1 FLORIDA DEPARTMENT OF TRANSPORTATION TECHNICAL SPECIFICATIONS For BROOKSVILLE MAINTENANCE YARD FPN# Prepared By: URS CORPORATION SOUTHERN September 2011

2 FLORIDA DEPARTMENT OF TRANSPORTATION TABLE OF CONTENTS For BROOKSVILLE MAINTENANCE YARD SECTION TITLE DIVISION 01 GENERAL REQUIREMENTS SUBMITTALS PRODUCT SUBSTITUTIONS PROJECT CLOSEOUT CLEANING PROJECT RECORD DOCUMENTS GUARANTEES/WARRANTIES/REPAIRS DIVISION 02 - SITE CONSTRUCTION SELECTIVE DEMOLITION DIVISION 03 - CONCRETE "Not Used" DIVISION 04 - MASONRY UNIT MASONRY DIVISION 05 - METALS COLD-FORMED METAL FRAMING METAL FABRICATIONS Brooksville Maintenance Yard TABLE OF CONTENTS Page 1 of 3

3 SECTION TITLE DIVISION 06 - WOOD AND PLASTICS ROUGH CARPENTRY FINISH CARPENTRY/CASEWORK DIVISION 07 - THERMAL AND MOISTURE PROTECTION SEALANTS AND CAULKING DIVISION 08 OPENINGS STEEL DOORS AND FRAMES WOOD DOORS FINISH HARDWARE DIVISION 09 FINISHES GYPSUM WALLBOARD ACOUSTICAL CEILINGS RESILIENT FLOORING PAINTING DIVISION 10 SPECIALTIES FIRE EXTINGUISHERS AND ACCESSORIES TOILET ACCESSORIES DIVISIONS 11 THROUGH 14 "Not Used" DIVISION 15 - MECHANICAL GENERAL MECHANICAL REQUIREMENTS PIPING AND SPECIALTIES INSULATION VIBRATION ISOLATION PLUMBING FIXTURES AND EQUIPMENT HEATING, VENTILATING AND AIR CONDITIONING DUCTWORK AIR DISTRIBUTION DEVICES AUTOMATIC TEMPERATURE CONTROL TEST AND BALANCE Brooksville Maintenance Yard TABLE OF CONTENTS Page 2 of 3

4 SECTION TITLE DIVISION 16 - ELECTRICAL GENERAL ELECTRICAL REQUIREMENTS RACEWAYS WIRES AND CABLES JUNCTION AND PULL BOXES OUTLET BOXES AND FITTINGS WIRING DEVICES PANELBOARDS IDENTIFICATION MOTOR AND CIRCUIT DISCONNECTS FUSES CIRCUIT BREAKERS SUPPORTING DEVICES SURGE PROTECTIVE DEVICES FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS SERVICE ENTRANCE GROUNDING LIGHTING FIXTURES AND LIGHTING CONTROLS LAMPS END OF TABLE OF CONTENTS Brooksville Maintenance Yard TABLE OF CONTENTS Page 3 of 3

5 DIVISION 01 GENERAL REQUIREMENTS

6 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION SUBMITTALS PART 1 - GENERAL 1.01 WORK INCLUDED A. The provisions of this Technical Special Provision Section apply to those required submittals that are related to individual units of Work, not to administrative submittals, such as payment requests, insurance certificates, and progress reports. B. In addition to specific provisions of this Technical Special Provision Section regarding Work-related submittals, Technical Special Provisions Sections in Divisions 02 through 16 contain submittal requirements. C. Specific requirements in other Technical Special Provisions Sections shall take precedence over the general requirements contained in this Technical Special Provision Section RELATED SECTIONS A. PRODUCT SUBSTITUTIONS: Section B. PROJECT CLOSEOUT: Section C. GUARANTEES/WARRANTIES/ REPAIRS: Section SUBMISSION AND APPROVAL SCHEDULE A. Prepare a complete schedule of Work-related submittals, including shop drawings, product data, and samples. Submit this Schedule of Submittals to the Engineer for review and acceptance concurrent with the submittal to the Engineer of the Working Schedule required by Article 8-3 Prosecution of Work of the Florida Department of Transportation (FDOT) Standard Specifications for Road and Bridge Construction, Latest Adopted Edition, as amended. Coordinate this Schedule of Submittals with the Working Schedule and revise as needed to reflect changes in the Working Schedule. The following requirements will be used in evaluating the sufficiency of the Contractor s Schedule of Submittals: 1. Submittals are listed in chronological order based on anticipated submission date. 2. Critical submittals, which will impact the Critical Path of the project, are clearly identified. Brooksville Maintenance Yard SUBMITTALS

7 3. Submittals involving materials, products, and/or items that require a long lead time for procurement are clearly identified. 4. A generic description of work covered by the Submittal is indicated. 5. The Submittal is linked with an activity or event number on the Working Schedule. 6. Identification as to pertinent Technical Special Provisions Section. 7. Item(s) involved. 8. Name of pertinent Subcontractor or supplier and the name of pertinent manufacturer. 9. Schedule date of delivery of pertinent items to the Project. B. Color Schedule: Submit separate listing of items requiring color selection by Engineer PROCEDURE REQUIREMENTS A. Coordination: Coordinate the preparation and processing of submittals with the performance of the Work. Coordinate each separate submittal with other submittals and related activities such as testing, purchasing, fabrication, delivery and similar activities that require sequential activity. 1. Coordinate the submittal of different units of interrelated Work so that one submittal will not be delayed by the Engineer s or the Department s need to review a related submittal. The Department reserves the right to withhold action on any submittal. 2. Scheduling: In each appropriate administrative submittal, such as the Working Schedule, show the principal Work-related submittals and time requirements for coordination of submittal activity with related Work. 3. Coordination of Submittals Times: Prepare and transmit each submittal to the Engineer sufficiently in advance of the scheduled performance of related Work and other applicable activities. Transmit different kinds of submittals for the same unit of Work so that processing will not be delayed by the Engineer s or the Department s need to review submittals concurrently for coordination. 4. Coordinate both procedural timing and listing, including naming and sequencing, of reports and activities required by provisions of this Technical Special Provision Section and other Technical Special Provision Sections, to afford consistency and logical coordination between submitted reports or lists. Maintain coordination and correlation between separate reports by updating at monthly or shorter time intervals. Make appropriate distribution of each report and updated report to entities involved in Work. Brooksville Maintenance Yard SUBMITTALS

8 5. Review Time: No Contract Time extension shall be authorized due to the Contractor's failure to transmit submittals to the Engineer and the Department sufficiently in advance of the Work and in accordance with the approved submittal schedule. B. Submittal Preparation: 1. Each submittal shall comply with Section 5 - CONTROL OF THE WORK of the FDOT Standard Specifications for Road and Bridge Construction, latest adopted edition, as amended, and other requirements contained in this Technical Special Provision Section. 2. Each Submittal shall be organized by the specific Technical Special Provision Section applying to the item or items included in the Submittal and shall be so identified in the Submittal Schedule prepared by the Contractor. Submittals that are not organized by Technical Special Provision Section will not be accepted for review and will be returned to the Contractor without comment. (Example; submittals organized by TSP Section 05500, not Division 05.) 3. Submittals shall be complete and include all items required by the specific Technical Special Provision Section. C. Submittal Transmittal: 1. Package each submittal appropriately for transmittal and handling. Transmit each submittal from the Contractor to the Engineer on a submittal form acceptable to the Department. Submittals received from sources other than the Contractor will be returned to the sender "without action. 2. Record relevant information and requests for data on the submittal form. On the submittal form, or on a separate sheet attached to the form, record deviations from the requirements of the Contract, if any, including minor variations and limitations. Review of a submittal will be undertaken only if all information is provided. 3. Resubmittals whether total or partial shall be clearly marked Resubmittal and handled as submittals herein specified except that the revised information be clearly identified. D. Submittal Numbering: 1. The Contractor shall number consecutively each submittal. This numbering system shall be in order of submittal. Any resubmittal required shall have the same number as the original submittal followed by notation signifying that this is a second (or third, etc.) submittal; example: #10 (2nd submittal), #10a or #10R3. Brooksville Maintenance Yard SUBMITTALS

9 E. Additional Copies: 1. Where applicable the individual Technical Special Provisions Section will indicate if any additional copies of submittals are required above the quantities specified in Section 5 - CONTROL OF THE WORK of the FDOT Standard Specifications for Road and Bridge Construction. 2. If a submittal requires additional copies and those copies are not provided, the Contractor will be notified by the Engineer of the need for these additional copies. The review of the submittal by the Engineer and the Department will proceed, but action on the submittal not be finalized until such additional copies are received. 3. The Contractor will not be entitled to any time extension or other compensation for any delays arising from his failure to provide required additional copies with a submittal SPECIFIC SUBMITTAL REQUIREMENTS A. General: 1. Where it is necessary to provide intermediate submittals between the initial and final submittals, provide and process intermediate submittals in the same manner as for initial submittals. 2. Shop Drawings, Product Data, and Samples submitted to the Engineer for Engineer s review shall first be checked and approved by the Contractor. Shop Drawings, Product Data, and Samples received without the Contractor's approval stamp will be cause for immediate return without further action. Each drawing correctly submitted will be reviewed by the Engineer and the Department and marked accordingly. 3. Specific submittal requirements for individual units of Work are specified in the applicable Technical Special Provision Section. Except as otherwise indicated in the individual Technical Special Provision Sections, comply with the requirements specified herein for each type of submittal. 4. Shop and setting drawings shall present complete and accurate information relative to all working dimensions, equipment weight assembly and sectional view, all necessary details pertaining to coordinating the Work of the Contract, lists of materials and finishes, parts lists and the description thereof, lists of spare parts and tools where such parts or tools are required, no-scale control diagrams for control wiring and control piping, and all other items of information that area required to demonstrate detail compliance with the Drawings and Technical Special Provisions. Brooksville Maintenance Yard SUBMITTALS

10 5. If the Contractor proposes equipment requiring a different layout from that shown on the Drawings and if such substitution is acceptable to the Engineer, the Contractor shall submit drawings showing the revised layout of all affected structures, piping, and equipment. The cost of the revised layout shall be borne by the Contractor. B. Shop Drawings: 1. Information required on shop drawings includes, dimensions, identification of specific products and materials that are included in the Work, compliance with specified standards and notations of coordination requirements with other Work. Provide special notation of dimensions that have been established by field measurement. Clearly indicate deviations from the Contract on the shop drawings. 2. Coordination Drawings: Provide coordination drawings where required for the integration of the Work, including Work first shown in detail on shop drawings or product data. Show sequencing and relationship of separate units of Work that must interface in a restricted manner to fit in the space provided, or function as indicated. Coordination drawings are considered shop drawings. C. Product Data: 1. General information required specifically as product data includes manufacturer's standard printed recommendations for application and use, compliance with recognized standards of trade associations and testing agencies, and the application of their labels and seals (if any), special notation of dimensions which have been verified by field measurement, and special coordination requirements for interfacing the material, product or system with other Work. 2. Preparation: Collect required product data into a single submittal for each unit of Work or system based on Technical Special Provision Section. Mark each copy to show which choices and options are applicable to the Project. Where product data has been printed to include information on several similar products, some of which are not required for use on the project, or are not required for use on the project, or are not included in this submittal, mark the copies to show clearly which information is not applicable. a. Where product data must be specially prepared for required products, materials or systems, because standard printed data is not suitable for use, submit data as shop drawings and not as product data. b. Clearly mark each copy to identify pertinent products or models. c. Show performance characteristics and capacities. Brooksville Maintenance Yard SUBMITTALS

11 D. Samples: d. Show dimensions and clearances required. e. Show wiring or piping diagrams and controls. f. Indicate finish. g. Supplement standard information to furnish information specifically applicable to Work. h. Modify drawings and diagrams to delete information that is not applicable to Work. 1. Submit samples for the Engineer s visual review of type, color, pattern, and texture, and for a final check of the coordination of these characteristics with other related elements of the Work. Samples are also submitted for quality control comparison of these characteristics between the final sample submittal and the actual Work as it is delivered and installed. a. Refer to individual sections of these Technical Special Provisions for additional sample requirements that may be intended for examination or testing of additional characteristics. Compliance with other required characteristics is the exclusive responsibility of the Contractor; such compliance is not considered in the Engineer s and the Department s review and "Action" indication on sample submittals. b. Documentation required specifically for sample submittals includes a generic description of the sample, the sample source or the product name or manufacturer, compliance with governing regulations and recognized standards. In addition, indicate limitations in terms of availability, sizes, delivery time, and similar limiting characteristics. 2. Preparation: Where possible provide samples that are physically identical with the proposed material or product to be incorporated in the Work; provide full scale, fully fabricated samples cured and finished in the manner specified. Where variations in color, pattern, or texture are inherent in the material or product represented by the sample, submit multiple units of the sample (not less than 3 units), which show the approximate limits of variations. Where samples are specified for the Engineer s selection of color, texture, or pattern, submit a full set of available choices for the material or product. Mount, display, or package samples in the manner specified to facilitate the review of indicated qualities. Prepare samples to match the Engineer s sample where so indicated. Brooksville Maintenance Yard SUBMITTALS

12 a. Refer to individual sections of these Technical Special Provisions for samples that are indicated to be returned to the Contractor for incorporation in the Work. Such samples must be in an undamaged condition at the time of use. Indicate such special requests regarding the disposition of sample submittals on the submittal form. 3. Mock-Ups: Mock-ups are special form of samples, which are too large or otherwise inconvenient for handling in specified manner for transmittal of sample submittals. Mock-ups and similar samples specified in individual sections of these Technical Special Provisions are recognized as a special type of sample. Comply with requirements for samples to greatest extent possible, and process transmittal forms to provide records of activity. a. Field Samples: E. Miscellaneous Submittals: (1) Construct mock-up for Engineer s visual examination, for quality control, and performance of required testing. (2) Erect at location acceptable to Engineer. (3) Size of Area: As specified in respective Technical Special Provision Section. (4) Fabricate each sample and mock-up complete and finished using materials, fabrication, and installation methods identical with those indicated for Work. (5) Remove mock-ups at conclusion of Work or when acceptable to Engineer if not incorporated into Work. 1. Inspection and Test Reports: Classify each inspection and test report as being either "shop drawings" or product data" depending on whether the report is specially prepared for the project, or a standard publication of workmanship control testing at the point of production. Process inspection and test reports accordingly. 2. Warranties, Bonds, and Maintenance Agreements: Refer to Technical Special Provision Section GUARANTEES/WARRANTIES/ REPAIRS, for specific general requirements on warranties, product bonds, workmanship bonds, and maintenance agreements. In addition to copies desired for the Contractor s use, furnish two (2) executed copies of such warranties, bonds, or agreements. Provide two (2) additional copies where required for maintenance manuals. 3. Standards: Where submittal of a copy of standards is indicated, and except where copies of standards are specified as an integral part of a Product Data submittal, submit a single copy of standards for the Engineer s use. Where workmanship, whether at the project site or elsewhere is governed by a standard, furnished additional copies of the standard to fabricators, installers and others involved in the performance of the Work. Brooksville Maintenance Yard SUBMITTALS

13 4. Closeout Submittals: Refer to Technical Special Provision Section PROJECT CLOSEOUT, and to individual Sections of these Technical Special Provisions for specific submittal requirements of project closeout information, materials, tools, and similar items. 5. General Distribution: Provide additional distribution of submittals to subcontractors, suppliers, fabricators, installers, governing authorities, and others as necessary for the proper performance of the Work. Include such additional copies of submittals in the transmittal to the Engineer where the submittals are required to receive Action marking before final distribution. Record distributions on transmittal forms CONTRACTOR'S DUTIES A. Review submittals prior to transmittal; determine and verify field measurements, field construction criteria, manufacturer s catalog numbers, and conformance of submittal with requirements of Contract. B. Coordinate submittals with requirements of Work and of Contract. C. Submittals or Accompanying Transmittal Letter Shall Contain: 1. Date of submission and dates of previous submissions when applicable. 2. Project title and number. 3. Contract identification. 4. Names of subcontractor, supplier, and manufacturer. 5. Identification of product with Technical Special Provision Section number. 6. Field dimensions, clearly identified as such. 7. Relation to adjacent or critical features of work of materials. 8. Applicable standards, such as ASTM or Federal Specification numbers. 9. Identification of revisions on resubmittals. 10. Additional information required by Contract. 11. Contractor executed review and approval marking or stamp. 12. Blank space for Engineer s and Department s action marking or stamp. D. Clearly identify on submittals, or in writing at time of submission, deviations in submittals from requirements of Contract. Contractor s responsibility for deviations in submittals from requirements of Contract is not relieved by Engineer s and Department s review of submittals unless the Department gives written acceptance of specific deviations. Brooksville Maintenance Yard SUBMITTALS

14 E. Apply Contractor's mark or stamp, sign, and date, Signature of Contractor s authorized person certified verification of products, verification of field measurements and field construction criteria, and coordination of information within submittal with requirements of work and of Contract. Submittals without Contractor's executed mark or stamp and signature will be returned without disposition. F. Submittals that are received from sources other than through Contractor s office will be returned by Engineer without action. Delays resulting therefrom shall be Contractor s responsibility. G. Package each submittal appropriately for transmittal and handling. H. Distribute reproductions of shop drawings, copies of product data, and samples, which bear Department s stamp of approval, to jobsite file, record documents file, subcontractors, suppliers, and other entities requiring information. I. Do not fabricate products or being work which required submittals until return of submittal with Department s acceptance. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used END OF SECTION Brooksville Maintenance Yard SUBMITTALS

15 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION PRODUCT SUBSTITUTIONS PART 1 - GENERAL 1.01 WORK INCLUDED A. This Technical Special Provision Section defines Products and specified administrative and procedural requirements for handling requests for substitutions PRODUCTS A. The term Product generally refers to materials, products, components, and other items that the Department and the Engineer have determined to be desirable to be incorporated into the project, which meet the established design criteria for the project, and which provide the desired quality. B. The Technical Special Provisions generally list a minimum of three (3) manufacturers/suppliers, with catalog/model numbers, for each product specified. The Contractor is advised that the use of Products on this Project is encouraged and will serve to expedite the review and approval of required submittals SUBSTITUTIONS A. If the Contractor proposes the use of a material, component, or other item for incorporation into the project that is not a Product, such items shall be considered substitutions. Approval of substitutions by the Department is required before the Contractor may make submittals as required by the appropriate Section of the Technical Special Provisions. Approval of substitutions is subject to the following requirements and conditions: 1. The burden of proof that a proposed substitution is equivalent to a Product shall rest entirely on the Contractor. 2. The Contractor shall provide documentation satisfactory to both the Department and the Engineer that the proposed substitution complies with the plans and Technical Special Provisions as follows: a. Applicable Technical Special Provision Section Numbers. b. Applicable Drawing Numbers. Brooksville Maintenance Yard PRODUCT SUBSTITUTIONS

16 Brooksville Maintenance Yard PRODUCT SUBSTITUTIONS

17 c. Samples, where applicable or requested. d. A detailed comparison of the significant qualities of the proposed substitution relative to the specified item. e. Information on how the proposed substitution coordinates with other items of Work on this project including any modifications to the various items of Work necessary to accommodate the substitution. f. Certification by the Contractor that the proposed substitution will perform adequately for the intended application as required by the plans and Technical Special Provisions. 3. The Engineer s decision to accept or reject a proposed substitution shall be final. B. Where an accepted substitution require a different quantity or arrangement of foundations, supports, ductwork, piping, wiring, conduit, and any other equipment or accessories normal for the accepted substitution, the Contractor shall effect all required modifications including the work of other trades impacted by the substitution at no additional cost to the Department. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used END OF SECTION Brooksville Maintenance Yard PRODUCT SUBSTITUTIONS

18 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION PROJECT CLOSEOUT PART 1 - GENERAL 1.01 WORK INCLUDED A. This Section specifies general administrative and procedural requirements for project closeout. The requirements include, but are not limited to, the following: 1.02 RELATED WORK 1. Substantial Completion and Final Acceptance inspection procedures. 2. Project Record Document submittals. 3. Operating instructions and maintenance manual submittals. 4. Submittal of warranties, guarantees, and maintenance agreements. 5. Final cleaning. A. SUBMITTALS: Section B. PRODUCT SUBSTITUTIONS: Section C. CLEANING: Section D. PROJECT RECORD DOCUMENTS: Section E. GUARANTEES/WARRANTIES/REPAIRS: Section SUBSTANTIAL COMPLETION A. Prior to a request for an inspection for Substantial Completion, the Contractor shall maintain the following procedures: 1. The Contractor shall conduct weekly walk-through inspections in the presence of the Engineer in the month prior to the request for Substantial Completion. Each inspection shall determine outstanding work necessary to meet the Substantial Completion requirements stipulation Brooksville Maintenance Yard PROJECT CLOSEOUT

19 under this Section. A list of outstanding work required will be updated by the Engineer with the Contractor weekly. Brooksville Maintenance Yard PROJECT CLOSEOUT

20 2. The outstanding work list will be reduced progressively from the initial weekly inspection until, in the opinion of the Engineer, the Contractor s work qualifies as to the state of readiness for the formal inspection punch-list prior to Substantial Completion acceptance by the Department. B. Substantial Completion acceptance shall require that the following be accomplished: 1. The stage of completeness that constitutes the state of Substantial Completion acceptance is based on the essential completion of the Contract requirements including, but not limited to, the following: a. All civil, structural, architectural, mechanical, plumbing, and electrical work is complete. b. Letter from the Contractor stating that all code violations have been corrected along with copies of Final Inspection Reports representing each discipline to the Building Inspection/Permitting Agency. c. All mechanical, electrical systems have been made operational and tested under the direct supervision of the manufacturer's qualified factory representative, in the presence of the accepting authority having jurisdiction over the Work. (1) The manufacturers have issued a certified letter of compliance and satisfactory operation to the Engineer. (2) The manufacturers have provided the required operation training, for the purpose of aiding the Department's maintenance and operations personnel to become familiar with the systems. d. Turn over all releases enabling the Department unrestricted use of the Work and access to services and utilities. e. Complete clean up requirements, including touch-up painting. Touch-up and otherwise repair and restore marred exposed finishes. f. Provide the Engineer with the following list of approvals and certifications: (1) Letter of approval from the Building Inspection/ Permitting Agency inspector. 2. Upon the confirmation that the above requirements have been satisfied, the Contractor shall request the Engineer to schedule an inspection for Substantial Completion acceptance. Brooksville Maintenance Yard PROJECT CLOSEOUT

21 Brooksville Maintenance Yard PROJECT CLOSEOUT

22 3. The Contractor shall provide the Engineer with a list of all items needed from the Engineer to request a Certificate of Occupancy for the facilities constructed for this project. These items may include, but are not limited to, the following: a. Certification that the structure meets or exceeds the flood plain criteria defined in the FEMA document 44 CFR - Part 60. b. Certification of compliance to the Department of Environmental Regulation Management Pollution Control. 4. After these items are provided, the Contractor may apply to the Building Inspection/Permitting Agency for a Certificate of Occupancy for the facilities constructed by this project. Upon receipt of the Certificate of Occupancy, the Contractor shall provide the following: a. Insurance changeover. b. Make final changeover of permanent locks and transmit keys to the Engineer. Advise the Engineer of changeover in security provisions. C. After the Contractor receives the Certificate of Occupancy, the Department will make a declaration of Substantial Completion acceptance covering only that portion of the Project subject to Substantial Completion acceptance, will occupy the new facilities, and will have two (2) weeks to list any deficiencies not apparent during the inspection for Substantial Completion acceptance. D. Substantial Completion acceptance shall continue until Final Acceptance FINAL ACCEPTANCE A. Prior to a request for an inspection for Final Acceptance, the Contractor shall maintain the following procedures: 1. The Contractor shall conduct weekly walk-through inspections in the presence of the Engineer in the month prior to the request for Final Acceptance. Each inspection shall determine outstanding work necessary to meet the Final Acceptance requirements stipulation under this section. A list of outstanding work required will be updated by the Engineer with the Contractor weekly. The outstanding work list will be reduced progressively from the initial weekly inspection until, in the opinion of the Engineer, the Contractor s work qualifies as to the state of readiness for the formal inspection punch-list prior to Final Acceptance by the Department. Brooksville Maintenance Yard PROJECT CLOSEOUT

23 B. Final Acceptance for the Project shall require that the following be accomplished: 1. All record documents, maintenance manuals, and equipment operational instructions have been turned over to the Department s representatives and equipment operational demonstrations have been performed pursuant to Section PROJECT RECORD DOCUMENTS. 2. All punch list items completed and accepted. 3. Remove temporary facilities from the site, along with construction tools and equipment, mock-ups, and similar elements. 4. Turn over Warranties, Guarantees, Workmanship Bonds, Maintenance Agreements, Final Certifications, and similar closeout documents on various materials, systems and equipment, neatly bound and in order to the Engineer. 5. Turn over extra stock as specified in other Technical Special Provisions to the person designated by the Engineer to be in charge of the operation and maintenance of the building. 6. Provide instruction to Department in maintenance of equipment and finishes. C. Upon Final Acceptance, the Department shall provide written notice to the Contractor for maintenance of the Project. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used END OF SECTION Brooksville Maintenance Yard PROJECT CLOSEOUT

24 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION CLEANING PART 1 - GENERAL 1.01 WORK INCLUDED A. Final Cleaning Prior to Substantial Completion: 1. Provide Final Cleaning of the Work, immediately prior to Substantial Completion acceptance, consisting of cleaning each surface or unit of Work to normal "clean" condition expected for a first-class building cleaning and maintenance program. Comply with manufacturer's instructions for cleaning operations. 2. The following are examples, but not by way of limitation, of cleaning levels required: a. Remove labels which are not required as permanent labels, including all gum residue. b. Clean exposed exterior and interior hard surface finishes, to a dirt-free condition, free of dust, stains, films and similar noticeable distracting substances. Except as otherwise indicated, avoid disturbance of natural weathering of exterior surfaces. Restore reflective surfaces to original reflective condition. Buff out scratches and marks on exposed metal surfaces. c. Clean concrete floors and slabs in non-occupied spaces broom clean. Remove noticeable paint marks and construction stains. D. Clean light fixtures and lamps so as to function at full efficiency. Replace any damaged lens. B. Final Cleaning Prior to Final Acceptance: 1. Provide Final Cleaning of the Work, immediately prior to Final Acceptance expected for a first-class building cleaning and maintenance program. Brooksville Maintenance Yard CLEANING

25 1.02 RELATED WORK 2. The following are examples, but not by way of limitation, of cleaning levels required: a. Clean areas in accordance with Paragraph A. above for building areas affected by the Contractor for work performed after the Substantial Completion acceptance. b. Clean Project site of litter and foreign substances. Sweep paved areas to a broom-clean condition; remove stains, petrochemical spills and other foreign deposits. A. PROJECT CLOSEOUT: Section PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used END OF SECTION Brooksville Maintenance Yard CLEANING

26 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.01 WORK INCLUDED A. Provide Record Documents and Maintenance Manuals: 1.02 RELATED WORK 1. The provisions of this section apply to the maintaining, marking, recording and submitting of Project Record Documents and organizing operating and maintenance data into suitable sets of manuals under this Contract. 2. Do not use record documents for construction purposes, protect from deterioration and loss in a secure, fire-resistive location. Provide access to record documents for the Engineer s reference during normal working hours. A. PROJECT CLOSEOUT: Section B. GUARANTEES/WARRANTIES/REPAIRS: Section SUBMITTALS A. Record Documents: At completion of all Work under this Contract, deliver record documents to the Engineer, in duplicate with transmittal, containing as a minimum, the following: 1. Date. 2. Project title and numbers. 3. Contractor s name and address. Include final list of all subcontractors. 4. Title and number of each record document. 5. Certification that each document as submitted is complete and accurate. 6. Contractor s signature, or that of the Contractor s authorized representative. Brooksville Maintenance Yard PROJECT RECORD DOCUMENTS

27 B. Operating Instructions and Maintenance Manuals: 1. Submit three (3) copies of each completed manual on equipment and systems, in final form, to the Engineer for distribution. Provide separate manuals for each unit of equipment, each operating system, and each electric and electronic system. 2. Refer to Specification Sections for individual requirements on operating and maintenance of the various pieces of equipment and operating systems RECORD DOCUMENTS A. Record Drawings: 1. Maintain a clean, undamaged, updated set of blue or black line whiteprints of Contract Drawings, including sheets issued as part of Department authorized changes, and Shop Drawings. The set shall be marked to scale by a competent draftsman to indicated the actual installation and/or location where the installation and/or location varies substantially from the Work as originally shown due to Addenda, Alternates, Change Orders, Field Orders, etc. 2. Mark whichever drawings are most capable of showing conditions fully and accurately. Where shop drawings are used, record a cross-reference at the corresponding location on the Contract Drawings. 3. Use a red erasable pencil; use other colors to distinguish between variations in separate categories of the Work. 4. Give particular attention to concealed elements that would be difficult to measure and record at a later date. 5. Note related Change Order numbers where applicable. 6. Do not revise the prints by attaching the actual sketches issued by the Engineer. Where the work was installed exactly as shown on the Contract Drawings, the prints shall not be disturbed other than being marked PROJECT RECORD DOCUMENTS". 7. Each sheet shall be clearly marked "PROJECT RECORD DOCUMENTS. 8. Organize record drawing sheets into manageable sets by discipline, bind with durable paper cover sheets, and print suitable titles, dates, and other identification on the cover of each set. 9. Review the completed Project Record Drawings and ascertain that all data furnished on the prints is accurate and truly represents the work as actually installed. Brooksville Maintenance Yard PROJECT RECORD DOCUMENTS

28 10. The record drawing prints, including those changed and unchanged, shall be submitted to the Engineer for compliance review. 11. Any deviations from the method of executing Project Record Drawings as described above will be considered just cause for rejection by the Engineer and the Contractor will be required to conform and resubmit. 12. The record drawings shall be current with each month s pay estimate application, and subject to the Engineer s review for acceptability, as a prerequisite to monthly payment. B. Record Project Manual/Specifications: 1. Maintain one complete copy of the Project Manual, including all addenda, and one copy of other written construction documents such as Change Orders and Modifications issued in printed form during construction. Mark these documents to show substantial variations in actual Work performed in comparison to the text of the Specifications and modifications due to Addenda, Alternates, Change Orders, Field Orders, etc. 2. Neatly cross out the non-conforming portion of the Project Manual and add by writing in the revised portion of the Project Manual. Do not revise the Project Manual by cutting and pasting the actual Addenda, Alternates, Change Orders, Field Orders, etc., as actually issued by the Engineer unless otherwise directed by the Engineer. 3. Give particular attention to substitutions, selection of options and similar information on elements that are concealed or cannot otherwise be readily discerned later by direct observation. Note related Record Drawing information and Product Data. 4. The Volume(s) of Project Manual shall be clearly marked PROJECT RECORD DOCUMENTS. 5. Review the completed Record Project Manual and ascertain that all data furnished on the Project Manual is accurate and truly represents the work as actually installed. 6. Submit the Record Project Manual to the Engineer for compliance review. 7. Any deviations from the method of executing Record Project Manual as described above will be considered just cause for rejection by the Engineer and the Contractor will be required to conform and resubmit. 8. The Record Project Manual shall be current with each month's pay estimate application, and subject to the Engineer's review for acceptability. Brooksville Maintenance Yard PROJECT RECORD DOCUMENTS

29 C. Record Product Data: 1. Maintain one copy of each Product Data submittal. Mark these documents to show significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the site, and from the manufacturer's installation instructions and recommendations. 2. Give particular attention to concealed products and portions of the Work that cannot otherwise be readily discerned later by direct observation. Note related Change Orders and mark-up of record Drawings and Project Manual. 3. Upon completion of mark-up, submit complete set of record Product Data to the Engineer for the Department's records. D. Record Samples: 1. Immediately prior to the date of Final Acceptance, meet at the site with the Engineer and the Department s personnel to determine which of the submitted Samples that have been maintained during progress of the Work are to be transmitted to the Department for record purposes. Comply with delivery to the Department s sample storage area. E. Miscellaneous Record Submittals: 1. Miscellaneous record submittals shall include, but not be limited to, the following: a. Warranties. b. Inspection and test reports. c. Field records. d. Surveys. e. Mix records. f. Inspections by governing authorities. 2. Refer to individual specification sections for requirements of miscellaneous record-keeping and submittals in connection with actual performance of the Work. 3. Immediately prior to date(s) of Final Acceptance, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for continued use and reference. Submit to the Engineer for the Department s records. Brooksville Maintenance Yard PROJECT RECORD DOCUMENTS

30 PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used END OF SECTION Brooksville Maintenance Yard PROJECT RECORD DOCUMENTS

31 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION GUARANTEES/WARRANTIES/REPSIRS PART 1 - GENERAL 1.01 WORK INCLUDED A. This section specifies general administrative and procedural requirements for guarantees, warranties, and related repairs (or replacement) required by the Contract Documents, including manufacturer s standard warranties on products and special warranties. B. Disclaimers and Limitations: Manufacturer s disclaimers and limitations on product warranties do not relieve the Contractor of the warranty on the Work that incorporates the products, nor does it relieve suppliers, manufacturers, and subcontractors required to countersign special warranties with the Contractor RELATED WORK A. PROJECT CLOSEOUT: Section B. PROJECT RECORD DOCUMENTS: Section C. Specific requirements for warranties for the Work and products and installations that are specified to be warranted are included in other TECHNICAL SPECIAL PROVISIONS. D. Certifications and other commitments and agreements for continuing services to the Department are specified elsewhere in the TECHNICAL SPECIAL PROVISIONS CONTRACTOR S GUARANTEE A. Upon completion of the Work, the Contractor shall furnish a written guarantee stating that all materials and workmanship are guaranteed against defects for a period of one (1) year from the Date of Final Acceptance of the Work. Defects due to faulty materials and/or workmanship developed during the guarantee period shall be repaired or replaced, as required, by the Contractor at no additional cost to the Department and as acceptable to the Department. 1. For Contractor s guarantees greater than one (1) year in duration, all Brooksville Maintenance Yard GUARANTEES/WARRANTIES/REPAIRS

32 other provisions as specified in this Section shall remain in force. Refer to other TECHNICAL SPECIAL PROVISIONS for these guarantees. Brooksville Maintenance Yard GUARANTEES/WARRANTIES/REPAIRS

33 B. The guarantee shall state the name of the Department, provide full guarantee terms and conditions, effective date and termination date, and the name, license number, address and telephone number of the Contractor. The guarantee shall be signed by the Contractor or the Contractor s chief executive and notarized. C. The term start of the one (1) year guarantee will not be recognized until all outstanding work items (deficiency list) have been completed and acknowledged as accepted in writing by the Department MANUFACTURER, SUPPLIER, AND SUBCONTRACTOR WARRANTIES A. In addition to the Contractor s one (1) year guarantee, all other manufacturer, equipment supplier, and subcontractor warranties shall commence on the Date of Final Acceptance of the total Contract as acknowledged in writing by the Department, and taken over for use by the Department. 1. Plumbing Fixtures and Plumbing Systems will not be accepted nor the initiation of warranty start recognized until these systems are functioning properly and acknowledged as accepted in writing by the Department. B. Manufacturer and supplier warranties shall not relieve the Contractor of liability under the one (1) year guarantee. Such warranties shall supplement the one (1) year guarantee. 1. Written warranties made to the Department are in addition to implied warranties, and shall not limit duties, obligations, rights, and remedies otherwise available under the law, nor shall warranty periods be interpreted as limitations on time in which the Department can enforce such other duties, obligations, rights, or remedies. 2. Ensure that all warranties comply with these stipulations prior to submission. C. Repairs: 1. All repairs or replacements resulting from a breach of warranty shall be promptly performed. 2. If, with ten (10) calendar days after the mailing date of the written notice by the Department to the Contractor requesting repairs or replacement resulting from a breach of warranty, the Contractor shall neglect to make or undertake with due diligence to make the same, the Department may make such repairs at the Contractor s expense; provided, however, that in the case of emergency where, in the judgment of the Department, delay would cause serious loss or damage, repairs or replacement may be made without notice being sent to the Department, and the Department shall pay the cost thereof. Brooksville Maintenance Yard GUARANTEES/WARRANTIES/REPAIRS

34 1.05 SUBMITTALS A. Submit written warranties to the Department prior to the Date of Final Acceptance. If the Department designates a commencement date for warranties other than the Date of Final Acceptance, or a designated portion of the Work, submit written warranties on the Department's request. B. Warranties shall be submitted properly executed by the Contractor, and also executed by the subcontractor, supplier or manufacturer, or a combination thereof, as stipulated in other TECHNICAL SPECIAL PROVISIONS. Warranties shall also be fully identified and contain all appropriate terms and conditions. C. Provide a bound manual for all manufacturer, equipment supplier, and subcontractor warranties required by the Contract Documents. Identify each warranty with proper TECHNICAL SPECIAL PROVISION. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used END OF SECTION Brooksville Maintenance Yard GUARANTEES/WARRANTIES/REPAIRS

35 DIVISION 02 SITE CONSTRUCTION

36 FLORIDA DEPARTMENT OF TRANSPORTATION SECTION SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 WORK INCLUDED A. Work includes all labor, materials, equipment, and supervision necessary to complete all selective site and building demolition work including salvage, removal and disposal services required for remodeling, renovation, and addition work as indicated on Drawings DEFINITIONS A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled. B. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated. C. Remove and Salvage: Detach items from existing construction and deliver them to Department ready for reuse. D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled QUALITY ASSURANCE A. Qualifications of Demolition Contractor: 1. Demolition shall be performed only by a qualified Contractor with at least five (5) years documented experience in operations of a similar nature. B. Requirements of Regulatory Agencies: 1. Comply with governing local and state safety codes pertaining to demolition work, and the following: a. FDOT Standard Specifications for Road and Bridge Construction, 2010 Edition, as amended. Brooksville Maintenance Yard SELECTIVE DEMOLITION

37 Brooksville Maintenance Yard SELECTIVE DEMOLITION

38 b. ANSI A10.6 Safety Requirements for Demolition Operations. c. NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations. 2. Comply with governing EPA notification regulations before beginning demolition. Comply with hauling and disposal regulations of authorities having jurisdiction SUBMITTALS A. Schedule: 1.05 JOB CONDITIONS 1. Submit schedule for any temporary disconnection of electrical, telephone, security, mechanical and/or plumbing service for Department's approval. Such disconnections shall be restricted to outside of normal operating and/or business hours. A. Condition of Areas: 1. The Department assumes no responsibility for actual condition of areas to be demolished. B. Protection of Existing Construction: 1. Existing construction adjacent to demolition operations, and those portions designated to remain shall be given maximum protection while demolition work is in process. Damage to these portions shall be repaired or replaced at no additional cost to the Department. C. Salvage: 1. If indicated or otherwise required by Department, salvageable items shall include both existing items which shall be removed and relocated to new areas or re-used in existing locations as indicated on Drawings; and salvageable items which shall be turned over to the Department for future maintenance. In both cases, salvageable items shall remain the property of the Department and be carefully removed from the structure as work progresses. Items to be salvaged or re-used shall be determined by Engineer and/or Department. 2. Items to be re-used shall be stored in a safe, secure area, and be protected from damage until they are re-installed per Drawings. Items which are to be turned over to the Department for future maintenance shall be transported to an area designated by the Department. Brooksville Maintenance Yard SELECTIVE DEMOLITION

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16.

Specific requirements for individual units of work are included in the appropriate sections in Divisions 2 through 16. SECTION 01 77 00 - PROJECT CLOSE-OUT PART 1 - GENERAL DESCRIPTION OF REQUIREMENTS: Definitions: Project close-out is the term used to describe certain collective project requirements, indicating completion

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services

More information

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT)

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) 1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT) The use of an existing elevator during construction shall be strictly prohibited. Any deviation

More information

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS 23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters

More information

SECTION PROJECT CLOSEOUT

SECTION PROJECT CLOSEOUT PART 1 - GENERAL 1.01 SCOPE OF WORK A. This Section specifies administrative and procedural requirements for project closeout, including but not limited to: 1. Close-out procedures 2. Final cleaning 3.

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION 1.07 SUPPLEMENTS d. Complete using typewriter or electronic printing. 3. Include detailed lubrication instructions and diagrams showing points to be greased or oiled; recommend type, grade, and temperature

More information

Capital Projects Group Mechanical Work Commissioning Specification

Capital Projects Group Mechanical Work Commissioning Specification Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:

More information

SECTION COMMON WORK RESULTS FOR ELECTRICAL

SECTION COMMON WORK RESULTS FOR ELECTRICAL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

More information

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

A. This Section includes administrative and procedural requirements for quality assurance and quality control. SECTION 01400 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

Submission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit

Submission, Review and Approval of Construction Documents Submission and Review of a Completed Application for Permit Building Code The Florida State University Building Code Administration Program (BCA) was established in 2001 and is responsible for ensuring that all construction activities on FSU owned facilities are

More information

TENOCHCA HALL - FAN COIL UNITS, RESTROOM AND FINISH RENOVATION PROJECT NO

TENOCHCA HALL - FAN COIL UNITS, RESTROOM AND FINISH RENOVATION PROJECT NO SECTION 26 05 00 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL REQUIREMENTS 1.1 RELATED DOCUMENTS A. The general conditions and Division 1 are part of this section and the contract for this work and

More information

Project Manual Index of Specifications Shenandoah Schools Concession Building

Project Manual Index of Specifications Shenandoah Schools Concession Building INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

Project No: Pakenham Branch Library, Pakenham, Ontario Section DECEMBER, 2016 Page 1 of 5

Project No: Pakenham Branch Library, Pakenham, Ontario Section DECEMBER, 2016 Page 1 of 5 DECEMBER, 2016 Page 1 of 5 1 GENERAL 1.01 SUBMITTALS.1 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures..2 Two weeks prior to Substantial Performance of the Work, submit to

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.

C. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products. SECTION 01400 QUALITY CONTROL SERVICES PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification

More information

Division 00 Procurement and Contracting Requirements

Division 00 Procurement and Contracting Requirements SECTION 00 01 10 TABLE OF CONTENTS Division SECTION NO. VOLUME ONE Title SECTION TITLE Division 00 Procurement and Contracting Requirements 00 11 00 Invitation to Bidders 00 21 00 Instructions to Bidders

More information

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS INDIANA UNIVERSITY BIDDING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 (REVISED 2005) MINORITY,

More information

SECTION SUPPLEMENTARY GENERAL CONDITIONS

SECTION SUPPLEMENTARY GENERAL CONDITIONS SECTION 00800 SUPPLEMENTARY GENERAL CONDITIONS PART 1 - GENERAL 1.1 SCOPE OF WORK In general, the Work consists of application of a fluid applied membrane, installation of new tapered insulation, installation

More information

DIVISION 16. Electrical Specifications

DIVISION 16. Electrical Specifications DIVISION 16 Electrical Specifications 16.1 General - Provide all electrical materials and methods as shown on the Drawings, as specified herein, and as needed for a complete and proper installation, including

More information

GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT

GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT JUNE 13, 2018 PROJECT MANUAL SAVANNAH-CHATHAM COUNTY PUBLIC SCHOOL SYSTEM DULOHERY WEEKS GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT TABLE

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina Project Manual for Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR Conway, South Carolina DWG Consulting Engineers 1009 Anna Knapp Blvd. Suite 202 Mt Pleasant, South Carolina 29464

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Notice to Bidders

More information

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers DIVISION 01 GENERAL REQUIREMENTS 012500 Substitution Procedures 012600 Contract Modification Procedures 013100 Project Management and Coordination 013150 Requests for Information 013200 Construction Progress

More information

DeKalb County Library Dunwoody Library Staff Area Renovation

DeKalb County Library Dunwoody Library Staff Area Renovation PROJECT MANUAL DeKalb County Library Dunwoody Library Staff Area Renovation OWNER: DeKalb County Library Email: kimbroj@dekalblibrary.org Contact: Jackee Kimbro 404-508-719-, ext. 2236 ARCHITECT: MEP ENGINEER:

More information

Copyright 2010 AIA Georgia Institute of Technology Facilities Closeout Procedures. 2/15

Copyright 2010 AIA Georgia Institute of Technology Facilities Closeout Procedures. 2/15 SECTION 017700 - CLOSEOUT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following: 1.

More information

PROJECT MANUAL. for. NEW MEXICO STATE UNIVERSITY GERALD THOMAS HALL Fume Hood Replacement at the MAIN CAMPUS for LAS CRUCES, NEW MEXICO

PROJECT MANUAL. for. NEW MEXICO STATE UNIVERSITY GERALD THOMAS HALL Fume Hood Replacement at the MAIN CAMPUS for LAS CRUCES, NEW MEXICO PROJECT MANUAL for NEW MEXICO STATE UNIVERSITY GERALD THOMAS HALL Fume Hood Replacement at the MAIN CAMPUS for LAS CRUCES, NEW MEXICO FOR REVIEW ONLY NOT FOR CONSTRUCTION December 2016 SET NO. 6501 Americas

More information

B. Sections and all references contained therein form a part of this Section of the Specifications.

B. Sections and all references contained therein form a part of this Section of the Specifications. KARGES-FAULCONBRIDGE, INC. KFI: 14-044.00 SEWARD MONTESSORI SCHOOL ADDITION & REMODELING SECTION 260010 - PART 1 - GENERAL 1.01 SCOPE OF WORK A. Drawings and general provisions of the Contract, including

More information

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL 1.01 DESCRIPTION SECTION 16000 GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL A. This Section includes the general provisions applicable to electrical work and testing of the completed electrical systems.

More information

SECTION CLOSEOUT PROCEDURES

SECTION CLOSEOUT PROCEDURES SECTION 017700 - PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for contract closeout, including, but not limited to, the following: 1. Substantial Completion procedures. 2. Final Completion

More information

1ARCHITECTURE TABLE OF CONTENTS

1ARCHITECTURE TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 0102 COVER 00 0107 SEALS PAGE 00 0111 TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 1000 01 2000 01 2100 01 2300 01

More information

WOOD FLOORING WOOD FLOORING

WOOD FLOORING WOOD FLOORING 09550 - WOOD FLOORING 09550-1 PART ONE: GENERAL 1.1 Description WOOD FLOORING 1.1.1 Work in this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance

More information

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109 RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS 6610 Willow Park Drive Suite 200 Naples, FL 34109 MAY 23, 2012 NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS

More information

DIVISION 2- EXISTING CONDITIONS

DIVISION 2- EXISTING CONDITIONS DIVISION 2- EXISTING CONDITIONS 024100- SELECTIVE DEMOLITION PART 1 - GENERAL: 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL PERMIT SET FEBRUARY 27, 2017 Commonwealth Architects 101 Shockoe Slip Richmond, VA 23219 CITY

More information

GENERAL REQUIREMENTS

GENERAL REQUIREMENTS CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 01001-1 PART 1 GENERAL 1.1 Work Covered By Contract Documents.1 Work covers, in general terms: demolition, removals, site preparation and complete construction

More information

SECTION A. Examination, preparation, and general installation procedures.

SECTION A. Examination, preparation, and general installation procedures. SECTION 01 7000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Cutting and patching. C. Cleaning and protection. D. Substantial Completion E. Final

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

SECTION BASIC ELECTRICAL REQUIREMENTS

SECTION BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to work of this section. 1.2 SUMMARY A. This section specifies

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018 CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL BID SET April 4, 2018 Commonwealth Architects 101 Shockoe Slip, Fl 3 Richmond, VA 23219 CITY

More information

PRODUCT SPECIFICATIONS

PRODUCT SPECIFICATIONS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: High density cast resin architectural products, including columns, panels, caps, bases, trim elements and balustrade systems. Specifier Note: Article below

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5 ADDENDUM NO. 1 TO SCOPE OF WORK: Section 0220, Form 01004/5 PROJECT: Tankless Water Heaters Installation Glenn Edge and Rich Martin Apartments and Main Office Water Heater Replacement New Memorial Community

More information

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows: SECTION 16050 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: General requirements for providing basic electrical materials and methods. B. Related Work Specified in Other Sections Includes: 1. Certain

More information

TOWNES + architects, P.A.

TOWNES + architects, P.A. TOWNES + architects, P.A. 2421 North 12th Avenue, Pensacola, Florida 32503 Telephone: (850) 433-0203 Florida Registration AA-26001051 PROJECT MANUAL City of Pensacola Fleet Maintenace Garage Re ovation

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

SECTION GENERAL REQUIREMENTS

SECTION GENERAL REQUIREMENTS SECTION 01005 GENERAL REQUIREMENTS PART 1 GENERAL 1.01 WORK COVERED BY CONTRACT DOCUMENTS A. Work of this Contract comprises the chiller and cooling tower replacement at Five Oaks Middle School which includes

More information

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of: 02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01 40 00 PART 1 - GENERAL 1.1 SUMMARY A. This section covers the establishment and operation of the Contractor s Quality Control (CQC) system as specified by the General Conditions of the Contract.

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

PAULDING COLLEGE & CAREER ACADEMY

PAULDING COLLEGE & CAREER ACADEMY PAULDING COLLEGE & CAREER ACADEMY 000110 OF THE PROJECT MANUAL FOR THE CONSTRUCTION OF: PAULDING COLLEGE & CAREER ACADEMY DALLAS, GEORGIA DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000101 TITLE

More information

5GLOBAL. specification guide summary PART 1 GENERAL

5GLOBAL. specification guide summary PART 1 GENERAL This MANU-SPEC utilizes the Construction Specifications Institute (CSI) Manual of Practice, including MasterFormat, SectionFormat, and PageFormat. A MANU-SPEC is a manufacturerspecific proprietary product

More information

SECTIONAL OVERHEAD DOORS SECTION SECTIONAL OVERHEAD DOORS PART 1 GENERAL

SECTIONAL OVERHEAD DOORS SECTION SECTIONAL OVERHEAD DOORS PART 1 GENERAL 13686.00 SECTIONAL OVERHEAD DOORS 083613-1 1.1 RELATED DOCUMENTS SECTION 083613 - SECTIONAL OVERHEAD DOORS PART 1 GENERAL A. Drawings and general provisions of Contract, including General and Supplementary

More information

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE 1.01 AUTHORITY OF THE ENGINEER CONTROL OF WORK A. The work included in the contract is to be done to the complete satisfaction of the Engineer, and the decision of the Engineer as to the true construction

More information

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS GENERAL The commercial bidding process is a well-defined path of positioning oneself to be the successful bidder amongst a group purporting to offer the same quality materials and labor. There are certain

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT TABLE OF CONTENTS INTRODUCTORY INFORMATION Section 00 00 10 Title Page 00 00 20 Table of Contents DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT Section 00 02 00 Invitation

More information

Saint Anselm College Lower Level Cooling Carr Center Manchester, New Hampshire. Project No April 18, % Review.

Saint Anselm College Lower Level Cooling Carr Center Manchester, New Hampshire. Project No April 18, % Review. Saint Anselm College Lower Level Cooling Carr Center Manchester, New Hampshire Project No. 17343 April 18, 2017 100% Review 2017 Harriman This Page Intentionally Left Blank DIVISION 01 - GENERAL REQUIREMENTS

More information

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR PROJECT MANUAL FOR Ogden Regional Medical Center 5475 South 500 East Ogden, UT 84405 for MountainStar Healthcare Construction Documents NJRA Architects, Inc. 5272 South College Dr. Murray, Utah 84123 Telephone:

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

2012 VIRGINIA INDUSTRIALIZED BUILDING SAFETY REGULATIONS

2012 VIRGINIA INDUSTRIALIZED BUILDING SAFETY REGULATIONS 13VAC5-91-10. Definitions. The following words and terms when used in this chapter shall have the following meanings unless the context clearly indicates otherwise. Administrator means the Director of

More information

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set PROJECT MANUAL POINT BLANK RANGE & GUN SHOP 600 Corporate way Knoxville, TN Bid/Permit Set Division Section Title SPECIFICATIONS GROUP DIVISION 01 - GENERAL REQUIREMENTS 011000 SUMMARY 012600 CONTRACT

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

C. Samples: For each exposed product and for each color and texture specified, <Insert dimensions> in size.

C. Samples: For each exposed product and for each color and texture specified, <Insert dimensions> in size. SECTION 08 12 16 - ALUMINUM DOOR FRAMES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

SECTION DOOR HARDWARE

SECTION DOOR HARDWARE SECTION 087100 -DOOR HARDWARE PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS

SECTION EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS SECTION 074233 EXTERIOR SOLID PHENOLIC RAINSCREEN PANELS PART 1 - GENERAL 1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

City Of Mendota Construction Procedures

City Of Mendota Construction Procedures City Of Mendota Construction Procedures Building Permit Application: A permit shall be obtained prior to commencing work of any type. Failure to do so may result in doubling the permit fees. At the time

More information

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01600 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

SECTION SUMMARY OF WORK

SECTION SUMMARY OF WORK SECTION 011000- SUMMARY OF WORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and Division 01 Specification Sections

More information

EXECUTION REQUIREMENTS

EXECUTION REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: Execution requirements. B. Related Requirements: 1. Specification Sections 2 through 49. PART 2 - PRODUCTS (Not Used). PART 3 - EXECUTION 3.1 SAFETY 01

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION 016000 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage,

More information

END OF SECTION SECTION FINAL CLEANING PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDE

END OF SECTION SECTION FINAL CLEANING PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDE d. Clean exposed hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Plumbing Contractor: Clean

More information

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control 1. DESCRIPTION 2. MATERIALS Furnish, install, relocate, or remove radar vehicle detection systems (RVDS) of

More information

Beverly Gardens Park City of Beverly Hills, CA. Block #9: Elm Foothill Garden

Beverly Gardens Park City of Beverly Hills, CA. Block #9: Elm Foothill Garden Beverly Gardens Park Block #9: SPECIFICATIONS 100% CD / BID SET TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION No. TITLE 011000.Summary. 3 012213.Unit Prices...1 012500.Substitution Procedures

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

A New Barn for Brian & Julie Sims FM 2590 Canyon, TX. Gregg Bliss, Architect 1001 S.E. 3rd Ave. Amarillo, TX

A New Barn for Brian & Julie Sims FM 2590 Canyon, TX. Gregg Bliss, Architect 1001 S.E. 3rd Ave. Amarillo, TX A New Barn for Brian & Julie Sims 21400 FM 2590 Canyon, TX Gregg Bliss, Architect 1001 S.E. 3rd Ave. Amarillo, TX 79102 806-372-2966 14-020 Division Section Title Pages PROCUREMENT AND CONTRACTING DOCUMENTS

More information

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS 669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects

More information

SECTION GENERAL ELECTRICAL REQUIREMENTS

SECTION GENERAL ELECTRICAL REQUIREMENTS SECTION 26 00 10 GENERAL ELECTRICAL REQUIREMENTS PART 1: GENERAL 1.01 SCOPE OF WORK A. Contractor shall provide all labor, materials, equipment, machinery and tools necessary to put into satisfactory operation

More information

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION SECTION 024119 SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

St. Monica Food Pantry Construction Waste Management and Disposal SBA-13105

St. Monica Food Pantry Construction Waste Management and Disposal SBA-13105 St. Monica Food Pantry 01 7419-1 SECTION 01 7419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 SUMMARY: A. Work of this section includes administrative and procedural requirements for

More information

SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. A. This Section includes administrative and procedural requirements for the following:

SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. A. This Section includes administrative and procedural requirements for the following: SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner.

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner. SECTION 02 41 19 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE

PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE PROJECT MANUAL FOR: HUMPHREYS CO. SHERRILL BUILDING RENOVATIONS: NEW URGENT CARE CLINIC & EXTENSION SERVICE OFFICE HUMPHREYS COUNTY BOARD OF SUPERVISOR BELZONI, MISSISSIPPI APRIL 20, 2016 EMILY POOLE ARCHITECTURE,

More information

ADDENDUM 2 - JULY 14, 2015

ADDENDUM 2 - JULY 14, 2015 7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures

More information

CONSTRUCTION STANDARD DOCUMENT

CONSTRUCTION STANDARD DOCUMENT CONSTRUCTION STANDARD DOCUMENT OVERALL CONSTRUCTION SCHEDULE REQUIREMENTS The Overall Schedule shall be prepared by the Contractor based on information from all subcontractors engaged on this project.

More information

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE PROJECT MANUAL / TECHNICAL SPECIFICATIONS WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS - FENCING PACKAGE 3201 E. HOUSTON STREET SAN ANTONIO, TEXAS 78219 OCTOBER 6, 2017 HUMBERTO SALDANA & ASSOCIATES, INC.

More information

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION SECTION 02 41 14 SELECTIVE BUILDING DEMOLITION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for systematic removal of site improvements or portions of exterior and interior of buildings

More information

SECTION ALTERATION PROJECT PROCEDURES

SECTION ALTERATION PROJECT PROCEDURES SECTION 013516 ALTERATION PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for protection of existing facilities during construction operations. 2. Demolition and removals

More information

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated. SECTION 024119 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

155 North Beech, Casper, WY * (307) * (307) Fax INDEX

155 North Beech, Casper, WY * (307) * (307) Fax INDEX INSTRUCTION TO BIDDERS 155 North Beech, Casper, WY 82602 * (307) 265-0603 * (307) 266-5414 Fax PART 1: INSTRUCTION TO BIDDERS INDEX BIDDING DOCUMENTS. 2 CONTRACTOR APPLICATION FORM.2 EXAMINATION OF CONTRACT

More information