The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study

Size: px
Start display at page:

Download "The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study"

Transcription

1 Creative Construction Conference 2015 The U.S. Army Corp of Engineers traditional design review vs. A BIM review: A case study Miranda Griffin, Scott W. Kramer, Ph.D.* 118 M. Miller Gorrie Center, Auburn University, Auburn Alabama USA Abstract In the current turbulent funding environment, it is important that the U.S. Government spends every construction dollar wisely and does everything possible to get the best rate of return on those dollars. It is essential that cost control is managed during the design and construction phases of a project. The United States Army Corps of Engineers (USACE) recognized that having construction documents that are easily understood, free of design errors and omissions and met the needs of the customer saved time and money during the construction phase of the project. Because of this realization, USACE developed a formal design review process known as Bidability, Constructability, Operability and Environmental (BCOE) reviews. The BCOE review process has three goals (1) Identify problems related to errors, omissions, and inconsistencies that would keep contractors from bidding on a project; (2) Identify inappropriate construction methods and materials that would increase construction cost; (3) Identify building systems and components that would result in buildings that are difficult to maintain and operate. This case study was performed to analyze the effects of the Bidability, Constructability, Operability, and Environmental (BCOE) review process and Building Information Modeling (BIM) on a complex construction project managed by Mobile District, USACE. It was determined that performing the BCOE review ensures code compliance and customer requirements but BIM modeling easily identified design errors and conflicts. Keywords: BIM; Constructability; Design Errors; Project Delivery 1. Introduction U.S. Army Corp of Engineers BCOE Review Process The United States Army Corps of Engineers is mandated to perform a bidability, constructability, operability and environmental (BCOE) review for all construction projects [1]. Constructability and bidability are defined as the ease with which a designed project can be built and the ease with which the contract documents can be understood, bid, administered and executed. Operability is defined as the ease with which a project can be operated and maintained. An environmental review is performed to assure the protection of land, water, animals, plants, air and other natural resources from the effects of construction as stated in the environmental assessment. Also, the operation of the constructed project must protect the environment as stated in the environmental assessment. The purpose of the BCOE process is ensure efficient construction that is environmentally sound, to minimize cost and time growth, to avoid unnecessary changes and claims, as well as to ensure safe, efficient operations by the user [1]. The assigned reviewers are required to enter their review comments into the Automated Review Management System (ARMS). The PM collates the comments and sends them to the responsible design Architect Engineer (AE) firm. The AE firms provides copies of the comments to their sub architect engineer firms- electrical, mechanical, structural, and specialty systems. The AE firm and the sub architect engineer firms reviews the comments presented Tel.: ; fax: kramesw@auburn.edu 506

2 by the assigned reviewers and prepares a response for each comment. The PM coordinates a meeting to be attended by the assigned reviewers, AE firm and sub architect engineer firm, and project management personnel. During the meeting, agreement is reached between the AE firm and the person who made the comment of the action required in response to each comment. Either the AE firm clarifies that the design as presented is correct or the AE agrees that a change should be made to the design documents. This process continues until the final design has been corrected per the final design review meeting. After the approved final design is presented to the PM from the AE firm, the contract documents are put out for the construction contractors to bid. 2. Background Information for the Case Study The 7 th Special Forces, Phase I Military Construction project is a project that is part of the Base Realignment and Closure Program (BRAC). The project involves the construction of the entire compound on a virgin site for the Army s 7 th Special Forces Group. As part of the BRAC program, the 7 th Special Forces Group was slated to move their function to Eglin Air Force Base, which houses many other Special Forces group, in an effort to maximize joint training of all the Special Forces components. Phase I includes the construction of eight facilities, two elevated water towers, an underground communications and power distribution system, asphalt roads, a new intersection at Highway 85 and the clearing of 350 acres. Of the eight facilities constructed, four were designed by one Architect Engineer (AE) firm coded AE1. The remaining four facilities were designed by another AE firm coded AE2. The facilities designed by AE1 were four different facilities: Group Headquarters (), Group Support Battalion (), Dining Facility () and Combat Training Readiness Facility (). The four facilities designed by AE2 were four Battalion Headquarters (Batt HQ) that were exactly the same, so AE2 was responsible for only one design. The site work design was performed by one sub-architect engineer firm for the entire project. AE1 and AE2 worked with this sub-architect engineer firm to design the layout of the compound and to design all of the exterior systems to the facilities like the communications, power, storm water, and roadways. Each of the facilities has multiple electrical and mechanical systems within them. Each facility has a fire protection system, Heating, Ventilation Air and Conditioning system, Access Control system, and plumbing. The Batt HQ,, and have weapons vaults and a Secure Compartmentalized Information Facility (SCIF). The Dining Facility is a complex design of its own because a food kitchen consultant must work with the AE to coordinate the mechanical systems within the food kitchen equipment with the mechanical systems of the building. AE1 decided of his own accord to use BIM for each of the facilities that were his design responsibility. However, he was not able to use BIM for the other disciplines, electrical, mechanical, structural, because the sub architect firms did not have the BIM software and were not trained on how to use it (AE1, personal communication, November 17, 2012). AE2 did not use BIM for any portion of his design. The design concept of Phase I began in The average time from design concept to actual construction completion for the United States Corps of Engineers is five years. Because the project was a BRAC project, there was a definite completion date of September 15, However, there was an uncertainty of when the actual construction could begin because the site selection was held up in an environmental assessment with another project that was being challenged by the community. The AE firms were instructed to design the facilities without having a firm site selection. The Corps of Engineers continued the normal BCOE process and completed the design of each facility. When the site selection was finally completed the sub AE firm worked with each of the AE firms to finalize the layout of the compound and the location of each facility within the compound. The construction contract was awarded in January, The contract amount was $154,683,000. As stated earlier, the contract had a congressionally set completion date of September 15, 2011 which gave the contractor a construction time of two years and nine months to build eight facilities plus the power, communications and site infrastructure. Recognizing that the construction time had been significantly reduced, Mobile District, USACE decided to implement BIM during the construction phase. Because of funding, the BIM model of the facilities and the infrastructure was delayed at the onset of construction by four months. When the modeler was able to start the BIM models of the buildings, requests for information (RFI s) were generated to address the design errors that were detected by the BIM software. 507

3 3. Rational for the Case Study Mobile District, USACE has a robust military construction program. Each year billions of dollars are used to construct facilities for their military customers. Because of the national budget crisis, funding for military projects is highly competitive and the customers want the greatest return on their investment through cost effective design and construction processes. Controlling the time and cost growth of the project during the construction phase is very important to having a successful project. For many years, USACE has used the BCOE review process to eliminate as many design omissions and errors as possible during the design phase. Using the traditional BCOE approach, the designers, reviewers and builder are limited to using the two dimensional (2-D) drawings/views [2]. Using BIM, the designer creates an accurate geometric representation of the facility that is data-rich and facilitates collaboration among the designer and the reviewers. The BIM model is a common model of the facility that each person uses to either create their portion of the design or to use the software to analyze the design. Once the final BIM model is signed off on, the design is locked and can be transferred to the constructors for the construction phase. Since the BIM model can be used for virtual visualization, the constructors can use it to plan the most time efficient construction schedule for the project. The traditional BCOE review process stops at the design phase and is of no benefit to the constructors. BIM has the benefit of being used to same time during the design and the construction phase. Saving time and cost during the life-cycle of the project is of major importance to UASCE and our customers. Because using construction funding wisely is crucial as funding for construction projects becomes more competitive, USACE can show their customers that we are taking a proactive approach to finding effective management of this problem by investigating how BIM and other tools can be used to improve our construction process. 4. Data & Analysis Table 1 Facility BCOE REVIEW COMMENTS BY BUILDING & DISCIPLINE 35% REVIEW 65% REVIEW FINAL REVIEW BATT HQ Mech Architect Elect Plumbing Structural Fire Prot Total Table 1 depicts the number of comments by trade and by facility given by the reviewers during the three phases of the BCOE review process. As stated earlier in this paper, the civil/site work design was not completed until it was time to advertise the project for bidding and did not have a BCOE process. There are no comments for the civil/ site work design. The number of comments given for the and Batt HQ from the 35% review to the final design remained almost the same indicating that either the original comments revised the design in such a way that each time the design was presented it appeared like it was new design, the design was not back checked per the comment or the designer did not sufficiently correct the design per the original comment. If this facility were modeled during the design phase using BIM, the designer could have made the change per the comment in real time and collaborated in real time for accuracy and clarity to resolve the review comment. The steadiness of comments for these two facilities, also, was an indication that the documents for these two facilities would create the greatest difficulty for the contractor to understand during the construction phase. This fact is shown in Table 2 by the number of RFI s that were generated using BIM. Both the and Batt HQ have the two highest numbers of RFI s. The disciplines that have the three highest numbers of RFI s are architecture, structural and electrical. Two of these disciplines had the highest number of comments during the BCOE review. This indicates that the traditional BCOE process did not resolve whatever the issues were for these portions of the design. Whatever the errors were, the BIM modeler found them and quickly identified them for correction. If the error was identified early enough in the 508 BATT HQ BATT HQ

4 construction phase and no additional materials were needed, no additional cost was involved with making the change. If the response to the RFI, required the re-order for material that was either already onsite but not installed, the Government was assessed a cost for re-procurement. In a worse case, material actually installed, the Government was assessed a cost for re-procurement, re-work and overhead for time impacts. The installation of the structural steel and the electrical conduit for the security system for the first Battalion Headquarter facility was a worse case situation. The responses to the RFI s for the structural steel installation of the Battalion Headquarters would result in a new conflict and a new RFI to describe the new conflict. If the designer was using BIM, the conflict could have been resolved quicker and without creating a new conflict because the clash detection ability of the software would have identified any conflicts when the object was moved. The BIM modeler could have identified what correction was needed but in the contract arrangement the modeler was not to perform any design, only identify where the conflicts were in the design. Table 2 Request for Information (RFI s) by Building & Comment Facility BATT INFRASTRUCTURE TOTAL HQ Architect Structural % of these are resubmissions. Mech Elect Fire Prot Plumbing Concrete Civil/Site Total Table 3 shows which portion of the design had the most changes and the cost for those changes. The and the Dining Facility had the least number of changes and the lowest cost for changes. These two facilities also, had the two lowest numbers of comments during the BCOE review process. The two things that the two facilities did not have that the others did have are a weapons vault and a SCIF. A SCIF requires careful coordination between the electrical, mechanical, structural, and architectural designers. The structural steel for the walls of a SCIF has a precise layout requirement that must be met for it to be certified for its intended use. The steel design sets the precedence for how the remaining items are designed for the SCIF. An error in the steel design starts a domino effect on the remaining design of the SCIF. The numerous structural steel errors of the Battalion Headquarter facility caused a change order late in the construction phase that caused an expensive change for the electrical installation. The electrical conduits were installed but the design correction required them to be removed and re-installed. Table 3 Facility # of Changes by Facility & BATT. HQ Infrastruc. $ Value of Changes by Facility & BATT HQ Infrastruc. Mech ,763 52,892 46,529 74, ,766 0 Architect ,11, ,407 8,835 78, ,180 47,221 Elect , ,271 73,213 73,213 6,554, ,519 Plumbing , , ,348 Structural ,235 38,519 3, ,180 0 Fire Prot ,024 53, , ,277 0 Concrete ,836 23,823 Civil/Site , ,879 9,574,666 Total ,553, , , ,158 8,570,894 10,794,

5 The portion of the design that had the second highest number of changes but the highest cost was the infrastructure. The infrastructure design was completed late in the design phase and did not go through the formal BCOE process. However, in this instance the BCOE review process would not have helped to eliminate most of the changes that occurred on the infrastructure because the changes were related to environmental permitting. The Florida Northwest Florida Water Management (NWFWM) department mandated most of the changes for the infrastructure design. The changes were related to meeting their standards for establishing stabilized site after all of the trees were removed from the 350 acres. The civil/site work designer provided a design that was easily constructible but NWFWM had strict standards of how they wanted the civil/site work designed. NWFWM issues the permit for the project and is the Authority Having Jurisdiction (AHJ) so the Government and the civil/site work designer were at their mercy. Two of the 39 changes on the infrastructure design were due to a different site condition. There was clay discovered in areas of the site that were not revealed by the borings. There were six changes on the electrical design for the infrastructure that were due to conflicts with the storm water piping. The BIM modeler did not model the infrastructure but if the model was performed it would have revealed the conflict between the electrical conduits and the storm water piping. The $732,519 that was spent on the electrical changes could have been saved. The BIM model would not have helped save the cost due to NWFWM requirements though the BIM software has the ability to verify code compliance. BIM could have been used to show that the civil/site work designed met those code requirements. In this instance the opinion of the NWFWM would override, regardless. Table 4 - Constructability Analysis Building # of Issues Identified Trade Percentage BHQ 90 Framing 58% 14 HVAC 17% 56 Fire Protect 2% 51 Steel 19% 11 Concrete 3% TOTAL 222 All other trades 1% (Information Courtesy of Thompson Engineering, Mobile, AL) The information shown in Table 4 shows the number of issues identified in each facility by the BIM software and the percentage of those items by trade. Per the constructability analysis report, the cost savings that was realized during the construction phase of the project was $3,064,000 to $6,432,000. (Thompson Engineering, personal communication, November 21, 2012) The cost savings are based upon the construction time saved and the labor that was saved by not having to do re-work. Constructability Report showing Clash Detection. Cut view from design document indicating conflict. Figure 1 (Courtesy of Thompson Engineering, Mobile, AL) 510

6 The BIM software indicates the conflict by clash detection and provides a report of the issue as shown in Figure 1. These reports can be used during the design phase to correct the design or during the construction phase to assist the constructor. The constructability reports were used by the construction contractor on the Phase I project to save time during the construction. In Figure 1, the conflict indicated is between the HVAC ductwork and structural steel members. This same report was used to show the HVAC ductwork was entering the electrical room in a location that would violate the National Electrical Code. The traditional BCOE review process did not reveal these design errors. 5. Conclusion On the 7 th Special Forces Phase I project, the RFI s that were saved by the BCOE review process was mainly code compliance and customer specific requirements. Very few of the comments revealed any design conflicts. Both code compliance and customer satisfaction items are very important and do result in time and cost savings. The elimination of conflicts and design omissions in the construction documents results in cost savings and customer satisfaction through the construction of a facility that is constructible, operable and maintainable. The design errors were discovered through the use of BIM. Although the BIM model was delayed by four months from the construction start, the modeler was able to build the models of the facilities in time to report the many conflicts between the structural steel and other systems in time to minimize construction delays. If BIM had been used during the design phase, the number of RFI s eliminated during the design phase would have virtually erased the RFI s that were generated during construction phase. The BCOE review process alone did not eliminate the RFI s that were generated from design conflicts and omissions. The cost savings realized of using BIM for the design review would easily have been approximately $10,798,067 which is the cost of the mechanical, electrical, architectural and structural changes. The clash detection software of the BIM models of the facilities identified design conflicts between the various systems that were not identified through the traditional BCOE review process. All design conflicts will not be discovered or eliminated by either the BCOE review process or BIM because there is a human factor involved with each. However, using the two processes together may eliminate the majority of the design conflicts. References [1] East, W., Roessler, T., Lustig, M., (1995) Improving The Design-Review Process: The Reviewer s Assistant, Journal of Computing In Civil Engineering, [2] Korman, T., Simonian, L., Spiedel,E., (2008), Using Building Information Modeling to Improve the Mechanical, Electrical, and Plumbing Coordination Process for Buildings, American Society of Civil Engineers. 511

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

CHAPTER 7 Building Information Modeling

CHAPTER 7 Building Information Modeling CHAPTER 7 Building Information Modeling Dr Nabil Elsawalhi Associate Professor of Construction Management 1 Information and Communication Technology/ Building Information Modeling New approaches to construction

More information

INTEGRATED PROJECT DELIVERY AIA / AGC JOINT COMMITTEE

INTEGRATED PROJECT DELIVERY AIA / AGC JOINT COMMITTEE INTEGRATED PROJECT DELIVERY AIA / AGC JOINT COMMITTEE 03.24.09 INTRODUCTION: PRESENTERS CLYMER CEASE, AIA, LEED AP / PRINCIPAL / PEARCE BRINKLEY CEASE + LEE ARCHITECTURE SHANN RUSHING, AIA / ASSOCIATE

More information

STRATEGIC ARCHITECTURAL DESIGN: HOW TO MEET BUSINESS GOALS AND MAXIMIZE ROI

STRATEGIC ARCHITECTURAL DESIGN: HOW TO MEET BUSINESS GOALS AND MAXIMIZE ROI STRATEGIC ARCHITECTURAL DESIGN: HOW TO MEET BUSINESS GOALS AND MAXIMIZE ROI TABLE OF CONTENTS PART I: STRATEGIC PROJECT PLANNING AND SMARTER DESIGN...4 PART II: STRATEGIES TO CAPTURE VALUE AND SAVINGS

More information

Bronx Mental Health Redevelopment Project

Bronx Mental Health Redevelopment Project Bronx Mental Health Redevelopment Project Residential Village Bronx Campus Transitional Living Residences, Haven House Horizon House, and Studio Apartments BIM Orientation December 20, 2012 1 Bronx Mental

More information

Dallas City Performance Hall: Building Information Modeling as a Decision-Making Tool

Dallas City Performance Hall: Building Information Modeling as a Decision-Making Tool Dallas City Performance Hall: Building Information Modeling as a Decision-Making Tool Will Mitchell Corgan Associates, Inc. DL5395 Dallas City Performance Hall is a 750-seat theater facility scheduled

More information

600 - Phase C Intermediate Review Checklist for the Architect- Engineer

600 - Phase C Intermediate Review Checklist for the Architect- Engineer 600 Phase C Intermediate Review Checklist for the Architect Engineer This checklist is to be used by the ArchitectEngineer during Phase C of the Project and shall be included in the Intermediate Review

More information

Benjamin D. Hall Interdisciplinary Research Building

Benjamin D. Hall Interdisciplinary Research Building Benjamin D. Hall Interdisciplinary Research Building Design. Build. Operate. Maintain. 2007 BIM AWARDS AIA Technology in Architectural Practice Table of Contents ARCHITECT S STATEMENT DESCRIPTIVE DATA

More information

changes and modifications are inevitable, even in the contemporary BIM approach in the building design process, and developing a collaborative BIM pla

changes and modifications are inevitable, even in the contemporary BIM approach in the building design process, and developing a collaborative BIM pla Developing the Standard Operating Procedures of BIM Collaboration Management for General Contractor Hui-Hsuan Yang 1 and Yu-Cheng Lin 2 1) PhD Student, Department of Civil Engineering, National Taipei

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

UTILITY COORDINATION FOR CAPITAL IMPROVEMENTS PROJECTS

UTILITY COORDINATION FOR CAPITAL IMPROVEMENTS PROJECTS DIVISION V SECTION 5900 UTILITY COORDINATION FOR CAPITAL IMPROVEMENTS PROJECTS Best Management Practices (March 17, 2010) APWA 5900 March 2010 DIVISION V DESIGN CRITERIA 5900 Utility Coordination for Capital

More information

The Efficient Construction Delivery Method

The Efficient Construction Delivery Method The Efficient Construction Delivery Method March 2010 Today s Altered Landscape & JOC The Efficient Construction Delivery Method A Job Order Contract is a long-term, indefinite delivery-indefinite quantity

More information

Realizing Complex Design Through BIM The Louisiana State Museum and Sports Hall of Fame

Realizing Complex Design Through BIM The Louisiana State Museum and Sports Hall of Fame The Louisiana State Museum and Sports Hall of Fame Location: Natchitoches, Louisiana Category: A: BIM Excellence Type: New Construction Site Area: 36,500 sq. ft. GSF Total: 27,000 sq. ft NAA Total: 18,900

More information

Measuring the Impact of BIM in Design-Bid-Build

Measuring the Impact of BIM in Design-Bid-Build Measuring the Impact of BIM in Design-Bid-Build A Case Study Dace A. Campbell, AIA, LEED AP // BNBuilders // 2 November 2011 The Associated General Contractors of America (AGC) is a Registered Provider

More information

9 QA/QC DURING DESIGN 9.3 DESIGN REVIEWS

9 QA/QC DURING DESIGN 9.3 DESIGN REVIEWS Chapter: Procedure: 9 QA/QC DURING DESIGN 9.3 DESIGN REVIEWS Revised: May 15, 2018 PURPOSE The purpose of this procedure is to provide a guideline for design reviews. Design reviews are usually conducted

More information

[FISK CORPORATE HEADQUARTERS]

[FISK CORPORATE HEADQUARTERS] Thesis Proposal Stephen Blanchard 12/14/2012 Advisor: Dr. Messner [FISK CORPORATE HEADQUARTERS] Houston, Texas Executive Summary With the completion of the Fisk Corporate Headquarters project taking place

More information

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards I. INTRODUCTION The Los Angeles Community College District is currently undertaking the largest public sector sustainable building effort in the United States, funded by its Proposition A/AA and J Bond

More information

Design-Assist Delivery for Prefabricated Building Components

Design-Assist Delivery for Prefabricated Building Components Design-Assist Delivery for Prefabricated Building Components Darren Olsen, Duncan Varner, Mark Taylor, Salman Azhar and Mark Tatum Auburn University Auburn Alabama Prefabrication offers a potential means

More information

Careers List Professional Careers in Construction

Careers List Professional Careers in Construction Careers List Professional Careers in Construction Architect Designs buildings, including the preparation of detailed construction drawings and specifications, and advises on their construction. May specialize

More information

Review Plan. For. Lock & Dam No. 2 Scour Hole Repair, Implementation Documents. Bladen County, North Carolina P2 #:

Review Plan. For. Lock & Dam No. 2 Scour Hole Repair, Implementation Documents. Bladen County, North Carolina P2 #: Review Plan For Lock & Dam No. 2 Scour Hole Repair, Implementation Documents Bladen County, North Carolina P2 #: 111630 U.S. Army Corps of Engineers Wilmington District Wilmington, North Carolina July

More information

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF

FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE

More information

CUTTING INDIRECT SPEND COSTS THE POWER OF THIRD-PARTY SOURCING

CUTTING INDIRECT SPEND COSTS THE POWER OF THIRD-PARTY SOURCING CUTTING INDIRECT SPEND COSTS THE POWER OF THIRD-PARTY SOURCING INTRODUCTION The business environment is ever-evolving, fluctuating moment to moment and year to year. The marketplace in which you deal today

More information

APPENDIX D CONSTRUCTION PHASE CRITERIA

APPENDIX D CONSTRUCTION PHASE CRITERIA A. GENERAL REQUIREMENTS CONSTRUCTION PHASE CRITERIA For the Construction Phase of the Project, the Architect/Engineer (A/E) is responsible for providing project administration for the Owner in accordance

More information

Chapter 2 CONSULTANT SERVICES

Chapter 2 CONSULTANT SERVICES A. INTRODUCTION Chapter 2 CONSULTANT SERVICES 1. In order to supplement the work of the OGS D&C professional design staff, private sector Architectural/Engineering (A/E) Consultants are frequently employed

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply

More information

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM WHAT S INSIDE: 1 BENEFITS Keep constructability top-of-mind Improve project margins Make better

More information

Best Practices Manual

Best Practices Manual Best Practices Manual Canada, C1A 7L3 Page 1 of 18 Table of Contents Introduction 0 Division 00 - Bid Documents 0.1 Alternate Bids 0.2 To be developed 1 Division 01 - General Requirements 1.1. Tender Document

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT AND MANAGER that offers comprehensive management throughout the project, from concept to completion, yielding the greatest possible benefit to the owner. IPS will offer uncolored

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING Baltimore, Maryland Dan Weiger Architectural Engineering, 5th Year Construction Management Option Thesis Proposal Advisor: Dr. John I. Messner January 26, 2009

More information

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CEMP-ET Engineer Regulation 1110-345-53 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Engineering and Design STRUCTURAL STEEL CONNECTIONS Distribution Restriction Statement

More information

How to Best Represent Your Firm: Proposal Writing Tips

How to Best Represent Your Firm: Proposal Writing Tips How to Best Represent Your Firm: Proposal Writing Tips Hugh Scott Pittman, PE Project Engineer Contract Management Section Shane D. Hall, PE Chief Contract Management Section Huntington, WV US Army Corps

More information

SPEED FRAMING: FRAMER AND COMPONENT MANUFACTURER TEAM UP WITH TECHNOLOGY. A case study by MiTek

SPEED FRAMING: FRAMER AND COMPONENT MANUFACTURER TEAM UP WITH TECHNOLOGY. A case study by MiTek SPEED FRAMING: FRAMER AND COMPONENT MANUFACTURER TEAM UP WITH TECHNOLOGY A case study by MiTek TIMBER TECHNOLOGIES AND PRECISION TRUSS SET NEW STANDARDS IN PRECISION AND SPEED Executive Summary: Timber

More information

Central Consolidated School District Purchasing Procurement Guidelines

Central Consolidated School District Purchasing Procurement Guidelines Central Consolidated School District Purchasing Procurement Guidelines Procurement Purchasing Procedures: The following procedures have been implemented to comply with the State of New Mexico regulations

More information

DESIGN + BUILD CONSTRUCTION

DESIGN + BUILD CONSTRUCTION DESIGN + BUILD CONSTRUCTION The Power of Design and Construction Traditional construction methodology is changing. Under the traditional approach, design and construction services are split into separate

More information

American Buildings Company. ABC & BIM BIM is driving an unparalleled revolution in the construction industry using 3D digital modeling software.

American Buildings Company. ABC & BIM BIM is driving an unparalleled revolution in the construction industry using 3D digital modeling software. American Buildings Company ABC & BIM BIM is driving an unparalleled revolution in the construction industry using 3D digital modeling software. The BIM process produces a digital prototype of your project,

More information

Integrated Project Delivery

Integrated Project Delivery NSBA/COSA Copyright 2015 National School Boards Association. All rights reserved. Integrated Project Delivery Code of Hammurabi (circa 1772 BC) 229 If a builder build a house for some one, and does not

More information

USERS BENEFITS IN USING BIM (BUILDING INFORMATION MODELING) Nilforoushan, Massih. Saint John International University, Turin, Italy

USERS BENEFITS IN USING BIM (BUILDING INFORMATION MODELING) Nilforoushan, Massih. Saint John International University, Turin, Italy USERS BENEFITS IN USING BIM (BUILDING INFORMATION MODELING) Nilforoushan, Massih Saint John International University, Turin, Italy (Email: Nilforoushan.ma@gmail.com) Keyword: Performance assessment in

More information

PRESENTERS. Paul James. Senior Vice Vice President, Risk Risk Management & & General Counsel. Bond Brothers, Inc.

PRESENTERS. Paul James. Senior Vice Vice President, Risk Risk Management & & General Counsel. Bond Brothers, Inc. Senior Vice Vice President, Risk Risk Management & & General Counsel PRESENTERS Paul James Senior Vice President, Risk Management & General Counsel Bond Brothers, Inc. Kenneth Rubinstein Co-Chair of Construction

More information

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY

More information

HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN

HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN PROJECT INTRODUCTION PROGRAM + DESIGN RESPONSE Built-to-Suit prototype Medical Clinic was designed in response to tenant s extensive development

More information

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING

JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING JOHNS HOPKINS HOSPITAL NEW CLINICAL BUILDING Baltimore, Maryland Dan Weiger Architectural Engineering, 5th Year Construction Management Option Thesis Proposal Advisor: Dr. John I. Messner December 12,

More information

Current Status of Building Information Modeling (BIM) Adoptability in the U.S. Electrical Construction Industry

Current Status of Building Information Modeling (BIM) Adoptability in the U.S. Electrical Construction Industry Fifth International Conference on Construction in the 21 st Century (CITC-V) Collaboration and Integration in Engineering, Management and Technology May 20-22, 2009, Istanbul, Turkey Current Status of

More information

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA

REQUEST FOR PROPOSALS FOR. Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA REQUEST FOR PROPOSALS FOR Site Civil Services for the Iowa River Landing Arena CITY OF CORALVILLE IOWA City of Coralville Iowa Coralville, IA Page 1 of 6 Please review and provide response to this letter

More information

SIX KEY BENEFITS OF BUILDING INFORMATION MODELING (BIM)

SIX KEY BENEFITS OF BUILDING INFORMATION MODELING (BIM) SIX KEY BENEFITS OF BUILDING INFORMATION MODELING (BIM) INTRODUCTION Comprehensive planning is key to every successful construction project, and smart use of technology can significantly improve the planning

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

2011 BIM Awards. Using BIM to Design and Build the Wounded Warrior Headquarters and Hope and Care Center. Category A: BIM Excellence

2011 BIM Awards. Using BIM to Design and Build the Wounded Warrior Headquarters and Hope and Care Center. Category A: BIM Excellence Using BIM to Design and Build the Wounded Warrior Headquarters and Hope and Care Center Category A: BIM Excellence Project Description 01 Maintaining Integrity of Design 03 New Concepts Procedures and

More information

Change Order Causation; Who is the Guilty Party?

Change Order Causation; Who is the Guilty Party? Change Order Causation; Who is the Guilty Party? Darren Olsen, Roger Killingsworth and Brandon Page Auburn University Auburn, Alabama Change orders are an all too common part of construction projects.

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge

More information

Requests for Information pm Draft for Request for Proposals Sprouts - Shell/Civil Issued on April 25, 2018

Requests for Information pm Draft for Request for Proposals Sprouts - Shell/Civil Issued on April 25, 2018 Requests for Information - 0.08.18 pm Draft for Request for Proposals Sprouts - Shell/Civil Issued on April 2, 2018 RFI 01 Is the RFP due at 4pm or pm on May 16th? An Addendum will change to due date to

More information

Review Plan U.S. Army Corps of Engineers Northwest Division Kansas City District. Kanopolis Dam Emergency Gate Replacement

Review Plan U.S. Army Corps of Engineers Northwest Division Kansas City District. Kanopolis Dam Emergency Gate Replacement Review Plan U.S. Army Corps of Engineers Northwest Division Kansas City District Kanopolis Dam Emergency Gate Replacement April 2015 1. PURPOSE AND REQUIREMENTS 1.1 PURPOSE This Review Plan is intended

More information

AIA Technology in Architectural Practice 2008 BIM Award Harley-Davidson Museum. M. A. Mortenson Company. All rights reserved.

AIA Technology in Architectural Practice 2008 BIM Award Harley-Davidson Museum. M. A. Mortenson Company. All rights reserved. AIA Technology in Architectural Practice 2008 BIM Award Harley-Davidson Museum Tableof Contents DESCRIPTIVE DATA Architect s Statement 3 Contractor s Statement 4 Owner s Statement 5 Project narrative The

More information

Design Review Process FACILITY OPERATIONS

Design Review Process FACILITY OPERATIONS Design Review Process FACILITY OPERATIONS DESIGN REVIEW LEAN TEAM AUGUST 2016 CONTENTS Introduction...3 Participants...3 Design Reviewers Facility Operations...4 Providing Feedback...5 Design Review Sessions...6

More information

BID PHASE GUIDELINES

BID PHASE GUIDELINES Chapter 7 BID PHASE GUIDELINES A. INTRODUCTION 1. The Bid Phase starts once the project has been accepted by the OGS D&C Office of Project Control (OPC) and passed on to the OGS D&C Office of Contract

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

Technology Transforms Existing Building Into 21st Century Workspace

Technology Transforms Existing Building Into 21st Century Workspace Project Overview Technology Transforms Existing Building Into 21st Century Workspace The Northwestern Mutual - Van Buren Office Building project included the complete remodel of a seven-story, 162,087-square-foot

More information

Jay Miller Director of Operations Baker Electric Solar

Jay Miller Director of Operations Baker Electric Solar Construction Industry Breakout Jay Miller Director of Operations Baker Electric Solar (content assist from Wayne Holley) July 22, 2016 PMI SD San Business Diego Presentation Chapter www.pmi-sd.org 2015

More information

The Maryland-National Capital Park and Planning Commission

The Maryland-National Capital Park and Planning Commission Class Definition: Under direction and as a Licensed Registered Professional Architect, Landscape Architect or Engineer, manages (1) a set of the most challenging park, recreation facility design or construction

More information

TABLE OF CONTENTS I. PARTIES TO THE CONSTRUCTION PROJECT...1 A. OWNER...1 B. ARCHITECT...1 C. INSPECTING ARCHITECT...1 D. CONTRACTOR...

TABLE OF CONTENTS I. PARTIES TO THE CONSTRUCTION PROJECT...1 A. OWNER...1 B. ARCHITECT...1 C. INSPECTING ARCHITECT...1 D. CONTRACTOR... Page TABLE OF CONTENTS I. PARTIES TO THE CONSTRUCTION PROJECT...1 A. OWNER...1 B. ARCHITECT...1 C. INSPECTING ARCHITECT...1 D. CONTRACTOR...1 E. SUBCONTRACTOR...1 F. CONSTRUCTION MANAGER...1 II. THE CONTRACT

More information

6/10/2018. Building Information Modeling Overview. Pirtle s History with Building Information Modeling (BIM)

6/10/2018. Building Information Modeling Overview. Pirtle s History with Building Information Modeling (BIM) Building Information Modeling Overview Pirtle s History with Building Information Modeling (BIM) 1 Pirtle & BIM Pirtle & BIM Pirtle delivers first As-Build Model to FAU and UF Pirtle delivers 4D model

More information

The Case For QUALIFICATIONS-BASED SELECTION

The Case For QUALIFICATIONS-BASED SELECTION AMERICAN COUNCIL OF ENGINEERING COMPANIES OF OKLAHOMA 201 N.E. 27TH STREET SUITE 135 OKLAHOMA CITY OK 73105-2740 405.525.7696 FAX 405.557.1820 E-MAIL: jsullins@acecok.org WEBSITE: www.acecok.org The Case

More information

The Sterling & Francine Clark Art Institute

The Sterling & Francine Clark Art Institute The Sterling & Francine Clark Art Institute Williamstown, MA. Senior Thesis Proposal Mohamed S. Alali, CM Dr. Rob Leicht December Executive Summary The Senior Thesis Proposal purpose is to overview the

More information

P U R C H A S I N G D E P A R T M E N T K R I S T E N J. S P I C O L A, CPPB A N N U A L R E P O R T P U R C H A S I N G A G E N T

P U R C H A S I N G D E P A R T M E N T K R I S T E N J. S P I C O L A, CPPB A N N U A L R E P O R T P U R C H A S I N G A G E N T P U R C H A S I N G D E P A R T M E N T A N N U A L R E P O R T K R I S T E N J. S P I C O L A, CPPB P U R C H A S I N G A G E N T The mission of the Purchasing Department of the Board of Water Works of

More information

The Sterling & Francine Clark Art Institute

The Sterling & Francine Clark Art Institute The Sterling & Francine Clark Art Institute Williamstown, MA. Revised Senior Thesis Proposal Mohamed S. Alali, CM Dr. Rob Leicht January 13, Executive Summary The Senior Thesis Proposal purpose is to overview

More information

A Comparison of Realized Benefits of BIM Implementation on Commercial Building and Parking Garage Projects

A Comparison of Realized Benefits of BIM Implementation on Commercial Building and Parking Garage Projects A Comparison of Realized Benefits of BIM Implementation on Commercial Building and Parking Garage Projects Jonathan W. Elliott, Ph.D., Svetlana Olbina, Ph.D., and Manikandan Natesan Colorado State University

More information

BIM Checklist. Introduction

BIM Checklist. Introduction Introduction This Building Information Modeling (BIM) Checklist is intended to be used as a guide for project stakeholders who are looking to implement BIM/VDC in a design-build project. Since integration

More information

To Bid or Not To Bid

To Bid or Not To Bid To Bid or Not To Bid That Should NOT Be a QUESTION When soliciting bids for various purchases, including asphalt and road equipment, townships have a variety of tools at their fingertips. From requests

More information

BIM Standard and Specifications for San Mateo County. Project Development Unit

BIM Standard and Specifications for San Mateo County. Project Development Unit BIM Standard and Specifications for San Mateo County Project Development Unit Table of Contents A. INTRODUCTION AND GENERAL REQUIREMENTS... 2 B. DEFINITIONS, TERMS, AND DESCRIPTIONS... 3 C. BIM KICK OFF

More information

Construction Defects and Contract Breach 1

Construction Defects and Contract Breach 1 Construction Defects and Contract Breach 1 Presented by: David Hansen Eichelbaum, Wardell, Hansen, Powell, and Mehl P.C. 1 Copyright 2015, Eichelbaum, Wardell, Hansen, Powell, and Mehl P.C. 1 Construction

More information

practice Midland Steel Reinforcement Supplies TEKLA SOFTWARE Solutions

practice Midland Steel Reinforcement Supplies TEKLA SOFTWARE Solutions in TEKLA SOFTWARE practice Midland Steel Reinforcement Supplies Leading independent reinforcing steel fabricator, Midland Steel, has been using Tekla software to communicate its vast experience in business,

More information

Albuquerque District

Albuquerque District US ARMY CORPS OF ENGINEERS Albuquerque District Government 237 217 200 to Business 80 252 Outreach 237 217 200 119 174 237 217 200 27.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120

More information

ATTACHMENT 4. New Eastside Regional Park Phase 1. BIM (Building Information Modeling) 3D Design & Modeling Program Requirements

ATTACHMENT 4. New Eastside Regional Park Phase 1. BIM (Building Information Modeling) 3D Design & Modeling Program Requirements ATTACHMENT 4 New Eastside Regional Park Phase 1 BIM (Building Information Modeling) 3D Design & Modeling Program Requirements Bidders to be aware all BIM are for your information only and are not for estimating

More information

BIM Design & Construction Requirements. Follow-up Seminar. September 10,

BIM Design & Construction Requirements. Follow-up Seminar. September 10, BIM Design & Construction Requirements Follow-up Seminar September 10, 2009 www.indiana.edu/~uao/iubim.html Opening Comments Two years ago Indiana University began the process of embracing the use of Building

More information

FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors TAKE A CLOSER LOOK ENGINEERING SERVICES

FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors TAKE A CLOSER LOOK ENGINEERING SERVICES FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors TAKE A CLOSER LOOK ENGINEERING SERVICES FACILITY ENGINEERING It s what s inside that counts. Modern facilities require the

More information

The Impact of BIM and VDC on Company Business Processes

The Impact of BIM and VDC on Company Business Processes By Terry D. Bennett, LS LPF MRICS LEED AP Senior Industry Manager, Civil Engineering and Heavy Construction Autodesk, Inc. Paper prepared for presentation at the Geometric Design Lessons Learned: Case

More information

Attachment 1 Architectural Services

Attachment 1 Architectural Services A. Phase 1, Programming and Schematic Design: 1. Ascertain the requirements for each project through a meeting with the COUNTY, and a review of an existing schematic layout of each project, if such layout

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

BIM Design & Construction Requirements Indiana University

BIM Design & Construction Requirements Indiana University BIM Design & Construction Requirements Indiana University AGC BIM Forum - Philadelphia October 9, 2009 www.shp.com Opening Comments Two years ago Indiana University began the process of embracing the use

More information

THE PROCESS. Phase 1 Pre-Design Objective: Determine the owner s criteria for the project. Fee Breakdown: 5-10% of total fee.

THE PROCESS. Phase 1 Pre-Design Objective: Determine the owner s criteria for the project. Fee Breakdown: 5-10% of total fee. Considerations on Hiring an Architect How the Design Process Works Page 1 of 9 This guide explains the progression of a typical project from an idea through construction of an actual building. Projects

More information

The Maryland-National Capital Park and Planning Commission

The Maryland-National Capital Park and Planning Commission Class Definition: Under direction, manages a full range of challenging projects to design or construct park or recreation facilities as a Registered Professional Architect; works fully proficiently as

More information

I. Project Overview and Limits. Project Goal

I. Project Overview and Limits. Project Goal Scope of Work and Deliverables for Subsurface Utility Engineering (SUE) for both Underground and Overhead Utilities on T.H. 10, and its Connecting Roads under S.P. 8001-40 I. Project Overview and Limits

More information

DBE METHODOLOGY AND GOAL FOR VALLEY REGIONAL TRANSIT FOR FEDERAL FISCAL YEARS: 2017, 2018, and 2019

DBE METHODOLOGY AND GOAL FOR VALLEY REGIONAL TRANSIT FOR FEDERAL FISCAL YEARS: 2017, 2018, and 2019 DBE METHODOLOGY AND GOAL FOR VALLEY REGIONAL TRANSIT FOR FEDERAL FISCAL YEARS: 2017, 2018, and 2019 November 30, 2016 Page 1 of 6 OVERVIEW OF THE GOAL-SETTING PROCESS The following narrative explains the

More information

AGENDA. BIM Opportunities for CMMS

AGENDA. BIM Opportunities for CMMS AGENDA BIM Opportunities for CMMS Mark Falzarano, BIM Leader, AE Services Group, Barton Malow Company Keith Vandenbussche, FMA, Director, Facilities Services, Barton Malow Company Jason Wells, Vice President,

More information

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

Construction coordination

Construction coordination SBS5322 Basics of Building Information Modelling http://ibse.hk/sbs5322/ Construction coordination Ir. Dr. Sam C. M. Hui Faculty of Science and Technology E-mail: cmhui@vtc.edu.hk Jan 2018 Contents Construction

More information

Addendum #2 Bid Opportunity RFP to Replace the Township of Wellesley s Fire Station #2. Closing Date: Friday, January 25, :00 hrs.

Addendum #2 Bid Opportunity RFP to Replace the Township of Wellesley s Fire Station #2. Closing Date: Friday, January 25, :00 hrs. Addendum #2 Bid Opportunity 2018-08 RFP to Replace the Township of Wellesley s Fire Station #2 Closing Date: Friday, January 25, 2019 09:00 hrs. Question 1: How close to the property line can the septic

More information

Full-Scope Commissioning for High-Quality Buildings

Full-Scope Commissioning for High-Quality Buildings Full-Scope Commissioning for High-Quality Buildings Pieter L. van der Mersch, PE, QCxP University of Colorado Boulder 21 st National Conference on Building Commissioning AIA Quality Assurance The Building

More information

DESIGN FOR INFRASTRUCTURE SERVICE LIFE

DESIGN FOR INFRASTRUCTURE SERVICE LIFE DESIGN FOR INFRASTRUCTURE SERVICE LIFE INTRODUCTION Process flows from design to construction, maintenance and rehabilitation For infrastructure to function effectively, it must start with a good design

More information

A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS. 10 Advantages of. Design Build

A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS. 10 Advantages of. Design Build A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS 10 Advantages of Design Build WHERE TO START Welcome. I prepared this guide after seeing so many people struggle with understanding

More information

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent

KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent KRISTOPHER J. BRICE Construction Management Faculty Consultant: Dr. Christopher Magent 8353 University Boulevard, Moon Township, PA 15108 Thesis Proposal THIRD REVISION 3/19/2010 Table of Contents Executive

More information

BIM Execution Plan. Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP

BIM Execution Plan. Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP BIM Execution Plan Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP By signature below, this BIM Execution Plan is herewith adopted and incorporated into the Agreement, dated,

More information

Requests for Information pm Draft for Request for Proposals Sprouts - Shell/Civil Issued on April 25, 2018

Requests for Information pm Draft for Request for Proposals Sprouts - Shell/Civil Issued on April 25, 2018 Requests for Information - 05.0.1 5pm Draft for Request for Proposals Sprouts - Shell/Civil Issued on April 25, 201 RFI 01 Is the RFP due at 4pm or 5pm on May 16th? Response: RFI 02 Do you have an anticipated

More information

Eastern Michigan University

Eastern Michigan University Eastern Michigan University Prepared by: EMU Physical Plant Facilities Planning and Construction Page Intro-1 Purpose of Eastern Michigan University Physical Plant; Facilities Planning and Construction

More information

Implementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood

Implementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and

More information

The Maryland-National Capital Park and Planning Commission

The Maryland-National Capital Park and Planning Commission Class Definition: Under direction, manages a full range of challenging projects to design or construct park or recreation facilities as a Registered Professional Landscape Architect; works fully proficiently

More information

Is the art and science of precision measurement and navigation in and on construction sites.

Is the art and science of precision measurement and navigation in and on construction sites. THEOMETRICS Is the art and science of precision measurement and navigation in and on construction sites. There is little benefit from Innovations without Implementation. Technology drives business only

More information

WHITE PAPER PROTON THERAPY THREE STEPS TO ACHIEVE SUCCESSFUL MEP COORDINATION FOR PROTON THERAPY PROJECTS. May 2018

WHITE PAPER PROTON THERAPY THREE STEPS TO ACHIEVE SUCCESSFUL MEP COORDINATION FOR PROTON THERAPY PROJECTS. May 2018 WHITE PAPER PROTON THERAPY THREE STEPS TO ACHIEVE SUCCESSFUL MEP COORDINATION FOR PROTON THERAPY PROJECTS May 2018 www.gilbaneco.com PROTON THERAPY White Paper THREE STEPS TO ACHIEVE SUCCESSFUL MEP COORDINATION

More information