1 Bane NOR Railway Tender Conference Venjar Langset Project Erik Pascal Johansen
2 Agenda Health, safety & the environment General description of the project Contract strategy Scope of work Main project milestones Organization and project follow-up Bane NOR s expectations to contractors Selected items of the project 2
3 Health, safety and the environment Ambition/Goal: Europe's safest railway Motto: Expect the unexpected and plan for it Strategic Objectives Zero occupational accidents Zero major accidents Zero hazardous exposure to chemicals and noise Optimal waste management and zero discharges Main Actions Compliance and leadership HSE culture, awareness, visible at site Risk and change management and ALARP Efficient and robust emergency preparedness Active experience transfer and learning Improve contract strategy and contractual requirements 3
4 General description of the project Work to be executed while the existing track is in operation Extension from 1 to 2 railway tracks over a 4 km stretch from Venjar to Eidsvoll (to the east of the existing one) Four bridges (Nessa, Kvisldalen, Mork, Ålborgveien) and two new culverts to be build in parallel with the existing ones Soft-soil tunnel at Eidsvoll (Wergeland tunnel) to be build in parallel with the existing one Adjustments of track system at Eidsvoll station 4
5 General description of the project (cont.) Work to be executed while the existing track is in operation Extension of the existing railway track (filling into Vorma) including a new 7,5 km double railway from Eidsvoll to Langset 900 m long railway bridge over Vorma near Minnesund From Venjar to Wergeland tunnel it is planned to reuse the existing power supply infrastructure. Modification of the of existing signal system on the stretch Venjar to Eidsvoll (Siemens) New power supply infrastructure and new signal system (Thales) from Eidsvoll to Langset Several technical buildings, temporary roads and temporary and permanent landfills 5
6 Contract strategy Estimated contract value VEN: 1 2 billion NOK Estimated contract value ENL: 1 1,8 billion NOK The tender process is divided in two steps Request for information as basis for a prequalification Technical/commercial proposal as basis for an evaluation and a contract award NS 8405 adjusted to Bane NOR requirements (Norwegian Building and Civil Engineering Contract) Contact language is Norwegian. Venjar Eidsvoll Langset Preparatory work Detailed engineering Various contracts Contract with AAJ Substructure Rails, power supply, tele, catenary Signal Construction Contract (VEN) Frame Agreement with Thales Construction Contract (ENL) Frame Agreement with Siemens 6
7 Scope of work Experienced and professional organization Timely procurement, well organized FATs, ensure follow-up of subcontractors and vendors Well planned logistics, handling of company provided items Organized construction start-up meetings, good planning, well and safe executed work Good planning and execution of mechanical completion and commission activities Timely delivery of FDV documentation Supply resources during functional testing Procurement Construction Installation Commissioning Assistance to company Construction Contract (VEN) Construction Contract (ENL) 7
8 Main project milestones Activity Date Budget 2018 approval in the Stortinget End 2017 Issue enquiry, Construction Contract (VEN) October/November 2017 Contract award and commencement of the Work, VEN August/September 2018 Issue enquiry, Construction Contract (ENL) December/January 2017/2018 Contract award and commencement of the Work, ENL November/December 2019 Start of operations, VEN Late Autumn 2022 Completion of the Work, VEN Summer 2023 Start of operations, ENL Autumn 2023 Completion of the Work, ENL Mid/End
9 Organization and project follow-up Bane NOR will establish site team(s) at contractor s site(s) in order to obtain efficient and open communication with contractor s personnel throughout all phases of the planning and execution Contractor shall regard this team as a support to their work and utilize these key personnel to achieve a common successful project execution 9
10 Bane NOR s expectations to Contractors HSE Zero harm vision Execute the work in accordance with Bane NOR s Zero harm vision Contractor shall ensure and demonstrate implementation of the highest HSE standards Management systems Contractors shall use a professional management system to plan and execute the work Project control, document management, risk management, change management, design verification etc. Experienced and professional resources Contractor shall provide a project management organization with experienced and competent personnel Contractor shall develop an integrated project organization including main subcontractors Learning organization and continuous improvement Contractor shall document a commitment to continual learning and improvement within own organisation Open dialogue Bane NOR and contractor shall have an open dialog and cooperate on a discipline level 10
11 Selected items of the project - 3D model Extension from 1 to 2 railway tracks over a 4 km stretch from Venjar and Eidsvoll (to the east of the existing one) Four bridges (Nessa, Kvisldalen, Mork, Ålborgveien) and two new culverts to be build in parallel with the existing ones Soft-soil tunnel at Eidsvoll (Wergeland tunnel) to be build in parallel with the existing one Adjustments of track system at Eidsvoll station 900 m long railway bridge over Vorma near Minnesund Extension of the existing railway track (filling into Vorma) including a new 7,5 km double railway track from Eidsvoll to Langset From Venjar to Wergeland tunnel it is planned to reuse the existing power supply infrastructure Modification of the of existing signal system on the stretch Venjar to Eidsvoll (Siemens) New power supply infrastructure and new signal system (Thales) from Eidsvoll to Langset Several technical buildings Temporary roads Temporary and permanent landfills 11
Prosjects on the Main line (Hovedbanen)
Prosjects on the Main line (Hovedbanen) Causal requirement: New basic route model and phasing-in of new trains Turning tracks Stabling siding tracks Railway yards Platform extensions Organisation: Portfolio
More informationJoint Qualification System (JQS) Experience transfer from JQS Verification audits
Joint Qualification System (JQS) Experience transfer from JQS Verification audits JQS Verification System NORSOK S-006 HSE evaluation of contractors Standardized basic HSE requirements to oil and gas suppliers
More informationWe create the railway of the future
We create the railway of the future Helga Nes Executive Vice President Infrastructure Construction Railway Tender Conference 2018 WELCOME! 2 Bane NOR SF A state-owned enterprise We create the Customers
More informationCURRICULUM VITAE. Vordingborg - Denmark (Italy) Italian
CURRICULUM VITAE Name: Profession: Current residence: Date of birth: Tel. e-mail: Nationality: Massimiliano Amoroso Senior Quality and HSE Manager (Civil Engineer) Vordingborg - Denmark 09.02.1976 +39
More informationENGINEERING MANAGEMENT
ENGINEERING MANAGEMENT Identification Selection Definition Execution Develop engineering to sufficient detail to enable a Class 4 or 5 capital estimate to be prepared for the alternative. Use benchmarking,
More information2 ConocoPhillips Health, Safety and Environmental Management System
Section 2 summary 64 2.1 Overview 65 2.2 ConocoPhillips HSEMS Standard 65 2.2.1 Element 1: Policy and leadership 66 2.2.2 Element 2: Risk assessment 66 2.2.3 Element 3: Legal requirements and standards
More informationUpcoming projects. Infrastructure Construction Division
1 Upcoming projects Infrastructure Construction Division 3 About Bane NOR Bane NOR is a state-owned company responsible for the national railway infrastructure. Our mission is to ensure accessible railway
More informationIndustry Briefing Surface and Viaduct Civil Works Contract
Industry Briefing Surface and Viaduct Civil Works Contract 2 North West rail link Introduction The North West Rail Link is one of Australia s largest ever transport infrastructure projects. It is a priority
More informationThe Challenges of Moving from a Project to an Operational Railway. Nigel Ash, Managing Director, Network Rail Consulting
The Challenges of Moving from a Project to an Operational Railway Nigel Ash, Managing Director, Network Rail Consulting 2nd Annual Saudi Arabia, Transport & Infrastructure Conference, April 2015 Contents
More informationHSES-SP Management in Contracts. HSE Prequal Questionnaire for Bidders.
APPENDIX 5 HSES-SP Management in Contracts. HSE Prequal Questionnaire for Bidders. Read before to fill in: 1. The purpose of this Questionnaire is to obtain information on how Health, Safety, Environment
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationGroup Health & Safety. Management System
Group Health & Safety Management System 2010 H ealth and Safety is our first priority. It has been our priority for several years and it will continue to be until it becomes clearly embedded in the culture
More informationMoving from Projects to Operational Rail
Moving from Projects to Operational Rail David Milburn, Technical Head Signalling & Control Systems Network Rail Consulting (NRC) 2nd Annual Middle East Transport Infrastructure Projects 2015, Dubai Contents
More information1. THE PROJECT Introduction to The Project History and status of The Tender for the D&B contract... 3
TABLE OF CONTENTS 1. THE PROJECT... 2 1.1 Introduction to The Project... 2 1.2 History and status of The Tender for the D&B contract... 3 1.3 The Tender documents for the D&B Contract... 3 1.4 Special
More informationHealth & Safety Policy
Health & Safety Policy March 16_rev 1.0 Page 1 H&S Policy Manual Contents 1. INTRODUCTION 2. POLICY STATEMENT 3. OBJECTIVES SHORT TERM OBJECTIVES 4. OVERVIEW OF H&S POLICY SYSTEM FUNCTIONAL PRINCIPLES
More informationSUSTAINABILITY STRATEGY
SUSTAINABILITY STRATEGY Walker Construction (UK) Limited is a UK wide Civil Engineering & Building company We are committed to sustainability. As a company we are involved with an industry where our activities
More informationTerms of Reference and Requirements
Terms of Reference and Requirements A. PROJECT BACKGROUND 1 Shanghai Municipal People s Government has commissioned EXPO as the Project Developer. EXPO s work includes: earth and site-works, detailed design
More informationEnvironmental Management System Manual (EM-01) Revision No. : 2 Date : 1/6/2017. Revision History Sections Affected
ECS GROUNDWORK LTD Management (EM-01) Revision No. : 2 Date : 1/6/2017 Prepared by : Approved by : Stephen Roth (EMR) Martin Reynolds (Managing Director) Revision Date Description Revision History Sections
More informationOHS Management of Contractors in Capital Works and Maintenance
OHS Management of Contractors in Capital Works and Maintenance Physical Resources/Risk, Health and Safety Prepared by: Physical Resources/Risk, Health and Safety Version: 08/04/2008 Contents Page 1. INTRODUCTION...
More informationHealth, Safety, Environment & Sustainability Policy
Health, Safety, Environment & Sustainability Policy Version 4 ERM Power Limited ABN 28 122 259 223 Version 4 0 Contents 1. Health, Safety, Environment & Sustainability Policy... 2 1.1 Our approach to health,
More informationHSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY
HSE INTEGRATED MANAGEMENT SYSTEM MANUAL & QUALITY POLICY Quality, Health, Safety & Environmental Integrated Management System Manual HAZARD : An object, physical effect, or condition with potential to
More informationThe anglo american Safety way. Safety Management System Standards
The anglo american Safety way Safety Management System Standards 2 The Anglo American Safety Way CONTENTS Introduction 04 Anglo American Safety Framework 05 Safety in anglo american 06 Monitoring and review
More informationDesign out. Waste Workshop. A guidance document produced by Network Rail in collaboration with:
Design out Waste Workshop A guidance document produced by Network Rail in collaboration with: Guidance on Designing out Waste: How to run a Design out Waste Workshop This document provides guidance on
More informationBHG Operational Awareness Program May 8, 1998 Configuration Management Revision 0 Page 1 of 11 CONFIGURATION MANAGEMENT
Page 1 of 11 CONFIGURATION MANAGEMENT 1.0 SCOPE This Performance Assessment Guide for Configuration Management will be used to carry out the oversight responsibility of the U.S. Department of Energy (DOE)
More informationAnnex I: Summary of duty holders
The Construction (Design and Management) Regulations 2007: Industry Guidance Annex I: Summary of duty holders Summary of key changes in CDM 2007 Regulations are re-ordered to group duties together by duty
More informationHealth and Safety Management Standards
Management Standards Curtin University Sept 2011 PAGE LEFT INTENTIONALLY BLANK Management Standards Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Documents... 4 2. Management System Model...
More informationClimate mitigation in infrastructure projects. Cecilia Kjellander Birgitta Aava Olsson
Climate mitigation in infrastructure projects Cecilia Kjellander Birgitta Aava Olsson Trafikverket the Swedish Transport Administration Our tasks To be responsible for the long-term planning of the transport
More informationAgenda 9. Date of meeting 21 February 2014 Date of report 4 February Report by Assistant Chief Executive (Operations) 1.
Subway Modernisation: Award of contract for Independent Competent Person for Rolling Stock, Signalling and Control System, Control Room and Associated Equipment Delivery Date of meeting 21 February 2014
More informationTable of contents 1. INTRODUCTION REQUIREMENTS DEFINITIONS ATTACHMENTS REVISIONS REFERENCES...
Page : 1 of 9 Part of: Specification Owner: Approved by: Made by/revised by: Kvaerner Corporate Responsibility SVP HSSE & QM Torill Møklebust Sjur M. Hopland/Torill Møklebust Purpose The objective of this
More informationNorwegian Railway directorate. June 2018 Norwegian tunnel safety conference
Norwegian Railway directorate June 2018 Norwegian tunnel safety conference Our role and mission «The Railway Directorate shall ensure that the railway sector is operated as efficiently, safely and environmentally
More informationCrossrail: The Collaborative Client - Managing Contractor Performance
Crossrail: The Collaborative Client - Managing Contractor Performance Steve Hails MSc CMIOSH AIEMA Health & Safety Director Crossrail What is Crossrail? A new railway for London and the south east 118
More informationBILBAO DECLARATION BUILDING IN SAFETY
BILBAO DECLARATION BUILDING IN SAFETY European Construction Safety Summit Introduction: Construction is one of Europe's largest industries. Unfortunately, it also has the most problematic occupational
More informationNorway-Drammen: Architectural, construction, engineering and inspection services 2017/S Contract notice. Services
1 / 5 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:282369-2017:text:en:html Norway-Drammen: Architectural, construction, engineering and inspection services 2017/S 137-282369 Contract
More informationE-Procurement on large tenders: advantages and disadvantages for European contractors. April 2015
E-Procurement on large tenders: advantages and disadvantages for European contractors April 2015 Agenda Background Tendering truths Advantages of etendering Example of etendering in practice etendering
More informationScope skills for CHS Categories
Scope skills for CHS Categories Required for all categories of registration Different categories have different requirements Stage 1 Stage 2 Stage 3 Stage 4 Stage 5 Stage 6 Initiation Briefing Concept
More informationE6 KVITHAMMAR - ÅSEN TENDER CONFERENCE
E6 KVITHAMMAR - ÅSEN TENDER CONFERENCE Værnes, Radisson Blu Hotel 03.09.2018 AGENDA Nye Veier, E6 Trøndelag Project description (SoW), E6 Kvithammar-Åsen Project execution model Tender documents Prequalification
More informationSwedish Road Administration Stockholm Region
Vägverket 1 Swedish Road Administration Stockholm Region Olle Rosén Vägverket 2 Closer Co-operation Background contracts slides 2-12 FIA report slides 13-32 In practice and results slides 33-42 Vägverket
More informationTool Box Talk Procedure
APPENDIX 4 Tool Box Talk Procedure Purpose Delivery of Effective Tool Box Talks, in which: Supervisors communicate hazards and controls to the work team prior to commencing a task, People discuss and understand
More informationIRPC Operational Excellence Management System
IRPC Operational Excellence Management System 1 Leaderships Message Evolution of OEMS as IRPC s core management system, together with active engagement with our stakeholders through the P-E-O-P-L-E Code
More informationOwner s Representative SCOPE OF SERVICES
Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,
More informationEnergy Institute Framework for High-level Process Safety Management
Energy Institute Framework for High-level Process Safety Management Process Safety Management for Steam & Power Generation Martin W. Ball July 2010 Introduction Purpose of Presentation. Provide an update
More informationHUGHS LIMITADA- SHEQ HSE RESPONSIBILITIES
HSE RESPONSIBILITIES All levels of Management take an active interest in the development and implementation of the Health & Safety and Environmental Management System. Demonstrating Leadership in HSE Participation
More informationServices for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations
Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations Contents Contents... 2 Preface... 3 Issue Record... 3 Assessment
More informationApplication of FIDIC CC for EU- Funded Projects in Bulgaria
Application of FIDIC CC for EU- Funded Projects in Bulgaria Assen Antov Transport Engineer Advisor to the Minister of Regional Development and Public Works EFCA Annual Conference 2016, 02 04 June 2016,
More informationOIL INDIA LIMITED KG BASIN PROJECT KAKINADA GLOBAL EXPRESSION OF INTEREST NO. OIL/KGB/EOI-22
OIL INDIA LIMITED KG BASIN PROJECT KAKINADA GLOBAL EXPRESSION OF INTEREST NO. OIL/KGB/EOI-22 Oil India Limited, KG Basin Project, Door No. 11-4-7, Nookalamma Temple Street, Ramarao Peta, Kakinada-533004,
More informationContractor Selection & Management Guideline Rev01. Revision 00. April 2011
Contractor Selection and Management Guideline Revision 00 April 2011 Document Details and Issue Record Rev No. Details Date Author 00 Draft 10/04/2011 CJMD Checked Text Calcs Approved Document Reference:
More informationNorway-Sandnes: Consultative engineering and construction services 2016/S Contract notice. Services
1 / 5 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:224564-2016:text:en:html Norway-Sandnes: Consultative engineering and construction services 2016/S 125-224564 Contract notice Services
More informationCONTRACTOR PROFILE GUIDE
Date:20/04/2010 Page 1 / 15 CONTRACTOR PROFILE GUIDE APRIL 2010 Date:20/04/2010 Page 2 / 15 VERSIONS Version Author Date Description 1.0 20/04/2010 Contractor profile user guide CONTENTS 1. INTRODUCTION...3
More informationODFJELL DRILLING QHSE PROGRAMS Safety will never be compromised
ODFJELL DRILLING QHSE PROGRAMS 2017 Safety will never be compromised Zero failures and incidents Despite the challenging economic climate, Odfjell Drilling delivered strong QHSE results for 2016. In 2017,
More informationCircular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management THE MINISTRY OF CONSTRUCTION
THE MINISTRY OF CONSTRUCTION Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management Pursuant to the Government s Decree No. 63/2012/ND-CP of August 31, 2012, defining the functions,
More informationDeep Panuke. 01U 12 Mar 08 Issued for Use C. Hewitt N. Coonan D. Riffe R. MacQueen Rev Date Reason for Issue Prepared Checked Checked Approved Title
01U 12 Mar 08 Issued for Use C. Hewitt N. Coonan D. Riffe R. MacQueen Rev Date Reason for Issue Prepared Checked Checked Approved Title EOI SS06 DM EN PQ SS 0006 01U Project Originator Info. Category Disc
More informationThe BEST Framework EDF Group s Expectations for Managing Health and Safety. The EDF Group BEST Framework
Version 1 The BEST Framework EDF Group s Expectations for Managing Health and Safety The EDF Group BEST Framework 2 CONTENTS 1 2 3 4 5 6 7 8 Leadership in Health and Safety 07 Incident Management 09 Contractor
More informationGENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN
Project Procedures GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN 07/28/2011 PAGE 1 OF 7 1.0 PURPOSE 1.1 PURPOSE OF ENGINEERING PROJECT PROCEDURES This P-4 series of Engineering Project Procedures provides
More informationHealth and Safety Toolkit
Health and Safety Toolkit H&S Conception, Design & Planning Checklist This checklist is for use at the outset of a project and should be regularly reviewed as the concept and design phases progress. The
More informationCONSTRUCTION INDUSTRY FORUM FOR NORTHERN IRELAND THURSDAY 7 APRIL 2016
CIFNI (16) P01 CONSTRUCTION INDUSTRY FORUM FOR NORTHERN IRELAND THURSDAY 7 APRIL 2016 Subject: Recommendation: Sustainability requirements and proposals to protect the delivery of BuySocialNI in Government
More informationConstruction Waste Measurement Guide
Draft V6 Last updated: February 2013 Construction Waste Measurement Guide A guide to measuring and reporting waste from construction activities 1 Introduction This document provides guidance on how to
More informationICT challenges in a greenfield hospital project May 2012
Bringing service to life ICT challenges in a greenfield hospital project May 2012 Presented by Peter Nevin Technology & Systems Director Serco Fiona Stanley Hospital Project Agenda Background Fiona Stanley
More informationConstruction Safety Audit Scoring System (ConSASS) Audit Checklist
I 1.1 1 OSH Policy The occupier's management with executive or site responsibility shall define and document its policy for safety including objectives for its commitment to safety. (CP79 - Section 1.2)
More informationSANGUINE TECHNO - COMMERCIAL SOLUTIONS
SANGUINE TECHNO - COMMERCIAL SOLUTIONS Today s Challenges of Infrastructure Industry Developer Holistic feasibility study Optimum engineering management Workable EPC & EPCM concept International quality
More informationHumantech Environmental Management System Manual
Humantech Management System Version 1.0 March 2014 Humantech, Inc. Humantech Management System Revision No.: 1 Date : 03-10-14 Prepared by: Approved by: (EMR) President Revision History Revision Date Description
More informationCrossrail UK. Enabling Quality Asset Information. for maintenance reliability and asset management professionals. oct/nov 14. uptimemagazine.
UPTIME MAGAZINE OCTOBER/NOVEMBER 2014 for maintenance reliability and asset management professionals Crossrail UK Enabling Quality Asset Information uptimemagazine.com AM Asset Management Enabling Quality
More informationRISQS Audit Protocol. Plant Operations Scheme. Document no.: RISQS-AP-004. Plant Operations Scheme
RISQS Audit Protocol Plant Operations Scheme Document no.: RISQS-AP-004 Revision Author Checked by Approved by Date Reason for revision approved 01 Carl Rulton Alan Thomas Richard Sharp 27-02-18 Initial
More informationSupplier Pre-qualification. AEP Southern Operations Melbourne June 2012
Supplier Pre-qualification ICN Presentation Jeff Ward Location Quality and Inspection Services Manager Jeff Ward, Location Quality and Inspection Services Manager AEP Southern Operations Melbourne June
More informationCapital Works Engineer Water and Wastewater. Permanent, full-time. Manager Water and Wastewater. Superannuation Leaseback vehicle
Position Description Position Summary Position Title: Position Status: Reports to: Location: Capital Works Engineer Water and Wastewater Permanent, full-time Manager Water and Wastewater Administration
More informationEast Central College
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationCONTRACTS MANAGER (Civil Engineering) THE COMPANY
THE COMPANY Farrans Construction is a long established UK Civil Engineering and Building company operating in various sectors within the UK. A subsidiary of CRH plc, Farrans Construction have a turnover
More informationCompany QESH Management Representative
PROJECT MANAGEMENT Page: 1 of 8 PROJECT MANAGEMENT ISSUE STATUS Issue Date: 11-04-2016 Issued for Use Revision Date: 05-06-2017 Revision No.: 1 Action Position Issued By: Reviewed By: Reviewed By: Approved
More informationWHS Management Plans
WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the
More informationCorporate Policy and Procedure
Corporate Policy and Procedure POLICY CATEGORY AUTHORITY RELATED POLICIES APPROVED BY Safety Management When Outside Contractors are Retained (Contractor Safety Management Program) (the Policy ) Health
More informationAlbion Water Limited. Environmental Management System Manual
Albion Water Limited Revision No. : 1 Prepared by : Gareth King Approved by : David Knaggs Revision History Revision Date Description Sections Affected Revised By Approved By Table of Content 0.0 Terms
More informationQHSE program.
2016 QHSE program www.odfjelldrilling.com 3 Preface 4 policy 4 HSE policy 4 Environmental principles 5 Security Policy 6 Corporate 7 Mobile Offshore Drilling Units 8 Odfjell Well Services 9 Platform Drilling
More informationQuestions to be responded to by the firm submitting the application
Questions to be responded to by the firm submitting the application Why do you think this project should receive an award? How does it demonstrate: innovation, quality, and professional excellence transparency
More informationCONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationManager Asset Delivery
POSITION DESCRIPTION Manager Asset Delivery 1 POSITION DETAILS Position Title: Reports to: Department: Location: Manager Asset Delivery General Manager Assets Assets Traralgon Date: December 2018 Document
More informationOccupational Health and Safety Management Manual v2.2
Occupational Health and Safety Management Manual v2.2 Written: February 2013 Author: David Seymour, Director of Operations Co Author: Mathew Sprake, Operations Manager Approved: Board of Directors 1. Introduction
More informationAgenda for information meeting October 18, :00-14:30
Agenda for information meeting October 18, 12:00-14:30 Public-Private Partnership, PPP projects in the Norwegian Public Roads Administration (NPRA) The framework for the new PPP projects in the NPRA Bettina
More informationTemporary permanent storage
Temporary permanent storage TWG 2- meeting 2018 The Hague Ragnhild Larsen 21. november 2018 Temporary permanent storage what do we mean? Borderline between transport and storage Article 2 c: shall not
More informationKPI. Continuous Improvement Test (CIT) Measurement. To be measured in line with HSE guidance for calculating the Accident Incident Rate (AIR)
Summary Table Key area of Health and Safety 1.1. Reportable RIDDOR accidents in the hubco members and Tier 1 suppliers' organisations active in the hub territory (business wide AIR). where the number of
More informationAlberta Transportation The City of Edmonton The City of Calgary
Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for
More informationNorth West Rail Link. Achieving Social and Economic Development through Strategic Approaches to Major Project Procurement
North West Rail Link Achieving Social and Economic Development through Strategic Approaches to Major Project Procurement Greater Western Sydney Social Procurement and Economic Development Forum Claire
More informationChapter 13 Management and Monitoring
Chapter 13 Management and Monitoring TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Construction Phase Roles and Responsibilities... 13-1 13.2.1 BP... 13-1 13.2.2
More informationTAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH
TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH Chris Rolison CEO, Comply Serve Limited The Collaborative Systems Engineering Approach Collaboration A system
More informationOperational Integrity / Process Safety : Still Learning. Richard Taylor HSE Manager, Europe Africa
Operational Integrity / Process Safety : Still Learning Richard Taylor HSE Manager, Europe Africa 1 Agenda Why??? The Challenges Operational Integrity Project Reporting Process Safety Incidents Process
More informationDevelopment of expertise: Road maintenance Future competence requirements Summary
Development of expertise: Road maintenance Future competence requirements Summary ViaNova Plan og Trafikk AS December 2009 Task Report Development of expertise: Road maintenance Future competence requirements
More informationFive Star Environmental Audit Specification August 2016
Five Star Environmental Audit Specification August 2016 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page 1 Introduction to the Five Star Audit model 1 2
More informationQHSE Policy. Our licence to operate
QHSE Policy Our licence to operate Contents Service Quality and HSE represent a top priority for us not only because they are vital to the success of our business, but because lives depend on their successful
More informationtrinity ISO 45001:2018 A New Standard for OH&S Management System 4/27/2018
ISO 45001:2018 A New Standard for OH&S Management System Sue Sung, Ph.D., PE Director Global EHS Services trinity 1974 One office - Dallas, Texas Air quality specialty 2018 Over 50 U.S. offices, plus China,
More informationDATA ITEM DESCRIPTION
DATA ITEM DESCRIPTION Title: HUMAN SYSTEMS INTEGRATION PROGRAM PLAN Number: Approval Date: 20070404 AMSC Number: N7716 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:
More informationCriteria for the sustainable procurement of Construction Works
Criteria for the sustainable procurement of Construction Works Version: 1.6 Date: October 2011 Sustainability criteria for Sustainable Public Procurement of Construction Works version 1.6 1 This criteria
More informationSECTION CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationCrossrail Brief to INCOSE Chris Sexton Technical Director
Crossrail Brief to INCOSE Chris Sexton Technical Director 24January 2012 Delivering a world-class affordable railway, safely, and through effective partnerships What is Crossrail? Largest civil engineering
More informationG4: APPROACH TO TRAINING AND EMPLOYMENT
HIGH SPEED TWO INFORMATION PAPER G4: APPROACH TO TRAINING AND EMPLOYMENT This paper outlines the arrangements proposed for training and employment in the relation to the construction and operation of HS2
More informationLevel 6 NVQ Diploma in Construction Contracting Operations Management
Level 6 NVQ Diploma in Construction Contracting Operations Management Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements
More informationKey Elements of a World Class Construction Safety Program
Key Elements of a World Class Construction Safety Program EHS Today Safety Leadership Conference October 28, 2014 Rich Baldwin, CSP Bob Fitzgerald, CHST, CSP Introduction to PCL Founded in 1906 Industrial,
More informationAmendments Any revisions or amendments must be approved by the Project Director before being distributed or implemented.
Details of Revision Amendments Document Control The Project Director is responsible for ensuring that this Plan is reviewed and approved. The Support Services Director is responsible for updating this
More informationOur projects Khursaniyah Gas Plant
Our projects Khursaniyah Gas Plant NGL recovery and sweetening on a world scale A grassroots gas treatment facility built by Technip for Saudi Aramco Khursaniyah Saudi Arabia Jubail Arabian Sea This large
More informationSustainability Plan Colombia
Sustainability Plan 2016 Colombia Legal notice 2 Our vision of corporate responsibility and the preparation of this Plan 3 Stakeholders' expectations and the corresponding actions of the Plan 6 Program
More informationProject Management Consultancy Services. Ensuring safe and successful execution of your projects
Project Management Consultancy Services Ensuring safe and successful execution of your projects Deep expertise in Project Management Consultancy TechnipFMC s Project Management Consultancy business unit
More informationRail Safety Worker Competency Project Update March March 2011 Rail Safety Worker Competency Project 1
Rail Safety Worker Competency Project Update March 2011 22 March 2011 Rail Safety Worker Competency Project 1 ARTC Competency Matrix Update Internally Endorsed: Track and Civil Plant and Equipment Safeworking
More informationGUIDELINES TO REGULATIONS RELATING TO MANAGEMENT IN THE PETROLEUM ACTIVITIES (THE MANAGEMENT REGULATIONS) 1 January (Updated 1 October 2009)
GUIDELINES TO REGULATIONS RELATING TO MANAGEMENT IN THE PETROLEUM ACTIVITIES (THE MANAGEMENT REGULATIONS) 1 January 2002 (Updated 1 October 2009) Petroleum Safety Authority Norway (PSA) Norwegian Pollution
More information