC FILING

December 11, 2013 VIA ELECTRONIC FILING VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No. ER14- -000 Compliance

More information

Coordinated Procurement Transmission in the Northeast

Coordinated Procurement Transmission in the Northeast Coordinated Procurement Transmission in the Northeast February 26, 2016 New England States Committee on Electricity NESCOE is New England s Regional State Committee, governed by a Board of Managers appointed

More information

Zero Net Carbon Portfolio Analysis

Zero Net Carbon Portfolio Analysis Zero Net Carbon Portfolio Analysis Prepared for: Platte River Power Authority December 5, 2017 This Report was produced by Pace Global, a Siemens business ( Pace Global ) and is meant to be read as a whole

More information

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008 Transmission Planning at the Midwest ISO Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008 Midwest ISO: What We Do Monitor flow of power over the high voltage

More information

Transmission Planning Strategies to Accommodate Renewables

Transmission Planning Strategies to Accommodate Renewables Transmission Planning Strategies to Accommodate Renewables P R E S E N T E D A T : EUCI Austin Renewable Energy Grid Operations P R E P A R E D B Y : J. Michael Hagerty Johannes Pfeifenberger Judy Chang

More information

Standard EOP System Restoration from Blackstart Resources

Standard EOP System Restoration from Blackstart Resources A. Introduction 1. Title: System Restoration from Blackstart Resources 2. Number: EOP-005-2 3. Purpose: Ensure plans, Facilities, and personnel are prepared to enable System restoration from Blackstart

More information

Integrated Resource Plan

Integrated Resource Plan 2011 Integrated Resource Plan Addendum Let s turn the answers on. June 27, 2011 For more information, contact: PacifiCorp IRP Resource Planning 825 N.E. Multnomah, Suite 600 Portland, Oregon 97232 (503)

More information

Sustaining & Enhancing Reliability in NY

Sustaining & Enhancing Reliability in NY Sustaining & Enhancing Reliability in NY Stephen G. Whitley President & CEO New York Independent System Operator Northeast Power Coordinating Council General Meeting December 1, 2010 Albany, NY Topics

More information

Regulatory Issues and Smart Grid Transmission Solutions

Regulatory Issues and Smart Grid Transmission Solutions O C T O B E R 2 2, 2 0 1 3 B O S T O N, M A S S A C H U S E T T S Regulatory Issues and Smart Grid Transmission Solutions CIGRE Grid of The Future Symposium Michael I. Henderson D I R E C T O R, R E G

More information

Cost Development Guidelines

Cost Development Guidelines DRAFT Manual 15 Language Clean Version Approved by CDS on October 25, 2012 PJM Manual 15: Cost Development Guidelines Revision: 20 Effective Date: November 1, 2012 Prepared by Cost Development Subcommittee

More information

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional

More information

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE Q U É B E C S H Y D R O P O W E R R E S O U R C E S P O W E R I N G T H E E M P I R E S TAT E LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE Hydro-Québec, New York s energy partner for decades,

More information

Local Market Power Mitigation Enhancements

Local Market Power Mitigation Enhancements Local Market Power Mitigation Enhancements Draft Final Proposal May 6, 2011 CAISO/M&ID/CRH May 6, 2011 page 1 Draft Final Proposal Local Market Power Mitigation Enhancements Table of Contents 1. Introduction...

More information

Potential Impacts of a Renewable and Energy Efficiency Portfolio Standard in Kentucky

Potential Impacts of a Renewable and Energy Efficiency Portfolio Standard in Kentucky Potential Impacts of a Renewable and Energy Efficiency Portfolio Standard in Kentucky Prepared for the Mountain Association for Community Economic Development & the Kentucky Sustainable Energy Alliance

More information

INTEGRATED RESOURCE PLAN

INTEGRATED RESOURCE PLAN HOOSIER ENERGY INTEGRATED RESOURCE PLAN 2016 UPDATE WHAT IS RESOURCE PLANNING? Key features Inputs Resource mix n Member input n Board policies n Regulatory requirements n Risk adjusted least cost Energy

More information