1 PROJECT EXECUTION STRATEGIES OVERVIEW UpTech Upstream Oil & Gas Summit Designing And Building Success

2 AGENDA Industry Situation Traditional Project Stage Progression Project Schedule Compression Contracting Strategies and Tools to Achieve Project Success

3 Current Industry Situation Need for faster projects Cost and schedule overruns Mistrust Rigid gated procedures How can we develop systems for selecting the right execution strategy to satisfy project expectations?

4 How do we improve our project execution strategy selection? Need to understand: 1. Where are we? 2. Where do we want to end up? 3. Options available to get us there 4. Factors to consider (risk and benefits) Our goal is to help our customers be more successful.

5 Project Considerations Quality Scope/Safety Budget Schedule

6 Project Timeline Regular Project Schedule Tender & Procurement Long Lead Tender & Procurement Materials Concept FEL 1 Class 5 FEL 2 Class 4 FEED Class 3 Detailed Design Tender Construction Construction Commissioning & Start-up Project Sanction Kickoff Completion

7 Project Timeline Accelerated Project Schedule Tender Construction Concept FEL 1 FEL 2 FEED Detailed Design Tender & Procurement Long Lead Construction Tender & Procurement Materials Commissioning & Start-up Acceleration Kickoff Project Sanction Completion

8 Project Timeline Compressed Project Schedule Tender Construction Concept FEL 1 FEL 2 Feed Scope Change Feed Update Approval Delay Detailed Design Construction Commissioning & Start-Up Tender & Procurement Long Lead Tender & Procurement Materials Compression Kickoff Regular Project Sanction Project Sanction Completion

9 Project Timeline Accelerated Crash Project Procurement Long Lead Procurement Materials NO TENDER Concept FEL 1 FEL 2 FEED Construction Commissioning & Start-up Acceleration Detailed Design Project Sanction Kickoff Completion

10 Project Timeline Compressed Crash Project Procurement Long Lead Procurement Materials NO TENDER Conce pt FEL 1 FEL 2 Feed Scope Change Feed Update Scope Change 2 Feed Update Approval Delay Detailed Design Commissioning & Start-up Construction Compression Regular Project Sanction Project Sanction Kickoff Completion

11 Project Components Engineering Procurement Construction

12 Engineering Engineering Contractual Basis Lump sum Reimbursable target Fee as % of capital Reimbursable

13 ENGINEERING Engineering Contractual Terms - Based on Scope Definition

14 PROCUREMENT There are many systems that are used for procurement of equipment, material and services. Owner direct purchasing As agent on behalf of customer Zero dollar account Consultant/Contractor as part of contract

15 PROCUREMENT Once the procedure for procurement is selected, the way things get purchased can fit into different methods based on schedule constraints. Lump sum tender and bid evaluation Supplier cost plus fee Time and material at agreed shop rates Purchase stock items Purchase used items Use customer stock or used items

16 Construction Construction Contracting Strategies Tendered lump sum Tendered unit prices Cost plus fixed fee Cost plus % fee Force account

17 CONSTRUCTION Construction Plan Based on Design Maturity

18 CONSTRUCTION Construction Contracting Strategies - Based on CM Capabilities

19 Integrated Projects Lump Sum Tendered with bid evaluation, FEED as part of tender process Tendered with bid evaluation, FEED done prior to tender Cost plus fixed fee Cost plus fee as % of capital Reimbursable Project Execution Strategies / May 15, 2014

20 INTEGRATED PROJECT APPROACH Integrated Contracting Strategy - Based on Scope Definition Project Execution Strategies / May 15, 2014

21 The Keys To Project Success Assemble the right team for the project Forward planning - develop strategy early Understanding risks and benefits of each strategy Ability to recognize when to/and how to adjust strategy as project proceeds

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

Corporate Performance Briefing and Management Policy for FY2008

Corporate Performance Briefing and Management Policy for FY2008 Corporate Performance Briefing and Management Policy for FY2008 Global Toyo for Client Value Enhancement May 14, 2008 Yutaka Yamada President & CEO Contents 2008 1. Looking Back FY2007: Mid-term Plan Achieved

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

PROJECT DELIVERY METHODS

PROJECT DELIVERY METHODS Understanding the Construction Contract Project Delivery Methods ISBA April 7,2017 Copyright 2017 by K&L Gates LLP. All rights reserved. Design Bid Build Design Negotiate Build Construction Manager Advisor

More information

Owner s Representative/Owner Team Roles, Obligations and Responsibilities

Owner s Representative/Owner Team Roles, Obligations and Responsibilities Page1 Achieving Excellence in Capital Projects Delivery Owner s Representative/Owner Team Roles, Obligations and Responsibilities By George E. Baram P.Eng., M.Sc., PMP, CCE, Fellow AACE International The

More information

Request for tenders: Baseline Assessment of Scrap Metal Recycling in Samoa and Drafting of the Regional Scrap Metal Strategy

Request for tenders: Baseline Assessment of Scrap Metal Recycling in Samoa and Drafting of the Regional Scrap Metal Strategy PO Box 240, Apia, Samoa E: sprep@sprep.org T: +685 21929 F: +685 20231 W: www.sprep.org The Pacific environment, sustaining our livelihoods and natural heritage in harmony with our cultures. REQUEST FOR

More information

Managing Mega Projects. Wed 6 th July, Martin Urquhart Project Director

Managing Mega Projects. Wed 6 th July, Martin Urquhart Project Director Managing Mega Projects Wed 6 th July, Martin Urquhart Project Director Overview 13,500psi, 350 F, 500 MMscfd 6 Development Wells / 1 PWRI well CPF Jacket 7,874 mt Topsides 13,898 mt WHP 12+2 Slots Jacket

More information

Purchasing Policy Update: Implementation of the Uniform Guidance Procurement Standard. Katie Cattrell, Training Specialist

Purchasing Policy Update: Implementation of the Uniform Guidance Procurement Standard. Katie Cattrell, Training Specialist Purchasing Policy Update: Implementation of the Uniform Guidance Procurement Standard Katie Cattrell, Training Specialist 1 Agenda 1. Background and Timeline 2. Procurement Thresholds 3. Procurement Standards

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects George F. Jergeas PhD, PEng Professor of Project Management, University of Calgary October 24, 2012: BREAKOUT:

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

How we see it EPC vs EPCM

How we see it EPC vs EPCM How we see it EPC vs EPCM To EPC or Not to EPCM EPC and EPCM contracting are both very prevalent types of contracts within the construction industry. Dependent on the level of risk the Owner of a project

More information

Standard Appraisal Framework for Hybrid Maintenance Contracts

Standard Appraisal Framework for Hybrid Maintenance Contracts NZ Transport Agency Page 1 of 5 Standard Appraisal Framework for Hybrid Maintenance Contracts This document is considered a guideline for the establishment of a performance system for the NZ Transport

More information

Design-Build (DB) and Construction Manager / General Contractor (CMGC)

Design-Build (DB) and Construction Manager / General Contractor (CMGC) Design-Build (DB) and Construction Manager / General Contractor (CMGC) IDOT and Industry Preliminary Joint Review for Proposed Legislation December 18, 2012 Welcome Introductions Agenda Purpose Definitions

More information

NEC Experience Sharing on Improvement of Fuk Man Road Nullah Partnering and Financial Aspects from Contractor s view. Ir Ko Wing Nin, Ken

NEC Experience Sharing on Improvement of Fuk Man Road Nullah Partnering and Financial Aspects from Contractor s view. Ir Ko Wing Nin, Ken NEC Experience Sharing on Improvement of Fuk Man Road Nullah Partnering and Financial Aspects from Contractor s view Ir Ko Wing Nin, Ken 1 Agenda Tendering Subletting Early Warning Notification 2 Partnering

More information

Project developers for Oil Terminals, SPM/CBM/FSO and Maritime Operations

Project developers for Oil Terminals, SPM/CBM/FSO and Maritime Operations Project developers for Oil Terminals, SPM/CBM/FSO and Maritime Operations Contracting Strategies for Terminal Construction page 2 Contracting Strategies for Terminal Construction Choosing the way to contract

More information

Construction contracting methods: Managing risk and delivery in an ever-changing environment

Construction contracting methods: Managing risk and delivery in an ever-changing environment Construction Law in 2010 Putting the Principles into Practice Construction contracting methods: Managing risk and delivery in an ever-changing environment Michael Creedon Partner 28 October 2010 Society

More information

CHAPTER 4 EXISTING PROJECT EXECUTION MODELS

CHAPTER 4 EXISTING PROJECT EXECUTION MODELS CHAPTER 4 EXISTING PROJECT EXECUTION MODELS 4.1 OVERVIEW 4.2 COMPONENTS OF MODEL 4.2.1 ORGANISATIONAL STRUCTURE 4.2.2 MANAGEMENT INFORMATION SYSTEM 4.2.3 PROJECT MANAGEMENT SYSTEM 4.2.4 RISK MANAGEMENT

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction

More information

(Online Procurement Initiative)

(Online Procurement Initiative) Internet Negotiations (Online Procurement Initiative) Objective Share Intel s present findings in the application of Internet negotiations (I-NEG) for construction services and facilities equipment. Specifically,

More information

Building Schools for the Future: Procurement Review

Building Schools for the Future: Procurement Review Building Schools for the Future: Procurement Review ICT in BSF 18 March 2008 Tim Byles Chief Executive Partnerships for Schools Background Strong programme momentum Focus to date on pre-engagement and

More information

Contracting and Procurement Strategy. at the Heart of Project Delivery. Tehran, January 28 th, OMV Upstream

Contracting and Procurement Strategy. at the Heart of Project Delivery. Tehran, January 28 th, OMV Upstream Contracting and Procurement Strategy at the Heart of Project Delivery Tehran, January 28 th, 2017 OMV Upstream OMV Upstream Project Delivery Global Project Portfolio Core 2 - Northsea Aasta Hansteen Gulfaks

More information

// Achieving the Unachievable

// Achieving the Unachievable // Achieving the Unachievable A Case Study on Aligning a Project with Stakeholder Expectations Dr. Dan Patterson, PMP CEO & President, Acumen February Table of Contents INTRODUCTION TO THE PROJECT 3 S1:

More information

UNDP Procurement. UNDP Angola Procurement

UNDP Procurement. UNDP Angola Procurement UNDP Procurement The term procurement refers to the process of acquiring goods, works and services. The process spans the whole cycle from identification of needs, choosing the adequate procurement methods,

More information

Rice Building Institute September 13, 2007

Rice Building Institute September 13, 2007 Rice Building Institute September 13, 2007 TMHS Capital Construction Program Sid Sanders, Vice President Facilities Planning and Construction Methodist System Overview Willowbrook San Jacinto Medical Center

More information

Pre Proposal Proposal Meeting

Pre Proposal Proposal Meeting SOUTHERLY WWTC SECOND STAGE RETURN SLUDGE PUMP IMPROVEMENTS Design Build Project Pre Proposal Proposal Meeting August 15, 2012 Introduction Progressive Design-Build Procurement Approach Request For Proposals

More information

Rate Schedule FT Firm Transportation Service

Rate Schedule FT Firm Transportation Service Rate Schedule FT Firm Transportation Service 1. Availability This Rate Schedule is available for the transportation of natural gas by Heartland Gas Pipeline for any Customer: 1.1 Where Customer: a) Has

More information

SUPPLIER QUALIFICATION SYSTEM (SQS)

SUPPLIER QUALIFICATION SYSTEM (SQS) SUPPLIER QUALIFICATION SYSTEM (SQS) Providing global visibility of Shell suppliers www.shell.com/supplier/qualification OUR APPROACH TO SUPPLIER PREQUALIFICATION Shell Contracting & Procurement is responsible

More information

Alternative Project Delivery Methods and Procurement

Alternative Project Delivery Methods and Procurement Alternative Project Delivery Methods and Procurement Board of Airport Commissioners Meeting 2 June 2014 Presented by: Roger A. Johnson, Deputy Executive Director Definitions Project Delivery Method o The

More information

Proposal for Preconstruction Services CM/GC Services-TMSF Office and Maintenance Building Project

Proposal for Preconstruction Services CM/GC Services-TMSF Office and Maintenance Building Project Equal Opportunity Employer January 5, 2015 Exhibit A Exhibit A CM/CG Preconstruction Services Proposal Diane Morrison, CPPB PW Purchasing Specialist Public Works Department 150 N Capitol Blvd. Boise, Idaho

More information

UWI Executive Certificate in Public Procurement Law: Major Procurement Projects. Program Agenda. Presented by Paul Emanuelli

UWI Executive Certificate in Public Procurement Law: Major Procurement Projects. Program Agenda. Presented by Paul Emanuelli The University of the West Indies Cave Hill Campus Faculty of Law UWI Executive Certificate in Public Procurement Law: Major Procurement Projects Program Agenda Presented by Paul Emanuelli Savannah Beach

More information

Village of Lynbrook. Request for Proposal Engineering Services. Police License Plate Reader/Intersection Camera System

Village of Lynbrook. Request for Proposal Engineering Services. Police License Plate Reader/Intersection Camera System Village of Lynbrook Request for Proposal Engineering Services Police License Plate Reader/Intersection Camera System 1 Columbus Drive Lynbrook, NY 11563 516-599-8300 July 16, 2018 Table of Contents 1.

More information

Definition. Name of the tool or technique Project mission statement

Definition. Name of the tool or technique Project mission statement Tools and Techniques Definitions (or by alphabetic order ; see below) A definition of each of the tools and techniques is provided below. The primary sources of definitions were the PMBOK Guide and Max

More information

IMPROVING SUBCONTRACT CONDITIONS TOWARDS SUCCESSFUL INFRASTRUCTURE PROJECTS IN GAZA

IMPROVING SUBCONTRACT CONDITIONS TOWARDS SUCCESSFUL INFRASTRUCTURE PROJECTS IN GAZA MPROVNG SUBCONTRACT CONDTONS TOWARDS SUCCESSFUL NFRASTRUCTURE PROJECTS N GAZA Rebhy El Sheikh Palestinian Water Authority, Gaza Technical Director, MSc Mechanical Engineering ABSTRACT: Amongst the so many

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

Planning and Analysis Construction Operation

Planning and Analysis Construction Operation Planning and Analysis Construction Operation Session 2: Contract Strategy Prepared by zacoeb@ub.ac.id Introduction At the early stage of a project and once a project manager is selected, the main issue

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

Owners Perspective on Contracting Domestic Projects

Owners Perspective on Contracting Domestic Projects Projects have become larger and more complicated. Take advantage of the Economy of Scale in the commodity markets. Increased instrumentation due to Process Safety Management. Perception that only large

More information

1. FROM (Bidder): (Name)

1. FROM (Bidder): (Name) Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3

More information

Alternative ways of financing infrastructure

Alternative ways of financing infrastructure Alternative ways of financing infrastructure By Rikke Beckmann Danielsen, partner Financial Advisory, DK June 2017 Project overview Wide range of different projects Impact that matters We work on large

More information

Why Use an Architect?

Why Use an Architect? Architects Can Help Interpret Your Dreams Into A Built Reality Architects provide a service that extends well beyond producing a set of drawings. An architect will listen to your dreams, your aspirations,

More information

TERRE project. Elastic need, social welfare and counter-activations

TERRE project. Elastic need, social welfare and counter-activations TERRE project Elastic need, social welfare and counter-activations Author: TERRE TSOs Date 12/03/2018 Page 1 of 14 Contents 1 Introduction... 3 1.1. Background... 3 2 Elastic need... 4 2.1. Examples...

More information

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily

More information

Ancillary Services: Tender Procurement and Development

Ancillary Services: Tender Procurement and Development Ancillary Services: Tender Procurement and Development Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight

More information

Officer Recommendations

Officer Recommendations Policy and Resources Committee 19 July 2018 Title Report of Wards Status Award of Contract to Community Sector Development Partner Leader of the Council All Public (with separate exempt report) Enclosures

More information

Alternative Delivery for Municipal Water & Wastewater Projects in 2012

Alternative Delivery for Municipal Water & Wastewater Projects in 2012 Alternative Delivery for Municipal Water & Wastewater Projects in 2012 a OWEA 2012 Making a Pass at Going Green Looking Towards the Future June 20, 2012 Dennis Tinkler, P.E. Agenda Ohio s Methods of Performing

More information

Project Management in the Design and Construction Industry

Project Management in the Design and Construction Industry Project Management in the Design and Construction Industry Design & Construction Institute of Nova Scotia 2011 February 4, 2011 Game Plan Project Management 201 Consultant s Perspective Contractor s Perspective

More information

At Procurement Australia, We get it.

At Procurement Australia, We get it. WE GET IT At Procurement Australia, We get it. We re always doing the leg work for better results. Welcome to our world. The following pages share our unique approach to helping businesses like yours get

More information

Public procurement rules

Public procurement rules Major infrastructure and energy projects in CEE Public procurement rules Case Study: Poland The European Union will invest 170 billion in ten former Eastern block countries in Central and Eastern Europe

More information

Supplier qualification system guide

Supplier qualification system guide Supplier qualification system guide Transforming the way we work together aldermore.co.uk Responsible business practices Aldermore is committed to introducing responsible business practices that make it

More information

BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER

BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER January 2012 This Primer was produced for the United States Agency for International Development (USAID). It was prepared

More information

The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents

The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents CCDC Standard Construction Documents CCDC 2-1994 Stipulated Price Contract Standard prime contract between

More information

Business of Anaerobic Digestion Project Delivery Basics

Business of Anaerobic Digestion Project Delivery Basics Business of Anaerobic Digestion Project Delivery Basics BioCycle West Pre-Conference Workshop April 16 th Portland Oregon Adam Halsband Business Development Manager EISENMANN Corporation Agenda Key Components

More information

5 Best Practices In Capital Project Estimating for the Process Industries. Executive Brief

5 Best Practices In Capital Project Estimating for the Process Industries. Executive Brief 5 Best Practices In Capital Project Estimating for the Process Industries Executive Brief Introduction As Engineering, Procurement and Construction firms (EPCs) around the world face the reality of fewer

More information

FERC GAS TARIFF. Second Revised Volume No. 1 CROSSROADS PIPELINE COMPANY FILED WITH THE FEDERAL ENERGY REGULATORY COMMISSION

FERC GAS TARIFF. Second Revised Volume No. 1 CROSSROADS PIPELINE COMPANY FILED WITH THE FEDERAL ENERGY REGULATORY COMMISSION FERC GAS TARIFF Second Revised Volume No. 1 Of CROSSROADS PIPELINE COMPANY FILED WITH THE FEDERAL ENERGY REGULATORY COMMISSION Communications concerning this Tariff should be addressed to: James R. Downs,

More information

inform practice note Issued by the Construction Industry Development Board

inform practice note Issued by the Construction Industry Development Board construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery CONSTRUCTION PROCUREMENT

More information

Nutrition Supplier Meeting 2015 UNICEF Supply Division Copenhagen

Nutrition Supplier Meeting 2015 UNICEF Supply Division Copenhagen Nutrition Supplier Meeting 2015 UNICEF Supply Division Copenhagen Anthropometric Equipment/Mechanical Scales Annika Schwenk MSc.Pharm UNICEF SD Medicines and Nutrition Centre 30 th June 2015 Nutrition

More information

Is Your District Ready For the New Law?

Is Your District Ready For the New Law? Is Your District Ready For the New Law? Ben Pintabona Operations Manager Scaparotti Construction Group Craig Weise Construction Reform Program Director Ohio School Facilities Commission Sylvia Gillis,

More information

CLARIFICATIONS N 2 SERVICE CONTRACT NO CPF III Event Organisation. Clarification request received on 28 December 2016:

CLARIFICATIONS N 2 SERVICE CONTRACT NO CPF III Event Organisation. Clarification request received on 28 December 2016: Clarification request received on 28 December 2016: Clarification published on 17 January 2017: General explanation: The CEFTA Secretariat kindly requests all tenderers to take into account that the

More information

An Introduction to Engineering Design in the Nuclear Industry

An Introduction to Engineering Design in the Nuclear Industry An Introduction to Engineering Design in the Nuclear Industry Nuclear Supply Chain Event 28 th April 2016 Part 2: The Design Process Rob Barrand Lead Process Engineer Robert.barrand@nnl.co.uk Overview

More information

Inform Practice Note #23

Inform Practice Note #23 Inform Practice Note #23 September 2010 (Version 1 - September 2010) Construction Procurement Strategy cidb s Inform Practice notes provide guidance and clarity in achieving client objectives in construction

More information

A cost analysis is required for any negotiated (non competitive) contract procurement on behalf of any University program, if:

A cost analysis is required for any negotiated (non competitive) contract procurement on behalf of any University program, if: SECTION 7: ACQUISITION PROCEDURES SUBJECT: COST ANALYSIS PROCEDURE 7.4.2 POLICY: A cost analysis is required for any negotiated (non competitive) contract procurement on behalf of any University program,

More information

Rodica Sasu*, Argentina Tataru** BROWN FIELD REHABILITATION SUCCESS THROUGH AN EFFECTIVE PROJECT MANAGEMENT SYSTEM

Rodica Sasu*, Argentina Tataru** BROWN FIELD REHABILITATION SUCCESS THROUGH AN EFFECTIVE PROJECT MANAGEMENT SYSTEM AGH DRILLING, OIL, GAS Vol. 34 No. 2 2017 http://dx.doi.org/10.7494/drill.2017.34.2.577 Rodica Sasu*, Argentina Tataru** BROWN FIELD REHABILITATION SUCCESS THROUGH AN EFFECTIVE PROJECT MANAGEMENT SYSTEM

More information

LM032: Advanced Tendering Procedures & Bid Evaluation

LM032: Advanced Tendering Procedures & Bid Evaluation LM032: Advanced Tendering Procedures & Bid Evaluation LM032 Rev.001 CMCT COURSE OUTLINE Page 1 of 6 Training Description: The engagement and management of contractors and suppliers is a vital part of the

More information

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 09.03.2016 Project phases time Inception initiation Preliminary analysis

More information

Agenda Part 1 (up to break)

Agenda Part 1 (up to break) Welcome to the Use of the NEC3 Engineering Construction Contract as a project management tool Presenter : Jon Broome leading edge projects consulting ltd jon@leadingedgeprojects.co.uk +44(0)7970 428 929

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

DRAFT. Request for Proposal for Construction Manager at Risk Services ASHRAE. New Headquarters Building. Peachtree Corners, GA

DRAFT. Request for Proposal for Construction Manager at Risk Services ASHRAE. New Headquarters Building. Peachtree Corners, GA DRAFT Request for Proposal for Construction Manager at Risk Services ASHRAE New Headquarters Building Peachtree Corners, GA 1. INTRODUCTION AND PROJECT DESCRIPTION A. Introduction On behalf of ASHRAE,

More information

Support for Competitive Procurement of Renewables in Mongolia

Support for Competitive Procurement of Renewables in Mongolia TERMS OF REFERENCE Support for Competitive Procurement of Renewables in Mongolia 1. Background The European Bank for Reconstruction and Development ( EBRD or the Bank ) and the Mongolian Ministry of Energy

More information

An overview of the Standard for Infrastructure Procurement and Delivery Management

An overview of the Standard for Infrastructure Procurement and Delivery Management An overview of the Standard for Infrastructure Procurement and Delivery Management National Treasury Instruction No 4 of 2015/2016, issued in terms of the Public Finance Management Act of 1999 (PFMA),

More information

Metropolitan Council

Metropolitan Council 2011-A17 Program Evaluation and Audit Metropolitan Council Professional Services Contracts Review August 15, 2011 INTRODUCTION Background Program Evaluation and Audit (Audit) recently conducted a review

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 04.03.2015 Project phases time Inception initiation Preliminary analysis

More information

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside

More information

Capital Projects Do your homework. CIM Toronto October 2014 Rocks and Stocks Chris Twigge-Molecey

Capital Projects Do your homework. CIM Toronto October 2014 Rocks and Stocks Chris Twigge-Molecey Capital Projects Do your homework CIM Toronto October 2014 Rocks and Stocks Chris Twigge-Molecey 2 Causes of capital over-runs Old news The symptoms: Persistent over-runs Late start-up Poor ramp-up to

More information

ADDENDUM #1. CRUISE TERMINAL NO. 10 DESIGN/BUILD MOBILE PASSENGER GANGWAY for CANAVERAL PORT AUTHORITY PUR-RFP

ADDENDUM #1. CRUISE TERMINAL NO. 10 DESIGN/BUILD MOBILE PASSENGER GANGWAY for CANAVERAL PORT AUTHORITY PUR-RFP ADDENDUM #1 CRUISE TERMINAL NO. 10 DESIGN/BUILD MOBILE PASSENGER GANGWAY for CANAVERAL PORT AUTHORITY PUR-RFP-15-12 October 16, 2015 This addendum is issued as part of the Bidding Documents for the above

More information

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

Project Time Management. Course Objectives. Outline

Project Time Management. Course Objectives. Outline Project Time Management Institute for Facilities Management Course Objectives Explore the challenges with managing a campus project schedule Review industry practices and contractual issues Discuss incentive

More information

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM)

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM) Costs and benefits of reducing waste in construction Defence sector new build Woolwich single living accommodation modernisation (SLAM) Value Percentage of 3.2m construction cost Cost saving potential

More information

POLICY FOR PROCUREMENT INCLUDING WORK OUTSOURCED TO OTHER ORGANISATIONS AND INDIVIDUALS

POLICY FOR PROCUREMENT INCLUDING WORK OUTSOURCED TO OTHER ORGANISATIONS AND INDIVIDUALS Arts Marketing Association POLICY FOR PROCUREMENT INCLUDING WORK OUTSOURCED TO OTHER ORGANISATIONS AND INDIVIDUALS Title: Policy for procurement including work outsourced to other organisations and individuals

More information

Intelligent e-supply Chain Decision Support

Intelligent e-supply Chain Decision Support University of Minnesota Digital Technology Center December 2002 Intelligent e-supply Chain Decision Support Norman M. Sadeh e-supply Chain Management Laboratory School of Computer Science Carnegie Mellon

More information

supplier qualification system guide Milton Keynes - Oakgrove

supplier qualification system guide Milton Keynes - Oakgrove supplier qualification system guide Milton Keynes - Oakgrove responsible business practices Metro Bank is committed to introducing responsible business practices that make it easier for our suppliers to

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

GP Systems of Choice Lot 3 How to Buy Guide

GP Systems of Choice Lot 3 How to Buy Guide GP Systems of Choice Lot 3 How to Buy Guide Contents 1. Introduction 2. Disclaimer 3. Benefits of Catalogue 4. The Buying Process 5. Selection Process 6. Legal Documentation 7. Completing the Contract

More information

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS

ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS ATLANTIC PROVINCES ASSOCIATION OF LANDSCAPE ARCHITECTS CONSULTANT FEE SCHEDULE FOR LANDSCAPE ARCHITECTURAL CONSULTING SERVICES A GUIDELINE NOV 2008 TABLE OF CONTENTS Table Of Contents... 2 INTRODUCTION...

More information

Mini Tender PART A External Wall Insulation, Mechanical and Electrical Installation

Mini Tender PART A External Wall Insulation, Mechanical and Electrical Installation Mini Tender PART A External Wall Insulation, Mechanical and Electrical Installation Instructions for Mini Tender Throughout the contractual parts of the Mini Tender, the Bidder is referred to as a Subcontractor

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Advance Purchase Commitment Considerations

Advance Purchase Commitment Considerations ZIKV Diagnostics webinar 30th August 2016 Advance Purchase Commitment Considerations Lama Ramzi Suleiman Overview UNICEF and PAHO have been working with USAID to put together an Advance Purchase Commitment

More information

Definition document for wholly owned companies

Definition document for wholly owned companies Freedom of Information Act 2000 Definition document for wholly owned companies This guidance is for wholly owned companies which are public authorities for the purpose of the Freedom of Information Act

More information

FAST TRACK PROJECT IMPLEMENTATION CHARLOTTE WATER IDLEWILD BOOSTER PUMP STATION PIPING IMPROVEMENTS

FAST TRACK PROJECT IMPLEMENTATION CHARLOTTE WATER IDLEWILD BOOSTER PUMP STATION PIPING IMPROVEMENTS NC AWWA-WEA 95 TH ANNUAL CONFERENCE FAST TRACK PROJECT IMPLEMENTATION CHARLOTTE WATER IDLEWILD BOOSTER PUMP STATION PIPING IMPROVEMENTS Chuck Bliss, P.E. Charlotte Water Kyle Massey, P.E. Black & Veatch

More information

From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process

From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process www.provelio.com Summary This paper is an independent project manager s critique of two projects. One

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

THE TRUE VALUE OF PROJECT RISK ANALYSIS

THE TRUE VALUE OF PROJECT RISK ANALYSIS THE TRUE VALUE OF PROJECT RISK ANALYSIS Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Much has been written in recent years about the benefits of conducting a project

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification