CASE STUDIES EPC NTPC LIMITED. Mandsaur, Madhya Pradesh CASE STUDY
|
|
- Aubrey Butler
- 6 years ago
- Views:
Transcription
1 CASE STUDIES NTPC LIMITED Mandsaur, Madhya Pradesh CASE STUDY
2 NTPC LIMITED Mandsaur, Madhya Pradesh PROJECT OVERVIEW R Site Co-ordinates 24.1N, 75.8E R Plant capacity 50 MW R Connection Type & Connected to Grid connected- 220/33KV Grid substation, R Connected to NTPC, Gujjerkhedi, Mandsaur R Rated System Power 50 MW R Total Site Span 5.05 km R Number of Modules About 1,60,000 nos. R Inverter Solar Grid Connected Inverter (40 nos.) R Power Evacuation 50 MW power are being evacuated with 33KV line from individual projects and the same are connected with 220KV GSS R Total Land Area 250 acres
3 be installed in an optimum manner. Mitigation: Variable pitch design methodology was implemented to mitigate shading losses in the undulated land. Weather: The temperature in the region was at C whereas during winters the temperature would drop down to 100 C. Mitigation: To keep up with the deadline, the project team at site used to wear winter jackets during the cold season and they braved the summer with potable water which was adequately provided by us. CASE STUDIES NTPC Limited Mandsaur, MP CHALLENGES & SOLUTION Land Undulation: The land is undulated with an inclination of 11 degrees. Mitigation: A special drilling machine (Crawler) was used on the undulated land. This also allowed us to achieve excellence without a single incident. Soil and Land Strata: Soil in the area is essentially weathered rock soil and the land is quite undulated which posed a serious challenge for the project team to start the basic drilling work. Furthermore, the project engineering team had to make the site layout in such a way that the Module Mounting Structure & the PV modules could Local Manpower: Predominantly, local manpower was used. The team faced lots of hurdles during the initial days to get the necessary permissions from the local bodies and government authorities. Mitigation: Understanding the situation, Team Vikram Solar acted efficiently and initiated a dialogue with all the local bodies & government authorities and subsequently, the persisting issue was mutually resolved. Construction Power & Water: There was dearth of electricity at the construction site and there was no water storage facility in the vicinity. What aggravated the matter was that there was no permission from the Government of Madhya Pradesh for the bore well too. Mitigation: The Team had to use Diesel Generator set for power and water from neighbouring villages to carry on uninterrupted construction work.
4
5 PROJECT USP Three special types of MMS were established, ranging from 00 to 110, for handling the undulating land slope. To tackle the hurdle of land inclination, up to a measure of 110, and the foundation of Module Mounting Structure, a special type of drilling machine (Crawler) was used, which is a first-of-its-kind usage at solar projects in India. The execution and installation time got reduced substantially by using readymade STP (Sewage Treatment Plant) in place of a traditional brick septic tank. Solar PV Modules with binning of 2.5Wp were used, which reduced the mismatch loss. Solar PV Module with 4 bus bars in the DCR category was introduced by Vikram Solar. High quality MMS manufacturing was done by Vikram India, which helped the team maintain the timeline without compromising on quality. In-house PEB design was done which helped the project team adhere to the strict quality guidelines that we follow. CASE STUDIES NTPC Limited Mandsaur, MP 19
6 STEP BY STEP DEVELOPMENT Site preparation Site preparation Structure mounting Array junction box Control room
7 CASE STUDIES NTPC Limited Mandsaur, MP Fencing Control room 21
8 STEP BY STEP DEVELOPMENT Weather monitoring station Switch yard
9 ENVIRONMENTAL BENEFITS Expected Annual Energy Yield million unit. The plant is also expected to reduce CO 2 emissions to the tune of metric tonnes annually. CASE STUDIES NTPC Limited Mandsaur, MP 23
NTPC LIMITED. Bhadla, Rajasthan CASE STUDY
NTPC LIMITED Bhadla, CASE STUDY NTPC LIMITED Bhadla, PROJECT OVERVIEW R Site Co-ordinates 27.5N, 72.0E R Plant capacity 130 MW (2 blocks of 65 MW each) R Connection Type & Connected to Grid connected -
More informationBE PART OF A SUNNY FUTURE WITH INDIA S LEADING SOLAR SOLUTIONS PROVIDER
BE PART OF A SUNNY FUTURE WITH INDIA S LEADING SOLAR SOLUTIONS PROVIDER VIKRAM SOLAR WHO WE ARE Vikram Solar Limited is a globally recognized reliable solar energy solutions provider, specializing in high
More informationWe are pleased to quote our best price for 5 M W Solar Plant as appended. Annexure I : Price Schedule for 5 M W Solar Plant
Dear Sir Greetings to you Subject: Offer for Supply of 5 M W Solar Plant Ref: Add posted on site Dear Sir, Greetings to you We are pleased to quote our best price for 5 M W Solar Plant as appended. Annexure
More informationSolar PV Nominated Technical Persons Criteria
MCS Company Scheme Criteria for: Solar PV Nominated Technical Persons Criteria Current Criteria This document shows the Competence Criteria required to be met by a company undertaking the type of work
More informationBRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE
JUNE 2017 ENVIRONMENTAL IMPACT ASSESSMENT PROCESS CONSTRUCTION OF THE PROPOSED BRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE NORTHERN CAPE BACKGROUND INFORMATION DOCUMENT A commercial
More informationHARTEK POWER PVT LTD SOLAR BUSINESS CATALOGUE (Formerly known as Amtek Energy & Power Pvt Ltd)
(Formerly known as Amtek Energy & Power Pvt Ltd) SOLAR BUSINESS CATALOGUE 2015-16 2 P a g e Contents 1. Introduction 2. Mission SOLAR 3. Why us? 4. Engineering Procurement Construction Services 4.1 Process
More informationTHE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks
THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Issued by: Review Cycle: Asset Management & Regulation, ESB Networks Three years Contents 1.0 Introduction....3 1.1 Definitions...3 1.2 Aim of Planning...5
More information5.5 KW DC PV SYSTEM Optimal Location W Solar PV Panels 60 Cell 250W PV Module
13.5' 36' YOUR LOGO HERE 21.5' 5.5 KW DC PV SYSTEM Optimal Location 22 250W Solar PV Panels Driveway 23' 36" 19' 9" ➋ 13' 2" 36" 36" 36" 6' 6" Array Modules Azimuth Tilt Yield kwh/kw/yr 9.5' 36" ➊ 12 169
More informationContents QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR GREEN JOBS. Introduction Qualifications Pack- Solar PV Site Surveyor
QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR GREEN JOBS Contents 1. Introduction and Contacts....[1] 2. Qualifications Pack....[2] 3. Glossary of Key Terms.[3] 4. OS Units.....[5] OS describe what
More informationAn inverter is the heart of a solar PV installation and it plays a critical role in maximizing energy harvest.
Conext RL PV Inverters: Superior energy harvest and return on PV system investment By Prasad Rao and Ranjeet Kuberkar Abstract An inverter is the heart of a solar PV installation and it plays a critical
More informationBANKABILITY OF SOLAR PROJECTS HOW TO MAKE YOUR PV PROJECT BANKABLE? HOW TO SELECT EPC CONTRATCOR? ROLE OF TECHNLOGY SELECTION
0 HOW TO MAKE YOUR PV PROJECT BANKABLE? HOW TO SELECT EPC CONTRATCOR? ROLE OF TECHNLOGY SELECTION BANKABILITY OF SOLAR PROJECTS www.firstgreen.co IMPACT OF O&M ON BANKABILITY SOLAR RESOURCE ASSESSMENT
More informationCenter for Study of Science, Technology & Policy. ENERGISING DATA-DRIVEN POLICY MAKING AND INVESTMENT IN RENEWABLE POWER: Lessons from India
Center for Study of Science, Technology & Policy ENERGISING DATA-DRIVEN POLICY MAKING AND INVESTMENT IN RENEWABLE POWER: Lessons from India CSTEP: Key Research Areas Energy Renewables, Nuclear Smart Grid,
More informationEXPRESSION OF INTENT FOR 100 MW SOLAR PV PROJECT ON EPC BASIS AT KHARAGHODA
EXPRESSION OF INTENT FOR 100 MW SOLAR PV PROJECT ON EPC BASIS AT KHARAGHODA EOI No. 38(Com)Purchase/2016-17 EOI Issue date 28.12.2016 Last date and time of 19.01.2017 upto 15.00 Hrs at office of Submission
More informationSOLAR. Ground, Rooftop, Water, Space. Think Solar Think BHEL
SOLAR Ground, Rooftop, Water, Space Think Solar Think BHEL About BHEL Established in 1964, Bharat Heavy Electricals Limited is an integrated power plant equipment manufacturer and one of the largest engineering
More informationSURINDER RAINA GM-I/C(RE & Nuclear)
13.02.17 SURINDER RAINA GM-I/C(RE & Nuclear) 1 1 Outline Renewable Energy in India Solar Projects in NTPC -EPC Mode -Developer Mode Wind Projects in NTPC New Initiatives 2 Renewable Energy in India Installed
More informationInvestigating the Shading Impact of Rail on the Energy Output of a PV System in Hong Kong
Investigating the Shading Impact of Rail on the Energy Output of a PV System in Hong Kong Jinqing Peng a, b, Lin Lu b,*, Hongxing Yang b, Tao Ma b, KM HO c, Peter Law c a College of Civil Engineering,
More information7 Project Description
7 Project Description 7.1 Project Promoter The CEB (Green energy) Co. Ltd. is a private company fully owned by the Central Electricity Board incorporated on 11 October 2016 to promote the generation of
More informationFact sheet. Photovoltaic systems. Why consider photovoltaics?
Fact sheet Photovoltaic systems In this Fact sheet: What is a photovoltaic system? Choosing the right system Choosing solar modules Orientation and pitch Maintenance Why consider photovoltaics? Photovoltaic
More informationGlobal Top 10 Trackers for 2016 GTM Research
Global Top 10 Trackers for 2016 GTM Research #1Indian Tracker Technology installed FY 2016-2017 ONLY GLOBAL Tracker Technology Organization with Multiple Solutions WHY TRACK THE SUN? Punjab Pavagada *
More informationHome PV System Design
Home PV System Design Step #1 Evaluate Home Energy Needs (based on 2007 & 2008 PG&E bill) Averaged annual electricity usage is around 4,500kWh Step #2 Determine System Requirements (Grid-tied, Fixed tilt)
More informationSOLAR ENERGY ASSESSMENT REPORT. For 80.5 kwp. Meteorological Data Source NASA-SSE. Date 18 October, Name of Place Uttar Pradesh.
SOLAR ENERGY ASSESSMENT REPORT For 80.5 kwp Name of Place Uttar Pradesh Client abc Capacity 80 kw Meteorological Data Source NASA-SSE Email ezysolare@gmail.com Order No. #1410180006 Date 18 October, 2014
More informationNABCEP PV Technical Sales Job Task Analysis
NABCEP PV Technical Sales Job Task Analysis Introduction This document presents an in-depth Job Task Analysis for solar electric professionals who gather site specific information and analyze customer
More informationDepartment of Electrical Engineering. Industrial Visit Report. Sardar Sarovar Narmada Nigam Limited Hydro Electric Power Station
Department of Electrical Engineering Industrial Visit Report Sardar Sarovar Narmada Nigam Limited Hydro Electric Power Station on 10 th March, 2017 Faculties Accompany: Prof. Anish Vora Prepared by: Prof.
More informationPHOTOVOLTAIC SYSTEMS. Syllabus. 1 Photovoltaic systems
PHOTOVOLTAIC SYSTEMS Syllabus 1 Photovoltaic systems 1 Identify typical photovoltaic (PV) installations a) grid connected b) building integrated c) non-integrated 2 State typical expected outputs of a
More informationAdditional Information on Project Components
Additional Information on Project Components A. Part A: Ashuganj 450 MW Combine Cycle Power Plant 1. Description 1. The proposed project involves retirement of the existing combined cycle power plant (CCPP)
More informationSri: Sustainable Power Sector Support Project
Environmental Monitoring Report June 2015 Sri: Sustainable Power Sector Support Project Prepared by Ceylon Electricity Board for the Asian Development Bank. This environmental monitoring report is a document
More informationM/s.NEERAJ KUMAR JAIN
EXECUTIVE SUMMARY OF DARSHANI LATERITE AND RED OCHRE DEPOSIT Area : 15.00 Ha. Village Budhanwara, Tahsil Bohriband, Dist. Katni MADHYA PRADESH For M/s.NEERAJ KUMAR JAIN KATNI 1 BUDHANWARA LATERITE AND
More informationAN EFFECTIVE STUDY ON PERFORMANCE ANALYSIS OF GRID CONNECTED PV SYSTEM
AN EFFECTIVE STUDY ON PERFORMANCE ANALYSIS OF GRID CONNECTED PV SYSTEM Jignesh L. Rohit 1, Prof. K.D. Panchal 2 1 P.G. Student, M. E. (Energy Engineering), Government Engineering College, Valsad, Gujarat
More informationFrom Rooftops to Farmtops. Augmenting India s Distributed Solar Goals through net-metered solar pumps
From Rooftops to Farmtops Augmenting India s Distributed Solar Goals through net-metered solar pumps Introduction The Government of India has recently announced a scheme for solar water pumps known as
More informationTRAINING PROGRAM ON SOLAR POWER PROJECT DEVELOPMENT
Duration : 5th Oct 2015 to 10th Oct 2015 TRAINING PROGRAM ON SOLAR POWER PROJECT DEVELOPMENT DAY 1 / 05.10.2015 (MONDAY): Welcome speech- and introduction of the training program FIRSTGREEN + MNIT + NISE
More informationModel Curriculum. Solar PV Maintenance Technician - Civil (Ground Mount) GREEN JOBS RENEWABLE ENERGY Operation & Maintenance SGJ/Q0116, V1.
Model Curriculum Solar PV Maintenance Technician - Civil (Ground Mount) SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: GREEN JOBS RENEWABLE ENERGY Operation & Maintenance SGJ/Q0116, V1.0 4 1 TABLE
More informationINDIAN INSTITUTE OF TROPICAL METEOROLOGY
INDIAN INSTITUTE OF TROPICAL METEOROLOGY (An Autonomous Body under the Ministry of Earth Sciences,Govt. of india) Dr. Homi Bhabha Road, Pashan, Pune-411008 IITM/EM/ SOLAR NOTICE FOR EXPRESSION OF INTEREST
More informationLECTURE 15 PHOTOVOLTAIC MATERIALS. ECE 371 Sustainable Energy Systems
LECTURE 15 PHOTOVOLTAIC MATERIALS ECE 371 Sustainable Energy Systems 1 SHADING IMPACTS ON I-V CURVE The output of the PV cell is reduced significantly when even a small portion of it is shaded Even a single
More informationFinancial Benefits of Integrating East West Fixed, Single and Dual Axes Tracking PV Systems in the Supply Mix of a South African Research Campus
Financial Benefits of Integrating East West Fixed, Single and Dual Axes Tracking PV Systems in the Supply Mix of a South African Research Campus (Conference ID: CFP/871/2018) Henerica Tazvinga*, Enose
More information1 Project description
1 Project description Akfen Renewables (the "Company") is currently developing a portfolio of (PV) power plants located in the provinces of Konya, Amasya, Tokat, Van and Malatya provinces in Turkey. This
More informationTable 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others
1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines
More informationShed Nos: 38 & 39, Plot Nos: 26 & 27, Phase: II, Industrial Development Area, Cherlapally, Hyderabad Telangana
COMPANY PROFILE An ISO 9001 : 2008 Company Shed Nos: 38 & 39, Plot Nos: 26 & 27, Phase: II, Industrial Development Area, Cherlapally, Hyderabad - 500 051. Telangana Tele : +91 40 2970 7726 Mail ID : srtind.2008@gmail.com
More informationMegawatt Solutions Private Limited
Megawatt Solutions Private Limited Contact us T-93, 4 th Floor, Gautam Nagar, Yousuf Sarai Commercial Complex, New Delhi-110049 smalik@megawattsolutions.in, Tel: 011-40536349 Indigenous High-Efficiency
More informationMonroe County s Path to Solar Energy: Western New York s Largest Municipal Solar Installation
Monroe County s Path to Solar Energy: Western New York s Largest Municipal Solar Installation April 24, 2018 Michelle Virts, MCDES Nathan Rizzo, Solar Liberty Monroe County 13 MW 13 MW 45,000 Solar Modules
More informationAnnex B2.3. Background Information Document
Annex B2.3 Background Information Document Background Goldfields South Deep Mine, in partnership with Enel Green Power, proposes to design, construct, and operate 2x20MW Solar PV plants on Mine owned property
More informationFEASIBILITY REPORT FOR ROUTE SELECTION OF 132 KV DOUBLE CIRCUIT TRANSMISSION LINE
FEASIBILITY REPORT FOR ROUTE SELECTION OF 132 KV DOUBLE CIRCUIT TRANSMISSION LINE FOR PROPOSED 126 MW WIND POWER PROJECT OF WELSPUN RENEWABLES ENERGY PVT.LTD IN DISTRICT PRATAPGARH, RAJASTHAN TABLE OF
More informationRESULTS A)Without any area B) Within restricted
SL. No. Vineeti Technologies Customer Name Project report version V-00 Hourly power demand (Watt.hr) Value 1 Date 04-04-2017 Peak demand (W) 200000 Average demand/hr in _morning 2 Site Location Mysore
More informationGuidelines for Solar Photovoltaic Installation
WEST COVINA FIRE DEPARTMENT Fire Prevention Bureau 1435 W. Puente Ave. West Covina, CA 91790 (626) 338-8800 Guidelines for Solar Photovoltaic Installation PURPOSE SCOPE TABLE OF CONTENTS..2..2 REQUIREMENTS..2
More informationMAXIMIZING. Making Use of Existing Roofs
MESSAGE MAXIMIZING Solar Power Generation Making Use of Existing Roofs In this article, Satish N Diwakar outlines various aspects of solar photovoltaic (SPV) systems on rooftops, including evaluation of
More informationBuilding Solar Friendly Roofs
Building Solar Friendly Roofs Presented by John Maissan Leading Edge Projects Inc. Yukon Housing Corporation Contractor Breakfast April 15, 2015 Presentation Outline Why solar Sun angles by time of day
More informationGuideline for Fire Safety. Elements of Solar. Photovoltaic Systems
Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 This document was developed by the Orange County Fire Chiefs Association, Orange County Fire Marshal Committee. It is based
More informationAvailable online at ScienceDirect. Procedia Technology 24 (2016 ) Tahira Bano a,*, K.V.S. Rao a
Available online at www.sciencedirect.com ScienceDirect Procedia Technology 24 (2016 ) 505 512 International Conference on Emerging Trends in Engineering, Science and Technology (ICETEST - 2015) Levelized
More informationBURBANK FIRE DEPARTMENT 311 East Orange Grove Avenue, Burbank CA Fax
BURBANK FIRE DEPARTMENT 311 East Orange Grove Avenue, Burbank CA 91502 818 238 3473 Fax 818 238 3479 SOLAR PHOTOVOLTAIC INSTALLATION GUIDELINES BASED ON THE CSFM PV GUIDELINES (REVISED APRIL 2017) The
More informationOutline Construction and Environmental Management Plan
1.1.1 Gwent Farmers Community Solar Scheme January 2018 Outline Construction and Environmental Management Plan www.savills.co.uk Project: Client: Gwent Levels Community Solar Scheme Partnership Ltd Job
More informationMOUNTING SYSTEMS PRODUCT CATALOG
MOUNTING SYSTEMS PRODUCT CATALOG MOUNTING SYSTEMS Reliable solar modules support Mounting systems, as solar modules supporting equipment, represent an important part of the final solar solution. Integrated,
More informationNEONERGY ENGINEERING PVT LTD
SOLAR HYDRO TRANSMISSION LINES BALANCE OF PLANT NEONERGY ENGINEERING PVT LTD Authorized dealer for ZYTECH Solar Modules Bengaluru, Karnataka 560 066 sales@neonergy.co www.neonergy.co +91 80952 41041 Ver
More informationKINGSTON SOLAR LP. Sol-Luce Project Overview. August 13, 2014
KINGSTON SOLAR LP Sol-Luce Project Overview August 13, 2014 PROJECT HIGHLIGHTS Facility to be located on approximately 800 acres of land bridging the City of Kingston and Loyalist Township Comprised of
More informationSubtask 1: Economic of PV System Performance and Reliability
TASK 13: PERFORMANCE AND RELIABILITY OF PV SYSTEMS Subtask 1: Economic of PV System Performance and Reliability Mauricio Richter (3E), Jan Vedde (SiCon) Mike Green (M.G.Lightning Electrical Engineering)
More informationVersion 05.1 Page 1 of 16
CDM-MR-FORM Monitoring report form (Version 05.1) MONITORING REPORT Title of the project activity 15 MW Solar Photovoltaic Power Project at Gujarat UNFCCC reference number of the project activity 8671
More informationASSESSMENT AND DESIGN OF ROOFTOP SOLAR PV SYSTEM. Click to begin
ASSESSMENT AND DESIGN OF ROOFTOP SOLAR PV SYSTEM Click to begin TOPICS Solar Energy Systems Types of solar energy systems Solar Energy Terminologies Solar PV system Types of Solar PV systems Solar PV System
More informationRykove Solar Project Non-Technical Summary
Rykove Solar Project Non-Technical Summary 16 July 2018 1 Introduction This document provides a non-technical overview of the proposed development plans of private company Grin Agro Servis to construct
More informationSource: Ministry of New & Renewable Energy (MNRE)
NATURAL POWER Durja Energy is a business unit of renewable energy systems which deals in Solar Products used in various high-growth segments such as Infrastructure, Retail, IT, ITES, Hospitality, Healthcare
More informationModel Curriculum. Solar PV Designer SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: GREEN JOBS RENEWABLE ENERGY Designer SGJ/Q0110, V1.
Model Curriculum Solar PV Designer SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: GREEN JOBS RENEWABLE ENERGY Designer SGJ/Q0110, V1.0 7 Solar PV Designer Solar PV Designer 2 TABLE OF CONTENTS 1.
More informationGreenCo BANGALORE INTERNATIONAL AIRPORT LIMITED, BENGALURU
GreenCo Experience @ BANGALORE INTERNATIONAL AIRPORT LIMITED, BENGALURU ABOUT BIAL Public limited company under Indian Companies Act Private Public Partnership BOOT project transferred after 60 years (30
More informationCustomer Sited Solar PV & The Impact of Grid Interactive Systems
Customer Sited Solar PV & The Impact of Grid Interactive Systems Solar Photovoltaic Anguilla bathed in power every day 6 KWh per sq. meter per day (6 full sun hours) Sun comes out every day Anguilla has
More informationImpact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc.
Impact of Variable Generation on the Vermont Transmission Grid Chris Root Vermont Electric Power Company, Inc. croot@velco.com VELCO-managed assets 738 miles of transmission lines, 115kV to 450kV, predominantly
More informationSuburbia 1, Kyoto 0. Why Canadians must link home to environment to achieve Canada s Kyoto targets. by Louise St.Germain
Suburbia 1, Kyoto 0 Why Canadians must link home to environment to achieve Canada s Kyoto targets by Louise St.Germain In recent years, much awareness has been raised around the world about climate change
More informationTraining: MED-SOLAR MODULE :4. Constructing and Starting-up Of a Solar Power Plant
Training: MED-SOLAR MODULE :4 Constructing and Starting-up Of a Solar Power Plant By: Ramzi AbouSaid Managing Director of ASACO General Trade and Contracting www.asacogtc.com President of the Lebanese
More informationOPERATIONAL ISSUES AND INNOVATIVE APPROACH FOR PERFORMANCE IMPROVEMENT AT NTPC UNCHAHAR SOLAR PV PLANT
OPERATIONAL ISSUES AND INNOVATIVE APPROACH FOR PERFORMANCE IMPROVEMENT AT NTPC UNCHAHAR SOLAR PV PLANT Ravi Prakash Singh AGM (O&M Opn. & Commg.) NTPC Unchahar Amit K Gautam Sr. Manager (O&M Opn. & Commg.)
More informationMonitoring of 20 kwp photovoltaic system
Monitoring of 20 kwp photovoltaic system Milan Belik ABSTRACT The document describes influence of basic meteorological value to proposition of photovoltaic arrays. Results from 3 years long measurements
More informationESD 28 th Annual Solid Waste Technical Conference
Revenue Stream from Solar Photovoltaic Systems at Landfill Sites ESD 28 th Annual Solid Waste Technical Conference Lansing, Michigan April 11, 2018 ABOUT NOVA A Minority owned company, established in 1992
More informationSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National Highways Anurag Swain Sr. Deputy General Manager (Electrical & Instrumentation), My Home Power Consultancy Services Pvt. Ltd My Home Hub, 3 rd Block, 5 th
More informationSolar Energy System of the Month: Zero-energy house with photovoltaics and heat pump
1 von 5 06.02.2009 11:07 German Solar Energy System of the Month Print this page Banner Advertising Bulletin Board Events Solar Magazine Funding for Solar Energy Companies Solarstore (G) Non-Profit Organizations
More informationPHOTON ENERGY SYSTEMS LIMITED. Solar Energy for today & tomorrow
PHOTON ENERGY SYSTEMS LIMITED Solar Energy for today & tomorrow COMPANY VISION to be an innovative and competitive global enterprise providing end-toend solar energy solutions to customers COMPANY DIVISIONS
More informationRef. No.: SRMU/NDP-I/VBMPS-II/ INVITATION FOR QUOTATION FOR SUPPLY OF GOODS UNDER SHOPPING PROCEDURES
Ref. No.: SRMU/NDP-I/VBMPS-II/ dt.22.09.2017 To INVITATION FOR QUOTATION FOR SUPPLY OF GOODS UNDER SHOPPING PROCEDURES P Dear Sir, Sub : INVITATION FOR QUOTATIONS FOR SUPPLY OF Rooftop Solar PV system
More informationSolar Powered Irrigation Pumps: Opportunities and Challenges for India
Solar Powered Irrigation Pumps: Opportunities and Challenges for India NILANJAN GHOSE 11 October 2017 Page 1 Presentation Outline Understanding Solar Powered Irrigation Pump (SPIP) :as a technology Market
More informationModule 13 Assignment. Integrating Landscape and Buildings. For one of the projects listed below, describe the methods used by the designers
1 Module 13 Assignment Integrating Landscape and Buildings For one of the projects listed below, describe the methods used by the designers (planners, construction managers) to achieve integration of human
More informationSolar PV, Wind, and Storage System Design. Ilya Chernyakhovskiy, NREL April 26, 2018 Dushanbe, Tajikistan
Solar PV, Wind, and Storage System Design Ilya Chernyakhovskiy, NREL April 26, 2018 Dushanbe, Tajikistan Design Consideration 1: Technology Generation 1 Megawatt installed PV capacity powers ~160 homes
More informationSolar (PV) Panel Installation and Maintenance With The Help Of PVSYST And PVSOL
Solar (PV) Panel Installation and Maintenance With The Help Of PVSYST And PVSOL Training Objective: This training program is designed for new Entrepreneurs, Prospective Entrepreneurs, working Professional
More informationThe Energy Supply and Purchase Agreement (ESPA) was signed between Solar Energy Ltd and the Central Electricity Board on 28 November 2014.
EXECUTIVE SUMMARY E1 Introduction The proponent is SOLAR FIELD LTD, a consortium between 1. Dhamma Energy, a company based in Spain, specialised in photovoltaic projects 2. Harel Mallac & Co. Ltd, a company
More informationPHOTON ENERGY SYSTEMS LIMITED SYSTEM INTEGRATION & EPC PROFILE
PHOTON ENERGY SYSTEMS LIMITED SYSTEM INTEGRATION & EPC PROFILE COMPANY VISION to be an innovative and competitive global enterprise providing end-toend solar energy solutions to customers COMPANY DIVISIONS
More informationMorgan County Planning Commission. Petition for: Text Amendment. Article 7, Regulations for Specific Uses
Staff Report Morgan County Planning Commission Petition for: Text Amendment Applicant: Applicant s Agent: Zoning Ordinance: Morgan County Zoning Ordinance Article 7, Regulations for Specific Uses Summary
More information5. Solar Photovoltaic System
5. Solar Photovoltaic System 5.1 Introduction Harnessing of non polluting renewable energy resources to control green house gases is receiving impetus from the government of India. Under the JNNSM, rooftop
More informationLEED, Alternative building Materials, Alternative Energy. Yossi Bronsnick 10/8/2015
LEED, Alternative building Materials, Alternative Energy Yossi Bronsnick 10/8/2015 Outline Taitem Engineering Sustainability & USGBC/LEED Alternative Energy Alternative Building Materials Taitem Engineering
More informationOWN YOUR SUN. Ashu Gupta Vice President - Corporate Ujaas Energy Limited
OWN YOUR SUN Ashu Gupta Vice President - Corporate Ujaas Energy Limited A Presentation on Success Stories on investments in Renewable Energy Sector in Uttar Pradesh & Uttrakhand SOLAR POWER A Greener,
More informationContents. What is a solar water pump? 3-4. Smart Solar Water 5-6. Small Centrifugal Pump Systems 7. MPPT Diaphragm Pump Systems 8
Solar Water Systems Contents Pages What is a solar water pump? 3-4 Smart Solar Water 5-6 Small Centrifugal Pump Systems 7 MPPT Diaphragm Pump Systems 8 Large Centrifugal Pump Systems 9 Pump Price List
More informationSOLAR SOLUTIONS PROVIDER
YOUR LEADING SOLAR SOLUTIONS PROVIDER SOLAR MODULES SOLAR EPC 1GW ANNUAL MODULE PRODUCTION CAPACITY SOLAR ROOFTOP THE VIKRAM GROUP With a legacy of over 4 decades VIKRAM SOLAR Renewable Energy India s
More informationDesign Guide for Solar Water Pumping. Dankoff Solar Products, Inc.
Special advance-publication for the Advanced PV Course Solar Energy International May 2001 Design Guide for Solar Water Pumping Dankoff Solar Products, Inc. The world s most diverse selection of solar
More information6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs
Project: Sorang Hydro Electric Project - 100 MW Overview: M/s.Himachal Sorang Pvt.Ltd., Hyderabad, is developing the Run of the River Sorang Hydro Electric Project (100MW) in Kinnaur District of Himachal
More informationNew York Community Solar Facility Decommissioning Plan
New York Community Solar Facility Decommissioning Plan July 2017 Prepared For: Town of Dryden, NY Delaware River Solar 33 Irving Place, Suite 1090 New York, NY 10003 Table of Contents Page 1. Introduction
More informationGroundwater resources at risk in the basalts (Deccan traps) of western India
Future Groundwater Resources at Risk (Proceedings of the Helsinki Conference, June 1994). IAHSPubl.no. 222, 1994. 513 Groundwater resources at risk in the basalts (Deccan traps) of western India S. D.
More informationEMBRACE THE INFINITE POWER OF THE SUN WITH PV MODULES BY VIKRAM SOLAR 1GW ANNUAL MODULE PRODUCTION CAPACITY
EMBRACE THE INFINITE POWER OF THE SUN WITH PV MODULES BY VIKRAM SOLAR 1GW ANNUAL MODULE PRODUCTION CAPACITY WHO WE ARE Vikram Solar is a globally recognised reliable solar energy solutions provider, specialising
More informationEMBRACE THE INFINITE POWER OF THE SUN WITH PV MODULES BY VIKRAM SOLAR 1GW ANNUAL MODULE PRODUCTION CAPACITY
EMBRACE THE INFINITE POWER OF THE SUN WITH PV MODULES BY VIKRAM SOLAR 1GW ANNUAL MODULE PRODUCTION CAPACITY WHO WE ARE Vikram Solar is a globally recognised reliable solar energy solutions provider, specialising
More informationCritical Load Serving Capability by Microgrid using 100% Renewable Energy
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Critical Load Serving Capability by Microgrid using 100% Renewable Energy P. PENKEY,
More informationBOLAND ENVIRONMENTAL CONSULTANTS CC
BOLAND ENVIRONMENTAL CONSULTANTS CC y ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Proposed Photo-Voltaic Solar Power Plant On Farm Nuwerus, No. 450 Portion 6, Worcester DEA REF. NO: 12/12/20/2019 BACKGROUND
More informationQUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR GREEN JOBS SUB-SECTOR: RENEWABLE ENERGY OCCUPATION: DESIGNER REFERENCE ID: SGJ/Q0109
Insert SSC logo height 0.51, width 2.84 QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR GREEN JOBS Contents 1. Introduction and Contacts.......[1] 2. Qualifications Pack....[2] 3. Glossary of Key Terms....[3]
More informationFloating Solar PV Technology An Introduction
Floating Solar PV Technology An Introduction Floating Solar Technology Market Outlook The Global Floating Solar Panels Market is expected to reach US$ 842.0 Million by 2023, expanding at a CAGR (Compound
More informationContents. What is a solar water pump? 3-4. Smart Solar Water 5-6. Small Centrifugal Pump Systems 7. MPPT Diaphragm Pump Systems 8
Solar Water Systems Contents Pages What is a solar water pump? 3-4 Smart Solar Water 5-6 Small Centrifugal Pump Systems 7 MPPT Diaphragm Pump Systems 8 Large Centrifugal Pump Systems 9 Pump Price List
More informationNow we come to an important power electronic device that makes the modern PV system widely usable.
ET3034TUx - 7.4 - Inverters in PV systems Welcome back. Now we come to an important power electronic device that makes the modern PV system widely usable. I am talking about the solar inverter. To know
More informationSUCCESSFUL SOLAR POWER BUSINESS The Power and Renewable Energy Seminar 2016 Hosted by the Indonesian Gas Society
SUCCESSFUL SOLAR POWER BUSINESS The Power and Renewable Energy Seminar 2016 Hosted by the Indonesian Gas Society Jakarta 8 December 2016 www.canadiansolar.com Canadian Solar Corporate Overview Founded
More informationGrid-connected photovoltaic module and array sizing based on an iterative approach
International Journal of Smart Grid and Clean nergy Grid-connected photovoltaic module and array sizing based on an iterative approach F. Q. Alenezi *, J. K. Sykulski, M. Rotaru a lectronics and Computer
More informationNiagara Generation Modeling. David Edelson Market Issues Working Group January 22 th, 2016
Niagara Generation Modeling David Edelson Market Issues Working Group January 22 th, 2016 Purpose The purpose of this presentation is to begin a discussion with Market Participants on the modeling of the
More informationPV Powered DC System for Protection Control and Monitoring (PCM) in Sub-Stations
PV Powered DC System for Protection Control and Monitoring (PCM) in Sub-Stations Avneesh Kumar 1, Jai Dev Sharma 2 1,2 M. Tech Student, Centre of Energy Studies, Indian Institute of Technology Delhi (India)
More informationPreliminary Design Review MARS-OZ PIGLET MARSYSTEMS i MARSYSTEMS
Preliminary Design Review MARS-OZ PIGLET MARSYSTEMS 2015 i MARSYSTEMS EXECUTIVE SUMMARY The MarsOz Piglet is an analogue research station to be located in Arkaroola, South Australia for Mars Society Australia.
More informationModel Curriculum. Solar PV Structural Design Engineer SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL:
Model Curriculum Solar PV Structural Design Engineer SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: GREEN JOBS RENEWABLE ENERGY Designer SGJ/Q0109, V1.0 5 Solar PV Structural Design Engineer Solar
More information