Publicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build

Size: px
Start display at page:

Download "Publicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build"

Transcription

1 1 Leigh Sata, Santa Rosa Junior College Kelle Lynch McMahon, Peralta Community College Mark Kelley, Dannis Woliver Kelley Deidree Sakai, Dannis Woliver Kelley 2 1

2 Publicly Bid: Design-Bid-Build Multiple-Prime Contracting Negotiated, Non-Bid: Lease-Leaseback* Design-Build Hybrid: Construction Management At Risk Integrated Project Delivery (IPD) 3 4 2

3 Construction Manager (Opt.) District Architect General Contractor =Owner Team Subcontractors 5 5 Advantages Familiar and established way of delivering a project. A/E of record works for District and represents owner. Suitable Advantages for competitive bidding w/ lowest price initially. Disadvantages No early contractor involvement. Potential conflicts between general contractor and architect after construction begins. Higher Disadvantages probability of change orders, including deductive ones. Could be adversarial. 3

4 Legal perspective Industry perspective District perspective 7 District Architect Construction Manager Trade Contractors =Owner Team 8 4

5 Advantages Trade contractors are procured through competitive lowest responsible bidders. Avoids general contractor mark-up. Competitive selection (not low bid) for construction manager to lead project. Can rebid portions of the work, rather than the whole scope, if needed. Disadvantages Disadvantages Potential conflicts between multiple contractors and architect after construction begins. Bids over budget are challenging to adjust to obtain cost reductions. Potential overlaps or gaps in scopes of work. Construction Higher risks due to multiple contractors, particularly delay/interference claims. Difficult to coordinate and control schedule. Additional work and risk for District: more scopes of bid protests; contract admin. Legal perspective Industry perspective District perspective 10 5

6 11 Construction Manager (Opt.) District Architect LLB Builder =Owner Team Trade Contractors

7 Owner Architect Builder Owner lease to Builder Owner makes tenant improvement payments Lease expires (grey area) Design Input From LLB Entity Construction Construction start Time Construction completion and lease payments begin K-12 (Ed. Code 17406): (a) (1) Notwithstanding Section 17417, the governing board of a school district, without advertising for bids, may let, for a minimum rental of one dollar ($1) a year CCDs (Ed. Code 81335): The governing board of a community college district may let, at a minimum rental of one dollar ($1) a year 14 7

8 Authorized by Education Code Provides Districts with flexibility and benefits that may not be possible with some of the other delivery methods. LLB allows an owner to select a GC during the design/preconstruction phase through a defined qualification and fee based selection process. All requirements for construction and/or public works are still applicable; i.e. prevailing wage, bonds, insurance, indemnification, Field Act compliance (seismic and accessibility), and skilled workforce requirements. 15 Advantages A District may use Lease- Leaseback to finance the project. The District does not have to award contract to lowest bidder. Generally less adversarial, fewer change orders, less litigation. The District may participate in selecting Developer-Contractor, and all the trade contractors and suppliers. Solicitation of savings/cost can create costs savings. Disadvantages Uncertainty (post- Davis v. Fresno USD environment); risk-averse CM CCDs still avoid. Steeper District/public learning curve than bid-based contracts. Thought to be more expensive up front than bid-based contracts. Conflict of interest still a major issue (not resolved by the new K- 12 statute). 8

9 Legal perspective Industry perspective District perspective 17 Program Architect District Design-Build Entity (Architect + Contractor) =Owner Team Trade contractors 18 9

10 Advantages Builder and architect are on the same team. Disadvantages Builder and architect are on the same team. Multiple packages may provide greater opportunity for participation by local trade contractors. Earlier knowledge of construction costs; guaranteed during design of project. No common standards for methodology. Steeper District/public learning curve than bid-based contracting. Single point of responsibility: Design risk shift to the Design- Build Entity. Turn-key delivery, less day-today District involvement. Less District control. Legal perspective Industry perspective District perspective 20 10

11 21 District Architect Construction Manager Trade Contractors =Owner Team 22 11

12 District Architect Construction Manager Trade Contractors =Owner Team 23 Advantages Potential for faster delivery systems. SU B Mitigate material shortages and price escalation issues vs. multiple-prime contracting. Design Advantages May bring construction input into design phase if properly procured. Disadvantages No common standards for this methodology; confirm appropriate procurement. Steeper District/public learning curve than bid or statutory contracting methods. Disadvantages Confirm legal authorization to use this method; risk-averse CCDs avoid. May facilitate value engineering. 12

13 Legal perspective Industry perspective District perspective

14 Advantages Potential for faster delivery systems. May be the wave of the future for cooperative project delivery. SU B Fewer disputes, resolved Design earlier. Advantages Disadvantages No common standards for methodology in CA CCD projects. Very steep learning curve for all parties to delivery method. Confirm legal authorization to use this method. Disadvantages Legal perspective Industry perspective District perspective 28 14

15 Design-Bid-Build Multi-Prime Contracting Lease-Leaseback Design-Build CM at-risk Integrated Project Delivery 29 Q & A 15

16 Leigh Sata, Santa Rosa Junior College Kelle Lynch McMahon, Peralta Community College Deidree Sakai, Dannis Woliver Kelley Mark Kelley, Dannis Woliver Kelley 31 16

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center Construction 101 C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center This training is provided for educational, compliance and loss-prevention purposes only and, absent the

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG

More information

Project Delivery Method

Project Delivery Method Project Delivery Method Presenters San Diego Community College District Facilities Management Lance Lareau District Architect UC Berkeley graduate 30 years of architecture experience 2 nd generation architect

More information

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Choosing a Project Delivery Method. A Design-Build Done Right Primer Choosing a Project Delivery Method A Design-Build Done Right Primer DESIGN-BUILD DONE RIGHT PRIMER 1 Choosing a Project Delivery Method A DESIGN-BUILD DONE RIGHT PRIMER A DESIGN-BUILD INSTITUTE OF AMERICA

More information

PROVING OUR PROFESSIONALISM

PROVING OUR PROFESSIONALISM PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods

More information

BID AND PURCHASING LAWS/BEST PRACTICES

BID AND PURCHASING LAWS/BEST PRACTICES BID AND PURCHASING LAWS/BEST PRACTICES BEFORE YOU DO ANYTHING, ASK YOURSELF THIS QUESTION. Is this purchase or contract for goods or services exempt from the bid laws? Exemptions: Piggy back off a contract

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE Risks Associated with Alternative Delivery Methods Managing Expectations Presented by Dan Becker, CCM, PMP, CCE 1 3 Primary Methods for Delivering Projects in WA and OR Design/Bid/Build Design/Build CM

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005 CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS August 2005 Projects Requiring Licensed Architect / Engineer: *Project Cost Threshold New Construction or Additions $135,000 + Major Repairs

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

JOB ORDER CONTRACTING (JOC)

JOB ORDER CONTRACTING (JOC) JOB ORDER CONTRACTING (JOC) A LEAN Best Management Practice for Efficient Construction Project Delivery All product and company names are trademarks or registered trademarks of their respective holders.

More information

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for

More information

AIA Contract Documents

AIA Contract Documents AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).

More information

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K CONTRACTS CATALOG Updated Docs Inside ou Ah ead o f the Cur v e gy epin e K ... BUILDING A BETTER WAY! Whether working at the office, from the road or even at home, the platform provides instant access

More information

Procurement Guidelines

Procurement Guidelines Reference 21 CM@Risk Procurement Guidelines Draft June 5, 2014 Purpose: These guidelines are intended to provide (1) assistance to those who may be responsible for implementation, processing and/or management

More information

Role of Procurement / Purchasing Within the Authority

Role of Procurement / Purchasing Within the Authority Role of Procurement / Purchasing Within the Authority What is Purchasing s Role / Why Is Purchasing Important? The Authorized entity within the Water Authority that procures the goods / services required.

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

You Can t Build Without CEQA!

You Can t Build Without CEQA! You Can t Build Without CEQA! November 16, 2016, 9:15 a.m. Leigh Sata, Sonoma County Junior College District Mark Kelley and Jessika Johnson, Dannis Woliver Kelley Amy Skewes-Cox, AICP, Amy Skewes-Cox

More information

Illinois State Board of Education Nutrition and Wellness Programs Division. Procurement: NSLP Equipment Assistance Grant

Illinois State Board of Education Nutrition and Wellness Programs Division. Procurement: NSLP Equipment Assistance Grant Illinois State Board of Education Nutrition and Wellness Programs Division Procurement: NSLP Equipment Assistance Grant 2 Applicable Procurement regulations: When purchasing equipment, you must follow

More information

Project Labor Agreements. September 18, 2012

Project Labor Agreements. September 18, 2012 Project Labor Agreements September 18, 2012 Project Labor Agreements - Definitions Pre-Hire Collective Bargaining Agreement Used on Large Complex Construction Projects Employing Multiple Trades Terms and

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

More information

1/4/2014. Alternative Project Delivery Methods 1. Agenda

1/4/2014. Alternative Project Delivery Methods 1. Agenda Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia

More information

Thank you for coming this morning and learning about us.

Thank you for coming this morning and learning about us. Thank you for coming this morning and learning about us. Government agencies are one of the largest consumers of goods and services in the country. As you likely know, selling to government agencies is

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNIVERSITY OF CALIFORNIA, SAN DIEGO BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSOCIATE VICE CHANCELLOR CAPITAL PROGRAM MANAGEMENT TEL: (858) 534-2177 FAX: (858) 534-4363

More information

FEMA PA Match Training

FEMA PA Match Training FEMA PA Match Training PROCUREMENT REQUIREMENTS USING CDBG-DR FUNDS Regulatory/Statutory Citations Selection Procedures - (2 CFR 200.319) Conflict of Interest - (2 CFR 200.318) Contract Administration

More information

Selection of Contractor Step 5. June 2013

Selection of Contractor Step 5. June 2013 Selection of Contractor Step 5 June 2013 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement of Contractor

More information

AVIATION AUTHORITY POLICY

AVIATION AUTHORITY POLICY PURPOSE: To establish a policy for the selection of development related professional services firms, including design-build firms for professional services and the Consulting Engineer, pursuant to the

More information

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department Date: March 30, 2011 ADDENDUM No. 3 BID NO.: 10-11/27 PCCD Smart

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

Choosing a TSO Supplier

Choosing a TSO Supplier Choosing a TSO Supplier TM on Technical Support Organization (TSO) Roles and Responsibilities John Moore Nuclear Power Engineering Section j.h.moore@iaea.org Vienna, May 16, 2013 International Atomic Energy

More information

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

The documents in the A-Series relate to various forms of agreement between an owner and a contractor.

The documents in the A-Series relate to various forms of agreement between an owner and a contractor. A-Series A- S E R I E S The documents in the A-Series relate to various forms of agreement between an owner and a contractor. A101 Owner-Contractor Agreement Form Stipulated Sum Basis of payment is a stipulated

More information

TORONTO MUNICIPAL CODE CHAPTER 67, FAIR WAGE SCHEDULE A, FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY

TORONTO MUNICIPAL CODE CHAPTER 67, FAIR WAGE SCHEDULE A, FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY 67-A1. Definitions. 67-A2. City of Toronto Council references. 67-A3. Purpose and history of Fair Wage Policy. 67-A4. Intent of Fair Wage Policy. 67-A5. Application. 67-A6.

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of

More information

SAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop

SAN DIEGO COMMUNITY COLLEGE DISTRICT. SDCCD Design/Build Subcontracting Plan Preparation Workshop SAN DIEGO COMMUNITY COLLEGE DISTRICT SDCCD Design/Build Subcontracting Plan Preparation Workshop April 7, 2015 Welcome Chris Manis Vice Chancellor, Facilities Management Purpose To share information useful

More information

Coordination of Consultants

Coordination of Consultants Coordination of Consultants Ontario Association of Architects Practice Tip PT.27 Version 1.0 May 21, 2012 2012 OAA, all rights reserved. Persons who are not members of the OAA must obtain written permission

More information

CONSTRUCTION MANAGEMENT AGREEMENT

CONSTRUCTION MANAGEMENT AGREEMENT CONSTRUCTION MANAGEMENT AGREEMENT This Construction Management Agreement ( Agreement ) is made and entered into effective November 1, 2012, by and between the Newark Unified School District ( District

More information

Professional Practice 544

Professional Practice 544 February 22, 2016 February 29, 2016 Professional Practice 544 AIA-B101 Owner - Architect Agreement Michael J. Hanahan Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

VICTOR VALLEY UNION HIGH SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR

VICTOR VALLEY UNION HIGH SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR VICTOR VALLEY UNION HIGH SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR GENERAL CONTRACTOR AND MECHANICAL, ELECTRICAL, PLUMBING, FIRE PROTECTION AND UNDERGROUND PIPELINE SUBCONTRACTOR LICENSEES (License

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

Department of Public Works Division of Engineering. Nassau County, New York

Department of Public Works Division of Engineering. Nassau County, New York TOWN OF OYSTER BAY Department of Public Works Division of Engineering Nassau County, New York REQUEST FOR PROPOSALS FOR CONSULTANT SERVICES SOLICITATION NO. 2017-12 NOTES: 1. ISSUANCE DATE: Thursday, October

More information

Progressive Design-Build

Progressive Design-Build November 15,2016 Progressive Design-Build A Smart Alternative to Lease/Lease back? PRESENTERS Praful Kulkarni, AIA Rebekah Gladson, FAIA, DBIA Robynne T. Parkinson, JD, DBIA Presentation Outline Value

More information

CHAPTER 6: PROJECT MANAGEMENT

CHAPTER 6: PROJECT MANAGEMENT CHAPTER 6: PROJECT MANAGEMENT 6.1 Overview 6.2 Phases of a Capital Project 6.3 Project Management Team 6.4 Selecting Design and Construction Professionals 6.5 Project Delivery Method 6.6 Developing a Work

More information

Continuing Education Credits

Continuing Education Credits Recent Developments in (IPD) for NECA Members October 14, 2013 9:00-9:50 AM Following this session, you will be able to: Explain the concept and structure of an IPD project. Identify the issues and risks

More information

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES 1 of 15 CS & ASSOCIATES EXPERIENCE & BACKGROUND Established in 2003 by Charla Curtis, Former LCP Director for LAUSD Certified MBE/

More information

PROCUREMENT GUIDELINES For Grantees Receiving Federal Transit Funds via MDOT Revised March 2017

PROCUREMENT GUIDELINES For Grantees Receiving Federal Transit Funds via MDOT Revised March 2017 Michigan Department Of Transportation 3182 (03/17) PROCUREMENT GUIDELINES For Grantees Receiving Federal Transit Funds via MDOT Revised March 2017 Page 1 of 28 PURPOSE The purpose of these guidelines is

More information

Understanding Public Bid Law La. R.S. 38:

Understanding Public Bid Law La. R.S. 38: Understanding Public Bid Law La. R.S. 38:2211-2293 E R I N D A Y, A S S I S T A N T A T T O R N E Y G E N E R A L L O U I S I A N A D E P A R T M E N T O F J U S T I C E Application All Political Subdivisions

More information

INNOVATIVE CONTRACTING GUIDELINES

INNOVATIVE CONTRACTING GUIDELINES Office of Construction and Innovative Contracting INNOVATIVE CONTRACTING GUIDELINES A+B Bidding Lane Rentals Incentives/ Disincentives Liquidated Savings Design-Build Warranties Pay for Performance No

More information

PROJECT PROCUREMENT MANAGEMENT. 1 Powered by POeT Solvers Limited

PROJECT PROCUREMENT MANAGEMENT. 1  Powered by POeT Solvers Limited PROJECT PROCUREMENT MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited CONDUCT PROCUREMENT PROCESSES BY PROCESS GROUP Planning Executing Monitoring and controlling Closing 12.1 12.2 12.3 12.4

More information

Commonwealth of Massachusetts DEPARTMENT OF HOUSING & COMMUNITY DEVELOPMENT Deval L. Patrick, Governor Aaron Gornstein, Undersecretary FOR

Commonwealth of Massachusetts DEPARTMENT OF HOUSING & COMMUNITY DEVELOPMENT Deval L. Patrick, Governor Aaron Gornstein, Undersecretary FOR 1 23 Commonwealth of Massachusetts DEPARTMENT OF HOUSING & COMMUNITY DEVELOPMENT Deval L. Patrick, Governor Aaron Gornstein, Undersecretary REQUEST FOR RESPONSES (RFR) FOR WEB-BASED BID DOCUMENT DISTRIBUTION

More information

TEAMING, SUBCONTRACTING, AND JOINT VENTURES

TEAMING, SUBCONTRACTING, AND JOINT VENTURES 888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 TEAMING, SUBCONTRACTING, AND JOINT VENTURES 2013 NATIONAL HUBZONE CONFERENCE SEPTEMBER 10, 2013 Presented

More information

Project Procurement Considerations in This Market. October 14, 2016

Project Procurement Considerations in This Market. October 14, 2016 Project Procurement Considerations in This Market October 14, 2016 Overview Thank you for being here! Introduction About QBS Colorado Project Delivery Methods Market Information Federal & State Information

More information

IRVINE UNIFIED SCHOOL DISTRICT CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20

IRVINE UNIFIED SCHOOL DISTRICT CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20 CONTRACTOR S PREQUALIFICATION QUESTIONNAIRE, 20 The Irvine Unified School District ( District ) has determined that bidders on an annual basis must be prequalified prior to submitting a bid on a project

More information

BID AWARD: 16 COS HANFORD EDUCATIONAL CENTER MODULAR CLASSROOM (SITE WORK)

BID AWARD: 16 COS HANFORD EDUCATIONAL CENTER MODULAR CLASSROOM (SITE WORK) COLLEGE OF THE SEQUOIAS COMMUNITY COLLEGE DISTRICT Board of Trustees Meeting July 10, 2017 BID AWARD: 16 COS HANFORD EDUCATIONAL CENTER MODULAR CLASSROOM (SITE WORK) Status: Presented by: Action Byron

More information

PROCUREMENT STANDARDS. Program Regulations found in: 7 CFR Parts 210, 215, 220, 225, and 226 and 2 CFR

PROCUREMENT STANDARDS. Program Regulations found in: 7 CFR Parts 210, 215, 220, 225, and 226 and 2 CFR Program Regulations found in: 7 CFR Parts 210, 215, 220, 225, and 226 and 2 CFR 200.318-.326 Procurement standards Program Regulations Government-wide Regulations Procurement Monitoring What to look for?

More information

Stacey Camillo, Contract Administration. As-Needed Construction Contracting

Stacey Camillo, Contract Administration. As-Needed Construction Contracting Stacey Camillo, Contract Administration As-Needed Construction Contracting November 3, 2016 Why we are here Agenda Introductions Methods of getting construction work in San Francisco New As-Needed Construction

More information

CCA Contract Forms Type Members Non-Members

CCA Contract Forms Type Members Non-Members To order CCA documents and/or seals please email planroom@saskatoonconstruction.ca CCA Contract Forms Type Members Non-Members CCA 1-2008 Stipulated Price Subcontract Electronic $52.00 $67.00 Seals $6.00

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 09.03.2016 Project phases time Inception initiation Preliminary analysis

More information

COMMUNITY COLLEGE DISTRICT OF JEFFERSON COUNTY, MISSOURI REQUEST FOR PROPOSAL: WINDOW, DOOR, AND FRAME REPLACEMENT

COMMUNITY COLLEGE DISTRICT OF JEFFERSON COUNTY, MISSOURI REQUEST FOR PROPOSAL: WINDOW, DOOR, AND FRAME REPLACEMENT COMMUNITY COLLEGE DISTRICT OF JEFFERSON COUNTY, MISSOURI REQUEST FOR PROPOSAL: WINDOW, DOOR, AND FRAME REPLACEMENT RFP # 1710002 Sheree Bell Due Date: November 30, 2017 Procurement Coordinator Not later

More information

New Developments in Alternative Dispute Resolution: What CM s Should Know CMAA National Conference October 27, 2009

New Developments in Alternative Dispute Resolution: What CM s Should Know CMAA National Conference October 27, 2009 New Developments in Alternative Dispute Resolution: What CM s Should Know 2009 CMAA National Conference October 27, 2009 Presentation Outline 1. Current Industry and Market Conditions 2. Dispute Prevention

More information

Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects

Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Presented by: Robyn Minter Smyers Alan S. Ritchie Heather A. Bartzi Erin Luke Presentation Team Robyn Minter Smyers

More information

Giorgiana Teccuci Aisha Nadar

Giorgiana Teccuci Aisha Nadar Giorgiana Teccuci Aisha Nadar Role of the Consulting Engineer in the Context of the New Yellow Book & its Dispute Board Provisions Agenda The FIDIC Contracts The Consulting Engineer and their role What

More information

BID THRESHOLD AND QUOTES

BID THRESHOLD AND QUOTES April 27 th & 28 th, 2016 As Presented By: Matthew Cavallo, Township Manager for the Township of Verona & Gerald T Reiner Jr., Purchasing Agent for the County of Bergen BID THRESHOLD AND QUOTES Jurisdiction

More information

PURCHASING POLICY. Policy No CONTENTS:

PURCHASING POLICY. Policy No CONTENTS: Policy No. 1502 PURCHASING POLICY CONTENTS: POLICY: The Village of Heisler shall conduct its purchasing in accordance with generally recognized purchasing practices including, wherever possible, the competitive

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

This policy will outline the requirements for competitive bids on goods and services purchased by the College.

This policy will outline the requirements for competitive bids on goods and services purchased by the College. Policy Name: Procurement Sole Source/Competitive Bid Policy Updated/Reviewed: August 10, 2017 Effective Date: November 15, 2010 Office with Primary Responsibility: Procurement Services Offices with Secondary

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 04.03.2015 Project phases time Inception initiation Preliminary analysis

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

Pennsylvania Association of School Business Officials

Pennsylvania Association of School Business Officials Pennsylvania Association of School Business Officials Mailing Address: Office Location: P.O. Box 6993 2608 Market Place Harrisburg, PA 17112-0993 Harrisburg, PA 17110 Telephone 717-540-9551 www.pasbo.org

More information

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build

More information

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013 FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS June 1, 2013 For general guidance the following information is provided as an aid to those preparing submittals in response to Design-Build solicitations.

More information

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3

More information

Section 1 - Homeowners and the EBB Program... Page 2. Section 2 - Participating Contractors... Page g. Section 3 - Dispute Resolution...

Section 1 - Homeowners and the EBB Program... Page 2. Section 2 - Participating Contractors... Page g. Section 3 - Dispute Resolution... About EBB Earthquake Brace + Bolt (EBB) was developed to help homeowners lessen the potential for damage to their houses during an earthquake. A residential seismic retrofit strengthens an existing older

More information

Finance & Technology Administrator (815) ext 223

Finance & Technology Administrator (815) ext 223 2017 PAVING IMPROVEMENTS BID PACKET Due: Location: April 26, 2017 by 10:00 am Oregon Park District Fairgrounds Park 607 Fair Park Drive Oregon, IL 61061 Bid Proposal: 2017 Paving Improvements Administrative

More information

PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR

PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR PROGRESSIVE DESIGN BUILD WHAT IS IT? AN UPDATE FROM LAST YEAR Moderator: Praful Kulkarni, AIA President/CEO of gkkworks National Chairman of DBIA Presenters: Geoffrey Neumayr, SE Chief Development Officer

More information

What is the Department of Public Works Project Labor Agreement (DPW-PLA)?

What is the Department of Public Works Project Labor Agreement (DPW-PLA)? City of Los Angeles Department of Public Works PLA / Public Works Infrastructure Stabilization Policy Frequently Asked Questions for Project Labor Agreement 2015-2020 Please note: This document is meant

More information

Integrated Project Delivery

Integrated Project Delivery 2014 HDR Architecture, 2014 HDR, Inc., all all rights reserved. Integrated Project Delivery It s A New World, And How It Can Benefit Municipal Owners Rich Atoulikian, PMP, PE Rich.Atoulikian@hdrinc.com

More information

The Brickfields Trust. Procurement and Tendering Policy and Procedures

The Brickfields Trust. Procurement and Tendering Policy and Procedures Procurement and Tendering Policy and Procedures CONTENTS PAGE NO: 1. QUOTATION AND TENDERING... 3 2. PROCEDURES... 3 3. ACCEPTANCE OF TENDER... 4 4. UNSUCCESSFUL BIDS... 5 2 1. QUOTATION AND TENDERING

More information

ACCOUNTING SYSTEM/PROMPT PAYMENT

ACCOUNTING SYSTEM/PROMPT PAYMENT ACCOUNTING SYSTEM/PROMPT PAYMENT FILE: DIA TITLE: Timely Settlement of District Liabilities POLICY: Each principal or other person in charge of district funds used for external procurement of goods or

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

Assessment RFP Development Toolkit Introduction to the Toolkit Joseph A Martineau Senior Associate. Who is the Audience for this Toolkit?

Assessment RFP Development Toolkit Introduction to the Toolkit Joseph A Martineau Senior Associate. Who is the Audience for this Toolkit? Assessment RFP Development Toolkit Introduction to the Toolkit Joseph A Martineau Senior Associate Who is the Audience for this Toolkit? This toolkit is targeted toward state education agency (SEA) staff

More information

WEATHERIZATION ASSISTANCE PROGRAM PROCUREMENT. A. Introduction

WEATHERIZATION ASSISTANCE PROGRAM PROCUREMENT. A. Introduction WEATHERIZATION ASSISTANCE PROGRAM PROCUREMENT A. Introduction Procurement is the acquisition of goods and/or services. Proper procurement will result in the goods/services are appropriate and that they

More information

Submitted by: Kathleen Krauss, CPPB, Purchasing Manager, City of Deltona, FL

Submitted by: Kathleen Krauss, CPPB, Purchasing Manager, City of Deltona, FL Purchasing Month Jeopardy Submitted by: Kathleen Krauss, CPPB, Purchasing Manager, City of Deltona, FL This game helps individuals learn about Purchasing. We actually pass out the questions prior to the

More information

DESIGN-BUILD WASHTO WYDOT

DESIGN-BUILD WASHTO WYDOT DESIGN-BUILD An OVERVIEW for STATE DEPARTMENTS of TRANSPORTATION Prepared for WASHTO (Western Association of State Highway and Transportation Officials) WYDOT by Wyoming Department of Transportation June

More information

Owner s Representative SCOPE OF SERVICES

Owner s Representative SCOPE OF SERVICES Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,

More information

UNC Chapel Hill Informal Contracting Guidelines

UNC Chapel Hill Informal Contracting Guidelines UNC Chapel Hill Informal Contracting Guidelines 1. Informal Contracts Informal bids are referenced by NC General Statute (NCGS) 143-131 as construction or repair work that does not reach the limits prescribed

More information