1 HRSG Inspection Tasks Presented By: Bryan F. Craig, P.E HRST Inc. 1 Goals: HRSG Inspection 1. Document condition of equipment 2. Identify items that need immediate maintenance 3. Identify items that need budgeting and planning for maintenance next year 4. Identify problems early, allowing time for scrutiny and analysis 5. Due diligence..show stakeholders you have proactive approach. 2 1
2 HRSG Inspection Key Elements 1. Dedicated inspectors Good inspections take days not hours! 2. Recording observations (facts) Photos, measurements, notes 3. Organize facts logically Every fact should be accurately linked to a specific location. 4. Measurements at critical areas Thickness (UT), Gap distance, crack length 5. Three location types Gas Path Steam/Water Side Exterior 3 HRSG Inspection Gas Side Inspection Areas Access Lanes (inlet duct, firing duct, SCR, lanes between bt tube bundles, stack) Crawl spaces under and above tube headers Important to document locations clearly for future reference Best to prepare in advance, rather than identify problem locations on the fly 4 2
3 5 Inlet Duct Items:* 1. Liner System Gas Side Tasks Loose plates, spinning washers, exposed insulation, failed studs. 2. Flow distribution plates or vanes 3. Tubes & Fins corrosion, warping, vibration wear 4. Baffles & Tube Ties vibration damage, wear, expansion interferences, weld cracks. 6 3
4 Inlet Duct Liner Loose & broken components 7 Inlet Duct Liner Spinning Washers 8 4
5 Inlet Duct Liner Liner Gaps, Exposed Insulation 9 Flow Distribution Grid 10 5
6 Tube Ties Tube & fin wear at tube tie 11 Failed Tube Ties 12 6
7 Gas Side Tasks Firing Duct Checklist 1. Liner System (same as inlet duct, plus look for oxidized components) 2. Duct Burner: Sag in elements or baffles Nozzle plugging Coke buildup Burner wing condition 3. Tubes & Fins (same as inlet duct, plus) Evidence of flame impingement or local hotspots 4. Baffles & Supports 5. Location of firing duct thermocouples 13 Reheater upstream of duct burner 14 7
8 Burner Baffle Failures Coen baffle weld seam cracks & failures Coen fix for baffle weld seam cracks & failures. May not be enough, some cracking still being found
9 Carbon Buildup Carbon inside gas pipe. Build up has fractured the gas pipe. Coking: Usually due to olefins in refinery gas. Sometimes coking occurs with natural gas due to poor air/fuel mixing at burner. 17 Oxidized Liner Components 18 9
10 Local Burner Hotspots 19 Gas Side Tasks Tube Bundle Access Lane Checklist: 1. Liner System (same checks as inlet & firing ducts, problems less prevalent) 2. Tubes & Fins: corrosion, warping 3. Baffles & Supports (same as previous) 4. Catalyst Fouling Gas bypass around perimeter Packing between blocks 20 10
11 Tube & Fin Fouling 21 Tubes & Fins Tube Buckling Superheaters & Economizers 22 11
12 Tubes & Fins Cracking HPSH Tube 23 Gas Baffles Exhaust flow into page Sidewall Baffles Center (Laning) Baffles Upper Header Tubes Header (Bulkhead) Baffles Lower Header 24 12
13 Baffle Failures 25 Baffle Gaps Decrease Performance 26 13
14 Catalyst Fouling Catalyst Gas Bypass 28 14
15 Gas Side Tasks Crawl Space Checklist: 1. Water from tube leaks? 2. Floor debris 3. Liner condition 4. Liner fit up around piping and hanger penetrations 5. Baffles 6. Bent piping 7. Header corrosion 8. Tube/header joint condition (if visible) 29 Spray pattern is a leak indication 15
16 Fin scale debris on crawlspace floor Oxidized carbon steel debris on crawlspace floor 16
17 Accelerated corrosion near penetrations, probably caused by rain water leaking past penetration seal. Roof debris blocks drainage holes, trapping rainwater
18 Bulkhead Gas Bypass Hot Exh 35 Gap between baffle and floor is too large, allows gas bypass, decreasing performance
19 Bent Drains Indicate Stress 37 Exterior Tasks Exterior Inspection Checklist 1. Casing hotspots, cracks 2. Piping penetration seals 3. Access door condition 4. Foundations 38 19
20 Casing Access Doors Hot Spot 39 Penetration Seals Bellows cracks can be difficult to see. Tight cracks, bellows are compressed when off line. Look for hot spots, and nearby insulation fur
21 These bellow cracks were easy to see! However, it took some extra effort to climb up on the roof casing to inspect. 41 HRST Upgraded Pipe Penetration Seal PROBLEM: Tears in Fabric Cracks in Bellows Delay box SOLUTION: HRST Pipe Penetration Seals 42 21
22 Casing Stress & Cracks Expansion Stress Points (Typ) 43 Casing Stress & Cracks 22
23 Casing Crack Hotspots 23
24 HRSG Inspection Water/Steam Side Tasks Steam Drums are the only non intrusive access to the water/steam side in a modern HRSG. Drums are often also inspected by the water chemistry dept and insurance inspector. 47 Water/Steam Side Inspection Tasks Steam Drum Checklist 1. Drum surface condition 2. Signs of distress on steam separation equipment & belly pan 3. Thickness of belly plates and steam separators 4. Mechanical Integrity 5. Approximate waterline vs. drawing 6. Debris 48 24
25 Drum Surface Condition 1. Drum surface details (color, condition, pits) Color Red is good in an oxidizing environment Red is bad in a reducing environment Condition Keep track of surface defects from manufacture Track whether smoothness (roughness) is changing Pits Do you have them? What do they look like underneath? 49 Oxygen Attack in Steam Drum Offline 25
26 HP Drum Condition Surface defects in an HP drum from rolling steel NOT a significant issue 51 Signs of Distress 2. Signs of distress on steam separation equipment & belly pan Cracks in the belly pan Cracks in the final separator corners Weld seams in the shell and shell to head Downcomer indications 52 26
27 Cracks? Signs of Distress Baffle Cracks? 53 HP Belly Pan Cracks (or baffle plate) 54 27
28 Downcomer Indications 55 Thickness of Belly Pans and Steam Separation Equipment 3. UT test F/W, Deltak, Vogt, NEM, Aalborg, Alstom, etc Belly Pans Cyclones (F/W = horizontal, others = vertical) N/E and Cerrey Belly Pans (no cyclones) 56 28
29 Ultrasonic Thickness Measurements Thickness measurements are a useful tool to document condition of drum internals, tubes and piping. Be specific about locations & documentation Most measurements are simple thickness for general documentation or to track Flow Accelerated Corrosion More sophisticated UT used for crack detection: shear wave, phased array
30 Cyclones worn through from FAC 59 Belly Pan Thinning UT in LP & IP Check here! 60 30
31 LP Belly Pan Hole (FAC) 61 Mechanical Integrity 4. Integrity of Internals Piping Broken U Bolts Missing nuts Plugged Chem Feed Lines Separators Failure Plugging Missing hardware 62 31
32 HP Fallen Chem Feed Line U bolt broke off 63 HP Drum Chem Feed Line 64 32
33 HP Drum broken cyclone attachment 65 Deltak Perforated Plate Above Mesh Separator 66 33
34 Deltak Mesh Separator Failure 67 Approximate Water Line vs. Drawing 5. Water Line Readings The water line is often falsely reading low due to proximity of the downcomer or pump suction to the level transmitters. The suction effect of those large lines pulls on the level sensing lines. Plugging of the lines is problematic if they are positioned off the bottom of the shell. The number one cause of faulty level indication or control is calibration or compensation 68 34
35 LP water level 69 LP level transmitter proximity to pump suction 70 35
36 Debris in level tap Lower level tap magnetic debris 71 Debris in Drums 6. Debris bi Amount Color Magnetite vs. Hematite? Flakes vs. Powder? 72 36
37 Debris in drum 73 Summary Gas Side AccessLanes (inlet duct, firingduct, SCR, between tube bundles, stack) Crawl spaces under and above tube headers Exterior Casing hotspots, cracks Piping penetration seals Access door condition Foundations Steam/Water Side Steam Drums are the only non intrusive access to the water/steam side in most HRSGs 74 37
38 HRSG Inspection Further Work Online or Hot Inspection HRSG inspection while unit is operating Ideal for finding hotspots, casing cracks, penetration seal failures Can check hot position of spring hangers Extended Scope offline inspection Depending on the age, quantity & severity of cycles and history of issues, more intrusive inspection techniques may be best to quantify condition. Common techniques: 1. UT tubes and piping beyond spot checks (A Scan, Phased Array, or Shear Wave) 2. Dye Penetrant or Magnetic particle testing of suspect areas 3. Conventional and Digital X Ray (Radiography) 4. Eddy Current Testing 5. Piping Assessment 6. Hardness and Replication (P91) 7. Desuperheater removal & inspection 8. Borescoping 9. Tube samples 75 Any Questions? Bryan F. Craig, P.E HRST Inc. bcraig@hrstinc.com (office) (cell 76 38
HRSG Inspection Planning Guide
HRSG Inspection Planning Guide Second Edition P. Jackson D. Moelling J. Malloy M. Taylor Copyright 2006 by Tetra Engineering Group, Inc. All Rights Reserved. Reproduction or translation of any part of
More informationCMI Energy Aftermarket Solutions
CMI Energy Aftermarket Solutions 1 Optimize with CMI Aftermarket Solutions Complete support for any HRSG make or configuration! Field Services Inspections / Evaluations Failure Analysis Technical Consultations
More informationDesign Considerations for Advanced Combined Cycle Plant Using Fast Start Drum Type HRSGs
Presented To: Hot Topic Hour A Babcock Power Inc. Company By: Deron Johnston Date: Mar.7/13 Design Considerations for Advanced Combined Cycle Plant Using Fast Start Drum Type HRSGs Authors: Akber Pasha,
More informationINSPECTION PROCEDURE FOR SHELL AND TUBE HEAT EXCHANGERS
APPROVED: DATE APPROVED: DATE EFFECTIVE: Technical Writer: Content Expert: Purpose References Establish inspection guidelines to ensure mechanical integrity and continued reliable operation of shell and
More informationQuality Inspection 8618 London Heights San Antonio, TX Phone: (210)
Quality Inspection 8618 London Heights San Antonio, TX 78254 Phone: (210) 240-0476 PRE DRYWALL INSPECTION REPORT Prepared For: DELETED (Name of Client) Concerning: DELETED, San Antonio, TX 78258 (Address
More informationREVIEW OF HRSG CAPABILITIES FOR FLEXIBLE OPERATION
The Future of Gas Turbine Technology 7 th International Gas Turbine Conference 14-15 October 2014, Brussels, Belgium Paper ID Number (14) REVIEW OF HRSG CAPABILITIES FOR FLEXIBLE OPERATION Pascal Decoussemaeker
More informationTen Year Retrospective Look at HRSG FAC Assessment and Incidence. Peter S. Jackson, PhD, PE, David S. Moelling, PE, Mark Taylor, Mech. Eng.
Ten Year Retrospective Look at HRSG FAC Assessment and Incidence Peter S. Jackson, PhD, PE, David S. Moelling, PE, Mark Taylor, Mech. Eng. Ten years after we first reported at the 1999 EPRI Maintenance
More informationGeothermal Operations and Material Science
Geothermal Operations and Material Science Einar Jón Ásbjörnsson, Ph.D. Materials Challenges in Geothermal Utilization Reykjavík University if it ain't broke, don't fix it Engineering rule of thumb Geothermal
More informationNon Destructive Inspection Technology for Thermal Power Plants
37 Non Destructive Inspection Technology for Thermal Power Plants MIKIYASU URATA *1 KIYOTAKA AOKI *1 NAOYA URATA *2 KOICHI TAGAMI *2 MANABU KONDO *2 SHINTARO MATSUMOTO *3 In boiler facilities for thermal
More information3 Steps to Better Steam Temperature Control Proven Strategies to Minimize Thermal Stress and Tube Leaks
December 17 3 Steps to Better Proven Strategies to Minimize Thermal Stress and Tube Leaks www.emerson.com/ December 17 Commercial power generators are having to significantly change how they operate their
More information- Identify inspection finding that "rise to the top", or are most common to units across the fleet
AEP BRO Conference 2009 AEP Core Boiler Inspection Group (ACBIG) In 2007 the (ACBIG) was conceived and implemented by AEP in an effort to improve boiler availability and consistency across the AEP fleet.
More informationDownsizing a Claus Sulfur Recovery Unit
INFRASTRUCTURE MINING & METALS NUCLEAR, SECURITY & ENVIRONMENTAL Downsizing a Claus Sulfur Recovery Unit OIL, GAS & CHEMICALS By Charles L. Kimtantas and Martin A. Taylor ckimtant@bechtel.com & mataylo1@bechtel.com
More informationSafer, Faster, and Cost-efficient NDE Services.
Safer, Faster, and Cost-efficient NDE Services www.geckorobotics.com The Big Problem with Plant Inspections Downtime: Inspections often take several days. Costly: It requires a team of inspectors and oftentimes
More informationNondestructive Testing
Nondestructive Testing Prof. A.K.M.B. Rashid Department of MME BUET, Dhaka Nondestructive inspections fundamentals Classification of nondestructive inspections Radiographic inspection Magnetic particle
More informationHeat Recovery Steam Generators for Flexibility
Heat Recovery Steam Generators for Flexibility Landon Tessmer IAGT October 2016 Overview The grids needs flexible power HRSG and OTSG Designs Supplementary Firing Fresh Air Firing Case Study Balance of
More informationBODY OF KNOWLEDGE API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION
BODY OF KNOWLEDGE API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION October 2009 (Replaces November 2008) API Authorized Aboveground Storage Tank Inspectors must have a broad knowledge
More informationTFC KAOHSIUNG FACTORY 30 KMT AMMONIA STORAGE TANK INSPECTION REPORT. By: Jackson Yang (TFC R&D Department) 01 Oct 2016
TFC KAOHSIUNG FACTORY 30 KMT AMMONIA STORAGE TANK INSPECTION REPORT By: Jackson Yang (TFC R&D Department) 01 Oct 2016 1 CONTENT 1. Introduction 2. Internal Inspection Planning 3. Applied Inspection Technique
More informationInsulating Cellular Concrete Steel Joists Painting. A. America Society for Testing and Materials (ASTM):
SECTION 05120 STRUCTURAL STEEL PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03342 - Insulating Cellular Concrete. 2. 05210 - Steel Joists. 3. 09900 - Painting. 1.02 REFERENCES A. America Society
More informationDCU Process Control. Protecting Critical Investments & Optimizing Process Control with Advanced Temperature Measurement Systems
DCU Process Control Protecting Critical Investments & Optimizing Process Control with Advanced Temperature Measurement Systems Presented By: Taylor Fama Regional Technology Manager 1 AGENDA I. Intro to
More informationGLIMPSES OF IMPROPER WATER CHEMISTRY IN A SUBCRITICAL PULVERIZED COAL FIRED BOILER AT A THERMAL POWER PLANT
GLIMPSES OF IMPROPER WATER CHEMISTRY IN A SUBCRITICAL PULVERIZED COAL FIRED BOILER AT A THERMAL POWER PLANT By K.K.Parthiban / Venus Energy Audit System & Sri Devi Boiler Equipment and Spares. Introduction
More informationContents EN 14015:2004 (E) page
Contents page Foreword... 11 1 Scope... 12 2 Normative references... 13 3 Terms, definitions, symbols and abbreviations... 15 3.1 Terms and definitions... 15 3.2 Symbols... 19 3.3 Abbreviations... 21 4
More informationPredictive Maintenance (PdM) & Proactive Maintenance (PAM) Dr. Khaleel Abushgair
Predictive Maintenance (PdM) & Proactive Maintenance (PAM) ۱ Predictive Maintenance (PdM) Also known as Condition- Based Maintenance. Uses non-intrusive testing techniques, visual inspection and performance
More informationPhysical and Metallurgical Analysis Aids in Understanding Recovery Boiler Tube Cracking. November, 2014
Physical and Metallurgical Analysis Aids in Understanding Recovery Boiler Tube Cracking November, 2014 PdM Technology Infrared Thermography Gas Find IR Example of LNG Leak Safety Minute Economizer Tube
More informationNewman Station Units 1, 2, and 4 Condition Assessment Report. El Paso Electric, Inc. El Paso, TX
Newman Station Units 1, 2, and 4 Condition Assessment Report prepared for El Paso Electric, Inc. El Paso, TX April 2010 Project No. 53549 prepared by Burns & McDonnell Engineering Company, Inc. COPYRIGHT
More informationInspection of Steel Girder Bridges
Course Outline Inspection of Steel Girder Bridges Bridge superstructure systems Defects in steel members Failure mechanics Fatigue Constrained Induced fracture (CIF) Inspection Inspection of Pin & Hanger
More informationGas Turbine & Combined Cycle Plants
Gas Turbine & Combined Cycle Plants Introduction With a worldwide reputation for excellence, DEKOMTE de Temple manufactures fabric and stainless steel expansion joints for all applications within a gas
More informationCorrosion in GASCO Habshan CBA Units and its mitigation
Corrosion in GASCO Habshan CBA Units and its mitigation Orlando de Matos Inspection Department Head MESPON 2016 - Abu Dhabi 9 th to 11 th October 2016 AGENDA Introduction Process Description for CBA Units
More informationFront Range Power Plant: Air Cooled Condenser Tom Cook, PE Colorado Springs Utilities, Operating Engineering Group Air Cooled Condenser User Group:
Front Range Power Plant: Air Cooled Condenser Tom Cook, PE Colorado Springs Utilities, Operating Engineering Group Air Cooled Condenser User Group: October 2018 Supply Reliability (1,149 MW Total) Martin
More informationHIGH ENERGY PIPING INSPECTION PROGRAM
HIGH ENERGY PIPING INSPECTION PROGRAM JOEL LUNDQUIST STRESS ANALYSIS SECTION B&V ENERGY AGENDA About Black & Veatch Introduction Power Piping Code Initial Baseline Assessment Evaluation by Non-Destructive
More informationStorage & loading on site SOFREGAZ
Large Cryogenic above ground LNG Tank Full Containment (9% inner wall + Pre-stressed concrete outer wall) Typical Construction Sequence March 4 th 2011 Storage & loading on site Storage & loading on site
More informationTRANSPORTATION AND OTHER DAMAGE
TRANSPORTATION AND OTHER DAMAGE Effects of Wind Contact with an overpass Wind fallen tree damage Contact with a guard rail Contractor doing repairs for transit damage done by a transporter while shipping
More informationM R I C. MAERSK Reefer Inspection Criteria. (All Lines) (For use with all Refrigerated Containers (Reefers) in-service) Version 4: 2016
M R I C MAERSK Reefer Inspection Criteria (All Lines) (For use with all Refrigerated Containers (Reefers) in-service) Version 4: 2016 MRIC Version 4 (English) revised December 2015 Page 1 of 10 1. INTRODUCTION
More informationFinding the Root Cause is Critical
Finding the Root Cause is Critical Have you ever repaired a tube leak and put the boiler back in service, only to be forced off-line by another leak? Identifying and correcting the root cause is essential.
More informationHigh Energy Piping Inspection Program for Power Generation and Process Industries. For Regulatory Compliance, Safety, and System Longevity
High Energy Piping Inspection Program for Power Generation and Process Industries For Regulatory Compliance, Safety, and System Longevity EAPC Industrial Services offers an inspection plan for assessment
More informationINSPECTION GUIDELINES: JOIST AND UNDERFLOOR COMBO
Joist and Underfloor Combo Page 1 of 7 Revision Date: 10/02/2017 DEVELOPMENT SERVICES BUILDING INSPECTION INSPECTION GUIDELINES: JOIST AND UNDERFLOOR COMBO INSPECTION CODE: 212, 213 SCOPE: RESIDENTIAL
More informationapplications and fabric types fabric expansion joints
applications and fabric types typical applications Fabric expansion joints compliment the Radcoflex range of metal expansion joints, and provide a viable alternative in applications requiring a light weight
More informationEnvironmental Process Control Field Report 8-Oct-14
Environmental Process Control Field Report 8-Oct-14 Underwater Cleaning / Inspection Cathedral Water Co. Clearfork Tank Potable Water Storage Tank Submitted To: Environmental Process Control Alan Leslie
More informationElement C6.2 Generic Hazards and Modes of Failure
.2 Generic Hazards and Modes of Failure Common Machinery Hazards Procedures / permits Consider Operation Maintenance Cleaning Common Machinery Hazards Drills Entanglement Poorly guarded drive pulleys Chuck
More informationM C I C. MAERSK Container Inspection Criteria. (All Lines) (For use with all DRY Containers in-service) Version 7: 2016
M C I C MAERSK Container Inspection Criteria (All Lines) (For use with all DRY Containers in-service) Version 7: 2016 MCIC Version 7 (English) revised December 2015 Page 1 of 9 1. INTRODUCTION 1.1 General
More informationPhased Array Applications
Phased Array Applications Omniscan Phased Array Inspection of Plate/Butt Welds 40 degree beam 70 degree beam 2 Phased Array Inspection of Plate/Butt Welds Omniscan analysis view of one-line scan using
More informationBoiler Life and Availability Improvement Program - Program 63
Boiler Life and Availability Improvement Program - Program 63 Program Description Program Overview Safety and availability loss due to pressure part failures are two key issues driving R&D on major fossil
More informationsites under the deposit become anode and the lead to pitting. Hence, a good design should not allow the built up of impurities on surface
CORROSION CONTROL BY DESIGN As an old adage says corrosion prevention must start at the blackboard, at design stage, A good design is no more costly than a bad design. A bad design is always more expensive
More informationCentrifuge Information Sheet CI/08/1 Page 1 of 11. Inspection of Chemical Centrifuge Baskets DANGER IMPORTANT SAFETY INFORMATION
Centrifuge Information Sheet CI/08/1 Page 1 of 11 Thomas Broadbent and Sons Limited Centrifuge Division Information Sheet CI/08/1 Inspection of Chemical Centrifuge Baskets DANGER IMPORTANT SAFETY INFORMATION
More informationPSL/26 ISSUE 13 PCN CERTIFICATION AVAILABLE. Certification Services Division Newton Building, St George s Avenue Northampton, NN2 6JB
Certification Services Division Newton Building, St George s Avenue Northampton, NN2 6JB Tel: +44(0)1604-893-811. Fax: +44(0)1604-893-868. E-mail: pcn@bindt.org PSL/26 ISSUE 13 PCN CERTIFICATION AVAILABLE
More informationCoker Safety and Reliability Lessons Learned
Coker Safety and Reliability Lessons Learned Dale Wilborn 2015 Coking.com Conference COKER SAFETY & RELIABILITY Current Situation The Delayed Coker industry has had many incidents with severe consequences,
More informationCITY OF SELMA, TEXAS Inspection Guidelines: Residential
Selma, Texas, located in Bexar, Comal, and Guadalupe Counties Responsible party: Larry Verner, P.E. City Engineer Ph. (210) 651-7828 lverner@ci.selma.tx.us The Permits and Inspections Department welcomes
More informationFlow Accelerated Corrosion Failures in Gas to Liquids Plant ( Methane Gas Reforming Plant) Tsepo Ndou Senior Metallurgist PetroSA South Africa
Flow Accelerated Corrosion Failures in Gas to Liquids Plant ( Methane Gas Reforming Plant) Tsepo Ndou Senior Metallurgist PetroSA South Africa Introduction to Flow-Accelerated Corrosion Flow-accelerated
More informationMarina Coast Water District Marina, CA Steel Reservoir #2
WATER TANK INSPECTION REPORT Prepared for the Marina Coast Water District Marina, CA Steel Reservoir #2 October 26, 2005 490 Industrial Park Road Deep River, CT 06417 Tel: (860) 526-2610 Fax:(860) 526-5018)
More informationUBC Technical Guidelines Section Edition Thermal Insulation for Piping Page 1 of 5
Page 1 of 5 1.0 GENERAL 1.1 Related UBC Guidelines.1 Refer to Division 33 and Division 23 - Underground Steam and Condensate Piping.2 Refer to Division 23 - Steam and Condensate Piping Above Grade 1.2
More informationRadon Vent Pipe System. Labeling Performance Indicators
Section 6 Radon Vent Pipe Labeling Performance Indicators Radon Vent Pipe System Connected after sub-grade system installed Pipe cannot be trapped Provide space in chases Support at each floor level Discharge
More informationDe Montfort Mark 7 Incinerator (Flatpack)
De Montfort Mark 7 Incinerator (Flatpack) Introduction This design is specially for those occasions when a large number of incinerators are to be built at one location and transported to the places where
More information5. POST-EARTHQUAKE INSPECTION
5. POST-EARTHQUAKE INSPECTION When required by the building official, or recommended by the Interim Guidelines in Chapter 4, post-earthquake inspections of buildings may be conducted in accordance with
More informationCrawl Space Moisture Control
Crawl Space Moisture Control Crawl space foundations are found in many homes. Typically, these foundation types are equipped with operable vents designed to provide ventilation for moisture control. Unfortunately,
More informationB. Provide equipment complying with this specification and manufactured by one of the following:
SECTION 230910 PAINT SPRAY BOOTH PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide Paint Spray Booth, Prep Booth and Paint Mix Room, and associated ventilation equipment, complying with the
More informationCounty of Santa Barbara, California Facility Condition Assessment Total: $238,124. Appendix 1 Probable Cost Estimates Detail
Project No.:P03000.001 Building Number: P03000-Lompoc County Offices Grounds Project Description: Mill and Overlay with some Partial Depth Patching Background: The site comprises asphalt pavement for the
More informationModel # PR /21/2018 Page 1 of 10
Model # PR-32 11/21/2018 Page 1 of 10 1/21/2018 Page 2 of 10 1675 Locust Street Red Bud, IL 62278 Phone: 618-282-8200 Fax: 618-282-8202 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic
More information3. Roof Expansion Joints between New Building and Existing Building.
SECTION 077200 - ROOF ACCESSORIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Amendments to General Conditions and Division 01 Specification
More informationSuccess with 2009 IECC in Arkansas Tech Tips for Builders HVAC INSTALLATION
Success with 2009 IECC in Arkansas Tech Tips for Builders TECH TIPS: 1. Seal all duct work to drywall and/or subfloor and all HVAC penetrations in the building envelope with foam, caulk or mastic. Use
More informationThe use of Heavy Plate in the fabrication of Urea Pool Reactor
The use of Heavy Plate in the fabrication of Urea Pool Reactor (by F. Foroni, F. Fusari, N. Maestri, P. Marangoni, F. Orlandi) Abstract One of the principal items of high pressure equipment in the design
More informationOn-Line Diagnostics Techniques in the Oil, Gas, and Chemical Industry
On-Line Diagnostics Techniques in the Oil, Gas, and Chemical Industry 1. INTRODUCTION Lee Robins, Business Development Manager, Tracerco lee.robins@matthey.com Unfortunately, the vessels and pipelines
More informationCUI (CORROSION UNDER INSULATION) MECHANISM THEORY AND PRACTICE
CUI (CORROSION UNDER INSULATION) MECHANISM THEORY AND PRACTICE Prepared By: Mohammed AbuALRub SAFCO Reliability Dept. December 10, 2015 CONTENT Introduction CUI PhenomenaMain components of the cold insulation
More information1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.
PAGE 051200-1 SECTION 051200 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More informationENERGY solutions. Recover wasted energy to increase efficiency and save money immediately.
ENERGY recovery solutions Recover wasted energy to increase efficiency and save money immediately. Cleaver-Brooks Engineered Boiler Systems Manufacturers of HRSGs, Waste Heat Recovery Units, and Waste
More informationCorrosion Under Insulation Detection Methods and Inspection
Corrosion Under Insulation Detection Methods and Inspection June 18, 2013 NACE Section Meeting James Higgins PetroChem Inspection OVERVIEW General causes of CUI Suspect Areas- how to find and where to
More information2012 IPC Sections
Study Session 3 2012 IPC Sections 308 316 General Regulations II OBJECTIVE: To develop an understanding of those general provisions regarding plumbing systems that are not specifically addressed in other
More informationRamifications Of Cracks At The Fillet Welds Of High Temperature Steam Headers
Ramifications Of Cracks At The Fillet Welds Of High Temperature Steam Headers R W Coade 1, J D Butler 2 & D Zimmerman 2 1 HRL Technology Pty Ltd., e-mail: rcoade@hrl.com.au 2 ATCO Power Canada Ltd., Alberta,
More informationSulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard
Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard Introduction SRU s (Sulfur Recovery Units) are critical pieces of equipment in refineries and gas plants. SRUs remove sulfur compounds from certain
More information1. ARI 410 Standard for chilled water, hot water and steam coils. 2. ARI 430 Central Station Air Handling Units
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationPre-Fabricated Roof Curbs
Knock Down Curb Assembly Instructions These roof curb assembly instructions are to be used as general guidelines only. Included with shipment are as-built drawings for proper location of sections and channels.
More informationCentral Station Air Handler Specification
Central Station Air Handler Specification PART 1: GENERAL 1.01 WORK INCLUDED (Model CS 3 ) Mechanical Specification A. Provide complete air handling unit(s) suitable for indoor installation. Contractor
More informationCOMPUTATIONAL FLUID DYNAMICS IN EQUIPMENT DESIGN AND FAILURE ANALYSIS
COMPUTATIONAL FLUID DYNAMICS IN EQUIPMENT DESIGN AND FAILURE ANALYSIS Presented TXLA NACE Chapter October 15, 2013 Presented by Carl Matherne BASF TOTAL Petrochemicals Problem Background The BASF TOTAL
More informationINSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST
Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING
More informationRemote Digital Video Inspection
CASE STUDY Remote Digital Video Inspection (RDVI TM ) Case Studies Water Tube Boilers HRSG Boilers Condensate Return Systems Pressure Vessels Tanks Pressure Piping Heat Exchangers Fin Fans Gas Turbines
More information2015 IPC Sections 308 through 316
Study Session 3 2015 IPC Sections 308 through 316 General Regulations II OBJECTIVE: To develop an understanding of those general provisions regarding plumbing systems that are not specifically addressed
More information5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationView from the Penthouse
View from the Penthouse The DNFM Technical News Letter David N. French Metallurgists Ph: 502-955-9847 Fax: 502-957-5441 Web: www.davidnfrench.com Load Cycling As many coal-fired power plants designed for
More informationInspection of water injection pipelines and future needs. By: Mikael Georgson and Roger Hunsbedt. Statoil ASA
Inspection of water injection pipelines and future needs By: Mikael Georgson and Roger Hunsbedt Statoil ASA Abstract Statoil ASA has recently inspected several water injection pipelines that have shown
More informationSITE AND BUILDING INSPECTION CHECKLIST
PARISH BUILDING Page 1 of 6 SITE AND GROUNDS DATE INIT COMMENTS DATE INIT COMMENTS Ramps & Provisions for Handicap Designated parking spaces for Handicap Has soil dropped or heaved Is there standing water
More informationCombined Cycle HRSG and Balance of Plant - Program 88
Program Description Program Overview The design of modern heat recovery steam generators (HRSGs) and balance-of-plant (BOP) systems is a complex interrelationship between many parameters and variables.
More informationCoal-Fired Boiler Optimization
Hot Topic Coal-Fired Boiler Optimization Improving Boiler Efficiency September 27, 2012 By Richard F. (Dick) Storm, PE, CEO and Danny Storm, President Optimum Coal Fueled Steam Plant Performance Begins
More informationPULSED EDDY CURRENT (PEC) Lyft - Pulsed eddy current reinvented
PULSED EDDY CURRENT (PEC) Lyft - Pulsed eddy current reinvented 1 PRESENTATION CONTENT Applications and basics of the technology Compensated wall thickness feature (CWT), Dynamic mode feature, SmartPulse
More informationCanadian Natural Resources Ltd. GENERAL PRESSURE VESSEL INFORMATION Job #
District: Karr Creek Facility: Sturgeon Lake Battery Vessel Name Equipment Number: Oil Treater Orientation: Horizontal Canadian Natural Resources Ltd. GENERAL PRESSURE VESSEL INFORMATION Job # 10.113812
More informationOn-line corrosion mapping of industrial plant using advanced electrical resistance techniques
UK NDT 2002 Conf. On-line corrosion mapping of industrial plant using advanced electrical resistance techniques David M. Farrell and Bernard J. Robbins Rowan Technologies Ltd. Manchester M41 9DX, England.
More informationErrata for the 2003 Uniform Plumbing Code Study Guide (5th Printing)
Errata for the 2003 Uniform Plumbing Code Study Guide (5th Printing) The following is a list of changes that we found after the fifth printing of the 2003 Uniform Plumbing Code Study Guide. These changes
More information1.15 Chemical Tanker Longitudinal corrugated bulkhead (vertical type).
Table A.1 corrugated bulkhead s Case Ship Type Damage Location 1.1 Chemical Tanker Longitudinal corrugated bulkheads (horizontal type) in way of mid cargo area. 1.2 Product Tanker Transverse corrugated
More informationDESIGN GUIDELINE FLUID-APPLIED WATERPROOFING
DESIGN GUIDELINE FLUID-APPLIED WATERPROOFING (TO RESTORE EPDM MEMBRANES) PART 1 GENERAL 1.01 DESCRIPTION A. The scope of this design guideline is to describe the installation of the ALDOCOAT Silicone reflective
More informationFIELD COPY ATTACHMENT
FIELD COPY ATTACHMENT The released plans for the project must be on site and available to the inspectors at all times. No inspection will be done without the released field plans. If you have any questions,
More informationEncapsulated, Sealed & Closed Crawlspace Installation Manual
YourCrawlSpace, Inc. 1007 Johnni4 Dodds Blvd. Mt. Pleasant, SC 29464 Toll Free: 877-44-CRAWL (27295) Local: (843) 593-1115 Encapsulated, Sealed & Closed Crawlspace Installation Manual Copyright 2017 Your
More informationSCR Control Strategy and CEMS for an Ultra-Low NO x Emitter
SCR Control Strategy and CEMS for an Ultra-Low NO x Emitter Dale P. Evely, P.E. Harrison B. Manning Consulting Engineer Senior Engineer Instrumentation and Control Instrumentation and Control Southern
More informationSECTION MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN
SECTION 08350 MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationTank Inspection Report Town of Christiansburg, VA Hills Tank Liquid Engineering Corporation 36903
Tank Inspection Report Liquid Engineering Corporation 36903 GENERAL Tank Name: Type: On-Grade Standpipe City: Christiansburg Tank Capacity: 500,000 Gallon State: Virginia Type of Construction: Welded Steel
More informationCase Studies of Pulsed Eddy Current to Measure Wall Loss in Feedwater Heater Shells
Case Studies of Pulsed Eddy Current to Measure Wall Loss in Feedwater Heater Shells By Marvin J. Cohn Jordan W. Norton Power Inspection Consultants, Inc. ABSTRACT There have been several feedwater heater
More informationAPI 653 Training Course
API 653 Training Course The API 653 Classes consist of "Pre-Course Home Study" materials and "5 days of Classroom" instructor lead training. Registration for the API 653 Training Course should be received
More informationOptimization of FCCU Expansion Joint Application, System Design and Reliability Considerations. Tej Chadda Director, Technology Technical Services
Optimization of FCCU Expansion Joint Application, System Design and Reliability Considerations Tej Chadda Director, Technology Technical Services Optimization of FCCU Expansion Joint Expansion Joints in
More informationRECOVERY BOILER WATER AND FIRE SIDE DAMAGE MECHANISMS April 2015 Western Canada BLRBAC. Craig Reid, M.A.Sc., P.Eng. Acuren Group Inc., Richmond, B.C.
RECOVERY BOILER WATER AND FIRE SIDE DAMAGE MECHANISMS April 2015 Western Canada BLRBAC Craig Reid, M.A.Sc., P.Eng. Acuren Group Inc., Richmond, B.C. GENERAL CORROSION FAC (Alias erosion) Feedwater Piping
More informationGPA GCC (Corrosion in Gas Plants) 28 November 2007 (Bahrain)
Root Cause Analysis Booster Station 150 Stainless Steel Piping Failure Kuwait Oil Company Gas Management Group GPA GCC (Corrosion in Gas Plants) 28 November 2007 (Bahrain) M. F. Al-Otaibi, A. W. Al-Mithin
More informationSECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System
SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF MODULAR PAN SYSTEM PART 1 GENERAL 1.1
More informationInsulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS
Insulation First Revison October 2016 DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS 1. General Information This Guide describes the use of Kingspan GreenGuard DC14 Drainage
More informationWHITE PAPER The Criticality of Proactive Maintenance on Isolated Phase Bus Duct Systems
WHITE PAPER The Criticality of Proactive Maintenance on Isolated Phase Bus Duct Systems Introduction Isolated Phase Bus Duct (IPBD) is the main conduit for power distribution in a power generation facility.
More informationUBC Technical Guidelines Section Edition Insulation of Tanks, Steam and Condensate Piping Page 1 of 6
Page 1 of 6 1.0 GENERAL 1.1 Related UBC Guidelines.1 Refer to Division 33 and Division 23 - Underground Steam and Condensate Piping.2 Refer to Division 23 - Steam and Condensate Piping Above Grade.3 Section
More information