An Environmental Consulting and Industrial Hygiene Company

Size: px
Start display at page:

Download "An Environmental Consulting and Industrial Hygiene Company"

Transcription

1 An Environmental Consulting and Industrial Hygiene Company TECHNICAL SPECIFICATIONS & SCOPE OF WORK FOR ASBESTOS & LEAD PAINT DISTURBANCE AT THE DATA CENTER HVAC IMPROVEMENT PROJECT BUILDING 1300 CABRILLO COLLEGE APTOS, CALIFORNIA Prepared for Cabrillo Community College District Prepared by March 23, S. Bascom Avenue Campbell, California (408) Fax (408)

2 CONTENTS SECTION TITLE PAGE I General Project Information... 3 II Summary of Haz-Mat Work... 5 III Detailed Haz-Mat Abatement Procedures IV General Project Requirements V Asbestos Removal Requirements & Procedures VI Detailed Execution of Asbestos Related Work VII Lead Paint Handling & Disturbance Procedures VIII Detailed Execution of Lead Paint Handling Work IX Air Quality Monitoring by Owner s IH Consultant Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 2

3 SECTION I GENERAL PROJECT INFORMATION Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 3

4 GENERAL PROJECT INFORMATION Owner: Mr. Jon Salisbury Construction Project Manager Innovative Construction Services, Inc. Cell: Hereinafter in these documents, ICSM or any of its officers and/or representatives is referred to as the Owner s Representative. Project Name: Project Location: Industrial Hygiene (IH) Consultant: Abatement Contractor: Building 1300 Data Center HVAC Improvements Cabrillo Community College 6500 Soquel Drive Aptos, CA Hereinafter in these documents, the haz-mat work within the above-referenced Building on campus is referred to as the Project or Site. (ESI) 2220 S. Bascom Avenue Campbell, California Mr. Hooman Sotoodeh, Ph.D., PE Sr. Industrial Hygienist Cal/OSHA Certified Asbestos Consultant Tel. (408) Fax (408) Hooman@EnviroScience-Inc.com Hereinafter in these documents,, or any of its officers and/or representatives is referred to as the IH Consultant. To be selected by competitive bidding. An Environmental Consulting and Industrial Hygiene Company Hereinafter in these documents, the selected abatement contractor or any of its officers and/or representatives, are referred to as the Contractor. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 4

5 SECTION II SUMMARY OF HAZ-MAY WORK Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 5

6 GENERAL SUMMARY OF WORK This haz-mat abatement specification was prepared in anticipation for an HVAC upgrade project at Building 1300 of Cabrillo Community College, involving the following 2 Tasks: 1. Disturbance, drilling or cutting into wallboard with asbestos-containing joint compound/skim coat; 2. Removing HVAC equipment with leaded coating on exterior panels. Table 1 (below) summarizes the scope of work for asbestos or lead disturbance at this Site. Prior to bid submission, all General or Haz-Mat Abatement Contractors shall field-verify ALL quantities or use the architect s drawings for quantity take-offs. Table 1 HAZ-MAT SUMMARY OF WORK HAZ-MAT TASK STEPS INVOLVED EST. QUANTITY Erect a mini enclosure system around each section Approx. of wallboard to be cut or disturbed or around the HVAC 10 sections of Cutting or Drilling equipment to be demolished (with lead paint). wallboard through wallboard (4 x4 each) or textured skim coat Place the enclosure system under negative pressure with asbestos using a HEPA-filtered vacuum cleaner or small HEPA filtration device. OR Using personnel in full PPE and wet methods cut the wallboard while minimizing dust or debris or remove panels with lead paint while minimizing dust. Removing HVAC equipment with Upon completion of cutting, place all waste in Approx. lead containing paint 6-mil disposable bags, and HEPA vacuum & wet-wipe 10 HVAC Panels the entire containment and the floor plastic. (4 x4 each) Then demobilize from the area and request a final clearance inspection & sampling from the Owner s IH Consultant. Do not remove any containment barriers until authorized to do so by the Owner s IH Consultant. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 6

7 SAMPLE SETUP PHOTOS Typical dust protection containment setup during Drilling Activity Typical floor protection poly setup during Drilling Activity Trained haz-mat worker in full PPE getting ready to drill into ACM or Lead Drill or coring machine equipped with HEPA dust collection device (To be used on this project) Floor HEPA Vacuum for prompt cleanup of asbestos and lead dust from surfaces Back-pack HEPA Vacuum for prompt cleanup of asbestos and lead dust from surfaces Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 7

8 SITE PLAN Building 1300 Data Center HVAC Improvements Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 8

9 HAZ-MAT WORK SCHEDULE To be determined by the CM, Owner & GC after contract award. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 9

10 SECTION III DETAILED HAZ-MAT ABATEMENT PROCEDURES Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 10

11 POTENTIAL ASBESTOS HAZARDS This haz-mat abatement specification was prepared in anticipation for an HVAC upgrade project at Building 1300 of Cabrillo Community College, involving the following 2 Tasks: 1. Disturbance, drilling or cutting into wallboard with asbestos-containing joint compound/skim coat; 2. Removing HVAC equipment with leaded coating on exterior panels. Improper disturbance or dislocation of asbestos-containing materials (ACMs) may cause asbestos fibers to be released into the building's atmosphere, thereby creating a potential health hazard to other construction workers, students, staff, public, or other occupants who may be around during disturbance activities. Apprise all workers, supervisory personnel, subcontractors and consultants who will be at the jobsite of the seriousness of asbestos hazards and of proper work procedures, which must be followed. Where in the performance of the work all personnel, including without limitations workers, supervisory personnel, subcontractors, or consultants may encounter, disturb, or otherwise function in the immediate vicinity of any identified ACMs or performing general demolition tasks, take appropriate continuous measures as necessary to protect all building occupants, from the potential hazards of exposure to airborne asbestos fibers. Such measures shall include the procedures and methods described herein, and compliance with regulations of applicable federal, state and local agencies. ACM disturbance shall be conducted by EPA/AHERA-trained asbestos workers, with proper personal protective equipment (PPE), under full or partial containment (depending on the friability of the ACM), and using wet removal procedures. According to OSHA Construction Industry Standard for asbestos (29CFR ) & general industry asbestos standard (29CFR ) workers performing asbestos abatement must be trained, equipped with respirators with full body protection, and must be medically fit to wear respirators, as certified by an independent physician. SUMMARY OF ASBESTOS TESTING ESI did not conduct any asbestos sampling in Building However, Building 1300 is identical in construction type and age to Buildings 1400 and 1500, which have been surveyed and sampled by ESI in Feb Table 2 below summarizes the types, locations, and asbestos content of all suspect ACMs sampled by ESI, and analyzed by a NVLAP-certified independent laboratory in Buildings 1400 and Any confirmed ACMs are also assumed to exist in Building 1300, and shall be handled by a State-licensed, and DOSH-registered asbestos abatement contractor. Prior to bid submission, all haz-mat abatement contractors SHALL attend a site visit to familiarize themselves with building conditions, locations, and quantities of all ACMs to be abated or disturbed. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 11

12 Should any additional suspect material not characterized in this survey be discovered during work by the General Contractor (GC), construction shall stop, and the IH Consultant shall be notified immediately for proper sampling and analysis of the newly-discovered suspect material(s). The GC shall not make any assumptions in regards to the asbestos content, or lack of, any newly-discovered suspect material. Table 2 SUMMARY TABLE OF ASBESTOS SAMPLING IN BUILDINGS 1400 & 1500 Sample Sampled Sample Asbestos Recom- Number Material Location Concentration mendation MECHANICAL ROOM (UPPER LEVEL) 1400-L1 Drywall joint E. Wall of Drywall ND* N/A** compound mechanical room Joint Compound <1%C*** Abate as ACM L2 Drywall joint S. Wall of Drywall ND N/A compound mechanical room Joint Compound <1%C Abate as ACM L3 Drywall joint W. Wall of Drywall ND N/A compound mechanical room Joint Compound <1%C Abate as ACM L4 Vibration Mechanical room Black Damper ND N/A damper furnace L5 Vibration Mechanical room Black Damper ND N/A damper air ducts L6 Air duct Around air ducts of White Tape ND N/A joint tape mechanical room L7 Furnace Around furnace in White Tape ND N/A tape mechanical room L8 Caulking Around furnace of Gray Caulking ND N/A material mechanical room Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 12

13 Table 2 SUMMARY TABLE OF ASBESTOS SAMPLING IN BUILDINGS 1400 & 1500 Sample Sampled Sample Asbestos Recom- Number Material Location Concentration mendation GROUND LEVEL (AROUND CEILING REGISTERS AND GRILLS) 1400-L9 Ceiling tile SE side next to White Tile ND N/A material the entry way L10 Vibration SE side next to White Damper ND N/A damper the entry way L11 Ceiling tile Next to the White Tile ND N/A material assistant office L12 Vibration Next to the White Damper ND N/A damper conference room L13 Air duct Around air ducts Tan Tape ND N/A joint tape conference room L14 Drywall joint Above ceiling tiles Joint Compound 2%C Abate as ACM compound of main classroom Drywall ND N/A L15 Air duct Around air ducts Gray Tape ND N/A joint tape NE side ducts L16 Wall Ceiling of White Texture ND* N/A** texture asst office L17 Ceiling SW side of White Tile ND N/A tiles main classroom L18 Drywall joint Ceiling of the Joint Compound 2%C*** Abate as ACM compound computer Tech office Drywall ND N/A L19 Wall Ceiling of the White Texture ND N/A texture computer Tech office L20 Roofing Roof of Black Roofing ND N/A material Building 1400 * None Detected ** None Applicable *** Chrysotile-type Asbestos Based on the analytical findings of the LIMITED bulk samples collected at 2 identical Building (i.e., 1400 & 1500), ESI assumes that all wallboard and textured skim coats in Building 1300 are asbestos containing as well & shall be handled as such. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 13

14 POTENTIAL LEAD DUST HAZARDS NOTE: Lead-containing paint (LCP) does NOT needs to be abated. Paint, which is subject to drilling or similar disturbance may pose a respiratory health hazard and shall be dealt with in accordance with regulations & these specifications. If any painted surface on Site contains any concentration of lead, it will be considered to be lead-containing paint per Cal/OSHA s definition. Drilling into or otherwise disturbing leaded coatings is considered to be a Trigger Task activity according to OSHA lead in Construction Standard (29 CFR ) & OSHA General Industry Lead Standard (29 CFR ). Therefore workers conducting lead paint disturbance activities shall be trained, equipped with respirators with full body protection, and must be medically fit to wear respirators, as certified by an independent physician. In accordance with the above-referenced OSHA regulations, and in compliance with California Code of Regulations (CFR) Title 8, Section "Lead in Construction, the employer shall limit employee exposure to lead by using lead-safe work practices. These involves, regulated area, poly protective covering below drilling areas, wet methods to suppress lead dust, HEPA vacuum attachments or shrouds on the drills, personal protective equipment, and prompt cleanup of all debris, by trained personnel. Furthermore, the haz-mat contractor shall at all times during disturbance of leaded coatings perform personal air monitoring. The OSHA standard requires that no employee be exposed to lead dusts or fumes at concentrations greater than fifty micrograms per cubic meter (50 µg/m 3 ) of air, averaged over an eight-hour period. This is known as the Permissible Exposure Level (PEL). If any worker s exposure exceeds the action level (AL) of 30 µg/m 3, work practices causing the elevated lead levels shall cease or be modified to lower personal exposure. Rags and paint dust, and paint chip debris shall be treated as hazardous waste if laboratory results indicate a lead (Pb) concentration of 5 milligrams per liter or greater using the EPAapproved Toxicity Characteristic Leaching Procedure (TCLP) test or equivalent, or greater than 1,000 mg/kg using the total lead assay. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 14

15 SUMMARY OF PAINT CHIP SAMPLING ESI did not conduct any Paint Chip sampling in Building However, Building 1300 is identical in construction type and age to Buildings 1400 and 1500, which have been surveyed and sampled by ESI in Feb. 2016, for lead. Table 3 below summarizes the types, locations, and lead concentration of any suspect LCPs sampled by ESI, and analyzed by an EPA-certified independent laboratory in Buildings 1400 and Any confirmed LCPs are also assumed to exist in Building 1300, and shall be handled by a State-licensed, and RRP-trained lead abatement contractor. Prior to bid submission, all hazmat abatement contractors SHALL attend a site visit to familiarize themselves with building conditions, locations, and quantities of all LCPs to be abated or disturbed. Table 3 SUMMARY TABLE OF PAINT CHIP SAMPLING AT BUILDINGS 1400 AND 1500 Sample Painted Surface Paint Lead Recom- Number (Color) Location Concentration mendation 1400-P1 Furnace paint Furnace 0.33 % Treat all interior (Green) in the or surfaces painted mechanical room 3,300 ppm* this color as lead containing P2 Compressor tank Air compressor 0.46 % paint in the or Same as 1400-P1 (Silver) mechanical room 4,600 ppm P3 Interior wall Interior wall <0.010 % paint of the student or None (White) assistant office <LOD** P4 Interior wall Interior wall <0.010 % paint of the main or None (White) classroom <LOD * Parts Per Million ** Limit of Detection Based on the analytical findings of the LIMITED paint chip sampling conducted in Buildings 1400 and 1500, ESI assumes that all Furnace and Air Compressor panels in the Mezzanine of Building 1300 are lead containing as well & shall be handled as such. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 15

16 DUTIES OF THE OWNER S IH CONSULTANT During the course of the hazardous material (haz-mat) abatement of this project, the Owner shall secure and pay for the services of an independent Industrial Hygiene Consulting firm (ESI) to be present on site. ESI s duties are as follows: 1) The Consultant will be the Owner's representative during haz-mat abatement and until final air or dust wipe clearance is achieved in each containment. The Consultant will advise and consult with the Owner. The Consultant will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents; 2) The Consultant will have a site technician for air quality monitoring, contractor supervision, and to determine in general if the haz-mat related work is proceeding in accordance with the Contract Documents during the life of this project. On the basis of his/her on-site observations as a Consultant, he/she will keep the Owner informed of the progress of the Work; 3) Outside the scope of these contract documents, the Consultant will not be responsible for, and will not have control or charge of abatement means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, and he will not be responsible for the Contractor's failure to carry out the work in accordance with the Contract Documents. Outside the scope of these contract documents, the Consultant will not be responsible for, or have control or charge over the acts or omissions of the Contractor, Subcontractors, or any of their agents or employees, or any other persons performing any of the Work; 4) The Consultant and his employees (up to two individuals), shall at all times have access to the work area wherever it is in preparation and progress. The Consultant further reserves the right to stop the work at any time that he feels that workmanship or procedures are not in accordance with these contract documents or safety and health issues are violated; 5) The Contractor shall provide the Consultant with two (2) new half-mask type H respirators equipped with dual HEPA cartridges, and up to 2 changes of disposable clothing per work shift per person, for such access to the work area so the Consultant may perform his functions under the Contract Documents; and 6) Within the limits authorized by the Owner, the Consultant will have authority to reject work, which does not conform to these Contract Documents. Whenever, in his opinion, he/she considers it necessary or advisable for the implementation of the intent of the Contract Documents, he/she will have the authority to require special inspections or testing of the Work. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 16

17 SECTION IV GENERAL PROJECT REQUIREMENTS Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 17

18 NOTIFICATION LETTERS Where required by law, send written notification as required by the following state and federal agencies at least 10 working days prior to beginning any work on ACMs or LCPs. Send a copy of all notification letters to the IH Consultant and a second copy to the Owner. 1) USEPA National Emission Standards for Hazardous Air Pollutants (NESHAPS) USEPA Region 9 Asbestos NESHAPS Contact Air Management Division 215 Fremont Street San Francisco, CA ) Cal-OSHA Carcinogen Control Unit Cal-OSHA District Office 7700 Edgewater Drive, Suite 102 Oakland, CA ) Monterey Bay Unified Air Pollution Control District, Enforcement Division MBAPCD Silver Cloud Court Monterey, CA ) State of California Division of Occupational Safety and Health Lead-Work Pre Job Notification Include the following information in the notification letters sent to all agencies: Name and address of Property Owner Description of the area of the facility being abated, including the size, age, and use of the room within each building An estimate of the approximate quantity of friable ACM present in each building in terms of square feet of surface area Location of the building or rooms within each building being abated Scheduled starting and completion dates of abatement Nature of planned abatement and method(s) to be used Procedures to be used to comply with the requirements of USEPA National Emission Standards for Hazardous Air Pollutants (NESHAPS) Asbestos Regulations (40 CFR 61 Subpart M) Name and location of the waste disposal site where the friable ACM will be deposited Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 18

19 SUBMITTAL REQUIREMENTS No portion of the work requiring submittals shall be commenced until the submittals are approved by the Owner s IH Consultant. Delays to start of work caused by late or disapproved submittals shall be the sole responsibility of the Contractor. No extensions will be made to the contract time on account of such delays. Submit to the Owner and IH Consultant all submittals in the same order requested below. Submit one copy of the required submittals in Electronic Format. No paper submittal will be accepted. Pre-Start Submittals The following items shall be submitted for review by the Owner s IH Consultant after the issuance of the "Notice to Proceed" and at minimum 2 weeks prior to mobilization of the hazardous material haz-mat sub-contractor on-site: 1. Regulatory agency notifications (MBAPCD and Cal-OSHA) 2. DOSH registration for asbestos-related work 3. State contractor license issued by CSLB 4. Copies of all citations from any regulatory agency (past 3 years) 5. Certifications (AIHA, NVLAP, and ELAP) of accredited lab analyzing personal air samples 6. Contingency plans for emergencies including telephone numbers and location of emergency services (local hospitals, fire, ambulance, etc.) 7. Work schedule (start and completion dates for each phase) and hours of work on-site for each task 8. Current worker training, medical, and fit test certificates for asbestos and lead (CDPH cards) 9. Signed copies of Worker Acknowledgment certificates (elsewhere in this document) 10. Negative air machine certification report (DOP tests for each machine must be performed on-site prior to start of abatement) 11. Sample copy of asbestos & lead warning signs to be used 12. Asbestos & lead disturbance work plans 13. DTSC transportation license for the hazardous waste transporter 14. Hazardous waste disposal site license and certification to accept asbestos & lead wastes Post Completion Submittals The following items shall be submitted for the Owner and Consultant s records after the completion of the project. NOTE: The contractor s final request for payment will not be processed by the District unless all documents and records listed below are included in the final submittal. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 19

20 1. Daily Asbestos & Lead removal Decon logs 2. Daily manometer charts (to be submitted to the Consultant on a daily basis at the completion of each shift) 3. Daily personal air sample analysis data (to be submitted to the Consultant on a daily basis within 24 hours of sample collection) 4. Hazardous waste manifest(s) 5. Non-hazardous waste data form(s) for non-friable asbestos waste Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 20

21 QUALIFICATIONS OF THE HAZ-MAT ABATEMENT CONTRACTOR The Contractor must specialize in the removal of asbestos, disturbance of lead paint, and other hazardous materials identified in the scope of work, have been successfully engaged in such work for not less than 2 years, and be capable of demonstrating his/her ability to perform asbestos and lead disturbance activities by submitting the following: 1. A list of prior contracts performed during the past three years including: the names, addresses, and telephone numbers of at least three (3) owners for whom similar contracts were performed; and the cost, year of work, and description of work of each such contract. 2. Evidence of successful completion of prior contracts by submission of copies of all final clearance air sampling (for asbestos abatement projects), and dust wipe sampling (for lead disturbance projects), which may be from a third party Industrial Hygiene firm. ADMINISTRATIVE AND SUPERVISORY PERSONNEL The Contractor must provide a full-time General Superintendent who is experienced in administration and supervision of asbestos abatement projects including work practices, protective measures for building and personnel, disposal procedures, etc. This person is the Competent Person as required by CAL/OSHA in Title 8 CCR, Section 1529, Construction Safety Orders, for the Contractor and is the Contractor's representative responsible for compliance with all applicable federal, state and local regulations, particularly those relating to asbestoscontaining materials. This person must have completed a course at an EPA Training Center or equivalent certificate course in asbestos abatement procedures, have had a minimum of two years on-the-job training and meet any additional requirements set forth in CAL/OSHA Title 8, Section 1529, Construction Safety Orders for a Competent Person. WORKER TRAINING Train, in accordance with CAL/OSHA Title 8, 1529, all workers in the dangers inherent in handling asbestos and breathing asbestos dust and in proper work procedures and personal and area protective measures. Include but do not limit the topics covered in the course to the following: Methods of recognizing asbestos Health effects associated with asbestos Relationship between smoking and asbestos in producing lung cancer Nature of operations that could result in exposure to asbestos Importance of and instruction in the use of necessary protective controls, practices and procedures to minimize exposure including: Engineering controls Work Practices Respirators Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 21

22 Housekeeping procedures Hygiene facilities Protective clothing Decontamination procedures Emergency procedures Waste disposal procedures Purpose, proper use, fitting, instructions, and limitations of respirators as required by 29 CFR & CAL/OSHA Title 8, CCR 1529 Appropriate work practices for the project Requirements of medical surveillance program Review of 29 CFR 1926 & CAL/OSHA Title 8, CCR 1529 Negative air systems Work practices including hands on or on-job training Personal decontamination procedures Personal and area air monitoring procedures MEDICAL EXAMINATIONS Provide medical examinations for all workers, conducted within 12 months of the start of work, who may encounter an airborne fiber level of 0.1 f/cc or greater for an 8 hour time weighted average. In the absence of specific airborne fiber data provide medical examination for all workers who will enter the work area for any reason. Examination shall as a minimum meet OSHA requirements as set forth in CAL/OSHA Title 8, CCR In addition, provide an evaluation of the individual s ability to work in environments capable of producing heat stress in the worker. Submit, at a minimum, for each worker the following: Name and Social Security Number Physician's written opinion including at a minimum the following: - Whether worker has any detected medical conditions that would place him/her at an increased risk of material health impairment from exposure to asbestos - Any recommended limitations on the worker or on the use of personal protective equipment such as respirators - Statement that worker has been informed by physician of results of the medical examination and of any medical conditions that may result from asbestos exp. Copy of information that was provided to physician in compliance with CAL/OSHA Title 8, CCR 1529 Statement that worker is able to wear and use the type of respiratory protection proposed for the project, and is able to work safely in an environment capable of producing heat stress in the worker. Notarized Certifications: Submit certification signed by an officer of the abatement contracting firm and notarized that exposure measurements, medical surveillance, and worker training records are being kept in conformance with CAL/OSHA Title 8, CCR Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 22

23 CONTRACTOR RESPONSIBILITY The Contractor shall assume full responsibility and liability for the compliance with the project specifications, and the most stringent applicable Federal, State, and local regulations pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor is also responsible for all applicable fees due to any Federal, State, and local regulatory agency. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable Federal, State, and local regulations. The Contractor shall indemnify, defend, protect, and hold the Owner, the IH Consultant, and their employees, officers, and assigns harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other regulation on the part of himself, his/her employees, or his/her subcontractors. The Contractor shall assume full responsibility for replacement or repair of any incidental damages caused by abatement or activities associated with abatement. CERTIFICATE OF WORKER'S ACKNOWLEDGMENT After each worker has been included in the Contractor's Respiratory Protection Program, completed the training program, and medical examination, secure a fully executed copy of this form and return to the IH Consultant with other submittals. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 23

24 CERTIFICATE OF WORKER'S ACKNOWLEDGMENT PROJECT SITE: BUILDINGS: Building 1300 Cabrillo Community College District ADDRESS: 6500 Soquel Drive Aptos, CA ABATEMENT CONTRACTOR: Working with asbestos & lead can be dangerous. Inhaling asbestos fibers has been linked to various types of cancers. If you smoke and inhale asbestos fibers the chance that you will develop lung cancer is greater than that of the non-smoking public. Ingesting lead particles or inhaling lead dust can be associated with lead poisoning and elevated lead blood levels. Your employer's contract with the owner for the above project requires that you be supplied with the proper respirator and be trained in its use. You must also be trained in safe work practices and in the use of the equipment found on the job. You must receive a medical examination. These things are to have been done at no cost to you. By signing this certification you are assuring the owner that your employer has met these obligations to you. RESPIRATORY PROTECTION I have been trained in the proper use of respirators, and informed of the type of respirator to be used on the above-referenced project. I have a copy of the written respiratory protection manual issued by my employer. I have been equipped at no cost with the respirator to be used on the above project. TRAINING COURSE I have been trained in the dangers inherent in handling asbestos and breathing asbestos dust and in proper work procedures and personal and area protective measures. The topics covered in the course included the following: Physical characteristics of and health hazards associate with asbestos Respiratory protection and use of personal protective equipment Negative air systems and work practices including hands on training Personal decontamination procedures and personal air monitoring MEDICAL EXAMINATION I have had a medical examination within the past 12 months, which was paid for by my employer. This examination included: health history, pulmonary function tests and may have included an evaluation of a chest X-Ray. WORKER S NAME: SIGNATURE: SS Nº: xxx-xx- DATE: SUPERINTENDENT: Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 24

25 CONTRACTOR s USE OF PREMISES General: The Contractor shall limit his/her use of the premises to the work indicated, so as to allow for Owner occupancy and use by the other contractors (if needed). Use of the Site: Confine operations at the site to the areas permitted under the Contract. Portions of the site beyond areas on which work is indicated are not to be disturbed. Conform to site rules and regulations affecting the work while engaged in project construction. Keep existing driveways and entrances serving the premises clear and available to the Owner, IH Consultant, and their employees at all times. Do not use these areas for parking or storage of materials. Do not unreasonably encumber the site with materials or equipment. Confine stockpiling of materials and location of storage sheds to the areas pre-approved by the Owner. If additional storage is necessary, obtain and pay for such storage off site. Lock automotive type vehicles, such as passenger cars and trucks and other mechanized or motorized construction equipment, when parked and unattended, so as to prevent unauthorized use. Do not leave such vehicles or equipment unattended with the motor running or the ignition key in place or accessible to unauthorized persons. Maintain existing building in a safe and weather-tight condition throughout the abatement period. Repair damage caused by abatement operations. Take all precautions necessary to protect the building during the abatement period. Smoking or open fires will not be permitted within the building enclosure or on the premises. PATENTS AND ROYALTIES All fees or claims for patents, royalties or licenses on materials, equipment or processes used in the performance of work on this project shall be included in the bid amount. Without in any way limiting any other obligations in the contract documents, the Contractor shall defend, indemnify, save and hold harmless the Owner and the IH Consultant(s) and their officers and employees from all claims or liabilities, including costs and expenses, which may arise from the use on this Project of any patented or copyrighted materials, equipment, or processes. STOP WORK If the Owner or the IH Consultant presents a written stop work order immediately and automatically stop all work. Do not recommence work until authorized in writing by Owner through IH Consultant. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 25

26 SECTION V ASBESTOS REMOVAL REQUIREMENTS & PROCEDURES Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 26

27 CUTTING or DRILLING THROUGH ASBESTOS-CONTAINING MATERIAL OR LEAD-CONTAINING PAINT Containment: The following minimum containment is required: A layer of 6-mil thick polyethylene (poly) sheeting on all critical openings (i.e., windows, doors, ceiling penetrations, air vents, and other openings into the work area). A layer of 6-mil thick poly directly below the drilling area, extending at least 10-feet out. A decontamination unit, equipped with a change area (clean room), water for hand-washing, and an equipment room (dirty room) in a central area of the Site for access by all abatement personnel. An adequate number of HEPA-filtered vacuum cleaners to attach to drilling equipment for dust control (as shown on the right). Respiratory Protection: Drilling Method: Disposal: Clearance: Acceptance Criteria: With proper documentation from previously-performed personal sampling on a similar type of abatement work with a similar crew size, trained asbestos abatement personnel may wear half mask, air purifying, Type H respirators, equipped with dual HEPA cartridges. Full body coveralls, gloves, boots, hard hats & eye protection are also required for wallboard demolition. Slightly wet the wallboard or painted surface with a surfactant to minimize visible emissions during cutting, drilling or coring activity. Using a saw or drill equipped with a HEPA vacuum dust collection shroud, cut or drill through the asbestos or lead surface while minimizing dust generation. The Owner s IH Consultant will determine cleanliness of the surface by looking for dust or debris directly below the drilling activity. If found, the haz-mat contractor shall immediately HEPA-vacuum any dust or debris on the floor, or any other surface near the drilling activity. Place any drill or core cuttings in approved 6-mil labeled disposal bags. Wet-wipe the exterior of the bag and place inside a second bag and carry outside the containment. Do not accumulate more than 2 inches of liquid in the disposal bags. The top disposal bag shall have all necessary OSHA generator information prior to removal from the Site. All waste shall be properly disposed of at an approved hazardous waste landfill (class III) accompanied by the proper hazardous waste manifest. The hazardous and non-hazardous waste manifests may only be signed by a representative of the Owner. Provide 48-hr advance notice to the Owner s representative for all such manifest signing. The IH Consultant will use the air samples collected during drilling or coring activity as final clearance, together with a visual inspection. Air samples will be analyzed by PCM for airborne fibers, and by Flame AAS for airborne lead dust at a certified independent laboratory. Results will be reported to the Contractor within 24 hours of sample delivery to the laboratory. PCM samples are considered acceptable if the fiber concentration indicate fibers/cc or less. AAS samples are considered acceptable if the lead concentration is 30 µg/m 3 or less, or if the dust wipe samples on floor surfaces are 40 µg/ft 2 or less. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 27

28 SECTION VI DETAILED EXECUTION OF ASBESTOS RELATED WORK Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 28

29 WORK AREA ISOLATION The areas where asbestos abatement work takes place in each area of the Site is considered contaminated, and must be isolated from the balance of the building, and decontaminated at the completion of the asbestos-removal work. The Contractor shall completely isolate the work area from other parts of the building so as to prevent asbestos-containing dust or debris from passing beyond the isolated area. Should the area beyond the work area(s) become contaminated with asbestos-containing dust or debris as a consequence of the work, the Contractor shall clean those areas as specified later in the guidelines. All such required cleaning or decontamination shall be performed at no additional cost to the Owner. The Contractor shall place all tools, scaffolding, staging, etc., necessary for the work in the area to be isolated prior to erection of plastic sheeting temporary enclosure. All uncontaminated removable furniture, equipment, and/or supplies shall be removed from the work area before commencing work, or in case of fixed furniture shall be completely covered with two (2) layers of polyethylene sheeting, at least 6 mil in thickness, securely taped in place with duct tape. Such furniture and equipment shall be considered outside the work area unless covering plastic or seal is broached. Prior to abatement start, the Contractor shall disable the ventilating system(s) or any other system bringing air into or out of the work area. To do so, the Contractor shall inform the Owner s representative in writing, at least 48 hours prior to scheduled shut down. Any delays caused as a result of not following this noticing requirement, shall be the sole responsibility of the Contractor. CONTROL ACCESS Access to the work area shall be only through the Decontamination Unit. All other means of access shall be closed off and sealed and warning signs displayed on the clean side of the sealed access. Warning Signs shall be provided at each visual and physical barriers reading as follows in both English and Spanish: LEGEND DANGER ASBESTOS CANCER AND LUNG DISEASE HAZARD AUTHORIZED PERSONNEL ONLY RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA NOTATION 3" Sans Serif Gothic or Block 1" Sans Serif Gothic or Block 1" Sans Serif Gothic or Block 1" Sans Serif Gothic or Block 14 Point Gothic Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 29

30 CRITICAL BARRIERS The work area shall be completely separated from other portions of the building, and the outside air by sheet plastic barriers at least 6 mil in thickness, or by sealing small openings and penetrations with duct tape. All ventilation openings (supply and exhaust), lighting fixtures, clocks, doorways, windows, convectors and speakers, and other openings into the work area, especially above partition walls (if applicable), shall be individually sealed with duct tape alone or with polyethylene sheeting at least 4 mil in thickness, taped securely in place with duct tape. The seal shall be maintained until all work including Project Decontamination is completed. Sheet Plastic barriers at least 6 mil in thickness as required to completely seal openings from the work area into adjacent areas shall be provided by the Contractor. The perimeter of all sheet plastic barriers shall be sealed with duct tape and spray cement. PRIMARY AND SECONDARY BARRIERS If applicable to this project, all contaminated furniture, equipment, and or supplies shall be cleaned with a HEPA-filtered vacuum cleaner or by wet cleaning, prior to being moved or covered. All surfaces in the work area shall be cleaned with a HEPA-filtered vacuum or by wet wiping prior to the installation of any sheet plastic. Work areas shall be enclosed with two (2) layers of plastic sheeting, at least 4 mil in thickness, on walls and a single layer of poly on the ceiling of the containment. The ceiling poly shall be mechanically supported with wood or PVC tube framing. Both spray-glue and duct tape shall be used for all seams in the wall and ceiling coverings. All joints including the joining of the wall poly with the edge of the floor shall be taped with duct tape. In addition to the 2 layers of 4 mil poly on walls, a 4' high layer of 4 mil poly shall be fastened to the wall of the containment area to act as splash guard. NOTE: The top layer poly on all surfaces as well as plywood and other wood material used in the construction of the containment barriers must be fire-rated to comply with the local fire department regulations and restrictions. If stairs and ramps are within the containment area and are not being abated they shall be covered with 4 mil plastic and a 3/4" exterior grade plywood shall be provided with treads securely held in place, over plastic. Rungs or rails are not to be covered with any type of protective material. GLOVE BAG WORK PREPARATION If during construction, any thermal system insulation (TSI) is identified as requiring abatement inside wall cavities, or above ceilings, use the glovebag removal procedure as described herein. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 30

31 1. Isolate the area in which glove bag work will take place by placing barrier tape at least six feet from all open entrances to the affected room. Determine emergency exit provisions. Locate HEPA-filtered negative pressure units in the immediate area of glove bag work so as to provide at least four air changes per hour in the work area. 2. Place asbestos warning signs at all open entrances to work area conspicuously and so they can be easily read. They must conform to all Federal, State, and local regulatory requirements. 3. If possible, turn off or isolate the HVAC system in the work area from the rest of the building. If this is not possible, detail appropriate emergency provisions to turn off the system if required. 4. Double-check pipe, valve, etc., to ensure it is not too hot to work on and will not burn workers. It is preferable that all services be shut down to work site for worker safety. 5. In accordance with OSHA safety standards, and other applicable legal requirements, provide sufficient power so as not to cause electrical overload and circuit failure. Minimum respiratory protection in the form of Half Mask Type-H respirators with dual HEPA cartridges, and protective equipment in the form of disposable Tyvek coveralls, hoods and booties shall be worn by all workers and visitors who enter the barrier taped area or are involved in work set-up or actual performance of the glove bag operations, in any way. All applicable requirements with regards to respirators and protective equipment and clothing must be satisfied. In an area well outside the area where the work is to be performed (another room, if practicable, or the clean room if a mini-enclosure is used), workers and visitors shall wear protective equipment and clothing and a clean respirator. Workers shall pick up clean work equipment and tools and enter the work area. All workers and visitors who enter the work area must sign the appropriate log upon entry and exit. The logs shall be kept in the clean room where a mini-enclosure is used or well outside the work area if a mini-enclosure is not used. RECOMMENDED GLOVE BAG WORK PRACTICES If performing glove bag abatement procedures, the Contractor is required to follow the general work practices described below: 1. Glove bags must be installed so that they completely cover the pipe or other structure where asbestos work is to be done. Multiple glove bags shall be placed next to each other so that removal of one does not release fibers into the air from adjacent glove bags. All glove bags shall be smoke tested for air leakage after installation, and leaks shall be repaired to achieve an airtight enclosure before removal begins. If leaks are discovered, repair and repeat the smoke tube check. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 31

32 The glove bag is attached to the pipe or other removal area by folding the open edges together and securely sealing them with tape. All openings in the glove bag must be sealed with tape or equivalent material. The bottom seam of the glove bag must also be sealed with tape or equivalent to prevent any leakage from the bag that may result from a defect in the bottom seam. Put all tools in tool pouch (razor knife, damp rag, wire snips, etc., as required). Attach glove bag to work site. Use double-sided tape to hold top two flaps together, overlapping without wrinkles or air pockets. Leave enough slack at top of bag when removal starts. The weight of insulation and water can strain even a well-constructed seal at the top. Seal edges of glove bag around pipe to make an airtight seal. Use tape or a reusable or disposable strap (included with some glove bag brands). 2. Use nozzle port in bag to allow tip of sprayer nozzle to be inserted to spray amended water. Also, this opening will be used to insert end of the HEPA vacuum attachment. Each time hole is used, re-seal flap immediately with tape. Thoroughly wet work site inside bag with amended water. Do not fill bag up with excess water, which could cause the bag to tear and fall. Place arms in armholes and hands in gloves. Carefully remove the asbestos, wetting the material as required during removal. The choice of tool to use to remove the ACM depends on the type of material to be removed. ACM are generally covered with painted canvas and/or wire mesh. Painted canvas can be cut with a razor knife and peeled away from the ACM underneath. Once the canvas has been peeled away, the ACM underneath may be dry, in which case it should be re-sprayed with a wetting agent to ensure that it generates as little dust as possible when removed. If the ACM is covered with wire mesh, the mesh should be cut with nips, tip snips, or other appropriate tool and removed. One worker shall accomplish removal while a second worker simultaneously wets material. A wetting agent must then be used to spray any layer of dry material that is exposed beneath the mesh, the surface of the stripped underlying structure, and the inside of the glove bag. 3. After removal of the layer of ACM, the pipe or surface from which asbestos has been removed must be thoroughly cleaned with a plastic brush and wet-wiped with a wetting agent until no traces of the ACM can be seen. Use damp rag (in tool pouch) to wipe exposed pipe or metal clean of all visible foreign material. Thoroughly wet clean all reusable tools with water pump and place in tool pouch for latter recovery. Wash down sides of bag so all visible debris collects at the bottom of the bag. (An alternative method of tool recovery is to grasp the washed tools in one glove, pull inside out so tools are inside glove neck, seal and cut. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 32

33 4. Any asbestos-containing insulation edges that have been exposed as a result of removal or maintenance activity must be encapsulated with bridging encapsulant to ensure that the edges do not release asbestos fibers the atmosphere after the glove bag has been removed. 5. When the asbestos removal and encapsulation have been completed, a vacuum hose from a HEPA-filtered vacuum must be inserted into the glove bag through the port to remove any air in the bag that may contain asbestos fibers. Suck air out for two to three seconds. Do not suck water into vacuum. When the air has been removed form the bag, tape over hole in the bag and the bag should be squeezed tightly (as close to the top as possible and below tool pouch if tools are to be recovered), twisted, and sealed with tape to keep the asbestos material safely in the bottom of the bag. The HEPA can then be removed from the bag. The glove bag itself then shall be removed from the work area. Pull polyethylene asbestos disposal bag over lower portion of glove bag. Cut glove bag loosely across top; do not pull or tear. Recover tools and immediately immerse them in water to complete cleaning. Because of the extreme weight of these materials, all glove bags shall be double-bagged. Use wetable cloth, end caps, duct tape or spray glue (or a combination to ensure that all damaged surfaces of the insulation are sealed. After the work area has been rendered free of all visible asbestos residues, to the satisfaction of the IH Consultant, an additional spraying of encapsulating agent shall be applied to all pipe surfaces in the work area and to all plastic surfaces. Clean-up materials must also be treated as asbestos waste. Following the completion of work, the disposable clothing shall be HEPA-vacuumed, removed and placed in double polyethylene disposal bags. The disposal bags shall then be sealed. All polyethylene bags of waste shall then be taken to the transport vehicle for transportation to the disposal facility (workers taking waste materials to the transport vehicle must be protected by respirators and must wear protective clothing and equipment.) The respirator shall be removed only after it is wet-wiped clean. Each worker will wash face and hands after removal work and before breaks, lunch, end of the work day, or any other stoppage in the work. If practicable, a shower enclosure may be used for worker clean-up. If not practicable (i.e., due to limited space or unavailability of tap water), other available showering facilities may be used after completing wet washing of face and hands in clean buckets of water placed at the exit. For projects involving the glove bag removal techniques where no full asbestos enclosure system is required or where only a mini-enclosure is required, the nearest in-place shower facility shall be identified and designated for use in case of accidental fiber release; alternately, a portable shower shall be set up by the Contractor and available near the work area, if practicable. Technical Specifications & Scope of Work for Asbestos & Lead Disturbance at Page 33

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc.

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc. The following work procedures are specified on all full containment asbestos abatement projects that we design. A. Preliminary Air Sampling: Many buildings contain background fiber levels prior to, or

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

These procedures are to be followed by all persons required to perform the following work:

These procedures are to be followed by all persons required to perform the following work: These procedures are to be followed by all persons required to perform the following work: Entry into any ceiling space above which an asbestos-containing fireproofing or thermal insulation is present.

More information

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification SECTION 028200 - ABESTOS ABATEMENT PART 1 - GENERAL 1.1 SCOPE OF WORK A. The following asbestos-containing materials is known to be present on the First and Second Floor classrooms of the North Wing of

More information

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the City of Vancouver Invitation to Tender including all available documents,

More information

Certification Number: NAT Lead Renovation, Repair and Painting Program

Certification Number: NAT Lead Renovation, Repair and Painting Program Certification Number: NAT-117534-2 Lead Renovation, Repair and Painting Program August 2018 Lead Renovation, Repair and Painting Program TABLE of CONTENTS I. Purpose II. Risk Identification III. Responsibilities

More information

BASF Corporation Title: ASBESTOS HANDLING, REMOVAL AND DEMOLITION

BASF Corporation Title: ASBESTOS HANDLING, REMOVAL AND DEMOLITION Procedure No.: IH-6 Page: 1 of 16 Preparer: Owner: Approver: RECORD OF REVISIONS Date Details of Change 11/02/01 Added a Record of Revisions table. 08/14/08 Review of entire procedure. Deleted 4.3.3 and

More information

CLASS I AND II ABATEMENT PROJECT SUBMITTALS

CLASS I AND II ABATEMENT PROJECT SUBMITTALS 5.1 Pre-Work Submittals CLASS I AND II ABATEMENT PROJECT SUBMITTALS Abatement contractors shall submit the following in a bound notebook to AU or our designated representative at the mandatory pre-construction

More information

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the Invitation to Tender including all available documents, meeting minutes,

More information

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 REFERENCE: ISSUE DATE: January, 1983 CHANGES: TOPIC: Asbestos INITIATED BY: Business Services DATE OF

More information

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995.

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995. April 2012, rev. 00 02 8213 Asbestos Abatement 1. General 1.01 Summary of Work A. Contractor 1.02 Definitions 1. The Contractor shall provide removal and proper disposal of asbestos containing materials.

More information

SECTION 2080 ASBESTOS ABATEMENT

SECTION 2080 ASBESTOS ABATEMENT SECTION 2080 ASBESTOS ABATEMENT PART 1 - GENERAL 1.01 SECTION INCLUDES A. Specification for the abatement of identified asbestos-containing materials (ACMs) and asbestos-containing construction materials

More information

Section Asbestos Removal

Section Asbestos Removal Section Cover Page Section 02 82 33 2017-10-01 Use this Section to specify removal of materials containing asbestos, as listed below. Always use in conjunction with Section 02 82 01 - Asbestos Control

More information

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts 1) Introduction Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts Triumvirate Environmental Inc. (TEI) shall perform

More information

Site Specific Hazardous Material Abatement Work Plan

Site Specific Hazardous Material Abatement Work Plan Site Specific Hazardous Material Abatement Work Plan Jobsite Location: Pier 31 Building and Roof Repair Project Port of San Francisco San Francisco, California Prepared By: North Tower Environmental, Inc.

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations. 2. Scope The OSHA requirements and this

More information

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES

APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES TY PE 2 WOR K PR OCE DUR ES These procedures are to be followed by all maintenance personnel and contractors performing the following work at KPDSB buildings.

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work: 125 Syndicate Avenue, Thunder Bay, Ontario Page 1 of 5 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing the following work:.1 Removing asbestos-containing transite

More information

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f:

VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA p: f: VERTEX Corporate Headquarters 400 Libbey Parkway Weymouth, MA 02189 www.vertexeng.com p: 781.952.6000 f: 781.335.3543 EZRA BAKER ELEMENTARY SCHOOL/GYMNASIUM ASBESTOS ABATEMENT WORK PLAN ASBESTOS CONTAINING

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 8 1. Purpose This policy assists in protecting USPL workers from exposure to lead and to gain compliance with state and federal regulations.

More information

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS PART 1.0 GENERAL REQUIREMENTS.............................................. 1 1.1 Introduction.............................................................

More information

Rowan University Asbestos Management Program

Rowan University Asbestos Management Program Rowan University Asbestos Management Program Table of Contents I. Introduction II. Regulatory Compliance III. Department Responsibilities for Asbestos A. EHS (Safety Specialist Staff) B. EHS (Asbestos

More information

LEAD HAZARD CONTROL PROGRAM

LEAD HAZARD CONTROL PROGRAM LEAD HAZARD CONTROL PROGRAM Supervisor s Manual Prepared by Environmental Health and Safety Services Occupational Safety Programs GLOSSARY Abatement or Deleading CFR Control Measure Encapsulation EPA HEPA

More information

In general, the management plan development process consisted of:

In general, the management plan development process consisted of: NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department

More information

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Materials Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace

More information

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager

Asbestos Management Plan. Program originated: 02/2000 Last updated: 6/2015. Wendel Reece University Safety Manager Asbestos Management Plan Program originated: 02/2000 Last updated: 6/2015 Wendel Reece University Safety Manager TABLE OF CONTENTS I. Introduction II. Purpose III. Operations and Maintenance Asbestos Related

More information

Asbestos Management Program

Asbestos Management Program Oct. 10/06 Oct 10/06 1/13 Table of Contents 1 INTRODUCTION...2 2 PURPOSE...2 3 SCOPE...2 4 ROLES & RESPONSIBILITIES...2 5 INVENTORY...6 6 ACCESS CONTROL...6 7 INSPECTION...6 8 CLASSIFICATIONS OF ASBESTOS

More information

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION SECTION 13280 ASBESTOS CONTAINING MATERIALS REMEDIATION PART 1 GENERAL 1.1 SECTION INCLUDES A. Furnishing all labor, materials, equipment, and transportation necessary for properly and safely removing,

More information

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02

BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 BRIGHAM YOUNG UNIVERSITY IDAHO ENVIRONMENTAL, HEALTH & SAFETY SAFETY DEPARTMENT ASBESTOS MANAGEMENT PROGRAM EH-006-R02 Department Title: Safety Department Page: 2 Department Title: Safety Department Page:

More information

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION The following appendix includes information and standard drawings that are diagrammatic and are used only to convey intent. Guidelines for Use of Sample

More information

Work Plan dated February 17, Prepared by Axiom Partners, Inc. Stephen E. Minassian Massachusetts Asbestos Designer License #AD051928

Work Plan dated February 17, Prepared by Axiom Partners, Inc. Stephen E. Minassian Massachusetts Asbestos Designer License #AD051928 ABATEMENT WORK PLAN FOR EMERGENCY ASBESTOS ABATEMENT PROJECT CONSENTINO MIDDLE SCHOOL 685 WASHINGTON STREET HAVERHILL, MASSACHUSETTS Work Plan dated February 17, 2016 Prepared by Axiom Partners, Inc. Stephen

More information

ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps)

ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps) Los Rios Community College District Sacramento City College ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps) GENERAL This addendum forms a part

More information

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2065

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2065 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2065 APPROVED: SIGNED DATE: March 8, 2007 Jon Adams Director of Compliance TITLE: SUBJECT: RULE 4002 NATIONAL EMISSION

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

3. Asbestos Handling Program

3. Asbestos Handling Program 1.0 Introduction 3. Asbestos Handling Program This program will establish guidelines and procedures in the operations and maintenance of asbestos containing materials at PLU to protect all employees, contractors,

More information

Asbestos Management Program

Asbestos Management Program SUPERIOR-GREENSTONE DISTRICT SCHOOL BOARD Asbestos Management Program Introduction Asbestos, a designated substance, is a natural fibre commonly used in the manufacture of building materials. The use of

More information

INTRODUCTION TO THE PROGRAM

INTRODUCTION TO THE PROGRAM INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information

More information

Addendum Number One. USC Preston College Bathroom and Flooring Renovations Part II Project Number: H SG

Addendum Number One. USC Preston College Bathroom and Flooring Renovations Part II Project Number: H SG Compass 5 Partners, LLC Date of Issue: 03/31/14 Addendum Number One Project: USC Preston College Bathroom and Flooring Renovations Part II Project Number: H27-6068-SG TO: ALL BIDDERS OF RECORD This addendum

More information

BID SHEET EAST AND WEST TECHNOLOGY ASBESTOS ABATEMENT

BID SHEET EAST AND WEST TECHNOLOGY ASBESTOS ABATEMENT Renovations Asbestos Abatement BID SHEET EAST AND WEST TECHNOLOGY ASBESTOS ABATEMENT Asbestos Material Quantity Unit Price Bid Price Mud Compound Insulation 795 each Floor Tile 10,560 sf Lab Counter Tops

More information

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY

AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY AUBURN UNIVERSITY RISK MANAGEMENT & SAFETY ASBESTOS CONTROL PROGRAM September 22, 2006 Table of Contents 1.0 Introduction... 4 2.0 Purpose and Applicability... 4 3.0 Roles and Responsibilities... 5 3.1

More information

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES Project Description: Date Work Conducted: Completed by: (Name and Dept) NOTIFICATION/AWARENESS: 1.

More information

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 2 Definitions 2 Responsibilities 3 Hazard

More information

Asbestos and Lead Considerations in Construction Projects. Sean Purcer Senior Consultant Anthony Price Senior Consultant

Asbestos and Lead Considerations in Construction Projects. Sean Purcer Senior Consultant Anthony Price Senior Consultant Asbestos and Lead Considerations in Construction Projects Sean Purcer Senior Consultant Anthony Price Senior Consultant Who We Are History Founded in 1990 by Environmental, Health and Safety (EHS) managers

More information

Asbestos Awareness Program

Asbestos Awareness Program Safety Manual 1 of 9 Safety Manual Sect: 1.0 Purpose 2.0 Scope Rel. Date: Last Review: This program covers Ardent policy related to asbestos, either discovered or suspected in the workplace. Ardent recognizes

More information

40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT

40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT 69 Bridge Street Dedham, MA 02026 Phone 781.251.0040 Fax 781.251.0901 40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT for WHITMAN MIDDLE SCHOOL 100 Corthell Avenue Whitman, MA 02382 Initial

More information

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS

ATTACHMENT A RFP # BH ASBESTOS ABATEMENT REQUIREMENTS 1. DESCRIPTION OF WORK: ATTACHMENT A RFP # 024-0-2016BH ASBESTOS ABATEMENT REQUIREMENTS The work includes pre-cleaning, repair and/or removal and disposal of friable and non-friable asbestos containing

More information

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22 Page 1 of 22 Asbestos Survey Project Summary Pursuant to your request; Environmental, Inc., has performed an Asbestos Building Survey on 8/13/2014 and limited to the above referenced location. The Interior/Exterior/Roof

More information

EPA s New Renovation, Repair and Painting Rule

EPA s New Renovation, Repair and Painting Rule When is Compliance with the EPA Renovation, Repair, and Painting Rule Required? Scope of Rule: Renovation, repair and painting activities on target housing or child-occupied facility built before 1978

More information

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions.

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions. 028333 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions. B. Contract Drawings. 1.2 SUMMARY A. The lead removal work is in support

More information

Asbestos Management Program

Asbestos Management Program ENVIRONMENTAL HEALTH & SAFETY Reed College 3203 Southeast woodstock boulevard Portland, Oregon 97202-8199 Asbestos Management Program Effective Date: 6/16/2009 Revision Dates or Last Date: 2/2016 I. Purpose...

More information

Emergency Asbestos Abatement Project Monitoring September 21, 2013 Peebles Elementary School Bourne, Massachusetts

Emergency Asbestos Abatement Project Monitoring September 21, 2013 Peebles Elementary School Bourne, Massachusetts Emergency Asbestos Abatement Project Monitoring September 21, 2013 Peebles Elementary School Bourne, Massachusetts Bourne Public Schools Bourne, Massachusetts February 5, 2014 Fuss & O Neill EnviroScience,

More information

SECTION POLYCHLORINATED BIPHENYLS (PCB) REMOVAL

SECTION POLYCHLORINATED BIPHENYLS (PCB) REMOVAL SECTION 18200 POLYCHLORINATED BIPHENYLS (PCB) REMOVAL PART 1 GENERAL 1.01 RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division

More information

40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT INDIAN HEAD ELEMENTARY SCHOOL

40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT INDIAN HEAD ELEMENTARY SCHOOL 69 Bridge Street Dedham, MA 02026 Phone 781.251.0040 Fax 781.251.0901 40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT for INDIAN HEAD ELEMENTARY SCHOOL 726 Indian Head Street Hanson,

More information

Rutgers Environmental Health and Safety (REHS)

Rutgers Environmental Health and Safety (REHS) Rutgers Environmental Health and Safety (REHS) Program Name: Asbestos Management Program Responsible Executive: Executive Director of REHS Adopted: Reviewed/Revised: August 2, 2018 1. Program Statement

More information

CADMIUM AWARENESS Revision Date: 04/2017

CADMIUM AWARENESS Revision Date: 04/2017 CADMIUM AWARENESS 7.1 PURPOSE 7.1.1 The purpose of this policy is to provide guidelines for safely working with cadmium. It includes provisions for training, PPE guidelines, monitoring, medical surveillance,

More information

Post Abatement Project Report - Sample Draft Form:

Post Abatement Project Report - Sample Draft Form: Post Abatement Project Report - Sample Draft Form: 3701-3215 (B) (B) Each lead abatement contractor or lead abatement project designer shall issue a report for each lead abatement project performed. The

More information

Idaho Solid Waste Association

Idaho Solid Waste Association Idaho Solid Waste Association Idaho Snow: Debris from Collapsed Buildings EPA Asbestos Requirements for Demolishing a Building John Pavitt U.S. Environmental Protection Agency Region 10, Alaska Operations

More information

DIVISION 02 EXISTING CONDITIONS 2010 Edition, Published January 1, 2010; Document Revision Date: February 7, 2017

DIVISION 02 EXISTING CONDITIONS 2010 Edition, Published January 1, 2010; Document Revision Date: February 7, 2017 2010 Edition, Published January 1, 2010; Document Revision Date: February 7, 2017 02 00 00. EXISTING CONDITIONS 02 30 00. SUBSURFACE INVESTIGATION.1 Architect/Engineer RESPONSIBILITIES: The Architect/Engineer

More information

Asbestos Management Program. Site Function: Ecology, Health and Safety (EHS) Procedure No.: WYN Page: 1 of 13

Asbestos Management Program. Site Function: Ecology, Health and Safety (EHS) Procedure No.: WYN Page: 1 of 13 (EHS) Procedure No.: WYN032.051 Page: 1 of 13 Preparer: Owner: Approver: EHS Specialist EHS Specialist EHS Hub Manager Revision Date Revision Number 12/2003 1 New standard. 3/2012 2 5/2017 3 Revision History

More information

ASBESTOS DISPOSAL INFORMATION (Revised 07/15/18)

ASBESTOS DISPOSAL INFORMATION (Revised 07/15/18) Fairbanks North Star Borough Division 455 Sanduri Street Fairbanks, Alaska 99701 (907) 459-1482 FAX 459-1017 ASBESTOS DISPOSAL INFORMATION (Revised 07/15/18) The FNSB Division accepts asbestos on a scheduled

More information

Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS

Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS Appendix B PROCEDURES FOR REMOVAL OF MOULD-CONTAMINATED MATERIALS The following procedures are presented as a guide. Comprehensive site-specific technical specifications for the removal of mould-contaminated

More information

Asbestos Abatement Supervisor Syllabus

Asbestos Abatement Supervisor Syllabus Time: 40 hours Maximum Class Size: 12 Prerequisites: Asbestos Awareness & Asbestos Abatement Worker Course Description: This course is designed to empower the CCL Asbestos Abatement Supervisor with the

More information

Asbestos During Brake and Clutch Service Work Self Inspection Checklist

Asbestos During Brake and Clutch Service Work Self Inspection Checklist Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Asbestos During Brake and Clutch Service Work Self Inspection Checklist Guidelines: This

More information

NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES

NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES NORTH DAKOTA DEPARTMENT OF TRANSPORTATION REQUEST FOR PROPOSAL ASBESTOS AIR MONITORING SERVICES September 12, 2008 INTRODUCTION North Dakota Department of Transportation (NDDOT) is seeking an asbestos

More information

UNIVERSITY OF COLORADO AT BOULDER

UNIVERSITY OF COLORADO AT BOULDER UNIVERSITY OF COLORADO AT BOULDER SPECIFICATION FOR INDUSTRIAL HYGIENE CONSULTING SERVICES ASBESTOS ABATEMENT PROJECTS IN FACILITIES FACILITY ASSESSMENTS- PROJECT SURVEILLANCE-AIR MONITORING PROCEDURES

More information

Asbestos Abatement Worker Syllabus

Asbestos Abatement Worker Syllabus Time: 40 hours Maximum Class Size: 12 Prerequisite: Asbestos Awareness Course Description: This course is designed to empower the participant with the skills and knowledge to work safely, effectively and

More information

Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature:

Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature: Certified Renovator Training Hands-On Skills Assessment Date: Address: City & State Student Name: Student Signature: Skill Skill Set Description #1 Using EPA Recognized Test Kits and Paint Chip Sample

More information

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos?

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos? CHAPTER 34 ASBESTOS 34 ASBESTOS This chapter provides some brief information about asbestos in construction. If you encounter asbestos on the job, you will need more information. Here are the two main

More information

Safety Policy and Procedure

Safety Policy and Procedure Safety Policy and Procedure Policy Number 045 Authorized By: The Cianbro Companies Alan Burton Title: Asbestos Operations Effective Date: 03/25/09 Page 1 of 10 1 Status 1.1 Update of existing policy, effective

More information

Adv. 3.2: Asbestos Abatement Rev

Adv. 3.2: Asbestos Abatement Rev ADVISORY NO. 3.2: ASBESTOS ABATEMENT TERMINOLOGY AND DEFINITIONS Abatement: Procedures to control fiber release from asbestos-containing materials, i.e., removal, encapsulation, or enclosure. Air Lock:

More information

Project Monitoring & Air Sampling

Project Monitoring & Air Sampling Project Monitoring & Air Sampling 1. Qualifications of Air Sampling Personnel. The project air sampling shall be conducted by an asbestos project air sampling technician who has been trained in the selected

More information

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:

1.1 SUMMARY.1 Comply with requirements of this Section when performing following work: Page 1 of 6 Part 1 General 1.1 SUMMARY.1 Comply with requirements of this Section when performing following work:.1 Removing roofing materials that are suspected of containing asbestos using wet material

More information

BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS

BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS OF 5 BUILDINGS 1400 E. MISSION BOULEVARD POMONA, CA PROJECT NO. 3009860 JUNE 23, 2017 Prepared

More information

University of Colorado at Boulder SOC Asbestos Abatement Specification TABLE OF CONTENTS

University of Colorado at Boulder SOC Asbestos Abatement Specification TABLE OF CONTENTS TABLE OF CONTENTS Asbestos Abatement Specification Pg. 2-3 Schedule of Asbestos-Containing Materials Pg. 3-5 Examination of Site Pg. 5 Work Under Other Contracts Pg. 5-6 Work Sequence Pg. 6 Asbestos-Containing

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

OLM Environmental, LLC PHONE: (919) LOCKWOOD FOLLY LANE; RALEIGH, NC CELLPHONE: (919)

OLM Environmental, LLC PHONE: (919) LOCKWOOD FOLLY LANE; RALEIGH, NC CELLPHONE: (919) OLM Environmental, LLC PHONE: (919) 212-3019 2317 LOCKWOOD FOLLY LANE; RALEIGH, NC 27610 CELLPHONE: (919) 931-0629 July 31, 2016 Zapolski Real Estate, LLC 501 Washington Street Durham, North Carolina 27701

More information

Work Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos

Work Practice for Penetrating or Removing Wallboard Systems with <1% Asbestos University of Washington Facilities Services Maintenance & Alterations 9.5.02 Work Practice for Penetrating or Removing Wallboard Systems with

More information

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278 PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278 PREPARED FOR: Mr. Roberto Aguirre City of San Francisco DPW, SAR, BCM 1680 Mission Street San Francisco, California PREPARED

More information

HIGGINSVILLE HABILITATION CENTER MISC. BUILDING RENOVATIONS STATE OF MISSOURI HIGGINSVILLE, MISSOURI SECTION ASBESTOS ABATEMENT PART 1 -GENERAL

HIGGINSVILLE HABILITATION CENTER MISC. BUILDING RENOVATIONS STATE OF MISSOURI HIGGINSVILLE, MISSOURI SECTION ASBESTOS ABATEMENT PART 1 -GENERAL HIGGINSVILLE HABILITATION CENTER MISC. BUILDING RENOVATIONS STATE OF MISSOURI HIGGINSVILLE, MISSOURI SECTION 028213 ASBESTOS ABATEMENT PART 1 -GENERAL 1.01 Description 1.02 Related Requirements 1.03 Applicable

More information

EPA s Lead Program Rule At-A-Glance

EPA s Lead Program Rule At-A-Glance EPA s Lead Program Rule At-A-Glance FLOW CHART 1: Do the Requirements Apply to the Renovation? If you will be getting paid to do work that disturbs painted surfaces in a pre-1978 home, apartment building,

More information

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control

NAVSEA STANDARD ITEM. 1.1 Title: Asbestos-Containing Material (ACM); control NAVSEA STANDARD ITEM ITEM NO: 009-10 DATE: 30 APR 2018 CATEGORY: I 1. SCOPE: 1.1 Title: Asbestos-Containing Material (ACM); control 2. REFERENCES: 2.1 29 CFR 1915.1001, Occupational Safety and Health Standards

More information

ASBESTOS SCIENCE TECHNOLOGIES, INC.

ASBESTOS SCIENCE TECHNOLOGIES, INC. ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - astinc17@yahoo.com Report for Trinity Valley Elem. School Willow Creek, Ca. Mold Report - Rooms 12 through

More information

Roseville OFFICE* 1911 Douglas Blvd, ste * Roseville, CA Phone (916) * Fax (916) *

Roseville OFFICE* 1911 Douglas Blvd, ste * Roseville, CA Phone (916) * Fax (916) * Roseville OFFICE* 1911 Douglas Blvd, ste 85-349* Roseville, CA 95661 Phone (916) 628-0050 * Fax (916) 781-6837 * www.hazmanage.com Camino Union Elementary School District Maintenance Building Demolition

More information

Calvin College Asbestos Operations and Maintenance Plan

Calvin College Asbestos Operations and Maintenance Plan Calvin College Asbestos Operations and Maintenance Plan INTRODUCTION Calvin College s Asbestos Operations and Maintenance Plan has three primary objectives: 1) remove existing contamination and remove/repair

More information

Anticipated ICR 56 Revisions. Relating to Fire/Life Safety & Other Significant Issues

Anticipated ICR 56 Revisions. Relating to Fire/Life Safety & Other Significant Issues Anticipated ICR 56 Revisions Relating to Fire/Life Safety & Other Significant Issues Introduction Anticipated Timeframe for ICR 56 Revisions ICR 56 Fire & Life Safety Issues Cleanup of uncontrolled asbestos

More information

GENERIC ASBESTOS OPERATION AND MAINTENANCE (O&M) PLAN

GENERIC ASBESTOS OPERATION AND MAINTENANCE (O&M) PLAN Environmental Sciences Corporation 25 Years of Environmental Excellence National Environmental Assessment, Compliance, Industrial Hygiene, UST/AST, Construction Management and Engineering Services GENERIC

More information

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101 Issued 6/1/95 Revised 11/08/2004; 3/6/06 Please direct any questions or comments about the applicability of this document to Luigi

More information

HEALTH AND SAFETY MANUAL

HEALTH AND SAFETY MANUAL HEALTH AND SAFETY MANUAL Title: Spray Finishing Approved by: Greg Savoy Rev. 1/108 1 Purpose/Scope: The Company is firmly committed to providing each of its employees a safe and healthy work environment.

More information

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California for Bay Shore Library Bret Harte Library Dana Library Background Information Site/Building Owner: City of Long Beach Site Contact: The City of Long Beach Public Works Department, 333 West Ocean Blvd. Long

More information

The following regulations and guidelines may apply to this policy:

The following regulations and guidelines may apply to this policy: FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY Lead Compliance Policy 6/29/15 Last Revision Purpose: The purpose of this policy is to outline the management of lead containing material,

More information

Developed and Presented by: Wisconsin Healthcare Engineering Association

Developed and Presented by: Wisconsin Healthcare Engineering Association Infection Control Risk Assessment (ICRA) Developed and Presented by: Wisconsin Healthcare Engineering Association What is an ICRA? An Infection Control Risk Assessment is a tool devised to protect patients

More information

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL

PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL PROPOSED PILOT PROGRAM WORK PLAN FOR THE REMOVAL OF ALUMINUM COLUMN COVERS AND FASCIA WITH NON-FRIABLE ACM CAULKING MATERIAL At 130 Liberty Street New York, New York Lower Manhattan Development Corporation

More information

Tasks estimated to generate a TWA of 50 micrograms per cubic meter of air include:

Tasks estimated to generate a TWA of 50 micrograms per cubic meter of air include: Lead Exposure Compliance Program for Construction The purpose of this program is to inform interested persons, including employees, that Prairie Construction is complying with the OSHA Lead Standard, Title

More information

TSI SAMPLE MANAGEMENT PLANNER INITIAL. Training Services International, Inc. Qualifications & Functions

TSI SAMPLE MANAGEMENT PLANNER INITIAL. Training Services International, Inc. Qualifications & Functions MANAGEMENT PLANNER INITIAL Asbestos Training Course Federal Edition Training Services International www.training.com What management planning qualifications exist? How do I become certified to perform

More information

SUBPART 56-5 PHASE IA: ASBESTOS SURVEY PLANNING AND DESIGN

SUBPART 56-5 PHASE IA: ASBESTOS SURVEY PLANNING AND DESIGN SUBPART 56-5 PHASE IA: ASBESTOS SURVEY PLANNING AND DESIGN 56-5.1 Asbestos Survey Requirements for Building/Structure Demolition, Renovation, Remodeling and Repair (a) (b) Asbestos Survey Required. An

More information

Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016

Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016 Asbestos Management Policy University of Wisconsin-Platteville Reviewed 4/2016 1.0 Purpose This written program is intended to comply with both state and federal asbestos regulations. Asbestos containing

More information

"ASBESTOS AWARENESS IN THE WORKPLACE"

ASBESTOS AWARENESS IN THE WORKPLACE MAJOR PROGRAM POINTS "ASBESTOS AWARENESS IN THE WORKPLACE" Training For THE OSHA ASBESTOS STANDARD Quality Safety and Health Products, for Today...and Tomorrow Outline of Major Points Covered in the "Asbestos

More information

Asbestos Management Program

Asbestos Management Program Asbestos Management Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 5/8/2018 Table of Contents 1.

More information

PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I:

PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY FACILITIES AND SERVICES PROCEDURES FOR REMEDIATION OF FUNGI IN INDOOR ENVIRONMENTS LEVEL I: SMALL ISOLATED AREA (less than 10sq. ft.) -- e.g. CEILING TILES AND

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.10/22/08, 10/15/09 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information