Retro-Commissioning & Commissioning Building Envelope Systems to Reduce Health Risks & Improve IAQ: What We Have Learned To Date
|
|
- Gyles Golden
- 6 years ago
- Views:
Transcription
1 Retro-Commissioning & Commissioning Building Envelope Systems to Reduce Health Risks & Improve IAQ: What We Have Learned To Date William A. Turner M.S., P.E. - President Steven M. Caulfield, P.E., CIH - Vice President Brian Decker, EIT - Mechanical Engineer Frederick McKnight, EIT - Chief Indoor Air Quality Engineer David Hart, NCARB - Project Architect Turner Building Science, LLC Loren Belida, AIA - Senior Vice President - Architecture The H.L. Turner Group Inc. Synopsis During , Turner Building Science, LLC had the opportunity to retro-commission and commission four moderately-sized building envelopes. These facilities included three mediumsized schools, and one medium-sized, multiple-story office facility. In the retro-commissioning situations, the diagnostic evaluations included observations of existing drawings; on-site visual observations of wall, roof, and floor/slab; actual construction during and after intrusive disassembly; infrared thermography observations; field modified ASTM moisture intrusion window system testing; ASTM concrete moisture testing; and standardized mold/fungi source testing procedures. In the new construction situation, commissioning included visual observations during the construction process, and other testing/evaluation techniques as warranted. In all of the buildings, careful evaluation of the HVAC system design and control functions, and the resulting building shell (envelope) pressures were also noted. The envelope retro-commissioning services were conducted in buildings where historically poor performance of the building envelope and possible health concerns were the drivers for the owner s decision to retro-commission the facilities. In two of the cases, the technical results determined that both mold remediation under containment and major envelope re-construction were warranted. The technical results were used to formulate major reconstruction plans for the building envelope in order to improve both long-term energy efficiency and building performance, and to reduce possible health risk within the facilities. The resulting successful reconstructions should allow the building envelope to perform well for another thirty to fifty years of service, and significantly reduce energy consumption due to envelope loss. Within this paper and during our presentation, we will summarize the testing procedures used, give examples of what was learned from the procedure, and explain how the results were used to develop a suitable corrective action plan and budget for reconstruction. In the newly constructed facility, envelope commissioning was simply used as part of the overall building HVAC Commissioning to confirm whether the owner was being delivered the design intent of the envelope design, and to develop a corrective action plan if warranted. Turner et al: Retro-Commissioning & Commissioning Building Envelope Systems to Reduce Health Risks Copyright By TBS, 2005, Materials May Be Used By Permission Only With Credits To Turner Building Science, LLC
2 INTRODUCTION Turner Building Science, LLC has enjoyed the opportunity of providing retro-commissioning and commissioning services for several buildings located in the climate of the Northeastern United States. (Ref. #1) The Northeast part of the United States can be an especially challenging location for design and construction activities, as it is considered to be cold and damp by professional literature; however, it also frequently experiences sometimes-lengthy summer conditions, very similar to a hot and humid climate. This paper and presentation will focus on various building envelope conditions we have found to be important while retro-commissioning and redesigning a failed school located in Central Massachusetts, and a new school located in Central New Hampshire. Lessons learned from both paper analysis and field performance testing commissioning activities will be presented. In the retro-commissioning case, the focus was to understand failure modes, design suitable long-term fixes, and to validate the expected performance of those fixes. In the new school, commissioning and performance acceptance testing activities were focused on the owner s goal to receive a building envelope that was likely to perform as well as intended in the climate where it is located. The ultimate goal, in both cases, was to provide a building with envelope systems that would both reduce health risks and improve Indoor Air Quality for the occupants, while ensuring longterm value for the owner. We believe that these goals are an important part of creating a sustainable building envelope. TYPES OF BUILDING ENVELOPE SYSTEM EVALUATIONS THAT CAN BE PERFORMED In the retro-commissioning or new construction situations, there are several types of building envelope paper calculations and field diagnostic evaluations that we are aware of that can be performed. These analyses can be done after the fact to determine failure modes or performance, or during design review (before construction) to predict expected building performance. Paper Calculation Reviews or Tools That We Have Found Useful: Building envelope review topics that we have currently determined to be useful activities include: Dew Point / Vapor Pressure Review: Predicting the vapor pressure relationships and location of dew point occurrences in wall, roof, or floor assemblies in occupied facilities, with significant indoor winter humidity, or significant outdoor summer humidity. Calculation tools include calculations found in American Society of Heating Refrigerating and Air Conditioning Engineers, Inc. (ASHRAE) Fundamentals publications. (Ref.# 2) Exterior Drainage Plane / Wind Barrier Review: Design drawing review for continuity and constructability of exterior drainage planes intended to keep wind driven rain (liquid water) out of the thermal envelope, and reduce the impact of liquid water / wind (infiltration) on the thermal envelope layers. 2
3 Interior Air Barrier / Vapor Barrier Review: Design drawing review for the continuity and constructability of interior air / vapor barriers designed to keep interior moisture out of the thermal envelope, and reduce the impact of interior moisture / air leakage (exfiltration) on the thermal envelope layers. Exhaust Re-entrainment Review (Micro Climate Analysis): Design drawing review and calculations, if needed, for predicting the expected impact of local point source emission sites, and exhaust locations on air intake locations (including operable windows and doors). Calculation Tools include calculations found in ASHRAE Fundamentals publications. (Ref.# 3) Thermal Performance Continuity Review: Design drawing review for predicting the expected continuity and thermal performance of a wall, roof, and below grade assemblies are based on actual conveyed construction details. This review also includes review of thermal breaks and vapor barriers in all earth contact areas. This is especially important with building envelopes that are expected to be high performance, and which include metal (conductive) structural components. Calculation tools include calculations found in ASHRAE Fundamentals publications, and commercial software. (Ref. #4) Thermal Performance Peak / Peak Occupancy Air Conditioning Impact Review: Design drawing review for predicting the expected impact of planned or sometimes unplanned occupancy periods, combined with low angle solar gain and glass (fenestration) design, on HVAC peak room cooling loads at maximum winter, low sun impact angles. Calculation Tools include calculations found in ASHRAE Fundamentals Publications, Commercial software, and our custom Advantage Displacement Ventilation Software. (Ref. #5, Ref. #6) Building Envelope Pressure Review: Design drawing review for predicting the expected overall long-term average building pressure relationship between the inside and outside of the building envelope under summer, swing season, and winter conditions. Building Envelope Air Leakage Review: Design drawing review for predicting the expected building air leakage rate and air leakage sites due to expected stack effect or planned pressure levels. (Ref. #7) Roof Ice Dam Review: Design drawing review for predicting the likely occurrence of roof snow melt from interior exfiltration or winter solar roof gain and subsequent ice damming in vented or un-vented roof assemblies. This is most applicable on roofs where microclimates and building roof designs are expected to significantly impact snow accumulation on a given Southern or Northern roof exposure. Useful Field Performance Evaluations: Performance testing (field verification) for various building envelope problems which we have most recently found to be useful include: Infrared Imaging of Buildings as Found: Determining the thermal (conductive) performance of roof and wall assemblies. There is an ASTM method for this procedure. (Ref. #8) 3
4 Infrared Imaging with Building Pressure Manipulation: Determining the air leakage sites in roof and wall assemblies. There is an ASTM method for using fan pressurization equipment to manipulate building pressures. (Ref. #9) Smoke Tracer Testing with Building Pressure Manipulation: Determining the air leakage sites in roof and wall assemblies utilizing theatrical fog with and without building pressure manipulation. There is a draft ASTM method for using this technique. (Ref. #10) Infrared Imaging and Visual Observations to Locate Moisture Infiltration/Leakage into the Thermal Envelope: Under certain defined conditions, IR Thermography, conducted indoors or outdoors with a uniformly heated interior space, has proven useful in locating currently damp wall assemblies that would be otherwise hard to find. Visual observations for signs of past water damage can also be useful. Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, Curtain Walls, and Wall Assemblies: Determining the actual conditions for water leakage, and utilizing intrusive disassembly to locate actual water leakage sites have proven invaluable for problem solving in existing structures. There is an ASTM method that outlines this activity. (Ref. #11) Field Determination of Exhaust Impacts on Air Intakes or Impact of Sewer Gas Leakage: Determining the observed airflow pattern of local exhausts or local point sources on air intakes under real life weather conditions. We typically utilize a tracer smoke (theatrical fog) for this evaluation. This method has also worked well for determining sanitary sewer gas vent (odor) reentrainment or internal leakage sites. Concrete Floor Moisture Emission Testing: Determining the concrete floor moisture emission rate is a common need in existing structures since the advent of water based floor adhesives. There are draft ASTM testing techniques and other standardized testing methods for this determination. (Ref. #12, Ref. #13) Building Envelope Pressure Monitoring: In some buildings, it is important to know the actual peak and long-term average pressures that the HVAC system imposes on the building envelope during normal operation, (summer, winter, swing season) versus what may have been intended or designed. Some Results From Applying These Retro-Commissioning or Performance Acceptance Testing Techniques Case Study A: Existing Central Massachusetts School Historically poor performance of the building envelope and occupant reported health concerns prompted the owners to retro-commission the facility. In this case, the actual trigger for the initial activity was a major roof collapse during a winter snow load event, which flooded and 4
5 closed the school. Additionally, flooding from sprinkler line breakage during the roof collapse and historic severe ice dams warranted a physical investigation to determine specific locations where mold growth had occurred on wallboard, such that it could be removed throughout the facility under proper containment. Retro-Commissioning Paper Study Evaluations and Performance Testing Lead to the Following Decisions: Dew Point / Vapor Pressure Review: Calculation of the vapor pressure relationships and location of dew point occurrence in the existing wall lead to a decision to add 2 inches of Extruded Polystyrene (EPS) insulation to the exterior of the six inch metal stud and fiberglass batt wall. This significantly improved the thermal envelope, moved the dew point into the EPS, and allowed the extra boiler capacity to be used to heat more outside air to bring the outdoor air supply to the currently recommended 15 CFM per person for classroom areas. Exterior Drainage Plane / Wind Barrier Review: Observed rotting wood near windows, failed window leakage tests, and intrusive disassembly revealed a failed exterior drainage plane system. The exterior drainage plane and wind barrier were re-designed. Interior Air Barrier / Vapor Barrier Review: Design drawing review for continuity of the interior air / vapor barriers and intrusive disassembly revealed that the system, as it existed, could remain in place, once mold contaminated gypsum wallboard was replaced. Exhaust Re-entrainment Review (Micro Climate Analysis) and Field Testing: Theatrical smoke testing revealed re-entrainment of several sewer gas vents, and as a result, the stacks were relocated. Boiler stack re-entrainment calculations lead to the extension of the boiler stack to move the exhaust plume above the rooftop HVAC air intakes. Infrared Thermal Performance Evaluation: Gross air leakage into the attic, and then to the outdoors, lead to a solution to move the thermal envelope to the pitched roof plane, and a drastic reduction of envelope exfiltration resulted. Building Envelope Pressure Testing: Fan pressure testing confirmed gross air leakage and observed reasons for the reported major ice dams. This also supported a re-design of the roofing system. Roof Ice Dam Review: Ice damming was reported to be a major problem and also supported the redesign of the roof insulation system. Infrared Imaging to Locate Moisture Infiltration/Leakage into the Thermal Envelope: This analysis confirmed gross rainwater entry into two wall systems and a soffit area. This also supported re-design of the roof. Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, Curtain Walls, and Wall Assemblies: This evaluation and intrusive disassembly lead to the redesign of the wall / windows flashing system, and replacement of all North exposure windows. 5
6 Concrete Floor Moisture Emission Testing: Results of this testing in the non-vented mode, followed by intrusive disassembly at representative locations, lead to a decision to provide perimeter footer drainage, a gully system to allow roof water to move away from the building, and a decision to strip and seal the concrete floor. Performance Acceptance Testing Prior to Re-occupancy was Conducted: Results of infrared imaging confirmed the delivery of a high-performance building envelope. HVAC commissioning activities resulted in further adjustments to the HVAC controls, and the development of a preventative maintenance plan. Follow Up: The occurrence of a small ice dam on a South exposure during very cold weather from solar gain and snow melt lead to minor modifications to the south facing roof valley. The technical results of the above evaluations were utilized to determine that major envelope redesign and re-construction was warranted, and to formulate major reconstruction plans for the building envelope. Goals of the envelope upgrade included both improved long-term energy efficiency/building performance, and reduced possible future health risk within the facility. Exterior metal stud walls were upgraded with EPS to R-30, and the attic insulation system was moved to the roofline and was changed to a true R-20, with a vented Polyiso system. The outdoor air supply to the classroom areas was doubled to meet current ASHRAE Std. 62 guidelines, and low sidewall returns were added. By utilizing energy recovery ventilation, a 100% outside air system was installed without increasing the boiler capacity. Flooring/site concrete moisture problems dictated the need for improved site drainage and the need to add a negative side moisture retarder floor sealing system prior to the use of water based mastics. The resulting successful major envelope upgrade, during roof and wall re-construction, should allow the building envelope to perform well for another 30 to 50 years of service, and significantly reduce energy consumption due to reduced envelope losses and the use of energy recovery ventilation. The above was accomplished during an intense four-month reconstruction period. Case Study B: New School Construction, Central New Hampshire: During the design process by The H.L. Turner Group, Inc., Turner Building Science, LLC provided a review of all design documents. Items considered in cooperation with the Architect of Record included the following: Dew Point / Vapor Pressure Review / Thermal Performance Review: Predicting the vapor pressure relationships and location of dew point occurrences in walls, roof, and floor assemblies lead to a design decision to use rigid foam insulation in all locations to improve overall building moisture and thermal performance. 6
7 Exterior Drainage Plane / Wind Barrier Review: Design review for continuity and constructability of exterior drainage planes lead to a decision to use essentially redundant drainage planes and wind barriers. Both tape joints on EPS, and a building paper, were employed under a masonry composition clapboard exterior with a small air space behind it. Interior Air Barrier / Vapor Barrier Review: Design drawing review for the continuity and constructability of interior air / vapor barriers design confirmed a continuous, rigid air barrier inside the entire structure. Exhaust Re-entrainment Review (Micro Climate Analysis): Design drawing review lead to the decision of where to locate boiler stacks for optimum separation and dilution from rooftop air intakes. Thermal Performance Peak / Peak Occupancy Air Conditioning Impact Review: Review for predicting the expected impact of planned low angle solar gain and glass (fenestration) design on HVAC peak room cooling loads lead to minimization of glass areas for improved daylighting performance, and minimum impact on the cooling burden for the Advantage Displacement Ventilation system. This system uses 100% outside air with enthalpy recovery and displacement air supply in all classrooms and assembly areas. It produces comfortable classroom conditions calculated to be at one-half the operating cost per CFM of outside air, compared to a conventional AC approach. Building Envelope Pressure Review: Design review for predicting the expected overall longterm average building pressure relationship between the inside and outside of the building envelope lead to the decision to focus on a slight overpressure, or neutral pressure design. Exhaust air supply is not greater than makeup air. Building Envelope Air Leakage Review: Design review for the envelope revealed a very tight envelope design which resulted in a reduction in the heating system capacity of the boilers. Roof Ice Dam Review: Design review revealed a very low likelihood of ice dams. Solar gain and snow melt experienced for one period in the winter did produce a small ice dam during very cold weather on a south exposure. Performance acceptance testing was conducted for the HVAC system controls and other building systems as follows: Infrared Imaging of Buildings as Constructed: Infrared testing confirmed no major air exfiltration or thermal losses. Determining at what point in the construction process to make this test remains a construction scheduling challenge. Field Determination of Exhaust Impacts on Air Intakes or Impact of Sewer Gas Leakage: Performance acceptance testing of the sanitary sewer vents revealed one vent impacting a rooftop air intake under certain prevailing winds, and two internal leakage sites resulting from poor workmanship. Determining when during construction to make this test remains a construction scheduling challenge. 7
8 SOME CONCLUSIONS: We have found that building envelope commissioning activities can reveal very valuable information that might otherwise not be observable or technically quantified. Quantification of the situation through standardized testing can result in acceptable conclusions for all parties involved in an often-complicated construction process. For example, Architects and Engineers of Record, Construction Managers, Contractors, Owners Representatives, etc. can then focus on effective decision making and problem resolution given objective technical evaluations. From these technical results, engineering and architectural designs, and their performance, can most often be predicted and field validated if needed. All of these commissioning efforts are intended to produce a high performance building that will meet the owner s and designer s intent, and with proper maintenance and operation, continue to do so. Commissioning activities that identify problem areas that could impact the occupant s health or the value of the owner s building can reduce the risk to all parties involved. The ultimate goal of building envelope commissioning activities is the delivery of a building with envelope systems that offer both reduced health risks and improved indoor air quality to the occupants, thus providing long-term, affordable value for the owner. We believe that these goals are an important part of creating a building envelope that will be sustainable, and would welcome feedback on any of the concepts we have presented. 8
9 REFERENCES CITED: 1. ASHRAE (1997), Fundamentals Handbook, Chapter 26, pp , American Society of Refrigerating and Air Conditioning Engineers, Atlanta, Georgia 2. ASHRAE (1997), Fundamentals Handbook, Chapter 22, pp , American Society of Refrigerating and Air Conditioning Engineers, Atlanta, Georgia 3. ASHRAE (1997), Fundamentals Handbook, Chapter 15, pp , American Society of Refrigerating and Air Conditioning Engineers, Atlanta, Georgia 4. ASHRAE (1997), Fundamentals Handbook, Chapter 24 & 23, pp , American Society of Refrigerating and Air Conditioning Engineers, Atlanta, Georgia 5. ASHRAE (1997), 1997, Fundamentals Handbook Chapter 28 & 29, pp , American Society of Refrigerating and Air Conditioning Engineers, Atlanta, Georgia 6. The H.L. Turner Inc. (2005), Proprietary Information, Advantage Displacement Ventilation, software, The H.L.Turner Group Inc., 27 Locke Rd. Concord, NH ASHRAE (1997), Fundamentals Handbook, Chapter 25, pp , American Society of Refrigerating and Air Conditioning Engineers, Atlanta, Georgia 8. ASTM (Reapproved 1997), Standard Designation: C Standard Practice for Thermgraphic Inspection of Insulation Installations in Envelope Cavities of Frame Buildings, Committee C-16.30, American Society for Testing and Materials, West Conshohocken, PA. 9. ASTM (1999) Standard Designation: E , Standard Test Method for Determining Air Leakage Rate by Fan Pressurization, American Society for Testing and Materials, West Conshohocken, PA. 10. Verbal Communication, (2005), Mr. Henri Fennel, Foam-Tech, P.O. Box 87 - North Thetford, VT ASTM (2000) Standard Designation: E , Standard Test Method for Field Determination of Water Penetration of Installed Exterior windows, Skylights, Doors, and Curtain Walls, by Uniform Cyclic Static Pressure Difference, American Society for Testing and Materials, West Conshohocken, PA. 12. ASTM (2002) Standard Designation: F , Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes, American Society for Testing and Materials, West Conshohocken, PA. 10
10 13. ASTM (2003) Standard Designation: F , Standard Test Method for Measuring Vapor Emission Rate of Concrete Subflooring Using Anhydrous Calcium Chloride, American Society for Testing and Materials, West Conshohocken, PA. 11
Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506
AABC Commissioning Group AIA Provider Number: 50111116 Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506 Dan Adam, RA, CxA, Facility Commissioning Group
More informationInnovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1
ABSTRACT Innovating Continuous Exterior Insulation Theresa A. Weston, PhD. 1 As the need to reduce energy usage and carbon consumption has increased, the need for energy efficient building envelopes has
More informationSenior Design Project for UNO. Design of the International Studies Building: An Environmental Analysis
Senior Design Project for UNO Design of the International Studies Building: An Environmental Analysis Design Intent Implement Passive & Active design strategies in order to make the building: More Energy
More informationThermal Bridging in Residential Construction
PHRC Webinar Series Tuesday, May 12, 2015 @ 1pm Thermal Bridging in Residential Construction Brian Wolfgang Housing Systems Specialist Pennsylvania Housing Research Center 219 Sackett Building University
More informationWhy Control Heat flow? How to Control Heat Flow? Thermal Performance. Modes of heat transfer: Thermal Control: Insulation & Thermal Bridges
Fundamentals Insulation and Thermal Bridges June 13-14, 2012 Why Control Heat flow? Joseph Lstiburek, Ph.D., P.Eng John Straube, Ph.D., P.Eng 2012 Thermal Control: Insulation & Thermal Bridges 1. Occupant
More informationInsulation Technologies and Installation Specifications for Better Energy Performance of Commercial Buildings
Insulation Technologies and Installation Specifications for Better Energy Performance of Commercial Buildings Wood Products Council is a Registered Provider with The American Institute of Architects Continuing
More informationBuilding Science Fundamentals Thermal Control: Insulation & Thermal Bridges May 29-30, Straube buildingscience.com 1 of 24
Fundamentals Thermal Control: Insulation & Thermal Bridges May 29-30, 2013 Straube buildingscience.com 1 of 24 Fundamentals Thermal Control: Insulation & Thermal Bridges May 29-30, 2013 Straube buildingscience.com
More informationMichigan Energy Code Training and Implementation Program
Michigan Energy Code Training and Implementation Program 1.0 Hour Advanced Program Course Number 16202 Residential Energy Plan Review School of Planning, Design & Construction Michigan State University
More information2001 National Workshop on State Building Energy Codes July th, 2001 Burlington, Vermont
2001 National Workshop on State Building Energy Codes July 16-19 th, 2001 Burlington, Vermont A Systems Engineering Approach to the Design of Energy and Resource Efficient Homes Presented By: Mark LaLiberte
More informationIntroduction. Introduction. Designing Building Envelopes to Meet Sustainable and Aesthetic Goals Part 1
Designing Building Envelopes to Meet Sustainable and Aesthetic Goals Part 1 Brian Miller, P.E., LEED AP Precast/Prestressed Concrete Institute Brad Nesset Thermomass Introduction Webinar is in two parts
More informationFeature Zone IECC 2009 IECC
Feature Zone 3 2006 IECC 2009 IECC Window U factor 0.65 0.50 Skylight U factor 0.65 0.65 Window SHGC 0.40 0.30 Ceiling R value 30 30 Wood frame R value 13 13 Mass wall R value 1 5 5/8 Floor R value 19
More informationField Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera
Field Determination of Water Penetration of Windows using Blowerdoor and Infrared Camera Walter Sebastian BMT Building Enviroment Consultants Ltd., Doktor Neergaards Vej 15, DK-2970 Hoersholm, Denmark
More informationA Closer Look Inspection Service 2015 IECC Residential DFW area handout
103.2 Information required on construction documents 1. Designation of the Thermal Building Envelope on the plans 2. Insulation Material and their R Value 3. Fenestration U and SHGC values 4. Area weighted
More informationIncorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure
Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure Peter Baker, Building Science Corporation ABSTRACT With rising utility cost, concerns
More informationMargaret Batts Tobin Laboratory
Roof Evaluation of Margaret Batts Tobin Laboratory The University of Texas At San Antonio Performed for UTSA Zero/Six Consulting, LLC 8423 Stewart Road Galveston, Texas 77554 409 740 0090 voice Table of
More informationCHAPTER 3. BUILDING THERMAL LOAD ESTIMATION
CHAPTER 3. BUILDING THERMAL LOAD ESTIMATION 3.1 Purpose of Thermal Load Estimation 3.2 Heating Load versus Cooling Load 3.3 Critical Conditions for Design 3.4 Manual versus Computer Calculations 3.5 Heating
More informationMoisture Considerations for Insulated Building Assemblies
PHRC Webinar Series Tuesday, November 10, 2015 @ 1pm Description Moisture Considerations for Insulated Building Assemblies Brian Wolfgang Housing Systems Specialist One critical design consideration in
More information2015 IECC Whole Building Air Leakage Compliance
2015 IECC Whole Building Air Leakage Compliance Presented by: Jeffrey Crowe, PE Project Manager www.becx.com www.pieglobal.com September 2012 Learning Objectives Understand 2015 International Energy Code
More informationDate Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection
Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over
More informationEnergy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort
Please add relevant logo here Energy Efficiency: Designing Wood-Frame Buildings for Occupant Comfort Presented by: Peter J. Arsenault, FAIA, NCARB, LEED-AP Disclaimer: This presentation was developed by
More information10 Steps to Save Energy in Your House
10 Steps to Save Energy in Your House Sealing and insulating your home is one of the most cost-effective ways to make your home more comfortable and energy efficient. You can do it yourself. In this chapter,
More informationCrawl Spaces and Basements: Defining the Building Envelope
Crawl Spaces and Basements: Defining the Building Envelope Rich Jones: INCAA, Charlie Smith: Kentucky Housing Corporation, Albert McMahon: NYSWDA 1 By attending this session, participants will: Identify
More informationCommercial Building Envelope Air Leakage
Commercial Building Envelope Air Leakage Presented by: Matt Heron, P.E., Pie Consulting & Engineering Stu Reeve, Energy Manager, Poudre School District Kim DeVoe, Energy Services Engineer, Fort Collins
More informationCan you Believe Energy Savings Forecasts
Can you Believe Energy Savings Forecasts By: Tony Woods Introduction Yes, says TonyWood. Especially when your project includes an upgrade to the building envelope. The relationship between high performance
More informationBEST4 Conference April 13-15, 2015
National Institute of Building Sciences Provider #G168 BEST4 Conference April 13-15, 2015 Design Considerations for Climate Change Paul Totten, Vice President, WSP Alexandra Connor, Project Associate,
More information2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building
2015 Michigan Residential Code Energy Worksheet for New Single-family Residential Building Building Department 52700 Van Dyke, Shelby Township, MI 48316 Phone (586) 731-5969 Fax (586) 803-2099 building@shelbytwp.org
More informationPREP + INSULATION. DISCLAIMER: These tools are for illustrative purposes only and
PREP + INSULATION HOME ENERGY UPGRADES What every contractor needs to know. Copyright 2012 Advanced Energy. All Rights Reserved 103 HOME ENERGY UPGRADES Prep + Insulation Contents Air sealing is a challenging
More informationHardin County Planning and Development Commission
Location by Climate Zone: Hardin County (per Table N1101.2), and the entire state of Kentucky is located in Climate Zone 4, the HDD is 4000 to 4999. Building Requirements; Building Thermal Envelope The
More informationLow-cost Construction for High-energy Savings. Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity
Low-cost Construction for High-energy Savings Brian J. Wimmer Construction Manager Rochester Area Habitat for Humanity construction@rahh.org Objectives: 1. Control air & moisture in high-performance, low-cost
More informationAdvanced technologies for enhancing the building envelope. 3M Building and Construction Market
Advanced technologies for enhancing the building envelope 3M Building and Construction Market Controlling air is crucial for the health & energy efficiency of buildings Ensuring you have the right air
More informationBoulder City NV Prepared by (Print Name) Signature Date
City of Boulder City Community Development Department Building & Safety Division 401 California Avenue Boulder City, NV 89005-2600 702-293-9282 (Main Line) 702-293-9392 (Fax) 2009 International Energy
More informationThe Role of Control Layers in Building Enclosure Design
The Role of Control Layers in Building Enclosure Design COLIN SHANE M.ENG., P.ENG. ASSOCIATE, SENIOR PROJECT MANAGER OCTOBER 13, 2016 Disclaimer: This presentation was developed by a third party and is
More informationCHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION
Chapter 1: Overview of Energy Efficient Construction 1 CHAPTER 1: OVERVIEW OF ENERGY EFFICIENT CONSTRUCTION Chapter 1 is a quick reference guide that discusses the key components and features of energy
More informationWEST VIRGINIA UNIVERSITY ALUMNI CENTER Morgantown, West Virginia
TECHNICAL REPORT I ASHRAE STANDARDS 62.1 AND 90.1 COMPLIANCE EVALUATION 8/29/08 WEST VIRGINIA UNIVERSITY ALUMNI CENTER Morgantown, West Virginia GREGORY SMITHMYER PENN STATE UNIVERSITY ARCHITECTURAL ENGINEERING
More informationINSTALLING WATER-RESISTIVE BARRIERS & FLASHING
INSTALLING WATER-RESISTIVE BARRIERS & FLASHING IN A TWO-LAYER STUCCO APPLICATION Fortifiber Building Systems Group provides this guide to assist installers by demonstrating a two-layer installation of
More informationCERTIFICATE OF FIELD VERIFICATION & DIAGNOSTIC TESTING (Page 1 of 8)
CERTIFICATE OF FIELD VERIFICATION & DIAGNOSTIC TESTING (Page 1 of 8) Builder or Installer Name Builder or Installer Contact Telephone Plan/Permit (Additions or Alterations) Number Compliance Method (Prescriptive)
More informationBoston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109
Boston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109 Building Envelope Designs meeting the requirements of the new Massachusetts Energy Code 780 CMR 13 For Educational
More informationInstructions for the Residential Building Data Collection Checklist 2009 International Energy Conservation Code with 2011 Georgia Amendments
Instructions for the Residential Building Data Collection Checklist 2009 International Energy Conservation Code with 2011 Georgia Amendments Use of these instructions with a residential data collection
More information2010 National Building Code Adoption and Associated Process Changes
Building Inspection City of Moncton 655 Main Street Moncton, NB E1C 1E8 Phone: (506) 856-4375 Fax: (506) 856-4348 Bulletin No. 14 From: Randy Richard Date: February 9, 2015 Subject: 2010 National Building
More informationUnited States Army Corp of Engineers Requirements for Air Barrier Systems in Buildings
United States Army Corp of Engineers Requirements for Air Barrier Systems in Buildings Timothy R. Posey, MBC, Scott W. Kramer, Ph.D. and Mark C. Tatum, P.E. Auburn University Auburn, Alabama This study
More informationBest Practice Recommendations for Wall Retrofit on the Two-Story Flexible Research Platform (FRP) at Oak Ridge National Laboratory (ORNL).
Best Practice Recommendations for Wall Retrofit on the Two-Story Flexible Research Platform (FRP) at Oak Ridge National Laboratory (ORNL). Wall retrofit strategies for retrofit on the interior side of
More informationCrawl Space Moisture Control
Crawl Space Moisture Control Crawl space foundations are found in many homes. Typically, these foundation types are equipped with operable vents designed to provide ventilation for moisture control. Unfortunately,
More informationInsulation Technologies and Installation Specifications for Better Energy Performance of Commercial Buildings
Insulation Technologies and Installation Specifications for Better Energy Performance of Commercial Buildings WoodWorks West Wood Products Council is a Registered Provider with The American Institute of
More informationInspection of New One- and Two- Family Dwellings
Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Inspection of New One- and Two- Family Dwellings Planning and Development
More informationOf Building Science: From Control Layers to High Performance Enclosures
Of Building Science: From Control Layers to High Performance Enclosures Energy Design Conference February 24, 2016 Duluth, MN Patrick H. Huelman Cold Climate Housing Coordinator University of Minnesota
More informationCommissioning Under the Influence
Commissioning Under the Influence Redefining the Traditional Role of the Commissioning Agent in the Design and Construction of the Building Envelope National Conference on Building Commissioning: May 2-4,
More informationInterpretation Variables and Common Areas of Confusion. Of the 2009 IECC
Interpretation Variables and Common Areas of Confusion Of the 2009 IECC 1. (Mandatory) provisions vs. (Prescriptive) provisions: The IECC contains flexibility by allowing different approaches to achieve
More information780 CMR: 9 th Edition Massachusetts State Building Code. Presented to: BSA Codes Committee. DATE: January 20, 2016
780 CMR: 9 th Edition Massachusetts State Building Code Presented to: BSA Codes Committee DATE: January 20, 2016 This course is registered with AIA CES for continuing professional education. Credit(s)
More informationInside Why Spray polyurethane Foam insulation? All About Spray polyurethane Foam Book 1
Foam Book Inside Why Spray polyurethane Foam insulation? All About Spray polyurethane Foam Book 1 SUSTAIN THROUGH KNOWLEDGE Book 1: Why Spray Polyurethane Foam Insulation Book 2: SPF & Thermal Barrier
More informationCOLD CLIMATE HOUSING RESEARCH CENTER CCHRC. Whole Wall R-Values
COLD CLIMATE HOUSING RESEARCH CENTER CCHRC Whole Wall R-Values Cold Climate Housing Research Center Colin Craven, Director, Product Testing Lab Robbin Garber-Slaght, EIT Disclaimer: The research conducted
More informationairflow in to, out of, and within buildings. These airflows are resisted by the airtightness of building elements including the exterior enclosure and
Airflow in to, out of, and within buildings is a fundamental factor of indoor air quality, comfort, durability, and energy consumption. Multi-unit residential buildings are uniquely complex in this respect
More informationIRC 2012 Key Changes
IRC 2012 Key Changes Overview of changes between the 2009 and 2012 IRC A Webinar Provided by The Pennsylvania Housing Research Center November 4, 2011 Presented by Mike Turns; Associate Director, PHRC
More informationPlan Check & Field Inspection Guide
Plan Check & Field Inspection Guide 1992 MEC, 1993 MEC, and 1995 MEC Inside This Guide Plan Check Field Inspection Plan Check Building plans and specifications must be submitted with each building application
More informationIntroduction. ED02 White Paper Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff 1
Building Enclosure Commissioning as Part of LEED V4 Total Commissioning Package Paul Meyer, PE, LEED AP BD+C, CEM, CBCP Senior Vice President, Commissioning WSP Parsons Brinckerhoff Learning Objectives:
More informationThe Role of Control Layers in Building Enclosure Design
The Role of Control Layers in Building Enclosure Design COLIN SHANE M.ENG., P.ENG., P.E. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. SEPTEMBER 14, 2016 Disclaimer: This presentation was
More information2013 COMMERCIAL PRODUCTS
2013 COMMERCIAL PRODUCTS EXPLORE GEOMETRY AND SPACE WITHOUT COMPROMISING BUILDING ENVELOPE PERFORMANCE Commercial design considerations come with very specific challenges that can t be addressed with just
More informationAir Infiltration & the Knauf Insulation EcoSeal
White Paper BI-WP-04 10-12 Air Infiltration & the Knauf Insulation EcoSeal System EcoSeal & Knauf Insulation Glasswool Products AN WHITE PAPER THE IMPACT OF OTHER BUILDING ELEMENTS ON AIR INFILTRATION
More informationCore Building Advances: Introduction to Sustainable Building & Building Science
Core Building Advances: Introduction to Sustainable Building & Building Science Rob Howard & Mike Mongeon Habitat for Humanity International rhoward@habitat.org mmongeon@habitat.org Introductions Name
More informationSmart Vapor Retarders
CertainTeed Smart Vapor Retarders Insulation B UILDING S CIENCE SMART VAPOR RETARDERS: A TECHNOLOGY PRIMER For years, builders have relied on a dual climate-zone classification for the placement of vapor
More informationNational Institute of Building Sciences. Paul Totten, PE, LEED AP Vice President, National Practice Leader, Building Enclosures
National Institute of Building Sciences Provider Number: G168 Design Considerations for Climate Change Session TU1A Paul Totten, PE, LEED AP Vice President, National Practice Leader, Building Enclosures
More informationMichigan Energy Code Training and Implementation Program
Michigan Energy Code Training and Implementation Program 1.0 Hour Advanced Program Course Number 16201 Residential Energy Air Sealing School of Planning, Design & Construction Michigan State University
More informationIndoor Air Quality (IAQ) Tailoring Lease Specifications S-852
Indoor Air Quality (IAQ) Tailoring Lease Specifications S-852 June 2015 Table of Contents Printed with permission from authors...3 Introduction...4 Outside air distribution...4 Air contaminant source...6
More informationSept 30, 2004 Page 1
Sept 30, 2004 Page 1 This section includes a manufacturer's guide specification for TERRAFOAM EPS building insulation. Refer also to Product Description for detailed product properties, options, and other
More informationHPW Protocol Reference Manual
1 HPW Protocol Reference Manual Change Log: UPDATED BY DATE UPDATED VERSION UPDATE DETAILS 2 Table of Contents: HIGH PERFORMANCE WALL ASSEMBLY... 4 THERMAL SPECIFICATION... 4 REQUIREMENTS FOR HPW INSULATION...
More informationWEB BASED APPLICATION SPECIFIC INSTALLATION INSTRUCTIONS
WEB BASED APPLICATION SPECIFIC INSTALLATION INSTRUCTIONS Replace Window with Patio Door Although all possible measures have been taken to insure the accuracy of the material presented, WIXSYS, and the
More informationBuilding Enclosure Performance for Existing and New Buildings
Building Enclosure Performance for Existing and New Buildings 2015 HESNI Annual Conference Rick Ziegler, PE Industry Construction Defect Claims Building Envelope - 70% Plumbing - 12% Freezing - 4% Fire
More informationEnergy-efficient weatherization
Energy-efficient weatherization For your home 4326 02/14 Puget Sound Energy P.O. Box 97034 Bellevue, WA 98009-9734 pse.com/myrebates Weatherize your way to comfort In this guide 4 Understanding weatherization
More informationNEW HOMES PROGRAM 2017 PROGRAM GUIDE
NEW HOMES PROGRAM 2017 PROGRAM GUIDE Focus on Energy, Wisconsin utilities statewide program for energy efficiency and renewable energy, helps eligible residents and businesses save energy and money while
More informationContinuous Insulation Systems for Exterior Walls
Continuous Insulation Systems for Exterior Walls High performance through sprayed-in-place foam insulation www.icynene.com Program Registration Icynene Inc. is a registered provider with The American Institute
More informationR-Value. Effective. Energy efficiency of masonry s thermal mass is recognized by code 9" 2" R21 + R18 THERMAL MASS +13 R13 R18
Article reprinted with permission from MasonryEdge/theStoryPole Vol 6 No 3 the Effectiveness of R-Value Effective Allow masonry s mass, which slowly warms and slowly releases heat for greater comfort levels,
More informationSealing the Envelope with SPF Insulation
solutions for the construction industry august 2012 Sealing the Envelope with SPF Insulation by Jim Lambach Photo Fransyl. Photo courtesy Bayer MaterialScience LLC In a time of ever-rising energy costs
More informationBuilding Envelope Systems Exam Learning Objectives
Building Envelope Systems Exam Learning Objectives Roofing Nomenclature 1. Define the following roofing terms: low, flat, sloped, conventional, protected/inverted, hybrid, BUR, modified bitumen, PVC, TPO,
More information2006 INTERNATIONAL ENERGY CONSERVATION CODE
2006 INTERNATIONAL ENERGY CONSERVATION CODE DOCUMENTATION Code Change No: EC28-06/07 Original Proposal Sections: IECC: 202, 402.5, 402.5.1 (New), Table 402.5.1 (New), 402.5.2 (New), 402.5.3 (New), 402.2.8,
More informationThe Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma
LEED Green Building Certification The purpose of the LEED Green Building Rating is to provide a national standard that aims to improve environmental, health and economic performance of buildings using
More informationBROCHURE # 108 CONSTRUCTION PLAN COMPONENTS
BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS Please note: This construction plan component list is to be used as a guide to assist you with your project. There may be elements unique to your project not
More informationBuilding Enclosure Details and Assemblies for Wood-Frame Buildings
Building Enclosure Details and Assemblies for Wood-Frame Buildings COLIN SHANE M.ENG., P.ENG. ASSOCIATE, SENIOR PROJECT MANAGER RDH BUILDING SCIENCES INC. NOVEMBER 19, 2015 Disclaimer: This presentation
More informationDESIGNING COMMERCIAL SUB-SLAB DEPRESSURIZATION SYSTEMS
DESIGNING COMMERCIAL SUB-SLAB DEPRESSURIZATION SYSTEMS Presented at the 2002 - AARST - 12 th Annual International Radon Symposium in Reno, Nevada Bill Brodhead WPB Enterprises, Inc., 2844 Slifer Valley
More informationBUILDING ENCLOSURE DESIGN GUIDE WOOD FRAME MULTI-UNIT RESIDENTIAL BUILDINGS. Summary. 1. Introduction
BUILDING ENCLOSURE DESIGN GUIDE WOOD FRAME MULTI-UNIT RESIDENTIAL BUILDINGS David Ricketts M.Sc., P.Eng. RDH Building Engineering Ltd., 224 West 8 th Avenue, Vancouver, B.C. V5Y 1N5 Summary 1. Introduction
More informationAttached Solar Greenhouse Plans for a solar heated greenhouse attached to your home
Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home Designed and built by New Mexico landscape architect John Mosely for his own Santa Fe home. The solar greenhouse shown
More informationSpray Polyurethane Foam. Insulation and Air Barrier Requirements of the 2012 I-Codes. Spray Foam Coalition
Spray Polyurethane Foam Design Guidance Insulation and Air Barrier Requirements of the 2012 I-Codes Spray Foam Coalition about the collaboration the center for the polyurathanes industry (CPI) of the
More informationIECC Commercial Significant Changes Summary Tier I
2009-2015 IECC Commercial Significant Changes Summary Tier I The first change is in the layout of the book. Instead of having Chapters 1-3 that applied to all projects and then having Chapter 4 Residential
More informationLocal Temperature Measurements on Full-Size Systems in the Laboratory: Insight into the Extent of Thermal Bridges in Building Envelope Components
Local Temperature Measurements on Full-Size Systems in the Laboratory: Insight into the Extent of Thermal Bridges in Building Envelope Components Thomas W. Petrie, Jan Ko ny, Jerald A. Atchley and André
More informationLEED And Your Indoor Environment
LEED And Your Indoor Environment An overview of LEED v3 and Indoor Air Quality David McCauley, CIE Council Certified Indoor Environmentalist ACAC CIE #1008005 USGBC's Mission To transform the way buildings
More informationPerformance-Risk Methodology for the Design of High-Performance Affordable Homes
April 3 rd, 2012 1 Performance-Risk Methodology for the Design of High-Performance Affordable Homes Building Enclosure Science & Technology Conference BEST3, Atlanta Rodrigo Mora, British Columbia Institute
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-07 27 10.00 10 (May 2014) ----------------------------------- Preparing Activity: USACE UFGS-07 08 27.00 10 (February 2013) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationBetter Buildings. Performance. Fundamentals. The Rules
Fundamental Goals Dr John Straube, P.Eng. Principal, Building Science Corporation Associate Professor, University of Waterloo Better Buildings Fundamentals Safe Healthy Comfortable Durable Affordable Environmentally
More informationColumbia Skylights may qualify your project for LEED points in the following categories: Columbia Skylights - Potential Contribution to LEED projects
3.0 Statement Columbia Skylights Statement for New Construction (NC) Version 3.0 Credit Documentation The Leadership in Energy and Environmental Design () Green Building Rating System promotes the adoption
More informationPrescriptive Checklist for the 2015 Washington State Energy Code
Prescriptive Checklist for the 2015 Washington State Energy Code Chapter 51-11R WAC STATE BUILDING CODE ADOPTION AND AMENDMENT OF THE 2015 EDITION OF THE INTERNATIONAL ENERGY CONSERVATION CODE, RESIDENTIAL
More informationBuilding Inspection Report
Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941
More informationBuilding code language is unclear regarding low-slope roof assembly ventilation. by Brian Erickson, P.E., and Liberty Lewis, P.E.
Building code language is unclear regarding low-slope roof assembly ventilation by Brian Erickson, P.E., and Liberty Lewis, P.E. 32 November 2009 www.professionalroofing.net Because of our current litigious
More informationBuilding & Ductwork Airtightness Standards
Building & Ductwork Airtightness Standards Version 1.02, August 2013 Standard Reference Technical Body Title ICS (International Classification for Standards) Scope Door and Windows EN 12207:1999 Windows
More informationMoisture and temperature conditions in cold lofts and risk of mould growth
Moisture and temperature conditions in cold lofts and risk of mould growth Sivert Uvsløkk, M. Sc. Norges byggforskningsinstitutt; sivert.uvslokk@byggforsk.no http://www.byggforsk.no/ KEYWORDS: roof, loft,
More informationREPORT HOLDER: THE DOW CHEMICAL COMPANY 1501 LARKIN CENTER DRIVE MIDLAND, MICHIGAN EVALUATION SUBJECT:
0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-3089 Reissued 07/2016 This report is subject to renewal 07/2018. DIVISION: 07 00
More informationFMA / AAMA / WDMA Installation Committee Update. Jim Katsaros / DuPont Building Innovations FMA Installation Committee April 24, 2012
FMA / AAMA / WDMA Installation Committee Update Jim Katsaros / DuPont Building Innovations FMA Installation Committee April 24, 2012 Topics for discussion. Review & Update on FMA/AAMA/WDMA Window & Door
More informationHigh Performance, Energy Efficient Design for Wood Frame Buildings
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Please add relevant logo here High Performance, Energy Efficient Design for Wood
More informationWhy test a system that has already been tested? Typical Manufacturers information for window to wall interface and basis for reported test results.
1 Pre-Construction Phase, & the Laboratory or Field Mock-Up Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by Fiona Aldous Why test a system
More informationDemystifying Testing Standards C t B ildi F d. Common to Building Facades. John Runkle, P.E. Architectural Testing, Inc. Learning Objectives
Demystifying Testing Standards C t B ildi F d Common to Building Facades John Runkle, P.E. Director, Forensic Services Architectural Testing, Inc. Architectural Testing Learning Objectives Understand laboratory
More information(Project Location) (your firm's name)
SECTION 07 21 00 THERMAL INSULATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the Conditions of the Contract and Division 01 Specification Sections
More informationExterior Perspective, East End
Interior Open Plan Private to Public Gradation Obstruction of Open Plan Exterior Perspective, East End University of Texas at Austin s intends to be an adaptable design using solar power as its inspiration.
More informationIntroduction to basics of energy efficient building design
Introduction to basics of energy efficient building design Pierre Jaboyedoff Seminar on Energy Efficient & Thermally Comfortable Buildings in Amravati For CRDA, Andhra Pradesh May 2 nd 2017 Indo-Swiss
More information