SCADA System Procurement Alternatives

Size: px
Start display at page:

Download "SCADA System Procurement Alternatives"

Transcription

1 SCADA System Procurement Alternatives 2017 Automation Committee Seminar August 24, 2017 Terry M. Draper, PE, PMP Discussion Topics SCADA Overview System Hardware / Software Procurement Additional System Configuration Options Summary 2 Presentation Goals Discussion of options available for procurement of SCADA Systems Compare relative strengths and weaknesses of each approach Provide general recommendations for each method 3 Technolgy 1

2 Definitions / Acronyms SCADA = Supervisory Control And Data Acquisition PCS = Plant Control System / Process Control System PLC = Programmable Logic Controller RTU = Remote Terminal Unit HMI = Human Machine Interface DCS = Distributed Control System 4 SCADA Systems An application of computer technology which: gathers information from field devices displays it for use by an operator executes automatic control sequences stores and displays data for analysis. 5 Elements of a Typical SCADA System Remote Communications Human Machine Interface (HMI) Interface to Remote Areas Historical Server Field Controller Networks 6 Technolgy 2

3 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 7 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 8 Traditional Design/Bid/Build Most common approach Detailed plans and specifications Low bid procurement Build phase provides oversight of contractors Often part of a larger physical improvement project, such as plant upgrade or rehabilitation project 9 Technolgy 3

4 Traditional Design/Bid/Build Advantages Lowest initial cost General Contractor responsible for coordination Disadvantages Limited Utility input or control Qualifications of system integrators and/or panel shops may vary Requires significant oversight to ensure compliance with specifications 10 Traditional D/B/B Recommendations Develop detailed vendor qualifications Name specifics wherever possible SCADA software Computer hardware Network hardware Specifications for screen development and workshops Extensive, detailed testing 11 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 12 Technolgy 4

5 DBB with Vendor Prequalification Maintains low bid procurement Detailed plans and specifications Adds list of prequalified system integrators Prequalification can be based on previous experience at an individual utility or with the Engineer Prequalification can be based on structured evaluation 13 D/B/B with Vendor Prequalifications Advantages Maintains low cost bidding environment GC remains responsible for coordination Only prequalified SI firms allowed to bid Disadvantages General Contractor perceptions of limited choices for subs No assurance the right team from SI will be on project Requires oversight to ensure compliance with specifications 14 D/B/B with Vendor Prequal Recommendations Everything we discussed for traditional D/B/B Develop methodology for prequalification of SI Specific experience Training Project experience (similar size and complexity) Maintain ability to allow additional System Integrators to petition to be qualified during bid period Verify approach with Utility procurement staff 15 Technolgy 5

6 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 16 Evaluated Procurement using RFP Typically used for stand-alone SCADA projects, but can be used for construction projects Functional specifications are part of Request for Proposal (RFP) System Integrator / Software Supplier responds to RFP SI outlines project approach in RFP Selection is Based on detailed evaluation of technology, approach and price what is the best value for the Utility? 17 Evaluated Procurement using RFP Advantages Allows SI / Software Vendor to propose their best approach Selected on qualifications and price, not price alone (best value) Disadvantages Cost to develop and evaluate RFP Typically not done for construction projects Can be contested, delaying project 18 Technolgy 6

7 Evaluated Procurement Recommendations Detailed RFP with functional requirements Detailed, objective evaluation criteria Allow sufficient time for proposers to develop responses Verify approach with utility procurement staff 19 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 20 Separate SCADA Systems Integrator Used as part of a physical expansion or rehab project Separate SCADA SI performing in parallel with General Contractor (GC) SI Selected by methods outlined previously Separate contract between utility and SI 21 Technolgy 7

8 Separate SCADA Systems Integrator Advantages Increased Utility control over SI Useful if more than one contract is underway at same facility Disadvantages No clear contractual relationship between SI and GC Additional coordination by Owner / Engineer Potential for schedule conflict and fingerpointing 22 Separate Systems Integrator Recommendations Detailed scope of work for systems integrator Coordinate between GC Contract and SI Contract to eliminate gaps Clearly outline schedule and contract interface requirements Scheduling techniques to minimize effect of schedule slip 23 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 24 Technolgy 8

9 Background Concepts: Design-Build Project Delivery Design-Bid Build Construction Management at Risk Design-Build Design-Build-Operate Design-Build-Finance-Operate Design-Build-Own-Operate-Transfer DBB CMAR DB DBO DBFO DBOOT 25 Background Concepts: Design-Build What is Design-Build Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the project owner to provide design and construction services. Types of Design-Build Performance Based Design-Build Prescriptive Design-Build Progressive Design-Build 26 Background Concepts: Design-Build OWNERS RERESENTATIVE OWNER DESIGN BUILD TEAM Designer Builder Design-Build: A Single Organization Offering Both Construction and A-E Services Through One Contract to an Owner Consultant Consultant Consultant Trade Contractor Trade Contractor Trade Contractor 27 Technolgy 9

10 Background Concepts: Design-Build Why Design-Build (again, from DBIA) Faster delivery Cost savings Better quality Singular responsibility Decreased administrative burden Reduced risk (to Owner/Utility) Reduced litigation claims 28 Design-Build Pros / Cons Pros: Cons Shortest schedule Major effort during Appropriate risk selection process transfer Limited case law Creative technology (better every year) solutions Loss of control over Potential lower costs design by Utility Owner guarantee of Multiple solutions design is a non-issue must be evaluated Trust and synergy QBS as a selection factor is a challenge 29 Advantages of Progressive DB Offers flexibility and Owner input, with final cost determined during design Best when Owner wants design input and design to budget Performance guarantee by D-B team Provides early price certainty and Owners off-ramp If agreement on Guaranteed Maximum Price (GMP) can t be reached Off-ramp Overall GMP can be determined as early as 30% Can support multiple phased GMPs 30 Technolgy 10

11 Progressive Design-Build Flow 30% Design- Prelim Cost Est 60% Design- With GMP Execute Contract to Construct Substantial Completion Team Selection Design Concept Review Solicit Sub & Vendor Quotes Receive and Review Pricing Price/Scope Review Finalize Design/ Build Contract Finalize Design Startup and Performance Testing Construction Operator Training Project Acceptance Permitting Progress Meetings LEGEND Crowder-HDR Team Action O&M Manuals Scope/Price Development CMUD B&V Action Milestone Event/ Checking Stop Implementation 31 The Progressive Part of Design-Build The Progressive Design-Build approach: Design Process Continues at least until Guaranteed Maximum Price Set For many utilities, a full biddable set is produced Owner provides input throughout the design Progress Design-Build provides benefits: Innovation during Design Flexibility for Equipment Selection Operations Input and Flexibility Cost Benefit Schedule Benefit 32 Procurement Alternatives Traditional Design/Bid/Build Traditional with Vendor Prequalification Evaluated Procurement Separate SCADA Systems Integrator Design/Build Approach Utility Direct Procurement 33 Technolgy 11

12 Utility Direct Procurement Utility contracts directly with System Integrator / Vendor No Engineer involvement in design or construction/configuration oversight Selection of SI based on low bid or prequalifications 34 Utility Direct Procurement Advantages No Engineering Fees Cost Advantage based on Procurement Methods May have Schedule Advantage Disadvantages Relies on In-House Expertise for Functional Requirements No Structured Design to take advantage of new technologies Increased Workload on Utility Staff throughout Implementation 35 Utility Direct Procurement Recommendations Develop Detailed Functional Requirements, Including Testing and Documentation Clearly Outline Schedule Ensure Sufficient Utility Staff for Oversight and Testing Observation Ensure Procurement Staff is On-Board with Direct Procurement Discuss with Professional Engineers Board regarding Design Responsibility 36 Technolgy 12

13 Additional System Configuration Approaches Utility provided programming Utility approved single programming vendor Engineer provides programming Other variations 37 Utility Provides Programming Advantages Highest level of control over final product Lower capital costs for programming Familiar with facility and usually with the process being controlled Disadvantages Utility is in critical path Burden on utility resources 38 Engineer Provides Programming Advantages Access to Process Experts Most Knowledgeable of Design Intent Increased Level of Utility Input and Control Selected on Qualifications Disadvantages Engineer in Critical Path Higher Cost Technolgy 13

14 Other Variations Engineer Subcontracts with Desired Integrator Contract Allowance for Systems Integration Owner Direct Contract with SI, SI coordinating with General Contractor 40 Summary SCADA Procurement Design-Build is gaining in popularity and usage Design-Bid-Build is still the predominant method Regardless of method used: Evaluate Existing Systems Plan for Migration Develop Implementation Plans Develop firm requirements / specifications Test / Test Again Extensive Training 41 Terry Draper tdraper@ema-inc.com Technolgy 14

Integrated Project Delivery

Integrated Project Delivery 2014 HDR Architecture, 2014 HDR, Inc., all all rights reserved. Integrated Project Delivery It s A New World, And How It Can Benefit Municipal Owners Rich Atoulikian, PMP, PE Rich.Atoulikian@hdrinc.com

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE Risks Associated with Alternative Delivery Methods Managing Expectations Presented by Dan Becker, CCM, PMP, CCE 1 3 Primary Methods for Delivering Projects in WA and OR Design/Bid/Build Design/Build CM

More information

Tampa Bay Water is a wholesale water

Tampa Bay Water is a wholesale water FWRJ Utilizing The Engineer-Procure-Construction Management Procurement Process To Get A Bang Without Going Bust Suzannah Folsom, Jonathan Kennedy, Jerry Russell, and Eric Peters Tampa Bay Water is a wholesale

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY?

ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY? ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY? Gordon Culp Smith Culp Consulting SmithCulp.com INTRODUCTION Are there alternative methods for delivering water and wastewater treatment

More information

PROVING OUR PROFESSIONALISM

PROVING OUR PROFESSIONALISM PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods

More information

1/4/2014. Alternative Project Delivery Methods 1. Agenda

1/4/2014. Alternative Project Delivery Methods 1. Agenda Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia

More information

Fairfax County Government Construction Management At Risk (CMAR)

Fairfax County Government Construction Management At Risk (CMAR) Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits

More information

FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS

FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS Linda Hanifin Bonner, Ph.D., WDBC Mark Halleman, P.E., Parsons Produced by the Water Design-Build Council 1 Key Factors Design-Build-Operate

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

Procurement Guidelines

Procurement Guidelines Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

Steps to a Successful SCADA Upgrade

Steps to a Successful SCADA Upgrade Steps to a Successful SCADA Upgrade Automation Seminar August 24 th, 2017 Deep River Event Center, Greensboro NC Dan McLaughlin Introduction Brief Speaker Bio Hometown: Mentor, OH BEE, Physics & CIS minor:

More information

WORLD BANK. Implementation Support Workshop February 06-10, 2012 Ankara

WORLD BANK. Implementation Support Workshop February 06-10, 2012 Ankara WORLD BANK Implementation Support Workshop February 06-10, 2012 Ankara 1 WORLD BANK Procurement Cycle and Planning PROCUREMENT CYCLE AND PLANNING 3 PROCUREMENT CYCLE CONTRACT PERFORMANCE GENERAL PROCUREMENT

More information

Construction Manager at Risk Delivery Method

Construction Manager at Risk Delivery Method County of Alameda Board of Supervisors Transportation and Planning Committee May 4, 2015 Caroline Judy, Acting Director Construction Manager at Risk Delivery Method Briefing and Discussion Purpose Briefing

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Seattle Public Utilities. Seattle Public Utilities Design-Build. Build-Operate Treatment Facility Projects

Seattle Public Utilities. Seattle Public Utilities Design-Build. Build-Operate Treatment Facility Projects NWCCC Seatac June 27, 2001 Providing water, solid waste, drainage, engineering and customer services Seattle Public Utilities Design-Build Build-Operate Treatment Facility Projects Elizabeth S. Kelly,

More information

A Complete Guide to Instrumentation

A Complete Guide to Instrumentation A Complete Guide to Instrumentation for Non-Instrumentation People 18-DEC-16 This course is Designed, Developed, and will be Delivered under ISO Quality Standards 03-07 December 2017 Dubai, U.A.E. A Complete

More information

Task Order Solicitation (TOS) for Terminal Island Water Reclamation Plant (TIWRP) Control Systems Support. Related Services Area

Task Order Solicitation (TOS) for Terminal Island Water Reclamation Plant (TIWRP) Control Systems Support. Related Services Area Task Order Solicitation (TOS) for Terminal Island Water Reclamation Plant (TIWRP) Control Systems Support Related Services Area TOS No. A3-16-08 Statement of Work 1. Background Terminal Island Water Reclamation

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

DBE/EDGE Contract Development Goal Update

DBE/EDGE Contract Development Goal Update DBE/EDGE Contract Development Goal Update Lyle Flower, Administrator Office of Consultant Services Deborah Green, Administrator Office of Small & Disadvantaged Business Enterprise John R. Kasich, Ohio

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR

PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR Moderator: Praful Kulkarni, AIA President/CEO of gkkworks National Chairman of DBIA Presenters: Geoffrey Neumayr, SE Chief Development Officer

More information

EXHIBIT A STATEMENT OF WORK

EXHIBIT A STATEMENT OF WORK EXHIBIT A STATEMENT OF WORK Contractor Name HP Enterprise Services, LLC Awarded Categories IIA. IIB. IIC. IIIA. IIIB. IIIC. A. OVERVIEW This Statement of Work (SOW) provides an overview of the IT Consulting

More information

Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements

Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements CMAA Presentation April 19, 2017 2014 HDR, Inc., all rights reserved. Introductions Joshua Gliptis, P.E. Howard County Bureau

More information

Integration and Connection Strategies to Maximize the Benefits from Your MES System

Integration and Connection Strategies to Maximize the Benefits from Your MES System Integration and Connection Strategies to Maximize the Benefits from Your MES System Jerry Gonzalez Business Systems Manager B. Braun Medical Inc Baha Korkmaz, PMP. Senior VP Operations North America Baha.Korkmaz@esp.ie

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response

More information

BOROUGH OF BERLIN. Municipal Planning Board Engineer. Term: January 1, 2018 to December 31, 2018.

BOROUGH OF BERLIN. Municipal Planning Board Engineer. Term: January 1, 2018 to December 31, 2018. BOROUGH OF BERLIN REQUEST FOR QUALIFICATIONS FOR MUNICIPAL ATTORNEY, MUNICIPAL AUDITOR, MUNICIPAL BOND COUNSEL, MUNICIPAL ENGINEER, MUNICIPAL WATER & SEWER ENGINEER, MUNICIPAL PROSECUTOR, MUNICIPAL PUBLIC

More information

Rental Property Registration and Crime Free Housing Software. Request for Proposal

Rental Property Registration and Crime Free Housing Software. Request for Proposal Rental Property Registration and Crime Free Housing Software RFP NO.: 13-11 Request for Proposal 19 December 2013 Page 1 TABLE OF CONTENTS Section 1 Introduction...3 General Information...4 RFP Submittal

More information

Operational Excellence in Upstream Oil and Gas

Operational Excellence in Upstream Oil and Gas Operational Excellence in Upstream Oil and Gas What is Operational Excellence? Is a consulting process that benchmarks the automation in your company against Industry Best Practices, for the following

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Resident Engineering Services - Business Model & Success Story

Resident Engineering Services - Business Model & Success Story Slide 1 Resident Engineering Services - Business Model & Success Story Alynn Burk Jamie Koehler Mirko Canel Genentech 2013 Invensys. All Rights Reserved. The names, logos, and taglines identifying the

More information

Quality Control & Integration, Inc.

Quality Control & Integration, Inc. Quality Control & Integration, Inc. Pump Control, Telemetry, SCADA, & Treatment Automation for Municipal and Industrial Water and Wastewater Applications Quality Control & Integration, Inc. 800 6th Street

More information

Common Myths and Best Practices. By Gr e g o r y A. Ga r r e t t

Common Myths and Best Practices. By Gr e g o r y A. Ga r r e t t Common Myths and Best Practices By Gr e g o r y A. Ga r r e t t 16 Contract Management October 2009 Examining 10 common myths and several best practices of risk management can help you apply an effective

More information

VENDOR BACKGROUND QUESTIONNAIRE

VENDOR BACKGROUND QUESTIONNAIRE VENDOR BACKGROUND QUESTIONNAIRE To be completed by Implementer - 1. Name of Company: 2. Company s DNB (D&B) Number: 3. Please state the date your company started in the business of implementing Electronic

More information

Request for Proposal Simulation-Based Learning Competition

Request for Proposal Simulation-Based Learning Competition International Council on Hotel, Restaurant, and Institutional Education February 1, 2018 Request for Proposal Simulation-Based Learning Competition RFP#2018-SIM-101 Your firm is invited to submit a proposal

More information

2012 Honeywell Users Group Americas Sustain.Ability. Ben Comtois Marjorie Ochsner 3rd Party Migration to Experion Sustainable and Flexible Solutions

2012 Honeywell Users Group Americas Sustain.Ability. Ben Comtois Marjorie Ochsner 3rd Party Migration to Experion Sustainable and Flexible Solutions 2012 Honeywell Users Group Americas Sustain.Ability. Ben Comtois Marjorie Ochsner 1 3 rd Party Migration to Experion Sustainable and Flexible Solutions Purpose Thinking about upgrading your DCS legacy

More information

Progressive Design-Build

Progressive Design-Build Progressive Design-Build Progressive Design-Build Design-Build Procured with a Progressive Design & Price A Design-Build Done RightTM Primer 1 Design-Build Progressive Design-build Design-Build Procured

More information

Project Procurement Considerations in This Market. October 14, 2016

Project Procurement Considerations in This Market. October 14, 2016 Project Procurement Considerations in This Market October 14, 2016 Overview Thank you for being here! Introduction About QBS Colorado Project Delivery Methods Market Information Federal & State Information

More information

Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects

Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Presented by: Robyn Minter Smyers Alan S. Ritchie Heather A. Bartzi Erin Luke Presentation Team Robyn Minter Smyers

More information

Continuing Education Credits

Continuing Education Credits Recent Developments in (IPD) for NECA Members October 14, 2013 9:00-9:50 AM Following this session, you will be able to: Explain the concept and structure of an IPD project. Identify the issues and risks

More information

Effective Utility Coordination Practices Using Alternative Contract Methods

Effective Utility Coordination Practices Using Alternative Contract Methods Effective Utility Coordination Practices Using Alternative Contract Methods Douglas D. Gransberg, PhD, PE, DBIA Gransberg & Associates, Inc. Norman, OK 73070-2395 dgransberg@gransberg.com NCHRP 20-07,

More information

Request for Qualifications (RFQ) #HM-R6-RFQ1 2018/2019 Highway Maintenance Agreements Prequalification RESPONSES TO RESPONDENT QUESTIONS SUMMARY #1

Request for Qualifications (RFQ) #HM-R6-RFQ1 2018/2019 Highway Maintenance Agreements Prequalification RESPONSES TO RESPONDENT QUESTIONS SUMMARY #1 RESPONSES TO RESPONDENT QUESTIONS SUMMARY #1 NOMINATED WORK EXAMPLES Question 1.01: When providing Nominated Work Examples, is it permitted for the Respondent Team to use Nominated Work Examples specific

More information

REQUEST FOR PROPOSAL FOR NETWORK/DATA MAINTENANCE AND SUPPORT SERVICES

REQUEST FOR PROPOSAL FOR NETWORK/DATA MAINTENANCE AND SUPPORT SERVICES REQUEST FOR PROPOSAL FOR NETWORK/DATA MAINTENANCE AND SUPPORT SERVICES Issued by: Midway City Corporation 75 North 100 West PO Box 277 Midway, UT 84049-0277 1-435-654-3223 INTRODUCTION Midway City was

More information

FACILITIES CONFERENCE

FACILITIES CONFERENCE FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity

More information

Public-Private Partnerships

Public-Private Partnerships Public-Private Partnerships A Design-Build Done Right TM Primer 1 Public-Private Partnerships Design-Build Public-Private Partnerships A DESIGN-BUILD DONE RIGHT TM PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

Strategic Management and Project Selection

Strategic Management and Project Selection Strategic Management and Project Selection Strategic Management and Project Selection Maturity of Project Management Overview Criteria for PS Models Nature of PS Models Types of PS Models Uncertainty Analysis

More information

SAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop

SAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop SAN DIEGO COMMUNITY COLLEGE DISTRICT SDCCD Design/Build Subcontracting Plan Preparation Workshop April 7, 2015 Welcome Chris Manis Vice Chancellor, Facilities Management Purpose To share information useful

More information

INFRASTRUCTURE ONTARIO VENDOR PERFORMANCE PROGRAM

INFRASTRUCTURE ONTARIO VENDOR PERFORMANCE PROGRAM INFRASTRUCTURE ONTARIO VENDOR PERFORMANCE PROGRAM TABLE OF CONTENTS Preamble... 1 1. Definitions... 1 2. Purpose... 2 3. Evaluation of Vendor Performance... 3 3.1 Vendor Performance Scorecard... 3 3.2

More information

City of Grand Rapids, Michigan. Request for Information # Payment Processing Services. Due Date: June 26, :00 A.M.

City of Grand Rapids, Michigan. Request for Information # Payment Processing Services. Due Date: June 26, :00 A.M. City of Grand Rapids, Michigan Request for Information #946-10-01 Due Date: June 26, 2015 11:00 A.M. Company Name: Company Phone #: Company Fax #: Company Address: WebSite Address Federal Identification

More information

Department of Public Works Division of Engineering. Nassau County, New York

Department of Public Works Division of Engineering. Nassau County, New York TOWN OF OYSTER BAY Department of Public Works Division of Engineering Nassau County, New York REQUEST FOR PROPOSALS FOR CONSULTANT SERVICES SOLICITATION NO. 2017-12 NOTES: 1. ISSUANCE DATE: Thursday, October

More information

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California.

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California. REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES FOR THE SPARTAN COMPLEX SEISMIC UPGRADE PROJECT SAN JOSE STATE UNIVERSITY ONE WASHINGTON SQUARE, SAN JOSE, CA 95192-0010 The Trustees of

More information

Request for Resume (RFR) MHBE IT IDIQ Master Contract All Master Contract Provisions Apply. Section 1 General Information

Request for Resume (RFR) MHBE IT IDIQ Master Contract All Master Contract Provisions Apply. Section 1 General Information Section 1 General Information RFR Number: (Reference BPO Number) Functional Area (Enter One Only) ADPICS Reference BPO number to be entered upon issuance Functional Area Eight IT Quality Assurance Consulting

More information

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013 FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS June 1, 2013 For general guidance the following information is provided as an aid to those preparing submittals in response to Design-Build solicitations.

More information

Role of Procurement / Purchasing Within the Authority

Role of Procurement / Purchasing Within the Authority Role of Procurement / Purchasing Within the Authority What is Purchasing s Role / Why Is Purchasing Important? The Authorized entity within the Water Authority that procures the goods / services required.

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

JOB ORDER CONTRACTING (JOC)

JOB ORDER CONTRACTING (JOC) JOB ORDER CONTRACTING (JOC) A LEAN Best Management Practice for Efficient Construction Project Delivery All product and company names are trademarks or registered trademarks of their respective holders.

More information

UNDERSTANDING FASB STANDARDS FOR CLOUD ACCOUNTING / ERP

UNDERSTANDING FASB STANDARDS FOR CLOUD ACCOUNTING / ERP UNDERSTANDING FASB STANDARDS FOR CLOUD ACCOUNTING / ERP By: Mike Kean Making sense of the accounting and cost management for cloud software systems For many manufacturing and production companies, a recent

More information

Windows Server 2003 migration: Your three-phase action plan to reach the finish line

Windows Server 2003 migration: Your three-phase action plan to reach the finish line WHITE PAPER Windows Server 2003 migration: Your three-phase action plan to reach the finish line Table of contents Executive summary...2 Windows Server 2003 and the big migration question...3 If only migration

More information

Project Delivery Method Selection Workshop

Project Delivery Method Selection Workshop 3 rd Avenue Bridge Rehabilitation, Minneapolis Project Delivery Method Selection Workshop Project Name: SP Project Workshop Date: 5/2/2017 Workshop Location: Water s Edge Room C Facilitator: Kevin Hagness

More information

UPGRADE OR REPLACEMENT INTEGRATED LIBRARY SYSTEMS

UPGRADE OR REPLACEMENT INTEGRATED LIBRARY SYSTEMS UPGRADE OR REPLACEMENT OF INTEGRATED LIBRARY SYSTEMS Copyright January 1988 Revised June 1990 Revised 2002 RMG Information Consultants Pty Ltd RMG Central Office 464 Dandenong Road 333 West North Ave.,

More information

COMPUTERISED SYSTEMS

COMPUTERISED SYSTEMS ANNEX 11 COMPUTERISED SYSTEMS PRINCIPLE This annex applies to all forms of computerised systems used as part of a GMP regulated activities. A computerised system is a set of software and hardware components

More information

Project Delivery Method

Project Delivery Method Project Delivery Method Presenters San Diego Community College District Facilities Management Lance Lareau District Architect UC Berkeley graduate 30 years of architecture experience 2 nd generation architect

More information

Two Parts of our Discussion

Two Parts of our Discussion Two Parts of our Discussion Part One: The basics (what, why, how, when, etc) An overview of process By no means comprehensive (not enough time) Part Two: From the trenches stuff Not contained in statute

More information

Alternative Project Delivery Status Update 2013

Alternative Project Delivery Status Update 2013 Alternative Project Delivery Status Update 2013 Eric Kahlig Division of Construction Management Alternative Project Delivery Innovative Contracting Manual Separate from Division of Innovative Delivery

More information

Invitation to Negotiate

Invitation to Negotiate Invitation to Negotiate Programming, Design, and Consulting Services Lisa Daws 4/3/2012 CLERKS OF COURT OPERATIONS CORPORATION Table of Contents Agency Background... 3 Statement of Purpose... 3 Scope of

More information

SYSTEM MODERNIZATION BEST PRACTICES

SYSTEM MODERNIZATION BEST PRACTICES tl SYSTEM MODERNIZATION BEST PRACTICES SYSTEM MODERNIZATION WORKING GROUP C1 5912-C aamva_systemmodernization_dvd_insert.indd 1 6/7/17 11:01 AM System Modernization Best Practices provides a roadmap to

More information

A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station

A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka, PE Karrie Buxton Jim Salerno Brett Burgett Rich Atoulikian, PMP, PE Cal Rozario, PMP 2014 HDR,

More information

REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION. Submittal Date: April 22, 11:00 AM (PST)

REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION. Submittal Date: April 22, 11:00 AM (PST) REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION Submittal Date: April 22, 2016 @ 11:00 AM (PST) Issued by: Southern California Coastal Water Research Project 3535 Harbor Blvd., Suite 110

More information

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective CMAA National Conference October 13, 2008 Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective Date Presenters Howard W. Ashcraft,

More information

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document

More information

CM AT RISK VS. DESIGN BID BUILD

CM AT RISK VS. DESIGN BID BUILD CM AT RISK VS. DESIGN BID BUILD A TEXAS CASE STUDY ON PROCUREMENT AND IMPLEMENTATION September 28, 2010 Acknowledgement Mike Adams, P.E Executive Director of Engineering and Utilities City of Midlothian

More information

Request for Proposal For: 2018 American Bar Association Temporary Services

Request for Proposal For: 2018 American Bar Association Temporary Services Table of Contents Bid Timetable [2] 1.0 General Bid Information [3] 2.0 Proposal Requirements [5] 3.0 Criteria for Selection [7] 4.0 Specifications and Work Statement [7] Appendix A: Bidder Response Sheet

More information

ADDENDUM NO. 1 TO SOUTHERLY TRUCK SCALE REPLACEMENT DESIGN BUILD PROJECT (TSR-2) RFP FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT AUGUST 13, 2012

ADDENDUM NO. 1 TO SOUTHERLY TRUCK SCALE REPLACEMENT DESIGN BUILD PROJECT (TSR-2) RFP FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT AUGUST 13, 2012 ADDENDUM NO. 1 TO SOUTHERLY TRUCK SCALE REPLACEMENT DESIGN BUILD PROJECT (TSR-2) RFP FOR THE NORTHEAST OHIO REGIONAL SEWER DISTRICT AUGUST 13, 2012 PROPOSALS DUE: 4:30 P.M. (OFFICIAL LOCAL TIME) ON TUESDAY,

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

Qualifications-Based Selection (QBS)

Qualifications-Based Selection (QBS) Qualifications-Based Selection (QBS) QBS refers to a procurement process established by the United States Congress as a part of the Brooks Act (Public Law 92-582; see also 40 USC 1101 et. seq.) and further

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

PLATTE RIVER RECOVERY IMPLEMENTATION PROGRAM REQUEST FOR PROPOSALS

PLATTE RIVER RECOVERY IMPLEMENTATION PROGRAM REQUEST FOR PROPOSALS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 PLATTE RIVER RECOVERY IMPLEMENTATION PROGRAM REQUEST FOR PROPOSALS SUBJECT: P17-025:

More information

Logistics and Material Handling

Logistics and Material Handling Logistics and Material Handling Change how your distribution center operates with a trusted partner. Make the most of your energy SM Fundamentally change how your distribution center operates with expertise

More information

Ethical Issues in Design-Build (Live Webinar)

Ethical Issues in Design-Build (Live Webinar) PDHonline Course R136W (2 PDH) Ethical Issues in Design-Build (Live Webinar) Instructor: J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax,

More information

Internal Construction Management at Michigan State University

Internal Construction Management at Michigan State University Internal Construction Management at Michigan State University MSU Construction Industry Research and Education Center Sp Funding Provided by MSU office of Vice President of Finance and Operations Grant

More information

Control systems Modernizations and upgrades

Control systems Modernizations and upgrades Control systems Modernizations and upgrades www.lahtiprecision.com 1 Lahti Precision is a batch house solution provider YOUR PARTNER IN RAW MATERIALS TECHNOLOGIES For decades, companies all around the

More information

Project Management in the Design and Construction Industry

Project Management in the Design and Construction Industry Project Management in the Design and Construction Industry Design & Construction Institute of Nova Scotia 2011 February 4, 2011 Game Plan Project Management 201 Consultant s Perspective Contractor s Perspective

More information

FGFOA 2017 Focus on the Future

FGFOA 2017 Focus on the Future IT Modernization: Bringing Government from Obsolete to Cutting Edge FGFOA 2017 Focus on the Future Christine Horrocks, CPA/CFF, CGMA Brent Pruim, CPA Topics Covered State of the industry with respect to

More information

Five approved ATCs that reduce project capital costs by an estimated $1.5 million.

Five approved ATCs that reduce project capital costs by an estimated $1.5 million. INTRODUCTION McCarthy Building Companies, Inc. (McCarthy) is one of the nation s leading design-build contractors. For the SH 71 Toll Lanes project, has recruited top tier talent from the transportation

More information

> EXCELLENCE MADE IN ITALY

> EXCELLENCE MADE IN ITALY > EXCELLENCE MADE IN ITALY Founded in 1996, ETA Srl is the natural development of the path of technical and business experiences of the founder starting from the 80 s. Today ETA Srl is a modern, renewed

More information

IBM Bluemix. The following IBM SaaS offerings are covered by these SaaS Specific Offering Terms: IBM Bluemix

IBM Bluemix. The following IBM SaaS offerings are covered by these SaaS Specific Offering Terms: IBM Bluemix IBM Terms of Use SaaS Specific Offering Terms IBM Bluemix The Terms of Use ( ToU ) is composed of this IBM Terms of Use - SaaS Specific Offering Terms ( SaaS Specific Offering Terms ) and a document entitled

More information

Reference report Oil & Gas

Reference report Oil & Gas Distributed generator management with WinCC OA The system integrator DMC, Inc., works extensively with a manufacturer of heat and power cogeneration systems used in a wide variety of industries from oil

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM

Contracting for Architectural and Engineering (A/E) Services Webinar. August 30, AM to 11:30 AM Contracting for Architectural and Engineering (A/E) Services Webinar August 30, 2011 10 AM to 11:30 AM 1 Where We're Going Today Webinar Operation - Fred Ward 5 minutes (+/-) Topic Introduction - John

More information

Design Build. What everyone ought to know about positioning their Design Build Projects for success

Design Build. What everyone ought to know about positioning their Design Build Projects for success Design Build What everyone ought to know about positioning their Design Build Projects for success San Francisco March 7, 2017 CMAA has met the standards and requirements of the Registered Continuing Education

More information

FLOW-X HUMAN MACHINE INTERFACE

FLOW-X HUMAN MACHINE INTERFACE FLOW-X HUMAN MACHINE INTERFACE Enhanced diagnostics & troubleshooting of flow measurements Measurement Data: from Well to Awareness STANDARD AND CUSTOMIZED SOLUTIONS Flow-Xplore is an out-of-the-box Human

More information