1 Residue Fluid Catalytic Cracker (RFCC) Project in Korea achieved remarkable benchmark targets Nov. 11, 2009 Presented by Mr. Sook-Hyung(Sam) Kwon
2 Table of Contents I. Introduction of SK Energy II. Background of the No.2 FCC Project III. General Description of the No.2 FCC Plant IV. Initial Project Goals V. Project Execution Strategies VI. Work Breakdown Structures VII. Implementation of Project Execution Strategies VIII. Performance of the No.2 FCC Project IX. Key Success Factors X. Pictures of the No.2 FCC Plant 2
3 I. Introduction of SK Energy Asia s Leading Energy Company - Asia s No.4 CDU Capacity of 1,115,000 B/D - World No.1 API Group III Lube Base Oil Manufacturer - Ranked No.29 in 2007 Forbes Global Top Oil & Gas Companies - Ranked No.74 in 2009 Fortune Global 500 Asia s Leading Energy Company Korea s No.1 Energy Provider - Korea s first oil refining company which was established in Largest domestic market share of 35% in petroleum product sales 3
4 I. Introduction of SK Energy Overall Process Block Diagram of SK Ulsan Complex AR #1~5 CDU LSR NAPH KERO LGO G/C & Me LSR Me Naphtha Cracker Propylene Reformate Reformate Reformer VDU RHDS Acetylene S/B Me MDU Ethylene BRU/Sul/ AEU Mixed Xylene XFU HC VRDS RFCC PE PO/SM PP Bz LBO PX CHx LCO LCN Propylene C3/C4 Acetylene Ethylene PE PO / SM PP Propylene Cyclohexane Benzene Toluene PX Gasoline Jet Fuel Kerosene Diesel Lube Base Oil Fuel Oil Asphalt B-C 4
5 I. Introduction of SK Energy Plant Capacity of SK Energy Refinery Process CDU MDU #1~5VDU CDU 7 (2) 8 (1) Capacity (MBPD) 1,115 (275) 329 (70) BRU(Benzene) 1 30 Reformer Units 4 (1) 5 (2) 137 (22) 121 (34) Hydrocracker 1 45 LBO 2 23 RHDS RFCC Petrochemical Plants Process Ethylene Unit Butadiene Ext raction Unit Butene-1 Sulfolane PX MTBE CHx PE PP Units (2) * ( ) : Incheon Refinery Capacity ( KMT/Yr) 860(C2=) 115(BD) 42(B-1) 3,020(BTX) (880) 958(PX/OX) 250(MTBE) 180(CHx) 396(PE) 366(PP) 5
6 II. Background of the No.2 FCC Project To Enhance SK s Competitiveness No.2 FCC Project SK s Lower Ratio of Up-grading Facilities Increased Premium Gasoline Demand Enhance Price Competitiveness Fulfill Environmental Regulations 6
7 III. General Description of the No.2 FCC Plant Process Scheme Unit : MB/D H2S SRP (620 T/ D ) Sulfur (510 T/D) Fuel Gas (2) AR Fuel Gas ( 0.3 ) C3/C4 (0.6) C3 ( 15.1 ) C4 (8.0) PRU (972 T/ D ) Propylene (11.8) Propane ( 3.2 ) Butamer (13) nc4 (13) H2 (80) HP (110 MSCFD ) No.2 RHDS ( 80 ) Naph (2.2) DSL (16.8 ) L/S B-C (60) B-C (3.6) No.2 RFCC ( 60 ) C4= (14.5) SHP (14.5) Gasoline ( 22 ) HCN ( 7.4 ) LCO ( 2.9 ) Alkylation Alkylate ( 18 ) ( 17.5 ) Sulfuric Acid SAR (180T/D) GDS ( 30 ) SLO ( 5.0 ) T-Gasoline ( 22 ) No.2 FCC plant consists of more than 10 process units and its supporting utility and offsite facilities. 7
8 III. General Description of the No.2 FCC Plant Utility & Offsite Facilities Area System Capacity Utilities Offsites Water Treatment System Cooling Water System Instrument & Plant Air System Nitrogen System Electrical Supply System (154 kv) Storage Tanks Raw Water Intake System Waste Water Treatment System Flare System 2,000 m3/h (Clarifier Base) 48,000 m3/h 37,000 Nm3/h (Dry Air Base) 5,000 ~ 20,000 Nm3/h (Contract) 160 MVA 1,500 MBbl (30 EA) 1,400 t/h (32 x 3.5 km) 7,000 t/d 1,000,000 kg/h Fire Fighting System & so on. Buildings Main Control Building, Admin. Building, Fire House, Maintenance Building, MCC/SW GR Rooms & so on. 8
9 IV. Initial Project Goals To enjoy big cracking margins before downturn, SK sets the schedule driven project goals while maintaining project qualities and not exceeding the budget. Description Project Goals Remarks Schedule 35 months from the start of FEED to commercial operation Unprecedented tight schedule Quality On-Stream Factor 0.95 (Note) No.1 FCC Project Record : 0.93 Cost Within the budget (US$ 2.0 Billion) Estimated TIC during Feasibility Study was US$ 2.3bil. Safety No Serious injury No-Death No-Serious Injury requiring hospitalization more than 3 months (Note) On-stream Factor = Actual treated quantities for 90 days after initial start-up divided by design capacity 9
10 V. Project Execution Strategies To establish the project execution strategies, SK evaluated and identified SQC risks through SWOT analysis of project environments. Project Environments Project Risks A lot of project experience - Know-how - Internal technical support - Trouble history A lot of operation experience Good cracking margin Leveled-up LECs capability Enhanced local manufacturers capability Manufacturers good will for SK S W O T O Limited space - Lay-down area - Construction space Limited engineers W World-wide project rushes Heavy workload of eng g company and manufacturers High price and long delivery Unstable construction workers union Schedule - Limited engineering companies resources - Longer procurement cycles - Construction workers union Cost - Seller s market - Increasing trend of equipment & material cost - Labor cost increase Quality - Lack of qualified engineers due to heavy workload - Manufacturers poor workmanship - Short construction period 10
11 V. Project Execution Strategies To overcome several project risks, SK established the following project execution strategies. Project Risks Required Actions Project Execution Strategies Schedule - Limited engineering companies resources - Longer procurement cycles - Construction workers union - Cost - - Seller s market - Increasing trend of equipment & material cost - Labor cost increase Quick decision making Minimize engineering periods Secure qualified engineers Secure manufacturing periods Early buying is buying chief Early selection of FEED and EPC contractors Incentive systems for schedule acceleration Strong owner management team with single responsibility Early selection of FEED and EPC contractors for parallel execution Early procurement of equipment and materials Promote teamwork among all partners Quality - Lack of qualified Engineers due to heavy workload - Manufacturers poor workmanship - Short construction period Quality Management tools Engineering quality check Enhance manufacturers workmanship Maintain design consistency Reinforced Quality Management driven by SK 11
12 VI. Work Breakdown Structures Considering project scale, fast-track schedule and limited engineering resources of contractors, SK divided the process area into four sections. [Work Breakdown Structures] Process Section FEED Detailed Engineering Critical Procurement Non-Critical Construction RHDS, HPU FEC LEC-1 FEC LEC-1 LEC-1 RFCC, GDS, PRU FEC LEC-2 FEC LEC-2 LEC-2 Sulfur, Alkylation FEC LEC-3 FEC LEC-3 LEC-3 Utilities & Offsites LEC-4 LEC-4 - LEC-4 LEC-4 FEC : Front-end Engineering Contractor, Shaw Group. LEC-1 : Local Engineering Contractor-1, Daelim Industrial Co, Ltd. LEC-2 & 4 : SK Engineering & Construction LEC-3 : Hyundai Engineering & Construction 12
13 VI. Work Breakdown Structures Contracting scheme SK Energy Process Design Licensed Units RFCC/PRU : UOP RHDS : CLG HP : HTAS Alkylation : Dupont SAR : MECS GDS : Axens SRU : CB&I WGS : Belco Butamer/ SHP : UOP Non-licensed Units ARU /SWTU : Shaw Utility & Offsite:SKEC Basic Design By FEC Project Spec & Procedure Basic Engineering Procurement Service for Critical Equipment LEC-1 Daelim RHDS HP LEC-2 SKEC RFCC PRU/GDS EPC LEC-3 Hyundai Sulfur Alkylation LEC-4 SKEC Utilities Offsites Detailed Engineering Procurement Assistance for owner supplied items Procurement Services except owner supplied items Construction & Construction Management Pre-commissioning Commissioning Assistance 13
14 VII. Implementation of Project Execution Strategies Strong Owner-Centered Project Management Team Project Champion Project Director Start-up Director Tech. Support Team (Existing) PT-1 PT-2 PT-3 PCT PET ST-1 ST-2 ST-3 MT LEC-1 LEC-3 LEC-2 LEC-4 FEC PT : Project Team, PCT : Project Control Team ST : Start-up Team, MT : Maintenance Team PET : Process Engineering Team Well aligned organization with WBS Single responsibility for EPC and Start-up Quick decision No PMC (Project Management & Consulting) Group 14
15 VII. Implementation of Project Execution Strategies Early Selection of FEED Contractor and EPC Contractors To achieve fast track project goal, SK selected FEED contractor and EPC contractors at the beginning stage of project for parallel execution. FEED Contractor Selection EPC Contractor Selection Heavy workload of engineering industry Selection at the beginning stage of main process licensor design FEED work with piecemeal licensor Information Incentive plan for P&ID & Equipment datasheets Multiple contractors in view of project scale EPC contractor selection at the beginning stage of FEED work Co-work and parallel work with FEED contractor Priority on procurement work E : Lump-sum, Procurement : Cost + Fee Construction : Unit Price Basis Enable to purchase equipment & material in time for long lead equipment Minimize design period 15
16 VII. Implementation of Project Execution Strategies Early Procurement of Equipment and Material Due to tight market situation, in-time delivery of critical equipments was the key success factor for achieving project goals. Market Situation Seller s Market (2005 ~ 2007) - Price goes up as time goes - Delivery lead time getting longer - Difficult to get quotation - Difficult to secure shop space - Early buying is buying cheap Procurement Approach Early identification of long lead critical equipment using No.1 FCC project data at the project planning stage Securing shop space for RHDS reactors - LOI issue before licensor design Asia s Leading - Procurement Energy Company cost finalizing after design freezing Early input of licensor datasheets issue schedule - Negotiation meeting with licensor - Kick-off meeting for licensor design RFQ issue using licensor datasheets - P/O spec finalization during TBE - Incentive program for FEED contractor 16
17 VII. Implementation of Project Execution Strategies Teamwork among all partners Good teamwork was essential for successful completion of the project. There were eight licensors, one FEED, four EPC contractors and hundreds of suppliers. Active communication was effective to get their good will and willingly support. Shared Project Goals Project goals Project Execution Plan & Strategy Team Building workshops among FEC & LECs Asia s Leading Energy Company Support to Contractors Dispatch LEC engineers to support FEED work Introduce Incentive program for FEED work and construction schedule acceleration Top Management Support & etc. Top management Impact visit to key suppliers Invite local suppliers to construction site and entertainment 17
18 VII. Implementation of Project Execution Strategies Reinforced Quality Management driven by SK SK organized owner QA/QC team and prepared/implemented Quality Management Plan (QMP) to ensure one-through Start-up. Why concerns? QMP Resources & Tools Licensor Design & FEED Quality - Lack of man-power - Level of completeness Detailed Design - Capability - Parallel execution & hurry-up Equipment & Material - Heavy workload - Lack of quality mind Control Area Licensor Requirement Optimum Design Reliability Job spec Code & Regulation Purpose Guarantee condition Performance & cost effectiveness Operability & Maintainability Requirement by law or regulation Resources - SK maintenance people - 3 rd party - Process design & FEED review - Resident inspector at shop & field Tools - Licensor contract - Inspection & Test plan - Lessons learned from operation and maintenance Construction - CPU - Tight schedule Workmanship Defect-free workmanship 18
19 VII. Implementation of Project Execution Strategies [Overall Quality Management Map (Sample)] Licensor Requirement Optimum Design Reliability /Operability Maintainability JOB Spec. / Code / Regulation Workmanship Licensor Requirement Plant Performance Reliability / Operability Maintainability Implement Code & SK Spec. Prevent Errors/Mistakes Licensor Requirement - Plot plan/pfd/p&id - Key Equipment Data Sheet - Operation Manual Review Optimum Design - H&M Balance - Sizing Equipment & C/V - Process Hydraulic - Flare system - Review Interconnecting Piping System Verify Optimum Sizing -3 rd Party - Sizing Main Equipment - Thermal Rating - Hydraulic Implement Operation Experience - Reliability Study - Metallurgy(MSD) - Trouble History Review Design - Plot Plan - P&ID, - Equipment Data Sheet - ESD Scheme - Operation Manual Operability of Inter-Uints Implement Basic Design Criteria Update SK Spec. HAZOP STUDY (1 st & 2 nd ) Update Feed/Product Handling - Feed Supply System - Product Handling - Implement S/U & S/D Procedure - Off-Spec. Handling - Flare System Utility Balance & Review System Consumption & Audit Review Consistency Check By LEC Reliability Study Tools Licensor Agreement Design Data of Other Unit Design Data of Other Unit Experience of Operation/Maintenance Lessons Learned Item Trouble History SK STD Spec. Code Requirement Trouble History 19
20 VII. Implementation of Project Execution Strategies [Overall Project Master Schedule] Plan Actual Description Remarks Process Design ~ Basic Design ~ Detailed Design ~ Procurement (Critical Equipment) ~ Procurement (All Other Equipment) ~ Site Preparation ~ Construction ~ Pre-com & Comm ~ Commercial Operation ~ 20
21 VIII. Performance of the No.2 FCC Project SK achieved project goals in every aspect. Initial Goals vs. Achievement Description Plan Actual Remarks Schedule 35 Months 31 Months from the Start of FEED to Commercial Operation Quality On Stream Factor (*) Cost 2.0 Billion US$ 1.95 Billion US$ Safety No Serious Injury No Serious Injury (*) On Stream Factor : Actual treated quantities for 90 days after initial start-up divided by design capacity 21
22 VIII. Performance of the No.2 FCC Project It took 72 days from M/C to get on-specification production, which reduced 18 days compared to existing No.1 FCC project. - Mechanical Completion : Mar.31, 08 - On-Spec. Production of Hydrogen Unit : May 8, 08 - On-Spec. Production of RHDS Unit : May 31, 08 - On-Spec. Production of RFCC/GDS Units : June.11, 08 - On-Spec. Production of Alkylation Unit : June.12, 08 Asia s Leading Energy Company SK achieved each design capacity for main units on June.25, 08. SK achieved process performance for each unit as designed. 22
23 VIII. Performance of the No.2 FCC Project SK achieved all process performances as designed satisfying products specifications as shown below : Unit Performance Indicator Project Specification Actual Operation RHDS Capacity, BPSD 80,000 Max. 86,000 T-AR Total Sulfur, wt% Max. 0.5 < 0.5 T-AR MCR, wt% Max. 6.0 < 4.8 C5+ Product Yield, vol. % Min. 98 > 98 RFCC Capacity, BPSD 60,000 Max. 73,000 LCN RON Min. 91 > 91 Propylene Purity, vol.% Min > Propylene Yield, vol. % ~18 (Note) GDS Capacity, BPSD 30,000 Max. 36,000 T-LCN Total Sulfur, wtppm Max. 10 4~8 Alkylation Capacity, BPSD 18,000 Max. 20,000 Alkylate RON Min. 95 > 95 Note : However the unit was originally designed to make high propylene yield of 19.6 vol.%, the actual propylene yield has been set in the range of 14~18 vol.% flexibly to meet market situation adjusting reactor temperature and reformulating RFCC catalysts since initial start-up. 23
24 VIII. Performance of the No.2 FCC Project The plant has been running without shut-down since the initial start-up operation on June.12, 08. SK tried to find the maximum capacity of No.2 FCC plant using equipment design margins and optimizing operating conditions. As a result, we found that the plant could be operating with the following capacity without any equipment revamp: Asia s Leading Energy Company - RHDS Unit : Max. 86,000 BPSD (Design Capacity : 80,000 BPSD) - RFCC Unit : Max. 73,000 BPSD (Design Capacity : 60,000 BPSD) 24
25 IX. Key Success Factors 1 Strong Project Management 2 Early Engagement of FEC and LECs 3 Early Procurement of Critical Equipments 4 Teamwork with SK, FEC and LECs 5 Enhanced Quality Management System 6 Accurate and In-time Decision 25 54
26 X. Pictures of the No.2 FCC Plant Before Construction (Apr. 2006) 26
27 X. Pictures of the No.2 FCC Plant After Mechanical Completion (Mar. 2008) 27
28 Thanks a lot! 28
Roud table two Refinery & Petrochemical Integration
Roud table two Refinery & Petrochemical Integration CAIRO: 15 / 16 February 2016 Questions on the global view 1. Owner s STRATEGY: NOCs and IOCs do they have different drivers? 2. SAVE the PLANET: change
More informationGT-LPG Max SM. Maximizing LPG Recovery from Fuel Gas Using a Dividing Wall Column. Engineered to Innovate
GTC Technology White Paper GT-LPG Max SM Maximizing LPG Recovery from Fuel Using a Dividing Wall Column Engineered to Innovate GT-LPG Max SM Maximizing LPG Recovery from Fuel Using a Dividing Wall Column
More informationIGCC FUJIAN PROJECT. Dario Camozzi - Snamprogetti, Italy Andrea Baldelli - Snamprogetti, Italy Sun Hong Sinopec Ningbo Engineering Company, China
IGCC FUJIAN PROJECT Dario Camozzi -, Italy Andrea Baldelli -, Italy Sun Hong Sinopec Ningbo Engineering Company, China Gasification Technologies 2007 San Francisco, October 14-17, 2007 1 Fujian Refining
More informationEvaluation of Hydrogen Production at Refineries in China. The new UOP SeparALL TM Process. Bart Beuckels, UOP NV
Evaluation of Hydrogen Production at Refineries in China The new UOP SeparALL TM Process Bart Beuckels, UOP NV IChemE Gasification Conference March 12, 2014 Rotterdam, the Netherlands 1914-2014 A Century
More informationProcess Gas Monitoring In Petroleum Refineries
Application Data Sheet ADS 103-2911AA01 July, 2005 Application Data Process Gas Monitoring In Petroleum Refineries APPLICATION Emerson offers several Rosemount Analytical gas analyzer technologies to meet
More informationProcess Economics Program
IHS Chemical Process Economics Program Report 289 New Routes to Styrene and para-xylene By Dipti Dave IHS Chemical agrees to assign professionally qualified personnel to the preparation of the Process
More informationHeavy Oil Upgrading Environment Market and Technology
2008 Rice RGF Global - Heavy E&C Forum Oil Upgrading Environment: Markets & Technology Eleventh Annual Forum Session September 9, 2008 Heavy Oil Upgrading Environment Market and Technology John D. Elliott
More informationOn-purpose Olefins through CATOFIN -CATADIENE Technologies
On-purpose Olefins through CATOFIN -CATADIENE Technologies Global Propylene & Derivatives Summit Sunil Panditrao Technology Manager CB&I Agenda Cracker Feedstock Trends Commercial Routes to Propylene CATOFIN/CATADIENE
More informationAbstract Process Economics Program Report No. 88A ALKYLATION FOR MOTOR FUELS (February 1993)
Abstract Process Economics Program Report No. 88A ALKYLATION FOR MOTOR FUELS (February 1993) Alkylation has become an important refinery process because of increasing demand for high octane and low vapor
More informationNo project is too big, too small, too simple or too complex
ROTARY No project is too big, too small, too simple or too complex 2 Our Track Record Offsite & Utilities Client Project Title Year of Completion United Arab Emirates, Fujairah ENOC Processing Company
More informationADVANCED PROCESS CONTROL
CHAPTER-11 ADVANCED PROCESS CONTROL Chapter No 11 Page No 1 INTRODUCTION The traditional control philosophy, what is called instrumentation in the chemical industries, is based on single loop control (sometimes
More informationICIS Margin Polystyrene (PS) Europe Methodology
Copyright 2014 Reed Business Information Ltd. ICIS is a part of the Reed Elsevier plc group ICIS Margin Polystyrene (PS) Europe Methodology This document is intended to provide methodology support for
More informationBiorefineries Workshop
Biorefineries Workshop - 2010 Renewable feedstock co-processing in oil refining / petrochemical units Luiz Fernando Leite UFRJ Firjan Convention Center Rio de Janeiro November 10-12, 2010 Biofuels & Bioproducts
More informationA World of Solutions Visit Product Storage Terminals for Bulk Liquids
A World of Solutions Visit www.cbi.com Product Storage Terminals for Bulk Liquids United Arab Emirates The most global experience of any tank company CB&I has more than eight decades of experience designing
More informationICIS Margin Polyethylene (PE) Asia Methodology
Copyright 2015 Reed Business Information Ltd. ICIS is a part of the Reed Elsevier plc group ICIS Margin Polyethylene (PE) Asia Methodology This document is intended to provide methodology support for customers
More informationFIRST ISSUE. Logistics master planning. Risk Based Process Safety. CDU preheat train performance improvement. PTT Energy Solutions. Issue 1, June 2012
PTT Energy Solutions Issue 1, June 2012 Energy optimization study IRPC Logistics master planning New refinery configuration and feasibility study Risk Based Process Safety CDU preheat train performance
More informationImproved Amylene Alkylation Economics
Improved Amylene Alkylation Economics J. Randall Peterson David C. Graves Ken Kranz David M. Buckler STRATCO, Inc. INTRODUCTION This paper discusses recent STRATCO research showing how amylenes can be
More informationFundamentals of Refinery Catalytic Processes
Page 1 of 7 Introduction Fundamentals of Refinery Catalytic Processes The success of every company depends of each employee s understanding of the business s key components. Employee training and development
More informationPetrochemical Complex Integration Feasibility Studies - an Investment that pays out
Petrochemical Complex Integration Feasibility Studies - an Investment that pays out Frederik Baars Global Petrochemicals Summit, Lisbon, 16 November 2016 2014 Fluor. All rights reserved. FLUOR is a registered
More informationTraining and Development
Page 1 Training and Development The success of every company depends of each employee's understanding of the business's key components. Employee training and development will unlock the companies' profitability
More informationRole of PDH in Asian Propylene Supply Market
Role of PDH in Asian Propylene Supply Market Chul-Jin (CJ) Kim CEO April 19, 2017 Agenda 1. SK Introduction 2. Asian Propylene Market 3. PDH as on-purpose process 4. Our Values to Customers 5. Key takeaways
More informationIntroduction to Chemical Plant Design Life Cycle
Introduction to Chemical Plant Design Life Cycle Process Safety Consideration Chemical Plant Design A project/endeavour/task to determine the structure of a process to produce a product in the way that
More informationPetro-Canada Refinery Conversion Project. Presentation to AACE, Calgary. November 9, 2005
Petro-Canada Refinery Conversion Project Presentation to AACE, Calgary November 9, 2005 TLM MOMENT All Losses are important and represent an opportunity to improve Health Safety Environmental Quality BUILDING
More informationRole of Sustainable Mega Projects on the Future of Iraq Economy & Human Capital
Role of Sustainable Mega Projects on the Future of Iraq Economy & Human Capital Iraq Energy Forum 2018 Dr Husain Al-Chalabi [ IEI Fellow] Role of Sustainable Mega Projects on the Future of Iraq Economy
More informationReport No. 29 ETHYLENE. August A private report by the PROCESS ECONOMICS PROGRAM I STANFORD RESEARCH INSTITUTE MENLO PARK, CALIFORNIA
Report No. 29 ETHYLENE by SHIGEYOSHI TAKAOKA August 1967 A private report by the PROCESS ECONOMICS PROGRAM I STANFORD RESEARCH INSTITUTE MENLO I PARK, CALIFORNIA CONTENTS 1 INTRODUCTION........................
More informationHydrogen for the NWR Upgrader by Lurgi MPG Technology A challenging Project
Hydrogen for the NWR Upgrader by Lurgi MPG Technology A challenging Project Washington DC 29.10.2014 l Max-Michael Weiss, Stefan Walter l Air Liquide Global E&C Solutions Germany GmbH, Frankfurt General
More informationRefining. Capability & Experience
Refining Capability & Experience Local delivery, global resources WorleyParsons provides a comprehensive range of refining services developed over 60 years of delivering grassroots, revamp, and expansion
More informationWWT Two-Stage Sour Water Stripping
WWT Two-Stage Sour Water Stripping Improve performance of sulfur recovery units ben efits The Chevron WWT Process is a two-stage stripping process which separates ammonia and hydrogen sulfide from sour
More informationFront End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track
progetti Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track By Armando Bianco, Engineering Manager, Eniprogetti Global Conference on EPC Contract & Project
More information50 Years of PSA Technology for H2 Purification
50 Years of PSA Technology for H 2 Purification 1 50 Years of PSA Technology for H2 Purification The first industrial application of Pressure Swing Adsorption (PSA) went on stream in 1966 at a Union Carbide
More informationWhiting Business Unit
Whiting Business Unit ENVIRONMENTAL STATEMENT FOR YEAR 2015 (Review of Y2014 performance) Introduction Recognizing the complex nature of petroleum refining operations and to ensure that we meet our stated
More informationHEAVY CRUDE UPGRADING: AN OPTION FOR GASIFICATION
/ HEAVY CRUDE UPGRADING: AN OPTION FOR GASIFICATION Luigi Bressan Foster Wheeler Italiana Corporation Michael J. McGrath - Foster Wheeler USA Corporation Gasification Technologies Council Conference San
More informationA - CONTACTOR REACTOR SHELL B - TUBE BUNDLE ASSEMBLY C - HYDRAULIC HEAD D - MOTOR E - IMPELLER F - CIRCULATION TUBE
STRATCO Contactor TM Reactor Performance Upgrade: Alkylation Tube Insert Technology Pam Pryor, STRATCO, Inc. Randy Peterson, STRATCO, Inc. Tom Godry, UOP LLC Yung Lin, UOP LLC The current trend towards
More informationProcess Economics Program
IHS Chemical Process Economics Program Report 287 Bio-Based Aromatics By Michael Arné IHS Chemical agrees to assign professionally qualified personnel to the preparation of the Process Economics Program
More informationResearcher, 1(2), 2009, Energy Integration Of Crude Distillation Unit Using Pinch Analysis
Energy Integration Of Crude Distillation Unit Using Pinch Analysis K.R. AJAO (Ph.D) Department of Mechanical Engineering, University of Ilorin, Ilorin, Nigeria e-mail: ajaomech@unilorin.edu.ng H. F. Akande
More informationNovember Nanticoke Refinery Reduction plan summary (OR 455/09)
S. Kuntz Nanticoke Refinery Manager 519.587.4992 November 2015 Nanticoke Refinery Reduction plan summary (OR 455/09) Provincial regulations set out requirements for business owners to inform Ontarians
More informationMeasurement made easy
ABB MEASUREMENT & ANALYTICS WHITE PAPER Hydrofluoric acid alkylation (HFU) unit optimization The use of robust pre-calibrated on-line analyzer technology for the measurement of HF acid purity This white
More informationPROCESS ECONOMICS PROGRAM
PROCESS ECONOMICS PROGRAM SRI INTERNATIONAL Mmlo Park. Cditomir 94025 Abstract Process Economics Program Report 121 B WORLD PETROCHEMICAL FEEDSTOCKS: 19792010 (May 1993) Wtxfd Pe&ochemica/ Feed&o&s: 7970-2070
More informationEngineering Company Role on Energy Projects
Engineering Company Role on Energy Projects The Grand Hotel, Taipei, 2007 Sept 13, 2007 Contents 1. Chiyoda as Eng g Company 2. Energy Supply and Demand 3. Trend & Nature of Production Facilities 4. Economy
More informationENI REFINING & MARKETING SANNAZZARO GASIFICATION PLANT PROJECT UPDATE AND START UP EXPERIENCE
Gasification Technologies 2006 Washington, DC October 1-4, 2006 ENI REFINING & MARKETING SANNAZZARO GASIFICATION PLANT PROJECT UPDATE AND START UP EXPERIENCE Dario Camozzi -, Italy Raffaella Lucarno -
More informationSyngas/Methanol to Olefins
Petrochemical Technology Renaissance Syngas/Methanol to Olefins R. J. Chang, Global Managing Director IHS Chemical Process Economics Program March 27 & 28, 2014 Houston, TX USA The Rise of Syngas - the
More informationKeys to Excellence in the Practice of Process Engineering. An overview by Scott D. Love, P.E. October 2016
Keys to Excellence in the Practice of Process Engineering An overview by Scott D. Love, P.E. October 2016 Outline What is excellence? How do I learn about my process? Learning examples Summary Questions?
More informationChanging US Crude Oil Imports are Driving Refinery Upgrades, Creating Opportunities
1 Changing US Crude Oil Imports are Driving Refinery Upgrades, Creating Opportunities Christopher Buehler, Ph.D., P.E. Praveen Gunaseelan, Ph.D. Crude Oil Quality Association October 22, 2009 Meeting Houston,
More informationPerformance Evaluation of Deethanizer Column Using Real Time Optimization
Performance Evaluation of Deethanizer Column Using Real Time Optimization Renanto Handogo, Indra Darmawan, Fadillah Akhbar Marsha, Juwari Department of Chemical Engineering Institut Teknologi Sepuluh Nopember
More informationBASED ON EXPERIENCE TGE GAS ENGINEERING EVOLUTION OF SAFETY DESIGN FOR CRYOGENIC TANKS REVAMP VS. NEW BUILT
BASED ON EXPERIENCE TGE GAS ENGINEERING EVOLUTION OF SAFETY DESIGN FOR CRYOGENIC TANKS REVAMP VS. NEW BUILT Page 1 CONTENT Overview on the services and experience of TGE Gas Engineering GmbH Examples of
More informationCHALLENGES FACING RUSSIA IN THE EFFORTS TO MODERNIZE THE PETROCHEMICAL AND GAS CHEMICAL INDUSTRY
OAO VNIPIneft CHALLENGES FACING RUSSIA IN THE EFFORTS TO MODERNIZE THE PETROCHEMICAL AND GAS CHEMICAL INDUSTRY V.M. Kapustin OAO VNIPIneft General Director, Gubkin Russian State Oil & Gas University, Head
More informationPilot Scale Biorefinery for Sustainable Fuels from Biomass via Integrated Pyrolysis and Catalytic Hydroconversion
8 th Task Meeting, Chicago, Illinois, 4 6 October, 2010 Pilot Scale Biorefinery for Sustainable Fuels Biomass via Integrated and Catalytic Hydroconversion Steve Lupton UOP LLC, A Honeywell Company IEA
More informationJereh-Primus GTL Solution
JEREH RODUCT ROFILE Index-216.3-V1/EN Jereh-rimus GTL Solution Gas Monetization and Flare Solution using STG+ Technology Simple Robust Economical www.jereh.com www.primusge.com gastoliquid@jereh.com WORLD
More informationOpportunities in a Globalising World: Strategies for Europe
Opportunities in a Globalising World: Strategies for Europe IHS Markit WPC Thomas Van De Velde March 21st, 2018 Borealis at a glance 2 nd largest polyolefin producer in Europe Head office in Vienna, Austria
More informationJOB SPECIFICATION FOR ROTARY PUMP (SCREW TYPE)
ENGINEERS tg,e.g tale% W INDIA LIMITED Goo e/ kw UndelOom JOB SPECIFICATION FOR A223-041-16-45-SP-5050, Rev.A Page 1 of 6 JOB SPECIFICATION FOR ROTARY PUMP PROJECT : UNIT : CLIENT : CONSULTANT : PDA REVAMP
More informationMethanol to Olefins. IOCL Conclave February 7, 2014
Methanol to Olefins A Pillar of Capacity Additions in China, but Does MTO have a Role in India? IOCL Conclave February 7, 2014 UOP LLC Des Plaines, Illinois, USA 2014 UOP LLC. All rights reserved. Topics
More informationGLOBAL EXPRESSION OF INTEREST ( EOI ) For CONSULTANCY SERVICES TO PROVIDE BASIC ENGINEERING AND PROCESS FOR LUBE OIL BLENDING PLANT
GLOBAL EXPRESSION OF INTEREST ( EOI ) For CONSULTANCY SERVICES TO PROVIDE BASIC ENGINEERING AND PROCESS FOR LUBE OIL BLENDING PLANT At BHARAT PETROLEUM CORPORATION LTD,Uran, Distt. Raigarh, Maharashtra.,India
More informationNanochem GuardBed. by Matheson In Partnership with SulfaTrap, LLC
Nanochem GuardBed by Matheson In Partnership with SulfaTrap, LLC Content Outlook Features & Data Examples Sales reference Data Sheet- Questionnaire Next steps 2 Outlook Defining the Problem Over 15 Different
More informationDevelopment of Technology for Advanced Utilization of Hydrogen from By-product Gas of Steelmaking Process
Technical Review UDC 669. 1. 054. 8 Development of Technology for Advanced Utilization of Hydrogen from By-product Gas of Steelmaking Process Ken-ichiro FUJIMOTO* Kimihito SUZUKI 1. Introduction Huge volumes
More informationBitumen Upgrader Residue Conversion to Incremental Synthetic Fuels Products
Bitumen Upgrader Residue Conversion to Incremental Synthetic Fuels Products Technical Paper Expander Energy Inc. Jan Wagner, P.Eng. Steve Kresnyak, P.Eng. Final Issue June 19, 2013 Introduction During
More informationPROCESS MOISTURE ANALYZERS Measuring moisture in gas or HC liquids in hazardous areas
PROCESS MOISTURE ANALYZERS Measuring moisture in gas or HC liquids in hazardous areas EExd Construction Safety by containment PROCESS MOISTURE ANALYZER Channel 1 dew-point & pressure sensor Through-glass
More informationHydrogen is a particularly
Optimised hydrogen production by steam reforming: part I Modelling optimisation of process and design parameters for minimising natural gas consumption in hydrogen production by steam reforming Sanke Rajyalakshmi,
More informationThe Uhde STAR process Oxydehydrogenation of light paraffins to olefins
The Uhde STAR process Oxydehydrogenation of light paraffins to olefins A company of ThyssenKrupp Technologies Uhde ThyssenKrupp 2 Table of contents 1. Company profile 3 2. Introduction 4 2.1 Steam reforming
More informationGlobal Gasoline, Global Condensate and Global Petrochemical Markets to 2020 and How much naphtha will end up in gasoline blending?
Study Prospectus Nexus - The Interaction Between: Global Gasoline, Global Condensate and Global Petrochemical Markets to 2020 and 2025 Can I export more naphtha? Should I build a splitter? Should I build
More informationCOAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee
COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract
More informationptq MEDIA DETAILS ptqq revamps gas catalysis
PTQ supplement Supplement to PTQ MEDIA DETAILS 2018 Q2 catalysis gas revamps REFINING PETROCHEMICALS SPECIAL FEATURES HEAT TRANSFER & FLUID FLOW MASS TRANSFER & SEPARATION PRINT ADVERTISING ONLINE ADVERTISING
More informationCompetitiveness of the EU Chemical Industry, a Key sector in the Refining Value Chain José Mosquera, Director Industrial Policy
Competitiveness of the EU Chemical Industry, a Key sector in the Refining Value Chain José Mosquera, Director Industrial Policy Second meeting of the EU Refining Forum 27 November 2013, Brussels 1 Profile
More informationChevron Makes History with JMJ s Incident and Injury-Free Safety Approach, Refurbishing its El Segundo Refinery with No Recordable Injuries
Working with JMJ, we achieved an extraordinary safety result no contractor recordable injuries despite conditions that would predict a significant level of recordable injury. JMJ helped us integrate the
More informationBASED ON EXPERIENCE TGE GAS ENGINEERING EPC EXECUTION OF BOREALIS ETHANE TANK PROJECT
BASED ON EXPERIENCE TGE GAS ENGINEERING EPC EXECUTION OF BOREALIS ETHANE TANK PROJECT www.tge-gas.com 24/10/2016 Page 1 CONTENT Overview on the Services and Experience of TGE Gas Engineering GmbH Project
More informationNovember Nanticoke Refinery Reduction plan summary (OR 455/09)
R. Henderson Nanticoke Refinery Manager 519.587.4992 November 2014 Nanticoke Refinery Reduction plan summary (OR 455/09) Provincial regulations set out requirements for business owners to inform Ontarians
More informationProblems at the Cumene Production Facility, Unit 800
Problems at the Cumene Production Facility, Unit 800 Background Cumene (isopropyl benzene) is produced by reacting propylene with benzene. During World War II, cumene was used as an octane enhancer for
More informationLignin conversion into bio-based chemicals
Engineering Conferences International ECI Digital Archives BioEnergy IV: Innovations in Biomass Conversion for Heat, Power, Fuels and Chemicals Proceedings Spring 6-12-2013 Lignin conversion into bio-based
More informationNEW GC-16 IN WEST KUWAIT MATERIAL REQUISITION FOR LEVEL GAUGE TABLE OF CONTENTS
TABLE OF CONTENTS Sh. 2 of 16 1 INTRODUCTION 4 1.1 Purpose 4 1.2 Definitions 4 1.3 Acronyms 4 1.4 Codes and Standard 5 1.5 Environmental Condition 6 1.6 Language 6 1.7 Units of Measurement 7 1.8 General
More informationSECTION 3.0 DEFINITION OF TERMS AND ABBREVIATIONS
SECTION 3.0 DEFINITION OF TERMS AND ABBREVIATIONS 3.1 Terms... 1 3.2 Symbols and Abbreviations... 2 September 2010 API Recommended Practice 571 3-1 3.1 Terms 3.1.1 Austenitic a term that refers to a type
More informationDraft for an Appendix O Cost Structures
CSPBankability Project Report Draft for an Appendix O Cost Structures to the SolarPACES Guideline for Bankable STE Yield Assessment Document prepared by the project CSPBankability funded by the German
More informationTurning Engineering Excellence into Engineering Excellence³. The perfect answer to the new world wide challenges in EPC Contracting
Turning Engineering Excellence into Engineering Excellence³ The perfect answer to the new world wide challenges in EPC Contracting - Company History Important Milestones Polymer Chemicals 1921 Friedrich
More informationOPTI. October 2002 SHELL GLOBAL SOLUTIONS CANADA INC.
SHELL GLOBAL SOLUTIONS October 2002 2 SHELL GLOBAL SOLUTIONS Gasification Technologies 2002 Integrated Oil Development Using OrCrude Upgrading and Shell Gasification Process Jim Arnold Phil Rettger Max
More informationPERP/PERP ABSTRACTS Styrene/Ethylbenzene
PERP/PERP ABSTRACTS 2009 Styrene/Ethylbenzene Process Technology (including New Developments such as Exelus' ExSyM Process via Methanol and Toluene), Production Costs, and Regional Supply/Demand Forecasts
More informationOil Markets, Midstream and Downstream
ENERGY Oil Markets, Midstream and Downstream Enhance your decision making with the power of IHS Markit integrated solutions for Oil Markets, Midstream and Downstream. Energy with IHS Markit is the leading
More informationPetrochemical Processing
Petrochemical Processing 2 Contents. 3 Introduction 4 Technology Outstanding process technology Feed flexibility Cracking furnace technology 5 Perfection Turn key perfection Global alliances 6 Responsibility
More informationShale Gas Revolution
Dr. Kuhlmann International Shale Gas Revolution Its Impact on the Chemical Industry and Global Shipping Trends 7 th Chemical & Product Tanker Conference London, March 18 th, 2015 Chemical value chain impacts
More informationStratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL
Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL is a service, general trading
More informationJapanese ODA Loan. Ex-Ante evaluation
Japanese ODA Loan Ex-Ante evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Matarbari Ultra Super Critical Coal-Fired Power Project (I) Loan Agreement: June 16, 2014 Loan
More informationMinimize Sulfur Pit Vent Contribution to Stack Emissions
Minimize ulfur Pit Vent Contribution to tack Emissions Grant Qui, P.E. Excel Paralubes - ConocoPhillips 2800 Old panish Trail 3008 MO Westlake, LA 70609 Houston, TX 77079 Al Keller Refining Technical ervices
More informationOPERATION GOOD PRACTICE IN PYGAS HYDROGENATION OPERATIONS THROUGH ADVANCED PROCESS CONTROL
GOOD PRACTICE I PYGAS HYDROGEATIO OPERATIOS THROUGH ADVACED PROCESS COTROL Advanced Process Control (APC) offers a solution to syematize the implementation of be practices to generate subantial benefits.
More informationOur strategy : Our mission is to provide consulting services and technical support throughout realization of projects in refining and
ООО INKO-TEK was established in December 2011 as a full cycle company, providing consulting services and technical support for projects in refining and petrochemical industry, from the stage of project
More informationReport No. 32 HYDROGEN. December A private report by the PROCESS ECONOMICS PROGRAM STANFORD RESEARCH INSTITUTE PARK, CALIFORNIA
Report No. 32 HYDROGEN by RICHARD G. DENNEY December 1967 A private report by the PROCESS ECONOMICS PROGRAM STANFORD RESEARCH INSTITUTE I I MENLO PARK, CALIFORNIA CONTENTS 1 2 3 4 5 6 INTRODUCTION....
More informationAMERICAN PETROLEUM INSTITUTE API RP 581 RISK BASED INSPECTION METHODOLOGY BALLOT COVER PAGE. Title: MODIFICATION OF API 581 CARBONATE CRACKING
AMERICAN PETROLEUM INSTITUTE API RP 581 RISK BASED INSPECTION METHODOLOGY BALLOT COVER PAGE Ballot ID: Title: Purpose: MODIFICATION OF API 581 CARBONATE CRACKING Modification of the damage factor to include
More informationBiobased materials and fuels via methanol The role of integration
Biobased materials and fuels via methanol The role of integration Joint Task 33 & IETS workshop at Göteborg, Nov2013 Ilkka Hannula VTT Technical Research Centre of Finland 2 Gasification and Gas Cleaning
More informationPetrochemical Industries in Egypt
Federation of Egyptian Industries Chamber of Chemical Industries Petrochemical Industries in Egypt Present and Future Dr. Sherif El-Gabaly Chairman, Chamber of Chemical Industries 2015 1 Chemical / Petrochemical
More informationCopyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1
Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different
More informationLight and Heavy Naphtha: International Market Analysis. Prospectus
Light and Heavy Naphtha: International Market Analysis Prospectus Contents The Market...2 Objective...3 Key Questions...4 Scope of work...5 Deliverables...6 Methodology... 7-8 Table of Contents... 9-11
More informationInvestment Development in Dungquat Economic Zone. Da Nang July 31, 2009
Investment Development in Dungquat Economic Zone Home of Vietnam s first Oil refinery Da Nang July 31, 2009 IN THE ACCELERATED GROWTH Dung Quat Economic Zone is designated for diversified investment fields,
More informationGetting Value Out Of Reconciled Data Using PI and Sigmafine. Ales Soudek Business Development
Getting Value Out Of Reconciled Data Using PI and Sigmafine Ales Soudek Business Development Outline What is the PI System? What is Reconciled Data/Sigmafine? Using PI to Manage Your Assets What Value
More informationLSU Natural Gas Conference
LSU Natural Gas Conference Presented by: Bob Purgason VP Gulfcoast Region Williams Companies Introduction Structural shift in natural gas pricing The crude to gas ratio: A critical relationship for NGL
More informationPERP Program Ethylene Oxide/Ethylene Glycol New Report Alert
PERP Program Oxide/ New Report Alert February 2006 Nexant s ChemSystems Process Evaluation/Research Planning program has published a new report, Oxide/ (04/05-5). To view the table of contents or order
More informationEnvironmental Improvement Plan. Sohar Refinery
Environmental Improvement Plan Sohar Refinery Feb 2014 Page 1 of 18 Waste Water Treatment Plant Improvements Background The treatment of the waste water of the Refinery was malfunctioning for a long period.
More informationPublished on Market Research Reports Inc. (https://www.marketresearchreports.com)
Published on Market Research Reports Inc. (https://www.marketresearchreports.com) Home > Nigeria Oil and Gas Market Insight and Outlook Report (H2 2015) - Forecasts of Exploration, Production, Refinery,
More informationPIMPRAPA KAROONMAKPHOL PTT GLOBAL CHEMICAL GROUP
PIMPRAPA KAROONMAKPHOL PTT GLOBAL CHEMICAL GROUP PTT GLOBAL CHEMICAL GROUP PTT GLOBAL CHEMICAL GROUP REFINERY AROMATICS OLEFINS POLYMERS EO-BASED PERFORMANCE GREEN CHEMICALS HIGH VOLUME SPECIALTIES [HVS]
More informationBrownfield Projects. Equinox Engineering
BROWNFIELD PROJECTS Equinox Engineering Brownfield Projects Equinox Engineering Ltd. is a world class provider of EPCM services to the global oil and gas marketplace. Founded in 1997, Equinox has successfully
More informationCOMMONLY ASKED QUESTIONS REGARDING SYNFUELS TECHNOLOGY
COMMONLY ASKED QUESTIONS REGARDING SYNFUELS TECHNOLOGY 1. What are the key benefits of your technology not applying the Fischer Tropsch process? What are the limitations of FT that your technology overcomes?
More informationMATERIALS OF CONSTRUCTION FOR PROCESS EQUIPMENT AND PIPING SYSTEMS
MATERIALS OF CONSTRUCTION FOR PROCESS EQUIPMENT AND PIPING SYSTEMS SECTOR / ENGINEERING NON-TECHNICAL & CERTIFIED TRAINING COURSE Appropriate material selection is the cornerstone of pressure equipment
More informationProcess Data Descriptions for the production of synthetic organic materials
Process Data Descriptions for the production of synthetic organic materials Input data for the MATTER study L.A.J. Joosten 98028 Department of Science, Technology and Society (Natuurwetenschap en Samenleving)
More informationUOP Selexol TM Technology Applications for CO 2 Capture
UOP Selexol TM Technology Applications for CO 2 Capture 3rd Annual Wyoming CO2 Conference June 23rd and 24th 2005 2009 UOP LLC. All rights reserved. Typical Gasification Complex Typical Raw Syngas H2 30-50%
More informationINDIAN OIL CORPORATION LTD Panipat Naphtha Cracker, Panipat, India
INDIAN OIL CORPORATION LTD Panipat Naphtha Cracker, Panipat, India Pre-Feasibility Report for Expansion of NCU,MEG,HDPE & PP Units and Catalyst Manufacturing unit JUNE 2016 1 CONTENTS 1. INTRODUCTION 3
More information