Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements
|
|
- Esther Sanders
- 6 years ago
- Views:
Transcription
1 Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements CMAA Presentation April 19, HDR, Inc., all rights reserved.
2 Introductions Joshua Gliptis, P.E. Howard County Bureau of Utilities Project Manager Brian Balchunas, P.E., BCEE HDR Project Manager David Hill, DBIA Clark Construction Construction Executive
3 Agenda Project purpose, background o Existing Treatment Plant and Processes o Master Plan o PER Choosing CMAR Delivery Selection Process CMAR Mechanics and Results o Design Collaboration and Innovation o GMP Development o Collaboration o Project Scope Refined Final Design Current Project Status
4 Project Objective: Design and construct a reliable, cost-effective, and socially responsible treatment facility resulting in beneficial use of LPWRP biosolids in Maryland, for a changing and unpredictable regulatory environment. Little Patuxent WRP Mission Statement: Provide environmentally responsible, reliable and cost effective water reclamation services to Howard County.
5 Project Purpose and Background
6 Existing Little Patuxent WRP
7 Existing LPWRP Solids Process RDP advanced alkaline stabilization process for Class A EQ biosolids (dewatered cake) Primary Clarifiers Centrifuge Dewatering Lime Solids Screening Gravity Thickener Thickened Primary Solids Storage Heat Secondary Clarifiers RDP Process DAF Thickeners Thickened WAS Storage To Land Application
8 2013 Biosolids Master Planning Develop a Biosolids Master Plan that provides a framework for reliable, cost-effective, and socially responsible treatment and beneficial use of LPWRP biosolids in a changing and unpredictable regulatory environment. Evolving regulations for agricultural land application o Winter land application ban o Phosphorus Management Tool More versatile biosolids product desired (i.e., useable in various markets) Biosolids volume reduction Workplace environment challenges with corrosive and dusty lime stabilization process
9 Master Planning Recommendation Replace RDP with anaerobic digestion and heat drying Anaerobic Digestion Dewatering Heat Drying Versatile Class A EQ product, multiple end-uses Volume reduction Relative cost Reliability Manageable process complexity Greatly improved work environment Reduced chemical costs (no lime!) Class A Biosolids
10 2014 Preliminary Engineering Report Bridging Document Solids thickening and storage improvements Digester configuration o Repurpose two existing pretreatment reactors, add third new digester o Risk: Constructabililty issues and site impacts Additional nutrient management o P: Struvite control with chemical addition o N: Centrate treatment - Deammonification o Risk: relatively new technologies and limited vendors Dryer options rotary drum or belt o Belt dryers selected less complex, lower operations and maintenance demands o Risk: relatively new and nearly unprecedented size of units; Site constraints
11 Choosing Delivery by Construction Manager at Risk (CMAR)
12 CMAR Delivery Why Do It? What are the Benefits? Complexity of Project o Maintenance of Plant Operations o Site Constraints o Innovative technology selection and procurement Speed in delivery Manage Risk Eliminate Exhaustive/Defensive Engineering Collaboration o Selection of most qualified team o Selection of key equipment and vendors Price Certainty o Estimates done by Contractor at each milestone o Guaranteed Maximum Price established (GMP) Schedule Certainty
13 Howard County Selection Process
14 Engineer and CMAR Solicitations Both follow Howard County s Quality Based Selection process o Expressions of Interest o Technical Proposals (Top 3-4) o Interviews o Consider Compensation for Proposals and Interviews County develops solicitation for Engineer o Issued summer 2015 o Under contract October, 2015 County and Engineer (acting as Owner s Rep) Develop Solicitation for CMAR o Issued late 2015 o Under contract March 2016 CMAR Contracts o Pre-construction modeled after County s professional services agreements o Construction modeled after County s construction agreements o Incorporated lessons learned from previous CMAR and DB agreements o EJCDC and DBIA reference documents as resources
15 CMAR Delivery Mechanics and Results
16 CMAR Involved from Early Design Stages Review, comment on Preliminary (30%) and Intermediate (60%) design submittals Other CMAR responsibilities o Early procurement of dryer systems and other major equipment items o Value engineering proposals o Constructability reviews o Site utilization plan o Maintenance of plant operations plan o Schedule Key Milestones» October 2018 Start of Phase I Processes» Working backwards leads to Early and On-Time Delivery of Final Design and GMP1 NTP o Procurement plan o Site Specific Safety Plan
17 GMP Development Estimates completed on each design submittal o Final GMP consistent with original 30% estimate Competitive bids for each of the major bid packages Joint interview and review of bidding companies (Owner, Engineer, CMAR) o Risk assessment o Scope verification o Quality o Understanding of delivery process Meet to review Owner Allowances and CMAR Contingencies o Place risk where it is best controlled Negotiated GMP within three weeks of receiving bids NTP for Phase 1 February, 2017
18 Collaborative Approach Workshops o Identifies the key decisions needed o Facilitates decisions for the owner o Opportunity for top and mid level team members to share ideas Partnering o Promotes High Level PM Discussions o Venue for voicing concerns or highlighting positives o Involve key sub-contractors and vendors Value Engineering BIM Outreach Envision
19 Leads to Results Right scope o Digester configuration and construction methods o Phosphorus removal o Equipment selection Tough decisions o Split Substation and MCC locations (PH1 Design Revision) o Relocate dryer building o Improved operations and site utilization
20 From where we started design STREAM BUFFER PLANT EFFLUENT LINE REPLACE SUBSTATION PS-2 CENTRATE EQUALIZATION WAS THICKENING MODS. CENTRATE TREATMENT DIGESTER NO. 1 DIGESTER BUILDING NO. 1 ADMINISTRATION BUILDING ADDITION MODIFIED GARAGE DIGESTER BUILDING NO. 2 DIGESTER NO. 2 DIGESTER NO. 3 DEWATERING AND DRYING BUILDING ODOR CONTROL BIOFILTERS PRODUCT STORAGE AND TRUCK LOADING DIGESTED SOLIDS STORAGE BOILER BUILDING DIGESTER GAS TREATMENT DIGESTER GAS FLARE NO. 2 WETLAND BUFFER
21 through collaboration the process evolved PHASE 1 REPLACE SUBSTATION PS-2 WAS THICKENING MODS. CENTRATE TREATMENT 1 GRAVITY THICKENERS DIGESTER NO. 1 NEW DIGESTER CONTROL BUILDING PHASE 2 PRIMARY SOLIDS SCREENING 2 DIGESTER NO. 2 DIGESTER NO. 3 DEWATERING AND DRYING BUILDING PHOSPHORUS PRECIP. BIOGAS FLARE ODOR CONTROL BIOFILTERS PRODUCT STORAGE AND TRUCK LOADING DIGESTED SOLIDS STORAGE THICKENED SOLIDS STORAGE DIGESTER GAS TREATMENT
22 to where we are today
23 Final Design Finalized digester configuration o Three new digesters for improved performance, operations Phosphorus precipitation for struvite management Deammonification process selection for centrate treatment Belt dryer pre-selection
24 LPWRP Biosolids Improvements Primary Clarifiers Centrifuge Dewatering Solids Screening Gravity Thickener Anaerobic Digesters Phosphorus Precipitation Belt Dryer Secondary Clarifiers Product Storage GBT Thickened Solids Storage (to plant drain) Centrate Treatment Digested Solids Storage To Customer
25 Project Status
26 Project Status and Schedule Phase 1 o NTP February 2017 o Digester construction to begin June 2017 o Digester start-up July 2018 o Remainder of construction through early 2019 Phase 2 o Preliminary Design submittal April 2017 o Intermediate Design submittal July 2017 o GMP Contract Documents September 2017 o GMP negotiations through December 2017 o Construction to mid 2020
Lessons Learned from CM-at-Risk and Design Build Projects at Water and Wastewater Treatment Plants. Lawrence H. Hentz Jr., P.E.
Lessons Learned from CM-at-Risk and Design Build Projects at Water and Wastewater Treatment Plants Lawrence H. Hentz Jr., P.E., BCEE Presentation Outline Background of Two >$110 M Projects Improvements
More informationWhy THP Made Sense for TRA
Why THP Made Sense for TRA June 16, 2016 Central Regional Wastewater System Treatment Plant (CRWS) CRWS Solids Treatment Area 2 162-mgd ADF permitted and 125- mgd average daily flows Pre-THP Solids Process:
More informationSolids Master Plan Briefing June 22, 2017
Solids Master Plan Briefing June 22, 2017 Meeting Agenda Review of Master Plan Process Status Update Technology Selection Budget & Next Steps Discussion Review of Master Plan Process Master Plan Process
More informationES.1 Solids Master Planning Background and Goals
Executive Summary The Arlington County Water Pollution Control Plant (WPCP) treats incoming wastewater flows for residents, businesses, and government agencies in the Arlington County sewer service area
More informationSustainable Struvite Control Using Residual Gas from Digester Gas Cleaning Process
WERF Targeted Collaborative Research (TCR) Sustainable Struvite Control Using Residual Gas from Digester Gas Cleaning Process November 13, 2014 Jing Luo, PhD, PE Manager, Sustainability and Energy Management
More informationComprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1
Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1 1 CH2M *Email: Cameron.Clark@ch2m.com KEYWORDS: biosolids, bioenergy,
More informationAPPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1
APPENDIX A PRELIMINARY TECHNICAL SPECIFICATIONS FOR BIOSOLIDS MANAGEMENT SERVICES JEA Buckman Residuals Management Facility 1. Background JEA is seeking biosolids management services from experienced biosolids
More informationA Battle to Be the Best: A Comparison of Two Powerful Sidestream Treatment Technologies: Post Aerobic Digestion and Anammox
A Battle to Be the Best: A Comparison of Two Powerful Treatment Technologies: Post Aerobic Digestion and Anammox David Oerke/CH2M Tom Johnson/CH2M Bruce Johnson/CH2M Heidi Bauer/CH2M Steve Graziano/CH2M
More informationIrvine Ranch Water District SCAP Energy Committee Meeting IRWD Biosolids Project Update. August 26, 2015
Irvine Ranch Water District SCAP Energy Committee Meeting IRWD Biosolids Project Update August 26, 2015 1 Presentation Agenda Introduction to IRWD IRWD s Biosolids Project Construction Update 2 Introduction
More informationTO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Paul Zimmerman DATE: April 5, 2017 RE: Water Renewal Fund Capital Projects
TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Paul Zimmerman DATE: April 5, 2017 RE: Water Renewal Fund Capital Projects MAJOR PROJECTS, INITIATIVES, CURENT ISSUES Clean Water: Major
More informationWEF Residuals and Biosolids Conference 2017
Reinventing Your Biosolids Management Program and Unlocking Resource Recovery with Thermal Hydrolysis The City of Raleigh s Journey C. Michael Bullard 1, Amy Hanna 1, Greg Knight 2, Kent Lackey 2, Brenan
More informationMasses at Massillon: IFAS for Industrial Loads and Nutrient Removal
OWEA Annual Conference, Sandusky, OH, Wednesday, June 24, 3:00-3:45 PM Masses at Massillon: IFAS for Industrial Loads and Nutrient Removal Kristin Waller, O Brien & Gere Kristin.Waller@obg.com #obgpresents
More informationKenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project
Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project Prepared By: Curt Czarnecki, P.E. Kenosha Water Utility Presented By: Joseph Hughes, P.E. Centrisys Corporation MIWEA June
More informationSustainable Biosolids Management: Direct Energy Use Does Not Tell All
Sustainable Biosolids Management: Direct Energy Use Does Not Tell All Ruth Borgmann, Hazen and Sawyer Erika Bailey, City of Raleigh TJ Lynch, City of Raleigh Stephanie Ishii, Hazen and Sawyer Amy Hanna,
More informationNever Give Up! Strategies for Overcoming Project Delivery Challenges and Roadblocks
Conference: Design-Build for Water/Wastewater Conference 2016 Paper/Presentation Title: Never Give Up! Strategies for Overcoming Project Delivery Challenges and Roadblocks Authors: David Schwartz, CDM
More informationJanuary 25, Utility of the Future One City s Journey
Wastewater Administrators Conference January 25, 2018 Utility of the Future One City s Journey Nathan Cassity, Utility of the Future 2013 Utility of the Future Clean water utilities are undergoing a remarkable
More informationThe TRA CRWS Master Plan. Past, Present, & Future of CRWS. Kaylee Dusek, EIT, Garver Matt Jalbert, PE, TRA
The TRA CRWS Master Plan Past, Present, & Future of CRWS Kaylee Dusek, EIT, Garver Matt Jalbert, PE, TRA TRA operates the largest water resource recovery facility in Texas CRWS N Dallas CRWS currently
More informationTransitioning to a Thermal Drying Program at DWSD. March 3, 2015
Transitioning to a Thermal Drying Program at DWSD March 3, 2015 Presentation Outline Background Project Drivers Thermal Drying Process at DWSD Product Quality Considerations Product Distribution & Marketing
More informationAre You Getting Your Money s Worth?
Are You Getting Your Money s Worth? Dividends of Performance-Based Polymer Procurement Keller Schnier, PE April 2016 Asheville, NC Acknowledgements Maggie Macomber, PE Charlotte Water Jackie Jarrell, PE
More informationEnergy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.
Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service
More informationPROJECT DELIVERY METHODS
Understanding the Construction Contract Project Delivery Methods ISBA April 7,2017 Copyright 2017 by K&L Gates LLP. All rights reserved. Design Bid Build Design Negotiate Build Construction Manager Advisor
More informationUpdate on Biosolids Regulatory & Market Trends. Michael D. Moore HDR Engineering, Inc.
Update on Biosolids Regulatory & Market Trends SARBS 2011 Michael D. Moore HDR Engineering, Inc. September 13, 2011 Agenda 1. Biosolids 101 2. Regulatory Trends 3. Market Trends 4. Perception & Reality
More informationRehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, Jeff Sturdevant Principal Kelvin George Principal
Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, 2017 Jeff Sturdevant Principal Kelvin George Principal Rehoboth Beach Ocean Outfall/CIP Project(s) Update Agenda
More informationWASSTRIP (Waste Activated Sludge. Stripping to Remove Internal. Phosphorus) complements Ostara s. Pearl nutrient recovery process in
WASSTRIP (Waste Activated Sludge Stripping to Remove Internal Phosphorus) complements Ostara s Pearl nutrient recovery process in bio-p plants by releasing magnesium, potassium and phosphate before it
More informationNitrogen and Phosphorus Harvesting and Reuse
October 19, 2017 Nitrogen and Phosphorus Harvesting and Reuse MWEA Sustainable Energy Seminar Agenda What is struvite and why recover it? Technologies for struvite recovery AirPrex piloting case studies
More informationTO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Shawn Wilson DATE: June 30, 2017 RE: Water Renewal Fund Capital Projects
TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Shawn Wilson DATE: June 30, 2017 RE: Water Renewal Fund Capital Projects MAJOR PROJECTS, INITIATIVES, CURENT ISSUES Clean Water: Major Projects
More informationWWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project. Erika L. Bailey, PE, City of Raleigh
WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project Erika L. Bailey, PE, City of Raleigh LNBA / NRCA 2017 Wastewater Treatment Plant Operators Training
More informationEVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION
EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION Jody B. Barksdale, P.E MWH; Juan R. Oquendo, P.E. MWH; Bruce A. Petrik, P.E. - MWH ABSTRACT. The threshold
More informationA -M WRF Solids Alternatives. Joint City Council Meeting
A -M WRF Alternatives Albany -Millersburg Joint City Council Meeting January 18, 2018 Overview Background Selection Criteria Alternatives Analysis Recommendation 1 Background A -M WRF began operating 2009
More informationCodigestion Case Studies Enhancing Energy Recovery From Sludge
Codigestion Case Studies Enhancing Energy Recovery From Sludge Dale Gabel, PE, BCEE MWRD PWO Seminar 1 May 23, 2012 What is Codigestion? Direct addition of high-strength organic wastes to municipal wastewater
More informationOperating Experience with Ostara Struvite Harvesting Process
Operating Experience with Ostara Struvite Harvesting Process Authors: Steve Reusser 1, Alan Grooms 1, Aaron Dose 1, Ahren Britton 2, Ram Prasad 2 1. Madison Metropolitan Sewerage District 2. Ostara Nutrient
More informationSelection, Implementation, Growth and Maturation of a Computerized Maintenance Management System in the Biosolids Industry
Selection, Implementation, Growth and Maturation of a Computerized Maintenance Management System in the Biosolids Industry Ohio Water Environment Association Biosolids Workshop December 7, 2017 Meet Your
More informationExecutive Summary. ES.1 Introduction
Executive Summary ES.1 Introduction The East Central Regional Water Reclamation Facility (ECRWRF) is a 70-mgd conventional activated sludge secondary treatment plant. Portions of the main plant s secondary
More informationRole of Entrant s Firm. »» Final Design»» Completion of Funding. »» Engineering Services During Applications. »» Plant Startup and Filtration
ROLE OF OTHERS For the design focus of the project, key partners included:»» Mortenson Construction, Contractor»» Jacobs, Contract Plant Operator»» Portland Engineering and Controls, I&C The City of The
More informationApplying Extractive Nutrient Recovery for Managing Phosphorus in Sidestreams and Biosolids
Applying Extractive Nutrient Recovery for Managing Phosphorus in Sidestreams and Biosolids Wendell Khunjar PhD, PE May 11, 2017 Embracing the new resource management paradigm Source water Drinking Water
More informationFairfax County Government Construction Management At Risk (CMAR)
Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of
More informationSolids Master Plan Briefing October 27, 2016
Solids Master Plan Briefing October 27, 2016 Meeting Agenda Review of Project/Stakeholder Meeting Role Update on Master Plan: Evaluating Technologies Financial Planning/Budgeting Process Next Steps Questions
More informationCenter Sanitation District
EHLS Center Sanitation District EHLS Engineering Erik Jorgensen Suzanne Givler Heath Anderson Leryn Gorlitsky Outline of Presentation Background Current and Future Conditions Decision Matrix Description
More information4/23/2012. Program development to Preliminary Design level by the Biosolids Program Manager. Thermal hydrolysis/digestion challenges and innovations
Perry Schafer, PE, BCEE, Brown and Caldwell DC Water Biosolids Management Team Program development to Preliminary Design level by the Biosolids Program Manager Thermal hydrolysis/digestion challenges and
More informationBiogas Cogeneration System Sizing and Payback Based on Weekly Patterns of Anaerobic Digestion and Biosolids Dryer Operation
Biogas Cogeneration System Sizing and Payback Based on Weekly Patterns of Anaerobic Digestion and Biosolids Dryer Operation John Kabouris, PhD, PE, CH2M HILL Bob Forbes, PE, CH2M HILL Tim Shea, PhD, PE,
More informationEvaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion
Evaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion Jody B. Barksdale, Juan R. Oquendo, and Bruce A Petrik his article discusses a case study in Florida for
More informationAlternate Project Delivery Experience at UOSA and PWCSA
Alternate Project Delivery Experience at UOSA and PWCSA Bob Angelotti, Director of Technical Services at UOSA Samer Beidas, Director of Engineering and Planning at PWCSA Presented at the VWEA 2015 Education
More informationINTEROFFICE MEMORANDUM
INTEROFFICE MEMORANDUM Date: Dec 3, 2015 To: Boise Public Works Commission From: Paul Zimmerman, Matt Hightree, and Jim Pardy Subject: Directors Report - Sewer Goal: Develop and implement a long-term wastewater
More informationDC Water Class A EQ Biosolids
DC Water Class A EQ Biosolids Bloom Marketing Update July 2nd, 2018 District of Columbia Water and Sewer Authority New Equipment = Marketing Opportunity Thermal Hydrolysis Process 3 Process Schematic Gravity
More informationThermal Hydrolysis Comes to Texas!
Thermal Hydrolysis Comes to Texas! Samir Mathur PE, BCEE CDM Smith Summer Seminar July 25, 2014 Presentation Outline Thermal Hydrolysis fundamentals TRA solids masterplan overview Testing objectives Testing
More informationPresented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division
Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division Project Delivery Methods Design-Bid-Build (DBB) Indefinite Delivery/Indefinite Quantity (ID/IQ) Construction Management at Risk
More informationJanuary 21, Presented by Lynne H. Moss, PE, BCEE
January 21, 2011 Presented by Lynne H. Moss, PE, BCEE Overview CRWS today Planning drivers Planning approach and key elements CRWS plan 2 CRWS Service Area 3 Existing Solids Management Train CRWS Solids
More informationTotal Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015
Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant February 2015 Today s Makeover Will Include Recent History of Blue Plains Solid Handling Processes Evolution
More informationMadison Metropolitan Sewerage District Request for Proposals Chloride Treatment Feasibility Study
Madison Metropolitan Sewerage District Request for Proposals Chloride Treatment Feasibility Study As part of an overall chloride reduction program, the Madison Metropolitan Sewerage District (District)
More informationPresentation Outline
Presentation Outline Nitrification/denitrification refresher Treatment technologies available for nitrification and BNR/ENR What is the problem? BNR/ENR VPDES permitting Causes of reduced BNR performance
More informationSchwing Bioset, Inc. Eric Wanstrom Schwing Bioset, Inc.
Schwing Bioset, Inc Eric Wanstrom Schwing Bioset, Inc. Nutrient (struvite) Recovery In partnership with: Nutrient Recovery Integrated Phosphate Management What are the Issues: Waste water inlet www.schwingbioset.com
More informationChapter 2: Description of Treatment Facilities
2020 Facilities Plan Treatment Report 2.1 Introduction Chapter 2: Description of Treatment Facilities This chapter defines the Milwaukee Metropolitan Sewerage District (MMSD) service area. It also describes
More informationDescription: D05_100_OVW_015_PlantOverview.htm Plant Overview Durham Plant Overview Last Update: October 30, 2013 Purpose:
D05_100_OVW_015_PlantOverview.htm Plant Overview Title: Durham Plant Overview Last Update: October 30, 2013 Purpose: To provide an updated layout of the Durham Advanced Wastewater Treatment Facility while
More informationCM AT RISK VS. DESIGN BID BUILD
CM AT RISK VS. DESIGN BID BUILD A TEXAS CASE STUDY ON PROCUREMENT AND IMPLEMENTATION September 28, 2010 Acknowledgement Mike Adams, P.E Executive Director of Engineering and Utilities City of Midlothian
More informationConducting Successful Energy Audits for Both Water and Wastewater Utilities By: Rich Atoulikian, HDR
2014 HDR Architecture, 2016 2014 HDR, Inc., all rights reserved. Conducting Successful Energy Audits for Both Water and Wastewater Utilities By: Rich Atoulikian, HDR 2016 HDR, Inc., all rights reserved.
More informationCOMMISSION MEETING. April 18, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing
COMMISSION MEETING April 18, 2018 Engineering and Construction Team Piscataway WWTP Bio-Energy Commissioners Status Briefing Item Number: Table of Contents 1. Commission Summary P. 1-2 2. Presentation
More informationWRF Webcast Integrated Treatment Process Management for Drinking Water and Wastewater Treatment Operations
No part of this presentation may be copied, reproduced, or otherwise utilized without permission. WRF Webcast Integrated Treatment Process Management for Drinking Water and Wastewater Treatment Operations
More informationThickening and Dewatering Optimization Matt Van Horne, PE Hazen and Sawyer July 14, 2016
Thickening and Dewatering Optimization Matt Van Horne, PE Hazen and Sawyer July 14, 2016 Agenda Equipment Specific Modifications Chemicals Feeding Cleaning and Maintenance Pretreatment 2 1 Optimization
More informationTampa Bay Water is a wholesale water
FWRJ Utilizing The Engineer-Procure-Construction Management Procurement Process To Get A Bang Without Going Bust Suzannah Folsom, Jonathan Kennedy, Jerry Russell, and Eric Peters Tampa Bay Water is a wholesale
More informationPRODUCT OFFERING BIOSOLIDS MANAGEMENT & RESOURCE RECOVERY GROUP. Interested in smaller sludge volumes & enhanced ph?
MUNICIPAL WASTEWATER BIOSOLIDS MANAGEMENT BIOSOLIDS MANAGEMENT & RESOURCE RECOVERY GROUP Biosolids management costs usually are in 30-60% range for capital as well as O&M expenses for a typical municipal
More informationSolids Dewatering Modernization
Solids Dewatering Modernization Replacing Plate & Frame Press Dewatering with Centrifuge at a Food Production Plant NEWEA Annual Conference, January 25, 2016 Carl Wilcox, P.E., Partner, Woodard & Curran,
More informationPost-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010
Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21
More informationPHOSPHORUS REMOVAL: TREATMENT
PHOSPHORUS REMOVAL: TREATMENT TECHNOLOGIES AND CAPABILITIES Jane Madden, PE, BCEE Senior Vice President CAWPCA Fall Workshop November 14, 2014 Agenda Phosphorus Removal Overview Phosphorus Regulations
More informationCrooked Creek Water Reclamation Facility Improvement Project Construction Package 4 (CP-4) Annual Update #1. Tuesday, May 29, 2018
Crooked Creek Water Reclamation Facility Improvement Project Construction Package 4 (CP-4) Annual Update #1 Tuesday, May 29, 2018 Agenda Facility History Construction Progress Project Update Schedule
More informationSo You ve Removed Your Phosphorus? Now What? JTAC Luncheon April 9 th, 2014
So You ve Removed Your Phosphorus? Now What? JTAC Luncheon April 9 th, 2014 Agenda RWHTF and Upcoming Regulatory Requirements Biological Phosphorus Removal Outcomes Liquid and Solids Stream Interactions
More informationWorkshop on good practices and experience in sludge management
Workshop on good practices and experience in sludge management EU Legal Framework 6 th June 2018, Warsaw A Picture Tells a Thousand Words Sludge Treatment Processes Products Uses Digestion Pre-treatment
More informationApplication of the AGF (Anoxic Gas Flotation) Process
Application of the AGF (Anoxic Gas Flotation) Process Dennis A. Burke Environmental Energy Company, 6007 Hill Road NE, Olympia, WA 98516 USA (E-mail: dennis@makingenergy.com http//www.makingenergy.com)
More informationBio-Recycling North Ranch
Bio-Recycling North Ranch Operation overview The project operates in accordance with WAC 173-308 and is permitted by Ecology. The Facility is located at 820 E. Webb Hill Rd. Union, Washington and is located
More informationCurrent Trends in Biosolids Management & Treatment
35 th Annual Spring Biosolids Symposium Current Trends in Biosolids Management & Treatment March 21, 2017 Stevens Point, WI Jay Kemp, PE, BCEE Black & Veatch Bill Marten, PE, BCEE Donohue & Associates
More informationPWCSA CONSTRUCTION MANAGEMENT AT RISK (CMAR) PROJECT DELIVERY
PWCSA CONSTRUCTION MANAGEMENT AT RISK (CMAR) PROJECT DELIVERY Outline What is the CMAR Delivery Method? What are the statutory requirements? Why use it at PWCSA? What are the different roles of the project
More informationPut your energy. inefficiency to work
The Upper Occoquan Service Authority s engine generator and gas-cleaning system were installed outside to minimize construction costs. Upper Occoquan Service Authority Put your energy inefficiency to work
More informationSometimes Being Faced With A Challenge Can Lead To Greater Opportunities
Sometimes Being Faced With A Challenge Can Lead To Greater Opportunities Making the Case for Energy Savings Performance Contracting at the Opequon Water Reclamation Facility Frederick-Winchester Service
More informationTeam Structures and Project Performance in the Design-Build / Integrated Project Delivery Marketplace. Mark E. Alpert, P.E.
Team Structures and Project Performance in the Design-Build / Integrated Project Delivery Marketplace Mark E. Alpert, P.E., DBIA CH2M HILL Introduction Team Structure Agenda Engineer-lead Integrated design-build
More informationCity of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals
City of Elk River Wastewater Treatment Facility Improvements Achieving Wastewater Treatment Goals By Tejpal Bala, P.E. Bolton & Menk, Inc. The City of Elk River received a new NPDES permit and the existing
More informationPre Submission Meeting Construction Manager at Risk. August 23, 2016
Pre Submission Meeting Construction Manager at Risk August 23, 2016 Health and Safety Hard hats and safety vests are required for today s site tour If you did not bring them, we have extras at the plant
More informationPerformance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility
Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Richard W. Gullick, Ph.D. Director of Operations Timothy Castillo Wastewater Manager Presented to the Albemarle County
More informationDefining the Benefits of Harvesting Phosphorus from Dewatering Filtrate
Defining the Benefits of Harvesting Phosphorus from Dewatering Filtrate Cameron Clark, PE CDM Smith August 1, 2013 Agenda Des Moines WRA Background Plant Nutrient Balance Nutrient Issues P Removal Technology
More informationPinellas County Utilities (PCU) operates
FWRJ Biogas Cogeneration System Sizing and Payback Based on Weekly Patterns of Anaerobic Digestion and Biosolids Dryer Operation John Kabouris, Bob Forbes, Tim Shea, Mike Engelmann, and Jim Delaney Pinellas
More informationSanta Rita Wastewater Treatment Plant Alternative Site Investigation
Santa Rita Wastewater Treatment Plant Alternative Site Investigation Durango City Council Work Session August 11, 2015 Hatch Mott MacDonald Renovate Vs. Relocate BNR Study Cost Summary Site Santa Rita
More informationRichard E. Beardslee City of Battle Creek. Steven L. Wordelman, P.E. Jones & Henry Engineers, Ltd.
Richard E. Beardslee City of Battle Creek Steven L. Wordelman, P.E. Jones & Henry Engineers, Ltd. Past Planning Current Situation Pilot Testing Temporary Approach Future Mid 1970 Mid 1990 2007 Make no
More informationEchoWater Project. Contractor Open House. January 14, Vick Kyotani Program Manager. Sacramento Regional County Sanitation District
EchoWater Project Contractor Open House January 14, 2014 Vick Kyotani Program Manager Agenda Welcome, Introductions and Purpose of the Meeting (Ruben) Overview of EchoWater Project (Vick) Project Details
More informationSCADA System Procurement Alternatives
SCADA System Procurement Alternatives 2017 Automation Committee Seminar August 24, 2017 Terry M. Draper, PE, PMP Discussion Topics SCADA Overview System Hardware / Software Procurement Additional System
More informationConstruction Management at Risk
Construction Management at Risk Implementation and Lessons Learned Virginia Water Environment Association Webinar Janelle Wright Okorie Director, Engineering and Technology Programs 21 October 2015 Alexandria
More information20 Years of Nutrient Removal City of Beloit
20 Years of Nutrient Removal City of Beloit Leon Downing, PhD, PE, & Bill Marten, PE, BCEE Donohue Harry Mathos & Nate Tillis City of Beloit IWEA Nutrient Removal and Recovery Workshop September 12, 2013
More information~~~~ WWTP Master Plan Project
~~~~ WWTP Master Plan Project City Council - April 7, 2014 WWTP History and Issues Constructed in 1994 Aging mechanical equipment - Frequent equipment failures - Resulted in TCEQ permit violations - High
More informationOdor Threshold Emission Factors for Common WWTP Processes
Odor Threshold Emission Factors for Common WWTP Processes Authored by: Michael A. McGinley, P.E. St. Croix Sensory, Inc. And Charles M. McGinley, P.E. St. Croix Sensory, Inc. Presented at Water Environment
More informationAnaerobic Digestion The New Frontier Ohio WEA Biosolids Specialty Workshop 11 December 2014 J. Hunter Long
Anaerobic Digestion The New Frontier Ohio WEA Biosolids Specialty Workshop 11 December 2014 J. Hunter Long Outline Process Basics Digester Component Parts Anaerobic Digester Process Configurations 21 st
More informationAirPrex : Process for Optimization of Biosolids Treatment with the option of Phosphate Recovery
carbon ǀ nitrogen ǀ phosphorus AirPrex : Process for Optimization of Biosolids Treatment with the option of Phosphate Recovery July 2015 Contents Biological Phosphate-Removal Influence of Phosphate on
More informationCommunity Workshop October 17, 2015
Community Workshop October 17, 2015 Goals for Workshop Education for attendees How City builds projects now Why a different method is being pursued for WRF Other workshops (not today) Architecture Treatment
More informationBMP Element 7 Roles and Responsibilities City of Richmond Public Utilities Wastewater Treatment
BMP Element 7 Roles and Responsibilities City of Richmond Public Utilities Wastewater Treatment Date of Last Review 11/10/16 Revision 15 Revised By Biosolids Team Approved By Biosolids Supervisor Revision
More informationTaking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses
Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses December 5, 2013 Matt Van Horne, P.E. 1 1 Agenda Why Sludge Pretreatment? What is OpenCel? Case Study #1: Philadelphia Water Department
More informationStartup of Virginia's Newest Organics Co-Digestion Facility. Dennis Clough, Energy Systems Group George Bevington, Gerhardt, LLC
Startup of Virginia's Newest Organics Co-Digestion Facility Dennis Clough, Energy Systems Group George Bevington, Gerhardt, LLC FWSA the Next 20 Years $14,000,000.00 $12,000,000.00 $10,000,000.00 $8,000,000.00
More informationConstruction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119
Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts
More informationMONTGOMERY STREET. Construction Manager at Risk (CMAR) Services
2 nd PRE-PROPOSAL CONFERENCE March 6, 2015 MONTGOMERY STREET (City Project #02432) Construction Manager at Risk (CMAR) Services PROCUREMENT MARCH 19, 2015 1 Michael Weiss, P.E. City of Fort Worth Project
More informationSmart Management for Small Communities Ellicottville, New York
Smart Management for Small Communities Ellicottville, New York Case Study of Energy Efficient Sustainable Improvements and Technologies Implemented at Wastewater Treatment Plants Presented by: Andrew Casolini
More informationStruvia Technology for Phosphorus Recovery. o Re-Water Braunschweig November 2015
Struvia Technology for Phosphorus Recovery o Re-Water Braunschweig 2.-3. November 2015 1 Resourcing the World o Vision of circular economy o Sous-titre o Waste and Waste Water are resources Veolia Water
More informationNeed-to-Know Criteria Wastewater Treatment Operator Class IV
2017 Need-to-Know Criteria Wastewater Treatment Operator Class IV A Need-to-Know Guide when preparing for the ABC Wastewater Treatment Operator Class IV Certification Exam Before You Dive In What is ABC
More informationAdvanced Aerobic Digestion. ThermAer. Autothermal Thermophilic Aerobic Digestion. Biosolids Treatment. Thermal Process Systems ThermAer Process
8 0 6 0 4 0 Advanced Aerobic Digestion ThermAer Autothermal Thermophilic Aerobic Digestion 2 0 Biosolids Treatment 0 Thermal Process Systems ThermAer Process ThermAer System Aerobic Process High Rate
More informationResource Recovery at Post Point. Turning our waste into valuable resources
Resource Recovery at Post Point Turning our waste into valuable resources July 31, 2017 AGENDA Project Overview Drivers Resource Recovery Summary of Community Feedback Preliminary Evaluation (TBL+) Results
More informationTime to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO
Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from
More information