1 Project developers for Oil Terminals, SPM/CBM/FSO and Maritime Operations

2 Contracting Strategies for Terminal Construction page 2

3 Contracting Strategies for Terminal Construction Choosing the way to contract the design and construction for a tank terminal construction project is a decision of which the influence on the project is often underestimated. The contracting strategy has a large and early impact on the execution and organization of the project. The choice influences the price, the risk and the duration of the project. And it determines the required level of pre-contract engineering. To guarantee efficient and fast early stages of the project, it is essential that the decision for a contracting strategy is taken early in the project. There are many ways to contract the construction of a tank terminal. This presentation describes the advantages and disadvantages of the various available options. How to contract engineering, procurement & construction of a tank terminal project page 3

4 Client managed construction When the client wished to manage everything himself Managed by the project organization of the client Typically a high number of contracts with different kinds of suppliers Client Engineer Consultant Contractor Equipment Material Package unit This requires large resources and expertise from the client. There are many alternative solutions. page 4

5 EPC Single contract Engineering, Procurement & Construction E, P & C by one main contractor Single contract based delivery of the complete scope of a project, typically with guarantees for the operational functionality of the installation. The required pre-contract engineering, often called FEED (Front-End Engineering Design), can be limited to a conceptual functionality design. The main contractor typically engineers and constructs a large part of the project themselves The main contractor procures the other parts of the project from suppliers and sub-contractors Engineer Suppliers Client EPC Contractor Sub Contractors page 5

6 Package Unit approach Multiple EPC contracts Functional or geographical clearly separated packages of work, each contracted in an EPC manner. Could be 2, 3 or a high number of packages. Introduces interfaces between the packages, both technical and organizational. The interfaces require more detailed precontract engineering (FEED s). Requires coordination by the client between the contractors of each package. Engineer Client Package 1 Package 2 Package 3 Suppliers Suppliers Suppliers page 6

7 EPC Contract formats Lump-sum Turn-key The contractor will deliver a functional construction (just turn the key) for a single, fixed all inclusive price (lump-sum). Functionality and delivery date are contractually guaranteed, often with penalties if not met. The client has essentially no influence on the detail design or construction of the project. The risk for overruns in time and budget are on the shoulders of the contractor. Design and Construct The contractor will first deliver the design, often for a fixed fee. This design is to be approved by the client. Based on the design and agreed unit rates, the contractor will calculate a fixed fee and delivery date for the construction. The client has a strong influence on the detail design of the project.. The risk for schedule and budget are on the shoulder of both parties. Unit Rates The contract consists of a price list of all units (supplies, manhours) to be delivered by the contractor. The contractor will invoice based on actually procured supplies and spent manhours. The client has a strong influence on the detail design and the construction of the project.. The risk for schedule and budget are on the shoulder of the client.. page 7

8 Most common contract forms For tank terminals, The most commonly chosen contracting strategies are: EPC, lump-sum turn-key Package units, design and construct Other strategies might however fit certain client-project combinations better. page 8

9 The contracting processes compared EPC Lump-sum Turn-key 1. Define location and required functionality of the terminal. 2. Contract an engineering company to make a FEED. This FEED can be limited to a functional, conceptual design. 3. Do a pre-qualification to determine the short-list of potential EPC contractors. 4. Define the contract format, incl. the contractor guarantees, HSE requirements etc. 5. Issue a Request for Proposal (RfP) consisting of the contract and the FEED to the short-listed contractors 6. Evaluate the bids and negotiate and award the contract. Package Units, Design and Construct 1. Define location and required functionality of the terminal. 2. Contract an engineering company to make a FEED. This FEED should be a basic design that defines the technical interfaces between packages.. 3. Do for each package a pre-qualification to determine the short-list of potential contractors. 4. Define the contract format(s), incl. the contractor guarantees, HSE requirements etc. And define the interface management procedure. 5. Issue for each package a Request for Proposal (RfP) consisting of the contract and the relevant part of the FEED to the short-listed contractors 6. Evaluate the bids and negotiate and award the contracts. page 9

10 EPC lump-sum turn-key Advantages Total project costs fixed in early stage All liability by the main contractor Small project team required by client Only functional design required up-front Mainly applicable for greenfield projects Disadvantages High project costs (risk factor added by Contractor) Almost no influence on the project by the Client Up-front engineering not sufficient for environmental permit application page 10

11 Package units, design and construct Advantages Most of the liabilities by the contractors Potential for negotiating low project costs LImited amount of engineering required before contracting Detailed influence on the design by the Client Makes good use of expert knowledge from contractors Disadvantages Late availability of fixed contracted project costs Large project team required by client Interfaces between contractors need to be engineered and managed by Client page 11

12 EPC management (EPCm) Engineering, Procurement & Construction management Engineering and management of Procurement and Construction typically by an engineering firm but could also be two or even three separate companies. The contract with the EPCm company(ies) can be lumpsum or based on unit rates or a combination of both. Contracts with contractors and suppliers directly with client but managed by EPCm engineers. The contracting strategy is to be agreed between client and EPCm engineers. EPCm Engineers Suppliers Client Contractors For large and/or complex (brown field) projects page 12

13 EPCm Advantages Potential for lower project costs Much influence on project by Client Quality determined earliest by choice of contractor/supplier Flexibility to change/adapt during design Fits brown field projects well Disadvantages More engineering hours Large project team required Late availability of final contracted project costs risk for overruns of initial budget and schedule page 13

14 How to make the contracting decision? Questions to ask yourself Do you want to be fast? EPC Do you want detailed influence on the quality of construction? Design & construct Is your project large and complex EPCm Do you want a low risk for budget over-run? Lump-sum, Turn-key Do you have your own, large project organization? Package units Do you want detailed influence on the design? EPCm Do you have limited experience in constructing a terminal? EPC Do you want guarantees on the functionality of the terminal EPC Do you want to negotiate yourself for the lowest price? package units Do you find this confusing? Engage Riverlake Solutions! page 14

15 Management contacts Jan Thijs Maatman MSc. Mining and Petroleum Engineering Since 1999 experience in contracting oil & gas Mobile Erik van Sliedregt MSc. Mechanical Engineering Since 1998 experience in marine contracting construction and production mangement Mobile Wilbert Versteeg Master of Business Sience Since 1996 experience in marine contracting oil & gas Mobile Feiko Jager MSc. Maritime Technology Since 1987 experience in oil terminal and maritime logistics Mobile page 15

16 Office Contact Sales Office Parklaan BC Rotterdam, The Netherlands Tel: Fax: Head Office 26, rue du Mont-Blanc 1201 Geneva, CH page 16

ARA Trading & Finance Seminar Mitigating Risk during Project Development

ARA Trading & Finance Seminar Mitigating Risk during Project Development ARA Trading & Finance Seminar Mitigating Risk during Project Development Mitigating Risk during Project Development While developing a tank terminal, like with any other industrial infrastructure project,

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Owner s Representative/Owner Team Roles, Obligations and Responsibilities

Owner s Representative/Owner Team Roles, Obligations and Responsibilities Page1 Achieving Excellence in Capital Projects Delivery Owner s Representative/Owner Team Roles, Obligations and Responsibilities By George E. Baram P.Eng., M.Sc., PMP, CCE, Fellow AACE International The

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods

5/21/13 PROCUREMENT 5/21/13. Agenda. Common Tendering Systems Procurement Methods PROCUREMENT 5/21/13 Agenda Common Tendering Systems Procurement Methods 1 Agenda Common Tendering Systems Procurement Methods Common Tendering Systems Competitive / Open-bid: (Qualified) contractors are

More information

Effective Purchasing, Tendering & Supplier Selection

Effective Purchasing, Tendering & Supplier Selection Effective Purchasing, Tendering & Supplier Selection Street, 55100 Kuala Lumpur, Malaysia. Tel: +60327326992 Mobile: +601 8909 0379 Fax: +60327326992 Effective Purchasing, Tendering & Supplier Selection

More information

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction

More information

How we see it EPC vs EPCM

How we see it EPC vs EPCM How we see it EPC vs EPCM To EPC or Not to EPCM EPC and EPCM contracting are both very prevalent types of contracts within the construction industry. Dependent on the level of risk the Owner of a project

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Liquefied Natural Gas to Power IPP Procurement Programme

Liquefied Natural Gas to Power IPP Procurement Programme Liquefied Natural Gas to Power IPP Procurement Programme Request for Qualification 5 October 2016 Outline of Presentation Procurement approach Purpose of the RFQ Framework of the RFQ Project Participants

More information

Modular Fabrication and Project Cargo Development

Modular Fabrication and Project Cargo Development 40 rue King Street Saint John, NB Canada E2L 1G3 T: 506.658.2877 T: 800.561.2877 F: 506.658.2871 info@enterprisesj.com www.enterprisesj.com Modular Fabrication and Project Cargo Development Project Description

More information

North American Development Bank. Engagement of Consultants

North American Development Bank. Engagement of Consultants North American Development Bank Engagement of Consultants ENGAGEMENT OF CONSULTANTS This Note has been prepared by the North American Development Bank (the Bank) to assist staff and borrowers in the implementation

More information

Liquefied Natural Gas to Power IPP Procurement Programme

Liquefied Natural Gas to Power IPP Procurement Programme Liquefied Natural Gas to Power IPP Procurement Programme Request for Qualification 5 October 2016 Outline of Presentation Procurement approach Purpose of the RFQ Framework of the RFQ Consortium Membership

More information

Public procurement rules

Public procurement rules Major infrastructure and energy projects in CEE Public procurement rules Case Study: Poland The European Union will invest 170 billion in ten former Eastern block countries in Central and Eastern Europe

More information

NOT FOR PRINT DISTRIBUTION

NOT FOR PRINT DISTRIBUTION Image courtesy of Freeport LNG Development, L.P. A World of Solutions Visit www.cbi.com LNG Liquefaction Diversified Services Across Energy Infrastructure Comprehensive Liquefaction Capabilities For more

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

REQUEST FOR PROPOSAL CWA TRAINING INITIATIVE. February 13, 2018

REQUEST FOR PROPOSAL CWA TRAINING INITIATIVE. February 13, 2018 REQUEST FOR PROPOSAL CWA TRAINING INITIATIVE February 13, 2018-1 - Table of Contents 1. Summary... 3 2. Background of Organization... 3 3. Proposal Guidelines and Requirements... 3-4 4. Contract Terms...

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

Alternative Project Delivery Methods and Procurement

Alternative Project Delivery Methods and Procurement Alternative Project Delivery Methods and Procurement Board of Airport Commissioners Meeting 2 June 2014 Presented by: Roger A. Johnson, Deputy Executive Director Definitions Project Delivery Method o The

More information

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

Becoming a Preferred Supplier. Cameron Lawford, SCMP Project Procurement Manager

Becoming a Preferred Supplier. Cameron Lawford, SCMP Project Procurement Manager Becoming a Preferred Supplier Cameron Lawford, SCMP Project Procurement Manager November 4 th, 2015 2 AGENDA Hatch Limited Ø Who We Are Ø What We Do Becoming a Preferred Supplier Ø Hatch Tools and Systems

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Procurement Management Processes

Procurement Management Processes Procurement Management Processes Olga Botero PM630-1004A-01 Contracting and procurement in project management Dr. Tony Prensa October 8 th 2010 Project Procurement Management includes the processes necessary

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

Project Delivery - Electric Utilities

Project Delivery - Electric Utilities Project Delivery - Electric Utilities Complex Project Delivery Traditional DBB approach changing for our utility clients Execution of large complex projects Alternate project delivery models EPC (Engineering,

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

PROJECT DELIVERY METHODS

PROJECT DELIVERY METHODS Understanding the Construction Contract Project Delivery Methods ISBA April 7,2017 Copyright 2017 by K&L Gates LLP. All rights reserved. Design Bid Build Design Negotiate Build Construction Manager Advisor

More information

Oman LNG L.L.C. Pre-Qualification of Tenderers NGH : PROVISION OF MANPOWER RECRUITMENT SERVICES

Oman LNG L.L.C. Pre-Qualification of Tenderers NGH : PROVISION OF MANPOWER RECRUITMENT SERVICES Oman LNG L.L.C. Pre-Qualification of Tenderers NGH-16-843 : PROVISION OF MANPOWER RECRUITMENT SERVICES Provision of Manpower Recruitment Services Page 1 of 7 06/09/16 GUIDELINES Response to this questionnaire

More information

LM032: Advanced Tendering Procedures & Bid Evaluation

LM032: Advanced Tendering Procedures & Bid Evaluation LM032: Advanced Tendering Procedures & Bid Evaluation LM032 Rev.001 CMCT COURSE OUTLINE Page 1 of 6 Training Description: The engagement and management of contractors and suppliers is a vital part of the

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

UNDP Procurement. UNDP Angola Procurement

UNDP Procurement. UNDP Angola Procurement UNDP Procurement The term procurement refers to the process of acquiring goods, works and services. The process spans the whole cycle from identification of needs, choosing the adequate procurement methods,

More information

QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector

QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector COMPANY PROFILE offers a complete service including Project Management, Engineering, Procurement, Construction Management, Training and related

More information

Petrochemical Complex Integration Feasibility Studies - an Investment that pays out

Petrochemical Complex Integration Feasibility Studies - an Investment that pays out Petrochemical Complex Integration Feasibility Studies - an Investment that pays out Frederik Baars Global Petrochemicals Summit, Lisbon, 16 November 2016 2014 Fluor. All rights reserved. FLUOR is a registered

More information

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Jim Mallorey, P.E. Metro Wastewater Reclamation District Chris Harper - University of Colorado Boulder January 23, 2014 1

More information

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS Pedro d Aça Castel-Branco ST Division Civil Engineering Group (ST/CE) CERN, Geneva, Switzerland Abstract The contracts for the civil

More information

Advance Collaborate Enrich

Advance Collaborate Enrich Job Order Contracting 101 A Facilities Management Tool Sponsored by the Center for Job Order Contracting Excellence and The National Association of State Facilities Administrators Job Order Contracting

More information

Introduction KH Engineering Benelux Engineering, Procurement, Construction Project Management Contracting Services and Consultancy

Introduction KH Engineering Benelux Engineering, Procurement, Construction Project Management Contracting Services and Consultancy www.khe.eu Global experience, local approach Introduction KH Engineering Benelux Engineering, Procurement, Construction Project Management Contracting Services and Consultancy Group Values Mission and

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation

More information

BALLYMUN REGENERATION LTD. INSTRUCTIONS TO TENDER FRAMEWORK AGREEMENT FOR PSDP CONSULTANT SERVICE

BALLYMUN REGENERATION LTD. INSTRUCTIONS TO TENDER FRAMEWORK AGREEMENT FOR PSDP CONSULTANT SERVICE BALLYMUN REGENERATION LTD. INSTRUCTIONS TO TENDER FRAMEWORK AGREEMENT FOR PSDP CONSULTANT SERVICE Issue Date: 12-08-07 Instructions to Tenderers Page 1 of 9 1. INTRODUCTION 1.1 Overview of BRL Ballymun

More information

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

PROJECT EXECUTION STRATEGIES OVERVIEW

PROJECT EXECUTION STRATEGIES OVERVIEW PROJECT EXECUTION STRATEGIES OVERVIEW UpTech Upstream Oil & Gas Summit Designing And Building Success AGENDA Industry Situation Traditional Project Stage Progression Project Schedule Compression Contracting

More information

ALTERNATIVE CONTRACTING METHODS

ALTERNATIVE CONTRACTING METHODS ALTERNATIVE CONTRACTING METHODS Conventional Design-Bid-Build Design/Build Negotiated General Contractor By Jeff Warner, AIA, LEED AP Principal, ALSC Architects CONVENTIONAL DESIGN-BID-BUILD The most traditional

More information

Growth of Middle Class Spending

Growth of Middle Class Spending Market Drivers Economic growth in China, India and surrounding emerging markets Middle class consumers are increasing their standard of living Higher quality food products and consumer goods Big ticket

More information

Preparing for Detroit s Growth

Preparing for Detroit s Growth Preparing for Detroit s Growth About VM3 A Strategic Management Consulting firm VM3 leverages over 30 combined years of mixed industry Fortune 100 corporate capital procurement and finance experience to

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide array of design, construction, construction administration,

More information

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1 Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different

More information

Role of Procurement / Purchasing Within the Authority

Role of Procurement / Purchasing Within the Authority Role of Procurement / Purchasing Within the Authority What is Purchasing s Role / Why Is Purchasing Important? The Authorized entity within the Water Authority that procures the goods / services required.

More information

Enterprise and Supplier Development (ESD) Mario Venter Executive, Resources and Industry AECOM South Africa

Enterprise and Supplier Development (ESD) Mario Venter Executive, Resources and Industry AECOM South Africa Enterprise and Supplier Development (ESD) Mario Venter Executive, Resources and Industry AECOM South Africa . Gas to Power definitely has a place in in Africa s power generation and energy sector and will

More information

Five Global Pty Ltd ABN (0) (0)

Five Global Pty Ltd ABN (0) (0) Five Global Pty Ltd ABN 78 158 704 226 +61 (0) 468 999 561 +61 (0) 427 119 234 Introduction What is the optimum project management model that an Owner should employ to deliver a successful project? It

More information

SEMS and Supplier Management- An Operator s Perspective

SEMS and Supplier Management- An Operator s Perspective SEMS and Supplier Management- An Operator s Perspective Petroleum Equipment Suppliers Association Legal Seminar Mar 26, 2013 Karl Van Scyoc Anadarko Petroleum Corporation Supplier? Organization or individual

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be Thanks to our host CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be reported to RCEP at RCEP.net. A certificate

More information

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services

Standard Form of Agreement Between Owner and Architect with Standard Form of Architect s Services B-Series B- S E R I E S The documents in the B Series relate to various forms of agreement between an owner and an architect for professional services. B141 Standard Form of Agreement Between Owner and

More information

A Guide for Doing Business with the Purchasing Services Office of Valdosta State University

A Guide for Doing Business with the Purchasing Services Office of Valdosta State University A Guide for Doing Business with the Purchasing Services Office of Valdosta State University The information below gives you assistance on providing goods and services to Valdosta State University (VSU).

More information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction

More information

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY RFP 18-PR-HCM-12 EXECUTIVE SEARCH SERVICES SCOPE OF WORK ATTACHMENT A

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY RFP 18-PR-HCM-12 EXECUTIVE SEARCH SERVICES SCOPE OF WORK ATTACHMENT A DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY RFP 18-PR-HCM-12 EXECUTIVE SEARCH SERVICES SCOPE OF WORK ATTACHMENT A Table of Content Section Page 1.0 Background 3 2.0 Contractor Qualifications 3 3.0 Scope

More information

SANGUINE TECHNO - COMMERCIAL SOLUTIONS

SANGUINE TECHNO - COMMERCIAL SOLUTIONS SANGUINE TECHNO - COMMERCIAL SOLUTIONS Today s Challenges of Infrastructure Industry Developer Holistic feasibility study Optimum engineering management Workable EPC & EPCM concept International quality

More information

Project Management in the Design and Construction Industry

Project Management in the Design and Construction Industry Project Management in the Design and Construction Industry Design & Construction Institute of Nova Scotia 2011 February 4, 2011 Game Plan Project Management 201 Consultant s Perspective Contractor s Perspective

More information

A Guide to Energy Performance Contracting in Public Buildings

A Guide to Energy Performance Contracting in Public Buildings A Guide to Energy Performance Contracting in Public Buildings European Energy Service Initiative 2020 codema.ie CODEMA European Energy Service Initiative 2020 WHAT IS EPC? Energy Performance Contracting

More information

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method Report on Effectiveness of the Construction Manager at Risk Project Delivery Method The project management plans described below, establish several elements or criteria for university project staff to

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

Advanced Tendering Procedures & Bid Evaluation Effective Tendering, Bidding Strategies & Evaluation

Advanced Tendering Procedures & Bid Evaluation Effective Tendering, Bidding Strategies & Evaluation ISO 9001:2008 Certified ISO 29990:2010 Certified (Certificate No:1007049195) ISO 29990 (Certificate No: 1078694951) Advanced Tendering Procedures & Bid Evaluation 10-14 September 2017 Dubai, United Arab

More information

A Complex SPIN Memorandum of Understanding model

A Complex SPIN Memorandum of Understanding model A Complex SPIN Memorandum of Understanding model December 2016 Co-funded by European Union Erik van Agtmaal and Johan Coolen Factor4 Lange Winkelstraat 26 2010 Antwerpen Belgium T: +32(0)3 225 23 12 E:

More information

ENGINEERING, PROCUREMENT & CONSTRUCTION MANAGEMENT

ENGINEERING, PROCUREMENT & CONSTRUCTION MANAGEMENT ENGINEERING, PROCUREMENT & CONSTRUCTION MANAGEMENT Petrofac Engineering & Production Services Petrofac at a glance Services for every stage of your project life cycle International oilfield services provider

More information

Phase 1B Report on Water Treatment Plant Improvements Project Delivery Options

Phase 1B Report on Water Treatment Plant Improvements Project Delivery Options 56 Exchange Terrace, Fourth Floor Providence, Rhode Island 02903 tel: 401 751-5360 fax: 401 751-5499 October 31, 2008 Ms. Julia A. Forgue, P.E. Director City of Newport Department of Utilities 70 Halsey

More information

Achieving Excellence in Capital Projects Delivery Focusing on Four Pillars. Introdution

Achieving Excellence in Capital Projects Delivery Focusing on Four Pillars. Introdution Page1 Achieving Excellence in Capital Projects Delivery Focusing on Four Pillars Introdution October 1, 2015 Prepared by: George E. Baram P.Eng., M.Sc., PMP, CCE, Fellow AACE International Baram and Associates

More information

QEN Construction of New Shaded Car Parking. Oman LNG L.L.C. Pre-Qualification of Tenderers QEN Construction of Artificial Grass

QEN Construction of New Shaded Car Parking. Oman LNG L.L.C. Pre-Qualification of Tenderers QEN Construction of Artificial Grass QEN-16-835 Construction of New Shaded Car Parking Oman LNG L.L.C. Pre-Qualification of Tenderers QEN-16-835 Construction of Artificial Grass At Oman LNG Site - Sur Page 1 of 6 GUIDELINES QEN-16-835 Construction

More information

The Role of Energy Service Companies (ESCOs) in Energy Performance Contracting (EPC) IEE project TRANSPARENSE

The Role of Energy Service Companies (ESCOs) in Energy Performance Contracting (EPC) IEE project TRANSPARENSE The Role of Energy Service Companies (ESCOs) in Energy Performance Contracting (EPC) IEE project TRANSPARENSE Dr. KONSTANTINOU Kostas, Director of Local Development, ANATOLIKI S.A Thessaloniki, November

More information

REQUEST FOR PROPOSALS FOUR YEAR CONTRACT FOR TEMPORARY EMPLOYEE SERVICES BID NO: Addendum 1: August 16, 2018

REQUEST FOR PROPOSALS FOUR YEAR CONTRACT FOR TEMPORARY EMPLOYEE SERVICES BID NO: Addendum 1: August 16, 2018 REQUEST FOR PROPOSALS FOUR YEAR CONTRACT FOR TEMPORARY EMPLOYEE SERVICES BID NO: 18-2050 : August 16, 2018 has been issued to address the following: 1. Modify one requirement to the Scope of Service. 2.

More information

Oman LNG L.L.C. Pre-Qualification Questionnaire QEN KV & 6.6KV SWITCHBOARD INSPECTION, SERVICE & TESTING OF HV CIRCUIT BREAKERS

Oman LNG L.L.C. Pre-Qualification Questionnaire QEN KV & 6.6KV SWITCHBOARD INSPECTION, SERVICE & TESTING OF HV CIRCUIT BREAKERS Oman LNG L.L.C. Pre-Qualification Questionnaire QEN-14-747 11KV & 6.6KV SWITCHBOARD INSPECTION, SERVICE & TESTING OF HV CIRCUIT BREAKERS GUIDELINES Response to this questionnaire shall be completed in

More information

Request for Expression of Interest (EOI)

Request for Expression of Interest (EOI) Request for Expression of Interest (EOI) Title Procure and deploy a Learning Management System (LMS) for WHO EOI Ref. No. Published Date 31/03/2017 Closing Date & Time 10/04/201717:00 (UTC +1) Contact

More information

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

Project Management Consultancy Services. Ensuring safe and successful execution of your projects Project Management Consultancy Services Ensuring safe and successful execution of your projects Deep expertise in Project Management Consultancy TechnipFMC s Project Management Consultancy business unit

More information

External Project Management & Integrated Services Approach to Well Construction

External Project Management & Integrated Services Approach to Well Construction External Project Management & Integrated Services Approach to Well Construction 17-21 September 2017 Dubai, United Arab Emirates 19-DEC-16 This course is Designed, Developed, and will be Delivered under

More information

DRAFT. Request for Proposal for Construction Manager at Risk Services ASHRAE. New Headquarters Building. Peachtree Corners, GA

DRAFT. Request for Proposal for Construction Manager at Risk Services ASHRAE. New Headquarters Building. Peachtree Corners, GA DRAFT Request for Proposal for Construction Manager at Risk Services ASHRAE New Headquarters Building Peachtree Corners, GA 1. INTRODUCTION AND PROJECT DESCRIPTION A. Introduction On behalf of ASHRAE,

More information

FACILITY PROJECT BIDDING OPTIONS OVERVIEW

FACILITY PROJECT BIDDING OPTIONS OVERVIEW FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

Best Practice - Lessons learned General Contract Management

Best Practice - Lessons learned General Contract Management TEBODIN Best Practice - Lessons learned General Contract Management Roy Piek, Director PMC Moscow April 19, 2017 Level of Influence Project Expenditures Visualization of Influence vs Expenditures during

More information

ENGINEERING CONSULTANCY SERVICES

ENGINEERING CONSULTANCY SERVICES Oman LNG L.L.C. Pre-Qualification of Tenderers QEN-16-825 ENGINEERING CONSULTANCY SERVICES Engineering Consultancy Services Page 1 of 7 10/05/16 GUIDELINES Response to this questionnaire shall be completed

More information

1913 Lausanne, Switzerland

1913 Lausanne, Switzerland FIDIC What is FIDIC? An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the

More information

Strategic Sourcing: Conclusion

Strategic Sourcing: Conclusion Strategic Sourcing: Conclusion The Future Is Now Strategic sourcing is a new approach that promises to substantially improve an organization s competitiveness. Rather than adopting a singular, transaction-based

More information

CoreconLink for Xero Integration

CoreconLink for Xero Integration www.corecon.com CoreconLink for Xero Integration Available CoreconLink Options QuickBooks Pro, Premier, Enterprise (US, Canada, UK) QuickBooks Online (All Countries) Pro, Premier, Quantum (Canada) 9.X

More information

THE ULTIMATE GUIDE for Creating the Right Relocation Strategy

THE ULTIMATE GUIDE for Creating the Right Relocation Strategy THE ULTIMATE GUIDE for Creating the Right Relocation Strategy Today, there are more relocation program options than ever for organizations looking to create the right relocation and mobility strategy for

More information

REQUEST FOR PROPOSALS YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS

REQUEST FOR PROPOSALS YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS REQUEST FOR PROPOSALS GUTHRIE MEMORIAL LIBRARY ENVELOPE REHABILITATION YORK COUNTY, PENNSYLVANIA TABLE OF CONTENTS Table of Contents Section 1: Background...... 2 Section 2: Scope of Services... 2 Section

More information

Advanced Tendering Procedures & Bid Evaluation

Advanced Tendering Procedures & Bid Evaluation An Intensive 5 Day Training Course Advanced Tendering Procedures & Bid Evaluation Effective Tendering, Bidding Strategies & Evaluation 10-14 Sep 2017, Dubai 21-MAY-17 This course is Designed, Developed,

More information

LM028: Procurement & Contract Management Negotiation

LM028: Procurement & Contract Management Negotiation LM028: Procurement & Contract Management Negotiation LM028 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: A contract can stand or fall on the expertise and performance of the Purchasing

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

Procurement Guidelines

Procurement Guidelines Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management

More information

Owner s Representative SCOPE OF SERVICES

Owner s Representative SCOPE OF SERVICES Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,

More information

EXHIBIT 6 Preconstruction Work

EXHIBIT 6 Preconstruction Work EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements

More information

27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs

27 June 2013 Warsaw, Poland. Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 27 June 2013 Warsaw, Poland Platts 8 th Annual European Nuclear Power 2013 Procurement for New Nuclear Programs 1 Procurement for New Nuclear Programs Nuclear power programs risk and opportunity Supplier

More information

A World of Solutions Visit Product Storage Terminals for Bulk Liquids

A World of Solutions Visit  Product Storage Terminals for Bulk Liquids A World of Solutions Visit www.cbi.com Product Storage Terminals for Bulk Liquids United Arab Emirates The most global experience of any tank company CB&I has more than eight decades of experience designing

More information

The following specific criteria will be evaluated and must be addressed in the proposal:

The following specific criteria will be evaluated and must be addressed in the proposal: 01/08/2018 Fundraising Consulting Firm Address City, State Zip Code Re: Request for Proposal Dear Bidder, Care Resource is seeking proposals from qualified fundraising/development firms, referred to as

More information

Oman LNG LLC Pre-Qualification Questionnaire GA Call-Off Contract for Supply of Furniture

Oman LNG LLC Pre-Qualification Questionnaire GA Call-Off Contract for Supply of Furniture Oman LNG LLC Pre-Qualification Questionnaire GA-17-906 Call-Off Contract for Supply of Furniture Pre-Qualification Questionnaire Page 1 of 5 GUIDELINES Response to this questionnaire shall be completed

More information