Alternative Delivery for Municipal Water & Wastewater Projects in 2012
|
|
- Quentin Johnson
- 5 years ago
- Views:
Transcription
1 Alternative Delivery for Municipal Water & Wastewater Projects in 2012 a OWEA 2012 Making a Pass at Going Green Looking Towards the Future June 20, 2012 Dennis Tinkler, P.E.
2 Agenda Ohio s Methods of Performing Public Construction Ohio Construction Reform (OCR) Alternative Project Delivery Methods Is a Work in Progress Chartered Cities vs. Other Jurisdictions Single-Prime Design/Bid/Build (D/B/B) Design/Build (D/B) project delivery Construction Manager at Risk (CMR) delivery Making a Pass at Going Green ($) Looking Towards the Future General Contractor Led D/B Actions to Move Us Forward 2
3 Ohio Construction Reform (OCR) June 2011: OCR HB 153 signed by Governor Alternative Project Delivery Methods: Retains multiple-prime Design/Bid/Build (D/B/B) project delivery (not recommended) Retains Construction Manager (CM) as agent delivery Allows Single-Prime D/B/B* Allows Construction Manager at Risk (CMR)* Allows Design/Build (D/B)* Allows for open-book Guaranteed Maximum Price (GMP), design-assist, and subcontractor prequalification within D/B and CMR delivery methods *To be discussed further today First changes in Ohio s method of performing public construction in over 134 years! 3
4 2012: Ohio Construction Reform Work in Progress Check this website for updates on Ohio Construction Reform: Allows Single-Prime D/B/B CMR documents final in February 2012 D/B documents final in April 2012 CMR and D/B Standard Requirements for Public Facility documents are a Work in Progress and are expected to be updated for Water/Wastewater projects Go To: to sign up for updates, make comments, learn, etc. 4
5 OCR: Chartered Cities vs. Other Jurisdictions Alternative Delivery Requirements for Ohio Public Water/Wastewater Facilities Chartered Cities OCR not Applicable Ohio Administrative Rules Apply Much flexibility to select best value of Numerous Alternative Delivery Methods Jurisdictions including Non-Chartered Cities, Villages, Townships, Etc. OCR Applies OCR Developed for State Work BUSINESS! Jacob Marley OCR is a Work in Progress and did not generally consider Water/Wastewater Projects 5
6 OCR: Single-Prime D/B/B Owner Advantages All Parties are Familiar Time-Tested Process Allows Thorough Collaboration/ Input between Owner and Design Engineer Owner Disadvantages Takes Time Linear Process Min. Collaboration between Engineer & Contractor Risks to Owner Relies on Engineer s Estimates Errors and Omissions result in Change Orders (but much less than Multi-Prime) Workable Project Engineer Owner GC Trade Subcontractors Contractual Relationships Working Relationships 6
7 OCR: CMR ( D/B Lite ) Owner Advantages CMR Pre-Construction Services: Improved Constructability, Pricing, and Possibly Schedule Price Guaranteed Maximum Price (GMP) During Design Engineer Owner Reduces Project Risk, Contingency, Design Omissions thereby less potential of Change Order Prequalification of Subcontractors may Increase Quality Owner Disadvantages No Single Responsible Party Separate Design/Construction Contracts CMR Engineer and CMR forced marriage Relies on Criteria Engineer for Initial Estimates Trade Subcontractors Complex GMP Process Risk of Agreement Added Costs for CMR Pre-Con Services Contractual Relationships Working Relationships 7
8 OCR: Design/Build Government does not solve problems; it subsidizes them. Ronald Reagan Owner Advantages Single Point of Contact and Single Contract for Performance and Guarantees Owner Disadvantages (Just for Starts) Subcontracting Process is Burdensome: Project Cost Unknown until final Subcontract Packages are designed, bid, and awarded Public Owners will need significant staff to review Subcontract Packages Higher Design Costs Will Delay Project and Add Administrative Costs; Project at Risk to Proceed unless all Sub Packages are designed, bid, and awarded Key Subcontractors are not Members of D/B Team and; therefore, do not provide meaningful innovation Criteria Engineer Owner Design/Builder Trade Subcontractors Contractual Relationships Working Relationships 8
9 Looking Toward the Future General Contractor Led Design/Build Owner Disadvantages Procurement can be Complex (Evaluated Bid) Criteria Engineer City Limited to Predict what will be Proposed (if Minimal Criteria Design for Complex Project) Price may include Significant Costs to offset Risk (if Minimal Criteria Design for Complex Project) Design/Builder Possible Limited Owner and D/B Team Collaboration Trade Subcontractors Contractual Relationships Working Relationships 9
10 Looking Toward the Future Most D/B Projects in US are General Contractor Led Design/Build Why Select GC Led Design/Build? Single-Point of Responsibility D/B Team (GC, Engineer, Subs) is Highly Collaborative with Owner Deliver Project Quickly - Problem Solved Costs: Earliest GMP (Lump Sum with Proposal) Low Procurement Costs Competition: Minimize Design/Construction Costs Potential for Maximum Innovation No Contractor Led Change Order Evaluate Proposals: What s Important to Customers? Source: The Water Design/Build Council 10
11 Looking Toward the Future General Contractor Led Design/Build Delaware, Ohio Upper Olentangy Water Reclamation Center For Example, we ran into Changes in Site Conditions Rather than going to Our own separate Corners and then arguing, delaying, sending letters, holding meetings we solved the problems together as a Team with No Project Delay. As a Team, we completed Value Engineering and Constructability Review to: Improve Facility Operations, Safety, and Reliability Improve Odor Control Design to Reduce Both Construction and Lifecycle Costs Later, Kokosing D/B Team was selected for $10M Sewer D/B Project (Repeat Business) The Team developed Trust and, as a result, delivered more Value for the same Cost to the City 11
12 Looking Toward the Future Actions to Move Us Forward Take Advantage of Ohio Construction Reform (OCR) After 134 Years, Stop the Craziness Get Rid of Multi-Prime Design/Bid/Build Owners Use Alternative Project Delivery that is most Advantageous to Your Customers Invest Time, Training, and Resources to Learn about all Alternative Delivery Methods Understand Advantages and Disadvantages of Each Alternative Project Delivery Method Recognize that any Alternative Delivery Method can Work with Proper Planning, Execution, and the Right Team Recognize that Owner must have strong leader to follow through with new Alternatives Encourage Ohio Department of Administrative Service to Update D/B Subcontractor Rules Go to and submit comments Source: The Water Design/Build Council 12
13 Questions & Answers a 13
14 a OWEA 2012 Making a Pass at Going Green Looking Towards the Future June 20, 2012
Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It
Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Jim Mallorey, P.E. Metro Wastewater Reclamation District Chris Harper - University of Colorado Boulder January 23, 2014 1
More informationSCADA System Procurement Alternatives
SCADA System Procurement Alternatives 2017 Automation Committee Seminar August 24, 2017 Terry M. Draper, PE, PMP Discussion Topics SCADA Overview System Hardware / Software Procurement Additional System
More informationAPPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)
APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter
More informationLB 889 The Political Subdivisions Construction Alternatives Act
1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.
More information1/4/2014. Alternative Project Delivery Methods 1. Agenda
Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia
More informationComparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013
Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should
More informationPROVING OUR PROFESSIONALISM
PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods
More informationRisks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE
Risks Associated with Alternative Delivery Methods Managing Expectations Presented by Dan Becker, CCM, PMP, CCE 1 3 Primary Methods for Delivering Projects in WA and OR Design/Bid/Build Design/Build CM
More informationChoosing a Project Delivery Method. A Design-Build Done Right Primer
Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA
More informationFACILITIES CONFERENCE
FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity
More informationProcurement Guidelines
Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationDesign Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright
Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development
More informationIntegrated Project Delivery
2014 HDR Architecture, 2014 HDR, Inc., all all rights reserved. Integrated Project Delivery It s A New World, And How It Can Benefit Municipal Owners Rich Atoulikian, PMP, PE Rich.Atoulikian@hdrinc.com
More informationConstruction Manager as Constructor (CMc) Manual
Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Harshman Demolition Response Deadline 3/28/18
More informationALTERNATE FORMS OF PROJECT DELIVERY
ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors
More informationConstruction Family of Documents
Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications
More informationFEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS
FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS Linda Hanifin Bonner, Ph.D., WDBC Mark Halleman, P.E., Parsons Produced by the Water Design-Build Council 1 Key Factors Design-Build-Operate
More informationProgressive Design-Build
November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value
More informationThe Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents
The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents CCDC Standard Construction Documents CCDC 2-1994 Stipulated Price Contract Standard prime contract between
More informationBest Practices for Exceeding Project Goals and Reducing Risk on Construction Projects
Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Presented by: Robyn Minter Smyers Alan S. Ritchie Heather A. Bartzi Erin Luke Presentation Team Robyn Minter Smyers
More informationLease-Leaseback Project Delivery Method
Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,
More informationA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station
A Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka, PE Karrie Buxton Jim Salerno Brett Burgett Rich Atoulikian, PMP, PE Cal Rozario, PMP 2014 HDR,
More informationChoosing Delivery Method
Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing
More informationPROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR
PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR Moderator: Praful Kulkarni, AIA President/CEO of gkkworks National Chairman of DBIA Presenters: Geoffrey Neumayr, SE Chief Development Officer
More informationDesign-Build Highway Projects: A Review of Practices and Experiences Final Report PRC F
Design-Build Highway Projects: A Review of Practices and Experiences Final Report PRC 15-53 F Design-Build Highway Projects: A Review of Practices and Experiences Texas A&M Transportation Institute PRC
More informationJob Order Contracting (JOC) ITB JE Overview August 2016
Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.
More informationConstruction Manager at Risk Delivery Method
County of Alameda Board of Supervisors Transportation and Planning Committee May 4, 2015 Caroline Judy, Acting Director Construction Manager at Risk Delivery Method Briefing and Discussion Purpose Briefing
More informationALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY?
ALTERNATIVE PROJECT DELIVERY METHODS DO THEY SAVE TIME AND MONEY? Gordon Culp Smith Culp Consulting SmithCulp.com INTRODUCTION Are there alternative methods for delivering water and wastewater treatment
More informationTampa Bay Water is a wholesale water
FWRJ Utilizing The Engineer-Procure-Construction Management Procurement Process To Get A Bang Without Going Bust Suzannah Folsom, Jonathan Kennedy, Jerry Russell, and Eric Peters Tampa Bay Water is a wholesale
More informationCCA Contract Forms Type Members Non-Members
To order CCA documents and/or seals please email planroom@saskatoonconstruction.ca CCA Contract Forms Type Members Non-Members CCA 1-2008 Stipulated Price Subcontract Electronic $52.00 $67.00 Seals $6.00
More informationA , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Wide HVAC Upgrades - Steam Lines Response
More informationProject Delivery Method
Project Delivery Method Presenters San Diego Community College District Facilities Management Lance Lareau District Architect UC Berkeley graduate 30 years of architecture experience 2 nd generation architect
More informationProgressive Design-Build
Progressive Design-Build A Design-Build Done Right TM Primer Progressive Design-Build 1 What is Progressive Design-build? Progressive Design-Build A DESIGN-BUILD DONE RIGHT TM PRIMER A DESIGN-BUILD INSTITUTE
More informationConsensusDocs. Catalog. Updated Docs Inside
ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even
More informationFairfax County Government Construction Management At Risk (CMAR)
Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of
More informationConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K
CONTRACTS CATALOG Updated Docs Inside ou Ah ead o f the Cur v e gy epin e K ... BUILDING A BETTER WAY! Whether working at the office, from the road or even at home, the platform provides instant access
More informationIntegrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective
CMAA National Conference October 13, 2008 Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective Date Presenters Howard W. Ashcraft,
More informationCM AT RISK VS. DESIGN BID BUILD
CM AT RISK VS. DESIGN BID BUILD A TEXAS CASE STUDY ON PROCUREMENT AND IMPLEMENTATION September 28, 2010 Acknowledgement Mike Adams, P.E Executive Director of Engineering and Utilities City of Midlothian
More informationHow do FIDIC contracts work
How do FIDIC contracts work Zoltán Záhonyi (MSc civil engineer, postgraduate in law) FIDIC Contracts Committee member FIDIC Accredited Trainer Z&Partners Consulting Engineers Ltd. Leading Partner, managing
More informationAIA Contract Documents
AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).
More informationNCHRP 20-07, Task 373 UTILITY COORDINATION USING ALTERNATIVE CONTRACTING METHODS
NCHRP 20-07, Task 373 UTILITY COORDINATION USING ALTERNATIVE CONTRACTING METHODS Prepared for: AASHTO Standing Committee on Highways Prepared by: Douglas Gransberg, Gransberg & Associate, Norman, Oklahoma
More informationLessons Learned from CM-at-Risk and Design Build Projects at Water and Wastewater Treatment Plants. Lawrence H. Hentz Jr., P.E.
Lessons Learned from CM-at-Risk and Design Build Projects at Water and Wastewater Treatment Plants Lawrence H. Hentz Jr., P.E., BCEE Presentation Outline Background of Two >$110 M Projects Improvements
More informationSAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop
SAN DIEGO COMMUNITY COLLEGE DISTRICT SDCCD Design/Build Subcontracting Plan Preparation Workshop April 7, 2015 Welcome Chris Manis Vice Chancellor, Facilities Management Purpose To share information useful
More informationSeattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices
Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district
More informationProject phases II. Tendering-constructionoperation
Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 04.03.2015 Project phases time Inception initiation Preliminary analysis
More informationPROJECT EXECUTION STRATEGIES OVERVIEW
PROJECT EXECUTION STRATEGIES OVERVIEW UpTech Upstream Oil & Gas Summit Designing And Building Success AGENDA Industry Situation Traditional Project Stage Progression Project Schedule Compression Contracting
More informationTrinity Well Field and Production Facilities Project Management Using CMAR
Trinity Well Field and Production Facilities Project Management Using CMAR Ian Taylor, P.E., PMP New Braunfels Utilities David Bennett, P.E. Freese and Nichols Kirby Anderson MGC Contractors February 27,
More informationCarolinas HealthCare System Case Study Collaborate Bid Build (CB 2 ) A Different Approach to Project Delivery
Carolinas HealthCare System Case Study Collaborate Bid Build (CB 2 ) A Different Approach to Project Delivery Carolinas HealthCare System Case Study Behavioral Health Davidson, NC Project Team Carolinas
More informationEffective Utility Coordination Practices Using Alternative Contract Methods
Effective Utility Coordination Practices Using Alternative Contract Methods Douglas D. Gransberg, PhD, PE, DBIA Gransberg & Associates, Inc. Norman, OK 73070-2395 dgransberg@gransberg.com NCHRP 20-07,
More informationInternational Subawards
International Subawards Alternatives to Cost Reimbursable Subrecipient Agreements Presentation for the Federal Demonstration Partnership International Subawards Subcommittee 11 January 2008 David Brady,
More informationDocument Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction
Document 00 41 13 - Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction Sealed bids will be received by Miami University at 181 Cole Service Building, Oxford,
More informationDesign-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka
Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka S. Ratnasabapathy and R. Rameezdeen Department of Building Economics, University of Moratuwa, Sri Lanka.
More informationSTUDY SPONSORS Charles Pankow Foundation 223 West Foothill Blvd., 2nd Floor Claremont, California (909)
Influencee of Project Delivery on Sustainable, High Perform mance Buildings November 2010 A Research Report of the Charles Pankow Foundation and the Design-Build Institute of America ACKNOWLEDGEMENTS
More informationProject phases II. Tendering-constructionoperation
Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 09.03.2016 Project phases time Inception initiation Preliminary analysis
More informationCritical Construction Industry Trends Influencing Process and Profitability
Critical Construction Industry Trends Influencing Process and Profitability Harvey M. Bernstein, F.ASCE, LEED AP Vice President, Industry Insights & Alliances McGraw Hill Construction Agenda General Industry
More informationRFP Restructuring Advisory Committee: Water and Sewer Question and Answer. Question Cut-Off 2/13/17
RFP 2017-0007 Restructuring Advisory Committee: Water and Sewer Question and Answer Question Cut-Off 2/13/17 1. What is the estimated value of the sewer system? Determining an appropriate valuation of
More informationProgressive Design-Build
Progressive Design-Build Progressive Design-Build Design-Build Procured with a Progressive Design & Price A Design-Build Done RightTM Primer 1 Design-Build Progressive Design-build Design-Build Procured
More informationConsensusDOCS are the only standard contract documents endorsed by 23 leading construction associations Construction Contracts Built by Consensus
ConsensusDOCS Contracts Catalog ConsensusDOCS are the only standard contract documents endorsed by 23 leading construction associations Construction Contracts Built by Consensus 1 The release of ConsensusDOCS
More informationStephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group
Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group INTRODUCTION EMPLOYER S CORE PRINCIPLES OF PROCUREMENT Value for money / Economy Efficiency / Fit for purpose
More informationProfessional Practice 544
Spring Semester 2017 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights
More informationMysore L. Nagaraja, P.E. Chairman
APTA 2013 ANNUAL CONFERENCE: SEPTEMBER 30, 2013 BIG TRANSPORTATION INFRASTRUCTURE PROJECTS WORLDWIDE: Global Overview Chairman Introduction The Focus of My Talk Global Overview of Cost Overruns and Delays
More informationAGENDA. BIM Opportunities for CMMS
AGENDA BIM Opportunities for CMMS Mark Falzarano, BIM Leader, AE Services Group, Barton Malow Company Keith Vandenbussche, FMA, Director, Facilities Services, Barton Malow Company Jason Wells, Vice President,
More informationConstruction Contract Basics
PDHonline Course P120 (2 PDH) Construction Contract Basics Instructor: Kevin D. Waddell, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response
More informationChapter 1, Introduction
Chapter 1, Introduction CHAPTER CONTENTS 1.1 THE DESIGNERS MANUAL A. Purpose B. Contents 1.2 THE DIVISION OF FACILITIES PLANNING 1.3 THE UNIVERSITY AS OWNER A. The Owner B. Owner Agency 1.4 CAPITAL IMPROVEMENTS
More informationPPC2000: Association Of Consultant Architects Standard Form Of Project Partnering Contract
PPC2000: Association Of Consultant Architects Standard Form Of Project Partnering Katie Saunders and David Mosey 1 Introduction PPC2000 (Mosey 2005) is a published form of multi-party contract for procurement
More informationForsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101
Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS
More informationPlanning Construction Procurement. A guide to developing your procurement strategy
Planning Construction Procurement A guide to developing your procurement strategy First published October 2015 Revised October 2016 ISBN: 978-1-98-851707-0 (Online) New Zealand Government Procurement PO
More informationICES Core Cost Engineering Competencies
CM CORE 1 Cost Engineering Commercial Management Core Competency Cost Engineering Specialism COMPETENCIES AND ASSESSMENT Financial and commercial processes in civil engineering January 2015 Technical Member
More informationOFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, CT BUILDING RFP NO.: RFP OPENING DATE: APRIL 16, 3:00 PM ADDENDUM #4.
OFFICE OF PROCUREMENT COOLING TOWER REPLACEMENT, RFP NO.: 618-009 RFP OPENING DATE: APRIL 16, 2018 @ 3:00 PM ADDENDUM #4 April 9, 2018 THIS ADDENDUM IS TO PROVIDE ANSWERS TO THE FOLLOWING QUESTIONS: NOTE:
More informationMANAGERIAL PROCESS STANDARDIZATION THROUGH ILLUSTRATIVE CASE STUDY
MANAGERIAL PROCESS STANDARDIZATION THROUGH ILLUSTRATIVE CASE STUDY Younghan Jung 1 and Thomas Mills 2 1 Department of Construction Management and Civil Engineering, Georgia Southern University, Statesboro,
More informationREQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES
REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES Pueblo Urban Renewal Authority (PURA) Pueblo Convention Center Expansion &
More informationMetropolitan Washington Airports Authority. Request for Qualifications Information (RFQI) RFQI No C084. for
Request for Qualifications Information (RFQI) RFQI No. for Project Controls Task Contract for Project Support & Management at Washington Dulles International Airport and Ronald Reagan Washington National
More information1913 Lausanne, Switzerland
FIDIC What is FIDIC? An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the
More informationSounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build
When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits
More informationMember level the optimum standard is given against each activity statement
QUANTITY SURVEYING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off
More informationContracting Methods and Risk Management
Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and
More informationAllowances, Saving, Changes and Contingency
Allowances, Saving, Changes and Contingency Design-Build and CM Construction FOR THE EXPERIENCE June 2017 Allowances, Saving, Changes and Contingency Overview The cost of the work plus a fee with a guaranteed
More informationADVERTISEMENT FOR BIDS
1. INVITATION ADVERTISEMENT FOR BIDS Sealed proposals for the following work will be received by the University of Kentucky, Capital Construction Procurement Section, Room #322 Peterson Service Building,
More informationSingle or multi-sourcing model?
Outsourcing 2007/08 Single and multi-sourcing models Anthony Nagle and Alistair Maughan, Morrison & Foerster www.practicallaw.com/8-380-6567 Once an organisation decides to outsource, one of its biggest
More informationStrategic Management and Project Selection
Strategic Management and Project Selection Strategic Management and Project Selection Maturity of Project Management Overview Criteria for PS Models Nature of PS Models Types of PS Models Uncertainty Analysis
More informationATTACHMENT A INFRASTRUCTURE FOR SPACEPORT DEVELOPMENT DESIGN-BUILD CONTRACTOR SCOPE OF SERVICES. Table of Contents
Table of Contents SECTION 1 - GENERAL... 3 1.01 Introduction... 3 SECTION 2 - PROJECT DESCRIPTION... 3 2.01 Introduction... 3 2.03 Project Summary... 4 SECTION 2 - RELATED PROJECTS... 5 3.01 General...
More informationAppendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America)
Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) 108 Appendix B: Questionnaire 109 CONSTRUCTION MANAGEMENT
More informationGrabbing the Bull by the Horns: Darigold's Successful Employment of Design-Build Delivery
Conference: Design-Build for Water/Wastewater Conference 2017 Paper/Presentation Title: Grabbing the Bull by the Horns: Darigold's Successful Employment of Design-Build Delivery Authors: Sheldon Knapp,
More informationUnderstanding the DCAA Audit Process and How to Prepare for Success
Understanding the DCAA Audit Process and How to Prepare for Success Breakout Session #: C11 Presented by: Beverly Arviso, CPA, Fellow, CPCM, CFCM Date: July 22, 2013 Time: 4:00-5:15 DCAA s Mission Compliance
More informationVersion 1.0. The Contract Management Standard Final Edition. Version 1.0
The Management Standard Final Edition 1 Purpose of the Management Standard The purpose of the Management Standard is to describe the nature of contract management in terms of the contract management processes
More informationPROJECT DELIVERY HANDBOOK
PROJECT DELIVERY HANDBOOK GuidetoCaliforniaSchooland CommunityCollege FacilityDelivery 2017 ThisversionincorporateschangesresultingfromlegislationincludingAB2316andSB693(2016). AssociationofCaliforniaConstructionManagersUpdatedJanuary17,2017
More informationS T A N D A R D B I D D I N G D O C U M E N T S. Procurement of Works. Caribbean Development Bank
S T A N D A R D B I D D I N G D O C U M E N T S Procurement of Works Caribbean Development Bank September 2007 ii Foreword These Standard Bidding Documents for Procurement of Works (SBDW) have been prepared
More informationConstruction Contracting Methods. By: Nick Thornsbury Falcon Engineering
Construction Contracting Methods By: Nick Thornsbury Falcon Engineering Typical Contracting Methods Used Key Elements that Affect Design Engineers How Changes Affect Design Engineers Typical Contracting
More informationMSBA Contractor Roundtable
Massachusetts School Building Authority Steven Grossman Chairman, State Treasurer John K. McCarthy Executive Director MSBA Contractor Roundtable Tuesday, December 2, 2014 www.massschoolbuildings.org Roundtable
More informationThe documents in the A-Series relate to various forms of agreement between an owner and a contractor.
A-Series A- S E R I E S The documents in the A-Series relate to various forms of agreement between an owner and a contractor. A101 Owner-Contractor Agreement Form Stipulated Sum Basis of payment is a stipulated
More informationPPPs Canada s experience Water sector
PPPs Canada s experience Water sector Mark Hodgson June 21, 2016 Santiago, Chile 1 Canadian PPP overview A growing market since 1993 2 Canadian PPP overview Project status 3 Canadian PPP overview Results
More informationConsensusDocs CONTRACTS CATALOG. ConsensusDocs BUILDING A BETTER WAY. See What s New at ConsensusDocs.org
ConsensusDocs CONTRACTS CATALOG ConsensusDocs BUILDING A BETTER WAY See What s New at ConsensusDocs.org ConsensusDocs Building A Better Way! Whether working at the office, from the road or even at home,
More informationAirport Owners Guide to Project Delivery Systems White Paper Update
Airport Owners Guide to Project Delivery Systems White Paper Update Steve Riano Chair, ACC Project Delivery Committee Bechtel Infrastructure Corporation Fall 2011 ACI-NA Operations & Technical Affairs
More informationVolume II: Cost Proposal and Business Information
Volume II: Cost Proposal and Business Information Part A: Cost/Price Information The City is under obligation to follow Federal, State and Local regulations to require an RFP and Bid for any construction
More informationRequest for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION
Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for
More information6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents
Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3
More information