UNOPS BILL OF QUANTITIES
|
|
- Damon Summers
- 6 years ago
- Views:
Transcription
1 UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES BILL OF QUANTITIES Ai Khanem Border Crossing Point Facilities Takhar, Afghanistan Customs and Police Office Buildings NOTICE TO ALL BIDDERS COMPLETE PROJECT PRICE: 1. All bidders MUST examine the complete project documents. These documents include the Drawings, BOQ, Schedules and Specifications. Any discrepancies between these documents are to be brought to the immediate attention of 2. Quotation given by the contractor on this BOQ are to cover any and all additional materials, labor or associated costs to complete the works as documented on the complete project documents. 3. Eventual claims for extra works are covered by project general documentation of contract. Currency: Project No: Project Title: Location: 810 Ai Khanem Border Crossing Point Facilities Takhar, Afghanistan Tender Title: Customs and Police Office Buildings
2 Ai Khanem Border Crossing Point Facilities Takhar, Afghanistan Customs Office Building
3 UNOPS Vertical Structures Unit DETAILS OF COMPONENT Currency: Component: Customs Office Building 1. General Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 1.1 Preliminaries 1.1 Occupied Areas, 1.1 Existing Services Schedule and 1.1 Items to be supplied schedules 1 Preconstruction work, mobilisation activities including paper/ documentation tasks. LS Post construction works and clean up. LS General Requirements 1.2 Inspection notification schedule and 1.2 Warranty schedules 1 Testing and Operation/Maintenance Manuals. LS 1.00 Subtotal General 2. Site 2.3 Earthwork 2.1 Identified hazardous materials and 2.3 Earthwork schedules 1 Excavation (any soil type) for foundation. This item includes all excavations, disposal and temporary support or shoring if needed. See drawing and schedule for details. CU.M Ground improvement under foundations. This includes supplying of filling materials and compacting the layers according to schedule and drawings. CU.M 11 3 Soil backfilling on RCC math foundation up to ground level. This includes supplying of needed materials. See drawings and schedules for levels/dimensions and details. CU.M 19 4 Gravel compaction, Class 2, at any places under the PCC/RCC shown inside the building or at sidewalk/ramp. This includes supplying of needed materials. See drawing and project schedules for dimensions and details. CU.M Subtotal Site 3. Structure 3.1 ConcreteGeneral 3.1 Non reinforced concrete, 3.1 Reinforced concrete and 3.2 Concrete Integral Finishes schedules NOTE: Cost for concrete items in this section includes reinforcement, steel anchorage embedded in concrete, shuttering, concrete, concrete curing and all to the complete job. 1 PCC lean concrete (10 Mpa) under the RCC foundations. CU.M RCC (20 Mpa) foundations, rectangular and trapezoidal foundation beams. CU.M 14 3 PCC, 40mm thick, lean concrete (10 Mpa) at the floor over the gravel compaction. CU.M /24
4 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 4 PCC concrete, 100mm thick, (20 Mpa) at the floor over the waterproofing layer. This item includes the stairs steps at the entrances and the ramps. CU.M RCC Columns, includes all columns (from 1.65 to +3.55) and supporting columns/ring beams for trusses on the roof. CU.M RCC (20 Mpa) slabs and beams. The items covers all slabs, beams and RCC floor for the bank. CU.M RCC Pavement (20 Mpa), for 1000mmwide side walks. This includes entrances and ramps. The cost includes expansion joint on side walk surface as shown and as well as the broom finish to the side walk/ ramp surfaces. CU.M Precast RC Concrete 3.3 Precast Concrete Prototypes Schedule 1 Precast RCC (20 Mpa) exterior window sill for all windows as per drawings. This includes all work need for complete installation. Lin M Brickwork 3.5 Brickwork construction schedule 1 Second Class Brick masonry with mortar. This includes all brick walls/ brick masonry in the entire building. The cost includes steel bars shown in the walls and their connection to the perimeter RCC elements. CU.M Light Timberwork 3.9 Light Timberwork schedule, 6.6 Interior painting and 6.6 Exterior painting schedules 1 Roof timber structure on the trusses. The cost includes 30mm thick wooden planks as shown on the drawing. This also cover all auxiliary and needed materials and supplying and installation of members including painting to make the surface ready for folded metal sheet roofing according to the drawing, schedule and specifications. SQ.M Concrete Unit Masonry 3.10 Concrete Unit Masonry 1 CMU masonry with mortar. This item covers all CMU works shown on the drawings for the building. The cost includes all needed materials, steel bars, anchors etc and works. CU.M Structural Steel 3.11 Structural Steel Schedules NOTE: Cost for steel related items in this section includes supplying materials and installation to the complete condition for all members, gussets, fasteners, connections, welding and other accessories and works needed to complete the job. The cost also includes painting according to the schedules and specifications for steel member painting, which is at least on coat of antirust followed by 2 other coats of oilbased painting for all surfaces and sides of the steel members. 1 Steel support, purlin, at the metal sheet roof as (Cshape 140x65mm + Lshape 50x50mm). See drawing for details. Lin M 56 2 Steel truss (TRUSS 1) at the roof. See drawing for details. No Steel truss (TRUSS 2) at the roof. See drawing for details. No Steel truss (TRUSS 3) at the roof. See drawing for details. No /24
5 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 5 Steel truss (TRUSS 4) at the roof. See drawing for details. No Steel truss (TRUSS 5) at the roof. See drawing for details. No Steel truss (TRUSS 6) at the roof. See drawing for details. No Steel truss (TRUSS 7) at the roof. See drawing for details. No Steel truss (TRUSS 8) at the roof. See drawing for details. No Steel truss (TRUSS 9) at the roof. See drawing for details. No Steel truss (TRUSS 10) at the roof. See drawing for details. No Steel truss (TRUSS 11) at the roof. See drawing for details. No Steel frame fixed ladder inside the toilet as the access way to the roof. The work and the cost includes construction of fixed later to the wall and the opening pane, its hardware and other accessories to complete the installation as per drawing and schedule. This also includes painting according to the schedules and specifications for steel surfaces painting. LS 1.00 Subtotal Structure 4. Enclosure 4.1 Waterproofing 4.1 Waterproofing system schedule 1 Bitumen waterproofing coat. This is a 35mm thick hot bitumen painting coats on dried PCC surface. The item applies on 40mm PCC at the floor beneath the 20 Mpa, 100mm thick PCC layer. This cost includes supplying and applying the coats with all needed accessories and work to do the job as per manufacturer's data and to the full satisfaction of UNOPS engineer. 2 Single layer bitumen membrane at the floor and walls of toilets/kitchen. This includes preparation of base layers shown on the drawings. Refer to schedule/drawing for details. 4.2 Roofing 4.2 Roofing materials, and 4.2 Gutter and Down pipe Schedules 1 Standing seam metal roofing (using GI sheet gauge 24). This includes all accessories required for installation of roof on the prepared timber plank (see item for the cost of timber plank on roof). The cost also includes all flashings, capping etc needed on the metal roof. 2 Metallic gutter around the roof (using GI sheet gauge 20). The cost includes all accessories required for complete installation of gutter such as supplying, fixing and others as per drawing and schedules. 3 Down pipes, PVC pipe classb. This includes all accessories required for complete installation such as supplying, fixing and others as per drawing and schedules. SQ.M 47 SQ.M SQ.M 68 Lin M Lin M /24
6 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 4.3 Windows and Window Hardware 4.3 Window, 4.3 Window Hardware, 4.5 Annealed Glasses, and 4.6 Glassblock work schedules 1 Wooden frame windows. The work includes making, transportation, installation, hardware, glazing, glassblock work around window, insect screen, 3 coats of oilbased painting, and other accessories required for complete installation as per drawings and schedule. 4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors, 4.4 Steel doors and 4.5 Annealed Glasses schedules SQ.M Wooden frame doors. The work includes making, transportation, installation, hardware, glazing, and other accessories required for complete installation as per drawings and schedule. SQ.M PVC frame doors. The work includes making, transportation, installation, hardware, glazing, and other accessories required for complete installation as per drawings and schedule. SQ.M Steel frame doors. The work includes making, transportation, installation, hardware, glazing, 1 coat of antirust followed by 2 other coats of oilbased painting, and other accessories required for complete installation as per drawings and schedule. SQ.M Glazing 4.5 Mirrors schedules 1 Mirrors (40x60cm) at toilets. This includes complete installation. No Insulation and Vapour Barriers 4.7 Insulation Schedules 1 Glasswool thermal insulation on RCC roof, beneath roof structure. See drawings and schedules for details. SQ.M Exterior Insulation and Finish System 4.8 EFIS Schedules 1 External wall insulation system, STOTHERM CLASSIC, (expanded polystyrene foam and organically bound render) "or equivalent ". See drawing and schedule for location and detail. The cost includes one preparation layer of cement render and all other process required for a complete job as per product's manufacturer data and UNOPS engineer satisfaction. Subtotal enclosure SQ.M Interior 5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule 6/24
7 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 1 Lasani wooden board, 16mmm, fixed ceiling for all soffits around the building. The cost includes all framing, fixing, oil based painting and needed work for a complete job to the full satisfaction of Engineer. SQ M Gypsum board, 16mmm, reflected ceiling for the side entrances of the building. The cost includes all framing, fixing, and needed work for complete job. SQ M Joinery 5.5 Joinery fixtures schedule 1 Wooden frame, MDF finish, wall mounted cabinet at the kitchen. See drawings for details. The cost includes making, installation, framing, hardware, finish, 3 coats oilbased painting and all to the complete job. LS Wooden frame, MDF finish, floor mounted cupboard at the kitchen. See drawings for details. The cost includes making, installation, framing, finish, hardware, stone table top, splash back, 3 coats oilbased painting and all to the complete job. LS Metalwork 5.6 Metal Fixtures Schedule 1 Metallic plaster beads for outer corners at the corridors only, including edge of walls. This includes any needed work for complete installation. See schedules and drawings for details. Lin M 7 2 Toilet roll holders. This also includes installation. No Grab rail for handicap toilet. One complete set. This includes supplying and complete installation. LS Soap dishes. This also includes installation. No Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule 1 Extinguishers, wall mounted, powdertype (9kg). No 4.00 Subtotal Interior 6. Finish 6.1 Plastering 6.1 Plastering Schedule Internal surfaces 1 Cement render medium CRM followed by cement render fine CRF on all internal surfaces of walls/ ceilings/ beams/ columns/ reveals. See schedule for detail. SQ.M 1,10 External surfaces 2 Gypsum board, decorative finish, at both main entrances foreheads. The cost includes supplying, making, installation and all to the complete condition as per Engineer's approval. 6.2 Cementitious Toppings 6.2 Cementitious Toppings Schedule SQ.M 4 7/24
8 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 1 In situ colored chips, colored mortar terrazzo, including marble trims for joints, for all floors as shown on the drawing. See schedule for details. The cost also includes stainless steel nosing at the outer edges of the stair steps at the entrances. SQ.M Tiling 6.3 Wall tiling and 6.3 Floor tiling schedules 1 Ceramic wall tiles for toilets, kitchen, around the drinking water fountain and any place shown. The cost includes bed preparation, bedding and grout. SQ.M 7 2 Ceramic floor tiles for toilets including bed preparation, bedding and grout. SQ.M Marble skirting for all rooms and halls where did not receive ceramic tiles. The cost includes bedding and grout. Lin M Painting 6.6 Interior/Exterior painting schedule Internal surfaces 1 Flat water based: Interior, on all surfaces that receive cement plaster. The cost includes wall putty (gypsum filling) layer before painting and all needed preparation of the surfaces for painting. See schedule for detail on this paint system SQ.M 1,10 Subtotal Finishes 8. Water Services 8.1 Water Services 8.1 Water services samples, 8.1 Water system piping, 8.1 Sanitary fixtures, 8.1 Water heater schedules and 8.1 Water Services Testing schedules NOTE: The cost for all pipes exposed to weather includes glass wool thermal insulation cover. The cost given for all GI and PVC pipes with diameter less than 60mm includes all required fittings, accessories and work for complete system installation. Water supply piping 1 GI water supply pipe D=32mm, including fittings and installation. Lin M 3 2 GI water supply pipe D=25mm, including fittings and installation. Lin M GI water supply pipe D=20mm, including fittings and installation. Lin M GI water supply pipe D=15mm, including fittings and installation. Lin M 5 5 Water supply bronze Valve D=32mm, including fittings and installation. No Water supply bronze Valve D=20mm, including fittings and installation. No Damp proof Insulation rubber tape for all GI Piping. Lin M 15 8 Water supply inspection manhole less than 1200mm deep. This includes excavation and any needed work to make the manhole as per drawings and schedule. No /24
9 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost Sanitation Piping 9 PVC pipe D=100mm, including supply and installation. This also includes supply and installation of PVC pipe from GI sheet downpipes to the open channel collector at the side walks. Lin M PVC pipe D=50mm, including fittings and installation. Lin M 5 11 Ventilation PVC pipes D=100mm (from toilets to roof). This also includes supplying and installation of PVC screen at the pipe inlets inside the toilets. See drawing and schedule for details. Lin M Ventilation PVC pipes D=50mm (from toilets to roof). This also includes supplying and installation of PVC screen at the pipe inlets inside the toilets. See drawing and schedule for details. Lin M 1 13 PVC Elbow D=100x100,45, including supply and installation. No PVC Tee D=100x100, 45, including supply and installation. No Sanitation Grease Trap less than 1200mm deep. This includes excavation and any needed work to make the manhole according to the drawings and schedules. No 1.00 Sanitary and other fixtures 16 Western toilet, including supply, installation and accessories. No Water fountain, including supply, installation and accessories. No Ceramic sink at toilets and labs, including mixer and all accessories, supplying and installation. No Floor trap D=50mm, including supply and installation. No Stainless steel sink, including supply and installation. No Ventilation cap D=100mm, including supply and installation. No Ventilation cap D=50mm, including supply and installation. No Service Sink, including supply and installation. No Electrical water boiler with capacity of 50 Liter, including supply and installation. No Electrical water boiler with capacity of 30 Liter, including supply and installation. No Sewer Manholes More than 1200mm deep. This includes excavation and any needed work to make the manhole according to the drawings and schedules. No 2.00 Subtotal Water Services 9. Electrical Services 9.1 Electrical Services 9.1 Electrical systems, 9.1 Electrical supply mains, 9.1 Electrical switchboard design, 9.1 Main 380VAC Distribution System, 9.1 Panel Construction, 9.1 Power accessories, 9.1 Lighting control and fittings, 9.1 Fire Detection Equipment Schedule Schedules and the Attachments 9/24
10 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost Note: for all items below the cost includes complete/installations with all needed accessories and works. Switchboard and sub boards 1 Sub distribution panel, 750x500x250 mm, powder coated, weatherproof, outdoor mounted metal. With Digital Measurement equipments. No Main circuit breaker, MCCB, 3x160Amps, Type C. No Circuit breaker, MCB, 1x32Amps, TypeC No Circuit breaker, MCB, 1x20Amps, TypeC No Distribution wiring 5 3 (1X6mm2) wires pulled in 24mm PVC Conduit, assorted colors as per phase requirement RST/UVW, white color for neutral and green color for grounding. Lin M (1X4mm2) wires pulled in 24mm PVC Conduit, assorted colors as per phase requirement RST/UVW, white color for neutral and green color for grounding. Lin M 1,50 Fittings/Fixtures 7 Single pole/double pole or two way light switch. No W circular surface ceiling mount, IP54 fluorescent light fixture. No W circular Pendant ceiling mount, IP54 fluorescent light fixture with all accessories. No W Circular Surface ceiling mount, IP54 fluorescent light fixture with all accessories. No x36W pendant ceiling mounted fluorescent light fixture, IP44.with all accessories. No x36W pendant ceiling mounted fluorescent light fixture, IP56. with all accessories. No Amp Duplex power receptacle. No Amp single water proof power receptacle. No Amp single water proof power receptacle for electrical water heater and kitchen. No 9.00 AC/Split Units and Exhaust fans BTU AC/ Split unit 220 V, 50 HZ Samsung made in Italy with all accessories. No Roof mounted exhaust fans. No Amp single electrical nonfuse disconnecting switch for AC/ Split unit. No Emergency evacuation lighting 19 2x10 watt IP65 wall mounted Emergency Light Fixture. No X10W surface mounted IP40 Exit light. No 4.00 Fire alarm system (including all associated cabling, wiring, mounting, etc) 21 Addressable fire alarm panel, with all accessories, to the complete and functioning job. LS Fire alarm push button, double action type, UL Listed No Fire alarm No Photoelectric type smoke detectors, UL Listed No Electrical Grounding and Lightning Protection. 10/24
11 Component: Customs Office Building Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost 25 Lightening protection as mentioned in lightening protection drawing with air terminal, electrodes, tape, connectors, clamp and grounding cable Set Grounding system as mentioned in grounding drawing with electrodes, tape, connectors, clamp and grounding cable Set 1.00 Labeling 27 Proper and correct all circuits numbering, cable circuit drawings, cable and switchboard labeling to the full satisfaction of UNOPS engineer. Subtotal Electrical Services LS /24
12 UNOPS Vertical Structures Unit SUMMARY OF COMPONENT Currency: Component: Customs Office Building Work Type Total for General Total for Site Total for Structure Total for Enclosure Total for Interior Total for Finish Total for Water Supply Services Total for Electrical Services Total for Customs Office Building
13 Ai Khanem Border Crossing Point Facilities Takhar, Afghanistan Police Office Building
14 UNOPS Vertical Structures Unit DETAILS OF COMPONENT Currency: Component: Police Office Building 1. General Description of Work/Items Unit Quantity Unit Cost Total Cost 1.1 Preliminaries 1.1 Occupied Areas, 1.1 Existing Services Schedule and 1.1 Items to be supplied schedules 1 Preconstruction work, mobilisation activities including paper/ documentation tasks. 2 Post construction works and clean up. 1.2 General Requirements 1.2 Inspection notification schedule and 1.2 Warranty schedules 1 Testing and Operation/Maintenance Manuals. Subtotal General LS 1.00 LS 1.00 LS Site 2.3 Earthwork 2.1 Identified hazardous materials and 2.3 Earthwork schedules 1 Excavation (any soil type) for foundation. This item includes all excavations, disposal and temporary support or shoring if needed. See drawing and schedule for details. CU.M 19 2 Ground improvement under foundations. This includes supplying of filling materials and compacting the layers according to schedule and drawings. CU.M Soil backfilling on RCC math foundation up to ground level. This includes supplying of needed materials. See drawings and schedules for levels/dimensions and details. CU.M Gravel compaction, Class 2, at any places under the PCC/RCC shown inside the building or at sidewalk/ramp. This includes supplying of needed materials. See drawing and project schedules for dimensions and details. CU.M 6 Subtotal Site 3. Structure 3.1 ConcreteGeneral 3.1 Non reinforced concrete, 3.1 Reinforced concrete and 3.2 Concrete Integral Finishes schedules NOTE: Cost for concrete items in this section includes reinforcement, steel anchorage embedded in concrete, shuttering, concrete, concrete curing and all to the complete job. 1 PCC lean concrete (10 Mpa) under the RCC foundations. CU.M 1 2 RCC (20 Mpa) foundations, rectangular and trapezoidal foundation beams. CU.M PCC, 40mm thick, lean concrete (10 Mpa) at the floor over the gravel compaction. CU.M /24
15 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 4 PCC concrete, 100mm thick, (20 Mpa) at the floor over the waterproofing layer. This item includes the stairs steps at the entrances and the ramps. CU.M RCC Columns, includes all columns (from 1.65 to +3.55) and supporting columns/ring beams for trusses on the roof. CU.M RCC (20 Mpa) slabs and beams. The items covers all slabs, beams and RCC floor for the bank. CU.M RCC Pavement (20 Mpa), for 1000mmwide side walks. This includes entrances and ramps. The cost includes expansion joint on side walk surface as shown and as well as the broom finish to the side walk/ ramp surfaces. CU.M Precast RC Concrete 3.3 Precast Concrete Prototypes Schedule 1 Precast RCC (20 Mpa) exterior window sill for all windows as per drawings. This includes all work need for complete installation. Lin M Brickwork 3.5 Brickwork construction schedule 1 Second Class Brick masonry with mortar. This includes all brick walls/ brick masonry in the entire building. The cost includes steel bars shown in the walls and their connection to the perimeter RCC elements. CU.M Light Steelwork 3.7 Light Steelwork, 6.6 Interior painting and 6.6 Exterior painting schedules NOTE: The following steel items include painting according to the schedules and specifications for steel member painting for complete installation. See drawing for details. 1 Steel frame cabinet for FirstAidKits at the hall of Police Office Building. The item and its cost include making, transportation, installation, hardware, finishes and all other accessories and work required for a complete cabinet to the full satisfaction of the Engineer. 2 Steel frame cabinets for Weapon Storages at the hall of Police Office Building. The item and its cost include making, transportation, installation, hardware, finishes and all other accessories and work required for a complete cabinet to the full satisfaction of the Engineer. 3.9 Light Timberwork 3.9 Light Timberwork schedule, 6.6 Interior painting and 6.6 Exterior painting schedules 1 Roof timber structure on the trusses. The cost includes 30mm thick wooden planks as shown on the drawing. This also cover all auxiliary and needed materials and supplying and installation of members including painting to make the surface ready for folded metal sheet roofing according to the drawing, schedule and specifications Concrete Unit Masonry 3.10 Concrete Unit Masonry LS 1.00 LS 1.00 SQ.M /24
16 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 1 CMU masonry with mortar. This item covers all CMU works shown on the drawings for the building. The cost includes all needed materials, steel bars, anchors etc and works Structural Steel 3.11 Structural Steel Schedules NOTE: Cost for steel related items in this section includes supplying materials and installation to the complete condition for all members, gussets, fasteners, connections, welding and other accessories and works needed to complete the job. The cost also includes painting according to the schedules and specifications for steel member painting, which is at least on coat of antirust followed by 2 other coats of oilbased painting for all surfaces and sides of the steel members. 3.7 Light Steelwork Schedule CU.M Steel support, purlin, at the metal sheet roof as (Cshape 140x65mm + Lshape 50x50mm). See drawing for details. Lin M 44 2 Steel truss (TRUSS 1) at the roof. See drawing for details. No Steel truss (TRUSS 2) at the roof. See drawing for details. No Steel truss (TRUSS 3) at the roof. See drawing for details. No Steel truss (TRUSS 4) at the roof. See drawing for details. No Steel truss (TRUSS 5) at the roof. See drawing for details. No Steel truss (TRUSS 6) at the roof. See drawing for details. No Steel truss (TRUSS 7) at the roof. See drawing for details. No Steel truss (TRUSS 8) at the roof. See drawing for details. No Steel truss (TRUSS 9) at the roof. See drawing for details. No Steel truss (TRUSS 10) at the roof. See drawing for details. No Steel truss (TRUSS 11) at the roof. See drawing for details. No Steel frame fixed ladder inside the toilet as the access way to the roof. The work and the cost includes construction of fixed later to the wall and the opening pane, its hardware and other accessories to complete the installation as per drawing and schedule. This also includes painting according to the schedules and specifications for steel surfaces painting. LS 1.00 Subtotal Structure 4. Enclosure 4.1 Waterproofing 4.1 Waterproofing system schedule 1 Bitumen waterproofing coat. This is a 35mm thick hot bitumen painting coats on dried PCC surface. The item applies on 40mm PCC at the floor beneath the 20 Mpa, 100mm thick PCC layer. This cost includes supplying and applying the coats with all needed accessories and work to do the job as per manufacturer's data and to the full satisfaction of UNOPS engineer. SQ.M 36 16/24
17 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 2 Single layer bitumen membrane at the floor and walls of toilets/kitchen. This includes preparation of base layers shown on the drawings. Refer to schedule/drawing for details. SQ.M Roofing 4.2 Roofing materials, and 4.2 Gutter and Down pipe Schedules 1 Standing seam metal roofing (using GI sheet gauge 24). This includes all accessories required for installation of roof on the prepared timber plank (see item for the cost of timber plank on roof). The cost also includes all flashings, capping etc needed on the metal roof. SQ.M Metallic gutter around the roof (using GI sheet gauge 20). The cost includes all accessories required for complete installation of gutter such as supplying, fixing and others as per drawing and schedules. Lin M Down pipes, PVC pipe classb. This includes all accessories required for complete installation such as supplying, fixing and others as per drawing and schedules. Lin M Windows and Window Hardware 4.3 Window, 4.3 Window Hardware, 4.5 Annealed Glasses, and 4.6 Glassblock work schedules 1 Wooden frame windows. The work includes making, transportation, installation, hardware, glazing, glassblock work around window, insect screen, 3 coats of oilbased painting, and other accessories required for complete installation as per drawings and schedule. 4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors, 4.4 Steel doors and 4.5 Annealed Glasses schedules SQ.M 5 1 Wooden frame doors. The work includes making, transportation, installation, hardware, glazing, and other accessories required for complete installation as per drawings and schedule. SQ.M 6 2 PVC frame doors. The work includes making, transportation, installation, hardware, glazing, and other accessories required for complete installation as per drawings and schedule. SQ.M Steel frame doors. The work includes making, transportation, installation, hardware, glazing, 1 coat of antirust followed by 2 other coats of oilbased painting, and other accessories required for complete installation as per drawings and schedule. SQ.M Glazing 4.5 Mirrors schedules 1 Mirrors (40x60cm) at toilets. This includes complete installation. No Insulation and Vapour Barriers 4.7 Insulation Schedules 1 Glasswool thermal insulation on RCC roof, beneath roof structure. See drawings and schedules for details. SQ.M /24
18 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 4.8 Exterior Insulation and Finish System 4.8 EFIS Schedules 1 External wall insulation system, STOTHERM CLASSIC, (expanded polystyrene foam and organically bound render) "or equivalent ". See drawing and schedule for location and detail. The cost includes one preparation layer of cement render and all other process required for a complete job as per product's manufacturer data and UNOPS engineer satisfaction. SQ.M 25 Subtotal enclosure 5. Interior 5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule 1 Lasani wooden board, 16mmm, fixed ceiling for all soffits around the building. The cost includes all framing, fixing, oil based painting and needed work for a complete job to the full satisfaction of Engineer. SQ M Gypsum board, 16mmm, reflected ceiling for the side entrances of the building. The cost includes all framing, fixing, and needed work for complete job. SQ M Joinery 5.5 Joinery fixtures schedule 1 Wooden frame, MDF finish, wall mounted cabinet at the kitchen. See drawings for details. The cost includes making, installation, framing, hardware, finish, 3 coats oilbased painting and all to the complete job. LS Wooden frame, MDF finish, floor mounted cupboard at the kitchen. See drawings for details. The cost includes making, installation, framing, finish, hardware, stone table top, splash back, 3 coats oilbased painting and all to the complete job. LS Metalwork 5.6 Metal Fixtures Schedule 1 Metallic plaster beads for outer corners at the corridors only, including edge of walls. This includes any needed work for complete installation. See schedules and drawings for details. Lin M Toilet roll holders. This also includes installation. No Grab rail for handicap toilet. One complete set. This includes supplying and complete installation. LS Soap dishes. This also includes installation. No Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule 1 Extinguishers, wall mounted, powdertype (9kg). No 4.00 Subtotal Interior 6. Finish 6.1 Plastering 6.1 Plastering Schedule 18/24
19 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost Internal surfaces 1 Cement render medium CRM followed by cement render fine CRF on all internal surfaces of walls/ ceilings/ beams/ columns/ reveals. See schedule for detail. SQ.M 88 External surfaces 2 Gypsum board, decorative finish, at both main entrances foreheads. The cost includes supplying, making, installation and all to the complete condition as per Engineer's approval. 6.2 Cementitious Toppings 6.2 Cementitious Toppings Schedule SQ.M 4 1 In situ colored chips, colored mortar terrazzo, including marble trims for joints, for all floors as shown on the drawing. See schedule for details. The cost also includes stainless steel nosing at the outer edges of the stair steps at the entrances. SQ.M Tiling 6.3 Wall tiling and 6.3 Floor tiling schedules 1 Ceramic wall tiles for toilets, kitchen, around the drinking water fountain and any place shown. The cost includes bed preparation, bedding and grout. SQ.M 7 2 Ceramic floor tiles for toilets including bed preparation, bedding and grout. SQ.M Marble skirting for all rooms and halls where did not receive ceramic tiles. The cost includes bedding and grout. Lin M Painting 6.6 Interior/Exterior painting schedule Internal surfaces 1 Flat water based: Interior, on all surfaces that receive cement plaster. The cost includes wall putty (gypsum filling) layer before painting and all needed preparation of the surfaces for painting. See schedule for detail on this paint system SQ.M 88 Subtotal Finishes 8. Water Services 8.1 Water Services 8.1 Water services samples, 8.1 Water system piping, 8.1 Sanitary fixtures, 8.1 Water heater schedules and 8.1 Water Services Testing schedules NOTE: The cost for all pipes exposed to weather includes glass wool thermal insulation cover. The cost given for all GI and PVC pipes with diameter less than 60mm includes all required fittings, accessories and work for complete system installation. Water supply piping 1 GI water supply pipe D=32mm, including fittings and installation. Lin M 3 19/24
20 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 2 GI water supply pipe D=25mm, including fittings and installation. Lin M GI water supply pipe D=20mm, including fittings and installation. Lin M GI water supply pipe D=15mm, including fittings and installation. Lin M Water supply bronze Valve D=32mm, including fittings and installation. No Water supply bronze Valve D=20mm, including fittings and installation. No Damp proof Insulation rubber tape for all GI Piping. Lin M 20 8 Water supply inspection manhole less than 1200mm deep. This includes excavation and any needed work to make the manhole as per drawings and schedule. No 4.00 Sanitation Piping 9 PVC pipe D=100mm, including supply and installation. This also includes supply and installation of PVC pipe from GI sheet downpipes to the open channel collector at the side walks. Lin M 5 10 PVC pipe D=50mm, including fittings and installation. Lin M Ventilation PVC pipes D=100mm (from toilets to roof). This also includes supplying and installation of PVC screen at the pipe inlets inside the toilets. See drawing and schedule for details. Lin M Ventilation PVC pipes D=50mm (from toilets to roof). This also includes supplying and installation of PVC screen at the pipe inlets inside the toilets. See drawing and schedule for details. Lin M PVC Elbow D=100x100,45, including supply and installation. No 1 14 PVC Tee D=100x100, 45, including supply and installation. No Sanitation Grease Trap less than 1200mm deep. This includes excavation and any needed work to make the manhole according to the drawings and schedules. No 1.00 Sanitary and other fixtures 16 Western toilet, including supply, installation and accessories. No Water fountain, including supply, installation and accessories. No Ceramic sink at toilets and labs, including mixer and all accessories, supplying and installation. No Floor trap D=50mm, including supply and installation. No Stainless steel sink, including supply and installation. No Ventilation cap D=100mm, including supply and installation. No Ventilation cap D=50mm, including supply and installation. No Service Sink, including supply and installation. No Electrical water boiler with capacity of 50 Liter, including supply and installation. No Electrical water boiler with capacity of 30 Liter, including supply and installation. No /24
21 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 26 Sewer Manholes More than 1200mm deep. This includes excavation and any needed work to make the manhole according to the drawings and schedules. No 3.00 Subtotal Water Services 9. Electrical Services 9.1 Electrical Services 9.1 Electrical systems, 9.1 Electrical supply mains, 9.1 Electrical switchboard design, 9.1 Main 380VAC Distribution System, 9.1 Panel Construction, 9.1 Power accessories, 9.1 Lighting control and fittings, 9.1 Fire Detection Equipment Schedule Schedules and the Attachments Note: for all items below the cost includes complete/installations with all needed accessories and works. Switchboard and sub boards 1 Sub distribution panel, 750x500x250 mm, powder coated, weatherproof, outdoor mounted metal. With Digital Measurement equipments. No Main circuit breaker, MCCB, 3x160Amps, TypeC. No Circuit breaker, MCB, 1x32Amps, TypeC No Circuit breaker, MCB, 1x20Amps, TypeC No. 3 Distribution wiring 5 3 (1X6mm2) wires pulled in 24mm PVC Conduit, assorted colors as per phase requirement RST/UVW, white color for neutral and green color for grounding. Lin M (1X4mm2) wires pulled in 24mm PVC Conduit, assorted colors as per phase requirement RST/UVW, white color for neutral and green color for grounding. Lin M 90 Fittings/Fixtures 7 Single pole/double pole or two way light switch. No W circular surface ceiling mount, IP54 fluorescent light fixture. No W circular Pendant ceiling mount, IP54 fluorescent light fixture with all accessories. No W Circular Surface ceiling mount, IP54 fluorescent light fixture with all accessories. No x36W pendant ceiling mounted fluorescent light fixture, IP44.with all accessories. No x36W pendant ceiling mounted fluorescent light fixture, IP56. with all accessories. No Amp Duplex power receptacle. No Amp single water proof power receptacle. No Amp single water proof power receptacle for electrical water heater and kitchen. No AC/Split Units and Exhaust fans BTU AC/ Split unit 220 V, 50 HZ Samsung made in Italy with all accessories. No /24
22 Component: Police Office Building Description of Work/Items Unit Quantity Unit Cost Total Cost 17 Roof mounted exhaust fans. No Amp single electrical nonfuse disconnecting switch for AC/ Split unit. No 8.00 Emergency evacuation lighting 19 2x10 watt IP65 wall mounted Emergency Light Fixture. No X10W surface mounted IP40 Exit light. No 4.00 Fire alarm system (including all associated cabling, wiring, mounting, etc) 21 Addressable fire alarm panel, with all accessories, to the complete and functioning job. LS Fire alarm push button, double action type, UL Listed No Fire alarm No Photoelectric type smoke detectors, UL Listed No Electrical Grounding and Lightning Protection. 25 Lightening protection as mentioned in lightening protection drawing with air terminal, electrodes, tape, connectors, clamp and grounding cable Set Grounding system as mentioned in grounding drawing with electrodes, tape, connectors, clamp and grounding cable Set 1.00 Labeling 27 Proper and correct all circuits numbering, cable circuit drawings, cable and switchboard labeling to the full satisfaction of UNOPS engineer. LS 1.00 Subtotal Electrical Services 22/24
23 UNOPS Vertical Structures Unit SUMMARY OF COMPONENT Currency: Component: Police Office Building Work Type Total for General Total for Site Total for Structure Total for Enclosure Total for Interior Total for Finish Total for Water Supply Services Total for Electrical Services Total for Police Office Building
24 UNOPS Vertical Structures Unit SUMMARY BILL OF QUANTITIES Currency: Tender Title: Customs and Police Office Buildings CONTRACT COMPONENTS Total for Customs Office Building Total for Police Office Building BOQ Value for whole tender in words: Zero Agreed on behalf of Contractor Name Position Signature UNOPS Name Position Signature Address and Mobile Number
UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan
UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ Original Issue Bamyan MAC Site Services Phase Bamyan, Bamyan, Afghanistan Project Components:. Site Services Phase NOTICE TO ALL BIDDERS COMPLETE
More informationPND Training Hall Conex Building, Kabul ABSTRACT OF COST
PND Training Hall Conex Building, Kabul ABSTRACT OF COST A Civil Works All work items shall be carried as per drawing, specification and instruction of the Engineer. 1 Sub-structure Works Earthwork in
More informationUNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Kabul University Project - Site Office Mobilization Kabul, Afghanistan
UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ Original Issue Kabul University Project Site Office Mobilization Kabul, Afghanistan Project Components: 1. Site Office Establishment NOTICE
More informationIslamic Republic of Afghanistan Ministry of Interior Affairs Central Prison Directorate
Islamic Republic of Afghanistan Ministry of Interior Affairs Central Prison Directorate Appendix II: Bill of Quantity for the construction of Boundary wall,guard towers, Check point,guard house, Access
More informationThe International Committee of the Red Cross
The International Committee of the Red Cross WATER & HABITAT DEPARTMENT Rozhawa / Hospital / Rehabiliation Phase II Rozhawa Hospital / Erbil City / Erbil 25 - February - 217 Rozhawa / Hospital / Rehabiliation
More informationSINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS Contractors General Conditions Site Works Setting out works: Rates
SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS 01000 Contractors General Conditions 02000 Site Works Setting out works: Rates shall include but not limited to all necessary equipments,
More informationUnit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M.
Bill of Quantities Nature of work : Construction of Health Center with 8 rooms (Clinics, Pharmacy, Labs, Fence & Latrines) Location: Shakreen- El Fasher Town- North Darfur State No. Description Qty Unit
More informationProject Manual Index of Specifications Shenandoah Schools Concession Building
INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationDevelopment of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL.
Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities for SIX CHAMBER VIP LATRINE FACILITY LOCATED AT PRIMARY & SECONDARY SCHOOL YEI RIVER COUNTY South Sudan JUN,
More informationThe Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits
The Compass ( 270 Lisgar Street, Brighton ) Features General Site Work 1. Construction Drawings 2. Building, Plumbing Electrical and Entrance Permits 3. Development and Septic Fees 4. Tarion New Home Warranty
More informationATBRA AHS Bill of Quantities Cost code Description Unit Qty ATBARA AHS 02000 Site Works Setting out works: Rates shall include but not limited to all necessary equipments,tools, and workmanship needed
More informationDescription Unit Quantity Rate Kshs. Amount Kshs.
BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove
More informationPROCUREMENT AND CONTRACTING DOCUMENTS GROUP
PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 00 Notice To Bidders 00 21 00 Instructions To Bidders 00 22 00 Supplementary Instructions To Bidders
More informationTable of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities
Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)
More informationBRIEF SPECIFICATION OF SCHOOL BUILDING. 1.1 Foundation Isolated and combined foundation as per structure design for G+1 story.
BRIEF SPECIFICATION OF SCHOOL BUILDING S.No. ITEM Specification 1 Foundation 1.1 Foundation Isolated and combined foundation as per structure design for G+1 story. 2 Superstructure 2.1 Superstructure RCC
More informationTABLE OF CONTENTS Public Safety Building
DOCUMENT 00 01 10 - TABLE OF CONTENTS VOLUME I DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS 00 01 10 Table of Contents 00 31 32 Geotechnical Data DIVISION 01 GENERAL REQUIREMENTS 01 10 00 Summary
More informationSchedule of Values Cruise Terminal 2 Expansion
Schedule of Values The Schedule of Values outlined below is intended to reflect the standard format that would be used in a Contractors Application for Payment. Values reflect materials and labor. General
More informationSERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS
SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,
More informationVOLUME 4 DIVISION SPECIFICATIONS
Page 1 Section Title Consultant Pages VOLUME 4 DIVISION 00-01 SPECIFICATIONS Division 00 - Procurement and Contracting Requirements 00 01 07 SEALS PAGE All 5 00 01 11r6 TABLE OF CONTENTS All 7 00 21 13r1
More information4.1.3 Project Manual
4.1.3 Project Manual (*Section requires Filed Sub-Bid) PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP Division 00 Procurement and Contracting Requirements Section 00 01 03 Project Directory Section 01
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Quantity Estimated Mobilization 1 LS
010100-01 Mobilization 1 LS 010500-01 Construction Surveying 1 LS 015000-01 Temporary Construction Fence 1 LS 029100-01 Tree Retention and Protection 1 LS 015150-01 Erosion and Sediment Control 1 LS Division
More informationWatercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS
Watercrest - Sand Hill - Columbia, SC 00 0110-1 TABLE OF CONTENTS DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS INTRODUCTORY INFORMATION Document 00 0101 Document 00 0110 Project Title Page CONTRACTING
More informationBuilding Systems and Design Elements included in SliDeRulE
Building Systems and Design Elements included in SliDeRulE No. System Subsystem Design Element 1.1.1 Foundation Deep Foundation Steel H-pile 1.1.2 Foundation Deep Foundation Steel pipe pile 1.1.3 Foundation
More informationAppendix J - Custom Uniformat for EDU Migration
Appendix J - Custom Uniformat for EDU Migration Nr. MTC Uniformat for VFA.facility Life (Years) Weight (1-100) Out of Scope Cost Y/N 1 A Substructure 150 N 2 A10 Foundations 150 N 3 A1010 Standard Foundations
More informationPROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California
PROGRAM COST MODEL for PEER Tall Buildings Study Concrete Structural Option Los Angeles, California March 8, 2010 PEER Tall Buildings Study Concrete Structural Option March 8, 2010 CONTENTS Page Nos. Overall
More informationBill of Quantities Project: Tenant Installations Address: Suncadia, First Floor, Pretoria SAHRA/FAC/01/05/2018
T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 Bill of Quantities Project:
More informationStandard Inclusions for
Standard Inclusions for Preliminaries Soil test Contour Survey & Site Assessment Property Service Information Working Drawings Building permit and application fees Engineering Site & Connections Connections
More informationGeneral Technical Specification
GENERAL For calculating the requirements of cement in various items of work the following standards will be adopted. Over the above theoretical quantity of cement, additional allowance upto plus or minus
More informationBuilding Permit Application
Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: ARCHITECT/ENGINEER ADDRESS:
More informationDivision 00 Procurement and Contracting Requirements
SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders
More informationSPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)
SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in
More informationFranklin Hall Renovation TABLE OF Document Indiana University Bloomington
VPS Project No. 2013022.00 Page 1 SPECIFICATIONS VOLUME I INTRODUCTORY INFORMATION Document 000010 - Table of Contents... 6 Document 000011 - Certification and Seals... 2 Document 000012 - Project Directory...
More informationSPACE TYPE: OUTSIDE PARKING (STRUCTURE)
SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.
More informationLOT 25 Blueleaf Place. Brookfield $511,879 SUMMARY
RENDERS ARE INDICATION ONLY Home size 27sq Land Size 512m2 LOT 25 Blueleaf Place Brookfield 5 2 2 $511,879 SUMMARY Land Price: $219,000 House Price: $292,879 (Fixed Price) Land Size: 512m2 House Size:
More informationDeluxe Inclusions for
Deluxe Inclusions for Preliminaries Soil test Contour Survey & Site Assessment Property Service Information Working Drawings Building permit and application fees Engineering Site & Connections Connections
More informationWork Write Up / Specification of Repairs HUD DIVISION 1. MASONRY HUD DIVISION 2. SIDING. Toll Free
/ / Paperport 2000 official estimating report Work Write Up / Specification of Repairs Toll Free 1-877-932-7177 Clients Name. GREAT CLIENT Property Address. NUMBER ONE GOOD ROAD METRO, VA 20000 Primary
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationExisting Site Aerial Frederick High School Feasibility Study September 5, 2012
Existing Site Aerial Building Developmental History 1981 1966 1939 1977 1978 1955 1966 Exterior Roof: Most of existing roof has multi ply built up roofing. Some areas have gravel ballast, others have cap
More informationTimberglen Recreation Center Summary
Timberglen Recreation Center Summary Address Building Purpose 3810 Timberglen Road Dallas, TX 75287 Recreation Center Original Year of Construction 2003 Building Area 15,000 SF Inspection Date August 2,
More informationTHE BEST INCLUSIONS ALTI 202
THE BEST INCLUSIONS ALTI 202 WHITE LABEL RANGE WHITE LABEL INCLUSIONS PRELIMINARY WORKS Site Survey, soil test, site inspections as required Building Permit application including applicable fee Full set
More informationIssued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS
669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects
More informationDIVISION 1 - GENERAL CONDITIONS TOTAL:
ITB 39-08/09 UNIT PRICE BID BREAKDOWN CONSTRUCTION OF THE 35th STREET RESTROOM FACILITIES & STREET END IMPROVEMENTS The following unit quantity breakdown is provided FOR INFORMATIONAL PURPOSES ONLY. Bidders
More informationPAULDING COLLEGE & CAREER ACADEMY
PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE
More informationBILLS OF QUANTITIES FOR CONSTRUCTION OF MODEL DISPENSARY BLOCK AT MGUNGANI / SALAITA
BILLS OF QUANTITIES FOR CONSTRUCTION OF MODEL DISPENSARY BLOCK AT MGUNGANI / SALAITA CONSTRUCTION OF MODEL DISPENSARY BLOCK Item DESCRIPTION QTY UNIT RATE TOTAL(KS ELEMENT : SUBSTRUCTURE (ALL PROVISIONAL):
More informationTABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS
AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding
More informationSTANDARD SPECIFICATIONS. Page 1
STANAR SPECIFICATIONS Page 1 Page 2 CERTIFICATION AN APPROVALS Complete soil test and engineer s report. Preparation and lodgement of evelopment including drafting of Architectural Plans and all applicable
More informationRENDERS ARE INDICATION ONLY. Land. Home size 26sq. 28 Ajay Way, Kurunjang LEGACY 26 $545,500 ACTUAL HOUSE IMAGE PRESENTED BY
RENDERS ARE INDICATION ONLY Land 28 Ajay Way, Kurunjang LEGACY 26 $545,500 Home size 26sq 5 2 2 ACTUAL HOUSE IMAGE Home Size 26sq Land Size 451m2 FUSION 27 5 2 2 Plans and illustrations are for marketing
More informationCarter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications
Carter's Oshkosh (SIS) #1185 - The Center at Pearland Parkway - Pearland, TX 77581 - Scope Of Work / Bid Qualifications Please fill out the blanks associated with your trade scope or work with the words
More informationPLANNING FOUNDATION FRAMING
TRITON MODEL 3208 Chiquita Blvd. S. #208 Cape Coral, FL 33914 (239) 549-5554 CBC 1259879 What s Included in a Poseidon Home PLANNING Provide all permits necessary to comply with local codes Provide all
More informationSECTION GROUNDING AND BONDING
SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationCONTAINERIZED STUDIO TYPE HOUSING UNITS JULY 2017
CONTAINERIZED STUDIO TYPE HOUSING UNITS JULY 2017 Table of contents Sheet Number A-01 A-02 A-03 A-04 A-05 A-06 A-07 A-08 A-09 A-10 A-11 A-12 A-13 A-14 A-15 A-16 A-17 A-18 A-19 A-20 A-21 FLOOR PLAN CONTAINER
More informationSINDH BANK LIMITED. Design Booklet. (For Sindh Bank s Upcoming Branches)
SINDH BANK LIMITED Design Booklet (For Sindh Bank s Upcoming Branches) 2016 S No Description Image A Civil & Interior works A1 Porcelain Tiles on Floor and Skirting Full body Porcelain of approved design,
More informationREQUEST FOR QUOTATION (RFQ) (Works)
REQUEST FOR QUOTATION (RFQ) (Works) DESCRIPTION: Rehabilitation of 1. Al Qalaa School; 2. Al Hasan Ebn Al Haitham School; 3. Omar Al Mokhtar School in Tajoura Municipality, Tripoli, Libya DATE: May 15,
More informationProject Specifications
Project Specifications Unit 1, 2 & 3 / 1 Carmen Street, NEWPORT These specifications form part of the building contract. The owner shall therefore ensure that the project specifications are fully and accurately
More informationCONSTRUCTION WORK AT THE AU MEDICAL CENTER
CONSTRUCTION WORK AT THE AU MEDICAL CENTER No Description of works Unit Quantity RENDER THE FOLLOWING TO THE AUC, Medical Center.01. Laboratory 1.0 Dismantling Works; 1.1 Remove carefully the existing
More informationNAAHB Workgroup Index General Ledger Account
NAAHB Workgroup Index General Ledger Account 1000 Series Preparation/Preliminaries 1000 Permits/Fees 1010 Building Permits 1020 HBA Assessments 1030 Warranty Fees 1100 Architectural/Engineering 1110 Blue
More informationDESIGN & CONSTRUCTION GUIDELINES
DESIGN & CONSTRUCTION GUIDELINES EDITION: USF FACILITIES MANAGEMENT - DC 5 DCG FACILITIES MANAGEMENT DESIGN & CONSTRUCTION PHONE: (813) 974-2845 4202 E. FOWLER AVENUE, OPM 1000 TAMPA, FLORIDA 33620-7550
More informationPROPOSED ERECTION AND COMPLETION OF CEREAL STORE.
PROPOSED ERECTION AND COMPLETION OF. AB/1 STORE ELEMENT NO. 1 A B SUBSTRUCTURES (ALL PROVISIONAL) Excavations Clear site of small bushes and grub roots of small trees and cart away Excavate average 150mm
More informationGeneral Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours
Basic Edition Standard Estimate Report Page 1 Name 1000 General Conditions 1107 Professional Consultant 10 Surveying 1.00 day 600.000 /day 600 - - - - - - 600 Professional Consultant 600 600 8.00 hours
More informationOur standard inclusions.
Our standard inclusions. We pride ourselves on offering you certainty on a fixed price that includes everything you need in your new home. Before you make a final choice on your new home, check that all
More informationDivision 09 FINISHES TABLE OF CONTENTS
Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING
More informationAnnex II- Lot 2. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State
Annex II- Lot 2 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State Lot: 2 Site 2-1: Allakandie All Prices of items shall include Supplying,
More informationEstimate FOR THE SEPTIC TANK
Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks
More informationTEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS OFFICE OF COLONIA INITIATIVES TEXAS BOOTSTRAP LOAN PROGRAM. Form 15 Work Write-Up
TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS OFFICE OF COLONIA INITIATIVES TEXAS BOOTSTRAP LOAN PROGRAM Form 15 Work Write-Up Owner-Builder Applicant Owner-Builder Co-Applicant Physical Address: City,
More informationDIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT
TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders
More informationPulaski County, Virginia
Pulaski County, Virginia Typical Carport Enclosure Details Based on the 2009 International Residential Code CONTENTS General Requirements... 2 Emergency Escape and Rescue... 2 Foundation and Floor... 3
More informationAnnex III- Lot 3. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State
Annex III- Lot 3 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State Lot: 3 Site 3-1: Sinja city All Prices of items shall include Supplying,
More informationConstruction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750
1 Preparation of a 18-Classroom School BoQ for constructing a 18-Classroom School - Najaf Site Preparation:Works for leveling the site and remove the garbage to authorized location according to supervisor
More informationBuildingAdvisor.com Estimating Checklist
BuildingAdvisor.com Estimating Checklist GENERAL REQUIREMENTS Plans and specifications Plan review Permits: Zoning, building, environmental, other Survey Impact fee Administrative costs Financing costs
More informationCONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist
CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist This checklist is a convenient reference to the 2012 Michigan Building Code. The checklist
More informationChild Friendly Schools in Rwanda
Child Friendly Schools in Rwanda Typical drawings of school building and toilet block Approved by MINEDUC/UCEFS Eng. Warren Habimana UNICEF Rwanda PO Box 381, Kigali Education section: tel. +250 592750-55
More informationPRM/KA/RERA/1251/446/PR/171230/002141
PRM/KA/RERA/1251/446/PR/171230/002141 Strategically located near the Embassy Golf Links Business Park, Bangalore over looking the KGA Golf Course. Centrally located and easily accessible from all parts
More informationItem # 1: Attached are the revised Table of Contents and Specifications added: Section Cabinets and Vanities
ADDENDUM NO. 1 Proposed Residence 422 Hickory Street Buffalo, New York 14204 February 15, 2019 Long Associates, Architects 189 Kenmore Avenue Buffalo, New York 14223 This addendum is issued to amend the
More informationTECHNICAL SPECIFICATIONS TABLE OF CONTENTS SUMMARY SERIES PRELIMINARIES & GENERAL REQUIREMENTS SPECIFICATIONS
TECHNICAL SPECIFICATIONS TABLE OF CONTENTS SUMMARY PART 1 PART 2 PART 3 PART 4 PART 5 PART 6 PART 7 SERIES 100 - PRELIMINARIES & GENERAL REQUIREMENTS SPECIFICATIONS CIVIL WORKS SPECIFICATIONS BUILDING
More informationSTANDARD PLAN RELEASE SUMMARY(SPR) Facilities Management Department
STANDARD PLAN RELEASE SUMMARY(SPR) Facilities Management Department Building Design: Nauvoo 00 Release Date: February 2001 Release Number: 1 Summarized below is a list of modifications made to the Standard
More informationSl. no Description of Work Unit Quantity Unit rate (BDT) Total cost (BDT) 3. Supplying, fitting and fixing country made Sqm 50
Specification for Renovation of Civil and Electrical works, supplying of furniture in Career Guidance & Employment Support Cell of Panchagarh Technical School and College (PTSC). A) Civil works. Sl. no
More informationCM ASSIGNMENT OF TEMPORARY FACILITIES see included IU Project Site Requirements
SECTION A CM INSTRUCTIONS TO BIDDERS SECTION B BID CATEGORY DESCRIPTIONS & BID FORMS BC-07: Building HVAC and Plumbing BC-08: Building Electric BC-09: General Trades BC-10: Masonry BC-11: Precast Structural
More informationSECTION The specification section is organized by placing information in three standard parts:
SECTION 14244 LIMITED USE HYDRAULIC ELEVATOR ***** Since 1982 Liftavator, Inc. has provided limited use/limited application (LU/LA) elevators, residential elevators, hydraulic vertical platform wheelchair
More informationCOUNTY GOVERNMENT OF SIAYA: PROPOSED ECD BLOCK
PROPOSED ECD BLOCK ELEMENT NO. 1 SUBSTRUCTURES (ALL PROVISIONAL) A B C D Site clearance Clear the site off grass, shrubs and all vegetation; cart away as directed Excavate vegetable soil average 200mm
More informationUNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section
More informationNorth Village Condominiums
North Village Condominiums An ambient community in Douglas, Massachusetts encompassing the luxury of Blackstone Valley s serene country surroundings FOUNDATION Builders General Specifications (As of 1/1/2017)
More informationAttil Hospital Project Bill of Quantities Table(1) Excavation and Backfill No Description Unit Qty
Attil Hospital Project Bill of Quantities Table(1) Excavation and Backfill Us$ Cent Us$ Cent Notes s for excavation works shall include: Removal of site obstacles, rocks, trees and small concrete of store
More informationDelta Gamma Sorority Renovation Budget Scope 3/7/2018
Delta Gamma Sorority Renovation Budget Scope 3/7/2018 PROJECT: Barbara Cerni Delta Gamma Sorority Tallahassee, Fla. This scope is based on the 50% Construction Documents drawn by BKJ Architecture dated
More information1 Site Preparation & marking L.S 1, brickwork in basement in cm 1: cft 19,975.00
GURUKULAM' TRUST CHILDREN SCHOOL KOVALAM - CHENNAI ESTIMATE FOR CONSTRUCTION OF THREE CLASS ROOMS - GROUND + TWO FLOORS BUILDING - INCLUDING STAIR-CASE Plinth area : Class Room - 28.50 x 23.25 = 662.625
More informationAnnex I- Lot 1. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State
Annex I- Lot 1 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State Lot: 1 Site 1-1: Sinnar city All Prices of items shall include Supplying,
More informationBUILDING ON THE CADASTRAL LOT NO. 713, MISLOĐIN, OBRENOVAC BILL OF QUANTITIES
BUILDING ON THE CADASTRAL LOT NO. 713, MISLOĐIN, OBRENOVAC BILL OF QUANTITIES No. I EARTH WORKS 1. Clear the terrain before the start of the building, including removal of existing non-load bearing layer
More informationCOPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31
Contents Preface to the Sixth Edition xi 1 Making Buildings 3 Learning to Build 4 Buildings and the Environment 5 The Work of the Design Professional 11 The Work of the Construction Professional 19 Trends
More informationPROJECT SPECIFICATIONS
PROJECT SPECIFICATIONS CITY OF PORTLAND BUREAU OF ENVIRONMENTAL SERVICES PROJECT SPECIFICATIONS FOR ANKENY PUMP STATION UPGRADE BES project number E07833 STANDARD REQUIREMENTS (DIVISION 0) GENERAL REQUIREMENTS
More informationSection : 100 TRESHOLD STAIRS DEPARTMENT NGL HALLWAY TOWARDS MUSEUM FFL DISABLED WC FEMALE WC MALE WC FFL 95.
Section 3-3 1 : 100 TRESHOLD STAIRS DEPARTMENT NGL 100.000 FEMALE WC DISABLED WC MALE WC HALLWAY TOWARDS MUSEUM FFL 98.100 FFL 95.400 GROUND WATER COLLECTIONAND PUMP ROOM LOWER DOORS TO AUDITORIUM LOWER
More informationNOTICE TO BIDDERS. TO: All Bidders FROM: Alvin Kumar DATE: 20 th July 2017 DESIGNATION: Deputy Manager Project
NOTICE TO BIDDERS TO: All Bidders FROM: Alvin Kumar : 20 th July 2017 DESIGNATION: Deputy Manager Project Proposed New Changing Room and Waoom Facility at Nasinu Campus LOCATION: LOCATION: FNU Nasinu Campus
More informationBUILDING DIVISION 120 Malabar Road, S.E., Palm Bay, FL Phone: (321) Fax: (321)
BUILDING DIVISION 120 Malabar Road, S.E., Palm Bay, FL 32907 Phone: (321) 953-8924 Fax: (321) 953-8925 CUSTOMER SERVICE INFORMATION ON COMMERCIAL PLAN REVIEW REQUIRED DOCUMENTS MUST BE SUBMITTED AT TIME
More information1 BILL NO.1 PRELIMINARIES AND GENERAL MANIFESTATION.
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT 1 BILL NO.1 PRELIMINARIES AND GENERAL MANIFESTATION. Clearing of site, site office/work shed, Toilet, etc. A provisional cost to be allocated in South African
More informationOur standard inclusions.
Our standard inclusions. We pride ourselves on offering you certainty on a fixed price that includes everything you need in your new home. Before you make a final choice on your new home, check that all
More informationARCHITECTURAL DRAWINGS
PROJECT DETAILS Implementation Partner: Project title: Grant No.: KIS062 Content : ARCHITECTURAL DRAWINGS SHEET NO. REHABILITATION OF GRANT NO.: - KIS062 COVER SHEET INDEX SHEET CONTENTS 01 02 03 04 05
More informationAppalachian Log Structures Construction Cost Estimating Guide
PLANNING Design/Architect Fees General Contractor Fees LOT CONSIDERATIONS Lot Costs Property Tax Surveying Zoning PRELIMINARY COSTS Taxes Building Permit Hazard/Liability Insurance Performance Bond Impact
More informationDavis Frame Co., Inc. Construction Budget Considerations
Davis Frame Co., Inc. Construction Budget Considerations ITEM BID 1 BID 2 BID 3 MISCELLANEOUS COSTS Surveying Building Permit Engineering Fees Interest on Construction Loan Property Taxes Hazard & Liability
More informationEXTERNAL WORKS EXCAVATION,BACKFILLING & SITE WORKS
BILLS OF QUANTITIES - Name of Project CONSULTANT: Name of Office DATE:APR. 2008 External Works EXTERNAL WORKS EXCAVATION,BACKFILLING & SITE WORKS page 1 BILLS OF QUANTITIES - Name of Project CONSULTANT:
More informationAnnex to the Accreditation Certificate D-ZE according to DIN EN ISO/IEC 17065:2013
Deutsche Akkreditierungsstelle GmbH Annex to the Accreditation Certificate D-ZE-11267-01-00 according to DIN EN ISO/IEC 17065:2013 Period of validity: 17.08.2018 to 01.10.2022 Holder of certificate: Materialprüfanstalt
More informationConstruction works for Establishment of School in Al-Latifiyah. Al-Latifiyah BoQ for constructing a 6-pre-fab Classroom School
1 Al-Latifiyah BoQ for constructing a 6-pre-fab Classroom School Preparation of a 6-Classroom School Site Preparation:Works for leveling the site and remove the garbage to authorized location according
More information