GENERAL REQUIREMENTS AND TECHNICAL SPECIFICATIONS

Size: px
Start display at page:

Download "GENERAL REQUIREMENTS AND TECHNICAL SPECIFICATIONS"

Transcription

1 11701 Community Center Dr Northglenn CO GENERAL REQUIREMENTS AND TECHNICAL SPECIFICATIONS TABLE OF CONTENTS SUBMITTAL PROCEDURES SPECIAL CONDITIONS CURED IN PLACE PIPE (CIPP) PUBLIC SANITARY UTILITY SEWERAGE PIPING PLANS 1

2 2/8/ SANITARY SEWER REHABILITATION SUBMITTAL PROCEDURES SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals. 1.3 DEFINITIONS A. Action Submittals: Written and graphic information that requires Engineer s responsive action. B. Informational Submittals: Written information that does not require Engineer s responsive action. Submittals may be rejected for not complying with requirements. 1.4 SUBMITTAL PROCEDURES A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. B. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineer receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals. 1. Initial Review: Allow 10 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination. 2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal. 3. Resubmittal Review: Allow 10 days for review of each resubmittal. C. Deviations: Highlight or otherwise specifically identify deviations from the Contract Documents on submittals. D. Additional Copies: Unless additional copies are required for final submittal, and unless Engineer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal. E. Submit a minimum of four paper copies of each submittal unless otherwise indicated. Two copies will be returned to the contractor. Section Page 1 of 6

3 2/8/ SANITARY SEWER REHABILITATION SUBMITTAL PROCEDURES 1. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Engineer. 2. Submit five copies of operation and maintenance manuals. F. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Engineer will return submittals, without review, received from sources other than Contractor. 1. Transmittal Form: Complete the sample form at end of Section and include with submittals. City will provide electronic version upon request. Include the following information: a. Project name. b. Date. c. Name of Contractor. d. Name of subcontractor. e. Name of supplier. f. Name of manufacturer. g. Submittal number. h. Number and title of appropriate Specification Section. i. Drawing number and detail references. j. Location(s) where product is to be installed. k. Other necessary identification. 2. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Engineer on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same label information as related submittal. G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal. 1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block and clearly indicate extent of revision. 3. Resubmit submittals until they are marked "A - NO EXCEPTIONS TAKEN or B - FURNISH AS CORRECTED. H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms. 1. Use for Construction: Use only final submittals with mark indicating "A - NO EXCEPTIONS TAKEN or B - FURNISH AS CORRECTED taken by Owner s Representative. I. Required Submittals: 1. Project Schedule 2. Subcontractor list if applicable 3. Sediment control plan 4. Traffic control plan 5. Product Data in accordance with 2.1B for the following: a. Pipe material b. Gaskets c. Fittings d. CIPP liner material Section Page 2 of 6

4 2/8/ SANITARY SEWER REHABILITATION SUBMITTAL PROCEDURES PART 2 - PRODUCTS 2.1 ACTION SUBMITTALS A. General: Prepare and submit Action Submittals required by individual Specification Sections. 1. Submit electronic submittals directly to extranet specifically established for Project. B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. 1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data. 2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable: a. Manufacturer's written recommendations. b. Manufacturer's product specifications. c. Manufacturer's installation instructions. d. Manufacturer's catalog cuts. e. Compliance with specified referenced standards. f. Testing by recognized testing agency. g. Application of testing agency labels and seals. h. Notation of coordination requirements. C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal of Engineer s CAD Drawings are otherwise permitted. D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed. E. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form: 1. Name, address, and telephone number of entity performing subcontract or supplying products. 2.2 INFORMATIONAL SUBMITTALS A. General: Prepare and submit Informational Submittals required by other Specification Sections. B. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of Owner s Representatives and owners, and other information specified. C. Welding Certificates: Prepare and provide documentation that welding procedures and personnel comply with AWS requirements. Include names of firms and personnel certified. D. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents. Section Page 3 of 6

5 2/8/ SANITARY SEWER REHABILITATION SUBMITTAL PROCEDURES E. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents. F. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers. G. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer. Include the following, as applicable: H. Material Safety Data Sheets (MSDSs): Submit information directly to Owner; do not submit to Owner s Representative. 1. Owner s Representative will not review submittals that include MSDSs and will return the entire submittal for resubmittal. 2.3 DELEGATED DESIGN A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated. 1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Engineer. B. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit three copies of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional. 1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services. PART 3 - EXECUTION 3.1 CONTRACTOR'S REVIEW A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer. B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents. 3.2 OWNER S REPRESENTATIVE'S AND CONSTRUCTION MANAGER'S ACTION Section Page 4 of 6

6 2/8/ SANITARY SEWER REHABILITATION SUBMITTAL PROCEDURES A. General: Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action. B. Action Submittals: Engineer will review each submittal, make marks to indicate corrections or modifications required, and return it. Engineer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows: 1. A - NO EXCEPTIONS TAKEN 2. B - FURNISH AS CORRECTED 3. C - REJECTED SEE REMARKS 4. D - REVISE AND RESUBMIT C. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party. D. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review. E. Submittals not required by the Contract Documents may not be reviewed and may be discarded. Section Page 5 of 6

7 2/8/ SANITARY SEWER REHABILITATION SUBMITTAL PROCEDURES SUBMITTAL TRANSMITTAL Project Name: Project Owner: Date Received: Checked By: Contractor: Project No. Address Address: Community Center Drive P.O. Box Northglenn, CO Spec Section: Drawing/Detail No. Attn: Attn: Item No. No. Copies Description Manufacturer Action Taken * Remarks: * The Action Designated Above is in Accordance with the Following Legend: A No Exceptions Taken B Furnish as Corrected D Revise and Submit E Engineer s review not required. C Rejected Comments: Distribution: Contractor File Field Owner Other By Date END OF SECTION Section Page 6 of 6

8 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS SECTION SPECIAL CONDITIONS PART 1 - GENERAL 1.1 PROJECT DESCRIPTION A. The Contractor shall furnish all material, labor, equipment and services necessary for, and incidental to, the construction of the 2012 Sanitary Sewer Rehabilitation project as specified herein and per attached drawings. 1.2 LOCATION OF WORK A. The work is located in Northglenn, Colorado, at various locations (see drawings for exact location). Prospective bidders should make themselves familiar with the location of the work and all potential access points so as to facilitate progress of the work in a well-organized fashion. 1.3 TIME OF WORK A. The Contractor shall complete all work required by these specifications within thirty (30) working days. The starting time for the Contract shall be ten (10) calendar days following the date of the Notice to Proceed. Working hours shall be 7:00 A.M. to 3:30 P.M. Monday through Friday. A working day shall be defined as any day, exclusive of Saturdays, Sundays and holidays, on which weather and other conditions not under the control of the Contractor will permit construction to proceed for a minimum of one half (1/2) of the day with a normal working force. The Contractor shall be responsible for submitting a schedule for all work to be performed. This schedule shall be updated weekly and resubmitted to the Engineer for acceptance. 1.4 PROTECTION OF EXISTING UTILITIES A. The Contractor shall be responsible for the protection of existing utilities such as water mains, sanitary and storm sewer systems, gas mains, electrical conduits, telephone lines, irrigation systems and any other utilities within the area; and if any damage or destruction occurs to these utilities, the Contractor shall be responsible for their repair and/or replacement at the Contractors expense. 1.5 QUALITY ASSURANCE A. Referenced Standards: 1., Public Right-of-Way Standards and Specifications (Latest Edition). The Public Right-of-Way Standards and Specifications are available on the website. B. In the event of a conflict occurring between or within the aforementioned Standards and Specifications and the project specifications, the more stringent standard will apply. The Contractor shall coordinate inspection of the work with Engineer. Any discrepancies found between the Drawings and Specifications and site conditions or any errors or omissions in the Drawings or Specifications shall be immediately reported in writing to the Engineer, who shall promptly correct such errors, or omissions in writing. Any Section Page 1 of 7

9 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS work done by the Contractor after his discovery of such discrepancies, errors or omissions WITHOUT written instructions by the Engineer shall be done at the Contractor's risk. C. s Standard Operating Procedures. 1.6 LIQUIDATED DAMAGES A. Liquidated damages shall be set at $ per day. This charge for liquidated damages will be in addition to other penalties set forth in the Contract. 1.7 SPECIAL CONSIDERATIONS A. Contractor shall be responsible for negotiations of any waivers or alternate arrangements required to enable transportation of materials to the site. B. Contractor shall be responsible for adhering to the s Standard Operating Procedures. 1.8 SPECIAL CONTRACT PROVISION A. The items listed in the Bid Summary are estimated for comparison purposes only. 1.9 CONTRACT DOCUMENTS FOR CONTRACTORS USE A. Refer to Trade Contractor Agreement. B. Contractor shall pick up two "no-charge" documents within 10 days from date of Notice to Proceed ORDER OF CONSTRUCTION AND CONSTRUCTION SCHEDULE A. Construction operations will be scheduled to allow the Owner uninterrupted operation of existing adjacent facilities. Coordinate connections with existing work to ensure timely completion of interfaced items. B. At no time shall Contractor or his employees modify operation of the existing facilities or start construction modifications without approval of the Owner except in emergency to prevent or minimize damage. C. Within 10 days after award of Contract, submit for approval a critical path type schedule. Account for schedule of Subcontracts. Include proper sequence of construction, various crafts, purchasing time, shop drawing approval, material delivery, equipment fabrication, startup, demonstration, and similar time consuming factors. Show on schedule as a minimum, earliest starting, earliest completion, latest starting, latest finish, and free and total float for each task or item. Evaluate schedule no less than monthly. Update, correct, and rerun schedule and submit to Engineer in triplicate with pay application and show rescheduling necessary to reflect true job conditions. When shortening of various time intervals is necessary to correct for behind schedule conditions, indicate steps to implement to accomplish work in shortest schedule. Information shall be submitted to Engineer in writing with revised schedule. Section Page 2 of 7

10 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS D. If Contractor does not take necessary action to accomplish work according to schedule, he may be ordered by Owner in writing to take necessary and timely action to improve work progress. Order may require increased work forces, extra equipment, extra shifts or other action as necessary. Should Contractor refuse or neglect to take such action authorized, under provisions of this contract, Owner may take necessary actions including, but not necessarily limited to, withholding of payment and termination of contract PERMITS A. Contractor is responsible for securing all required permits for the completion of the work with all agencies with jurisdictional authority. The will waive Right-of-way fees SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION A. These construction documents are to be governed, at all times, by applicable provisions of the Federal Law(s), including but not limited to the latest amendment of the following: 1. Williams-Steiger Occupational Safety and Health Act of 1970, Public Law Part 1910-Occupational Safety and Health Standards, Chapter XVII of Title 29, Code of Federal Regulations. 3. Part 1926-Safety and Health Regulations for Construction, Chapter XVII of Title 29, Code of Federal Regulations. 4. Part II Department of Labor Occupational Safety and Health Administration 29CFR Part 1926 Occupational Safety and Health Standards - Excavations; Final Rule PRECONSTRUCTION CONFERENCE A. A pre-construction conference shall be held at the Owner's office after award of Contract. Engineer will notify the Contractor as to the date and time of the conference 2 weeks in advance of the proposed date. Contractor's Project Manager and Project Superintendent and Contractor's Subcontractor Representatives shall attend. The Contractor should be prepared to discuss a detailed plan for construction of the project at the meeting PROGRESS MEETING A. The Engineer will conduct construction meetings involving: 1. Contractor s project manager 2. Contractor s project superintendent 3. Engineer s designated representative(s). 4. Contractor s subcontractors as appropriate to the work in progress. B. The Engineer s designated representative(s) will take meeting minutes and submit copies of the meeting minutes to participants and designated recipients identified at the Preconstruction Conference. Corrections, additions or deletions to the minutes shall be noted and addressed at the following meeting. C. The Engineer s designated representative(s) will have available at each meeting full chronological file of all previous meeting minutes. D. The Contractor shall have available at each meeting up-to-date record drawings. Section Page 3 of 7

11 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS E. The Contractor shall provide a two-week schedule projection at each weekly meeting CHANGE MODIFICATION PROCEDURES A. Request for Information (RFI s) 1. Contractor shall request clarification of contract documents by issuing a Request for Information to the RPR. Contractor shall afford at least 48 hours for Engineer's response. Engineer will provide electronic copy upon request. B. Field Orders: 1. A written order effecting a change in the work not involving an adjustment in the contract price or an extension of the contract time, issued by the Engineer or the Owner to the Trade Contractor during Construction. C. Change Order: 1. A written order to the Trade Contractor authorizing an addition, deletion, or revision in the work within the general scope of the contract documents, or authorizing an adjustment in the contract price and/or contract time. Owner will provide electronic copy upon request MEASUREMENT AND PAYMENT A. General: 1. The total bid price shall cover all work required by the Contract Documents. All costs in connection with the proper and successful completion of the work, including furnishing all materials, equipment, supplies, and appurtenances; providing all construction, installation equipment, and tools; and performing all necessary labor and supervision to fully complete the work and any mark-up, shall be included in the unit and/or lump sum prices bid. B. Estimated Quantities: 1. The estimated quantities identified in the Bid Summary are approximate and are to be used only (a) as a basis for estimating the probable cost of the work. The actual amounts of work done and materials furnished under unit price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work completed and materials furnished per the unit or lump sum prices shown on the bid summary. 2. No direct payment shall be made for site clearing and cleaning, excavation, or compaction accordance with industry standards and governing regulations. C. Measurement and Payment Items: 1. Base bid item 1 - Mobilization and Demobilization: The measurement and payment for mobilization and demobilization shall be on a lump sum basis. Contractor s cost shall include all cost of whatsoever nature. The unit price shall include at a minimum: Mobilization/demobilization of material labor and equipment. Bonds, insurance, licenses, and permits. Temporary construction and erosion control. The contractor shall perform street sweeping as needed as determined by the Engineer. Section Page 4 of 7

12 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS Direct site overhead including staging area, field office facilities for the contractor, moving and removing construction equipment to/from the project site and removal of any items placed on site by the Contractor. All other costs incurred or labor and operations which must be preformed prior to and after completion of the other items under this Contract in accordance with the Plans and Specifications. The lump sum price for Mobilization and Demobilization shall not exceed 5% of the total contract value. Contract Percent Complete Percent Available for Payment 5% 25% 10% 50% 25% 60% 50% 100% 2. Base bid item 2 Traffic Control: The measurement and payment for Traffic Control shall be on a lump sum basis. Contractor s cost shall include all materials, equipment and labor necessary to furnish the Traffic Control complete in place. The unit price shall include at a minimum: Cost of producing a traffic control plan (MHT) All material, equipment, and labor required in association with the approved traffic control plan. 3. Base bid item 3 Materials Testing: The measurement and payment for Materials Testing for any point repair that must be excavated shall be on a unit price basis. Contractor s cost shall include all materials, equipment and labor necessary to furnish the Materials Testing complete in place. The unit price shall include at a minimum: Materials testing including proctors and nuclear density compaction Compaction test shall be conducted at TWO (2) foot vertical intervals Materials testing of compacted soil is only required if trenchless point repairs are not able to be constructed on those lines as noted. All other related materials, work, and equipment required for the excavation of unclassified material in accordance with the Plans and Specifications. 4. Base bid items Sanitary Sewer Trenchless Point Repair: The measurement and payment for completing the point repairs shall be on a unit price basis. Contractor s cost shall include all materials, equipment and labor necessary to furnish the various sanitary sewer point repairs complete in place. The unit price shall include at a minimum: Protection of existing utilities; Grout all leaks, remove all debris and deposits and install and cure liner All other related materials, work, and equipment required to complete the various Sanitary Sewer Trenchless Point Repairs in accordance with the Plans and Specifications. 5. Base bid items Sanitary Sewer Structural Rehabilitation 8-inch mains: The measurement and payment for rehabilitating the sanitary sewer between manholes shown on the drawings shall be on a unit price basis. Contractor s cost shall include all material, equipment and labor necessary to furnish all 8-inch Sanitary Sewer Structural Rehabilitation complete-in-place. Section Page 5 of 7

13 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS The unit price shall include at a minimum: Remove all debris and deposits inside the pipe; Plug all leaks with chemical grout; Install and cure structural liner; TV Inspection prior to construction and after construction Materials and air tests in accordance with Section Cured in Place Pipe (CIPP) Cut in taps; and All other related materials, work, and equipment required to complete the 8-inch Sanitary Sewer Structural Rehabilitation in accordance with the Plans and Specifications. Alt - 1. Dewatering: The measurement and payment for dewatering the excavation for the removal and replacement of the existing sanitary sewer on a unit price basis. Contractor s costs shall include all materials, equipment and labor necessary to dewater the excavation. The unit price shall include at a minimum: Dewatering; and All other related materials, work, and equipment required to dewater the excavation in accordance with the Plans and Specifications. Alt - 2. By-pass pumping: The measurement and payment for by-pass pumping for the removal and replacement of the existing sanitary sewer on a unit price basis. Contractor s costs shall include all materials, equipment and labor necessary to by-pass pump. The unit price shall include at a minimum: By-pass pumping; and All other related materials, work, and equipment required to dewater the excavation in accordance with the Plans and Specifications. Alt - 3. Unclassified material excavation: The measurement and payment for the excavation of unclassified material per CDOT Standards and Specifications excavation required for the removal and replacement of the existing sanitary sewer on a unit price basis. Contractor s costs shall include all materials, equipment and labor necessary to excavate unclassified material. The unit price shall include at a minimum: Unclassified material excavation; and All other related materials, work, and equipment required for the excavation of unclassified material in accordance with the Plans and Specifications. Alt - 4. Structural Backfill (Flow-fill): The measurement and payment, in the event installation of structural backfill (Flow-fill) material is required, shall be on a unit price basis. Contractor s costs shall include all materials, equipment and labor necessary to install structural backfill (Flow-fill) material complete-in-place. The unit price shall include at a minimum: Backfill with structural (flow fill); and All other related materials, work, and equipment required, in the event installation of structural backfill (Flow-fill) is required, in accordance with the Plans and Specifications. Alt - 5. CDOT Class 1 Structural Backfill: The measurement and payment, in the event installation of CDOT Class 1 structural backfill material is required, shall be on a unit price basis. Contractor s costs shall include all materials, equipment and labor necessary to install CDOT Class 1 structural backfill material complete-in-place. Section Page 6 of 7

14 2/8/ SANITARY SEWER REHABILITATION SPECIAL CONDITIONS The unit price shall include at a minimum: Backfill of excavation and compaction of fill material; and All other related materials, work, and equipment required, in the event installation of CDOT Class 1 structural backfill is required, in accordance with the Plans and Specifications. Alt - 6. CDOT Class 2 Structural Backfill: The measurement and payment, in the event installation of CDOT Class 2 structural backfill material is required, shall be on a unit price basis. Contractor s costs shall include all materials, equipment and labor necessary to install CDOT Class 2 structural backfill material complete-in-place. The unit price shall include at a minimum: Backfill of excavation and compaction of fill material; and All other related materials, work, and equipment required, in the event installation of CDOT Class 2 structural backfill is required, in accordance with the Plans and Specifications. PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION 3.1 CONSTRUCTION REQUIREMENTS A. Contractor shall take reasonable precaution to prevent damage to existing facilities. All facilities damaged or removed during construction shall be restored or replaced to like new condition. END OF SECTION Section Page 7 of 7

15 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) SECTION CURED IN PLACE PIPE (CIPP) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 REFERENCES A. The following documents form a part of this specification to the extent stated herein and shall be the latest editions thereof. Where differences exist between codes and standards, the requirements of these specifications shall apply. B. ASTM - F1216 Standard Practice for Rehabilitation of Existing Pipelines and Conduits by the Inversion and Curing of a Resin-Impregnated Tube C. ASTM - F1743 Standard Practice for Rehabilitation of Existing Pipelines and Conduits by the Pull in and inflate and Curing of a Resin-Impregnated Tube D. ASTM - D543 Standard and Practice for Evaluating the Resistance of Plastics to Chemical Reagents E. ASTM - D638 Standard Test Method for Tensile Properties of Plastics F. ASTM - D790 Standard Test Methods for Flexural Properties of Un-reinforced and G. ASTM - D792 Standard Test Methods for Density and Specific Gravity of Plastics bydisplacement. H. ASTM - F Standard Practice for Rehabilitation of Existing Pipelines and Conduits by the Pulled in Place Installation of Glass Reinforced Plastic (GRP) Cured-in-Place Thermosetting Resin Pipe (CIPP) I. ASTM - D (2004) Standard Test Method for Determining Dimensions of Thermoplastic Pipe and Fittings J. ASTM - D2990 Standard Test Methods for Tensile, Compressive, and Flexural Creep and Creep- Rupture of Plastics K. ASTM - D (2002) Standard Practice for Determining Dimensions of Fiberglass (Glass- Fiber-Reinforced Thermosetting Resin) Pipe and Fittings L. ASTM - D3681 Standard Test Method for Chemical Resistance of Fiberglass (Glass Fiber Reinforced Thermosetting Resin) Pipe in a Deflected Condition M. ASTM - D5813 Standard Specification for Cured-in Place Thermosetting Resin Sewer Pipe 1.3 SUMMARY Section Page 1 of 10

16 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) A. These Specifications include the minimum requirements for the rehabilitation of sanitary sewer pipelines by the installation of Cured-In-Place Pipe (CIPP) within the existing, deteriorated pipe as shown on the plans included as part of these contract documents. B. The rehabilitation of pipelines shall be done by the installation of a resin-impregnated flexible tube which, when cured, shall be continuous and tight-fitting throughout the entire length of the original pipe. The CIPP shall extend the full length of the original pipe and provide a structurally sound, jointless and water-tight new pipe within a pipe. C. The Contractor is responsible for proper, accurate and complete installation of the CIPP using the system selected by the Contractor. D. Neither the CIPP system, nor its installation, shall cause adverse effects to any of the City s processes or facilities. The Contractor is responsible for legally disposing of all chemicals and materials used in the CIPP process and any resulting by-products. Disposal will not be permitted in the sewer system. The Contractor shall cleanup, restore existing surface conditions and structures, and repair any of the CIPP system determined to be defective. The Contractor shall conduct installation operations and schedule cleanup in a manner to cause the least possible obstruction and inconvenience to traffic, pedestrians, businesses, and property owners or tenants. 1.4 ACTION SUBMITTALS A. Fabric Tube including the manufacturer and description of product components. B. Flexible membrane (coating) material including recommended repair (patching) procedure if applicable. C. Raw Resin Data - including the manufacturer and description of product components. 1.5 INFORMATIONAL SUBMITTALS A. Manufacturers shipping, storage and handling recommendations for all components of the CIPP System. B. All MSDS sheets for all materials to be furnished for the project. C. Tube wet-out & cure method including: A complete description of the proposed wet-out procedure for the proposed technology, and the Manufacturer s recommended cure method - for each diameter and thickness of CIPP liner to be installed. The PWS shall contain a detailed curing procedure detailing the curing medium and the method of application. PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS A. These Specifications cover all work necessary to furnish and install, the (CIPP). The Contractor shall provide all materials, labor, equipment, and services necessary for traffic control, bypass pumping and/or diversion of sewage flows, cleaning and television inspection of sewers to be lined, liner installation, reconnection of service connections, all quality controls, provide samples Section Page 2 of 10

17 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) for performance of required material tests, final television inspection, testing of lined pipe system and warranty work, all as specified herein. B. The product furnished shall be a complete CIPP system including all materials, applicable equipment and installation procedures. The CIPP system manufacturer may submit, a minimum of 14 calendar days in advance of the bid date, required information to the Owner to obtain preapproval status. Those CIPP systems that have been pre-approved will not be required to furnish information as required in the submittal section of these specifications unless specifically requested to do so by the Owner or if any of the CIPP system components have changed from those preapproved by the Owner. All other CIPP systems or multi-component products will be required to meet the submittal requirements as contained herein. C. The CIPP shall be continuous and jointless from manhole to manhole or access point to access point and shall be free of all defects that will affect the long term life and operation of the pipe. D. The CIPP shall fit sufficiently tight within the existing pipe so as to not leak at the manholes, at the service connections or through the wall of the installed pipe. If leakage occurs at the manholes or the service connections the Contractor shall seal these areas to stop all leakage using a material compatible with the CIPP as directed by the Owner at the price bid therefore in the Proposal. If leakage occurs through the wall of the pipe the liner shall be repaired or removed as recommended by the CIPP manufacturer. Final approval of the liner installation will be based on a leak tight pipe. E. The CIPP shall be designed for a life of 50 years or greater. F. The CIPP may be designed as a liner to rehabilitate the existing pipe or as a fully structural stand alone pipe-within-a-pipe. Where specified in the contract documents the installed CIPP shall be a structurally designed pipe within a pipe, meet or exceed all contract specified physical properties, fitting tightly within the existing pipe all within the tolerances specified. The installed CIPP shall withstand all applicable surcharge loads (soil overburden, live loads, etc.) and external hydrostatic (groundwater) pressure, if present, for each specific installation location. G. The installed CIPP shall have a long term (50 year) corrosion resistance to the typical chemicals found in domestic sewage. H. All existing and confirmed active service connections and any other service laterals to be reinstated as directed by the Owner shall be re-opened robotically or by hand in the case of manentry size piping, to their original shape and to 95% of their original capacity. All over-cut service connections will be properly repaired to meet the requirements of these specifications. I. All materials furnished, as part of this contract shall be marked with detailed product information, stored in a manner specified by the manufacturer and tested to the requirement of this contract. J. Testing and warranty inspections shall be executed by the Owner. Any defects found shall be repaired or replaced by the Contractor. K. The Contractor shall furnish all samples for product testing at the request of the Owner. The Owner shall take possession of the samples for testing and shall maintain the chain of custody, deliver the samples to an approved laboratory and pay for all material and product testing performed under this contract. L. MATERIALS 1. The CIPP System must meet the chemical resistance requirements of theses contract documents. Section Page 3 of 10

18 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) 2. All materials, shipped to the project site, shall be accompanied by test reports certifying that the material conforms to the ASTM standards listed herein. Materials shall be shipped, stored, and handled in a manner consistent with written recommendations of the CIPP system manufacturer to avoid damage. Damage includes, but is not limited to, gouging, abrasion, flattening, cutting, puncturing, or ultra-violet (UV) degradation. On site storage locations, shall be approved by the Owner. All damaged materials shall be promptly removed from the project site at the Contractor s expense and disposed of in accordance with all current applicable agency regulations M. FABRIC TUBE 1. The fabric tube shall consist of one or more layers of absorbent non-woven felt fabric, felt/fiberglass or fiberglass and meet the requirements of ASTM F 1216, ASTM F 1743, ASTM D 5813 & ASTM F2019. The fabric tube shall be capable of absorbing and carrying resins, constructed to withstand installation pressures and curing temperatures and have sufficient strength to bridge missing pipe segments, and stretch to fit irregular pipe sections. The contractor shall submit certified information from the felt manufacturer on the nominal void volume in the felt fabric that will be filled with resin. 2. The wet-out fabric tube shall have a uniform thickness and excess resin distribution that when compressed at installation pressures will meet or exceed the design thickness after cure. 3. The fabric tube shall be manufactured to a size and length that when installed will tightly fit the internal circumference, meeting applicable ASTM standards or better, of the original pipe. Allowance shall be made for circumferential stretching during installation. The tube shall be properly sized to the diameter of the existing pipe and the length to be rehabilitated and be able to stretch to fit irregular pipe sections and negotiate bends. The Contractor shall determine the minimum tube length necessary to effectively span the designated run between manholes. The Contractor shall verify the lengths in the field prior to ordering and prior to impregnation of the tube with resin, to ensure that the tube will have sufficient length to extend the entire length of the run. The Contractor shall also measure the inside diameter of the existing pipelines in the field prior to ordering liner so that the liner can be installed in a tight-fitted condition. 4. The outside and/or inside layer of the fabric tube (before inversion/pull-in, as applicable) shall be coated with an impermeable, flexible membrane that will contain the resin and facilitate, if applicable, vacuum impregnation and monitoring of the resin saturation during the resin impregnation (wetout) procedure. No material shall be included in the fabric tube that may cause de-lamination in the cured CIPP. No dry or unsaturated layers shall be acceptable upon visual inspection as evident by color contrast between the felt fabric and the activated resin containing a colorant. 5. The wall color of the interior pipe surface of CIPP after installation shall be a light reflective color so that a clear detailed examination with closed circuit television inspection equipment may be made. The hue of the color shall be dark enough to distinguish a contrast between the fully resin saturated felt fabric and dry or resin lean areas. 6. Seams in the fabric tube, if applicable, shall meet the requirements of ASTM D The outside of the fabric tube shall be marked every 5 feet with the name of the manufacturer or CIPP system, manufacturing lot and production footage. 8. The minimum length of the fabric tube shall be that deemed necessary by the installer to effectively span the distance from the starting manhole to the terminating manhole or access point, plus that amount required to run-in and run-out for the installation process. 9. The nominal fabric tube wall thickness shall be constructed, as a minimum, to the nearest 0.5 mm increment, rounded up from the design thickness for that section of installed CIPP. Wall thickness transitions, in 0.5 mm increments or greater as appropriate, may be fabricated into the fabric tube between installation entrance and exit access points. 10. The quantity of resin used in the impregnation shall be sufficient to fill all of the felt voids for the nominal felt thickness. Section Page 4 of 10

19 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) N. RESIN 1. The resin shall be a corrosion resistant polyester or vinyl ester resin and catalyst system that when properly cured within the tube composite meets the requirements of ASTM F1216, ASTM F1743 or F2019, the physical properties herein, and those, which are to be utilized in the design of the CIPP for this project. The resin shall produce CIPP which will comply with or exceed the structural and chemical resistance requirements of this specification. O. STRUCTURAL REQUIREMENTS 1. The physical properties and characteristics of the finished liner will vary considerably, depending on the types and mixing proportions of the materials used, and the degree of cure executed. It shall be the responsibility of the Contractor to control these variables and to provide a CIPP system which meets or exceeds the minimum properties specified herein: 2. The CIPP shall be designed as per ASTM standards. The CIPP design shall assume no bonding to the original pipe wall. 3. The design engineer shall set the long term (50 year extrapolated) Creep Retention Factor at 33% of the initial design flexural modulus as determined by ASTM D-790 test method. This value shall be used unless the Contractor submits long term test data (ASTM D2990) to substantiate a higher retention factor. 4. The cured pipe material (CIPP) shall, at a minimum, meet or exceed the structural properties, as listed below. P. MINIMUM PHYSICAL PROPERTIES Property Test Method Cured Composite Per ASTM F1216 Cured Composite Per Design Flexural Modulus of Elasticity ASTM D ,000 psi Contractor Value (Short Term) Flexural Strength (Short Term) ASTM D-790 4,500 psi Contractor Value 1. The required structural CIPP wall thickness shall be based, as a minimum, on the physical properties of the cured composite and per the design of the Professional Engineer and in accordance with the Design Equations contained in the appendix of the ASTM standards, and the following design parameters: Design Safety Factor 2.0 (1.5 for pipes 36 or larger) Creep Retention Factor 33% Ovality 2% or as measured by field inspection Constrained Soil Modulus Per AASHTO LRFD Section 12 and AWWA Manual M45 Groundwater Depth As specified or indicated on the Plans Soil Depth (above the crown) As specified or indicated on the Plans Live Load Highway, railroad or airport as applicable Soil Load (assumed) 120 lb/cu. Ft. Minimum service life 50 years 2. The Contractor shall submit, prior to installation of the lining materials, certification of compliance with these specifications and/or the requirements of the pre-approved CIPP system. Certified material test results shall be included that confirm that all materials conform to these specification and/or the pre-approved system. Materials not complying with these requirements will be rejected. 3. The design soil modulus may be adjusted based on data determined from detailed project soil testing results as provided by the Owner in the contract documents. Section Page 5 of 10

20 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) PART 3 - EXECUTION 3.1 PREPARATION A. Preparation, cleaning, inspection, sewage by-passing and public notification. The Contractor shall clean the interior of the existing host pipe prior to installation of the CIPP liner. All debris and obstructions, that will effect the installation and the final CIPP product delivery to the Owner, shall be removed and disposed of. B. Cleaning of Pipe Lines - The Contractor shall remove all internal debris from the pipe line that will interfere with the installation and the final product delivery of the CIPP as required in these specifications. Solid debris and deposits shall be removed from the system and disposed of properly by the Contractor. Moving material from manhole section to manhole section shall not be allowed. As applicable the contractor shall either plug or install a flow bypass pumping system to properly clean the pipe lines. Precaution shall be taken, by the Contractor in the use of cleaning equipment to avoid damage to the existing pipe. The repair of any damage, caused by the cleaning equipment, shall be the responsibility of the Contractor. The Owner will designate a site for the disposal of all debris removed, from the Owner s sewer system, as a direct result of the cleaning operation. Unless otherwise specified by the Owner, the Contractor shall dispose of all debris at no charge. C. Contractor shall apply chemical grout and pressure test joints where I/I is apparent in the video. 3.2 INSTALLATION A. The CIPP liner shall be constructed of materials and methods, that when installed, shall provide a jointless and continuous structurally sound liner able to withstand all imposed static, and dynamic loads on a long-term basis. B. The Contractor may, under the direction of the Owner, utilize any of the existing manholes in the project area as installation access points. If a street must be closed to traffic because of the location of the sewer, the Contractor shall furnish a detailed traffic control plan and all labor and equipment necessary. The plan shall be in conformance with the requirements of the local agency having jurisdiction over traffic control. C. By-passing Existing Sewage Flows - The Contractor shall provide for the flow of existing mainline and service connection effluent around the section or sections of pipe designated for CIPP installation. Service connection effluent may be plugged only after proper notification to the affected residence and may not remain plugged overnight. Installation of the liner shall not begin until the Contractor has installed a sewage by-pass system and all pumping facilities have been installed and tested under full operating conditions including the bypass of mainline and side sewer flows. Once the lining process has begun, existing sewage flows shall be maintained, until the resin/felt tube composite is fully cured, cooled down, full televised and the CIPP ends finished. The Contractor shall coordinate sewer bypass and flow interruptions with the Owner at least 14 days in advance and with the property owners and businesses at least 3 business days in advance. The pump and bypass lines shall be of adequate capacity and size to handle peak flows. The Contractor shall submit a detail of the bypass plan and design to the Owner before proceeding with any CIPP installation. Compensation for by-pass pumping and all associated plans and approvals shall be at the price bid therefore in the Proposal. D. Contractor shall perform post-cleaning video inspections of the pipelines. Only PACP certified personnel trained in locating breaks, obstacles and service connections by closed circuit television shall perform the inspection. The Contractor shall provide the Owner a copy of the pre-cleaning Section Page 6 of 10

21 2/8/ SANITARY SEWER REHABILITATION CURED IN PLACE PIPE (CIPP) and post-cleaning video and suitable log, and/or in digital format for review prior to installation of the CIPP and for later reference by the Owner. E. Line Obstructions - It shall be the responsibility of the Contractor to clear the line of obstructions that will interfere with the installation and long-term performance of the CIPP. If pre-installation inspection reveals an obstruction, misalignment, broken or collapsed section or sag that was not identified as part of the original scope of work and will prohibit proper installation of the CIPP, the Contractor may be directed by the Owner to correct the problem(s) prior to lining by utilizing open cut repair methods. The Contractor shall be compensated for this work under a contingency pay item designated for open cut point repairs. Removal of any previously unknown obstructions shall be considered as a changed condition. The cost of removal of obstructions that appeared on pre-bid video documentation and made available to the Contractor, prior to the bid opening, shall be compensated for on a unit price basis in accordance with the contract documents. F. The Contractor shall be responsible for confirming the locations of all branch service connections prior to installing and curing the CIPP. G. The Contractor shall be allowed use water from an owner-approved fire hydrant in the project vicinity. Use of an approved double check backflow assembly shall be required. Contractor shall provide his own approved assembly. Contractor shall pay current market price for all water usage. H. The CIPP Liner shall be installed and cured in the host pipe per the manufacturer s specifications. I. CIPP installation shall be in accordance with the applicable ASTM standards with the following modification: J. The wet-out tube shall be positioned in the pipeline using the method specified by the manufacturer. Care should be exercised not to damage the tube as a result of installation. The tube should be pulled-in or inverted through an existing manhole or approved access point and fully extend to the next designated manhole or termination point. K. Prior to installation and as recommended by the manufacturer remote temperature gauges or sensors shall be placed inside the host pipe to monitor the temperatures during the cure cycle. Liner and/or host pipe interface temperature shall be monitored and logged during curing of the liner. L. Curing shall be accomplished by utilizing the appropriate medium in accordance with the manufacturer s recommended cure schedule. The curing source or in and output temperatures shall be monitored and logged during the cure cycles. The manufacturer s recommended cure schedule shall be used for each line segment installed, and the liner wall thickness and the existing ground conditions with regard to temperature, moisture level, and thermal conductivity of soil, per ASTM as applicable, shall be taken into account by the Contractor. M. The Contractor shall cool the CIPP in accordance with the approved CIPP manufacturer s recommendations as described and outlined in the PWS. N. Temperatures and curing data shall be monitored and recorded, by the Contractor, throughout the installation process to ensure that each phase of the process is achieved as approved in accordance with the CIPP System manufacturer s recommendations. 3.4 FINISH O. The installed CIPP shall be continuous over the entire length of a sewer line section and be free from visual defects such as foreign inclusions, dry spots, pinholes, major wrinkles and delamination. The lining shall be impervious and free of any leakage from the pipe to the surrounding ground or from the ground to inside the lined pipe. Section Page 7 of 10

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction 1.00 DESCRIPTION 1.01 WORK INCLUDED: This work shall include the furnishing of all labor, equipment and materials necessary

More information

Installation Practice InnerSeal

Installation Practice InnerSeal Installation Practice InnerSeal Rehabilitation of a Full-Length Sewer Service Lateral using One-Piece Main and Lateral Cured-In-Place Liner Assembly Installed By Means Of Air Inversion 1. Intent This instruction

More information

FOLDED (THERMOPLASTIC) PIPE (FP) INSTALLATION (HDPE, PVC, AND PVC TYPE A)

FOLDED (THERMOPLASTIC) PIPE (FP) INSTALLATION (HDPE, PVC, AND PVC TYPE A) FOLDED (THERMOPLASTIC) PIPE (FP) INSTALLATION (HDPE, PVC, AND PVC TYPE A) PERFORMANCE SPECIFICATION GUIDELINE August, 2006 Thanks to the following participants for the development of this document: Keith

More information

SECTION XXXXX CHEMICAL GROUTING

SECTION XXXXX CHEMICAL GROUTING SECTION XXXXX CHEMICAL GROUTING PART 1 -- GENERAL 1.01 SCOPE OF WORK A. Provide all labor, materials, accessories, equipment, and tools required for the rehabilitation, infiltration reduction, and root

More information

City of New Haven 101 FRONT STREET PO BOX 236 NEW HAVEN, MO Phone * * Fax

City of New Haven 101 FRONT STREET PO BOX 236 NEW HAVEN, MO Phone *  * Fax City of New Haven 101 FRONT STREET PO BOX 236 NEW HAVEN, MO 63068 Phone 573-237-2349 * www.newhavenmo.org * Fax 573-237-4696 February 12, 2015 Request for Bids Trenchless Reconstruction of Sanitary Sewers

More information

CEDAR RAPIDS METROPOLITAN AREA STANDARD SPECIFICATIONS FOR PUBLIC IMPROVEMENTS May 2014 SECTION SEWER LINERS

CEDAR RAPIDS METROPOLITAN AREA STANDARD SPECIFICATIONS FOR PUBLIC IMPROVEMENTS May 2014 SECTION SEWER LINERS SECTION 02310 SEWER LINERS PART 1 GENERAL 1.01 - References A. American Society for Testing and Materials (ASTM): 1. ASTM D638 Test method for tensile properties of plastics. 2. ASTM D790 Test method for

More information

ULTRAVIOLET LIGHT CIPP LINING OF EXISTING SEWERS

ULTRAVIOLET LIGHT CIPP LINING OF EXISTING SEWERS PART 1 GENERAL 1.01 DESCRIPTION A. SCOPE ULTRAVIOLET LIGHT CIPP LINING OF EXISTING SEWERS This contract covers the rehabilitation of severely deteriorated existing sanitary and combined sewers by lining

More information

EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: PLUMBING SECTION: SANITARY WASTE AND VENT PIPING

EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: PLUMBING SECTION: SANITARY WASTE AND VENT PIPING ICC-ES Report PMG-1273 Reissued 01/2018 This report is subject to renewal 01/2019 EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: 22 00 00 PLUMBING SECTION: 22 13 16

More information

Product Information. Polyester Felt Cured-In-Place Pipe (CIPP) Lining Tube

Product Information. Polyester Felt Cured-In-Place Pipe (CIPP) Lining Tube 1468 West Hospital Road Paoli, Indiana 47454 Phone: (812) 723-0244 Fax: (812) 723-0405 Polyester Felt Cured-In-Place Pipe (CIPP) Lining Tube Revised November 16, 2016 Company Profile Product Types Resins

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

SANITARY SEWER CHEMICAL GROUTING

SANITARY SEWER CHEMICAL GROUTING Specifications (As provided by Avanti International) The information contained in the document is property of Avanti International. Avanti offers the following verbiage as a technical reference to assist

More information

Infrastructure Point Repair System Technical Specifications

Infrastructure Point Repair System Technical Specifications 4301 A 34 t h Street North St. Petersburg, FL 33714 PH: 877-327-4216 Fax: 727-327- 4118 Web: www.irsi.net Infrastructure Point Repair System 1. Scope: This specification defines the approved methodology

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE

PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE PIPE BURSTING GRAVITY SEWER MAINS WITH HDPE PIPE SUGGESTED STANDARD SPECIFICATION January, 2012 Prepared by International Pipe Bursting Association Thanks to the following participants for the development

More information

SPECIAL SPECIFICATIONS UV CURED IN-PLACE SPIRAL WOUND FIBERGLASSS PIPE LINING

SPECIAL SPECIFICATIONS UV CURED IN-PLACE SPIRAL WOUND FIBERGLASSS PIPE LINING 5101.1 Description This item shall govern approved methods and materials for the rehabilitation of deteriorated gravity sewer and storm water pipes by an Ultra-Violet Light Cured-In-Place Pipe (CIPP) lining

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

CITY OF FARGO SPECIFICATIONS PIPE AND MANHOLE REHABILITATION

CITY OF FARGO SPECIFICATIONS PIPE AND MANHOLE REHABILITATION PIPE AND MANHOLE REHABILITATION PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans shall include all labor, materials, and equipment necessary

More information

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Baffle Wall Panel Products and Fabrications REVISED 11.

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Baffle Wall Panel Products and Fabrications REVISED 11. FRP Specifications Section 06 70 00 Fiberglass Reinforced Polymer (FRP) Baffle Wall Panel Products and Fabrications REVISED 11.2016 BRISTOL FACILITY 400 Commonwealth Ave., P. O. Box 580, Bristol, VA 24203-0580

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

EXHIBIT A SCOPE OF SERVICES Districtwide Storm Sewer Inspection

EXHIBIT A SCOPE OF SERVICES Districtwide Storm Sewer Inspection EXHIBIT A SCOPE OF SERVICES Districtwide Storm Sewer Inspection 1.0 Objective: The Department desires to obtain services from the Vendor to inspect existing storm sewer systems. This includes the remote

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

PRODUCT SPECIFICATIONS

PRODUCT SPECIFICATIONS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: High density cast resin architectural products, including columns, panels, caps, bases, trim elements and balustrade systems. Specifier Note: Article below

More information

EVALUATION SUBJECT: PERMA-LATERAL PULLED- IN-PLACE CURED-IN-PLACE PIPE LINING SYSTEM

EVALUATION SUBJECT: PERMA-LATERAL PULLED- IN-PLACE CURED-IN-PLACE PIPE LINING SYSTEM ICC-ES Report PMG-1074 Reissued 11/2017 This report is subject to renewal 11/2018 EVALUATION SUBJECT: PERMA-LATERAL PULLED- IN-PLACE CURED-IN-PLACE PIPE LINING SYSTEM DIVISION: 22 00 00 PLUMBING SECTION:

More information

Inland Pipe Rehabilitation. August 17 OAWWA Canton, OH

Inland Pipe Rehabilitation. August 17 OAWWA Canton, OH Inland Pipe Rehabilitation August 17 OAWWA Canton, OH Presentation Agenda Introduction to IPR IPR Products & Services RS Technik by HammerHead Advanced CIPP Process Spartanburg, SC project review IPR Overview

More information

May 8, 2017 ADDENDUM #1. IFB Resin Floor System For Highway Department Central District Building

May 8, 2017 ADDENDUM #1. IFB Resin Floor System For Highway Department Central District Building May 8, 2017 ADDENDUM #1 IFB 17-082 Resin Floor System For Highway Department Central District Building Addendum #1 is being issued to offer an alternate resin flooring system. 096700 FLUID-APPLIED FLOORING

More information

CIPP Lateral Renewal Connection System

CIPP Lateral Renewal Connection System Product Submittal Document Information CIPP Lateral Renewal Connection System ManEntry Lapel Liner Updated 6/12/14 Product Submittal Review ITEM 1. Manufacturer Company Name: LMK Technologies, LLC Contact

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

FRP Floor Panels Standard Specification

FRP Floor Panels Standard Specification 1. Scope Furnish all labor, materials, equipment and incidentals necessary to install the fiberglass reinforced polymer (FRP) products as specified herein. The work covered by this section shall include

More information

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set PROJECT MANUAL POINT BLANK RANGE & GUN SHOP 600 Corporate way Knoxville, TN Bid/Permit Set Division Section Title SPECIFICATIONS GROUP DIVISION 01 - GENERAL REQUIREMENTS 011000 SUMMARY 012600 CONTRACT

More information

PROJECT MANUAL Volume 1. Project: Clayton Greenway System -Mark s Creek Bridge Replacement

PROJECT MANUAL Volume 1. Project: Clayton Greenway System -Mark s Creek Bridge Replacement PROJECT MANUAL Volume 1 Project: Clayton Greenway System -Mark s Creek Bridge Replacement Owner: Town of Clayton Construction Manager: Lysaght & Associates Issued August 9, 2017 COVER SHEET 000000-1 TABLE

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

***************************************************************************************************************

*************************************************************************************************************** 03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE PROJECT MANUAL / TECHNICAL SPECIFICATIONS WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS - FENCING PACKAGE 3201 E. HOUSTON STREET SAN ANTONIO, TEXAS 78219 OCTOBER 6, 2017 HUMBERTO SALDANA & ASSOCIATES, INC.

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

Hydrodynamic Separation Product Calculator

Hydrodynamic Separation Product Calculator Hydrodynamic Separation Product Calculator Example Project BMP #1 CDS 2015-4 Project Information Project Name Example Project Option # A Country US State Kentucky City Covington Contact Information First

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan.

Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan. Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan. Addenda - Documents used by the Owner to incorporate interpretations or clarifications, modifications,

More information

INLINER LAY_InLiner Brochure_FA_ indd 1

INLINER LAY_InLiner Brochure_FA_ indd 1 INLINER LAY_InLiner Brochure_FA_010913.indd 1 Layne Inliner, LLC is the second largest cured-in-place pipe (CIPP) lining company in the United States. We began as the first U.S. licensee of the Inliner

More information

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES INTENT: To provide a system for reconstruction of concrete or masonry structures to stop inflow, infiltration, exfiltration, and

More information

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation)

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) PART 1 GENERAL SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) 1.01 SCOPE This specification includes the materials and procedures required for the internal sealing of the frame-chimney

More information

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION 1.07 SUPPLEMENTS d. Complete using typewriter or electronic printing. 3. Include detailed lubrication instructions and diagrams showing points to be greased or oiled; recommend type, grade, and temperature

More information

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools Division Section Title SPECIFICATIONS GROUP General Requirements Subgroup DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012600 CONTRACT MODIFICATION PROCEDURES 012900 PAYMENT

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

SPECIFICATIONS FOR AluSystems Aluminum Composite Panels Series 20 Dry Joint 1.00 GENERAL 1.01 RANGE OF WORK Section includes: Laminated panels and attachment systems for use as exterior cladding. A. Provide

More information

SECTION EXPANSION CONTROL

SECTION EXPANSION CONTROL SECTION 07 95 00 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems SECTION 02607-1 1.0 GENERAL 1.1 SCOPE: A. This section covers the work necessary for the construction of sanitary and storm system manholes, catch basins, and miscellaneous concrete structures complete.

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

Section [ ] Storm Water Treatment Device

Section [ ] Storm Water Treatment Device PART 1 GENERAL Section [ ] Storm Water Treatment Device 01.01.00 Purpose The purpose of this specification is to establish generally acceptable criteria for Storm Water Treatment Devices (SWTD) that treat

More information

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3

More information

INSPECTION AND ACCEPTANCE FOR MAINTENANCE

INSPECTION AND ACCEPTANCE FOR MAINTENANCE Inspection and Acceptance For Maintenance Page 1 (Last revised 6/29/10) INSPECTION AND ACCEPTANCE FOR MAINTENANCE SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Acceptance Sewer As Built Drwg Example

More information

SECTION RESINOUS FLOORING or SECTION QUARTZ FLOORING

SECTION RESINOUS FLOORING or SECTION QUARTZ FLOORING SECTION 09 67 23 RESINOUS FLOORING or SECTION 09 67 26 QUARTZ FLOORING PART 1 - GENERAL 1.1 SUMMARY (Specification writer shall add, delete or amend, as deemed necessary) A. Provide all labor, materials,

More information

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Molded Grating and Treads Products and Fabrications REVISED 11.

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Molded Grating and Treads Products and Fabrications REVISED 11. FRP Specifications Section 06 74 13 Fiberglass Reinforced Polymer (FRP) Molded Grating and Treads Products and Fabrications REVISED 11.2016 BRISTOL FACILITY 400 Commonwealth Ave., P. O. Box 580, Bristol,

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

There is an inspection report prepared after the Digester cleaning was carried out.

There is an inspection report prepared after the Digester cleaning was carried out. TERMS OF REFERENCE FOR CONSTRUCTION MANAGEMENT AND INSPECTION FOR THE REPAIRS AND GASPROOFING OF DIGESTER NO.2 AT THE GUELPH WASTEWATER TREATMENT PLANT BACKGROUND The work generally consists of Repairs

More information

1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings

1. B16.1 Cast Iron Pipe Flanges and Flanged Fittings, Class C 111 Rubber Gasket Joints for Ductile Iron Pressure Pipe and Fittings SECTION 33 34 00 SANITARY FORCE MAIN PART 1 GENERAL 1.1 SCOPE OF WORK A. This section specifies the requirements for furnishing and installing sanitary force main and appurtenances. The pipe shall be of

More information

Scope of Work Bid Package C-4 - West Polished Concrete

Scope of Work Bid Package C-4 - West Polished Concrete Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

A. ASTM C 150 Standard Specification for Portland Cement. B. ASTM C 595 Standard Specification for Blended Hydraulic Cements.

A. ASTM C 150 Standard Specification for Portland Cement. B. ASTM C 595 Standard Specification for Blended Hydraulic Cements. TECHNICAL SPECIFICATIONS SEWER MANHOLE REHABILITATION SYSTEM WITH A PROTECTIVE CEMENT LINER AND HIGH BUILD EPOXY COATING (As Provided by Standard Cement Materials) FOREWORD The following specification

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

PROJECT MANUAL BID DOCUMENT 95% REVIEW CHECKLIST PROJECT BID NO EPWU PEM. CONSULTANT SUBMITTED ON / / as a 95% (A) original

PROJECT MANUAL BID DOCUMENT 95% REVIEW CHECKLIST PROJECT BID NO EPWU PEM. CONSULTANT SUBMITTED ON / / as a 95% (A) original PROJECT BID NO EPWU PEM CONSULTANT SUBMITTED ON / / as a 95% (A) original RESUBMITTED ON / / as a 95% (B) revision 1.0 FRONT COVER 1.1 1.2 1.3 1.4 Title begins with location key words, otherwise with program/project

More information

INDUSTRIAL PIPE FITTINGS, LLC

INDUSTRIAL PIPE FITTINGS, LLC Page 1 of 9 SPIROLITE MUNICIPAL AND INDUSTRIAL ODOR CONTROL PIPING Municipal wastewater treatment plants, industrial processes and composting facilities can be assured of trouble free transport of foul

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Structural Shapes/Plate and Fabrications REVISED

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Structural Shapes/Plate and Fabrications REVISED FRP Specifications Section 06 71 00 Fiberglass Reinforced Polymer (FRP) Structural Shapes/Plate and Fabrications REVISED 11.2016 BRISTOL FACILITY 400 Commonwealth Ave., P. O. Box 580, Bristol, VA 24203-0580

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.4 PERMEATION GROUTING 7.4.1 Definitions 7.4.1.1 Geotechnical Data Report (GDR)

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE

SECTION POLYVINYL CHLORIDE (PVC) WATERLINE SECTION 02632 POLYVINYL CHLORIDE (PVC) WATERLINE PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required, and install polyvinyl chloride (PVC) waterline,

More information

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction - State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN

More information

Structural Lining of Water Mains. City of St. John s, Water and Wastewater Division

Structural Lining of Water Mains. City of St. John s, Water and Wastewater Division Structural Lining of Water Mains Overview Applications Pre-lining process Installation (Aqua-Pipe Product) Post-lining process Challenges Applications Alternative to water main reconstruction. Limited

More information

PROForms. Specifications SECTION FIBERGLASS REINFORCED POLYMER (FRP) PULTRUDED PRODUCTS

PROForms. Specifications SECTION FIBERGLASS REINFORCED POLYMER (FRP) PULTRUDED PRODUCTS PROForms Specifications SECTION 06600 FIBERGLASS REINFORCED POLYMER (FRP) PULTRUDED PRODUCTS Disclaimer BEDFORD REINFORCED PLASTICS INC. disclaims liability for any personal injury, property or other damages

More information

SECTION 806 MANHOLE REHABILITATION

SECTION 806 MANHOLE REHABILITATION SECTION 806 MANHOLE REHABILITATION 806-1 DESCRIPTION: This specification consists of all work, materials, labor and equipment required for manhole rehabilitation for the purpose of eliminating infiltration

More information

CITY OF ATLANTIC BEACH BID NUMBER PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA (904)

CITY OF ATLANTIC BEACH BID NUMBER PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA (904) CITY OF ATLANTIC BEACH BID NUMBER 1314-08 PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA 32233 (904) 247-5880 REQUEST FOR BID CONTRACT - CONCRETE REPAIRS FOR THE PUBLIC WORKS/UTILITIES

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

INVITATION TO BID ON TOWN PAVING PROJECTS

INVITATION TO BID ON TOWN PAVING PROJECTS INVITATION TO BID ON TOWN PAVING PROJECTS Offers shall be clearly labeled Paving Bid and submitted to: Town of Madison Paving Bid Attn: Tim Curtis, Town Manager 26 Weston Ave Madison, ME 04950 Bid opening:

More information

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm Sewers B. Abandonment of Storm Sewers 1.02 DESCRIPTION OF WORK A. Construct storm sewers. B. Abandon storm sewers. 1.03 SUBMITTALS Comply with

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING SECTION 334701 - WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. The Contractor shall provide all labor, materials, tools, and equipment required

More information

UNI-BELL PVC PIPE ASSOCIATION UNI-B-15-10

UNI-BELL PVC PIPE ASSOCIATION UNI-B-15-10 UNI-BELL PVC PIPE ASSOCIATION UNI-B-15-10 RECOMMENDED STANDARD SPECIFICATION FOR POLYVINYL CHLORIDE (PVC) FABRICATED PRESSURE FITTINGS November 2010 UNI-BELL PVC PIPE ASSOCIATION 2711 LBJ Freeway, Suite

More information

SPECIFICATION for ISCO HDPE DUAL CONTAINMENT PIPE

SPECIFICATION for ISCO HDPE DUAL CONTAINMENT PIPE SPECIFICATION for ISCO HDPE DUAL CONTAINMENT PIPE SECTION 15000 MECHANICAL 1. GENERAL 1.1 This specification shall govern the materials and installation of polyethylene dual contained system of pipe, structures

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 01 40 00 QUALITY REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Quality control and control of installation. Tolerances. References. Labeling. Mock-up requirements. Testing and inspection

More information

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter. STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer

More information

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Pultruded Grating/Treads and Fabrications REVISED

FRP Specifications. Section Fiberglass Reinforced Polymer (FRP) Pultruded Grating/Treads and Fabrications REVISED FRP Specifications Section 06 74 13 Fiberglass Reinforced Polymer (FRP) Pultruded Grating/Treads and Fabrications REVISED 11.2016 BRISTOL FACILITY 400 Commonwealth Ave., P. O. Box 580, Bristol, VA 24203-0580

More information

SECTION FIBERGLASS REINFORCED POLYMER (FRP) PANELS

SECTION FIBERGLASS REINFORCED POLYMER (FRP) PANELS SECTION 07 44 50 FIBERGLASS REINFORCED POLYMER (FRP) PANELS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Design, Engineering, manufacturing and erection of fiberglass reinforced panels. Delegated Design of

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CSB 7th Floor Orthopaedic Surgery Office Renovation Phase 2 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

Specifications for Concrete Embedment Liner

Specifications for Concrete Embedment Liner Specifications for Concrete Embedment Liner Part 1: GENERAL 1.01 SECTION INCLUDES A. Specifications and guidelines for MANUFACTURING high-density polyethylene embedment liners. 1.02 REFERENCES A. American

More information

ENGINEERING SPECIFICATION PULTRUDED DYNAFORM FIBERGLASS STRUCTURAL SHAPES FIBERGRATE MOLDED GRATING WITH GRATING PEDESTALS. January 24,

ENGINEERING SPECIFICATION PULTRUDED DYNAFORM FIBERGLASS STRUCTURAL SHAPES FIBERGRATE MOLDED GRATING WITH GRATING PEDESTALS. January 24, ENGINEERING SPECIFICATION PULTRUDED DYNAFORM FIBERGLASS STRUCTURAL SHAPES FIBERGRATE MOLDED GRATING WITH GRATING PEDESTALS January 24, 2014 06600-1 SECTION 06610 FIBERGLASS REINFORCED PLASTICS (FRP) FABRICATIONS

More information

Elastomeric Protected Membrane Roofing Fluid-Applied Protected Membrane Roofing. Restoration Coating System (RCS) over Cap Sheet

Elastomeric Protected Membrane Roofing Fluid-Applied Protected Membrane Roofing. Restoration Coating System (RCS) over Cap Sheet 07 55 53 Elastomeric Protected Membrane Roofing 07 55 56 Fluid-Applied Protected Membrane Roofing Restoration Coating System (RCS) over Cap Sheet PART 1 - GENERAL 1.1 SUMMARY A. This specification covers

More information

TAMDID PIPES GRP MANHOLE BROCHURE

TAMDID PIPES GRP MANHOLE BROCHURE TAMDID PIPES GRP MANHOLE BROCHURE 1) Types & Description of Manholes: Tamdid Pipes offer two types of Manholes; Structural and Liner Manholes: a. Structural Manholes Tamdid Pipes offers concentric and

More information

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project RES. NO. PROPOSAL FOR THE COMPLETION OF 2015-28 TO THE SATISFACTION OF THE BUTLER COUNTY COMMISSIONERS AND THE COUNTY ENGINEER: SAID WORK CONSISTING OF TYLERSVILLE ROAD IMPROVEMENTS, PHASE I TO THE COUNTY

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

ENGINEERING SPECIFICATION. PULTRUDED PEDESTRIAN FIBERGLASS GRATING SAFE-T-SPAN T1210 VINYL ESTER and ISOPHTHALIC. October 25, 2004 Revision 1

ENGINEERING SPECIFICATION. PULTRUDED PEDESTRIAN FIBERGLASS GRATING SAFE-T-SPAN T1210 VINYL ESTER and ISOPHTHALIC. October 25, 2004 Revision 1 ENGINEERING SPECIFICATION PULTRUDED PEDESTRIAN FIBERGLASS GRATING SAFE-T-SPAN T1210 VINYL ESTER and ISOPHTHALIC 1 PART 1 - GENERAL 1.1 SCOPE OF WORK SECTION 06610 FIBERGLASS REINFORCED PLASTICS (FRP) FABRICATIONS

More information