Supply chain risks and their threat to capital expenditure

Size: px
Start display at page:

Download "Supply chain risks and their threat to capital expenditure"

Transcription

1 Supply chain risks and their threat to capital expenditure David Robertson and Mark Cowling Technical by nature

2 Project CAPEX (GBP M / MW) [inflation adjusted] Offshore Wind Projects CAPEX Trends 4.0 Setana Beatrice Alpha Ventus Thornton Bank II Belwind Phase 1 Greater Gabbard Lincs Ormonde Borkum West II Rudong Sheringham Demonstrator Shoal Borkum Riffgrund Walney Phase I 3.0 Tuno Knob Thanet Rhyl Flats Rodsand II Teeside London Array Anholt Gwynt y Mor Gunfleet Phase I & II Dong Hai 2.0 Irene Vorrink Bockstigen Horns Rev North Hoyle Princess Amalia (Q7) Kentish Flats Robin Rigg Barrow Burbo Horns Rev II Egmond LID Baltic I 1.0 Scroby Sands Blyth Samsø Nysted Utgrunden Yttre Stengrund Middelgrunden Lillgrund Operational Under Construction Contracted Bubble Area represents capacity of wind farm Year of Commissioning

3 Case Study 1: 400MW Offshore Wind 30m LAT CAPEX Financial Close: CAPEX Outturn Cost: 1.4bn CAPEX Overspend 2.5bn

4 Case Study 2: 500MW Offshore Wind 30m LAT CAPEX Financial Close: CAPEX Outturn Cost: 1.75bn One single incident 2.05bn

5 CAPEX Trend and Case Studies CAPEX trends and case studies demonstrate: CAPEX has been consistently increasing over the past 10 years Outturn costs are significantly higher than CAPEX agreed at Financial Close Individual issues and resulting claims can increase CAPEX by 300m Opportunity to reduce CAPEX overspend through improving management of the supply chain

6 Problems within the Supply Chain Lack of understanding of the project supply chain components

7 Problems within the Supply Chain Manufacture: Single Contract Nacelle Main Bearing Main Shaft Gearbox Generator Power take-off Control system Yaw & Pitch system Rotor Blades Tower Steel Export Cable Array Cable Cable protection WTG Foundation Transition Piece Access System J Tube Substation Installation: Export Cable Laying Foundation Installation Array Cable Laying Construction Port Rent Substation Installation Guard Vessel Turbine Installation Commissioning Absence of contractual agreements between vendors leads to multiple installation contracts being affected by events on a single supply contract Multiple Contracts

8 Problems within the Supply Chain Equity 1 Equity 2 Equity 3 Equity 4 Equity 5 Stakeholder Map Turbine Supply Electricity Offtake Difficulties with Variation Order Approval Substation Supply Foundation Pre-piling Foundation Transport Developer Grid Connection Service & Maintenance Operational Management Foundation Supply Financial Advisor Cable Supply Banks & Lenders Technical DD Legal DD Insurance DD Model Audit

9 Supply Chain Management Procurement Develop: Financial Close Construction Implement: Project Close Corporate QHSE Procedures Corporate QHSE Procedures Project QHSE Plans Project QHSE Plans Project Execution Plan Project Execution Plan Risk Management Risk Management Planning / Scheduling Planning / Scheduling Interface Management Interface Management Supply Chain Management Supply Chain Management Document Management Document Management Change Management Change Management QA/QC Audit QA/QC Audit Contract / Commercial Contract / Commercial

10 Status Developer (Developer / Project Company) PMC (Project Management) Contractor 1 (WTG Foundation Supply) Contractor 2 (WTG Supply) Contractor 3 (Substation Supply) Contractor 4 (Cable Supply) Contractor 5 (Foundation & Substation Installer) Contractor 6 (WTG Installer) Contractor 7 (Cable Installer) Interface & Scope Matrix A - Project Management and Control Interface Name (Brief description based on physical location) L = Lead Responsibility S = Support Responsibility Detail Description A External interfaces Use of Construction Port Aim: Management of the Construction Port Action: Allocate usage of the Construction Port to contractors for shelter during storms, crew transfer and storage purposes. All other interface contractors will use the Construction Port for personnel transfer only. S S S S L S 2 Fisheries liaison Aim: Provision of Fisheries Liaison Action: Carry out all fisheries liaison. L S S S S S 3 Permits Aim: T o obtain all permits in due time to permit construction Action: Obtain all necessary permissions. Contractors to provide all inputs requested to support permit applications / submissions. L S S S S S S S S 4 Press releases and publicity Aim: T o control all contact with the media to ensure correct information is sent out and ensure non Disclosure Agreements are not breached. Action: Instigate or approve all press communications and media contact. All contractors to seek specific approval for all press releases. L S S S S S S S S 5 Deutsche T elekom Aim: T o ensure cable crossing agreements and working near to cable procedures are agreed. Action: Cable/installation contractor to work together to agree working methods with relevant third parties. 6 Grid provider Aim: T o ensure Grid Connection is available at the correct time. Action: Coordinate fabrication and installation activities and agree with Grid Provider when grid connection shall be available. 7 Marine Warranty Surveyor Aim: Provision of Marine Warranty Surveyor Action: A Marine Warranty Surveyor will be engaged. The Contractors are required to liaise with the Marine Warranty Surveyor and provide documentation and information necessary for the Marine Warranty Surveyor to perform his work. A Construction sequence / coordination 8 Construction sequence / coordination Aim: Provision of construction sequence / coordination Action: Contractors will work with Marine Supervisor to ensure safe and effective coordination of vessel movements at the work site. Installation Contractor will coordinate and prioritise vessel movements via a Marine Supervisor. Each Contractor will appoint a nominated vessel coordinator to manage and control their vessel movements. The Contractors' vessel coordinators will liaise with the Marine Supervisor. If 9 10 Provision of Guard Vessel Maintenance of installation progress at Worksite Aim: T o ensure all offshore works are carried out with a guard vessel in attendance. Action: Installation Contractors to provide a suitable guard vessel to warn other sea users of any installation works. Each contractor to ensure his Aim: vessels Coordination are protected. of worksite activities by Installation Contractor Action: All contractors will provide daily progress on site to enable preparation of up-to-date plots of data for issue and use by other contractors. Data to include installation of Foundations, Cables, WT Gs and all seabed obstructions such as jack-up footprints and anchor locations. L S S S S L S S L S S S S S L S S S S S S L S S S S S S S L L L L

11 Interface & Scope Matrix Foundation Vessel Bubble Curtain Vessel Foundation Vessel ROV Managing Interfaces = Prevention of delays = Cost avoidance

12 Risk Register Contractor 1 Contractor 3 Contractor 2 Project Risk? Contractor 4

13 Risk Register Risk: Delay in preparation of the foundations which may result in a requirement to postpone delivery of the cable. Mitigation: Optional 30-day delay mechanism agreed with the inter array cable supply and install contractor at no additional cost. Risk #1 Managing Risks = Prevention of Delays = Cost avoidance

14 Procurement Criticality Rating Early supply chain engagement = Prevention of Delays = Cost avoidance

15 Recommendations Improving management of the supply chain will help reduce: Industry risk profile CAPEX overspend

16 Contact Details: David Robertson Head of Project Management Services Phone: +44 (0) Mark Cowling Project Management Consultant Phone: +44 (0)

A2SEA Horns Rev 3. Jens Nielsen Head of Procurement August 2016

A2SEA Horns Rev 3. Jens Nielsen Head of Procurement August 2016 A2SEA Horns Rev 3 Jens Nielsen Head of Procurement August 2016 Agenda Introduction A2SEA Scope of Work - Horns Rev 3 Supply Chain Requirements How to register with A2SEA HSE Tour Introducing A2SEA Founded

More information

Town of Babylon Cost Accounting: Long Island Offshore Wind Project

Town of Babylon Cost Accounting: Long Island Offshore Wind Project Town of Babylon Cost Accounting: Long Island Offshore Wind Project Steve Bellone, Supervisor Dorian Dale, Energy Director Babylon s Cost Accounting: Long Island Offshore Wind Project (LIOWP) relied, for

More information

DONG Energy Renewables The offshore wind farms option

DONG Energy Renewables The offshore wind farms option DONG Energy Renewables The offshore wind farms option ENERGI E2/DONG Energy Mr Per Hjelmsted Senior Manager, Project Development 20 September 2006 DONG energy - a merger of six companies 6 companies Medarbejdere

More information

Green Engineering Technology Day , Scandic Hotel Kolding. Siemens Wind Power. Hardware In Loop Software Test System

Green Engineering Technology Day , Scandic Hotel Kolding. Siemens Wind Power. Hardware In Loop Software Test System Green Engineering Technology Day 24-03-2010, Scandic Hotel Kolding Siemens Wind Power Hardware In Loop Software Test System Agenda About Siemens Siemens Energy Sector Siemens Wind Power Hardware In Loop

More information

Carbon Trust Offshore Wind Accelerator Driving down the cost of offshore wind. 21 May 2013 Phil de Villiers

Carbon Trust Offshore Wind Accelerator Driving down the cost of offshore wind. 21 May 2013 Phil de Villiers Carbon Trust Offshore Wind Accelerator Driving down the cost of offshore wind 21 May 2013 Phil de Villiers 1 Carbon Trust mission is to accelerate the move to a low carbon economy Technology We help develop

More information

UK content analysis of Robin Rigg offshore wind farm

UK content analysis of Robin Rigg offshore wind farm UK content analysis of Robin Rigg offshore wind farm A report commissioned by E.ON Climate & Renewables September 2011 BVG Associates BVG Associates is a technical consultancy with expertise in wind and

More information

Offshore Wind. Foundations

Offshore Wind. Foundations Offshore Wind Foundations Foundations Ever since the first industrial offshore wind farm Horns Rev was built, Smulders has played an important role in the engineering and fabrication of steel foundations

More information

An Imagination Breakthrough: Offshore Wind Energy

An Imagination Breakthrough: Offshore Wind Energy An Imagination Breakthrough: Offshore Wind Energy Alternative Energy Technology Innovations: Savannah, Georgia Benjamin Bell GE Energy Overview Why Wind? Why Offshore? The Technology Wind Energy Economics

More information

Bernhard Messer (MD - OPUS MARINE GmbH)

Bernhard Messer (MD - OPUS MARINE GmbH) CLICK TO EDIT MASTER OPUS TITLE MARINE STYLE GmbH Presented by: Click to edit Master subtitle style Bernhard Messer (MD - OPUS MARINE GmbH) 1 OPUS IN A NUTSHELL Crew Transfers Offshore Container Salvage

More information

OffshOre Wind farm. Joint venture involving.

OffshOre Wind farm. Joint venture involving. LO N D O N A R R AY OffshOre Wind farm Joint venture involving www.londonarray.com Welcome to London Array London Array is the largest operational offshore wind farm in the world. Comprising 175 3.6MW

More information

Wind Accelerator. energy through targeted R&D. 21 January 2011

Wind Accelerator. energy through targeted R&D. 21 January 2011 Carbon Trust s s Offshore Wind Accelerator Accelerating progress of offshore wind energy through targeted R&D NOWITECH 21 January 2011 Phil de Villiers Our mission is to accelerate the move to a low carbon

More information

OFFSHORE WIND ENERGY IN EUROPE

OFFSHORE WIND ENERGY IN EUROPE OFFSHORE WIND ENERGY IN EUROPE Preben Maegaard President, World Wind Energy Association Chairperson, World Council for Renewable Energy SYMPOSIUM, COASTAL DEVELOPMENT INSTITUTE OF TECHNOLOGY, YOKOHAMA

More information

The European offshore wind industry key trends and statistics February A report by the European Wind Energy Association

The European offshore wind industry key trends and statistics February A report by the European Wind Energy Association The European offshore wind industry key trends and statistics 2015 February 2016 A report by the European Wind Energy Association Contents Contents Executive summary 3 Annual market in 2015 4 Cumulative

More information

New York State Offshore Wind Master Plan. October 20, 2017

New York State Offshore Wind Master Plan. October 20, 2017 New York State Offshore Wind Master Plan October 20, 2017 2 Offshore Wind Master Plan A comprehensive State roadmap for advancing development of offshore wind in a cost-effective and responsible manner

More information

Demand and Requirements of the Offshore Wind Industry concerning Ports worldwide

Demand and Requirements of the Offshore Wind Industry concerning Ports worldwide IAPH / HPA Demand and Requirements of the Offshore Wind Industry concerning Ports worldwide Final Report The International Association of Ports and Harbors Technical Committee Port Planning and Development

More information

Installation, commissioning and decommissioning offshore wind. Marcus Bentin

Installation, commissioning and decommissioning offshore wind. Marcus Bentin Installation, commissioning and decommissioning offshore wind Marcus Bentin Faculty of Maritime Studies Weiter 2 Maritime Industry in Germany 3 Installation of offshore wind turbines In 2015 3,230 offshore

More information

Planned intervention as a maintenance and repair strategy for offshore wind turbines

Planned intervention as a maintenance and repair strategy for offshore wind turbines Journal of Marine Engineering & Technology ISSN: 2046-4177 (Print) 2056-8487 (Online) Journal homepage: http://www.tandfonline.com/loi/tmar20 Planned intervention as a maintenance and repair strategy for

More information

The Future of the Ocean Economy - Offshore Wind

The Future of the Ocean Economy - Offshore Wind The Future of the Ocean Economy - Offshore Wind Workshop on Shipping and the Offshore Industry Monday 24 th November, 2014 OECD, Paris Key data sources EWEA Background Projections Technology Finance IEA

More information

Ørsted in the UK. Ørsted

Ørsted in the UK. Ørsted in the UK Let s create a world that runs entirely on green energy A company with purpose and vision At, we believe in a world that runs entirely on green energy. Climate change is one of the biggest challenges

More information

China Meeting the Challenges of Offshore and Large-Scale Wind Power: Regulatory Review of Offshore Wind in Five European Countries.

China Meeting the Challenges of Offshore and Large-Scale Wind Power: Regulatory Review of Offshore Wind in Five European Countries. The World Bank Asia Sustainable and Alternative Energy Program Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized China Meeting the Challenges

More information

The Past, Present and Future of Wind Supply Chains

The Past, Present and Future of Wind Supply Chains The Past, Present and Future of Wind Supply Chains DHL Global Wind Conference II - Hamburg 27 September 2016 By Richard van Aurich - MD, Renewable Energy - Germany & Denmark, SHL 27 September 2016 Agenda

More information

Offshore Wind Technology

Offshore Wind Technology Offshore Wind Technology Jason Jonkman Senior Engineer National Renewable Energy Laboratory Golden, Colorado Webinar: Offshore Wind Potential for the Great Lakes January 30, 2009 Why Offshore Wind? 28

More information

PES ESSENTIAL. PES: Europe

PES ESSENTIAL. PES: Europe PES ESSENTIAL 96 PES: Europe The cost of wind Like other renewable energy technologies, wind is capital intensive, but has no fuel costs. The key parameters governing wind power economics are the investment

More information

International Workshop on Wind Energy Development Cairo, Egypt March, 2010

International Workshop on Wind Energy Development Cairo, Egypt March, 2010 ti International Workshop on Wind Energy Development Cairo, Egypt 22-24 March, 2010 Starting Theory Final Ending Wind data needed farther offshore Class 6 winds likely on this 100 km 2 shoal Probable Location,

More information

Wind Energy: Overall Potential and Opportunities

Wind Energy: Overall Potential and Opportunities Wind Energy: Overall Potential and Opportunities Prepared by: Jens Peter Molly, DEWI GmbH on behalf of UNIDO Global Renewable Energy Forum Foz do Iguaçu, Brazil 18 21 MAY 2008 SITE ASSESSMENT. WIND TURBINE

More information

This report summarises construction and financing activity in European offshore wind farms from 1 January to 31 December 2017.

This report summarises construction and financing activity in European offshore wind farms from 1 January to 31 December 2017. This report summarises construction and financing activity in European offshore wind farms from 1 January to 31 December 2017. WindEurope regularly surveys the industry to determine the level of installations

More information

FOURTH M E E T I N G. Esbjerg, Denmark April 2004

FOURTH M E E T I N G. Esbjerg, Denmark April 2004 FOURTH M E E T I N G Esbjerg, Denmark 15-16 April 2004 Agenda Item: 6 Subject: Document Nr. Offshore wind parks WSF-4-6-1 Date: 1 April 2004 Submitted by: Secretariat Attached is an overview of existing

More information

Offshore Co-Operations. Dennis Schiricke Program Director Deutsche Windtechnik OC

Offshore Co-Operations. Dennis Schiricke Program Director Deutsche Windtechnik OC Offshore Co-Operations Dennis Schiricke Program Director Deutsche Windtechnik OC Safety Quality Joined Interest Responsibility Asset Utilization Partner in Offshore Business Cluster Synergy Asset Integrity

More information

UE 1.65 DirectDrive Turbine Technology

UE 1.65 DirectDrive Turbine Technology UE 1.65 DirectDrive Turbine Technology A World full of Energy. The right choice for the maximum return on your investment in wind energy. UE 1.65 DirectDrive With its simplicity and modularity the UE 1.65

More information

Swedish environmental legislation and how it is implemented. Malin Hemmingsson

Swedish environmental legislation and how it is implemented. Malin Hemmingsson Swedish environmental legislation and how it is implemented Malin Hemmingsson Malin.Hemmingsson@havochvatten.se Swedish Agency for Marine and Water Management (SwAM) Started its operations on July,1 2011

More information

Composites for offshore wind. Alun Roberts, 9 November 2011

Composites for offshore wind. Alun Roberts, 9 November 2011 Composites for offshore wind Alun Roberts, 9 November 2011 BVG Associates Wind and marine energy only Formed in 2005 Hands-on experience in the wind industry Market analysis Business development New technology

More information

Development of Human Activities in the North Sea

Development of Human Activities in the North Sea BE-AWARE Risk Assessment Seminar, Tønsberg, Norway Development of Human Activities in the North Sea David Johnson, Bonn Secretariat EWEA Members Across entire supply chain EWEA Wind Energy scenario to

More information

2 COWI expertise. Spudcan analysis for jack-up Power systems and SCADA Risk analyses. COWI - quality - schedule - cost. Worldwide experience

2 COWI expertise. Spudcan analysis for jack-up Power systems and SCADA Risk analyses. COWI - quality - schedule - cost. Worldwide experience COWI offshore wind 2 COWI expertise COWI is a highly versatile and multidisciplinary company. We provide services within engineering, environment and economics and operate worldwide from more than 35 international

More information

Building a Profitable Wind Business

Building a Profitable Wind Business GE Energy Building a Profitable Wind Business Vic Abate July 26, 2006 This document contains "forward-looking statements" - that is, statements related to future, not past, events. In this context, forward-looking

More information

Clean Line Energy Partners

Clean Line Energy Partners Clean Line Energy Partners 2012 Transmission investment is required to connect the best wind resources to load centers Clean Line projects Rock Island CA Centennial West Grain Belt Express Plains & Eastern

More information

DONG ENERGY IN THE UK

DONG ENERGY IN THE UK DONG ENERGY IN THE UK LEADING THE ENERGY TRANSFORMATION 2017 Contents Chairman s foreword 6 Green energy 12 Environment 16 Building a sustainable offshore wind industry 24 Communities 28 People 2016 was

More information

Environmental Impact Assessment Proportionate Assessment

Environmental Impact Assessment Proportionate Assessment Environmental Impact Assessment Proportionate Assessment Rufus Howard BSc LLM FIEMA CEnv PEIA MIoD 18 th July 2017 2005 to 2013 Trends Over Time 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 0 Oct-05

More information

Neart na Gaoithe Offshore Wind Farm Carbon Life Cycle Assessment Report Emu Ltd

Neart na Gaoithe Offshore Wind Farm Carbon Life Cycle Assessment Report Emu Ltd Neart na Gaoithe Offshore Wind Farm Carbon Life Cycle Assessment Report Emu Ltd Assignment Number: Document Number: L30056-S00 L-30056-S00-REPT-001 Xodus Group Ltd Cheapside House 138 Cheapside London

More information

Trends in offshore wind economics the past and the future

Trends in offshore wind economics the past and the future Downloaded from orbit.dtu.dk on: Apr 28, 218 Trends in offshore wind economics the past and the future Kitzing, Lena; Morthorst, Poul Erik Published in: Proceedings - 14th Wind Integration Workshop Publication

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.1 Voltage level Filename ONL15-058-T1_Voltage level_pp_v1 Version 1 - release for Expert

More information

Offshore Wind Power Production in Critical Weather Conditions

Offshore Wind Power Production in Critical Weather Conditions Downloaded from orbit.dtu.dk on: Dec 25, 2017 Offshore Wind Power Production in Critical Weather Conditions Cutululis, Nicolaos Antonio; Litong-Palima, Marisciel; Sørensen, Poul Ejnar Published in: Proceedings

More information

Project Development wpd offshore projects

Project Development wpd offshore projects Project Development wpd offshore projects GERMANY Butendiek (288 MW) Nordergründe (110 MW) Kaikas (580 MW) Aiolos (700 MW) Apollon (400-600 MW) Notos (318 MW) Baltic 1 (48,3 MW)* Baltic 2 (288 MW)* Hohe

More information

Project overview. Construction at the offshore wind farm site will begin in 2017 and the project is expected to be fully operational in 2019.

Project overview. Construction at the offshore wind farm site will begin in 2017 and the project is expected to be fully operational in 2019. Project overview Beatrice Offshore Windfarm Limited (BOWL) is a joint venture partnership between SSE Renewables (40%), Copenhagen Infrastructure Partners (35%) and Red Rock Power (25%). SSE is one of

More information

The Offshore Way. WIPOS Wind power offshore substation. Answers for energy.

The Offshore Way. WIPOS Wind power offshore substation. Answers for energy. The Offshore Way WIPOS Wind power offshore substation Answers for energy. WIPOS configuration flexibility to meet every challenge With the new wind power offshore substation WIPOS, Siemens has created

More information

Deliverable Definition of Performance Indicators (PIs) and Target Values. February Duration Nov 2012-Oct 2017

Deliverable Definition of Performance Indicators (PIs) and Target Values. February Duration Nov 2012-Oct 2017 Deliverable 1.2.2 Definition of Performance Indicators (PIs) and Target Values February 2014 Agreement n.: 308974 Duration Nov 2012-Oct 2017 Co-ordinator: Peter Hjuler Jensen, DTU PROPRIETARY RIGHTS STATEMENT

More information

DECISION 1 SCOPE AND CONSIDERATIONS... 2

DECISION 1 SCOPE AND CONSIDERATIONS... 2 MEMORANDUM TO Windfarm developers FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed: Frank de Vries 19.09.2017

More information

Wind Commissioning Guidance

Wind Commissioning Guidance Wind Commissioning Guidance 80% of Installed Capacity Operational Condition Precedent 2.1 (B) Version 2.0 Issued on 31 October 2017 Applicable to Investment Contracts, CFD Agreement and CFD Standard Terms

More information

RENEWABLE AND ALTERNATIVE ENERGIES

RENEWABLE AND ALTERNATIVE ENERGIES RENEWABLE AND ALTERNATIVE ENERGIES Degree in Energy Resources Engineering Academic year 2014-15 Prof. Pablo Castro Description: This is a case study for the development of a small wind farm: Wind farm

More information

Wind Energy: Opportunities and Challenges for Offshore Applications. Presentation Outline

Wind Energy: Opportunities and Challenges for Offshore Applications. Presentation Outline Wind Energy: Opportunities and Challenges for Offshore Applications Presentation to IEEE Richmond Section 07 September 2006 Saifur Rahman George Hagerman Manisa Pipattanasomporn VT Advanced Research Institute

More information

STRUCTURAL AND ECONOMIC OPTIMISATION OF BOTTOM-MOUNTED OFFSHORE WIND ENERGY CONVERTERS Overview on Final Results of the Opti-OWECS project

STRUCTURAL AND ECONOMIC OPTIMISATION OF BOTTOM-MOUNTED OFFSHORE WIND ENERGY CONVERTERS Overview on Final Results of the Opti-OWECS project STRUCTURAL AND ECONOMIC OPTIMISATION OF BOTTOM-MOUNTED OFFSHORE WIND ENERGY CONVERTERS Overview on Final Results of the Opti-OWECS project M. Kühn 1, W.A.A.M. Bierbooms 1, G.J.W. van Bussel 1 M.C. Ferguson

More information

Design and Development in Offshore Branch

Design and Development in Offshore Branch Bilfinger Mars Offshore sp. z o.o. Design and Development in Offshore Branch Szczecin, PONP 31-05-2016 Speaker: Dr Marek Los, Proxy, Head of Engineering, Design & Development Bilfinger Mars Offshore Agenda

More information

Offshore Wind Seminar Legal and commercial features of Transport and Installation Contracts

Offshore Wind Seminar Legal and commercial features of Transport and Installation Contracts Offshore Wind Seminar Legal and commercial features of Transport and Installation Contracts When: 8 November 2017 Where: Copenhagen, Denmark This inter-active session is for professionals working within

More information

ALPHA-OMEGA 1 MW WIND GENERATOR ALPHA OMEGA ECOLOGICAL SOLUTIONS. Direct Phones: &

ALPHA-OMEGA 1 MW WIND GENERATOR ALPHA OMEGA ECOLOGICAL SOLUTIONS. Direct Phones: & ALPHA-OMEGA 1 MW WIND GENERATOR ALPHA OMEGA ECOLOGICAL SOLUTIONS Athens Office: 8, R. Garibaldi & Sofroniskou str. Tel. +30.210.9228225 Email: info@alpha-omega.com.gr Direct Phones: +30.697.42 28 012 &

More information

Offshore Wind Energy in Europe

Offshore Wind Energy in Europe Off Wind Energy in Europe A. R. HENDERSON Section Wind Energy, Delft University of Technology, tel. +31-15-278-8092, email A.Henderson@CiTG.TUDelft.nl C. Morgan Garrad Hassan & Partners Ltd, tel: +44-1275-394360,

More information

Offshore Windpark Egmond aan Zee

Offshore Windpark Egmond aan Zee Offshore Windpark Egmond aan Zee Monitoring program and international collaboration Henk Kouwenhoven Monitoring and WTG package manager www.noordzeewind.nl 22 February 2007 EU Policy Workshop on offshore

More information

Subtittle if needed. If not MONTH Published in Month Offshore Wind in Europe

Subtittle if needed. If not MONTH Published in Month Offshore Wind in Europe Subtittle if needed. If not MONTH 2018 Published in Month 2018 Offshore Wind in Europe Key trends and statistics 2017 Offshore Wind in Europe Key trends and statistics 2017 Published February 2018 windeurope.org

More information

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction 9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of

More information

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Wind Power in Denmark Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Outline Status on wind power deployment and large scale integration Support system and consent

More information

Nordex USA, Inc. Wind Turbine Supply Chain Characteristics, Challenges and Opportunities. GACCoM Renewables & Energy Efficiency Roadshow 3 Sept 2009

Nordex USA, Inc. Wind Turbine Supply Chain Characteristics, Challenges and Opportunities. GACCoM Renewables & Energy Efficiency Roadshow 3 Sept 2009 Nordex USA, Inc. Wind Turbine Supply Chain Characteristics, Challenges and Opportunities GACCoM Renewables & Energy Efficiency Roadshow 3 Sept 2009 Page 1 1 Agenda 1 2 3 About Nordex Current situation

More information

Published by and copyright 2009: Siemens AG Energy Sector Freyeslebenstrasse Erlangen, Germany

Published by and copyright 2009: Siemens AG Energy Sector Freyeslebenstrasse Erlangen, Germany Published by and copyright 2009: Siemens AG Energy Sector Freyeslebenstrasse 1 91058 Erlangen, Germany Siemens Wind Power A/S Borupvej 16 7330 Brande, Denmark www.siemens.com/wind For more information,

More information

AT INCEPTION Manufacturing Quality Assurance CWC s Inspectors are embedded at the blade manufacturing facility during production of new blades.

AT INCEPTION Manufacturing Quality Assurance CWC s Inspectors are embedded at the blade manufacturing facility during production of new blades. INSPECTION PROGRAMS AT INCEPTION Manufacturing Quality Assurance CWC s Inspectors are embedded at the blade manufacturing facility during production of new blades. DURING CONSTRUCTION Site Delivery CWC

More information

Bligh Bank Offshore Wind Farm

Bligh Bank Offshore Wind Farm MUMM Project Monitoring: Concluding Report Executive Summary June 2011 MUMM Bligh Bank Offshore Wind 265503 RGE RGF 8 B Farm C:\DOCUME~1\bar56618\OTLocal\PimsLive\Workbin\57EDD310.0\Belwi nd Bligh Bank

More information

TURBINE FAILURE LITERATURE REVIEW AND THE WIND TURBINE CERTIFICATION PROCESS

TURBINE FAILURE LITERATURE REVIEW AND THE WIND TURBINE CERTIFICATION PROCESS TURBINE FAILURE LITERATURE REVIEW AND THE WIND TURBINE CERTIFICATION PROCESS Client Contact Green Mountain Power Corp. Charles Pughe Document No 41404/AR/03A Classification Client s Discretion Status Final

More information

Ormonde Offshore Wind Farm

Ormonde Offshore Wind Farm Ormonde Offshore Wind Farm Pile grouting for 31 four-legged jacket foundations in the Irish Sea, 10km off Barrow-In-Furness. Subsea and offshore grouting for the global energy construction industries FoundOcean

More information

Wind Energy Services. Ingeteam Inc.

Wind Energy Services. Ingeteam Inc. INGETEAM INC. Suite 102-1025 W. Glen Oaks Lane Mequon, WI 53092 - USA Phone: +1 262 240 9850 Fax +1 262 240 9854 Wind Energy Services Ingeteam Inc. www.ingeteam.com PCØØIICØ1_A INFORMATION SUBJECT TO MODIFICATION

More information

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Contents Contents... 2 Preface... 3 Issue Record... 3 Assessment

More information

Windfarm Slufter II. The Netherlands

Windfarm Slufter II. The Netherlands Windfarm Slufter II The Netherlands May 2017 Index Index...2 1. Introduction...3 2. General specifications...3 3. Scope of the windfarm...4 4. Availability...4 5. Production data...4 6. Site Access...4

More information

Making the Transfer from Oil and Gas to Offshore Wind: Our Experience

Making the Transfer from Oil and Gas to Offshore Wind: Our Experience Making the Transfer from Oil and Gas to Offshore Wind: Our Experience Richard Forbes Business Development Manager Oil and Gas www.foundocean.com Timeline History 1966 1970 1980 1990 2000 2010 2013 WIMPEY

More information

The European offshore wind industry

The European offshore wind industry The European offshore wind industry Key trends and statistics 2016 The European offshore wind industry Key trends and statistics 2016 Published in January 2017 windeurope.org This report summarises construction

More information

WIND ENERGY GROUP 3 MEMBERS: ALEJANDRO ESPINOLA JUAN C. ENRIQUEZ LINDA ALAMILLO THOMAS BROWN BRUCE SAENZ

WIND ENERGY GROUP 3 MEMBERS: ALEJANDRO ESPINOLA JUAN C. ENRIQUEZ LINDA ALAMILLO THOMAS BROWN BRUCE SAENZ WIND ENERGY GROUP 3 MEMBERS: ALEJANDRO ESPINOLA JUAN C. ENRIQUEZ LINDA ALAMILLO THOMAS BROWN BRUCE SAENZ Overview Problem statement Wind EnergyTechnologies Technical development Status in Renewable Energy

More information

FERRIBY MARINE SHIP SECURITY ASSESSMENT AUDIT CHECKLIST

FERRIBY MARINE SHIP SECURITY ASSESSMENT AUDIT CHECKLIST SHIP SECURITY ASSESSMENT AUDIT CHECKLIST SHIP SECURITY ASSESSMENT AUDIT CHECKLIST 1. A Ship Security Assessment (SSA) is a process that identifies weaknesses in physical structures, personnel protection

More information

Floating Wind Power in Deep Water Competitive with Shallow-water Wind Farms?

Floating Wind Power in Deep Water Competitive with Shallow-water Wind Farms? Floating Wind Power in Deep Water Competitive with Shallow-water Wind Farms? a report by Eystein Borgen Sway AS Pioneering projects with a few bottom-mounted wind turbines in shallow water were first installed

More information

OLAV OLSEN OFFSHORE WIND ++

OLAV OLSEN OFFSHORE WIND ++ NORWEGIAN OFFSHORE WIND CLUSTER, SOLA 31.10.2017 1 OLAV OLSEN OFFSHORE WIND ++ Trond Landbø Manager Business Area Energy/Renewable Dr.techn.Olav Olsen AS Dr.techn.Olav Olsen AS 2 DR.TECHN. OLAV OLSEN COMPANY

More information

Making Offshore Wind Power Profitable

Making Offshore Wind Power Profitable The information contained in this presentation shall only be used to evaluate Inwind as a cooperation partner and shall not be passed on to any third party. Inwind an Integrated Offshore Wind Contractor

More information

Offshore Wind Energy in Europe A Review of the State-of-the-Art

Offshore Wind Energy in Europe A Review of the State-of-the-Art WIND ENERGY Wind Energ. 2003; 6:35 52 (DOI: 10.1002/we.82) Review Article Offshore Wind Energy in Europe A Review of the State-of-the-Art Andrew R. Henderson, Delft University of Technology, Delft, The

More information

Ocean Energy Specialisation 2014 OER 1 and EPE 1&2 assignments

Ocean Energy Specialisation 2014 OER 1 and EPE 1&2 assignments Ocean Energy Specialisation 0 OER and EPE & assignments The following text describes the assignments for the OER and EPE & modules. The assignment intends to provide the students with an opportunity to

More information

Timothy Cornelius CEO, Atlantis Resources Limited. Atlantis Resources: November

Timothy Cornelius CEO, Atlantis Resources Limited. Atlantis Resources: November Timothy Cornelius CEO, Atlantis Resources Limited Atlantis Resources: November 2014 0 Atlantis Turbine Systems 1.5MW turbine system AR1500 detailed design contract with Lockheed Martin formally commenced

More information

Maritime Spatial Planning in the German EEZ

Maritime Spatial Planning in the German EEZ Maritime Spatial Planning in the German EEZ Bettina Käppeler, BSH 13.11.2012 Wadden Sea Forum 21st Meeting - Leck 1 Federal Maritime and Hydrographic Agency Bernhard-Nocht-Straße, Hamburg Neptunallee,

More information

Offshore Wind Energy in the Netherlands

Offshore Wind Energy in the Netherlands Offshore Wind Energy in the Netherlands Asset Management & Technical Innovations Bram Reinders Mark de la Vieter September 2014 Agenda Dutch Energy Policy & Industry Policy Offshore Wind Energy in the

More information

Innovation Paths in Wind Power: Insights from Denmark and Germany

Innovation Paths in Wind Power: Insights from Denmark and Germany Innovation Paths in Wind Power: Insights from Denmark and Germany Rasmus Lema and Frauke Urban Paper with Johan Nordensvärd and Wilfried Lütkenhorst Technological pathways to low carbon: Competition and

More information

Panel #2 - Wind logistics: Onshore towards offshore 2 nd Annual DHL Global Wind Conference

Panel #2 - Wind logistics: Onshore towards offshore 2 nd Annual DHL Global Wind Conference Panel #2 - Wind logistics: Onshore towards offshore Hamburg, September 26, 2016 Renewable Energy Solutions Presented by Thomas Poulsen, Managing Partner Wind logistics: Onshore towards offshore Key Definitions

More information

also report to the Project Manager on a day to day basis).

also report to the Project Manager on a day to day basis). Job Title Department Reports to Project Design Manager (PDM) Production Design Manager. (Whilst site based and a member of the project management team, the PDM will also report to the Project Manager on

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies CM CORE 1 Cost Engineering Commercial Management Core Competency Cost Engineering Specialism COMPETENCIES AND ASSESSMENT Financial and commercial processes in civil engineering January 2015 Technical Member

More information

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee);

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee); Ministerial Order issued by the Minister of Economic Affairs dated 3 October 27 No. WJZ / 722295, containing specific rules for permitting offshore wind energy permits for Wind Farm Sites I and II of the

More information

V MW. One turbine for one world. vestas.com

V MW. One turbine for one world. vestas.com V112-3.0 MW One turbine for one world vestas.com No. 1 in Modern Energy The world needs ever-greater supplies of clean, sustainable energy. Modern energy that promotes sustainable development and greater

More information

Table of contents TEMPORARY WORKS DESIGN BV 1

Table of contents TEMPORARY WORKS DESIGN BV 1 Table of contents Table of contents... 1 1 Company... 2 2 Overview of offshore piling services... 3 2.1 Combi-wall piling frame... 3 2.2 Cell wall template... 4 2.3 Trestle and berth piling template...

More information

Wind Energy Market Development and Economic Risk Management of Projects

Wind Energy Market Development and Economic Risk Management of Projects Wind Energy Market Development and Economic Risk Management of Projects Jens Peter Molly Deutsches Windenergie - Institut GmbH (German Wind Energy Institute) Global Wind Energy Congress, Geneva, Switzerland,

More information

Cost Reduction Potentials of Offshore Wind Power in Germany: comparison with Offshore Wind Cost Reduction Pathways Study

Cost Reduction Potentials of Offshore Wind Power in Germany: comparison with Offshore Wind Cost Reduction Pathways Study Commercial in confidence Cost Reduction Potentials of Offshore Wind Power in Germany: comparison with Offshore Wind Cost Reduction Pathways Study December with 213 Bruce Valpy Revision Purpose and description

More information

GE Renewable Energy BEST-IN-CLASS CAPACITY FACTOR. GE s

GE Renewable Energy BEST-IN-CLASS CAPACITY FACTOR. GE s GE Renewable Energy BEST-IN-CLASS CAPACITY FACTOR GE s 1.7-100 www.ge.com/wind GE S 1.7-100 PITCH Since entering the wind industry in 2002, GE Renewable Energy has invested more than $2 billion in next-generation

More information

Marine Management Organisation Marine Licence 1 Introduction

Marine Management Organisation Marine Licence 1 Introduction Marine Management Organisation Marine Licence 1 Introduction This is a licence granted by the Marine Management Organisation on behalf of the Secretary of State to authorise the licence holder to carry

More information

Without having Cost Estimation Model you are putting your Project on a Big RISK

Without having Cost Estimation Model you are putting your Project on a Big RISK July 2014 Without having Cost Estimation Model you are putting your Project on a Big RISK Drive your project with a appropriate Cost Estimation System to mitigate Risks Plug your project to Our NoDoC Database

More information

Realizing the Far and Large Offshore Wind Innovation Program (FLOW) Presentation at conference

Realizing the Far and Large Offshore Wind Innovation Program (FLOW) Presentation at conference Realizing the Far and Large Offshore Wind Innovation Program (FLOW) Presentation at We@Sea conference Den Helder, December 1, 2009 1 A. Vision and objectives: FLOW is instrumental to realizing the Netherlands'

More information

Changing the Scale of Offshore Wind: Examining Mega-Projects in the United Kingdom

Changing the Scale of Offshore Wind: Examining Mega-Projects in the United Kingdom Changing the Scale of Offshore Wind: Examining Mega-Projects in the United Kingdom SESSION: Wind Energy and the current international situation, Madrid, June 12, 2012 More than 50% of mega-projects are

More information

The GICON -TLP for wind turbines

The GICON -TLP for wind turbines The GICON -TLP for wind turbines Experimental Studies and numerical Modelling of structural Behavior of a Scaled Modular TLP Structure for Offshore Wind turbines J. Großmann, F. Dahlhaus, F. Adam, B. Schuldt

More information

GE Renewable Energy CAPACITY FACTOR LEADERSHIP IN HIGH WIND REGIMES. GE s

GE Renewable Energy CAPACITY FACTOR LEADERSHIP IN HIGH WIND REGIMES. GE s GE Renewable Energy CAPACITY FACTOR LEADERSHIP IN HIGH WIND REGIMES GE s 1.85-82.5 www.ge.com/wind GE S 1.85-82.5 PITCH Since entering the wind industry in 2002, GE Renewable Energy has invested more than

More information

U.S electricity flow, 2005

U.S electricity flow, 2005 Wind Energy Systems Prof. Surya Santoso Department of Electrical and Computer Engineering The University of Texas at Austin ssantoso@ece.utexas.edu U.S electricity flow, 2005 Unit is in quadrillion BTU

More information

OFFSHORE WIND ACCELERATOR PROJECT WEBINAR SERIES Understanding Regional Supply Chain Opportunities for Offshore Wind Global Wind Network (GLWN)

OFFSHORE WIND ACCELERATOR PROJECT WEBINAR SERIES Understanding Regional Supply Chain Opportunities for Offshore Wind Global Wind Network (GLWN) OFFSHORE WIND ACCELERATOR PROJECT WEBINAR SERIES Understanding Regional Supply Chain Opportunities for Offshore Wind Global Wind Network (GLWN) March 19, 2013 Housekeeping All participants will be placed

More information

National and International Standards for the Design of Offshore Substations. The Advantages of Offshore Substations Certification

National and International Standards for the Design of Offshore Substations. The Advantages of Offshore Substations Certification National and International Standards for the Design of Offshore Substations The Advantages of Offshore Substations Certification Folie 1 The two main Types of Certification Type or Component Certification

More information

Offshore wind: an update on the first tender round

Offshore wind: an update on the first tender round GERMANY Offshore wind: an update on the first tender round April 2017 Contents I. First auction closed on 3 April 2017 1 II. The results 1 III. "After the match is before the match" the next auction in

More information