Public Utilities Supplemental Specifications

Size: px
Start display at page:

Download "Public Utilities Supplemental Specifications"

Transcription

1 Public Utilities Supplemental Specifications Work Sequencing Sanitary Sewer Manhole and Manhole Inserts Water and Sanitary Sewer Record Drawings Contractor Compliance with Stormwater Pollution Prevention Test Pits Underground Sewer Service Lateral Tracer Wire Contractor to Obtain Construction General Permit

2 SUPPLEMENTAL SPECIFICATION FOR WORK SEQUENCING (PUBLIC UTILITIES PROJECTS) The Contractor shall submit, for review and approval by the Owner, a plan for the sequence of construction prior to commencing construction activities. The guiding concept of this plan will be to provide the shortest-term disruption to the project area residents or businesses. For all new pipe installations, the Contractor shall complete testing, and site restoration along each block or street section, not to exceed 1,000 feet, before continuing construction. The 1,000 feet is the maximum unrestored work length and is based upon the aggregate of unrestored work within the entire project and is not per block, street, or section. For water and sanitary sewer rehabilitation and replacement projects, the Contractor shall complete testing, and site restoration along each block or street section, not to exceed 1,000 feet, before continuing construction. Work will be sequenced in logical areas of the project neighborhood or groups of adjacent street sections. The 1,000 feet is the maximum unrestored work length and is based upon the aggregate of unrestored work within the entire project and is not per block, street, or section. Site restoration includes, but is not limited to pavement patching, concrete replacement, and cleanup. At the discretion of the Owner, the Contractor may be allowed to continue construction activities beyond the stated limits provided additional Contractor resources are being applied expeditiously to testing and site restoration. The Project Manager and the Inspector will review the approved plan for construction sequence monthly to compare the approved plan and actual work completion. If conditions have rendered the plan invalid, the Contractor will be required to submit an updated plan for construction sequence for review and approval. If the Contractor fails to restore the work area in a timely manner, the Owner may suspend additional construction activities and redirect Contractor resources to site restoration. Return to Top 1

3 SUPPLEMENTAL SPECIFICATION FOR SANITARY SEWER MANHOLES AND MANHOLE INSERTS 1. Manhole frames and covers shall be roadway type with deep socket covers and shall be fitted with dust covers and manhole inserts. Machine the frames and covers to prevent rattling. Each cover shall be cast or embossed on it in letters not less than 1-inch high "SEWER." The frame and cover assembly shall weigh at least 380 pounds. Acceptable manufacturers of manhole frame and covers are limited to those on the City s internet site as being approved by the City of Virginia Beach Department of Public Utilities product selection committee. All frames and covers shall receive a coat of black asphalt paint prior to delivery. The dust cover shall be 5/8-inch thick by 23-1/2-inch diameter and furnished with two 1-1/4-inch round handles at 180 degrees. All castings shall conform to the latest edition of ASTM A-48 Class 30 and shall be uniform in quality. 2. Manhole inserts shall be manufactured from corrosion-proof stainless steel suitable for atmospheres containing hydrogen sulfide and diluted sulfuric acid and other gasses and liquids associated with sanitary sewer collection systems. The insert shall be manufactured to fit the dust cover ring, upon which it rests. A vent hole and/or a valve, or a self-sealing gas detection pressure port, shall be provided. The hole or valve shall allow a maximum release of 0.5 to 1.5 psi and 5 gallons of water per 24 hours and must be unaffected by debris that may collect in the bottom of the insert. a. The insert body shall be manufactured of 304 stainless steel with a thickness of not less than 18 gauge. The insert body shall have a straight-side design and be properly sized to fit into the manhole frame ring, or dust cover ring, as applicable, for easy removal. b. The outside rim of the insert shall be manufactured with a gasket to provide a seal between the insert rim and the dust cover ring upon which it rests. The gasket material shall be made of close-cell neoprene and have a pressure sensitive adhesive on one side. The gasket shall be installed by the manufacturer and must be compatible with the insert material to form a long-lasting bond in wet or dry conditions. c. The insert shall have a stainless steel "D" type spring-loaded handle, with rubber coated grip, attached to the body of the insert with high-grade stainless steel continuous fillet type weld. d. Acceptable manufacturers of manhole inserts are limited to those on the City s internet site as being approved by the City of Virginia Beach Department of Public Utilities product selection committee. 3. Manhole steps for precast concrete manholes shall be limited to those on the Department of Public Utilities Approved Products List. 4. Precast manhole sections shall meet requirements of ASTM C No reduction in the inside diameter of large sanitary sewer manholes will be allowed below the cone section. 5. Protective coating for concrete manhole interior section shall be limited to those on the Department of Public Utilities Approved Products List, and in accordance with the construction plans and specifications. Revised January

4 6. Pipe to manhole connection shall be sealed with a flexible connector. The port shall be cored to the size, shape, surface finish and location required and not cast in the manhole. The flexible connector shall be a rubber sleeve with adjustable sealing bands meeting ASTM C specifications. The flexible connector shall be limited to those on the Department of Public Utilities Approved Products List. 7. Standard Manhole Frame and Cover shall be measured for each frame and cover complete with dust cover and manhole insert installed. 8. Standard Sanitary Sewer Manhole Frame and Cover shall be paid for at the contract unit price for each frame and cover complete with dust cover and manhole insert installed including adjustment to final grade. Return to Top Revised January

5 SUPPLEMENTAL SPECIFICATION FOR WATER AND SANITARY SEWER RECORD DRAWINGS 1. The Contractor shall maintain and keep one (1) set of drawings on site, updated with all changes made during the construction of this project. That set will become the "record drawings" and shall include the following information as a minimum: A. Size, material, horizontal location and vertical elevation of existing public and private utilities uncovered during the course of the work. This shall include telephone cables and conduits, TV cables, electrical cables and conduits, gas lines, water lines, sewer force mains, sanitary sewers, storm sewers, and the like. B. Horizontal location and vertical elevation of installed water mains and vacuum mains at every 100-foot station and at all fittings. Horizontal location and vertical elevation of force mains shall be recorded every 18-feet (every pipe joint) and at all fittings. C. Location (horizontal and vertical) and size of sanitary sewer taps and water main taps made, including corporations used for testing and chlorinating purposes; stations and offset distances to new water meter boxes, sanitary sewer cleanouts, and vacuum pits; and size of water and sanitary sewer service lines installed. D. Sizes and types of materials used, changes in sizes and types of materials, rim and invert elevations of manholes, mainline cleanouts, sanitary sewer cleanouts, and vacuum valve pits installed or tied into. All materials installed shall be identified with manufacturer s name. E. When constructing Vacuum Sanitary Sewer Systems, the Contractor shall complete standard pit drawings in conformance with the standard format provided by the Owner. Pit drawings shall include; type of pit, (deep or standard.), horizontal and vertical elevations for all sanitary sewer laterals including the location of cleanouts, the rim elevation of the valve pit, and the property addresses that correspond to each lateral. F. Location (horizontal and vertical) and size of lines plugged, capped, or abandoned. G. Location (horizontal and vertical) of sleeves, bends, reducers, restrained fittings and type of restraint used. H. Depth from rim of valve box to top of operating nut on valves, and length of valve extensions installed. I. Swing ties, station and offset distances to structures installed such as manholes, mainline cleanouts, air vents, hydrants, valve boxes, blow-offs, and vacuum gauge taps. Swing tie measurements shall be from permanent structures (e.g., power/telephone poles and storm sewer structures). 2. Monthly progress payments will not be approved for payment until the Project Manager and the Inspector have verified the Contractor's record drawings are current with construction. 1

6 3. The following guidelines for the accuracy of measurement for the record drawings shall apply: A. Gravity-fed and vacuum systems, both surface and sub-surface, require +/- 0.01' vertical and +/- 1' horizontal. B. Pressure systems (water and sanitary sewer force main) both surface and sub-surface, require +/- 0.1' vertical and+/- 1' horizontal. C. Utility service connections (water and sanitary sewer) shall follow the same guidelines applicable to the main system. 4. Within 30 calendar days after the end of construction, at or before submission of the final invoice, the Contractor shall provide the Inspector with one complete set of record drawings for the project, which must include any field changes or change orders authorized by the Owner, and which accurately reflect the as-built construction. Notations shall be neat and complete. 5. The cost of preparing the record drawings will not be measured separately and shall be included in various other items of work. 6. These drawings are a specific contract requirement of the Contractor. Final payment will not be made until these drawings have been submitted in a form accepted and approved by the Owner. Return to Top 2

7 SUPPLEMENTAL SPECIFICATION FOR CONTRACTOR COMPLIANCE WITH STORMWATER POLLUTION PREVENTION PLAN Effective Date: July 1, SCOPE: If a Stormwater Pollution Prevention Plan (SWPPP) was prepared for this project, the procedures contained herein specify the requirements that the Contractor and all subcontractors involved in land disturbing activities shall follow to ensure that the SWPPP for this project is adhered to. 2.0 BACKGROUND AND PURPOSE: The Virginia Department of Environmental Quality (VDEQ) has authorized the City of Virginia Beach (Owner) to discharge stormwater from this project under a Stormwater General Permit (VAR 10) issued pursuant to the Virginia Stormwater Management Program (VSMP) and the Virginia Stormwater Management Act and implementing regulations (9 VAC et seq.). As required by the Stormwater General Permit, included herein, a SWPPP has been prepared for this project. The SWPPP is incorporated in the Project Manual and is intended to control waterborne pollutant discharges in stormwater by some combination of interception, filtration and containment. The SWPPP requires that all land disturbing activities and associated pollution prevention measures be documented, inspected and maintained throughout the construction phase of the project until final stabilization is achieved and a Notice of Termination has been sent to VDEQ. The Owner has also developed an Erosion and Sediment Control (E&S) Control plan for this project. The approved E&S Control plans are incorporated into the SWPPP and shall be followed as part of the procedure for complying with the SWPPP. 3.0 COMPLIANCE PROCEDURES: A. Contractor Review and Acknowledgment of SWPPP; Inspections Conducted by Qualified Personnel: The Contractor and all subcontractor(s) involved in earthwork / land disturbing activities shall: 1) Review and comply with the SWPPP. 2) Execute the Contractor Delegation of Authority Form by an officer of the Contractor s Company, include it in the SWPPP and return a copy of the same to the Owner prior to commencement of construction (see Section III K of the General Permit for Signatory Requirements). 3) Sign the Contractor s Acknowledgement Form, include it in the SWPPP and return a copy of the same to the Owner prior to commencement of construction. 4) Ensure that all site personnel involved in earthwork operations / land disturbing activities are identified in and understand the requirements of the SWPPP. 5) Indicate in the SWPPP the names of all subcontractors involved in earthwork/land disturbing activities, submit Contractor s Acknowledgement Forms signed by all subcontractors performing earthwork/land disturbing activities to the Owner prior to commencement of construction and maintain copies of the same in the SWPPP. 1

8 6) Maintain a copy of the Registration Statement, Stormwater General Permit coverage verification letter, Stormwater General Permit and SWPPP on site at all times. 7) Provide Qualified Personnel to the project at all times. The Qualified Personnel will be responsible for conducting all required SWPPP inspections and insuring all related SWPPP documents are up to date and in full compliance with the permit requirements. The Qualified Personnel shall at a minimum: 1) be a Virginia Licensed Professional Engineer; or, 2) be another person who holds a certificate of competency from Virginia Soil and Water Conservation Board in the area of E&S Control Inspector or Combined Administrator, or 3) be a Virginia Certified Responsible Land Disturber. The Contractor s Qualified Personnel must be someone empowered to make modifications to this SWPPP and the pollutant control devices implemented, if needed, in order to increase effectiveness to an acceptable level. 8) Submit current proof of required certification(s) for Qualified Personnel to the Owner prior to the commencement of construction. 9) The Contractor s Qualified Personnel is authorized to recommend and implement modifications to the SWPPP as required to ensure the effectiveness of pollution prevention measures provided, that all such changes are approved by the Owner in writing before implementation unless immediate Contractor action is necessary to prevent unauthorized discharges. If immediate Contractor action is needed, then the Contractor shall notify the Owner of the action as soon as practicable. 10) Ensure that all required inspections are conducted, maintenance and corrective actions are taken, and document annotations are made as required by the SWPPP. 11) Install a sign conspicuously posted near the main entrance of the construction site containing a copy of the permit coverage letter. 12) Immediately contact the Owner if a representative from the VDEQ or the U.S. Environmental Protection Agency (USEPA) arrives on site for any purpose. 13) Cooperate fully and completely with the VDEQ and/or the USEPA representatives and make an immediate log entry of the inspection and the results of such inspection. B. Unauthorized Discharges: 1) The Contractor shall ensure that no discharges other than those authorized by the General Permit leave the site. 2) The Contractor shall notify the Owner of any discharge from the site not specifically authorized by the General Permit in accordance with the procedures contained in Part III (G) of the VSMP Stormwater General Permit. Such unauthorized discharges shall include, but not be limited to: oils, greases and other petroleum products, and hazardous substances of any type. In addition to Owner notification of unauthorized discharges, the Contractor shall: a) Notify the Owner immediately upon discovery of spills involving petroleum, oils, lubricants or other potentially hazardous materials and other pollutants. b) Clean up spilled petroleum, oils or lubricants, or other potentially dangerous materials upon discovery and cooperate fully with the Owner in the clean-up of such spills at the direction of the Owner. c) Document all spills using provided spill report forms and maintain completed spill forms in the SWPPP. C. Requirement to Monitor: 1) Required Recordkeeping: A record of the following dates shall be maintained in the SWPPP by the Contractor: 2

9 a) Commencement and Completion dates of each Land Disturbing Activity: The commencement date for E&S Control measure installation, site clearing, stockpile creation, stockpile removal, stockpile rework and the dates of all other land disturbing activities shall be recorded by the Contractor on the Site Stabilization and Construction Activity Dates form provided in the SWPPP. b) SWPPP Site Map Markup: A copy of the approved E&S Control plan and other such plans and drawings as may be required to depict the items required to be identified by the SWPPP shall be annotated during construction to reflect actual site conditions and the locations of both potential pollutant sources and pollution control measures. Prior to the commencement of construction activities, the contractor shall denote on the approved E&S Control plan sheets provided in the SWPPP the proposed locations for: i. SWPPP required postings ii. Portable toilet(s) iii. Concrete washout area(s) iv. Mason s area(s) v. Topsoil stockpile(s) vi. Portable fuel tank(s) vii. Dumpster(s) and other trash receptacles viii.materials storage and laydown area(s) ix. Vehicle/equipment maintenance area(s) x. Proposed additional erosion and sediment control practices planned by the Contractor not already depicted on the approved erosion and sediment control plans The Owner reserves the right to approve or disapprove the proposed location of any of the aforementioned items at its sole discretion. The Owner will provide written approval or disapproval of the proposed locations to the Contractor. The Contractor shall propose alternate location(s) for any item(s) disapproved by the Owner prior to commencement of construction activities. During construction, addenda, sketches, new sections and/or revised drawings shall be added to the approved SWPPP by the Contractor to reflect current site conditions, the locations of potential pollutant sources and their controls and construction methods. All revisions to the SWPPP must be documented, signed and dated by the Contractor s Qualified Personal and be maintained in the SWPPP Field File. c) Inspections: Reports for all inspections and dates that corrective actions are taken for deficiencies noted in inspections shall be maintained in the SWPPP Field File. d) Temporary Cessation of Activities: When construction activities temporarily or permanently cease on a portion of the site, the dates shall be noted. e) Stabilization: When permanent or temporary stabilization of exposed earth areas occur, the dates shall be noted. 2) Required Inspections: Between the times the SWPPP is implemented and final stabilization of the site occurs, inspections shall be conducted jointly by the Contactor s Qualified Personal and the Owner s Inspector. At least once every four business days, inspections shall be coordinated with the Owner s Inspector for review of site findings. The Contractor shall utilize the Owner s standard inspection checklist when conducting and recording inspections. All corrective actions required to prevent soil and suspended sediment loss from the site through stormwater shall be noted on the plans. The Contractor 3

10 shall make all SWPPP documents and the Field File available to the Owner monthly for review and conformation of permit compliance prior to the acceptance of each pay request for each period for which the Contractor is seeking payment. 3) Inspection Items: The Contractor shall utilize the standard inspection form provided by the Owner in all SWPPP inspections. In general, the following items shall be inspected during the events noted above: a) Locations where vehicles enter and exit shall be inspected for evidence of off-site sediment tracking. b) Sediment barriers shall be inspected for sediment trapping effectiveness. c) All disturbed areas and areas used for storing materials (including excess earth) that are exposed to rainfall shall be inspected for evidence of, or potential for, pollutants entering the drainage system or being released off-site. d) Seeded, sodded or otherwise newly vegetated areas shall be inspected to confirm that a healthy stand of vegetation has been achieved for erosion control purposes. e) All discharge points or areas where stormwater may collect before leaving the site to determine whether erosion control measures are effective in preventing impacts to receiving waters. D. System Maintenance and Corrective Actions: System maintenance and corrective actions for all deficiencies noted shall be undertaken by the Contractor within 48 hours of completion of the required inspections. All modifications necessary to increase the effectiveness of the SWPPP shall be made within seven (7) days of discovery of the need for increased effectiveness provided such modifications are approved by the Owner in writing unless immediate Contractor action is necessary to prevent unauthorized discharges. If immediate Contractor action is necessary to prevent unauthorized discharges, then the Contractor shall notify the Owner of such actions as soon as practicable. E. Record Maintenance and Availability: 1) Availability of SWPPP: The Contractor shall maintain the SWPPP and all related documents in the SWPPP Field File on the construction site at all times. The SWPPP shall be made available to any representatives of the VDEQ, USEPA or any representative of the Owner upon request. 2) Notification of Final Stabilization: Upon completion of final stabilization of the construction site, Contractor shall request a final inspection from the Owner. If at the sole discretion of the Owner, a determination is made that the site has achieved final stabilization, the Contractor shall complete and submit two copies of the completed Notice of Termination (NOT) to the Owner. 3) Disposition of Completed SWPPP: The Contractor shall return the complete SWPPP to the Owner upon completion of the project to ensure compliance has been reached. The Owner will retain the project SWPPP for a period of at least three years. 4

11 4) Verification of Compliance: The Contractor shall submit completed Contractor Certification Forms for any subcontractors performing land disturbing activities for which the Contractor is seeking payment as well as making the SWPPP Field File and related documents available to the Owner monthly for review and conformation of permit compliance for the payment period with each payment request for the project submitted to the Owner. If the project SWPPP Field File is found to not be in compliance the payment request will be noted as incomplete and will be returned to the Contractor without action by the Owner. Contractor shall submit the final annotated SWPPP along with a certification of compliance and two copies of the completed Notice of Termination to the Owner with the request for final payment on the project. A complete final payment request shall include the completed SWPPP Field File, including addenda, sketches, new sections and/or revised drawings. An incomplete final payment request will be returned to the Contractor without action by the Owner. 4.0 MEASUREMENT AND PAYMENT: Full compliance with the SWPPP will not be measured separately and shall be considered incidental to other pay items. Return to Top 5

12 SUPPLEMENTAL SPECIFICATION FOR TEST PITS 1. Description: This item will consist of performing test pits within the project for the purpose of locating underground utilities prior to excavation. Prior to any test pit operation, the Contractor is to review the location, number of test pits and the existing utilities with the Inspector. The Contractor shall obtain the vertical and horizontal location, measured off of the construction center line or base line, and will determine the size of the utility line being test pitted. Test pits performed without prior authorization from the Inspector will be at the Contractor's expense. 2. Materials: Materials for backfill and pavement replacement shall meet applicable provision of these specifications. 3. Method of Measurement: Test Pits will be measured in units of each. 4. Method of Payment: Test Pits will be paid for at the contract bid price. Such price will be full compensation for all tools, labor, materials, survey equipment and incidentals necessary to complete the work. Payment will be made under: Pay Item Test Pits Pay Unit Each Return to Top 1

13 SUPPLEMENTAL SPECIFICATION FOR UNDERGROUND SEWER SERVICE LATERAL TRACER WIRE Description: Copper tracer wire shall be installed with all PVC sanitary sewer lateral services. The wire shall extend from the mainline wye along the centerline of the lateral pipe and terminate at the cleanout. The wire shall be fastened to the lateral pipe and cleanout with stainless steel bands or plastic wire ties. Material: Wire must be UL listed and suitable for direct burial with plastic pipe to facilitate detection and tracing of underground sanitary sewer lateral piping. The wire must be AWG 10 solid copper with green polyethylene insulation, and must be resistant to moisture, chemicals, oil, impact, crush, and abrasion. Wire Specification: Conductor Solid copper per ASTM B-3 Insulation Polyethylene Temperature 60 C dry and wet Voltage 600 volts This item is considered incidental. No additional payment will be made for this work. Return to Top 1

14 1.0 SCOPE: Revised July 2015 SUPPLEMENTAL SPECIFICATION FOR CONTRACTOR TO OBTAIN CONSTRUCTION GENERAL PERMIT Effective Date: July 1, 2015 The Contractor shall submit a Stormwater Pollution Prevention Plan (SWPPP) for review and approval in order to obtain a Construction General Permit (CGP) from Virginia Department of Environmental Quality (VDEQ). A SWPPP was prepared for this project in accordance with Virginia Pollutant Discharge Elimination System (VPDES) as contained in the VDEQ VPDES stormwater general permit and implementing regulations (9VAC et. seq.), and has been included in the bid document. The Contractor may formally submit the provided SWPPP or prepare and submit his own independently. If Contractor chooses to prepare his own SWPPP independently, it shall be at least as stringent as the provided SWPPP. No additional time shall be granted to the Contractor for either preparation and submittal of SWPPP, or approval of same and receipt of CGP. The SWPPP is intended to control pollutant discharges in stormwater by some combination of interception, filtration, and containment. The SWPPP requires all construction related activities and associated pollution prevention measures be documented, inspected, and maintained by the Contractor throughout the construction stages of the project until final stabilization is achieved and a Notice of Termination has been received and accepted by the Department of Public Works VSMP Administrator. 2.0 COMPLIANCE PROCEDURES: A. Contractor Review and Acknowledgment of SWPPP; Inspections Conducted by Qualified Personnel: The Contractor shall: 1) Complete and execute the Construction General Permit Registration Statement upon approval of the SWPPP in accordance with 9VAC The CGP registration statement shall be signed in accordance with 9VAC , Part III K of the General Permit Requirements. 2) Meet with the Public Works VSMP Administrator and submit the CGP registration statement. 3) Pay the permit fees required for the CGP to VDEQ. 4) Provide the Owner a copy of the permit prior to commencement of any construction related activities. 5) Ensure that all site personnel involved in construction related activities are identified in and understand the requirements of the SWPPP. 6) Maintain a copy of the Contractor Certification Forms signed by all subcontractors performing construction related activities prior to commencement of construction in the SWPPP. 7) Ensure Qualified Personnel are authorized to recommend and implement modifications to the SWPPP as required to ensure the effectiveness of pollution prevention measures provided; all such changes must be approved by the Owner in writing before implementation unless immediate Contractor action is necessary to prevent unauthorized discharges. If immediate Contractor action is necessary, the Contractor shall notify the

15 Owner as soon as practicable. 8) Ensure that all required inspections are conducted, maintenance and corrective actions implemented, and document annotations made as required by the SWPPP. 9) Install a rain gauge at the construction site to record rainfall. 10) Install a sign conspicuously posted near the main entrance of the construction site containing a copy of the permit coverage letter and/or any other required documents. 11) Immediately contact the Owner if a representative from the VDEQ or the U.S. Environmental Protection Agency (USEPA) arrives on site for any purpose. 12) Cooperate fully and completely with the VDEQ and/or the USEPA representatives and make an immediate log entry of the inspection and the results of such inspection. B. Required Inspections: The Contractor shall perform inspections once every four business days; schedule of inspections shall be communicated to Owner s Inspector as early as practically possible. Alternative inspection schedules shall not be acceptable. The Contractor shall utilize the standard inspection checklist provided in the SWPPP when conducting and recording inspections. All corrective actions required to prevent soil and suspended sediment loss from the site through stormwater shall be noted on the plans. C. System Maintenance and Corrective Actions: System maintenance and corrective actions for all deficiencies noted shall be undertaken by the Contractor within 48 hours of completion of the required inspections. All modifications necessary to increase the effectiveness of the SWPPP shall be made within seven (7) days of discovery of the need for increased effectiveness provided such modifications are approved by the Owner in writing unless immediate Contractor action is necessary to prevent unauthorized discharges. If immediate Contractor action is necessary to prevent unauthorized discharges, then the Contractor shall notify the Owner of such actions as soon as practicable. D. Disposition of Completed SWPPP: The Contractor shall provide a digital copy (.pdf) of the final completed SWPPP to the Public Works VSMP Administrator upon completion of the project. The Contractor will retain the original project SWPPP for a period of at least three years after acceptance of the Notice of Termination. E. Verification of Compliance: The Contractor shall make the SWPPP Field File and related documents available to the Owner for review and confirmation of permit compliance for each payment request for the project submitted to the Owner. If the project SWPPP Field File is found to not be in compliance, the payment request shall be returned to the Contractor and no payment will be approved by the Owner. 3.0 MEASUREMENT AND PAYMENT: Full compliance with the SWPPP will not be measured separately and shall be considered incidental to other pay items. Return to Top Revised July 2015

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices. SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES B-1 General Notes: SACWSD Standard Construction Drawing Notes 1. No work shall begin on any water or wastewater construction project until the construction

More information

CONSTRUCTION PROCEDURE

CONSTRUCTION PROCEDURE ARTICLE X CONSTRUCTION PROCEDURE Section 1001 General Construction Specifications Sewers shall be constructed in accordance with the requirements of the latest editions of the "State of Ohio, Department

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

INSPECTION AND ACCEPTANCE FOR MAINTENANCE

INSPECTION AND ACCEPTANCE FOR MAINTENANCE Inspection and Acceptance For Maintenance Page 1 (Last revised 6/29/10) INSPECTION AND ACCEPTANCE FOR MAINTENANCE SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Acceptance Sewer As Built Drwg Example

More information

PUBLIC WORKS DEPARTMENT GENERAL NOTES

PUBLIC WORKS DEPARTMENT GENERAL NOTES PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard

More information

CITY OF FARGO SPECIFICATIONS REMOVALS

CITY OF FARGO SPECIFICATIONS REMOVALS REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

CITY OF FARGO SPECIFICATIONS REMOVALS

CITY OF FARGO SPECIFICATIONS REMOVALS REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation

More information

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS SECTION 39 MANHOLES 39-1 GENERAL Sewer and storm drain manholes, consisting of precast concrete manholes or

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details Changes for the 2017 TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details The following changes are made to the existing standards and details to clarify or improve existing information.

More information

APPLICATION FOR RIGHT OF WAY PERMIT

APPLICATION FOR RIGHT OF WAY PERMIT City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER

More information

SECTION NATURAL GAS DISTRIBUTION

SECTION NATURAL GAS DISTRIBUTION SECTION 33 51 00 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413 Page: 1 of 5 CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413 COMMERCIAL/RESIDENTIAL UTILITY PLAN COMPLETENESS CHECK LIST Updated

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork.

1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork. PAGE 334000-1 SECTION 334000 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 2004 Specifications CSJ 1062-04-047 SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 1. Description. Repair, rehabilitate, or replace deteriorated, leaking, or structurally unsound existing sanitary sewer

More information

GENERAL NOTES REQUIRED NOTES ON ALL PLANS

GENERAL NOTES REQUIRED NOTES ON ALL PLANS GENERAL NOTES REQUIRED NOTES ON ALL PLANS ALL MATERIALS, WORKMANSHIP AND CONSTRUCTION SHALL CONFORM TO THE CURRENT CITY OF SANTA ROSA DESIGN AND CONSTRICTIOIN STANDARDS AND CONSTRUCTION SPECIFICATIONS

More information

SECTION 1 GENERAL NOTES

SECTION 1 GENERAL NOTES ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS

More information

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM

DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM DIVISION II TECHNICAL SPECIFICATIONS SECTION S-003 SANITARY SEWER FORCE MAIN SYSTEM TABLE OF CONTENTS: I. DESCRIPTION:... 2 II. COORDINATION:... 2 III. CONSTRUCTION LAYOUT:... 3 IV. MATERIALS:... 3 V.

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater

More information

Construction Documents Checklist

Construction Documents Checklist Construction Documents Checklist The following must be completed prior to final approval of site development plans (Construction Documents) by the Town: Final Drainage Report signed by engineer-of-record

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

Procedures for Connecting to Central Sewer System

Procedures for Connecting to Central Sewer System Procedures for Connecting to Central Sewer System These procedures and requirements are taken from the Taney County Regional Sewer District s appoved Sewer Use Regulation, Article 4 Building Sewers and

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

TABLE OF CONTENTS. Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES. Chapter 4 - SANITARY SEWER. Chapter 5 - STORM SEWER

TABLE OF CONTENTS. Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES. Chapter 4 - SANITARY SEWER. Chapter 5 - STORM SEWER Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES Chapter 4 - SANITARY SEWER Chapter 5 - STORM SEWER Chapter 6 - EXCAVATION, TRENCING, BACKFILLING, AND BEDDING Chapter 11 - CONCRETE CURBS, CURB

More information

DEPARTMENT OF PUBLIC UTILITIES

DEPARTMENT OF PUBLIC UTILITIES DEPARTMENT OF PUBLIC UTILITIES Orangeburg, South Carolina PLUMBING RULES AND REGULATIONS TABLE OF CONTENTS Section Page 1.0 General... 1 1.1 Definitions... 1 2.0 Water Distribution System... 3 2.1 Water

More information

***************************************************************************************************************

*************************************************************************************************************** 02732 SANITARY FORCE MAIN *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 34 00. ***************************************************************************************************************

More information

Residential Sewer Backup Prevention Program

Residential Sewer Backup Prevention Program City of Wheaton Residential Sewer Backup Prevention Program Please Note: The City reserves the right to modify the policies, procedures and rules of this program or discontinue the program in its entirety

More information

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1993 Specifications CSJ 0144-01-060 SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1. General. (1) Scope. This Section includes the furnishing, installation, and subsequent

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

SECTION 10 - TRENCHING AND BACKFILLING

SECTION 10 - TRENCHING AND BACKFILLING SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements

More information

DOCUMENT SPECIAL PROVISIONS

DOCUMENT SPECIAL PROVISIONS DOCUMENT 00813 SPECIAL PROVISIONS ADDENDUM NO. 1, DECEMBER 16, 2016 PRICE ADJUSTMENTS FOR STRUCTURAL STEEL AND REINFORCING STEEL FOR CONTRACTS BID ON OR AFTER APRIL 5, 2011 ENGLISH UNITS December 12, 2016

More information

SECTION CONSTRUCTION SERVICES

SECTION CONSTRUCTION SERVICES SECTION 01100 CONSTRUCTION SERVICES PART 1 GENERAL 1.01 - Section Includes A. Mobilization. B. Construction Surveys. C. Record Documents. 1.02 Description Of Work A. Mobilization: includes the preparatory

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 PART 1 - GENERAL... 2 1.1 Work Included... 2 1.2 Related Sections... 2 1.3 Reference Standards... 2 1.4 Shop Drawings... 3 1.5 Certificates...

More information

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID:

TECHNICAL SPECIAL PROVISION FOR FINANCIAL PROJECT ID: TECHNICAL SPECIAL PROVISION FOR 1001 WATER DISTRIBUTION SYSTEM FINANCIAL PROJECT ID: 200105-7-52-01 The official record of this Technical Special Provision is the electronic file signed and sealed under

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

Section 403. DRAINAGE STRUCTURES

Section 403. DRAINAGE STRUCTURES 403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads

More information

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 33 11 13.24 POLYETHYLENE PRESSURE PIPE PART 1 GENERAL... 2 1.1 Description... 2 1.2 Reference Specification... 2 1.3

More information

GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM

GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM 1. GENERAL 1.01 DESCRIPTION GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS USING THE THERMOFORM (PVC) PIPE LINING SYSTEM A. The Contractor shall furnish all labor, equipment and materials necessary

More information

PERMANENT PAVEMENT REPAIR NO SCALE

PERMANENT PAVEMENT REPAIR NO SCALE SAWCUT EXISTING PAVEMENT 2" BITUMINOUS CONCRETE SURFACE COURSE, CLASS 2 (MIN) CLEAN EDGE PRIOR TO PAVING AND PAINT WITH LIQUID BITUMEN. INSTALL SEALANT OVER JOINT UPON COMPLETION 2" BITUMINOUS CONCRETE

More information

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD SPECIFICATIONS Establishing Minimum Standards for as Related To Fire Protection STANDARD # 103 REVISED 04/01/19 PAGES 7 SCOPE: These specifications shall

More information

SECTION 503 TEMPORARY PAVEMENT RESTORATION

SECTION 503 TEMPORARY PAVEMENT RESTORATION SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with

More information

SECTION GROUND WATER STORAGE TANKS

SECTION GROUND WATER STORAGE TANKS SECTION 33 16 13 GROUND WATER STORAGE TANKS PART 1: GENERAL 1.01 SCOPE A. Section includes requirements for designing, fabricating, and erecting a welded steel ground storage tank. 1.02 SYSTEM DESCRIPTION

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860)

City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT TEL: (860) FAX: (860) City of Middletown WATER & SEWER DEPARTMENT 82 Berlin Street Middletown, CT 06457 TEL: (860) 638-3500 FAX: (860) 343-8091 GENERAL REQUIREMENTS SANITARY SEWER MAIN AND LATERAL INSTALLATION JANUARY 2017

More information

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply: SECTION 400 SANITARY SEWER SYSTEM The design of sanitary sewers shall be in conformance with the applicable sections of the State of Washington, Department of Ecology manual, Criteria for Sewage Works

More information

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections. SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity

More information

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction

More information

Water Pollution Control for Work in Sensitive Areas

Water Pollution Control for Work in Sensitive Areas Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed

More information

NC State University Design and Construction Guidelines Division 33 Utilities

NC State University Design and Construction Guidelines Division 33 Utilities 1.0 Purpose A. These guidelines provide methods and requirements to ensure that the connections, attachments, extensions, or other site utility modifications meet NC State standards. B. NC State is responsible

More information

SUPPLEMENTAL SPECIFICATIONS AND DRAWINGS TO THE IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION TABLE OF CONTENTS

SUPPLEMENTAL SPECIFICATIONS AND DRAWINGS TO THE IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION TABLE OF CONTENTS PREFACE AND CITY ENGINEER S LETTER INDEX OF STANDARD DRAWINGS DIVISION 100 GENERAL CONDITIONS ARTICLE 1 DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms ARTICLE 2 PRELIMINARY MATTERS 2.01 Delivery of Bonds

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

1993 Specifications Contract No SPECIAL SPECIFICATION ITEM Concrete Surface Preparation For Cathodic Protection System Application

1993 Specifications Contract No SPECIAL SPECIFICATION ITEM Concrete Surface Preparation For Cathodic Protection System Application 1993 Specifications Contract No. 6033-36-001 SPECIAL SPECIFICATION ITEM 7182 Concrete Surface Preparation For Cathodic Protection System Application 1. Description. This Item shall govern for the providing

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: CONSTRUCTION SURVEY PART 1 - GENERAL 1.01 SECTION INCLUDES Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: A. Construction Survey: 1. Project

More information

CITY OF WESTLAND, MICHIGAN MIDDLE BELT ROAD SANITARY PUMPING STATION MODIFICATIONS

CITY OF WESTLAND, MICHIGAN MIDDLE BELT ROAD SANITARY PUMPING STATION MODIFICATIONS CITY OF WESTLAND, MICHIGAN MIDDLE BELT ROAD SANITARY PUMPING STATION MODIFICATIONS BIDS TO BE RECEIVED UNTIL 2:00 p.m., LOCAL TIME, TUESDAY, AUGUST 19, 2014 AT THE OFFICE OF THE FINANCE DEPARTMENT LOCATED

More information

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000

More information

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO.

SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. 2017-1 43 SOUTH GRANVILLE WATER AND SEWER AUTHORITY H STREET BY-PASS

More information

STANDARD SPECIFICATIONS

STANDARD SPECIFICATIONS TOWN OF COLONIE DEPARTMENT OF PUBLIC WORKS DIVISION OF PURE WATERS STANDARD SPECIFICATIONS for RESIDENTIAL SANITARY SEWER CONNECTIONS Latest Revision Date: November 2017 TABLE OF CONTENTS Section Page

More information

SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION

SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION SECTION VI POTABLE WATER, RECYCLED WATER, AND SANITARY SEWER SYSTEM FACILITY CONSTRUCTION A. CONSTRUCTION STEPS

More information

SECTION FACILITY LIGHTNING PROTECTION

SECTION FACILITY LIGHTNING PROTECTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 41 00 FACILITY LIGHTNING PROTECTION SPEC WRITER NOTE: Delete between //----//if not applicable to project. Also delete any other item or paragraph not applicable

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

REGIONAL CONSTRUCTION STANDARDS

REGIONAL CONSTRUCTION STANDARDS REGIONAL CONSTRUCTION STANDARDS SIXTH EDITION Publication Update 6.5 (Full Committee Approved Proposed Revision 6.5 Storm Sewer Joint Wrap - Section 302 As Publication Update 6.5) March 27, 2018 Copyright

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

SECTION WATER DISTRIBUTION SYSTEM

SECTION WATER DISTRIBUTION SYSTEM Conditions of Use/ Responsibility of Data Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK These guideline specifications are to be used by the A/E as a base document in the development

More information

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET

LAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000

More information

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete. SECTION 02720 STORM DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-place Concrete. 1.02 REFERENCES

More information

City of Logan Sanitary Sewer Design Standards

City of Logan Sanitary Sewer Design Standards City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR

More information

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005 Subdivision Requirements Manual Page 1 of 5 PART I - GENERAL 1.1 Related Work.1 Rough Grading: Section 02211 1.2 Scope of Work.1 This section includes the supply and installation of all labour and materials

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.

More information

New Administration Building

New Administration Building New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

Job Order Sewer Repair Services

Job Order Sewer Repair Services Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified

More information

Section 4 Service Lines

Section 4 Service Lines Section 4 Service Lines A. General 1. A service line is that portion of a sanitary sewer line that extends from the outer building wall or foundation wall to its connection with the sewer lateral at the

More information

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE SECTION 308 BORING AND JACKING PART 2 MATERIALS 2.2 STEEL CASING PIPE E. Casing pipe length shall conform to City of Meridian Standard Drawing SW1 Casing Length Requirements. 2.4 CARRIER PIPE SKIDS A.

More information

SECTION 2100 WATER MAIN

SECTION 2100 WATER MAIN SECTION 2100 WATER MAIN WATER MAIN PART 1 GENERAL 1.01 Section Summary A. This section includes product and installation requirements for water main pipe, gate valves, hydrants, fittings, and miscellaneous

More information