- Case History - 8 M Diameter 7 Km Long Beles Tailrace Tunnel (Ethiopia) Bored And Lined In Basaltic Formations In Less Than 12 Months
|
|
- Kathryn Hodges
- 5 years ago
- Views:
Transcription
1 RETC June, Case History - 8 M Diameter 7 Km Long Beles Tailrace Tunnel (Ethiopia) Bored And Lined In Basaltic Formations In Less Than 12 Months Antonio Raschillà, Site Manager, S.E.L.I. Spa Francesco Bartimoccia, Project Manager, S.E.L.I. Spa ABSTRACT On the 2 nd of June 27 SELI S.p.A. started the excavation of Beles Tailrace Tunnel (Ethiopia). The new 8,07 m diameter DS Universal TBM utilized for the tunnel excavation was manufactured by SELI S.p.A. and allowed the installation of 30 cm thick concrete lining, contemporaneously with the excavation of 7,2 m of tunnel. The greatest part of the tunnel alignment was excavated in hard and sound basaltic rocks. The paper describes the main steps of the tunnelling operations which led to a remarkably rapid excavation, with a peak production of 36 m / day and a final breakthrough achieved 46 days ahead of the contractual deadline. Furthermore the paper describes the work and logistic organization that was set up to efficiently perform the mechanized excavation in the very remote area of the project. THE PROJECT Beles project is one the multi-purpose projects, currently underway, to develop the resources in Ethiopia. The project area is located in the Amhara Region (north western of Ethiopia), about 150 Km to the Bahir Dar town (see figure 1). The Beles Multipurpose Project, committed to Salini Costruttori S.p.A., will be a single stage power plant with a total installed capacity of 460 MW. 1 of 14
2 RETC June, <Figure 1. General map of the project> The project, located in the South-Western bank of the Lake Tana, develops completely underground for a total length of about 20 Km, and consists of mainly: - 12 Km Headrace Tunnel (which will conveys water from Lake Tana into the penstock of the underground powerhouse) - 7,2 Km Tailrace Tunnel (which will discharges water into the Jehana River, a small tributary of the Beles River) - Underground Powerhouse with n. 4 Francis type turbines of 115 MW each and Transformer system m Penstock shaft - 90 m Surge Shaft THE TRACING AND GEOLOGY The SE-NW running tunnel is divided in a Tailrace Tunnel and Headrace Tunnel, with a total excavation length of nearly 19 Km. The Tailrace Tunnel runs from the Powerhouse to the outlet portal for 72 m with a slope of 0,15%, conveying the discharge water to the Jehana River (see figure 2). 2 of 14
3 E 1,3 01,5 03,0 N 26 8,0 N 26 9,5 1,3 E 04,5 1,0 N 27 1,3 E 27 2,5 06,0 N 07,5 ALL N POWERHOUSE E ALT SURGE SHAFT OUTLET DRAWING 30 A SP 020-A 26 6,5 1,3 1,3 27 4,0 E PLAN DRAWING 30 A SP 015-A E RETC June, ALT ALT SWITCHYARD 40 VB 40 ALT ALT 40 VB WEIR 1 WEIR Power House ADIT ALL ALL ALT E 27 4,0 1,3 09,0 N <Figure 2. Tracing of Tailrace Tunnel> Excavation started from the outlet towards the Power House. The geological conditions are described in TBM advance direction, as follows: From chainage 72 to 50 the tunnel penetrated a brecciated Basalt formation, which was composed of plateau flow basalt and pyroclastica (agglomerates and tuffites). The overburden in that range extended up to 120 m. Excavation conditions was good to fair for most of this TBM section, depending on the fracture intensity. From chainage 50 to 0 the tunnel section contained a series of aphanitic Basalt layers with some intercalations of brecciated basalt layers at an overburden from m. The rock mass crossed was good and favourable tunnelling conditions (see figure 3). <Figure 3. Front Face> 3 of 14
4 RETC June, The complete Tailrace tunnel was expected to intersect about 17 major lineaments; these zones were described with locally poor tunnelling conditions. The lineaments intersect the alignment most of the times at obtuse angle and almost vertically (see graph 1). LEGEND RECENT ALL ALLUVIAL DEPOSITS ALT ALLUVIAL TERRACES DEPOSITS RA FLUVIAL-LACUSTRINE DEPOSITS RL LACUSTRINE DEPOSITS QUATERNARY B3 B2 B1 QT QL THIRD BASALT FLOW SECOND BASALT FLOW FIRST BASALT FLOW PYROCLASTICS ROCK (TUFF AND LAPILLI TUFF) LACUSTRINE DEPOSITS TERTIARY VB APHANITIC BASALT PYROCLASTICS ROCK (TUFF AND LAPILLI TUFF) VESICULAR BASALT BRECCIATED BASALT FAULT and FRACTURE TERRACE EDGES KEY BED GEOLOGICAL BOUNDARIES ALT <Graph 1. Geologic profile> THE WORK AND METHOD OF EXCAVATION For the excavation and lining of the about 7,2 Km of Tailrace Tunnel was utilized a Double Shield TBM system designed and built by SELI Tecnologie. The tunnelling system executed all the following operations: - boring - erection of the precast lining - filling of the annular gap between the excavation and the precast lining by pea-gravel. - grouting of the rock around the lining TBM And Back-Up System Description TBM, back-up system and rolling stock were designed and manufactured by SELI Tecnologie (see figure 4) in the Italian factory of Aprilia (Rome) to ensure the maximum advance rates under variable ground condition through the complete mechanisation of all operations related to handling and installing precast segment, loading and exchanging muck trains and servicing the various TBM power units mounted on the rolling platforms. The table below resumes TBM specifications. 4 of 14
5 RETC June, TBM TYPE Double Shield Universal Cutterhead excavation diameter 8,070 mm (new cutters) TBM Shield Length (Including tail shield) 11,87 mt (TBM closed) TBM & Back-Up Length approx. 125 mt CUERHEAD AND CUERS Cutterhead structure No. 6 parts heavy structure bolted Number of cutting tools 52 Cutter type 17 inch disc backloading and recessed CUERHEAD THRUST Thrust Cylinders n bar max pressure Auxiliary Thrust Cylinders n bar max pressure Maximum advance speed 6 m/h CUERHEAD DRIVE Type Electric Cutterhead Power System 8 x 315 kw Electric water cooled motors Maximum Torque 5,250 knm Cutterhead Speed 0 to 6 rpm SEGMENT ERECTOR 6 movements radio controlled CONVEYOR SYSTEM Width 1,0 mm Capacity 550 t/h MACHINE WEIGHT Approx. 6 t BACK-UP COMPONENTS AUXILIARY - ZED system EQUIPMENT - Gas monitoring and alarm system - Pea gravel storing and pumping system - cement grouting storing, mixing and grouting system - emergency diesel generator - close circuit TV camera system - rock drilling equipment - PLC system (see figure 5) TBM was also equipped with a special Rock Drilling Equipment to probe in front of the Cutterhead and from the Gripper shield, which has 18 different holes (internal diameter 102 mm) where, by using a special support mounted on the erector, probe drilling can be carried out. An automatic recording device of the latest generation was installed on the TBM. Excavation parameters were visualized on a monitor in the operator cabin. The computer mounted in the operator cabin recorded and stored all the data by means of datalogging system. 5 of 14
6 RETC June, The recorded parameters were: TBM total thrust and pressure thrust on each thrust cylinder Penetration rate Cutterhead torque Cutterhead revolution per minutes Electric power consumption for each electric motor Stroke advance Steering parameters <Figure 4.TBM (called Hiwot) in Aprilia Factory (Rome)> <Figure 5. PLC System> Tunnel Transport System Tunnel excavation and segments installation, in DS Mode, are performed concurrently, except under unfavourable geological conditions. The rolling stock followed SELI philosophy and design tradition, that has proved to be successful in more than 5 Km of tunnels built. The choice of muck cars (fix body type) allowed the highest ratio among the transported weight and the own weight of the muck car. Furthermore, all lateral internal surface was smooth and didn t create any obstacle to the operations of unload of the muck. The wheels had large diameter and high capacity bearing for long life and low rolling friction. Each Tailrace tunnel trains included: - 13 fixed-body muck cars for a total capacity of 156 m 3 of muck (see figure 6) - 1 pea-gravel car transporting a silos of 5,3 m 3 of capacity - 3 flatbed cars for the transportation of precast segments - 1 personnel car having 16 seats capacity 6 of 14
7 RETC June, The number of trains utilized was 2/3 up to chainage 35 and n 4 from chainage 35 to the end of the tunnel. A fully automatic hydraulic muck car tippler (able to unload one muck car each 2 minutes and full train in 26 minutes) was located outside the tunnel portal. The tippler was complete with pusher for the train shunting and therefore there was no need of the locomotive to unload the train. <Figure 6. Tunnel portal> Lining The lining was an open type parallel ring rhomboidal segmental system, with the following characteristics: - External diam. 78 mm - Internal diam. 72 mm - Lining thickness 3 mm - Segment ring width 15m - N.6 segments + n.1 key stone - Invert with flat tracks and 3 central trenches - Dowel connectors in the circumferential joints - Grouting holes 7 of 14
8 RETC June, For assembling of the segment ring, the invert was installed first with the opportune dowels of the circumferential joint. Next step, the both left and right bottom sidewall segments was installed and kept in position by means of the auxiliary thrust cylinders. Afterward the both left and right top sidewall and as the last elements of the ring the roof segment and key stone were installed (see figure 7). Dowel connectors (three for each segment made by extruded polyetilene) had no structural function, but were installed just like simple connecting and centring devices. <Figure 7. Lining System> Pea Gravel Injection During excavation pea gravel was injected into the annular gap between rock mass and the lining. The size range of the pea-gravel was 8-12 mm and it has been dimensioned to allow its injection by using n 2 air pumps mounted on the deck n 3. A dedicated line arrived to the deck n 1 where, using flexible pipes, pea-gravel was injected behind the second-last completely assembled ring. Immediately after the injection the grouting holes was plugged with suitable wooden plugs to prevent escaping of pea-gravel. 8 of 14
9 RETC June, Contact Grouting Contact grouting was performed all along the tunnel (see figure 8) to grout the pea-gravel in the annular gap, following the excavation behind the back-up (see figure 9). Grouting was filled up also the small space between segment and segment along the joint where was present any opening. Grouting plant was installed at the Tunnel Portal and the grout mixture was pumped inside the tunnel by using n 2 lines of galvanized steel pipes. Grout equipment was composed by: - turbomixer having capacity of 15 lt and production rate of 15 mc/h - agitator having capacity of 40 lt - automatic dosing system for additives - automatic dosing system for bentonite - n 2 pumps, maximum flow rate of 1 lt/min and maximum pressure of 2 bar During the normal activities (excavation and regripping), in the range of the back-up decks, the chalking grooves was closed with mortar and all necessary repairs were done. <Figure 8. Tunnel inside sight> <Figure 9. Core drilling example> 9 of 14
10 RETC June, LOGYSTIC AND WORK ORGANIZATION Due to remote location of the project, it was necessary to overcome several logistic difficulties. The shipment of the TBM, back-up, rolling stock and all the other spare parts and materials was carried on from Italy to Gibuti and from Gibuti to the job site (in Bahir Dar area) through about 10 Kms of difficult roads (see figures 10,11,12), especially during the rainy periods. Particular attention was done in the Nile Bridge (see figure 13) crossing where all necessary checks of the structure took place before the passage of the main TBM components. The waiting to receive any shipment on site was about 4-5 months from purchase order. For this reason it was indispensable to plan possible spare parts as providently as possible, with considerable advance. <Figure 10. Portal area> <Figure 11. Road from Gibuti to site> It was also necessary to face low level of specialization of local manpower; a specialized SELI staff with adequate experience supervised all tunnel boring operations training local workers to assure the level of reached quality and productivity. <Figure 12. Road from Gibuti to site> <Figure 13. Nile Bridge crossing> 10 of 14
11 RETC June, Tunnelling operations was carried out 7 days/week in 3 shifts of 8 hours each, with shift changing at the front and a scheduled maintenance shift inside the tunnel of about 4 hours in the morning. The maintenance operations consisted mainly in cutterhead inspection and cutter changes as required, supply and extension of tunnel services, eventual probe drilling operations, maintenance pea-gravel lines. When special maintenance, repairs or probe drilling was required, the maintenance duration was extended beyond the normal 4 hours time. TBM PERFORMANCE The excavation of the tunnel started on the 2 nd June 27 and was completed the 31 st May 28, after less then one year at an average advance rate of about 20 metres per days. The maximum daily advance rate of 36 metres (24 rings) was achieved in January 08, while the best weekly advance rate was 189 metres achieved on the 27 th week of excavation (see graph 2). The best month, as shown in the graph 3, was December 07 with 724 metres of excavation during 29 days of work (excluding 25 th and 31 st of December) at an average rate of 25 metres per day. Beles Multipurpose Project - EPC Contract TAILRACE TUNNEL - Weekly Production 2, Weekly tunnel bored (ml) Production Cumulative 7201,65 mt 7.5, 188,86 mt 7.0, 6.5, 6.0, 150, 5.5, Ml of tunnel bored 1, 50, 0, 28/05/07 04/06/07 11/06/07 18/06/07 25/06/07 02/07/07 09/07/07 16/07/07 23/07/07 30/07/07 06/08/07 13/08/07 20/08/07 27/08/07 03/09/07 10/09/07 17/09/07 24/09/07 01/10/07 08/10/07 15/10/07 22/10/07 29/10/07 05/11/07 12/11/07 19/11/07 26/11/07 03/12/07 10/12/07 17/12/07 24/12/07 31/12/07 07/01/08 14/01/08 21/01/08 28/01/08 04/02/08 11/02/08 18/02/08 25/02/08 03/03/08 10/03/08 17/03/08 24/03/08 31/03/08 07/04/08 14/04/08 21/04/08 28/04/08 05/05/08 12/05/08 19/05/08 26/05/ Week 5.0, 4.5, 4.0, 3.5, 3.0, 2.5, 2.0, 1.5, 1.0, 5, 0, Chainage (m) <Graph 2. Weekly productions of the TBM DS SELI> 11 of 14
12 RETC June, Beles Multipurpose Project - EPC Contract TAILRACE TUNNEL - Monthly Production 8, Montly tunnel bored (ml) Production Cumulative 7201,65 mt 7.5, 750, 7.0, Ml of tunnel bored 7, 650, 6, 550, 5, 450, 4, 350, 3, 250, 2, 150, 1, 248,21 mt 565,46 mt 650,70 mt 6,32 mt 566,61 mt 50, 0, June '07 July '07 August '07 September '07 October '07 November '07 December '07 January '08 February '08 March '08 April '08 655,05 mt May '08 724,27 mt 651,95 mt 621,12 mt 648,33 mt 643,95 mt 625,68 mt 6.5, 6.0, 5.5, 5.0, 4.5, 4.0, 3.5, 3.0, 2.5, 2.0, 1.5, 1.0, Chainage (m) 5, 0, Month <Graph 3. Monthly productions of the TBM DS SELI> Graph 2 shows the very short period of the learning phase. Learning curve, usually long 2-3 months, was limited at less that one month. This important target was obtained through an easy and rapid interaction expatriate local personnel and an optimization of the necessary equipments. <Graph 4. Production lines of the TBM DS SELI> 12 of 14
13 RETC June, The graph 4 shows the constant advance of the excavation production (upper line) related with the contractual production (lower line) calculated on the basis of the RMR (Bieniawski) of the rock mass encountered. TBM completed the tunnel with 46 days of advance on contractual time. TIMING ANALYSIS BELES Outlet - Hydroelectric Power Project" General graphic - Total Various 2,4 % Zed/Laser surveyor problems 0,5 % Maintenance 23,4 % Geo 1,3 % Waiting 17,1 % Excavation 51,9 % TBM/B-UP Breakdown 3,5 % <Graph 5. TBM DS SELI timing analysis> Graph 5 above shows the good efficiency reached from the TBM (51,9 % included regripping time and ordinary waiting train). It was the result of a punctual daily maintenance (23%). In the Maintenance and Waiting items, particularly main point was time lost for Pea-gravel injection lines. Substantial delays were imputable to the necessary daily maintenance of the injection lines (to guarantee the good operation of the system) due to the characteristics of the material. Non available fluvial gravel in situ has imposed a sharpy material from quarry with consequent easy deterioration of the lines. Other important parameter was TBM breakdown (3,5 %), a low value considering the rock hardness (with the consequent problems relative to the vibrations) and TBM adjustment during learning phase. 13 of 14
14 RETC June, CONCLUSIONS Main problems encountered during the project were difficult logistic situation, especially for supplying materials and a local manpower with lack of specialization. It was possible to obtain good results through a sharp design and planning of all the activities, with the employment of specialized SELI human resources, who has organized in the better way all the work and has instructed the local manpower. Key factor was a careful planning and equipments employment, with consequent optimization of the work phases during the whole work. <Figure 14. Breakthrough of the TBM> 14 of 14
DIFFICULT GROUND SOLUTIONS:
Tunnelling April/May 2016 www.tunnellingjournal.com journal The international journal for the tunnelling industry SEE PAGE 6 SEE PAGE 12 SEE PAGE 27 WORLD NEWS MONITOR PROGRESS CUTTER CARE HIGHLIGHTS FROM
More informationTBM EXCAVATION AND TUNNEL DESIGN FOR ROCK TUNNELS UNDER HIGH COVER IN CRITICAL GEOLOGICAL CONDITIONS
TBM EXCAVATION AND TUNNEL DESIGN FOR ROCK TUNNELS UNDER HIGH COVER IN CRITICAL IL FUTURO DI SELI GEOLOGICAL CONDITIONS Condivisione di obiettivi e traguardi Remo Grandori_Swiss Tunnel Society September
More informationThe Robbins Company. Bheri Babai Diversion Multipurpose Project (BBDMP) Company Facts. Headquarters
Bheri Babai Diversion Multipurpose Project (BBDMP) Presented by Jim Clark, Projects Manager India The Robbins Company THE ROBBINS COMPANY THE ROBBINS COMPANY Company Facts More than 50 years of innovation
More informationFOR HIGHWAY TUNNEL GALLERIA SPARVO.
HERRENKNECHT EPB SHIELD S-574 FOR HIGHWAY TUNNEL GALLERIA SPARVO. PRODUCT PORTFOLIO OF HERRENKNECHT GROUP. MECHANIZED TUNNELLING TECHNOLOGY. STEEP TUNNELLING. St. Petersburg 30 downhill EPB Shield Access
More informationHIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY
Chapter 11 HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY Brian B. Khalighi and Joseph J. Diehl Atlas Copco Robbins Inc. and Grow Tunneling Corp. ABSTRACT
More information2
Company(ผ บรรยาย): Shimizu Corporation Technical Name(ห วข อเทคโนโลย ): High Performance TBM TBM ค ณภาพส ง Presenter: 水戸聰 Akira Mito 1 2 Example of Water Supply Tunnel High Overburden Ing-Yot Tunnel L=50.9km
More informationHardrock Tunnel Boring Machines
Bernhard Maidl, Leonhard Schmid, Willy Ritz, Martin Herrenknecht Hardrock Tunnel Boring Machines In co-operation with Gerhard Wehrmeyer and Marcus Derbort -=rnst & Sohn '-A Wiley Company Contents 1 Historical
More informationDesign and construction of the 5.5 km TBM excavated headrace tunnel of the Theun Hinboun Expansion Project, Lao PDR
VII-00094.01.EN/102.1-R-247 Design and construction of the 5.5 km TBM excavated headrace tunnel of the Theun Hinboun Expansion Project, Lao PDR Selim M. Sayah 1, Remo Crapp 1, Carlo Babini 2, Ivano Andreis
More informationExperts in tunneling with Tunnel Boring Machines
www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution
More informationØ1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati
Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati Steve Lamb The Robbins Company, Solon, Ohio, USA Steve Abernathy Midwest Mole, Inc., Indianapolis, Indiana, USA ABSTRACT: A Robbins
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationTBM Selection and Specification
By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements
More informationREHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL
REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL Roger BREMEN Engineer of the Hydraulic Department Lombardi Engineering Limited Via Simen 19 CH 6648 Minusio Switzerland ABSTRACT: A 7.5 km long
More informationThe Rio Grande project - Argentina
The Rio Grande project - Argentina Introduction The Rio Grande pumped storage project is located on the Rio Grande river near the town of Santa Rosa de Calamucita in the Province of Cordoba in Argentina.
More information2 Support of the cavity and settlement Support of the face Natural support Mechanical support...
Table of Contents The authors... VII Foreword to the 2nd Edition... IX 1 Introduction... 1 1.1 Basic principles and terms... 3 1.2 Types of tunnel boring machine according to DAUB... 5 1.2.1 Categories
More informationKing County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal
North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle
More informationService Automation. Making the way
Industrial Hydraulics Electric Drives and Controls Linear Motion and Assembly Technologies Pneumatics Service Automation Mobile Hydraulics profile Drive & Control Niles-Simmons Engineering on the cutting
More informationSEMMERING BASE TUNNEL LOGISTIC CHALLENGES
SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways
More informationPump storage hydro power plant (PSKW) Reißeck
Roland Schorn Short description The new pump storage power plant (PSKW) Reißeck II represents an expansion of the already existing group of power plants, Malta and Reißeck/Kreuzeck in Carinthia. The new
More informationTBM Case Histories. L.W. destwolinski. B. Mariucci. Chairmen. Kiewit Construction Co. Omaha, NE. Kiewit Construction Co. Omaha, NE
6 TBM Case Histories Chairmen L.W. destwolinski Kiewit Construction Co. Omaha, NE B. Mariucci Kiewit Construction Co. Omaha, NE Chapter 24 YINDARUQIN IRRIGATION PROJECT: HIGH SPEED TUNNELLING IN CHINA
More informationLogistics of Limited Space Urban Tunnelling at Singapore s Mega Metro
Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro S. Smading The Robbins Company, Singapore ABSTRACT: Today s mega metro projects are using multiple TBMs in difficult ground, short
More informationONSITE ASSEMBLY AND HARD ROCK TUNNELING AT THE JINPING-II HYDROPOWER STATION POWER TUNNEL PROJECT
ONSITE ASSEMBLY AND HARD ROCK TUNNELING AT THE JINPING-II HYDROPOWER STATION POWER TUNNEL PROJECT Stephen M. Smading The Robbins Company Joe Roby The Robbins Company Desiree Willis The Robbins Company
More informationDesign and Implementation of the South Hartford CSO Tunnel
Design and Implementation of the South Hartford CSO Tunnel Brian Canterbury, P.E., AECOM James Sullivan, P.E., AECOM Andrew Perham, The Metropolitan District The Metropolitan District NEWEA January 22,
More informationFrom Colonia Jardín to Cuatro Vientos
60 METROSUR Line 10, Section 1A Contractor: From Colonia Jardín to Cuatro Vientos The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was
More informationThe Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions
The Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions Detlef Jordan Robbins Europe GmbH, Germany ABSTRACT: The tunneling industry is abuzz about the upcoming Brenner Base Tunnel Project.
More informationThe return of TBMs to Norway at Røssåga HEPP TBM operation through extremely hard rock, unstable rock mass and other challenges
The return of TBMs to Norway at Røssåga HEPP TBM operation through extremely hard rock, unstable rock mass and other challenges S. Log The Robbins Company, Oslo, Norway D. Brox Leonhard Nilsen og Sønner,
More informationBREAKTHROUGH AND BURIAL OF TBMS ON THE BRISBANE AIRPORT LINK PROJECT
BREAKTHROUGH AND BURIAL OF TBMS ON THE BRISBANE AIRPORT LINK PROJECT Russell Connors 1 ABSTRACT The Airport Link Project (APL) was constructed in the Northern Suburbs of Brisbane and connects the Central
More informationTunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA
Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India D.Harding 1 1 The Robbins Company, Solon, Ohio, USA 1 INTRODUCTION The AMR project has been planned since 1983 and will provide irrigation
More informationInnovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines
Innovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines GHD Energy & Resources Brendan Henry Manager, Tunnels and Underground Spaces Safety Commitment Safety
More informationIEEE 18-May Intake. Tunnel. Outlet
IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion
More informationBrief of evidence Tunnelling construction
Brief of evidence Tunnelling construction 1 Personal Information and Qualification My name is Dr. Tim Jaguttis. I am a mechanical engineer and carry a PhD in mechanical engineering. Since 2008 I m a managing
More informationof GENERAL. A. Description
02920-1 of 11 SECTION 02920: EARTH TUNNELING 02920.01 GENERAL A. Description Earth tunneling shall include, but not necessarily be limited to, constructing earth tunnels and furnishing and installing tunnel
More informationINDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2
INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...
More informationPIPE JACKING & TUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS
PIPE JACKING & TUNNELING SYSTEMS 6(721 6(*'( 35$+6 '1$ 6558% //$ (920(5 DRIVEN FOR CUSTOMER SUCCESS OUR EQUIPMENT SYSTEMS Since inception, Akkerman has grown with the evolution of industry demands. We
More information11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.
Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge
More informationRisk Management - TBM Manufacturer s Perspective II
November 14-16, 2016 Risk Management - TBM Manufacturer s Perspective II History of LOVSUNS 350 TBMs Built to Date History of Risk Management Techniques Developed in the Late 60 s by NASA during the Apollo
More informationLARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL
Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore
More informationExpert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)
INDEX 2 Company Profile 4 Technical Description 13 Organization Chart 6 Quality & HSE 19 Services Offered 8 Certification 22 COMPANY PROFILE Company Profile 4 Thrustboring Technology Contracting Company
More informationrapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions.
herrenknecht AG utility tunnelling Traffic tunnelling SEPARATION PLANTS HERRENKNECHT SEPARATION PLANTS KEEP IT FLOWING. RAPID TUNNELLING THANKS TO EFFICIENT SEPARATION. Low-impact mechanized tunnelling:
More informationDORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018
DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Progress Report January 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development & Consulting
More informationTBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER
TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck Gerhard HARER 2 Project overview Koralm railway Part of the Baltic-Adriatic Core Network Corridor, which is one of the most
More information1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK
1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for
More informationDORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018
DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report February 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development
More informationTECHNOLOGY. Hydromill
TECHNOLOGY Hydromill Everywhere the diaphragm wall market is moving to higher and higher targets in terms of depth and verticality control. Metro stations, new foundations for residential and commercial
More informationLower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project
Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located
More informationProf. Eng. Daniele PEILA & Prof. Eng. Sebastiano PELIZZA
Course in Tunnelling and Tunnel Boring Machine Kurs w zakresie drążenia tuneli oraz maszyny drążącej BACK FILLING Prof. Eng. Daniele PEILA & Prof. Eng. Sebastiano PELIZZA The instantaneous filling of the
More information2 Technology of closed-face tunnelling machines
2 Technology of closed-face tunnelling machines 2.1 Machine types There are two basic types of pressurised closed-face tunnelling systems slurry tunnelling machines (STMs) and earth pressure balance machines
More informationPipetron Tunnel Construction Issues
Pipetron Tunnel Construction Issues James E. Friant Colorado School of Mines and Excavation Engineering Associates, Inc., 1352 SW 175th St., Seattle, WA 98166 Robert A. Bauer and David L. Gross Illinois
More informationEL VALOR DE INNOVACION EN TUNELES
EL VALOR DE INNOVACION EN TUNELES 24. - 25. NOVIEMBRE 2008 Harald Wagner, PhD, PE D2 Consult Ltda.,Linz/Austria ITA EXCO Experto Especial CONTENT 1. Preface / Introduction 2. Role of Ground Investigations
More informationDeveloped countries require a modern infrastructure Roads Railways Power Communications Water Wastewater
Introduction to Soft Ground Tunnelling in Urban Environment Dr. Noppadol Phienwej Geotechnical and Geo-environmental environmental Engineering School of Engineering and Technology Asian Institute of Technology
More informationCONTACTS LUCOP Sp. z o.o. Ul. Sejmu Czteroletniego 2 m Warszawa Tel
The LUCOP Sp. z o.o. is a company operating in the Polish market and belonging to the more than 40-year-old Italian group I.CO.P S.p.A. Its entry into the Polish market means technological and quality
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationCONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 616 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03
More informationITEM 432 TUNNEL CONSTRUCTION
AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.
More informationSTANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.
STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer
More information7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by
Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than
More informationTender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1
Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...
More informationHydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.
HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the
More informationMIEL I Hydroelectric Power Plant
MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers
More informationOptimization of Supports in a Road Tunnel through Conglomerate during Construction
Optimization of Supports in a Road Tunnel through Conglomerate during Construction Tülin SOLAK, Temelsu International Engineering Services Inc., Turkey, tulin.solak@temelsu.com.tr Bülent ULUKAN, Temelsu
More informationWalls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.
TECHNOLOGY Diaphragm walls Diaphragm walls are one of the most important technologies of special foundation engineering. A diaphragm wall is constructed using a trench excavated in ground and supported
More informationPipe Jacking. Japan Sewage Works Association
Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,
More informationCONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS
More informationKiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project
South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction
More informationPresented by: Frank Guyamier
FTBA Orlando Tuesday, March 20, 2012 Presented by: Frank Guyamier Project Engineer P3 PROJECT PARTNERS Public Sponsors 90% Equity Partner Design/Build Contractor 10% Equity Partner VMS Operator Federal
More informationSoil Improvement by Compaction Grouting
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 31-3223.12 Soil Improvement by Compaction Grouting Part 1 - General 1.01 Introduction
More informationJohn Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53
John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:
More informationDesign and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.
Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine. Alan Naismith 1, Dr Graham Howell 2, Howard Marsden 3. 1 SRK; 2 SRK; 3 Petra Diamonds (previously,
More informationLegislative Council Panel on Transport Subcommittee on Matters Relating to Railways
Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways Hong Kong Section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link Supplementary Information In the meeting of the
More informationCOMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS
fib Symposium Keep Concrete Attractive, Budapest 2005 COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS Kolic D. 1, Hörlein N. 2, Schneider K. 3, Steiner H. 3 NEURON Consult ZT 1, PORR Tunnelbau GmbH 2, ÖBB-Infrastruktur
More informationPrinciples for Tunnel Design. 20th to 21st April 2017 Kuala Lumpur
20th to 21st April 2017 Kuala Lumpur Mechanized Tunneling (TBM and Support Systems) Thorsten Tatzki Herrenknecht Asia Headquarters Pte. Ltd. Introduction: General Overview Shield Machines and Tunnel Boring
More informationDesign Data 4M. Jacking Concrete Pipe
Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing
More informationUnited Undersea Connecting the Tunnels to Marine Risers at the Victorian Desalination Project
United Undersea Connecting the Tunnels to Marine Risers at the Victorian Desalination Project T Burns 1 ABSTRACT The Victorian Desalination Project is being constructed near the town of Wonthaggi, in the
More informationMETHOD STATEMENT OF CONSOLIDATION GROUTING
METHOD STATEMENT OF CONSOLIDATION GROUTING Construction Technical Measures of Consolidation Grouting 1 Work Items 1.1 Compilation basis and instruction 1) Foundation treatment specification during detailed
More informationDesign Data 4. Jacking Concrete Pipe
Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing
More informationREPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID
REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID TRANSIT SYSTEM Chi-Te Chang, Ming-Jung Wang, Chien-Tzen Chang, and Chieh-Wen Sun Central District Office, Department of Rapid Transit System, Taipei
More informationConcrete Pipe Jacking
Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used
More informationRisk Management of the Restoration of Shanghai Metro Line 4
ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management of the Restoration of Shanghai Metro Line 4 X. P. Yu, W. J. Zhu
More informationTunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure
Tunnels content of the lecture 1st Hour Tunnels Immersed tunnels Comparison Bored Tunnels (short) Land tunnels 2nd Hour Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield
More informationTotal Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT
Total Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT A fuzzy logic excavation system for tunnel boring machines, which
More informationFull-text paper MAGLEV REQUIREMENTS FOR TUNNELS
Full-text paper MAGLEV REQUIREMENTS FOR TUNNELS (Emergency Concepts, Security Exits, Cross-section Design, Guideway Types in the tunnel, Sonic-Boom-Effects, Shocks) (*) Author: Dipl.-Ing. Andreas WERTH,
More informationDiaphragm wall Construction
Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support
More informationSECTION PACKAGE BOOSTER PUMP STATIONS
SECTION 331223 PACKAGE BOOSTER PUMP STATIONS Scope: The Contractor shall install a pump station at two locations to be determined by the Owner. These pump stations shall be designed to deliver flow to
More informationThe new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump
The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded
More informationGroundwater management during the construction of underground hydrocarbon storage in rock caverns
Groundwater management during the construction of underground hydrocarbon storage in rock caverns Amantini Eric, Cabon François, Moretto Anne. Géostock. 7 rue E. et A. Peugeot. 92563 Rueil-Malmaison. France.
More informationAssessment of Tunnel Stability with Geotechnical Monitoring
Assessment of Tunnel Stability with Geotechnical Monitoring G. Güngör, A. Şirin, S. Kiziroglu, H.D. Altuntas, A. Durukan General Directorate of Turkish Highways, Ankara, Turkey T. Solak Temelsu International
More informationCurrent Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View
Current Hydro Power Plant Projects of Verbund in Austria and the use of High Strength Steel an Operators View J. Mayrhuber and P. Stering VERBUND Austrian Hydro Power AG, Am Hof 6a, A-1010 Wien, Austria
More informationAlaska Way Viaduct Replacement Project
Alaska Way Viaduct Replacement Project Presented by Gregory Hauser, PE Former VP Underground Operations Retired Jan. 8, 2018 Currently Senior Technical Advisor for JCK Underground, Inc. The Existing Alaska
More informationGround Freezing for Tunnel, Shafts, and Adits
Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction
More informationInstallation Manual For Conical Tanks. INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS
INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS Page 1 of 10 INDEX 1. Health & Safety 3 2. Introduction 3 3. Requirements 3 4. Working Area 3 5. Equipment 3 6. 2 and 3 metre tank above ground
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 7.2 MICRO TUNNELING 7.2.1 General Where indicated on the Drawings, or where field
More informationA SAFE MINE IS AN EFFICIENT MINE. END OF STORY. TO GROUT OR NOT TO GROUT?
FEBRUARY 2013 - VOLUME 22 NUMBER 02 TO GROUT OR NOT TO GROUT? Brad Crenshaw, P.E. P.G., Ground Engineering Contractors, Scott Langley, White Oak Resources LLC, Vic Daiber, P.E. P.L.S., Pittman Mine Services
More informationLGP800/1200/200PI-D Grout Station
LGP800/1200/200PI-D Grout Station Description LGP800/1200/200PI D grout station is a combination of mixer, agitator and grout pump in one plant. It is mainly used in highway, railway, hydropower, construction,
More informationStevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets
Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority
More informationD&B versus TBM some case stories
D&B versus TBM some case stories TBM Applications II Bergen, June 6 th and 7 th Project Manager Anne Kathrine Kalager Case stories Two different Projects Considerations regarding excavation method: New
More information4th International Engineering and Construction Conference - July 28, 2006
4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast
More informationMICROTUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS
MICROTUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS OUR EQUIPMENT SYSTEMS Since inception, Akkerman has grown with the evolution of industry demands. We offer pipe jacking, microtunneling, guided boring
More informationDredging Mining Industry. Sand and Gravel Dredging equipments and Industrial Pumps
Dredging Mining Industry Sand and Gravel Dredging equipments and Industrial Pumps Dredging Mining - Industry About Nearly two-thirds of the non-fuel minerals mined each year are aggregates. Dragflow has
More informationThen the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.
11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration