FORMING THE RETAINING WALL FOUNDATION OUTER WALL

Size: px
Start display at page:

Download "FORMING THE RETAINING WALL FOUNDATION OUTER WALL"

Transcription

1 THE RETAINING WALL FOUNDATION SYSTEM This recipe is based on using 1 1/8 plywood forms ripped from 4x8 sheets into halves. It incorporates Rapid Form brand clips and anchor bolt holders. It is based on my successful formula. It can be adjusted to suit with other systems and materials. FORMING THE RETAINING WALL FOUNDATION OUTER WALL Install string lines to the inner batter board screws. Strings for the foundation walls are placed on the inner screws at ¼ inside the home footprint, allowing boards to be installed at 1/8 to ¼ clearance to the strings. Ideally the concrete ends up inside the home footprint by at least 1/8. Layout the form boards and support stakes around the foundation as you proceed. It is helpful to lay a form board across the perimeter footings to aid in walking in and out without breaking the sides of the trenches. Leaving boards on the ground in the sun for an extended time in the sun will cause the boards to warp. A carpenter s level will not be very accurate so set up a laser or water level. You should already have the foundation elevation established and batter boards set at that elevation so set the level to that elevation. Lay out the first form board at a string line intersection or home corner. Drive form stakes about 18 from each end of the form board and one in the center at 1 1/4 outside the string line. To install the stakes plumb, hang them from your fingertips and install them level. Drive the stakes deep enough to support the form boards and steel, but not so deep they cannot be easily removed after pouring the wall. With help from an assistant, hang the first board inside the stakes, outside the string and support at roughly the string level. Starting at the stake closest the string line intersection; set the board at wall grade using the level. Install one screw at the top of the stake. Now level the board at the other end and fasten that stake. Now rack the board forward or back until the board is just inside the string line intersection and fasten the stakes at the bottom on the first board at corners only to isolate movement. Install kicker stakes on the outside adjacent each support stake, hold the form board clear of the string and then adjust to 1/8 to ¼ clearance. Push or pull the support stakes as needed and fasten kicker with a screw at the top of the form board. If the board bows in too much, kick the inside temporarily out as needed to keep the string clear. Install a splice to the end of the form board needed to couple the next board. Lay out the next form board precisely as needed to aid in correct placement of the support stakes. Install stakes, and hang the next board. While holding the board roughly level, fasten the next board starting at the splice, butting square and tight. Next level the board at the far end stake and fasten the stakes and splice. Beyond the corner board, install only the top screws in the form boards for now, allowing flexibility at the bottom for rapid form clips that will be installed later. Install kickers as before and continue the process as needed. At the end of the wall, allow the form board to run past the string line intersection as convenient to avoid cutting a board. Continue around the perimeter securing the corners with kickers outside and inside if needed. To square offset wall sections, measure all wall insets at each end from the end strings adding string inset as needed. Fasten corners with screws on the outside intersections.

2 Upon completing the outside forms, remove the inner and center batter board screws, leaving the outer screw for plate installation. Check the footing for proper clearance set up the laser level Hang strings plumb 1 ¼ outside the string set the fist form board at a string intersection Level the board at each end stake set the kicker stakes clearing the string

3 Install a splice for the next board join the next board INSTALLING THE REINFORCING STEEL Install 5 lengths of tie wire to the inside of the wall tying the wire to the top of each support stake with a single twist. Allow the wires to hang free inside for tying and supporting steel. Layout 3 lengths of steel or per plan, starting at a corner and lower it into the footing starting 3 from wall corner. Lift the top piece of steel and support with a tie wire 5 in from each end and adjust it to 3 below the top of the form board. The tie wire should go behind and under the steel, up the outside, over the top, around the back of the wire, back out the front and down to the next piece. Adjust the steel ensuring the 3 clearance from the wall corner. Finish tying the top bar and lift out and support away from the wall with 1x3 form stakes on edge. Next hang the center bar the same way at midpoint of the concrete but no more than 18 from any other bar. Adjust the bar to 3 clearance from the corner like above and finish tying. Hang bottom bar 3 to 4 from the bottom of the footing. Wire should go under the bar, up the other side, wrap tightly 4 or 5 wraps, use up extra wire wrapping around the bar or cut off as needed. The next set of bars can be started allowing 24 minimum overlap or 30 for worry free inspections. Hang the bars as before, adjusting the overlap as needed. At the corners, either cut the bars to size or place corner bends as needed. It can be easier to start new stock at the corner and use a 5 piece of bar bent 90degrees at the center for a corner joint and splice. Tie splices and bar overlaps and is tied with doubled wire at each end. Speed ties are good for this, but standard tie wire can be used doubled for strength. The vertical steel reinforcing bars can be added next. Typically, reinforcing steel is placed at 32 or 48 on center but check the plan. Mark the forms for correct steel placement. Cut steel to length from top to bottom rebar with an extra inch for securing. Some plans require 90degree bends on the bottom end. Tie the steel starting at ½ above the top bar. Tie steel to each bar, keeping bar plumb. After all the reinforcing steel are tied and in place supported away from the wall with wood stakes; the footings must be cleaned again. Ensure that 3 minimum clearance exists from any steel to soil. It may help to dig under vertical

4 reinforcing steel if extra clearance is needed there and the horizontal steel has good clearance. Remember to remove the wood stakes supporting the steel away from the wall prior to pouring. \

5 After the inner forms are placed and rapid form clips used, the tie wire is moved to the rapid form clips and adjusted for height. THE UFFER GROUND INSTALLING The UFFER ground is a length of re bar or copper wire in the foundation footing that works in place of the grounding rod to ground the electrical service entrance panel and home. Typically, a length of grounding rebar or copper is placed in the footing with 20 minimum in the trench and supported separately from the reinforcing steel. If using copper, I suggest #4 solid bare copper wire, which is good for up to 200amp service, in a 30 length allowing 20 in the footing, 2.5 to the top of the wall and 7.5 outside the top of the wall to tie into the house panel unbroken. It is crucial to know where the panel will be on the house and allow extra wire as needed. Support the copper wire on concrete dobie blocks to keep it off the ground and keep it clear of the other reinforcing steel. Rebar can be used for a UFFER. Use 2 lengths of 20 bar. Place a 90degree bend at one end each allowing a tail long enough to go from near the bottom of the footing to above the wall high enough to tie on with a copper lead to the service panel. The 2 lengths are placed with tails back to back and rods running in opposite directions. Using 2 bars allows the minimum of 20 in the footing as required.

6 INSTALLING THE INNER FORM BOARDS Start with cleaning the footings again. Most walls are formed at 6 wide. I like the rapid form clips to properly space the forms for correct width walls. Start at an inside corner, 6 from the inside of the corner. Layout stakes, boards and form clips. Using a form clip for a guide to install form stakes, drive stakes plumb at the outside of the form clip. Stakes go at 18 from each board end and one in the middle. Use a torpedo level to level across from the outside form board at each end stake and fasten the stake to the board with a screw at the top of each stake. Rack the first board into final position and add the bottom screws to the stakes on the first board only. Install rapid form clips to the tops adjacent each outer stake with a screw each side. Add a splice board and start the next board leveling by lining up at the splice and then the outer stake. Fasten the forms to the top of the form stakes and continue the process until finished. At the corners, add brackets or blocking to prevent the forms from blowing out at the corners. Upon finishing, install kicker stakes and fasten with a screw on top at the form board. Where footings interfere with kicker layout, install kickers angled as needed to solid ground beside the footings. Move the reinforcing steel support wires from the support stakes one at a time to the rapid form clips, which will provide the support and center the steel. The wire should go through the hole in the center, over the top adjusting the steel to 3 clearance, wrap around itself 4-5 times and use extra wire around re bar. PLACING THE ANCHOR BOLTS Consult the plans for correct bolt spacing. Often the bolts are spaced at 2 to 4 on center on the short transverse walls. Usually they are placed at 4 to 6 on center on the long or longitudinal walls. Bolts must be placed with the length of plate to be used in mind. Bolts must also start at 4-12 from the end of each plate board. Each piece must have a minimum of 2 bolts each with spacing as required by the plans. I like to use 16 plate stock and 6 wide on retaining wall foundations is common. Start by marking the wall in 16 intervals. Next mark each 16 interval into proper bolt spacing. For instance if 6

7 maximum spacing is required, place bolts at 6, 5 6, , then from the next interval start over and complete the process around the foundation. Don t forget short offset walls and other places plate is needed. End one corner and start the next, starting back the width of the plate, such as 5 1/2 for 2x6 plate. I like to use commercial bolt holders such as monkey paws, or other holders that fasten to the wall. Install the bolts allowing proper clearance from the forms, usually 2 minimum. Bolts should be installed to a proper depth of 7 embedment, and enough bolt exposed to fasten the plate with a load bearing washer and a nut leaving 3 threads minimum exposed. Basically the bolt is set with the threads starting at the top of the concrete wall. Check the bolts for correct spacing at transverse and longitudinal walls. Ensure that each piece of plate will have a bolt at 4-12 from each end. When finished, clean the footings. A bolt had to be added where the anchor bolt did not have 4 minimum from the plate end. From the plate end, 4 to 12 is allowed for bolt placement. I use 10 in from each corner so that with either plate running to the corner, I am still within tolerance. Typically a 7 embedment will have the threads of a 10 bolt start at the top of the wall height.

8 Note the bolts at 4 minimum from the plate ends at this crawl space opening. The plate will stop at each side of the opening. The finished foundation ready for inspection should be clean, organized and look professional. Drain pipe for sewer A sewer drain pipe must be installed in a logical position determined by the drain layout on the house and the sewer hook up outside the home. The trench should start about 2 inside the forms and end about 3 outside the forms. Cut the trench across the perimeter footing so the sewer pipe will be at least 12 below finish grade. Level the trench to fall a quarter inch per foot. The pipe should be 3 ABS with a sleeve of 4 styrene pipe or foam pipe wrap to protect it from the concrete. On the inside the pipe should have a long sweep

9 elbow and a riser pipe for hook up later. Outside the wall the pipe will eventually have a 2 way clean out installed with a riser pipe high enough to cut back to finish grade later. After finish grading is completed cut the pipe below grade and install a clean out cap. The Foundation drain pipe If the foundation is the be back filled for a low finish floor height; grading the interior of the pad for drainage and installing a drain pipe to low ground is helpful to carry away unwanted water. At times a French drain is necessary or required to be installed outside the retaining wall. For the foundation drainpipe, install a length of styrene pipe through foundation wall at an elevation that will work with the grading to carry water out. Continue the pipe with at least 1% fall to low ground. If there is no low ground to drain the pad, a sump pump can be used. Sandy soil drains well and may not need any drainage considerations. Clay soils drain poorly and should have a drainage system. Inspection Install string lines for each row of footings and inspect the location or each footing. Inspect the form boards for proper bracing at joints, fastening at support and kicker stakes, clearance for the rebar, UFFER, footings clean and proper depth, ridge beam supports correct size and location. When the foundation has been fully inspected and passed by you, call in the inspection as directed by the permit. Stand inspection and have inspector sign off on the foundation, UFFER, setbacks, and any underground utilities that are ready. THE POUR Estimate your concrete volume using common geometry. A 12 deep x12 wide footing equals 1 cubic foot. Multiply the perimeter length by the footing value of 1 cubic foot 180 perimeter is 180 cubic feet. By using a 3 ½ slump mix, you can use up to a third less concrete on a perimeter footing. Next add the wall at 6 x24 equals 1 cubic foot multiplied by the perimeter length at 180 equals 180 cubic feet for the wall. Next add up the interior drilled pier footings and multiply x 3.14square feet for 24 diameter footings (Pie x radius square or 1 x1 =1 x3.14=3.14 square feet). For instance 60 footings at 3.14square feet equal cubic feet. Add these valued for a total of cubic feet. Divide by 27 cubic feet per yard to equal 20.3 cubic yards. Next determine a multiplier for waste based on footing condition and depth. Usually 10% to 20% is common. At 15% over the total is 23.3 cubic yards. Determine the size of the concrete trucks; 9 yards is common. Order 18 yards and a clean up truck (balance of the yardage needed as determined during the pour). Order a concrete pump and coordinate the rock and slump with the redimix supplier. Rock comes as pea gravel commonly used in a grout mix, a blend mix of pea gravel and ¾ rock and ¾ rock is standard. I prefer to use a ¾ blend mix which can be pumped through a 2 ½ minimum pump hose. The blend mix uses 5 ½ sacks of concrete per cubic yard. A grout mix can be pumped through a 2 pump hose and the ¾ mix requires a 3 hose which gets very heave and difficult to move. Slump is

10 a measure of the thickness. Picture filling a tube with concrete and removing the tube; how many inches the column slumps is the way slump is measured. Slump is critical. I order a 3 slump for the first truck which will be pumped into the perimeter footing to seal the base of the forms. The 3 slump is difficult to pump but reduces the yardage used by up to 1/3 in a perimeter wall since it stacks up nicely and seals the forms. Pour the perimeter footing just enough to seal the form boards at the bottom. I prefer a 4 slump mix for the balance of the interior piers and the wall portion of the pour. The 4 mix pumps reasonably well and makes a good finish product. More water nets a higher slump such as 5, 6 slump etc., which pumps and finishes nicely, however, it may crack excessively from evaporation and cause a homeowner concern. Next pour the wall just above the form boards and mechanically vibrate to blend the fresh concrete with the footing concrete. If no vibrator is available, tap each side with a hammer to settle the concrete. Use caution to not over stress the forms with the vibrator; make fast stabs in and out of the concrete since too much time with the vibrator may cause the concrete pressure to blow the forms. Have an assistant hand consolidate the wall with clean concrete as needed to top it off and fill voids on top. Screed the form boards at the top. Pour the interior footings with the remaining concrete and estimate shortage at between 4 and 8 footings per cubic yard depending on the overall size. 36 footings will require about 6 yards. Level the interior footings using a jitterbug tamper. Finish the foundation wall and clean around foundation bolts and rapid form clips. Using shovel, pull concrete away from the form boards to facilitate stripping the forms. Finish interior footings true and level using a swimming pool trowel if possible. Remove form support stakes as quickly as possible. Leave the forms in place for a few days. Poor a stiff mix to the bottom of the form boards with the first pass. I order the first truck with a 3 slump mix for the footing since it is thick enough to stack up and seal the footing yet can still be pumped. The mix in the photo is about 4 ½ slump and is flooding out from the bottom of the form boards. This costs a lot in lost concrete and labor.

11 The second pass fills the forms to the top. A 4 slump works well for the forms. One worker should quickly hand consolidate the top of the wall, filling voids by hand staying within reach of the pump hose. If necessary, an electric vibrator is used to consolidate and settle the concrete. Make quick stabs every couple feet. If you spend too much time, the concrete can blow the forms apart. In lieu of a mechanical vibrator, a hammer can be used to tap the forms for settlement with pretty good results.

12 A worker must quickly follow with a wood trowel to screed or strike of the concrete to grade while staying within reach of the worker consolidating or vibrating. A worker must quickly follow up with a finish pass using a steel trowel and staying within reach of the worker who is screeding. This worker should clean around the anchor bolts as he goes. After the wall is poured, the interior piers are filled and jitterbugged into rough level and then troweled smooth and level.

13 The excess concrete must be pulled away from the forms unless you would like to jack hammer it out later. Go fully around both sides and make sure the forms are scraped to the bottom. This work can be nearly eliminated by using a stiff slump such as 3 or 3 ½ slump for the perimeter footing. When using a 4 slump or higher for the perimeter footing, the concrete flows up and around the form boards. The vertical stakes must be removed now before they are stuck for good. Remove the screws and pull the stakes. Stakes can usually be pulled by hand or with a stake puller if necessary. Wipe them off and bundle them up for storage. FOUNDATION FORM STRIP & PLATE Listed below are items needed before completing a Foundation Form Strip & plate. Form Stripping Items Drills & Batteries (with Phillips bits) Flat Shovels (for scraping form boards) Mortar Patch Mortar Pan Mortar Trowel Duct Tape (to wrap stakes) Claw Hammer

14 Cement Finishing Block Jack Hammer Platting Items Pressure treated Plate (2x4 or 2x6) (verify quantities) 5/8 Nuts (verify quantities) Baring Plates (verify quantities) Sledge Hammer Corded drill Paddle Bits (11/16) Impact Wrench & 7/8 Socket Generator Extension Cords Skill Saw Builders Square & Pencil Chop Saw String Line STRIPPING THE FORMS When the concrete has set enough to remove forms (about 1day in hot weather, and 3 days in damp weather) you may begin stripping forms. First remove any remaining kicker stakes, fully removing the screws as you go and lean the stakes against the wall for easy pick up. Bundle the kicker stakes and put away. Remove the screws from all rapid form clips top and bottom. The rebar support wire must be snipped on the top rapid form clips. Remove all the rapid form clips from the top of the wall. Start pulling forms from the inside of the wall testing the concrete for surface strength. If it is not ready stop and resume later. If it is ready, proceed from the inside removing form boards, then the outside. The form boards must now be scraped clean of concrete both sides and edges. Spray diesel fuel or another form release agent on the boards as you put them away. The concrete surface should be inspected for rock pockets and damage. Proceed now with mixing mortar. Patch any significant rock pockets and holes in the wall. The mortar patch should be done within 8 days of placing the concrete in order to adhere to the curing concrete. Blade off the excess mortar as it sets. Next brush the surface with a burlap sac. This will help to blend the color in with the wall.

15 INSTALLING THE SIL PLATE The plate can be fit to the wall after stripping; however, the bolts should not be tightened more than snug until the concrete has set for 8 days or more. Tightening the bolts prematurely may cause failure of the concrete. Put the strings up on the outer batter board screws. Lay the plate out with concern for the corners and bolt layout pattern. Keep in mind the plate must have a bolt at 4-12 from each end. With a helper, hold the plate in position on top of the anchor bolts, leaving 1/4 clearance to the string line. While holding the plate firmly and precisely, strike the plate with a hammer to cause indenting by the anchor bolts. Repeat this process at each bolt checking the string line clearance at each bolt. Turn the plate over and drill the plate at no more than 1/8 diameter greater than the bolt diameter. Be careful and accurate to avoid having to open the hole excessively. Fit the plate section and fasten with a proper load bearing washer and nut. Tighten only to snug until the concrete has set 8 days or more. Proceed around the wall, keeping layout in mind. Check the plate for square, width and length in various locations. Ensure the plate matches the footprint of the home and the additional width gained at the marriage seams. With the plate on and fastened, double check all dimensions and make corrections as needed. Now the batter boards may be removed and put away.

Important: Before You Start

Important: Before You Start Advantage ICF System Advantage ICF System TM Field Guide Important: Before You Start Does Your Building Inspector Know You Are Building with the Advantage ICF System? You are required to check with your

More information

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best.

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Concrete Placement Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Above-grade pours require lifting equipment. Most

More information

Table of Contents. 1 Introduction. 2 Description. 3 Tools and materials. 4 Footings or slabs. 5 Coursing placement. 6 Reinforcing steel

Table of Contents. 1 Introduction. 2 Description. 3 Tools and materials. 4 Footings or slabs. 5 Coursing placement. 6 Reinforcing steel Table of Contents 1 Introduction 2 Description 3 Tools and materials 4 Footings or slabs 5 Coursing placement 6 Reinforcing steel 7 Alignment scaffold installation 8 Concrete placement 9 Exterior and interior

More information

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 )

SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 ) SpaVault TM Installation Guide for Bullfrog Spas (7-10 x 7-10 x 38 ) WARNING - When unpacking SpaVault, DO NOT discard styrofoam pieces, these are not packaging materials. Step 1 Excavation Important:

More information

INSTALLATION CHECKLIST 2 ND EDITION. Fox Blocks Abbott Drive Omaha, NE

INSTALLATION CHECKLIST 2 ND EDITION. Fox Blocks Abbott Drive Omaha, NE Fox Blocks INSTALLATION CHECKLIST ND EDITION Fox Blocks Installation Checklist: ND Edition 6110 Abbott Drive Omaha, NE 6110-69-6 WWW.FOXBLOCKS.COM INSTALLATION CHECKLISTS The Checklists on the following

More information

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! DURA - TRENCH INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation

More information

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation procedures

More information

Construction Procedures

Construction Procedures Construction Procedures 2016 Rev. 1.7 1 Contents Introduction...... 3 Base Row Layout........ 4 Drainage and Backfill..... 6 Compaction... 7 Subsequent Rows... 8 In Pictures.... 10 Variations.. 11 Step

More information

A-ONE Insulated Forms Installation Manual

A-ONE Insulated Forms Installation Manual A-ONE Insulated Forms Installation Manual Rockford, MN www.aoneform.com www.diversifoam.com info@diversifoam.com A-ONE Manual 180426.docx Disclaimer Notice The information in the A-ONE Insulated Forms

More information

Construction Procedures

Construction Procedures Construction Procedures 2014 Rev. 1.6 1 Introduction This manual presents the methods and procedures necessary for the proper erection of a LOCK+LOAD retaining wall. problems later during the service life

More information

Premier Railroad Grade Crossing Installtion Guide PREMIER RAILROAD GRADE CROSSING INSTALLTION GUIDE GUIDE GROUNDED IN STRENGTH

Premier Railroad Grade Crossing Installtion Guide PREMIER RAILROAD GRADE CROSSING INSTALLTION GUIDE GUIDE GROUNDED IN STRENGTH Premier Railroad Grade Crossing Installtion Guide PREMIER RAILROAD GRADE CROSSING INSTALLTION GUIDE GUIDE GROUNDED IN STRENGTH RELIABILITY STARTS WITH A WELL-DESIGNED PLAN. THE RIGHT PRODUCT FOR THE RIGHT

More information

How To Construct a Ferro Cement Tank

How To Construct a Ferro Cement Tank How To Construct a Ferro Cement Tank Be Advised The following power point presentation assumes that individuals using it to construct ferro-cement tanks have a basic knowledge of geometry and calculating

More information

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items: ITEM 431 PNEUMATICALLY PLACED CONCRETE 431.1. Description. This Item shall govern for furnishing and placing of "Pneumatically Placed Concrete" for encasement of designated structural steel members, the

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

RUNNERS (Required to convert to real property)

RUNNERS (Required to convert to real property) HUMBOLDT COUNTY BUILDING DEPARTMENT MANUFACTURED HOUSE/MOBILE HOME RUNNERS & PERIMETER FOUNDATION These requirements apply to the construction of permanent foundations necessary to convert to real property.

More information

Instructions for 12 IGT system

Instructions for 12 IGT system Instructions for 12 IGT system Step 1: IGT Site Preparation Site Location Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system. Since local soil and

More information

C.R. LAURENCE CO., INC. Intelli-Track SPS. Phase One - Installation Instructions

C.R. LAURENCE CO., INC. Intelli-Track SPS. Phase One - Installation Instructions Tools and Supplies: C.R. LAURENCE CO., INC. Intelli-Track SPS Phase One - Installation Instructions Ratchet Wrench with 4" Extension 9/16" Open-End Wrench (two required for suspension mounting) 9/16" Hex

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES Safety Precautions in the Excavation of a Sentinel Wedge take all necessary steps to make sure the pit is secured. Follow all OSHA requirements for digging

More information

BELMURO WALL SYSTEM INSTALLATION GUIDE

BELMURO WALL SYSTEM INSTALLATION GUIDE BELMURO WALL SYSTEM INSTALLATION GUIDE TABLE OF CONTENTS TABLE OF CONTENTS... 1 SYSTEM DESCRIPTION... 2 DRY STACK SYSTEM: INSTALLATION GUIDE... 5 GEOGRID WALL SYSTEM: INSTALLATION GUIDE... 9 MASONRY WALL

More information

TABLE OF CONTENTS. 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers

TABLE OF CONTENTS. 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers version 2.5 updated as of 08.04.2017 2 TABLE OF CONTENTS 1.0 INTRODUCTION 1.1 Greenstone Structural Engineered Panels 1.2 Drawing and Element Numbers 2.0 ASSEMBLY 2.1 Sequence of Assembly 2.2 Preparation

More information

General Brick Installation Instructions

General Brick Installation Instructions Excellent Resource for Clay Paver Installation: http://www.bia.org/resources/clay-brick-pavers/clay-paver-informational- Resources These are general guidelines only. Check your paver manufacturer's recommendations

More information

2.15 CONCRETE PLACEMENT

2.15 CONCRETE PLACEMENT 2.15 CONCRETE PLACEMENT PRE-PLACEMENT CHECKLIST DATE: FOREMAN: JOB: Prior to placing concrete in Logix insulated concrete forms, be certain to mark off each item on the checklist provided in this section.

More information

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated: SECTION 04220 CONCRETE UNIT MASONRY PART 1 - GENERAL 1.01 SCOPE: A. The CONTRACTOR shall furnish all labor, materials and equipment necessary for the masonry construction as shown on the drawings or as

More information

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS Underground Electric Distribution Standards I. SCOPE This section includes the standards for concrete, reinforcing steel, formwork, concrete placement, curing, and construction joints. Concrete work for

More information

Rough-in frame and flush-mount panel installation instructions

Rough-in frame and flush-mount panel installation instructions Welch Allyn, Inc. 3 State Street Road Skaneateles Falls, NY 33 USA Rough-in frame and flush-mount panel installation instructions 726080 DIR 8002869 Ver. A Revised 206- The Welch Allyn In-Floor Scale models

More information

Reinforced Earth wall Construction Manual

Reinforced Earth wall Construction Manual COVER PAGE CT-PE-W02 Rev: 5 Reinforced Earth wall Construction Manual Concrete Facing Reinforced Earth Malaysia Sdn Bhd 80-1, Jalan 8/62A Bandar Menjalara 52200 Kuala Lumpur Tel : 03-62746162, Fax : 03-62747212

More information

Concrete Framing Systems - Walls and Columns

Concrete Framing Systems - Walls and Columns Concrete Framing Systems - Walls and Columns Casting a Concrete Wall Wall Footing Reinforcing Wall Forms Pouring Concrete Finishing the Concrete Controlling Cracking Insulating Concrete Forms (ICF) Tilt-Up

More information

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION This Technical Notes contains the guide specifications in CSI format for Part III

More information

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures lower in height that use the FrogStone unit weight combined with gravel core infill to resist earth pressures

More information

NUDURA FIELD GUIDE CHECKLIST & PROJECT LOG

NUDURA FIELD GUIDE CHECKLIST & PROJECT LOG NUDURA FIELD GUIDE CHECKLIST & PROJECT LOG PROJECT: SITE ADDRESS: NUDURA INSTALLER: DATE: For more detailed information reference the most current NUDURA installation manual. www.nudura.com 866.468.6299

More information

TF-14. TF-14 Installation Guide

TF-14. TF-14 Installation Guide TF-14 Trench Drain Forming System Installation Manual TF-14 Installation Guide P.O. Box 837 # 259 Murdock Road # Troutman, NC 28166 Tel (704) 528-9806 # Fax (704) 528-5478 Toll free in the U.S., Canada,

More information

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular

More information

Heartland Perma-Column 1841 E 1450 Rd. Lawrence, KS (785)

Heartland Perma-Column 1841 E 1450 Rd. Lawrence, KS (785) Perma-Column Installation Instructions Unlike any other concrete post-frame foundation system, Perma-Column Precast Concrete Piers use 10,000 psi concrete and our unique Sturdi-Wall Plus wet-set bracket

More information

INSPECTION REQUIREMENTS: FOUNDATIONS

INSPECTION REQUIREMENTS: FOUNDATIONS Foundations Page 1 of 9 Revision Date: 1/2/2018 DEVELOPMENT SERVICES BUILDING INSPECTION INSPECTION REQUIREMENTS: FOUNDATIONS INSPECTION CODE: 204 SCOPE: RESIDENTIAL APPLICABLE CODES: 2016 CBC, CRC, CPC,

More information

Installation Manual. Foundations. Version 2

Installation Manual. Foundations. Version 2 Installation Manual Foundations Version 2 Contents Overview...1 Planning the Job... 2 Introducing DMX FlexSheet...2 Supplies Required...3 Tools Required...4 Preparing the Site...4 Where to Start?...5 Installing

More information

Before You Get Started, You Will Need

Before You Get Started, You Will Need LiteForm forming components should only be assembled by workers who have been properly trained. It is the installer s responsibility to make sure that training is done before construction begins. Serious

More information

INSTALLATION MANUAL KOCH

INSTALLATION MANUAL KOCH INSTALLATION MANUAL KOCH TECHNICAL SYSTEMS GROUP PRE-FAB ACOUSTICAL/THERMAL PANELS AND ENCLOSURES GEORGE KOCH SONS, LLC TECHNICAL SYSTEMS GROUP 10 South Eleventh Avenue Evansville, Indiana 47744 812-465-9600

More information

DETAIL INSTRUCTION No. 1

DETAIL INSTRUCTION No. 1 BEFORE BEGINNING INSTALLATION, PLEASE READ THROUGH ALL INSTRUCTIONS. Uncrate shipment and check against packing list to insure all materials are included before beginning installation. If any discrepencies

More information

Grizzly TM Part Number Spectrum Lane ~ Missoula MT ~

Grizzly TM Part Number Spectrum Lane ~ Missoula MT ~ Grizzly TM Part Number 21655 7100 Spectrum Lane ~ Missoula MT 59808 800.791.8056 ~ www.spectrumproducts.com 21655 Man Rev B You have purchased a Spectrum Products Grizzly starting platform. Providing the

More information

Foundation Manual. Part Number: Version: Updated: July 5, S. Meadows Pkwy. A-9, #329 Reno, NV

Foundation Manual. Part Number: Version: Updated: July 5, S. Meadows Pkwy. A-9, #329 Reno, NV Foundation Manual Part Number: 150002 Version: 1.22 Updated: July 5, 2009 748 S. Meadows Pkwy. A-9, #329 Reno, NV 89521 775-831-9463 www.mariahpower.com July 2009, Mariah Power, All Rights Reserved Dear

More information

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory

More information

Linear Drainage Z886. Perma-Trench. Installation Instructions. 100mm Clear Opening

Linear Drainage Z886. Perma-Trench. Installation Instructions. 100mm Clear Opening Linear Drainage Z886 100mm Clear Opening Perma-Trench Installation Instructions Z886 Tools Required Tape Measure Phillips Head Screwdriver Hammer Utility Knife Marker Cordless Drill Reciprocating Saw Ear

More information

Inigo Console Table INSTALLATION INSTRUCTIONS P74300, P A Page 1 of 5

Inigo Console Table INSTALLATION INSTRUCTIONS P74300, P A Page 1 of 5 P74300, P74301 Page 1 of 5 THANK YOU FOR CHOOSING KALLISTA We appreciate your commitment to Kallista quality products. Please take a moment to review this manual before you install your Kallista product.

More information

Water for the World. 7 y

Water for the World. 7 y Water for the World For effective water storage and water system operation, ground level storage tanks should be built for sufficient, and even excess, capacity and must be watertight to prevent leakage.

More information

Stretch Your Dollar Theme Designs Fire Pit

Stretch Your Dollar Theme Designs Fire Pit Stretch Your Dollar Theme Designs Fire Pit Tools Garden gloves Garden hose String (5 length) Stake Hammer or rubber mallet 3 Mason Chisel Tape measure 2 level 4 level (most homeowners don t have. We don

More information

T-WALL Retaining Wall System

T-WALL Retaining Wall System CONSTRUCTION MANUAL T-WALL Retaining Wall System The T-WALL Solution... THE NEEL COMPANY 8328 Traford Lane Springfield, VA 22152 Phone 703-913-7858 Fax 703-913-7859 T-WALL Retaining Wall System CONSTRUCTION

More information

Retaining Wall Installation Instructions PART 1 RETAINING WALL GENERAL

Retaining Wall Installation Instructions PART 1 RETAINING WALL GENERAL Retaining Wall Installation Instructions PART 1 RETAINING WALL GENERAL Work Included: Related Work All labor and material for the furnishing and installing of exterior stone landscaping wall. Masonry Contractor

More information

Instructions for 12 and 15 IGT systems (12 pictured)

Instructions for 12 and 15 IGT systems (12 pictured) Instructions for 12 and 15 IGT systems (12 pictured) Step 1: IGT Site Preparation Site Location Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system.

More information

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights 1 Exam Prep Placing Reinforcing Bars Tabs and s These 1 Exam Prep Tabs are based on the CRSI Placing Reinforcing Bars Recommended Practices, 9 th Edition. Each 1 Exam Prep tabs sheet has five rows of tabs.

More information

Garden WallScape Installation Guide

Garden WallScape Installation Guide By CornerStone Wall Solutions Inc. Garden WallScape Installation Guide GRAVITY/DETAILS The perfect balance... between design and nature Garden WallScape Overview note: bolded terms are defined in our online

More information

Single Post Anchor Part Number Spectrum Lane ~ Missoula MT ~

Single Post Anchor Part Number Spectrum Lane ~ Missoula MT ~ Single Post Anchor Part Number 21700 7100 Spectrum Lane ~ Missoula MT 59808 800.791.8056 ~ www.spectrumproducts.com 21700 Man Rev B You have purchased a Spectrum Aquatics Single Post Anchor. Providing

More information

PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM. SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual

PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM. SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual PV Mounting System 2703 SERIES 200 UL GROUND MOUNT SYSTEM SnapNrack Residential PV Mounting Systems Code Compliant Installation Manual Series 200 UL Introduction Series 200 UL Introduction SnapNrack Series

More information

1 Exam Prep Prov Module: Vertical Formwork Questions and Answers

1 Exam Prep Prov Module: Vertical Formwork Questions and Answers 1 Exam Prep Prov Module: 27308-14 Vertical Formwork Questions and Answers 1. The amount of formwork needed for a job can be influenced by. A. The size of the forming crew B. The project budget C. Materials

More information

Installation Manual. Foundations. Version 4.3ᵠ

Installation Manual. Foundations. Version 4.3ᵠ Installation Manual Foundations Version 4.3ᵠ (*) - Denotes Current Revisions throughout this Installation Manual Version 4 (ᵠ) - Denotes Current Revisions for Version 4.3 of this Manual Manual updated

More information

Linear Drainage ZF806 ZF812

Linear Drainage ZF806 ZF812 Linear Drainage ZF806 ZF812 Fiberglass Trench Installation Instructions ZF806 Accessories 6" [152mm] Wide Fiberglass Trench Drain System Below are some of the ZF806 trench drain components typical to an

More information

Installation and Fabrication Guidelines Sensitile Terrazzo - Terrazzo Lumina - PIXA

Installation and Fabrication Guidelines Sensitile Terrazzo - Terrazzo Lumina - PIXA Released August 2012 Sensitile Terrazzo, Terrazzo Lumina, and PIXA slab installation guidelines for horizontal and vertical use (tabletops, countertops, wall cladding etc). General Information Sensitile

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

Note on the assessment:

Note on the assessment: EXCERPTS Note on the assessment: The following is an excerpt from the book Post-disaster shelter: 10 Designs, IFRC, 2013. Inclusion of this design is for information purposes and does not necessarily imply

More information

PS 3000 Installation Manual Step-By-Step Procedures C.9. DOOR AND WINDOW OPENINGS C.9.1 PREPARE IN ADVANCE. C.9.2 VBUCK CONSTRUCTION.

PS 3000 Installation Manual Step-By-Step Procedures C.9. DOOR AND WINDOW OPENINGS C.9.1 PREPARE IN ADVANCE. C.9.2 VBUCK CONSTRUCTION. C.9. DOOR AND WINDOW OPENINGS Openings for doors and windows are formed with bucks, or frames, which are constructed to the rough opening dimensions required for the doors and windows to be installed.

More information

WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565)

WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565) WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565) PLASTIC CONDUIT AND FITTINGS PLACING INSTRUCTION NOTE: This "Guide" summarizes the opinions, recommendations, and practices of the Western Underground

More information

Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000

Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000 Instructions for the use of the Link 4 Pallet Rack Lifter (PRL) model 5000 (How to move your pallet racking using the Link 4 Pallet Rack Lifter) This process is for a typical rack move and reset. Each

More information

SECTION CHAIN LINK FENCES AND GATES (PARK)

SECTION CHAIN LINK FENCES AND GATES (PARK) SECTION 02821 CHAIN LINK FENCES AND GATES (PARK) PART I GENERAL 1.1 SECTION INCLUDES A. Installation of chain link fences, and gate units provided by single source including erection accessories, fittings,

More information

Installation Guide. PrivacyShield Outdoor Enclosure

Installation Guide. PrivacyShield Outdoor Enclosure Installation Guide PrivacyShield Outdoor Enclosure Table of Contents 1.0 Introduction... 2 2.0 Materials, Delivery & Tools... 2 3.0 Layout and Post Locations. 3 4.0 Foundations... 5 5.0 PVC Installation....

More information

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...

More information

Deck Design Mike & Melissa Deck Option #02

Deck Design Mike & Melissa Deck Option #02 Deck Design Mike & Melissa Deck Option #02 Congratulations! You just completed your Trex deck design. This report will provide the following information: Deck Layout Diagrams Basic Installation Tips Deck

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 7 NOTE: This special provision is generally written in the imperative mood. The subject, the

More information

Concrete weighs about 150 pounds per cubic foot

Concrete weighs about 150 pounds per cubic foot At Bassora, where they have no timber, they make arches without any frame. The mason, with a nail and a bit of string, marks a semicircle on the ground, lays his bricks, fastened together with a gypsum

More information

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution...

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution... T-WALL Retaining Wall System CONSTRUCTION MANUAL FOR RAILROAD PROJECTS T-WALL railroad units are 5.0' high x 7.5' wide. (stem lengths will vary) The T-WALL Solution... T-WALL Retaining Wall System CONSTRUCTION

More information

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE 44-1 44-1.01 Description 44-1 44-1.02 Materials 44-1 44-1.03 Proportions 44-1 44-1.04

More information

fusion shower pan on wood joists installation guide

fusion shower pan on wood joists installation guide a a) Wall b) Tile c) Shower Pan d) Liquid waterproofing e) Crack Isolation Tape f) Cement Board g) Subfloor h) Joists b c d f h g e fusion shower pan on wood joists installation guide www.trendingaccessibility.com

More information

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College SECTION 323113 - CHAIN LINK FENCES AND GATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

BioPrism Solid Surface

BioPrism Solid Surface Please read all instructions before installing products. STORAGE & HANDLING: Check for damage that may have occurred during transit. Keep receptor flat on pallet, as it was shipped, until ready to install.

More information

Multi-Piece EasyStep Product Installation Instructions

Multi-Piece EasyStep Product Installation Instructions Tools/materials you might need for proper installation 6D galvanized screws caulking gun shims tape measure 1/8 drill bit Phillips screw driver cardboard china marker (or grease pencil) furring strips

More information

Underground Exhaust System

Underground Exhaust System Operation and Maintenance Manual Underground Exhaust MONOXIVENT - SOURCE CAPTURE SYSTEMS - info@ Oct. - 2015 Underground Duct Construction Standards 1. Dig trench depth to allow for minimum distance from

More information

YOUR SPLASH PAD RESOURCE

YOUR SPLASH PAD RESOURCE 1 Index Permits & Inspections Material List Warnings Splash Pad Types Pre-Site Grading Plumbing Schematic Pressure Testing Concrete Preparation and Pour Housing/Nozzle Installation Above Ground Water Feature

More information

LINEAR DRAINAGE. Z886 Perma-Trench. 6" Perma-Trench Installation Instructions

LINEAR DRAINAGE. Z886 Perma-Trench. 6 Perma-Trench Installation Instructions LINEAR DRAINAGE Z886 Perma-Trench 6" Perma-Trench Installation Instructions Z886 Accessories 6" [152MM] WIDE TRENCH DRAIN SYSTEM Below are the components of the Z886 trench drain typical to an installation.

More information

ThermaSteel Corporation ASSEMBLY MANUAL

ThermaSteel Corporation ASSEMBLY MANUAL ThermaSteel Corporation ASSEMBLY MANUAL TABLE OF CONTENTS 1- INTRODUCTION 1.1 THERMASTEEL TM WALL PANELS 1.2 Drawing and Element Numbers 2- ASSEMBLY 2.1 Sequence of Assembly 2.2 Preparation of Foundation

More information

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM ARCHITECTURAL SPECIFICATIONS MANUFACTURER: InterBlock LLC PO Box 1123, Sheboygan, WI 53082 Phone Number 920-207-7234 SECTION 03100 STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM PART 1 GENERAL 1.01 Summary

More information

Encapsulated, Sealed & Closed Crawlspace Installation Manual

Encapsulated, Sealed & Closed Crawlspace Installation Manual YourCrawlSpace, Inc. 1007 Johnni4 Dodds Blvd. Mt. Pleasant, SC 29464 Toll Free: 877-44-CRAWL (27295) Local: (843) 593-1115 Encapsulated, Sealed & Closed Crawlspace Installation Manual Copyright 2017 Your

More information

adjustable fusion shower pan on wood joists installation guide

adjustable fusion shower pan on wood joists installation guide a a) Wall b) Tile c) Shower Pan d) Liquid Membrane e) Crack Isolation Tape f) Cement Board g) Subfloor h) Joists b d c f h g e adjustable fusion shower pan on wood joists installation guide www.trendingaccessibility.com

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

installation section three: Installation

installation section three: Installation section three: Installation block specifications...c2 wall layout, excavation...c3 protection of soils...c4 leveling pad...c5 lay first course...c6 backfill & compacting...c7 stepping & additional courses...c8

More information

RIGID SOLAR INSTALLATION MANUAL

RIGID SOLAR INSTALLATION MANUAL RIGID SOLAR INSTALLATION MANUAL Sunlover Heating Factory 5, 9 Jersey Road Bayswater VIC 3153 T: 03 9720 2133 F: 03 9720 3266 New South Wales 2/20-22 Foundry Road Seven Hills, NSW 2147 T: 02 9838 0000 F:

More information

Installation Instructions

Installation Instructions EconoDrain Trench Forming System Installation Instructions MultiDrain We Drain Your Site, Not Your Budget MultiDrain Systems, Inc. P.O. Box 88, Barium Springs, NC 28010 (704) 508-1010 or Toll Free 800-433-1119

More information

METATEK POWER HOUSE CONSTRUCTION BUILDER S GUIDE CHECKLIST

METATEK POWER HOUSE CONSTRUCTION BUILDER S GUIDE CHECKLIST BUILDER S GUIDE & CHECKLIST 1 Table of Contents OVERVIEW... 2 CONSTRUCTION GUIDELINES... 2 DO NOT MODIFY LIST... 3 OPTIONAL LIST... 3 BUILDING DRAWINGS... 4 CHECKLIST... 4 MATERIALS LIST... 15 MATERIALS

More information

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...

More information

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4.

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4. LATRINE CONSTRUCTION Pour flush latrine 2 Pour flush micro septic tank 3 Initial investment, location, human resources 4 Concrete rings 5 Box 6 Cover 7 Slab and ceramic pan 8 Ring mold 9 Structure and

More information

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2) Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction

More information

ACO DRAIN Site Installation Manual

ACO DRAIN Site Installation Manual ACO Construction & Building Products EXPANSION JOINT TO ENGINEER S DETAILS CONCRETE ACO DRAIN Site Installation Manual Fiberglass Drain Systems Getting Started ACO Drain consists of a full range of modular

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Sheet 1 of 5 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 812 and replace with the following: SECTION 812 PERMANENT SIGNING 812.1 DESCRIPTION

More information

SECTION NON-STRUCTURAL METAL FRAMING

SECTION NON-STRUCTURAL METAL FRAMING SECTION 09 22 16 PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies steel studs wall systems, shaft wall systems, ceiling or soffit suspended or furred framing, wall furring, fasteners, and accessories

More information

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 772 NOVEMBER 2017 (Formerly OPSS 772, November 2012) Note: The PROV published in November 2017 replaces OPSS 772 COMMON, November 2012 with no technical

More information

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

Genesis Panel Systems LLC Dura-Max Brick Panel Siding Installation Instructions

Genesis Panel Systems LLC Dura-Max Brick Panel Siding Installation Instructions Genesis Panel Systems LLC Dura-Max Brick Panel Siding Installation Instructions Thank you for purchasing the Genesis Dura-Max Brick Panel system for your project. The system allows you to have the look

More information

Concrete Framing: Slab on Grade

Concrete Framing: Slab on Grade Concrete Framing: Slab on Grade Casting a Concrete Slab on Grade Concrete Slabs Subgrade Preparation Drainage Layer Slab Edges Vapor Retarder (Moisture Barrier) Reinforcing Pouring the Concrete Finishing

More information

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting.

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting. ARMOR-BLOCK Installation guide Cap Block Exposed void for planting In situ soil Engineered backfill Compacted and prepared base Setback Lip Ph 0800 655 00 or visit www.csppacific.co.nz 19 February 08 /

More information

Zurn Z874. Trench Drain System. Installation Instructions

Zurn Z874. Trench Drain System. Installation Instructions Zurn Z874 Trench Drain System Installation Instructions Z874 Accessories Trench Drain System Below are the components of the Z874-X trench drain typical to an installation. Check your order to verify you

More information

Zurn Z874. Trench Drain System. Installation Instructions

Zurn Z874. Trench Drain System. Installation Instructions Zurn Z874 Trench Drain System Installation Instructions Z874 Accessories Trench Drain System Below are the components of the Z874-X trench drain typical to an installation. Check your order to verify you

More information

Low Maintenance Slabs Supports Are Needed for Long-Term Performance of Welded Wire Reinforcement In Slabs-On-Grade

Low Maintenance Slabs Supports Are Needed for Long-Term Performance of Welded Wire Reinforcement In Slabs-On-Grade TF 702-R-08 Low Maintenance Slabs Supports Are Needed for Long-Term Performance of Welded Wire Reinforcement In Slabs-On-Grade INTRODUCTION With its cost-efficiency and superior performance attributes,

More information