Best Practice Procedures. Construction to Commissioning

Size: px
Start display at page:

Download "Best Practice Procedures. Construction to Commissioning"

Transcription

1 Best Practice Procedures in the transition from Construction to Commissioning Deniz Metin Kaya Director of Construction Operations Foster Wheler Italiana 2012 Foster Wheeler. All rights reserved.

2 Why transition from Construction to Commissioning is so important? Safety environment is complex and difficult to manage Tight schedule: margins are usually eaten up by upstream project phases and little float to cope with unexpected events Major over-laps between various activities Number of participants are quite high compared to other project phases Stakeholders priorities sometimes conflict with each others Require very skilled and experienced personnel

3 What is Mechanical Completion? Construction is completed in accordance with drawings, specifications, vendor instructions, applicable codes and regulations and authority requirements All inspection, checking and testing works are completed System(s) and/or facilities are ready for pre-commissioning and commissioning

4 What is Pre-Commissioning and Commissioning? Non-operating adjustment adjustments and cold alignment checks (such as cleaning, drying and testing without introducing process and auxiliary fluids prior to equipment energization ) Pre-startup, check-out, system adjustment, equipment and system activation activities to prepare system(s) and/or facilities for operation (by introducing auxiliary fluids and with equipment energization)

5 Completion & Turnover Map Project Completion Data Base Engineering g Area Driven Construction Area Driven Construction System Completion System Completion System Completion System Completion System Completion Group of Systems Completion Group of Systems Completion Rea ady for Pla ant Start-up Preparation & Data Validation Measure construction progress Perform inspection i and test requirement Measure progress. Punch-Out & Acceptance Perform (pre) commissioning inspection and test. Measure progress. Punch-Out & Acceptance

6 Road Map for MC by Systems and Handover to Commissioning Pre-Commissioning Construction Commissioning Final TOS Test Punch Initial Walkdown MC Check-out List Pack List Walkdown Punch List TOD Testing

7 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over (Turn Over System)

8 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes

9 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes Punch List Formal inspection and identification of remaining outstanding works

10 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes Punch List Formal inspection and identification of remaining outstanding works Initial Walkdown Identification and closure of all category A punch items

11 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes Punch List Formal inspection and identification of remaining outstanding works Initial Walkdown Identification and closure of all category A punch items Final Walkdown Demonstration and acceptance of a pre-checked system for hand over & Punch List

12 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes Punch List Formal inspection and identification of remaining i outstanding t works Initial Walkdown Identification and closure of all category A punch items Final Walkdown Demonstration and acceptance of a pre-checked system for hand over & Punch List TOD Final dossier including all applicable as-built engineering documents and (Turn Over Dossier) construction certificates as per Inspection & Test Plan attesting the readiness for turn over

13 Construction Completion Milestones TOS Self-contained portion of a facility/system for hand over Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes Punch List Formal inspection and identification of remaining outstanding works Initial Walkdown Identification and closure of all category A punch items Final Walkdown Demonstration and acceptance of a pre-checked system for hand over & Punch List TOD Final dossier including all applicable as-built engineering documents and construction certificates as per ITP attesting the readiness for turn over

14 Breakdown of Systems System Process Systems Standard Systems Sub-Systems Sub-Systems Disciplines Disciplines

15 Typical TOS List BLACK UTILITIES TOS LIST SYSTEM SYSTEM NUMBER RUNNING DESCTRIPTION TOS SUBSYSTEM TOS DESCRIPTION AREA TOS BS BLACK STEAM 10 BAR BASEMENT BASEMENT TOS BS8 001 BLACK STEAM 8 BAR DISTR. BASEMENT BASEMENT TOS BS3 001 BLACK STEAM 3 BAR DISTR. BASEMENT BASEMENT BS10/8/3 010 BLACK STEAM TOS BS3 002 BLACK STEAM 3 BAR DISTR. BULK 1 BULK 1 TOS BS3 003 BLACK STEAM 3 BAR DISTR. BULK 2 BULK 2 TOS BS3 004 BLACK STEAM 3 BAR DISTR. STERILE FILTRATION STERILE FILTRATION TOS BS3 005 BLACK STEAM 3 BAR DISTR. CASA CASA TOS BSC CONDENSATE 10 BAR BASEMENT BASEMENT TOS BSC8 001 CONDENSATE 8 BAR BASEMENT BASEMENT TOS BSC3 001 CONDENSATE 3 BAR BASEMENT BASEMENT BSC10/8/3 011 CONDENSATE TOS BSC3 002 CONDENSATE 3 BAR BULK 1 BULK 1 TOS BSC3 003 CONDENSATE 3 BAR BULK 2 BULK 2 TOS BSC3 004 CONDENSATE 3 STERILE FILTRATION STERILE FILTRATION TOS BSC3 005 CONDENSATE 3 BAR BULK 2 CASA TOS CAI 001 CAI 10 BAR DISTRIBUTION BASEMENT BASEMENT TOS CAI 002 CAI 10 BAR DISTRIBUTION BULK 1 BULK CAI 012 CAI TOS CAI 003 CAI 10BAR DISTRIBUTION BULK 2 BULK 2 TOS CAI 004 CAI 10 BAR DISTRIBUTION CASA CASA TOS CAI 005 CAI 12 BAR GENER. AND DISTR. CASA CASA

16 Test Pack Identification

17 Punching and Walkdown

18 Punch List Management PUNCH LIST RESUMING FOR SUBCONTRACTOR Punch List Register WN LIS-0001 Date 28-apr-12 CONTRACTOR or VENDOR A B C NO GR. TOTAL To Close To Close To Close To Close To Close Closed Hold CONTRACTOR # CONTRACTOR # CONTRACTOR # CONTRACTOR # CONTRACTOR # CONTRACTOR # CONTRACTOR # CONTRACTOR # CONTRACTOR # VENDOR # VENDOR # VENDOR # VENDOR # VENDOR # VENDOR # VENDOR # TOT

19 Punch List by Discipline & Category

20 MC & Turnover Progress

21 Typical Project Statistics Project 1 Project 2 Project 3 Project 4 Systems Units Isometrics 3,400 4,000 22,000 1,500 Test packs 1,000 1,500 7, Inst Tags 3,500 4,200 17,000 5,000 Loop Dossiers ,750 2,000 Check Sheets 60, , , ,000

22 What is needed to administer this Transition Phase Standardised di d preparation for mechanical completion and commissioning i i Maximization of electronic data transfer from engineering and project controls Continuous and auditable progress measurement (physical vs. QC achievements) Management of system-wise completion Structured t and certified handover for all disciplinesi Controlling tool for the creation and management of all QC and MC forms

23 Basis of TAG Assignment At initial phase of engineering, each physical Object of the plant subject to a control: shall be TAG ged shall belong to a family (Object Class) shall be defined in case it does not represent an object (e.g: Hydrotest Circuit, Loop Folder, etc)

24 Typical Project Tree for TAG ging 1st Level Systems Project 2nd Level Sub-Systems 3rd Level Disciplines 4th Level TAGs

25 Assignment of Discipline TAGs Civil: Foundation List Steel Structure List Underground List (Pits, Duct, Sewer, etc.) Building TOS Instrument: Instrument List Cable List Fire & Gas More Engineering Disciplines Piping: Line List ISO List Hydro Test Pack Equipment: Rotating Pressure Vessels Heat Exchanger More TAG s Electrical: Cable List Equipment List Grounding More HVAC: Piping List Cable List Instrument List Equipment List More Equipment List

26 Turnover Vision System System Acceptance Certificate t Sub System INPUT Data Base OUTPUT System Ready for Pre- Commissioning Disciplines TAGs Mechanical Completion Certificate

27 Data Flow & Interfaces Data Base

28 Commissioning Systems Unit Group of Systems Overview Engineering TAG List Construction Areas Plant Area Constr Area Group of Systems Constr Area System System Select Quality Pack Type Select Quality Steps 28

29 Recommendations All stakeholders must be continuously kept up-to-date with the safety requirements of changing site conditions Phased system-wise completion and turnover scheme requires very efficient planning and scheduling The achievement of highest coordination standards between construction and commissioning teams is essential Construction contracts need to be structured with focus and incentives on system turn over and completion The administration of voluminous turnover documentation necessitate the implementation of a structured and tag oriented approach and application of software tools

30 THANK YOU Foster Wheeler. All rights reserved.

Building Foreman s Workface Packages. WFP Conference 2010 Calgary, Alberta December 1, 2010

Building Foreman s Workface Packages. WFP Conference 2010 Calgary, Alberta December 1, 2010 Building Foreman s Workface Packages WFP Conference 2010 Calgary, Alberta December 1, 2010 Introduction to FIWP Planning Plan the Work Release the Work Work the Plan Dedicated Planner Supervisor Materials

More information

M.C.C.S.INTERNATIONAL

M.C.C.S.INTERNATIONAL M.C.C.S.INTERNATIONAL Mechanical Completion and Commissioning Services Ltd. Formed in 1994 To fill a niche market in the area of Mechanical Completion and Commissioning M.C.C.S. Worldwide Ltd. Formed 2000

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Tenth Quarterly Update to the Estimate to Complete August - October Published January 2015 Table of Contents Section 1 - Executive Summary... 3 Section

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Ninth Quarterly Update to the Estimate to Complete May - July 2014 Published October 2014 Table of Contents Section 1 - Executive Summary... 3 Section

More information

Project Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects

Project Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects Project Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects Alan Richard Director Capital Projects Deloitte Transactions and Business Analytics LLP December 3, 2014 How did

More information

The execution of a Complex Project A guided tour

The execution of a Complex Project A guided tour The execution of a Complex Project A guided tour The COMPANY Client The actors The EPC Contractor The suppliers The sub-contractors The phases Sanction Sanction Conceptual evaluation + Pre-Project By COMPANY

More information

University of Delaware

University of Delaware SECTION 22 05 00_COMMON WORK FOR PLUMBING SYSTEM University Contact: Energy & Engineering Group (302) 831-1744 Part 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality

More information

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

University of Delaware

University of Delaware SECTION 23 05 00_COMMON WORK FOR HVAC SYSTEMS University Contact: Energy & Engineering Group (302) 831-1744 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality Control

More information

TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT. Masoud Bajestani WBN 2 Project Vice President

TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT. Masoud Bajestani WBN 2 Project Vice President TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT Masoud Bajestani WBN 2 Project Vice President 1 Project History May 1971- Application for Construction Permits for WBN Unit 1 and 2 requested January

More information

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria 5/1/2018 OC Meeting PJM Manual M36 System Restoration A.1 Critical Black Start Criteria A.1.1 Goal PJM and its stakeholders have developed requirements for the amount and redundancy of Black Start generation

More information

Deliverables list for Projects in the fertilizer industry

Deliverables list for Projects in the fertilizer industry Deliverables list for s in the fertilizer industry Document Development Guidance Department: s / Engineering Revision 1 August 2018 Doc. No: AKH01-GUI-ENG-LST-001 Contents 1. Synopsis... 2 2. Why develop

More information

Enwon (Australia) Pty Ltd

Enwon (Australia) Pty Ltd PROJECT QUALITY MANAGEMENT PLAN Project: Client: QUALITY STATEMENT The Management of Enwon is committed to the delivery of works and services in compliance with quality requirements for all of the company

More information

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section. SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Ensuring Process Safety & Asset Integrity Leveraging Plant Asset Information

Ensuring Process Safety & Asset Integrity Leveraging Plant Asset Information Ensuring Process Safety & Asset Integrity Leveraging Plant Asset Information Adrian Park Vice President, SmartPlant Enterprise Solutions, Intergraph Process, Power & Marine Progressive Safety and Asset

More information

Management System Requirements

Management System Requirements Management System Requirements Identification, Recognition, Application IAEA Technical Meeting Grading of the Application of Management System Requirements Vienna, 23 27 January 2012 RWE Technology GmbH

More information

Overview for a feasibility study

Overview for a feasibility study Overview for a feasibility study What, Why & Objectives of Feasibility Study? International Atomic Energy Agency Nuclear power option included within the national energy strategy MILESTONE 1 Ready to

More information

Leading Indicators and Dashboarding for Advanced Work Packaging. Lloyd Rankin

Leading Indicators and Dashboarding for Advanced Work Packaging. Lloyd Rankin Leading Indicators and Dashboarding for Advanced Work Packaging Lloyd Rankin Slide # AWP KPIs EWP RFI POC PWP CWP IWP 2017-10-24 Slide # 2 POC Defined Path of Construction (POC) Path of Construction is

More information

ENGINEERING SERVICES

ENGINEERING SERVICES ENGINEERING SERVICES www.elb.co.za Fast Moving Consumer Goods ABOUT ELB ENGINEERING SERVICES ELB Engineering Services (ELB) is an internationally recognised technology driven holistic solutions provider

More information

MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 104126-MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator Has 10 years experience in the field of inspection and quality assurance / control related to chemical, petrochemical, power plants

More information

PROCESS & PRODUCTION ENGINEERING DIRECTORY

PROCESS & PRODUCTION ENGINEERING DIRECTORY PROCESS & PRODUCTION ENGINEERING DIRECTORY INDEX 1.0 INTRODUCTION 4 2.0 PROCESS & PRODUCTION ENGINEERING SERVICES 5 2.1 Operating manuals and SOP/POG 5 2.2 Commissioning & start-up procedures 8 2.3 Simulation

More information

ISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan)

ISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan) ISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal

More information

Testing and Balancing, Commissioning, and Operationalizing Systems

Testing and Balancing, Commissioning, and Operationalizing Systems Testing and Balancing, Commissioning, and Operationalizing Systems After construction completion, the focus in a project turns to the commissioning effort. There are many different experiences and definitions

More information

POWER TRANSFORMER INSTALLATION

POWER TRANSFORMER INSTALLATION Project Procedure POWER TRANSFORMER INSTALLATION No.: P-6.2-8-1 07/20/2011 PAGE 1 OF 6 1.0 PURPOSE The purpose of this procedure is to ensure that power transformer installations are accomplished in compliance

More information

PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT

PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT PDG PROJECT DESIGN A00.1 GUIDES PROJECT DESIGN GUIDE A00.1 COMPETENCE STATEMENT AND ASSESSMENT Project Name: Name Project No.: Number Date: Date Document No.: PDG-PDG-PRO-A00.1 Date Created: 30 th Mar

More information

SUPPLIER QUALITY REQUIREMENTS

SUPPLIER QUALITY REQUIREMENTS SUPPLIER QUALITY REQUIREMENTS TABLE OF CONTENTS 1) PURPOSE PG 2 2) KINNEAR PURCHASE ORDER PG 2 3) USE AND COMMUNICATION PG 2 4) SUPPLIER APPROVAL PG 2 5) GENERAL REQUIREMENTS PG 3 SQD Rev 2 2014-08-13

More information

License/ Certification No Oct 8, 1988

License/ Certification No Oct 8, 1988 James Maningas Manalaysay PERSONAL DATA Age: 40 Date of Birth: Apr 23, 1968 Gender: Male Civil Status: Married Height: 160 cm Weight: 130 kg Nationality: Filipino Religion: Christianity - Catholic EDUCATION

More information

details on when MTO s are planned for each discipline? for each MTO what scope is planned to be covered? what the procurement action will be?

details on when MTO s are planned for each discipline? for each MTO what scope is planned to be covered? what the procurement action will be? Project System Audit Material Control Group Note: Not all items of the checklist shall be checked. It depends on the status of the work and whether it is the first, second or third audit. 1. Project Definition

More information

WM2016 Conference, March 6-10, 2016, Phoenix, Arizona, USA

WM2016 Conference, March 6-10, 2016, Phoenix, Arizona, USA Transitioning from Construction to Startup at WTP from a Plant Engineering Perspective 16461 Ryan M. Covert *, Jeffrey R. Markillie *, David I. Green *, Steven P. Churchill *, Roger A. Wahlquist *, Gregory

More information

Frazier Reliability Solutions

Frazier Reliability Solutions Frazier Reliability Solutions Mechanical Integrity Audit Checklist Location: Completed By: Date: MI Program Management Yes No Does the company and/or site have a documented MI policy? Does the MI program

More information

HSE Design Reviews and Action Close-out

HSE Design Reviews and Action Close-out HSE Design Reviews and Action Close-out Simon Round, Manager Design HSE, Amec Foster Wheeler, Shinfield Park, Reading, Berkshire RG2 9FW, UK HSE design reviews and the management and close-out of resulting

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Eleventh Quarterly Update to the Estimate to Complete November - January 2015 Published April 2015 Table of Contents Section 1 - Executive Summary... 3

More information

Selected pages (not a complete plan)

Selected pages (not a complete plan) Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Contact: FirstTimeQuality 410 451 8006 Pat [Pick the date] PROJECT-SPECIFIC

More information

Pressure Piping Construction Requirements QMS written description verification CHECKLIST AB-518b

Pressure Piping Construction Requirements QMS written description verification CHECKLIST AB-518b QMS written description verification CHECKLIST AB-518b Company Name: Company Address: Title of the written description of the management system or manual(s): Person responsible for the overall management

More information

GUIDE TO THE CHANGES IN PMP simpl learn i

GUIDE TO THE CHANGES IN PMP simpl learn i GUIDE TO THE CHANGES IN PMP- 2015 simpl learn i Table of contents Introduction the purpose of this manual 1 New Tasks: Initiating 3 New Tasks: Planning 4 New Tasks: Executing 6 New Tasks: Monitoring and

More information

ISO and Bentley

ISO and Bentley ISO 15926 and Bentley Manoj Dharwadkar, Ph.D. Director, Data Interoperability PCA FORUM 2009 AND MEMBERS MEETING Kuala Lumpur, October 20-21, 2009 Presentation Overview Bentley s portfolio and the interoperability

More information

IT Service Management with ADOit

IT Service Management with ADOit IT Service Management with ADOit - Scenarios, Approaches, Results - Contents 1. Aims and Objectives 2. Conditions and Requirements 3. Approach and Work Packages - 2 - Contents 1. Aims and Objectives 2.

More information

Business Case Our Challenge. Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects

Business Case Our Challenge. Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects Asset lifecycle definition of engineering information to support Operation, Maintenance and Projects Business Case Our Challenge How to move from the current position of; Intelligent schematics (P&ID s)

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Halliburton. All rights reserved. Flange Integrity Management

Halliburton. All rights reserved. Flange Integrity Management Flange Integrity Management Flange Integrity Management Why? North America Pressure Vessel Research Council found that each process facility in North America experienced 180 leaks per year, six of which

More information

CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROCEDURES (Revised 8/05)

CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROCEDURES (Revised 8/05) CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROCEDURES (Revised 8/05) 29CFR1910.147 Purpose Scope This policy establishes the requirements for energy control procedures, employee training and periodic inspections

More information

CMI Guidance Document

CMI Guidance Document CMI Guidance Document for Product Quality Plan Requirements Reference CMI-GD-PQP This document has been produced by the Administration Department of CertMark International (CMI). For technical information

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly

More information

ISO 9001:2015Certified

ISO 9001:2015Certified ISO 9001:2015Certified Introduction MCCS commenced business in 1993 as a small UK based Mechanical Completion and Commissioning company working mainly in the North Sea and Southern Europe on various projects

More information

PASS4TEST IT 인증시험덤프전문사이트

PASS4TEST IT 인증시험덤프전문사이트 PASS4TEST IT 인증시험덤프전문사이트 http://www.pass4test.net 일년동안무료업데이트 Exam : ISO20KF Title : ISO / IEC 20000 Foundation Vendors : EXIN Version : DEMO Get Latest & Valid ISO20KF Exam's Question and Answers from

More information

{CLIENT SITE} {CLIENT COMPANY}

{CLIENT SITE} {CLIENT COMPANY} https://www.industrydocs.org/maintprocs.html {CLIENT SITE} {CLIENT COMPANY} {Client Company} Author: {Author} 1701 Everyman Road Original Approved By: PSM Coordinator Anytown, USA 12345 Original Date Issued:

More information

Project Procedure 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /19/2011 PAGE 1 OF 4 FACILITY LIGHTING SYSTEMS INSTALLATION

Project Procedure 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /19/2011 PAGE 1 OF 4 FACILITY LIGHTING SYSTEMS INSTALLATION Project Procedure 07/19/2011 PAGE 1 OF 4 1.0 PURPOSE The purpose of this procedure is to ensure that facility lighting system installations are accomplished in compliance with Project specifications, applicable

More information

Construction Contract Workflow

Construction Contract Workflow Awarded CSA [R, U] Completed Setup Activities. contract, click on the "Contract details" dashboard. record, click on "edit" button the "Complete Setup" button is enabled, click on it. The system goes through

More information

SUPPLIER QUALITY CODES

SUPPLIER QUALITY CODES Supplier Quality s D07-00125 Rev A APPROVALS NAME AND TITLE SIGNATURE DATE M.G. Blankenship Senior Director, Operations I. Jimenez Materials Manager D07-00125-02 Page 1 of 5 SQC 1 SQC 2 SQC 3 SQC 4 SQC

More information

QSS 0 Products and Services without Bespoke Contracts.

QSS 0 Products and Services without Bespoke Contracts. QSS 0 Products and Services without Bespoke Contracts. Use: Typically Sub 50k processes without a bespoke contract. Amendment History Version Date Status V3 June 2018 Updated for 2018 deployment Contents

More information

Energy Institute Framework for High-level Process Safety Management

Energy Institute Framework for High-level Process Safety Management Energy Institute Framework for High-level Process Safety Management Process Safety Management for Steam & Power Generation Martin W. Ball July 2010 Introduction Purpose of Presentation. Provide an update

More information

Contract Quality Requirements Manual SLM Issue 3

Contract Quality Requirements Manual SLM Issue 3 Contract Quality Requirements Manual SLM 4.06.02 Issue 3 20 th October 2015 Gary Rushforth Supply Chain Quality Sellafield Ltd Introduction Sellafield Ltd (SL) aims to deliver excellence in everything

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

0100 GENERAL 0200 PROJECT MANAGEMENT

0100 GENERAL 0200 PROJECT MANAGEMENT TEXAS DEPARTMENT OF TRANSPORTATION 0100 GENERAL 0101 General requirements A. Maintenance Contractor shall be responsible for and shall carry out Maintenance Services for the Maintained Elements set forth

More information

Project Pr Health Checks Check and and Audits Week 8

Project Pr Health Checks Check and and Audits Week 8 Project Health Checks and Audits Week 8 Last Week Project Monitoring and Control Assignment Review This Week What is a Project Audit Purpose of Audits Types of Audits Project Management Processes Audit

More information

GLOBAL ENERGY FORUM. Managing Large EPC Projects with Data at Your Fingertips. Maurice Tayeh. February 20 th, 2014 Houston, Texas

GLOBAL ENERGY FORUM. Managing Large EPC Projects with Data at Your Fingertips. Maurice Tayeh. February 20 th, 2014 Houston, Texas GLOBAL ENERGY FORUM Managing Large EPC Projects with Data at Your Fingertips Maurice Tayeh February 20 th, 2014 Houston, Texas Global Capabilities and Expertise McDermott is a leading engineering, procurement,

More information

Terms of Reference and Requirements

Terms of Reference and Requirements Terms of Reference and Requirements A. PROJECT BACKGROUND 1 Shanghai Municipal People s Government has commissioned EXPO as the Project Developer. EXPO s work includes: earth and site-works, detailed design

More information

NEW GC-16 IN WEST KUWAIT MATERIAL REQUISITION FOR LEVEL GAUGE TABLE OF CONTENTS

NEW GC-16 IN WEST KUWAIT MATERIAL REQUISITION FOR LEVEL GAUGE TABLE OF CONTENTS TABLE OF CONTENTS Sh. 2 of 16 1 INTRODUCTION 4 1.1 Purpose 4 1.2 Definitions 4 1.3 Acronyms 4 1.4 Codes and Standard 5 1.5 Environmental Condition 6 1.6 Language 6 1.7 Units of Measurement 7 1.8 General

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

Low Voltage Switchgear Construction Checklist (under 500 kva)

Low Voltage Switchgear Construction Checklist (under 500 kva) Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

Our Contribution to the Forum

Our Contribution to the Forum Our Contribution to the Forum General presentation of the EPR TM Reactor CR1.1.1 Robustness PART 1 Margins - Simplicity PART 2 Quality of design and construction Quality of materials Redundancy PART 3

More information

Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan)

Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan) Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact:

More information

Project Execution Plan

Project Execution Plan Gulf Integrated Group Project Execution Plan P. O. Box: 19002, Doha Qatar Tel: +974-4582289/90/91 Fax: +974-4687886 COMMITTED TO QUALITY SECTION 1 1.0 INTRODUCTION Gulf Integrated Group (GIG) is pleased

More information

USACE NAVFAC Design Sample QA/QC Plan

USACE NAVFAC Design Sample QA/QC Plan USACE NAVFAC Design Sample QA/QC Plan 20 selected pages (out of ) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: First Time Quality 410 451 8006 Pat [Pick

More information

Internal Audit Report. Mica Kootenay Microwave Project. December 20, To:

Internal Audit Report. Mica Kootenay Microwave Project. December 20, To: December 20, 2001 To: R.J. Threlkeld G.S. Smyrl D.C. Bryson J.J. Haley P.L. Shtokalko G.N. Sherlock D.A. Harrison L.I. Bell M. Costello Audit and Risk Management Committee AU0209TD Audit Services Internal

More information

J.A. LOMBARDO & ASSOCIATES, INC. CONSULTING ENGINEERS

J.A. LOMBARDO & ASSOCIATES, INC. CONSULTING ENGINEERS J.A. LOMBARDO & ASSOCIATES, INC. CONSULTING ENGINEERS C SD J.A. Lombardo & Associates is a full-service multi-disciplined consulting engineering firm founded in 1979. We specialize in comprehensive electrical,

More information

Fire Protection Contractor QA/QC Plan Sample

Fire Protection Contractor QA/QC Plan Sample Fire Protection Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Fire Protection Standards & Inspection Forms Contact: Ed

More information

Citi Institutional Clients Group - Business Continuity Management

Citi Institutional Clients Group - Business Continuity Management Citi Institutional Clients Group - Business Continuity Management Enterprise Risk Management Establishing a Risk Control-based Continuity Program, CBCP, CBCP Senior Vice President, Citi Institutional Clients

More information

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS 1 33 63 00 - Underground Steam and Condensate Distribution System 1. Introduction A. Steam is distributed to University and Medical Center buildings through an underground piping system year-round at a

More information

OWNER USER INTEGRITY MANAGEMENT SYSTEM WRITTEN DESCRIPTION CHECKLIST AB-512(b)

OWNER USER INTEGRITY MANAGEMENT SYSTEM WRITTEN DESCRIPTION CHECKLIST AB-512(b) Company Name: Written Description of QMS Title and Rev. Status: Person who is responsible for preparing the owner s QMS written description: Name: Title: Telephone No.: ( ) Fax No.: ( ) Cell No.: ( ) E-Mail:

More information

150/ G Versus 150/ H Contractor Quality Control Program

150/ G Versus 150/ H Contractor Quality Control Program AC 150/5370-10G AC 150/5370-10H 1 Part 1 of General Provisions Part 2 of General Construction Items 2 Section 100 Item C-100 3 Quality Control Program (CQCP) 4 100-01 General. When the specification requires

More information

VALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY

VALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY VALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY Oren Levin, Diane Gordon VisionCare Ophthalmic Technologies, POB 3879, Petah Tikva 49130,

More information

SECTION HVAC AIR CLEANING DEVICES

SECTION HVAC AIR CLEANING DEVICES SECTION 23 40 00 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

SPI SPEL SP-P&ID USING SMARTPLANT FOUNDATION

SPI SPEL SP-P&ID USING SMARTPLANT FOUNDATION REPLACE GREY BOX WITH COMPANY LOGO. EDIT THIS IN THE SLIDE MASTER. SPI SPEL SP-P&ID USING SMARTPLANT FOUNDATION John Dressel, FLUOR Applications Specialist FOOTER: EDIT THIS AND THE DATE IN THE MASTER

More information

Strategic Issues Workshop Improving Brownfield Projects

Strategic Issues Workshop Improving Brownfield Projects 1 Strategic Issues Workshop Improving Brownfield Projects Warren Kennedy Burns & McDonnell Hunter Mayo Independent Project Analysis Pete Luan Pete Luan & Associates David Holland Amec Foster Wheeler Scott

More information

1. Project Definition

1. Project Definition Project System Audit Electrical Group Note: Not all items of the checklist shall be checked. It depends on the status of the work and whether it is the first, second or third audit. = EH&S related question

More information

A Compilation of WHO GMP Audit Points

A Compilation of WHO GMP Audit Points A Compilation of WHO GMP Audit Points Collected from WHOPIR of 28 companies Part III of VIII Current article Part III Production Prepared and Submitted By: Edited by : A. Jwalakanth B.Pharm, MBA (Aus)

More information

Microgeneration Installation Standard: MIS 3003

Microgeneration Installation Standard: MIS 3003 Microgeneration Installation Standard: MIS 3003 REQUIREMENTS FOR CONTRACTORS UNDERTAKING THE SUPPLY, DESIGN, INSTALLATION, SET TO WORK COMMISSIONING AND HANDOVER OF MICRO AND SMALL WIND TURBINE SYSTEMS

More information

Quality management systems

Quality management systems L E C T U R E 9 Quality management systems LECTURE 9 - OVERVIEW Quality management system based on ISO 9000 WHAT IS QMS (QUALITY MANAGEMENT SYSTEM) Goal: Meet customer needs Quality management system includes

More information

Your industrial operations, maintenance and services solutions

Your industrial operations, maintenance and services solutions Your industrial operations, maintenance and services solutions Health and Safety Zero Harm is embedded in our culture and is fundamental to our future success. We are committed to achieving our goal of

More information

RURAL ELECTRIFICATION AGENCY ENERGY FOR RURAL TRANSFORMATION PHASE III. Credit No.: 5653, Project ID.: P133312

RURAL ELECTRIFICATION AGENCY ENERGY FOR RURAL TRANSFORMATION PHASE III. Credit No.: 5653, Project ID.: P133312 RURAL ELECTRIFICATION AGENCY ENERGY FOR RURAL TRANSFORMATION PHASE III Credit No.: 5653, Project ID.: P133312 Procurement Reference No.: REA-ERTIII/SRVCS/17-18/00007 Terms of Reference for Senior Project

More information

EVERYTHING CAN BE IMPROVED.

EVERYTHING CAN BE IMPROVED. EVERYTHING AN BE IMPROVED.. W. BARRON IV - 1 PRODUT/SERVIE REQUIREMENTS/INTERNAL DESIGN REVIEWS III.A.1 Supplier Selection Supplier Selection is presented in the following topic areas: Product/Service

More information

AESOP 15604; ISSUE 2; STATUS PENDING APPROVAL; AUTHORITY CARL BLAZIK This document is the property of NSF ISR. Page 1 of 9

AESOP 15604; ISSUE 2; STATUS PENDING APPROVAL; AUTHORITY CARL BLAZIK This document is the property of NSF ISR. Page 1 of 9 This document is the property of NSF ISR. Page 1 of 9 ISO 9001 Quality Management Systems registration provides a set of uniform requirements for a quality management system. A number of quality management

More information

LOCKOUT TAGOUT STILL CRAZY AFTER ALL THESE YEARS?

LOCKOUT TAGOUT STILL CRAZY AFTER ALL THESE YEARS? LOCKOUT TAGOUT STILL CRAZY AFTER ALL THESE YEARS? Mark Haskins, CSP Practical Safety Solutions, LLC CBIA Safety & Health Conference May 23, 2018 WHY IS LOCKOUT TAGOUT IMPORTANT? OSHA estimates 50,000 injuries

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

Vendor Qualification Survey

Vendor Qualification Survey 1200 West 96 th St Minneapolis, MN 55431 Ph: 952-888-7900 Fax: 952-888-2719 Vendor Qualification Survey Vendor Information Company Name: Date: Address: City: Phone Number: email address: Product or Service

More information

International Association of Certified Practicing Engineers

International Association of Certified Practicing Engineers www.iacpe.com Knowledge, Certification, Networking Page: 1 71 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International is providing the introduction to the Training Module for your

More information

IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING

IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Page 1 / 11 Ver. 1.3 MANAGEMENT SPECIFICATION FOR THE IN-PILE CREEP RELAXATION AND POST-IRRADIATION THERMAL CREEP TESTING Abstract This document specifies the management requirements: the Supplier shall

More information

Peer Reviewer (Same as team members - see section 2.1)

Peer Reviewer (Same as team members - see section 2.1) MSC - Marine Stewardship Council Consultation Document: Audit Personnel Competencies Consultation Dates: 1 st April-3 rd May, 2011 MSC Contact: Graham Bruford FOR CONSULTATION Introduction Competency is

More information

An Example Of An Effective Lockout-Tagout Procedure

An Example Of An Effective Lockout-Tagout Procedure An Example Of An Effective Lockout-Tagout Procedure Lockout-tagout (LOTO) or lock and tag is a safety procedure which is used in industry and research settings to ensure that dangerous machines are properly

More information

INTRODUCTION TO QUALITY ASSURANCE

INTRODUCTION TO QUALITY ASSURANCE INTRODUCTION TO QUALITY ASSURANCE Basic Quality Terminology No more definitions...please! Page 1 Quality is the degree to which a specific product conforms to a design or specification H.L. Gilmore Product

More information

Audit of Weighing Services. Audit and Evaluation Services Final Report Canadian Grain Commission

Audit of Weighing Services. Audit and Evaluation Services Final Report Canadian Grain Commission Audit and Evaluation Services Final Report Canadian Grain Commission November 2016 Table of Contents 1. EXECUTIVE SUMMARY... 2 Conclusion... 2 Statement of Assurance... 2 2. INTRODUCTION... 3 Authority

More information

Communications Contractor QA/QC Plan Sample

Communications Contractor QA/QC Plan Sample Communications Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Communications Standards & Inspection Forms Contact: Ed Caldeira

More information

Essential Duties (Roles and Responsibilities)

Essential Duties (Roles and Responsibilities) WorkFace Planner Document Number: COP-WFP-JBI-02-2013-v1 WorkFace Planner Sample Job Description WorkFace Planner Construction Superintendent Prepared by: The WorkFace Planner is responsible for the conversion

More information

Richland County School District One. Lockout & Tagout Program (29 CFR PART )

Richland County School District One. Lockout & Tagout Program (29 CFR PART ) Richland County School District One Lockout & Tagout Program (29 CFR PART 1910.147) Hazardous Energy Control Program for Richland County School District One Purpose The purpose of this and other safety

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT AND MANAGER that offers comprehensive management throughout the project, from concept to completion, yielding the greatest possible benefit to the owner. IPS will offer uncolored

More information

Absolute Energy Raters Commissioning Plan Outline Template

Absolute Energy Raters Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither

More information