LTRC QUALITY CONTROL OF TRENCH BACKFILL AT HIGHWAY CROSS-DRAIN PIPES. Zhongjie Doc Zhang, PhD, P.E. October 2004
|
|
- Rudolph Ezra White
- 6 years ago
- Views:
Transcription
1 QUALITY CONTROL OF TRENCH BACKFILL AT HIGHWAY CROSS-DRAIN PIPES Zhongjie Doc Zhang, PhD, P.E. LTRC October 24 Louisiana Transportation Research Center
2 Purposes of Quality Control Guarantee sufficient surrounding support to pipes for their stability and integrity Provide adequate support to pavement structures at the locations of highway cross-drain pipes
3 Rideability Problem The unexpected deterioration of pavement ride comfort due to dips in pavement surfaces at highway cross- drain locations
4 Field Investigation Indicates Under the same traffic and environmental conditions, pavement dips occurred at some cross-drain pipe locations but not at others Pavement dips occurred mainly due to weaker trench backfill than adjacent subgrade soils
5 Pavement dips and PRR PRR is the ratio of average penetration resistances within and outside of a trench area Penetration Resistance Ratio with dip without dip Case Number
6 Typical DCP Profiles N DCP, Blows Per 1 cm Penetration Asphalt: 9 cm (3.5") Soil Cement: 21.5 cm (8.5") N DCP, blows/1 cm AC (2 cm or 8'' ) 2 Soil cement (15 cm or 6'') 4 concrete pipe 6 Depth, cm cm (36") out of trench in trench 1 in trench 2 Depth, cm Concrete pipe dia. = 66cm Concrete pipe dia. = 66 cm Backfill Backfill Subgrade N DCP, Blows Per 1 cm Penetration asphalt 4 cm (1.5 in). soil cement 2 cm (8 in). N DCP, Blows Per 1 cm Penetration Asphalt: 2 cm (8") Soil Cement: 15 cm (6") 4 4 in trench 1 in trench 2 out of trench 8 metal pipe: 112 cm (44 in.) 8 Depth, cm 12 Depth, cm 12 Concrete pipe: 112 cm (44 in) Site 1: in trench Site 2: in trench Site 3: ou t of tre nc h
7 Field Testing
8 DCP Data Probability Histogram Subgrade Soils Sand Backfill Average N DCP = 7. Median N DCP = Average N DCP = 4. Median N DCP = Probability (%) N DCP (blows / 1 cm) N DCP (blows / 1 cm)
9 Prevention of Pavement Dips To prevent pavement surface dips, trench backfill should be compatible with the adjacent subgrade soils in stiffness, or have a penetration blow count, N DCP, equal to or larger than 1 hammer blows per 4 inch (1cm) penetration in Louisiana
10 Objective of Field Testing Investigate How the criterion of backfill quality could be missed in the field construction What kind of measures should be taken to prevent it from occurring
11 Summary of Backfill Testing Sections Construction Project No. of Trenches Backfill Material Status of Testing In Trench On Subgrade (LA 964) 4 Sand (Compaction) Finished Finished (US 61) 4 Kentucky crushed limestone (Compaction) Finished Finished 1 Sand (flooding) Finished Not finished 1 Bedding material (3% sand, 7% gravel, compaction) Finished Not finished (LA 73/LA 74) 3 Selected soil PI < 1 Finished Finished 1 Mexican crushed limestone Finished Finished 1 Sand (compaction) Finished Not finished (LA 1) 4 RAP Finished Not finished
12 Major Influence Factors on Trench Backfill Quality Contractors Behavior Backfill Material Pipe Cover Layer Configuration of Cross-Drain Trench
13 Contractors Behavior The most important factor in quality control Most are experienced Tension can build in the field when under pressure due to construction delays, under traffic, bad weather, wrong moisture content of backfill, poor drainage conditions They should be a team player and share the consequences of the quality of their construction products, good or bad
14 Major Influence Factors on Trench Backfill Quality Contractors Behavior Backfill Material Pipe Cover Layer Configuration of Cross-Drain Trench
15 Backfill Material Compaction Moisture Adjustment Seepage Stability
16 Gradation of Different Backfills Gradation Curve DOTD Granular upbound 1 9 DOTD Granular lowbound Percent Passing, % sand, LA 964 Sand gravel, LA 964 Kentucky limestone Mexican limestone 1 Selected soil Grain Size, mm RAP
17 Gradation Characteristics of Backfill Material Material Effective size D 1 (mm) D 3 (mm) D 6 (mm) Uniformity Coefficient C u Coefficient of Gradation C c Sand Kentucky limestone Mexican limestone Bedding (Sand gravel) RAP Selected soil.14.48
18 Field Compaction Equipment Wacker Packer Vibratory Roller Vibratory Plate
19 Effects of Compaction NDCP, blows/1 cm Backfill Thickness, cm RAP, light RAP, medium RAP, heavy sand, light sand, medium sand, heavy crushed stone, light crushed stone, medium crushed stone, heavy
20 Field Compaction - Sand Depth (cm) N-DCP (blows/1cm) DCP 1 DCP 2 DCP N-DCP (blows/1cm) N-DCP (blows/1cm) Pipe Depth = 2.5"(52cm) "(225cm) Pipe Depth = "(cm) - 52"(133cm) Depth (cm) N-DCP (blows/1cm) DCP 5 Depth (cm) N-DCP (blows/1cm) DCP (a) Sand Backfill with Good Compaction (b) Sand Backfill with Poor Compaction
21 Field Compaction Kentucky Limestone N-DCP (blows/1cm) N-DCP (blows/1cm) Depth(cm) DCP 1 DCP 2 DCP 3 >15 >15 >15 >15 >15 >15 >15 >15 Pipe Depth=6"(15cm)-48"(122cm) Depth(cm) >15 DCP 1 DCP 2 DCP 3 >15 >15 >15 >15 >15 >15 Pipe Depth=4"(1cm)-52"(132cm) (a) 1-ft Lift (b) 2-ft Lift
22 Field Compaction RAP N-DCP (blows/1cm) N-DCP (blows/1cm) N-DCP (blows/1cm) N-DCP (blows/1cm) DCP 1 2 DCP 2 2 DCP 1 2 DCP 3 Pipe Depth = 16"(41cm) - 66"(168cm) Depth (cm) Depth (cm) Pipe Depth = 6"(15cm) - 56"(142cm) Depth (cm) Depth (cm) (a) 12-inch Lift (b) 18-inch Lift
23 Field Compaction Selected Soil N-DCP (blows/1cm) N-DCP (blows/1cm) DCP 1 2 DCP 4 Pipe Depth = 17"(43cm) - 71"(18cm) Depth (cm) Depth (cm)
24 Compaction Characteristic Summary Material Maximum Dry Density pcf Working Moisture Range, % Compaction in field Standard Proctor Modified Proctor Standard Proctor Modified Proctor Sand Difficult Kentucky limestone Very easy Mexican limestone Very easy Bedding (Sand gravel) Easy RAP Easy Selected soil Not easy
25 Backfill Material Compaction Moisture Adjustment Seepage Stability
26 Moisture Adjustment How fast a backfill material can be dried out in the field Laboratory dry-out test
27 Laboratory Dry-Out Test Results Hours to Optimum Moisture, hour % 5% 1% 15% 2% 25% 3% 35% Moisture Content, % Silt Sand Kentucky limestone Mexican Limestone RAP Bedding Material
28 Typical Moisture Content Values Material Optimum Moisture Content, % Maximum Moisture without water flowout, % Possible Field Moisture, % Field Working Moisture Range, % Sand 5 17 < Kentucky limestone < Mexican limestone < Bedding (Sand gravel) < RAP 6 15 < 15 9 Selected soil < 31 15
29 Backfill Material Compaction Moisture Adjustment Seepage Stability
30 Seepage Stability Resistance to erosion caused by underground water that goes through backfill, or water leaks to the backfill from the joints of cross-drain pipes. Backfill dry density Backfill cohesion or particle interlock Material comparison Density Strength Kentucky limestone: high high Mexican limestone: medium medium RAP: low high Bedding: medium medium Selected soil: low low Sand: low low
31 Summary for Backfill Material Kentucky limestone: The best choice Easy to compact to a high dry density and stiffness Narrow moisture range in the field Strong particle interlock with good seepage stability Followed by Mexican limestone, RAP, bedding material (sand gravel mixture), selected soil, and sand
32 Major Influence Factors on Trench Backfill Quality Contractors Behavior Backfill Material Pipe Cover Layer Configuration of Cross-Drain Trench
33 Pipe Cover Layer Refers to the subgrade soil over pipes It is a buffer zone between a pavement structure and pipes for construction and traffic loading A thick and well compacted cover layer will spread traffic loading well out of trench area
34 Pipe Cover Layer 4.4 feet N-DCP (blows/1cm) Cover Layer 1 = >15 47"(119cm) 53"(135cm) 15 Subgrade Subgrade Crushed Stone Crushed Stone Subgrade Subgrade Pipe 2 DCP 1 DCP 2 DCP 3 DCP 4 DCP 5 DCP 6 Limestone backfill
35 Construction Loading Influence Embedded pressure cells 8" Asphalt Pavement Pressure cells 8.5" Mexican Limestone Subgrade 42" 26.4" layer 1 layer 1 12" Pressure cell 4" 12" Selected Soil
36 Construction Loading on Binder Pressure, psi depth Top Horizontal psi Recorded Data Point depth Top Inclined Bottom Horizontal Pressure, psi psi Recorded Data Point Pressure, psi depth psi Recorded Data Point
37 Traffic loading influence - Stresses at various construction stages 36.8 psi 36.8 psi 36.8 psi 2" Wearing Course 36.8 psi 5" Binder Course 8.5" Soil Cement 25.5" Lime Treated 12" 4.56 psi 3.47 psi.88 psi.86 psi Bottom Guage psi 4.15 psi 1.19 psi 1.17 psi Subgrade S1 S2 S3 S4
38 Major Influence Factors on Trench Backfill Quality Contractors Behavior Backfill Material Pipe Cover Layer Configuration of Cross-Drain Trench
39 Configuration of Cross-Drain Trench Compaction in subgrade backfill areas is important If properly compacted, it can provide a smooth transition in stiffness Otherwise, it can be a weak area if poorly compacted Su bgrade Subgra de Backfill Are a Trench Backfill Are a Sub grade Backfill Area
40 Field Example of Subgrade Backfill Area
41 Unit Cost Comparison Material Material Unit Cost $/cubic yd Sand 5 6 Kentucky limestone 29 Mexican limestone 25 Bedding (sand gravel) 8 15 RAP Selected soil 3 8 Flowable Fill 7 1
42 Conclusions Material: Crushed Limestone is recommended as cross-drain trench backfill if their gradations meet LA Specification 13.3(d) Flowable fill can be used when cost is justified Sand and Selected soil that meet current LA DOTD specification can be used if proper compaction can be reached. More field testing work using RAP and bedding material as backfill should be conducted
43 Conclusions (cont.) Compaction control: Contractors share the consequences of their products by deducting payment for poor construction quality DCP test can be used for final acceptance Average DCP values over the depth of 4 ft within backfill shall at least be 1 blows per 4 penetration (smaller than 1 mm/blow), or Average DCP values over the 4 ft depth within and out of trench areas are compatible with each other
44 Implementation LTRC research project: Alternative Methods to Trench Backfill Project Review Committee recommends a change in the current specifications for Trench backfill Stone aggregate or recycled Portland cement concrete be required for backfill materials for all cross drain pipes and side drain pipes under paved areas of travel lanes, shoulders, and turnouts
45 Implementation (cont.) Each district evaluates the option of using RAP as trench backfill before RAP is officially specified as backfill material The modification of Section 71 is coming THANKS!
LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH
LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH Presentation Outline General Introduction Part II Site Preparation & Earthwork Part III Base Courses
More informationUtility Cut Restoration
Design Manual Chapter 9 - Utilities 9D - Utility Cut Restoration 9D-1 Utility Cut Restoration A. General Utility cuts are made in existing pavement sections to install a myriad of utilities and to repair
More informationFULL - DEPTH RECYCLING OF ASPHALT PAVEMENTS WITH PORTLAND CEMENT
FULL - DEPTH RECYCLING OF ASPHALT PAVEMENTS WITH PORTLAND CEMENT Dick Martin Pavement Recycling Specialist Road Recycling Council New England Region What is Full Depth Reclamation? FDR is the rehabilitation
More informationItem 247 Flexible Base
Item Flexible Base 1. DESCRIPTION 2. MATERIALS Construct a foundation course composed of flexible base. Furnish uncontaminated materials of uniform quality that meet the requirements of the and specifications.
More informationCONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL
CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard
More informationSECTION AGGREGATES
SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational
More information2.1 Backfill - General
2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish
More informationCITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5
Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 1.0 EXCAVATION AND FILL 1.1 GENERAL.1 The excavation or fill shall be made to provide proper grade, lines and crosssection for the laying of
More informationLTRC. Presented By. Khalil Hanifa, E.I. Geotechnical Research Engineer 10-3GT
Presented By Khalil Hanifa, E.I. Geotechnical Research Engineer LTRC 10-3GT Design Values of Resilient Modulus for Stabilized and Non-Stabilized Base Overview o o o o o o o o o o Background Implementation
More informationITEM 404LVT (Low Volume Traffic) ASPHALT CONCRETE Revised June 5, 2015
Notes to Designers: ITEM 404LVT (Low Volume Traffic) ASPHALT CONCRETE Revised June 5, 2015 Here s what s new in this latest revision of 404LVT This revised specification includes the following changes:
More informationSection 25 Aggregate Subbase
Black text from standard FAA spec Strikeout text deletions from FAA standard spec Blue text additions to FAA standard spec Red text notes to the Engineer/won t appear in spec I. DESCRIPTION A. GRANULAR
More informationCITY OF FARGO SPECIFICATIONS AGGREGATE BASES
AGGREGATE BASES PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, accessories, and equipment necessary
More informationITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)
ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) 275.1. Description. This Item shall govern for treating subgrade, new and/or existing base [with or without asphaltic concrete pavement (ACP)], or
More informationSECTION 10 - TRENCHING AND BACKFILLING
SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain
More informationSECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.
PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and
More informationSECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.
SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt
More informationSECTION TRENCHING & BACKFILLING
SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications
More informationPavement Design Webinar
Pavement Design Webinar JUNE 23, 2016 COLORADO ASPHALT PAVEMENT ASSOCIATION Who is CAPA? Producers /Suppliers Local Agencies Contractors Designers We are a resource for YOU 1 Mike Skinner, PE Director
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain
More informationSECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT
SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating
More informationSelect Subgrade Material, Compacted
314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.
More informationA. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):
SECTION 31 32 13.16 CEMENT STABILIZATION PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the specifications for cement stabilization of sandy or silty soil and consists of pulverizing, addition
More informationSECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS
SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01
More informationVDOT Pavement Recycling Initiative. Andy Babish, P.E. State Materials Engineer
Andy Babish, P.E. State Materials Engineer Pavement Recycling Initiative Background Goal and Key Components Going Forward 2 Initiative Background - 2008: 3 Full Depth Reclamation trial sections constructed
More information2016 Louisiana Transportation Conference Danny Gierhart, P.E. Regional Engineer Asphalt Institute
A Simplified Pavement Design Tool 2016 Louisiana Transportation Conference Danny Gierhart, P.E. Regional Engineer Asphalt Institute www.pavexpressdesign.com What Is PaveXpress? A free, online tool to help
More informationConstruction Specification for Concrete Unit Pavers
Engineering & Construction Services Division Standard Specifications for Road Works TS 3.80 September 2017 for Concrete Unit Pavers Table of Contents TS 3.80.01 SCOPE... 2 TS 3.80.02 REFERENCES... 2 TS
More informationCITY OF LETHBRIDGE SECTION Construction Specifications Page 1 of 7 BACKFILL REGULATIONS FOR PUBLIC RIGHT-OF-WAYS
Construction Specifications Page 1 of 7 1. GENERAL 1.1 The following specifications apply to compaction of all water, sewer and shallow utility service cuts, repairs, replacements, mainbreaks, extensions,
More informationIntroduction to Asphalt Pavement Design and Specifications
Introduction to Asphalt Pavement Design and Specifications Ensuring Good Performance in Flexible Pavement Design and Construction: accomplished through: 1. Proper structural (thickness) design for the
More informationThis study was undertaken to provide the LA DOTD with an implementation package to facilitate adoption of the new AASHTO Guide for Design of Pavement
This study was undertaken to provide the LA DOTD with an implementation package to facilitate adoption of the new AASHTO Guide for Design of Pavement Structures. The study included evaluation of design
More information205 - EXCAVATION AND EMBANKMENT FOR HIGHWAYS SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS. Common Excavation (Contractor-Furnished)
SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS 205.1 DESCRIPTION Excavate, haul, place, remove and dispose of the specified materials. Construct the embankments as specified in the Contract Documents.
More informationBASED ON DFD MASTER SPECIFICATION DATED 2/24/2014
1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment,
More informationBump Formation & Prevention
Bump Formation & Prevention In Asphalt Concrete Overlays Vern Thompson Central Region Sales Manager Crafco, Inc. INTRODUCTION Crack Treatments #1 Sealing cracks in asphalt concrete pavements is a widely
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular
More informationBASE CONSTRUCTION MATERIALS A Aggregate
BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3
More information1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods
SECTION 2000- EARTHWORK PART 1- GENERAL 1.01 SCOPE: This Section covers excavation, fill, and compaction of earth and rock for roadway, embankments, structural foundations, and planted areas. Topics include
More informationCold-in-Place Recycling
Design Manual Chapter 5 - Roadway Design 5J - Pavement Rehabilitation Program 5J-2 Cold-in-Place Recycling A. General Cold-in-place recycling (CIR) is the process of recycling an asphalt pavement in-place
More informationRecommended Specifications For Portland Cement Pervious Pavement
Recommended Specifications For Portland Cement Pervious Pavement Foreword Portland Cement Pervious Concrete Pavements have become increasingly popular as a method to meet water quality water run off regulations
More informationSOM August 2009 Alaska
Asphalt Rubber Finishing Course (ARFC) The end of the road for the tire. The beginning of the road for a quieter, smoother Pavement. SOM August 2009 Alaska Jim Delton, State Materials Engineer, Arizona
More informationWarm Mix Asphalt (WMA) Guide Specification for Highway Construction
Warm Mix Asphalt (WMA) Guide Specification for Highway Construction Division 400 - Asphalt Pavements and Surface Treatments SECTION 4XX - WARM MIX ASPHALT (WMA) PAVEMENT Warm mix asphalt (WMA) is the generic
More informationBACKFILL COMPACTION FOR VOLCLAY WATERPROOFING: An Essential Ingredient for a Successful Project
BACKFILL COMPACTION FOR VOLCLAY WATERPROOFING: An Essential Ingredient for a Successful Project For several years, CETCO has required that soil backfill placed against a foundation wall with Volclay waterproofing
More informationAggregate Specifications
Qualified Aggregate Technician Kentucky Specifications Aggregate Specifications State, FHWA, FAA, Contractor Kentucky Transportation Cabinet 107 Aggregate Size Designations Nominal Maximum Size The largest
More informationSECTION 2 TRENCH AND STRUCTURE EXCAVATION, BACKFILL AND COMPACTION
SECTION 2 TRENCH AND STRUCTURE EXCAVATION, BACKFILL AND COMPACTION 2.01 GENERAL. A. Scope. This section covers excavation, trenching, backfilling and grading incidental to the construction of sewers, pipelines
More informationCHAPTER 2. Restricted Residential ½ Street** Design Speed 25 MPH 25 MPH 25 MPH 25 MPH 40 MPH 50 MPH 55 MPH
CHAPTER 2 201 ROADS 201.1 General This section is to assist the designer in determining what is needed for the design of roads in public rights-of-way. For these standards, the terms used are: Restricted
More informationFull-Depth Reclamation with Cement
Full-Depth Reclamation with Cement 28th Annual Regional Local Roads Conference David L. Rettner Sr. Vice President American Engineering Testing, Inc. Design Construction Field Testing Performance Types
More informationSubgrade Modification A Practitioner s Experience With Sustainable Materials
Subgrade Modification A Practitioner s Experience With Sustainable Materials Terrence McCleary McCleary Engineering, 111 South 2 nd Street, Tonica, Illinois 61370, USA. E-mail: .
More informationHow to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.
1 How to Select the Appropriate Pavement Rehabilitation Option David Rettner, PE American Engineering Testing, Inc. 2 Pavement Rehabilitation Selection Understanding the Problem 3 Pavement Assessment Pavement
More informationSECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM
SECTION 32 32 23 SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM PART 1: GENERAL 1.01 Scope Work includes furnishing all materials, labor, equipment, and supervision to install a Stonebridge segmental
More informationPlantmix Asphalt Industry of Kentucky Winter Meeting February 10, 2011
Plantmix Asphalt Industry of Kentucky Winter Meeting February 10, 2011 AASHTO Guidelines for Geometric Design of Very Low-Volume Local Roads (2001) ADT 400 AASHTO Guide for Design of Pavement Structures
More informationC. Foundation stabilization for pipe and utility structures.
PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization
More informationSECTION IV. PIPELINE EXCAVATION AND BACKFILL
SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include
More informationWhat is it? What is Granular Base Stabilization ti (GBS)? Emulsion Full Depth Reclamation Process
Emulsion Full Depth Reclamation and Granular Base Stabilization An Engineered Approach 47 th Idaho Asphalt Conference Rocktober 25 th, 2007 Full Depth Reclamation (FDR) What is it? Rehabilitation technique
More informationStormTech Construction Guide
A division of StormTech solid end caps and pre-cored end caps StormTech chambers StormTech manifolds and fittings Acceptable fill materials per Table 1 Woven and non-woven geotextiles 80-7 DC REQUIRED
More informationSTANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL
STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19-1 19-1.01 Exploratory Excavation... 19-1 19-1.02 Trench... 19-1 19-1.02.AStorm Drain Pipe...
More information610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT
SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT 610.1 DESCRIPTION Construct a wearing surface composed of an asphalt prime coat followed by the applications of 2 asphalt seal coats and cover material as specified
More informationSACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG):
SACRAMENTO COUNTY ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG): ARHM-GG shall conform to the provisions for Type "A" asphalt concrete in Section 39, "Asphalt Concrete," of the State Standard Specifications
More informationSECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS
SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint
More informationPERMEABLE INTERLOCKING PAVERS
PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement
More informationMix Design & Construction -1-
Mix Design & Construction -1- AGENDA RCC Mix Design RCC Mix Production RCC Construction Process -2- THE FINAL SURFACE TYPE WILL DICTATE THE NECESSARY TECHNIQUES & EQUIPMENT NEEDED TO BE SUCCESSFUL Natural
More informationPAVING SLABS ON A CONCRETE BASE
SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.
More informationAsphalt Guidelines. Courtney Rousseau, P.E. Lloyd Consulting Group, LLC
Asphalt Guidelines Courtney Rousseau, P.E. Lloyd Consulting Group, LLC Objectives Review typical asphalt sections and other key components to ensure optimal material usage for your project Review hot mix
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SUPERPAVE HMA MIXTURES. C&T:CJB 1 of 5 C&T:APPR:SJP:DBP: FHWA:APPR:
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SUPERPAVE HMA MIXTURES C&T:CJB 1 of 5 C&T:APPR:SJP:DBP:10-03-07 FHWA:APPR:10-05-07 a. Description. This work shall consist of furnishing a HMA
More informationSECTION RIPRAP, BOULDERS, AND BEDDING
SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and
More informationTABLE OF CONTENTS. Background of Existing Facility 3. Proposed Work 4
TABLE OF CONTENTS SECTION PAGE Background of Existing Facility 3 Proposed Work 4 Objective of this Report 4 Required Data 4 Pavement Design Procedure 5 Other Data Requirements 7 Pavement Structures 8 Pavement
More informationInverted Pavement VULCAN MATERIALS COMPANY S EXPERIENCE
erted Pavement VULCAN MATERIALS COMPANY S EXPERIENCE What is an erted Pavement 2 to 3¼ HMA 6 to 8 Unbound Aggregate Base Compacted to 100% + Modified Proctor 6 to 10 Cement-Treated Base ( 4% cement) Prepared
More informationLS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION
LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete
More informationCold Central Plant Recycling (CCPR) China Experience
Cold Central Plant Recycling (CCPR) China Experience 2014 International and Western States Recycling Conference Denver - August 7 th, 2014 Stephane Charmot, PhD, PE Meadwestvaco Outline Background China
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More informationCHAPTER 7 PAVEMENT DESIGN. 1. Gradation (sieve and hydrometer analysis) 3. Moisture density relationships and curves
CHAPTER 7 PAVEMENT DESIGN 7.0 GENERAL The purpose of this chapter is to define the requirements for design of pavement within proposed and existing roadways for new subdivision streets and secondary roads.
More informationSECTION CONTROLLED LOW STRENGTH MATERIAL
SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including
More informationPolymeric Sand. Guide. for Pavement Joints. Installation. Easy to use Stays within joints HP POLYMERIC SAND RG+ POLYMERIC SAND. techniseal.
Polymeric Sand for Pavement Joints Easy to use Stays within joints Installation Guide techniseal.com TECHNISEAL POLYMERIC SAND FOR PAVEMENT JOINTS is a high-tech mix of graded sand and binder, specially
More informationTRENCH EXCAVATION AND BACKFILL
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction Section 300 - Trench Excavation and Backfill TRENCH EXCAVATION AND BACKFILL PART - GENERAL.0 SECTION INCLUDES A. Trench Excavation
More informationInformation Bulletin:
Equipment Advisory Adv. No. 2015012 R1 Supersedes: Adv. No. 2015012 R0 Issue Date: April 21, 2015 File: 1649.10 Information Bulletin: Backfill Revision Note Revised text since R0 edition is shown with
More informationExcavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.
Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet
More informationGravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures
A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures lower in height that use the FrogStone unit weight combined with gravel core infill to resist earth pressures
More informationSECTION 3: SUB BASE AND BASE COURSES
SECTION 3: SUB BASE AND BASE COURSES Page i TABLE OF CONTENTS SECTION 3: SUB BASE AND BASE COURSES i SECTION 3.01 MATERIALS FOR SUB-BASE AND BASE COURSES 1 3.01.01 SCOPE 1 3.01.02 GENERAL 1 3.01.03 GRANULAR
More informationINDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1
March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural
More informationUNDERSTANDING UNPAVED ROAD MATERIAL PERFORMANCE INTERPRETATION David Jones, PhD University of California Pavement Research Center
UNDERSTANDING UNPAVED ROAD MATERIAL PERFORMANCE INTERPRETATION David Jones, PhD University of California Pavement Research Center Unpaved road performance is linked to material properties, road shape and
More information205 - EXCAVATION AND EMBANKMENT FOR HIGHWAYS SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS
SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS 205.1 DESCRIPTION Excavate, haul, place, remove and dispose of the specified materials. Construct the embankments as specified in the Contract Documents.
More informationCity of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL
January 2000 Page 1 of 10 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 APPROVALS PART 2 PRODUCTS 2.01 CEMENT 2.02 WATER The General Conditions of the Contract,
More information1985: FT02 Kuala Lumpur - Kuantan (Temerloh) 1988: FT08 Pagar Sasak - Merapoh, Pahang
Cold In-Place Recycling in Malaysia INTRODUCTION CIPR technique was first introduced in Malaysia in mid 1980 s. o o 1985: FT02 Kuala Lumpur - Kuantan (Temerloh) 1988: FT08 Pagar Sasak - Merapoh, Pahang
More informationSECTION STORM DRAIN
PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract
More informationAn Overview of Low Cost Pavement Alternatives in Canada
An Overview of Low Cost Pavement Alternatives in Canada Venkat Lakkavalli P. Eng., M. Sc. Leader, Pavement Engineering The City of Calgary Alberta, Canada Acknowledgement Acknowledge Authors, Co-authors
More informationResilient Moduli and Structural Layer Coefficient of Flyash Stabilized Recycled Asphalt Base
27 World of Coal Ash (WOCA), May 7-1, 27, Northern Kentucky, USA http://www.flyash.info Resilient Moduli and Structural Layer Coefficient of Flyash Stabilized Recycled Asphalt Base Anil Misra 1, Sunil
More informationCement Stabilized Aggregate Base
Supplemental Technical Specification for October 28, 2015 Cement Stabilized Aggregate Base SCDOT Designation: SC-M-308 (10/15) 1. SCOPE 1.1. Cement Stabilized Aggregate Base (CSAB) consists of aggregate,
More informationCETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE
CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE 1.0 GENERAL 1.1 Scope A. This specification guideline covers the technical requirements for furnishing all labor, materials, equipment, and incidentals
More informationRoadway Base Stabilization Current Practice
Roadway Base Stabilization Current Practice AGC MNDOT TRANSPORTATION CONSTRUCTION AND GRADING INNOVATIONS FORUM December 6, 2016 OVERVIEW ROAD TYPES BASE STRENGTHENING APPLIES TO ALL KEY CONSIDERATIONS
More informationITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS
ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown
More informationStudent Services & Classroom Addition
SECTION 321216 - ASPHALT PAVING PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationCHAPTER 10 PAVEMENT DESIGN AND REPORT TABLE OF CONTENTS
CHAPTER 10 PAVEMENT DESIGN AND REPORT TABLE OF CONTENTS Section Title Page 10.1 General... 10-1 10.1.1 Existing Streets...10-1 10.1.2 AASHTO Design...10-1 10.1.3 Pavement Type...10-1 10.1.4 Treated Subgrade...10-1
More informationPuerto Rico. Pavement Preservation Conference and Technology Implementation. US. Department of Transportation Federal Highway Administration
Puerto Rico Pavement Preservation Conference and Technology Implementation US. Department of Transportation Federal Highway Administration Cold In-Place Asphalt Recycling Overview Michael L. Polak E.J.
More informationNova Scotia 2009 Pavement Preservation. Jim Chisholm Highway Construction Services
Nova Scotia 2009 Pavement Preservation Jim Chisholm Highway Construction Services 2009 Construction Overview Pavement Preservation Hot Mix Asphalt Overlays Cold in Place Recycling Pulverization/Graveling/HMA
More informationRoad Stabilization And Dust Control
Road Stabilization And Dust Control What to expect from SOS Environmental & Services? Dust Control? Less Road Maintenance Choices to meet needs and budget Technical Support Road Stabilization? Sub base
More informationCHAPTER 3 CONSTRUCTION AND TESTING OF SUBGRADE
CHAPTER 3 CONSTRUCTION AND TESTING OF SUBGRADE WHAT IS SUBGRADE? SUBGRADE EMBANKMENT FOUNDATION The top surface of an embankment or cut section, shaped to conform to the typical section upon which the
More informationITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS
ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing
More information