Commissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan

Size: px
Start display at page:

Download "Commissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan"

Transcription

1 Commissioning National Training for Commissioning, 2006 Presented By Paul Sra and Mike Cavan 1

2 Scope of Presentation Commissioning overview Commissioning requirements for LEED Standard Roles and responsibilities of key persons for projects in regard to commissioning Commissioning process and its deliverables Case studies 2

3 What is Commissioning? ASHRAE defines the commissioning process as a quality oriented process for achieving, verifying and documenting that the perforamnce of facilities, systems and assemblies meet the defined objectives and criteria Commissioning is a quality assurance process where verification against design criteria is carried out, and ensures that adequate documention and O & M training has been provided. 3

4 What is Commissioning? A planned program of activities that advances the built works from the earliest stages of the Planning Phase to a condition of full operation, meeting all objectives of commissioning as defined by the client s functional program and the design intent. Commissioning is documenting for future operations. 4

5 Commissioning Requirements for LEED Standards For any LEED project, there are 6 fundamental Cx items that must be followed to attain LEED Certification; Engage a Cx Manager/Commissioning Authority Review Design Intent & other Design documentation. Include Cx requirements in Construction Specifications Develop & utilize a Cx Plan Verify installation, functional performance, training & Cx documentation Provide a final Cx report at the end of the project 5

6 Securing the Additional Commissioning Credit in The LEED System In addition to fundamental building Commissioning, an additional commissioning related point could be achieved: Commissioning Authority independent of the design team shall conduct a peer review of the design development, construction documents and contractor s submittals such as shop drawings. Provide a single manual containing all information required for re-commissioning the bldg. system Conduct a near end of warranty and plan to address occupant concerns 6

7 Why do we Commission? We Commission in order to provide a smooth transition from construction of the built works to an operational state. 7

8 Level /Extent of Commissioning In order to manage the cost and result of the commissioning process, owners must consider the following three basic questions: What systems should be commissioned What tasks should be completed in order to commission each system Who should be responsible for each task. Other factors: Type of project- new construction, fit-up, general purpose office, laboratory, Heritage Facility 8

9 Level/Extent of Commissioning (cont.) Complexity of project: Is it a Floor fit-up or Level 3 Lab - HVAC Containment / Fumehoods / Biological Safety Cabinets Profile of project LEED Certification 9

10 Commissioning of Total Building Systems Vertical Transportation Building Envelope Building Automation System (BAS) Integrated Mechanical & Electrical Electrical Distribution Facility Architectural Roof system, curtain wall system Integrated Security Life Safety Systems Indoor Environment Emergency Power Generation Heating & Cooling Plant 10

11 Benefits of Commissioning 1) Comprehensive understanding of Client s needs (such as functional and operational requirements) 2) Reduce tenant complaints and reduce O&M costs (by providing appropriate systems & equipment considering maintainability) 3)Indoor air quality parameters verified 4) Protection of health & safety of occupants (e.g. verification of Fire protection, life safety systems, security & operation of facility) 11

12 Objectives of Commissioning (Cont d) 5) Meet established energy budgets 6) Facilitates quality of construction and installation 7) Comprehensive training and documentation 8) Reduce risk of system failure/shutdown 12

13 When does Commissioning start? Commissioning starts at the planning phase and continues throughout all phases of the project. Commissioning supports total quality assurance in the design and development of facilities to meet client s needs. 13

14 Commissioning Activities in the PDS: Who is Involved Commissioning involves an integrated team comprising of: The Owner/Client The Project Manager The Commissioning Manager / Authority The Designer (Consultant) The Contractor Property Manager 14

15 Owner / Client Responsibilities Provides program requirements (technical & functional) Defines performance objectives & standards (technical data sheets) Sets Budgets & Schedules (milestones) Participates in selective Performance Tests Attends Training Participates to Interim acceptance process 15

16 Project Manager Responsibilities Overall responsibility for delivery of the project (of which Commissioning is part) Manages: - Contracts (consultants, contractors, client). - Relationship (Professional and Technical Services, Owner, Consultants, Commissioning Manager, Contractors, Property Manager. - All funding. 16

17 Coordinates Commissioning activities with the project team Commissioning Manager / Authority Responsibilities Carries out Quality Assurance on behalf of the Owner / Investor, Project Manager & Property Manager Reviews Commissioning Plan to ensure that plan is tailored to facility requirements Manages Commissioning process. 17

18 Commissioning Manager / Authority Responsibilities (Cont d) Reviews: and accepts Designer developed Cx specifications which include check sheets and functional performance tests. Design Intent & Concept drawing Design progress drawings (33%,66%,99%,100% & tender drawings) O&M Manuals Witnessing of equipment, system & Integrated & system performance tests 18

19 Design Consultant Responsibilities Liable and accountable Develops the Commissioning Plan Produces the Commissioning manual and Design Intent Develops the Commissioning Specifications Develops the Training Plan Develops the Commissioning forms (PI/PV & checklists) Develops and certifies the functional performance tests 19

20 Design Consultant Responsibilities (Cont d) Administers and reports on the commissioning process with the Contractor Provides approvals on verifications and testing Witnesses testing (as required) Assists in documentation turnover 20

21 General Contractor Responsibilities Accountable contractually Executes the commissioning deliverables as defined in the contract documents Develops the Commissioning schedule Refines the Commissioning Plan Executes & documents the functional performance (tests) Prepares & submits the O&M manual, training, asbuilts, warranties 21

22 Property Manager Responsibilities Receives the facility once project is complete Receives all documents required for operation Manages the facility Implements the Management Plan (BMP, MMS, Service contracts) Operates the facility through out its useful life 22

23 The Commissioning Process-1 * The Commissioning Process is based on the National Project Management System (NPMS) Project Inception -Definition phase Project Identification Initiation phase Feasibility phase Analysis phase Identification Close -out phase 23

24 The Commissioning Process-2 * The Commissioning Process is based on the National Project Management System (NPMS) Project Delivery stage Planning phase Design phase Implementation phase Delivery Close-out phase 24

25 Commissioning Activities in the NPMS Project inception/project identification stage Owner identifies the project s operational and functional requirements as well as sets budgets and milestones Establishes Commissioning needs Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design Implementation Close-out Project Management Commissioning Process 25

26 Commissioning Activities in the NPMS Project Delivery - Planning phase A list of Commissioning deliverables is identified and is included in the consultant brief (RFP, scope of work) This includes definition of building O&M and user requirements A Commissioning Manager (for the project) is appointed Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design Implementation Close-out Project Management Commissioning Process 26

27 Commissioning Activities in the NPMS Project Delivery stage Design phase Develop design intent Preliminary O&M and energy budget Prepare Preliminary Commissioning Plan to meet facility requirements & users needs within the facility Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design Implementation Close-out Project Management Commissioning Process 27

28 Commissioning Activities in the NPMS Project Delivery stage Implementation phase Develop Building Management Manual Review design to ensure facility needs have been addressed Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 28

29 Commissioning Activities in the NPMS Project Delivery stage Implementation phase Finalize commissioning plan Develop specification and performance verification forms to permit effective Commissioning of the facility. Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 29

30 Commissioning Activities in the NPMS Project Delivery -Implementation phase Develop a Training Plan to meet the requirements of the facility operators. Provide input to requirements for the construction phase and establishes an O&M budget Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 30

31 Commissioning Activities in the NPMS Project Delivery -implementation phase Provide input to requirements for the construction phase and establishes an O&M budget Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 31

32 Commissioning Activities in the NPMS Project Delivery stage implementation Review the Building System Shop Drawings for O&M Develop the Commissioning Schedule Finalize the Commissioning Plan Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 32

33 Commissioning Activities in the NPMS Project Delivery stage implementation phase Completion of Product Information/ Performance Verification(PI/PV) forms Site Co-ordination Meetings Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 33

34 Commissioning Activities in the NPMS Project Delivery stage implementation phase Complete the installation checklist O&M Manuals As-Built drawings Warranties Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 34

35 Commissioning Activities in the NPMS Equipment, systems and integrated systems commissioning tests are performed and witnessed Operational and Maintenance Manual(s) are completed Finalize Building Management Manual Ensure Commissioning deliverables are provided Interim acceptance is recommended to the Project Manager Ensure training of O&M staff is completed Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design ImplementationClose-out Project Management Commissioning Process 35

36 Commissioning Activities in the NPMS Project Delivery stage closeout phase -1 Complete all deferred commissioning tests & activities Assist in the fine tuning of systems Complete all outstanding design and construction (contractual) deficiencies relating to O & M issues Recommend final acceptance to the project manager Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design Implementation Close-out Project Management Commissioning Process 36

37 Commissioning Activities in the NPMS Project Delivery stage closeout phase-2 Project Team evaluation of lessons learned Assist the project manager in preparation of the final evaluation report Project Inception Project Identification Project Delivery Definition Initiation Feasibility Analysis Identification Close-out Planning Design Implementation Close-out Project Management Commissioning Process 37

38 Summary - Commissioning Deliverables Commissioning Plan Design reviews for O&M impacts Design Intent / System Operating Manual Commissioning Specifications 38

39 Summary - Commissioning Deliverables (Cont d) Commissioning Performance testing (PI/PV & checklists) Commissioning schedule Training Operation and Maintenance manuals(o&m) As-Built drawings Warranty (Documentation) 39

40 Commissioning: Return on Investment Can reduce operational & maintenance costs (through effective recommendation in the selection of equipment) Results in a product delivery with fewer deficiencies Reduces tenant complaints Reduces operational surprises Operational savings offset commissioning costs in one to two years Extended lifecycle on equipment Reduces changes during and after construction 40

41 Cx Case Study Not Commissioned 41

42 Cx Case Study Not Commissioned 42

43 Retro Commissioning EMCS & Lighting Systems Objectives; Identify energy deficiencies Optimization of systems Identify HVAC IAQ issues 43

44 Retro Commissioning Constructed early 70 s Existing mechanical systems EMCS approx. 10 years old Lighting system approx. 6 years old 44

45 Retro Commissioning Involved Operations Staff Involved the EMCS / Lighting Service providers Involved the field device maintainer Will involve an Energy Engineer 45

46 Retro Commissioning Verifications performed on EMCS; Field sensors and devices Sequence of operations under normal / Emer. procedures. Trending of systems 46

47 Retro Commissioning Key EMCS Issues Identified; Damper performance / calibrations VSD 100% most of the time Induction units 27% failure rate. Pneumatic devices / transducer compatibility 34% failure rate Operator Training 47

48 Retro Commissioning Major Building Issues; Stack effect Age of existing equipment Change in occupancy (space optimization) Minor fit-ups in building over the years 48

49 Retro Commissioning Lighting System; Areas of Interest Review current system operation and documentation Identify Maintenance Issues Identify energy saving potentials Cx of lighting system controls and devices 49

50 Retro Commissioning Key Lighting system Issues Clock was not recognizing weekends and holidays. DOS based Operator interface Failed relays Additional Feature lights not on system Daylight Harvesting Change-out of tubes Operator Training 50

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015

Commissioning at NYP. Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 1 Commissioning at NYP Joseph Lorino, PE, LEED Vice President, Facilities Management November 4, 2015 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program

More information

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document

More information

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning A Building Commissioning Overview Presented by: Goetting & Associates Commissioning www.goettingcx.com What is the Definition of Commissioning? Building Commissioning is a Quality Assurance Process of

More information

Minnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation

Minnesota State Colleges and Universities. South Central College. Request for Proposals for Commissioning Agent. STEM and Healthcare Renovation Minnesota State Colleges and Universities South Central College Request for Proposals for Commissioning Agent STEM and Healthcare Renovation Date: 12/18/2017 ADDENDUM #1 1. The Sign-In sheet for the voluntary

More information

FACILITIES MANAGEMENT

FACILITIES MANAGEMENT FACILITIES MANAGEMENT Planning, Design & Construction September 24, 2014 Re: Request for Proposals- Commissioning Services Hardin Library for Health Sciences Upgrade Building Systems # University of Iowa

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

Introduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D.

Introduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D. New and xisting Facilities D. ric Gregory, CCP Commissioning Manager Sustainable Performance Program Manager mory University eric.gregory@emory.edu (404) 727-1388 Introduction Cx Manager at mory University

More information

Introduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1

Introduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1 Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:

More information

Commissioning: What Architects Need to Know

Commissioning: What Architects Need to Know Commissioning: What Architects Need to Know Rino Zan P.Eng., Morrison Hershfield Ltd. rzan@morrisonhershfield.com Ontario Association of Architects May 12 & 13, 2016 Commissioning: What Architects need

More information

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL SECTION 01815 - HVAC COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Building Commissioning

Building Commissioning Building Commissioning Roles, Responsibilities, and Benefits 2010 ASHRAE Annual Meeting CxA WORKSHOP Saturday, June 26, 2010 Jim Magee, CxA, LEED-AP Facility Commissioning Group Overview Cx Advocacy, Economics,

More information

Request for Commissioning Services Proposal [Review and edit to suit project]

Request for Commissioning Services Proposal [Review and edit to suit project] Request for Commissioning Services Proposal [Review and edit to suit project] Issuance Date: Closing Date: [ Insert Owner s Name ] (Owner) requests written proposals to secure commissioning authority (CxA)

More information

REQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa #

REQUEST FOR PROPOSAL. Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # REQUEST FOR PROPOSAL Commissioning Services College of Pharmacy Building Construct New Facility University of Iowa # Addendum #1 Issued Wednesday, February 10, 2016 Changes: Item #01: Item #02: Section

More information

Attachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #

Attachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone # UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial

More information

COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202

COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning

More information

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No March 2017

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No March 2017 DEPARTMENT OF THE ARMY ER 1110-345-723 U.S. Army Corps of Engineers CECW-CE Washington, DC 20314-1000 Regulation No. 1110-345-723 31 March 2017 Engineering and Design TOTAL BUILDING COMMISSIONING PROCEDURES

More information

TABLE OF CONTENTS. Appendix A DoDEA UFC High Performance Sustainable Building Compliance Checklist...9. Version 2.0 August2017 Page 2

TABLE OF CONTENTS. Appendix A DoDEA UFC High Performance Sustainable Building Compliance Checklist...9. Version 2.0 August2017 Page 2 TABLE OF CONTENTS Acronyms...3 1.0 Purpose...4 2.0 Applicability...4 3.0 References...4 4.0 Responsibilities...4 4.1 Department of Defense Education Activity, Headquarters (HQ DoDEA)...4 4.2 DoDEA Regional

More information

Commissioning Cx High Performance Facilities Green Projects-LEED

Commissioning Cx High Performance Facilities Green Projects-LEED Background High Performance Facilities Green Projects-LEED 15-or-so-Best Practices Thoughts & Ideas Glin W. Jay, CFM, CFMJ, PMP, IFMA Fellow Characteristics of FM O&M Models Deferred Industry Standard

More information

USGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit

USGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit USGBC National Capital Region MasterClass Series: The Ins and Outs of Existing Building Commissioning Analysis Credit Jeffrey Salay, PE, CEM, LEED AP Senior Principal 13 December 2017 GHT Limited is a

More information

What Contractors Need to Know about LEED Commissioning & IAQ Management

What Contractors Need to Know about LEED Commissioning & IAQ Management What Contractors Need to Know about LEED Commissioning & IAQ Management Presented by Energy Ace, Inc. Wayne Robertson, PE, CxA What is Commissioning? Commissioning is a systematic process of assuring that

More information

George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING

George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING AIA Quality Assurance Learning Objectives Demonstrate global results of the analysis of energy

More information

SMART COMMISSIONING. Matt Berbée, Caltech Glenn Friedman, Taylor Engineering Jim Meacham, Altura Associates

SMART COMMISSIONING. Matt Berbée, Caltech Glenn Friedman, Taylor Engineering Jim Meacham, Altura Associates SMART COMMISSIONING Matt Berbée, Caltech Glenn Friedman, Taylor Engineering Jim Meacham, Altura Associates Complexity of Smart Buildings Image Source: USGBC m TRADITIONAL COMMISSIONING DESIGN & CONSTRUCTION

More information

APPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects

APPENDICES DESIGN REQUIREMENTS. Appendix A. Performance Criteria for Design Projects PROVINCE OF NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND INFRASTRUCTURE RENEWAL DTIR Document DC350 APPENDICES DESIGN REQUIREMENTS Appendix A Performance Criteria for Design Projects 2010 EDITION Printed

More information

THERMA-FUSER VARIABLE AIR VOLUME DIFFUSER SYSTEMS

THERMA-FUSER VARIABLE AIR VOLUME DIFFUSER SYSTEMS SUSTAINABLE DESIGN FORM 010.901 REV 1211 THERMA-FUSER VARIABLE AIR VOLUME DIFFUSER SYSTEMS SUSTAINABLE DESIGN GUIDE StopWaste.Org LEED-NC Platinum Energy Foundation LEED-CI Platinum Adobe East Tower LEED-EB

More information

LEED LEED. Leadership in Energy and Environmental Design. A voluntary, consensus-based. high-performance, sustainable buildings and neighborhoods

LEED LEED. Leadership in Energy and Environmental Design. A voluntary, consensus-based. high-performance, sustainable buildings and neighborhoods LEED An Introduction to LEED V3 2009 LEED Leadership in Energy and Environmental Design A voluntary, consensus-based national standard for developing high-performance, sustainable buildings and neighborhoods

More information

Technical Retro-Commissioning of Existing Buildings

Technical Retro-Commissioning of Existing Buildings Standard S0 0 0 Technical Retro-Commissioning of Existing Buildings Review Draft (--) This draft has been recommended for public review by the responsible project committee. To submit a comment on this

More information

Non-Third Party ( Abbreviated ) Commissioning: Managing Conflict of Interest

Non-Third Party ( Abbreviated ) Commissioning: Managing Conflict of Interest Non-Third Party ( Abbreviated ) Commissioning: Managing Conflict of Interest Treasa Sweek CTG Energetics, Inc. Synopsis Abbreviated commissioning presents contractual and organizational challenges for

More information

Sustainable Building Operations & Upgrades

Sustainable Building Operations & Upgrades Sustainable Building Operations & Upgrades LEED for Existing Buildings 2010 Energy / Facilities Connections Conference Brightworks & Glumac Eric Baxter and Todd McGuire 12 May, 2010 The Value Proposition

More information

Net Zero Building Commissioning. Phillip Saieg, CEM, LEED AP O+M Josh Harwood

Net Zero Building Commissioning. Phillip Saieg, CEM, LEED AP O+M Josh Harwood Net Zero Building Commissioning Phillip Saieg, CEM, LEED AP O+M Josh Harwood AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects

More information

445: Building Commissioning

445: Building Commissioning 445: Building Commissioning Class Objectives Introduce the concepts and language of Commissioning to those with limited exposure. Bring new ideas and resources to those with commissioning experience. Focus

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.

More information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE Based upon B3 Minnesota Sustainable Building Guidelines VERSION 2.1 Notes to the reader have been added to this document within numerous text boxes

More information

Errata Sheet. LEED for Schools Reference Guide First Edition for the document titled:

Errata Sheet. LEED for Schools Reference Guide First Edition for the document titled: Errata Sheet for the document titled: LEED for Schools Reference Guide First Edition 2007 Notes: Updates to this document are posted on the LEED for Schools Rating System page and the Reference Guide electronic

More information

Commissioning Lighting Control Systems

Commissioning Lighting Control Systems AABC Commissioning Group AIA Provider Number 50111116 Commissioning Lighting Control Systems Course Number: CXENERGY1727 Jesse Felter, SSRCx Tom Divine, P.E., SSR April 27, 2017 Credit(s) earned on completion

More information

NAVFAC SOUTHWEST / OICC MCIWEST. World Class Construction Forum Commissioning

NAVFAC SOUTHWEST / OICC MCIWEST. World Class Construction Forum Commissioning NAVFAC SOUTHWEST / OICC MCIWEST World Class Construction Forum Commissioning 17 August 2011 Agenda 0830-0845: Welcome Aboard & Forum Introduction 0845-0900: Commissioning 0900-1015: Commissioning Lessons

More information

BCA. Commissioning The Building Envelope. Mike MeLampy & Kevin Knight. KTA Building Services Group. Presented by; Retro-Specs Consultants

BCA. Commissioning The Building Envelope. Mike MeLampy & Kevin Knight. KTA Building Services Group. Presented by; Retro-Specs Consultants BCA Commissioning The Building Envelope Presented by; Mike MeLampy & Kevin Knight KTA Building Services Group? 1 Latter-day Building Envelopes Simple Building Materials. Limited Layers. Master Tradesmen.

More information

PROJECT DESIGN EVALUATION AND APPROVAL PROCESS DESIGN AND CONSTRUCTION STANDARD

PROJECT DESIGN EVALUATION AND APPROVAL PROCESS DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL 1.01 General Requirements A. These guidelines are intended to provide a framework to evaluate building projects for the University of Texas at Austin to: 1. Verify the feasibility of options

More information

Commissioning Under the Influence

Commissioning Under the Influence Commissioning Under the Influence Redefining the Traditional Role of the Commissioning Agent in the Design and Construction of the Building Envelope National Conference on Building Commissioning: May 2-4,

More information

Research Analysis: Building Envelope and LEED Credits Introduction

Research Analysis: Building Envelope and LEED Credits Introduction : Building Envelope and LEED Credits Introduction Green buildings are no longer a new idea and are quickly becoming the trend in the slowly changing industry of building construction. Even though the essence

More information

Green Ordinance Implementation City of Dallas, TX

Green Ordinance Implementation City of Dallas, TX Green Ordinance Implementation City of Dallas, TX City of Dallas BUILDING INSPECTION DEPARTMENT Phase 1 Effective Date October 1, 2009 Applications for building permits Structure One ordinance amending

More information

Commissioning: The Most Important Component of LEED. Rick Miller, PE, LEED AP. RNM Engineering, Inc. San Luis Obispo, CA

Commissioning: The Most Important Component of LEED. Rick Miller, PE, LEED AP. RNM Engineering, Inc. San Luis Obispo, CA Commissioning: The Most Important Component of LEED by Rick Miller, PE, LEED AP RNM Engineering, Inc. San Luis Obispo, CA LEED and Commissioning EA Prerequisite Fundamental Commissioning of Building Energy

More information

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Matthew Tunnard, PE, CCP, LEED AP, Senior Engineer Horizon Engineering Associates, LLP AIA Quality Assurance

More information

LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction

LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction LEED v4 for Homes, Residential Project Summary and Checklist One and Two Family New Construction Summary Date of Application Path Project Project Address Owner Architect Third Party Third Party Provider

More information

RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE

RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT Adam Renzi, PE AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute

More information

Use of Commissioning for LEED Projects. H. Jay Enck President Commissioning & Green Building Solutions, Inc.

Use of Commissioning for LEED Projects. H. Jay Enck President Commissioning & Green Building Solutions, Inc. Use of Commissioning for LEED Projects H. Jay Enck President Commissioning & Green Building Solutions, Inc. AIA Quality Assurance Learning Objectives 1. Use of the commissioning process for more efficient

More information

LEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering

LEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering LEED Commissioning and Actual Energy Use John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering AIA Quality Assurance Learning Objectives 1. Why Best Practice and Fundamental Commissioning are

More information

DLR Group is ranked #1 by ARCHITECT, the official publication of the American Institute of Architects, in its 2012 ARCHITECT 50 ranking of U.S.

DLR Group is ranked #1 by ARCHITECT, the official publication of the American Institute of Architects, in its 2012 ARCHITECT 50 ranking of U.S. DLR Group is ranked #1 by ARCHITECT, the official publication of the American Institute of Architects, in its 2012 ARCHITECT 50 ranking of U.S. firms. This ranking is based on design excellence (reflected

More information

LEED 2009 for New Construction and Major Renovations

LEED 2009 for New Construction and Major Renovations LEED 2009 for New Construction and Major Renovations Bayshore District Operations Building Project Checklist 4.28.6 20 4 0 Sustainable Sites Possible Points: 26 Y? N d/c Notes: Y C Prereq Construction

More information

Analysis 1. LEED Analysis of Laboratory Buildings. Penn State School of Forest Resources University Park, PA

Analysis 1. LEED Analysis of Laboratory Buildings. Penn State School of Forest Resources University Park, PA Analysis 1 LEED Analysis of Laboratory Buildings Background The LEED program (Leadership in Energy and Environmental Design) established by the U.S. Green Building Council is becoming the standard by which

More information

Draft Policy for Commissioning/ Retro-Commissioning

Draft Policy for Commissioning/ Retro-Commissioning Draft Policy for Commissioning/ Retro-Commissioning Strategic Plan Task 3.2.4: Deliverable 2.E.3 Funded by: Southern California Edison Company Local Government Strategic Plan Strategies Program 2010 2012

More information

CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017

CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017 CODE REQUIREMENTS FOR BUILDING COMMISSIONING SCOTT WEAVER, PE, QCXP, LEED AP BD+C DIRECTOR, COMMISSIONING DECEMBER 1, 2017 OVERVIEW The recent adoption by the Centers for Medicaid and Medicare Services

More information

VOL. 2/ DESIGN+ CONSTRUCTION. Group 1 Projects. Building Design and Performance Standards. University of Hawaii at Manoa

VOL. 2/ DESIGN+ CONSTRUCTION. Group 1 Projects. Building Design and Performance Standards. University of Hawaii at Manoa University of Hawaii at Manoa Building Design and Performance Standards VOL. 2/ DESIGN+ CONSTRUCTION Group 1 Projects To be used by Design and Construction Teams [BLANK] Page 2 of 190 UHM BDPS- D+C GROUP

More information

Manage Deliverables - Construction Step 6 February 2015

Manage Deliverables - Construction Step 6 February 2015 Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection

More information

Pepco Holdings, Inc. (PHI) C&I Energy Savings Program Commissioning and O&M Incentives

Pepco Holdings, Inc. (PHI) C&I Energy Savings Program Commissioning and O&M Incentives Pepco Holdings, Inc. (PHI) C&I Energy Savings Program Commissioning and O&M Incentives Brooke Smallwood- Lockheed Martin Brooke is a Program Specialist for Lockheed Martin. Lockheed Martin is the implementation

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

LEED And Your Indoor Environment

LEED And Your Indoor Environment LEED And Your Indoor Environment An overview of LEED v3 and Indoor Air Quality David McCauley, CIE Council Certified Indoor Environmentalist ACAC CIE #1008005 USGBC's Mission To transform the way buildings

More information

ACOUSTICAL WALL TREATMENT SECTION 09840

ACOUSTICAL WALL TREATMENT SECTION 09840 ACOUSTICAL WALL TREATMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Site-fabricated, stretched fabric acoustical wall system built with rigid polymer stretching system to secure fabric over the wall

More information

ACHIEVE MULTI-BENEFITS USING THE. COMMISSIONING PROCESS FOR RETRO- COMMISSIONING OF BUILDINGS CLIMA 2005 Lausanne, Switzerland Paper Dorga274s

ACHIEVE MULTI-BENEFITS USING THE. COMMISSIONING PROCESS FOR RETRO- COMMISSIONING OF BUILDINGS CLIMA 2005 Lausanne, Switzerland Paper Dorga274s 1 ACHIEVE MULTI-BENEFITS USING THE COMMISSIONING PROCESS FOR RETRO- COMMISSIONING OF BUILDINGS CLIMA 2005 Lausanne, Switzerland Paper Dorga274s Authors Chad B. Dorgan, PE, PhD, CxAP, CCP Director, Facilities

More information

Building Information Modeling to Facilities Information Management and Beyond

Building Information Modeling to Facilities Information Management and Beyond Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas

More information

NAVY LEED COMMISSIONING NAVFAC Symposium 1 December 2010 David Bylund AIA LEED-AP Architects Hawaii

NAVY LEED COMMISSIONING NAVFAC Symposium 1 December 2010 David Bylund AIA LEED-AP Architects Hawaii NAVY LEED COMMISSIONING 2010 NAVFAC Symposium 1 December 2010 David Bylund AIA LEED-AP Architects Hawaii INTRODUCTION LEED v3 Navy & Sustainability Commissioning Lessons Learned LEED v3 LEED v3 LEED v3

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using

More information

Persistence Tracking in a Retro-commissioning Program

Persistence Tracking in a Retro-commissioning Program Persistence Tracking in a Retro-commissioning Program Mike Eardley Architectural Energy Corporation Synopsis The persistence of energy savings and electrical demand reductions created by retrocommissioning

More information

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group

More information

Commissioning for Energy Savings

Commissioning for Energy Savings Commissioning for Energy Savings Presented To: AEE / ASHRAE / USGBC 2013 Energy Expo St. Paul RiverCentre, St. Paul, Minnesota October 2, 2013 Presented By: Rebecca T. Ellis, PE LEED AP BD+C, CCP, CPMP

More information

BECx Design Phase Specification Review Workshop. Design Phase. Construction Risk Management. Building Enclosure Coordination Process

BECx Design Phase Specification Review Workshop. Design Phase. Construction Risk Management. Building Enclosure Coordination Process BECx Design Phase Specification Review Workshop Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by William R. Nash Design Phase Pre Design

More information

LEED Application Guide for Multiple Buildings and On Campus Building Projects

LEED Application Guide for Multiple Buildings and On Campus Building Projects LEED Application Guide for Multiple Buildings and On Campus Building Projects For Use with 2009 LEED Rating Systems for Design and Construction and Operations and Maintenance Released October 31, 2011

More information

Controls Master Planning Process leads to Campus-Wide BAS Upgrade. 11 February 2015

Controls Master Planning Process leads to Campus-Wide BAS Upgrade. 11 February 2015 Controls Master Planning Process leads to Campus-Wide BAS Upgrade 11 February 2015 Agenda BAS Overview / Benefits Case Study Confidential Energy Company, Illinois Integrated Master Planning Approach Stakeholder

More information

Volume II- Project Development Processes

Volume II- Project Development Processes Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required

More information

Genentech Building 20 Office LEED-CI Gold XL CONSTRUCTION

Genentech Building 20 Office LEED-CI Gold XL CONSTRUCTION Genentech Building 20 Office LEED-CI Gold Above and Beyond A LEED Gold 50,00 s.f. tenant improvement, the space was originally designed with a goal to achieve LEED silver certification. Innovative approaches

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

South Carolina Society for Hospital Engineers

South Carolina Society for Hospital Engineers South Carolina Society for Hospital Engineers Selecting Energy Partners: Criteria & Pitfalls and the Top 10 Ways to Reduce Energy in a Hospital Presented by Jon Dierking, PE, CEM, LEED AP Director of Energy

More information

Ron Wilkinson October 12, 2016

Ron Wilkinson October 12, 2016 British Columbia Chapter ASHRAE Existing Building Commissioning RON WILKINSON P.E., LEED AP, CPMP Wilkinson Cx Management Seattle, WA, USA 1-206-602-4460 rwilk99@gmail.com WCxM Wilkinson Commissioning

More information

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No.

RFQ for Architectural Services - Attachment 5 North Campus Student Housing Phase IV(b) Haggett Hall Replacement and Oak Hall Project No. SPECIAL CONDITIONS Article I, Section A delete this paragraph in its entirety and replace it with the following language: Owner s representative to act on its behalf with respect to this Agreement shall

More information

Non Residential Commissioning:

Non Residential Commissioning: Non Residential Commissioning: Title 24 Part 6 (Energy) vs. Part 11 (Cal Green) Contact Role Email Phone Gina Rodda Presenter gina@gabelenergy.com (510) 428-0803 ext 204 CEC Hotline title24@energy.ca.gov

More information

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) 3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions

More information

How We Retro-Cx 4M sf in Four Months. St. Louis Green Business Challenge

How We Retro-Cx 4M sf in Four Months. St. Louis Green Business Challenge How We Retro-Cx 4M sf in Four Months St. Louis Green Business Challenge Presenters David Meyers, AIA, CxA, PMP, LEED AP Manager of Commissioning Mr. Meyers is a Certified Commissioning Authority and Program

More information

COMMISSIONING REQUIREMENTS NEW YORK CITY COMMERCIAL CODE

COMMISSIONING REQUIREMENTS NEW YORK CITY COMMERCIAL CODE COMMISSIONING REQUIREMENTS NEW YORK CITY COMMERCIAL CODE For New and Substantial Renovation OVERVIEW New York State has established significant energy goals in its Reforming the Energy Vision strategy.

More information

PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition

PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition PROPOSED SAN FRANCISCO GREEN BUILDING CODE AMENDMENTS 2016 Edition Chapter 1 GENERAL SECTION 101 GENERAL 101.1 Title. These regulations shall be known as the California San Francisco Green Building Standards

More information

University of Washington. Request for Qualifications. Commissioning Authority Services for

University of Washington. Request for Qualifications. Commissioning Authority Services for University of Washington Request for Qualifications Commissioning Authority Services for University of Washington Fluke Hall Renovation Project Project Number: 203880 Submittal Date: July 18, 2013 at 3:00

More information

Working with SPiRiT as a LEED Adaptation

Working with SPiRiT as a LEED Adaptation Working with SPiRiT as a LEED Adaptation USGBC Fourth Annual Member Summit Tucson AZ - August 20, 2001 Dagmar Epsten, AIA, CCS LEED Accredited Professional President,, Atlanta, Georgia Working with SPiRiT

More information

The Energy Program Tricycle: Which Wheel Should You Put in Front?

The Energy Program Tricycle: Which Wheel Should You Put in Front? The Energy Program Tricycle: Which Wheel Should You Put in Front? Laurie Gilmer, P.E., CFM, SFP, LEED AP, CxA Conrad Kelso, P.E., CEM Meet our Presenters Laurie Gilmer, P.E., CFM, SFP, LEED AP, CxA Vice

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

THE KEMPER BUILDING 1 EAST WACKER DRIVE PHIL KEUHN SIEBEN ENERGY ASSOCIATES

THE KEMPER BUILDING 1 EAST WACKER DRIVE PHIL KEUHN SIEBEN ENERGY ASSOCIATES THE KEMPER BUILDING 1 EAST WACKER DRIVE BY PHIL KEUHN OF SIEBEN ENERGY ASSOCIATES CHAPTERfREGIONAL TECHNOLOGY A WARD - SHORT FORM 1. Category (Check one and indicate New or Existing, if applicable).,..(!)~8(}~lnerc[~i~~ii9in:~~).,...;;().

More information

The Benefits of Building Commissioning. Jay Cederberg, P.E. Energy Solutions Specialist

The Benefits of Building Commissioning. Jay Cederberg, P.E. Energy Solutions Specialist The Benefits of Building Commissioning Jay Cederberg, P.E. Energy Solutions Specialist All of these jobs would work nicely and probably give satisfaction if the man who knew the most or paid the most attention

More information

WELCOME. Page 1. WELCOME to the Building Environmental Comfort Verification Survey.

WELCOME. Page 1. WELCOME to the Building Environmental Comfort Verification Survey. WELCOME WELCOME to the Building Environmental Comfort Verification Survey. By answering a few brief questions, you can provide valuable information to assist in maintaining or improving temperature and

More information

Trinity Systems Inc.

Trinity Systems Inc. Trinity Systems Inc. Engineers-Architects-Construction Managers-Contractors COMPANY PROFILE Trinity Systems Inc. 9433 Tilmont St. Pico Rivera, CA. 90660 Tel. (323) 642-7039 Email: trinity@trinity-s.com

More information

TABLE OF CONTENTS Acronyms... 2

TABLE OF CONTENTS Acronyms... 2 TABLE OF CONTENTS Acronyms... 2 1.0 Purpose... 4 2.0 Applicability... 4 3.0 References... 4 4.0 Responsibilities... 5 4.1 Department of Defense Education Activity (HQ DoDEA)... 5 4.2 DoDEA Area Offices

More information

ESTATES SERVICES. Soft Landings An Introduction

ESTATES SERVICES. Soft Landings An Introduction ESTATES SERVICES Soft Landings An Introduction 2013 Capital Projects - Context Capital projects have responsibility for all new major build and refurbishment projects A major project is a project with

More information

Commissioning Electrical Systems: An Expansion of LEED

Commissioning Electrical Systems: An Expansion of LEED Commissioning Electrical Systems: An Expansion of LEED IEEE-SF-IAS April 26, 2011 by Rick Miller, PE, LEED AP RNM Engineering, Inc. San Luis Obispo, CA Outline LEED commissioning. What clients are actually

More information

A. The project is intended to achieve LEED Certification at the Silver Level per the U.S. Green Building Council LEED for Schools 2007 rating system.

A. The project is intended to achieve LEED Certification at the Silver Level per the U.S. Green Building Council LEED for Schools 2007 rating system. SECTION 23 01 01 HVAC LEED REQUIREMENTS PART 1 -GENERAL 1.1 WORK INCLUDES A. Compliance with LEED project requirements. B. Coordination of LEED construction phase activities. C. Data gathering of construction

More information

Building Optimization: Recommissioning Your Building to Deliver Peak Performance

Building Optimization: Recommissioning Your Building to Deliver Peak Performance Building Optimization: Recommissioning Your Building to Deliver Peak Performance Recommissioning uses simple solutions to improve building performance, value, and employee productivity. March 2009 / White

More information

Quality management systems

Quality management systems L E C T U R E 9 Quality management systems LECTURE 9 - OVERVIEW Quality management system based on ISO 9000 WHAT IS QMS (QUALITY MANAGEMENT SYSTEM) Goal: Meet customer needs Quality management system includes

More information

PROJECT CHECKLIST Links to Relevant Links to Relevant Responsible Suggested Red Folder

PROJECT CHECKLIST Links to Relevant Links to Relevant Responsible Suggested Red Folder PROJECT CHECKLIST Links to Relevant Links to Relevant Responsible Suggested Red Folder Phase Forms/DataBase FAMIS Tab SOP Person File Category APPLICABLE FAMIS STATUSES: SCHEM_DES and SD_EST_SENT DESIGN

More information

Low Cost Building Automation System for Small- and Medium- Sized Commercial Buildings

Low Cost Building Automation System for Small- and Medium- Sized Commercial Buildings Low Cost Building Automation System for Small- and Medium- Sized Commercial Buildings Srinivas Katipamula, Ph.D. Staff Scientist, Pacific Northwest National Laboratory Other TAG Members: Irfan Rehmanji

More information

Determining the Total Costs and Benefits of Commissioning Public Buildings

Determining the Total Costs and Benefits of Commissioning Public Buildings Determining the Total Costs and Benefits of Commissioning Public Buildings Bing Tso, SBW Consulting, Inc. Lisa Skumatz, SERA, Inc. David Cohan, Northwest Energy Efficiency Alliance ABSTRACT The Northwest

More information

COMMERCIAL HVAC SYSTEMS System Selection

COMMERCIAL HVAC SYSTEMS System Selection COMMERCIAL HVAC SYSTEMS System Selection Technical Development Program Technical Development Programs (TDP) are modules of technical training on HVAC theory, system design, equipment selection and application

More information

Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program

Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program Environmental Stewardship Conference October 05, 2013 Energy Water and Sustainability (EWaS) Program Agenda EWaS Overview History Who is EWaS? Mission EWaS Standards & Tools Energy Efficiency HVAC equipment

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-01 91 00.15 (May 2016) Change 2-08/17 ---------------------------------- Preparing Activity: USACE Supeseding UFGS-23 08 00.00 10 (January 2008) UNIFIED FACILITIES GUIDE

More information