The following set of activities associated with the project has been taken into account for the Environmental Impact Analysis:

Size: px
Start display at page:

Download "The following set of activities associated with the project has been taken into account for the Environmental Impact Analysis:"

Transcription

1 6.0 Predicted Environmental Impacts and Mitigation Measures 6.1 Stages and Impacts Considered An Environmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health and safety aspects and their respective impacts associated with construction, transport, operation and decommissioning of the wind farm have been considered. The following impact categories were analyzed for the proposed wind farm: Environmental Aspects a. Noise and Dust Generation b. Change in Land Use and Visual Impacts c. Freshwater consumption d. Ecology e. Solid Waste Generation (Construction wastes and scrap metals) f. Air pollution g. Used oil and lubricants h. Spillage of small amounts of hazardous/toxic materials i. Reduction in GHG emissions Socio Economic Aspects a. Employment Opportunities b. Birds mortality c. Congestion on roads d. Non Ionizing Radiation and Electromagnetic Interference Health and Safety Aspects a. Injuries to workers b. Risk of road accidents The following set of activities associated with the project has been taken into account for the Environmental Impact Analysis: Construction The construction phase relates mainly to onsite erection of the wind turbines and assembling of the associated facilities; Transport The transport phase includes transport of the WTG components from the port (Port Louis) to the wind farm site (Plaine Sophie); Sustainable Resource Management Ltd Page 31

2 transport within the wind farm site (Plaine Sophie) during construction, operation and decommissioning of the wind farm; transport from the wind farm site (Plaine Sophie) to the final disposal site during decommissioning of the wind farm. Operation The operation phase is related to the maintenance of the turbines, including oil changes, lubrication and transport for maintenance (usually by trucks), Decommissioning Decommissioning of the wind farm will be done after 20 years. The turbines will be dismantled and transported (by truck) from Plaine Sophie to Mare Chicose landfill. Toxic materials like lubricating oil, hydraulic fluids and insulating fluid will be sent for recycling and/or reuse. 6.2 Outcome of the Environment Impact Analysis The outcome of this exercise is presented in Table 6.1. Environmental, Socio Economic and Safety aspects related to each activity (Construction, Transport, Operation and Decommissioning) and their respective impacts have been determined. Each impact has been categorized according to its level of significance. Mitigation measures associated to these impacts are discussed correspondingly. The impacts of the proposed wind farm project at Plaine Sophie both during the construction and operation phases are summarized in Figure 6.1 and Figure 6.2. ~ 10 m 3 /day Concrete 200 kwh/day Electricity 25.5 m 3 /day Water 100 Jobs Construction Phase 14 Wind Turbine Generators 1,000 kg/day Construction Waste 90 kg/day Domestic Waste 20 Trips/day Figure 6.1: Impacts during Construction Phase of Proposed Wind Farm Sustainable Resource Management Ltd Page 32

3 140 MWh/day Electricity 3.2 m 3 /day Water 25 Jobs Operational Phase 20 kg/day Domestic Waste < 45 db(a) Noise to neighborhood Moderate to Low Visual Impact Figure 6.2: Impacts during Operation Phase of Proposed Wind Farm Sustainable Resource Management Ltd Page 33

4 Stage Type (E, SE, S) N/P Severity Likelihood Significance Table 6.1 Environmental, Socio Economic and Safety Aspects and Impacts Activity Aspect Impact Level of Significance Manpower requirement Unloading of the WTG components from trucks and operation of heavy machinery including cranes and concrete pumps onsite Sanitary and potable water usage, and construction of wind turbine foundation Creation of employment Injuries to workers Freshwater consumption SE P S N E N Harmful but Mild effect, easily 1 Construction Excavation and construction of wind turbine foundations, construction of stainless steel huts for installation of transformer, switchgear and power condition devices; laying of overhead distribution cables for connecting to nearby high voltage substation Use of equipment such as crane lorry, hand-held breaker, concrete lorry mixer and vibratory poker Removal of fittings of the WTGs from packaging Construction waste Ecology Energy consumption Change in land use visual effects Noise and dust generation Solid waste generation Solid waste generation E, SE N E P SE N SE, S N E N E N Mild effect, easily Harmful but Harmful but Harmful but Harmful but Harmful but Sustainable Resource Management Ltd Page 34

5 Stages Type (E, SE, S) N/P Severity Likelihood Significance Table 6.1 (Continued) Environmental, Socio Economic and Safety Aspects and Impacts Activity Aspect Impact Level of Significance 2 Transport Vehicles used to transport the WTG components from the port (Port Louis) to the wind farm site (Plaine Sophie) Vehicles used onsite for daily inspection of operation of the wind turbines Vehicles used onsite for maintenance of the wind turbines Risk of road accidents SE N Congestion SE N Air pollution leading to global warming and increase in carbon footprint Air pollution leading to global warming and increase in carbon footprint Air pollution leading to global warming and increase in carbon footprint E N E N E N Mild effect, easily Mild effect, easily Mild effect, easily Harmful but Harmful but Sustainable Resource Management Ltd Page 35

6 Stages Type (E, SE, S) N/P Severity Likelihood Significance Table 6.1 (Continued) Environmental, Socio Economic and Safety Aspects and Impacts Activity Aspect Impact Level of Significance Maintenance of the turbines Used oil and lubricants E N Spillage of small amounts of hazardous /toxic materials E N Harmful but Harmful but Visibility of wind turbines Landscape and visual impact SE, E N Harmful but 3 Operation Generation of electricity from the 14 wind turbines Movement of rotor blades of the WTGs Tower, rotor blades and generation of the WTGs Shadows of the rotating blades of the wind turbines Reduction in GHG emissions E P Creation of employment SE P Noise generation Impact on birds Non ionizing radiation and electromagnetic interference SE, E SE, E SE, E N N N Risk of road accidents E N Harmful but Relatively harmless Relatively harmless Relatively harmless Sustainable Resource Management Ltd Page 36

7 Stages Type (E, SE, S) N/P Severity Likelihood Significance Table 6.1 (Continued) Environmental, Socio Economic and Safety Aspects and Impacts Activity Aspect Impact Level of Significance 4 Decommissioning Dismantling of wind turbines Scrap metals SE N Used oil E N Relatively harmless Harmful but Vehicles to transport the metal scraps and used oil to recycling facilities and, the rest of the components to Mare Chicose landfill GHG emission E N Harmful but Sustainable Resource Management Ltd Page 37

8 Severity to 25 Requires immediate action to 20 Harmful but to 9 Mild Effect, easily to 4 Relatively harmless Likelihood Severity Likelihood 1 No Impact 1 Very Improbable 2 Negligible Impact 2 Not Probable 3 Considerable Impact 3 Rarely Occurring 4 Great Impact 4 From Time to Time 5 Very Great Impact 5 Fairly Regularly E- Environmental Impact N- Negative Impact S- Safety Impact P- Positive Impact SE- Socio Economic Impact Sustainable Resource Management Ltd Page 38

9 The aspects and associated impacts are classified according to the relevant activities followed by the associated level of significance (see Table 6.1) Aspects, Impacts and Mitigation Measures related to Construction Activities Creation of Employment during Construction. Level of significance: Nil Activity: Construction Aspect: Manpower Positive Socio Economic Impact: Creation of employment The La Marie region has some 28,480 inhabitants and the proposed project will create around 100 part time jobs during the construction phase. Therefore, the surrounding neighborhoods will be benefited by creation of employment. No special mitigation measures will be required for the positive impact during the construction phase Injuries to Workers Level of significance: 16 (Harmful but ) Activity: Construction Aspect: Unloading of WTG components from trucks to the wind farm site, and operation of heavy machinery including cranes and concrete pumps Negative Safety Impact: Injuries to workers during the handling of components of the WTGs, operation of heavy machinery including cranes and concrete pumps Falls represent one of the major risks associated with installation of the wind turbines. Providing appropriate Personal Protective Equipments (PPEs) to workers Safety precautions will be taken by the workers during unloading and other processes. To avoid injuries to the workers, appropriate PPEs like safety shoes, safety helmet and Sustainable Resource Management Ltd Page 39

10 gloves will be provided to all workers onsite. A health and safety officer will ensure that all site operations are safe according to the Occupational Safety and Health Act, which recommends the use of engineering or work practice controls to manage or eliminate hazards to the greatest extent possible. Workers working in towers can use the ladder system, along with a full body harness and lanyard, as a means of fall protection. Work on the nacelle will involve installation of electrical control units, which requires cables to be installed through the length of the tower. The nacelle in itself will be spacious and will have anti-skid surfaces to allow quick access to safety rails and fire extinguisher. The long bended crane rail system inside the nacelle makes handling of parts safe and convenient. Finally, extra precaution has been taken with the hinged door system and more strategic eye placements for tie-off Freshwater Consumption during Construction Level of significance: 9 (Mild effect, easily ) Activity: Construction Aspect: Water used by workers. Negative Environmental Impact: Freshwater consumption Water will be required for cleaning and drinking purposes by the workers, and construction of wind turbine foundation All practical measures will be taken to avoid wastage of freshwater onsite like sensitization on proper usage of water onsite and repairing of any leakages. The amount of water used will be approximately 21 m 3 for sanitary and potable water use and 4.5 m 3 for concrete mixing on a daily basis Negative Impact on Ecology Level of significance: 9 (Mild effect, easily ) Activity: Construction Aspect: Excavation and construction of wind turbine foundations, construction of stainless steel huts for installation of transformer, switchgear and power condition Sustainable Resource Management Ltd Page 40

11 devices; laying of overhead distribution cables for connecting to nearby high voltage substation Negative Socio Economic and Environmental Impact: Ecology The proposed project involves excavation and construction of the wind turbine foundation, construction of stainless steel huts for installation of transformer, switchgear and power condition devices and laying of overhead distribution cables for connecting to the nearby high voltage substation. The potentially negative ecological impacts that may arise from the construction phase include: 41,000 m 2 of forest cleared for construction activities of the wind farm accounting for 9% of total area leased resulting in direct forest loss and forest fragmentation; Loss of foraging and feeding ground of the associated wildlife; Direct and indirect impacts to watercourses, including deterioration of water quality, sedimentation effect, as a result of construction activities and discharge. Increased human activities and disturbance due to the project during construction may affect the surrounding natural habitats and the associated wildlife like the monkeys. The area is poor in fauna and flora, the impact on ecology of the site will be extremely low as per the terrestrial fauna and flora survey carried out (see Annex 11). Construction activities will be carried out over a short period (18 months) compared to the 20 year lifetime of the project and as such, construction activities do not warrant any special mitigation measure apart from standard best practice construction. Out of the area deforested, 7,350 m 2 will be restored with endemic and native species. It is to be noted that there are no animal species of conservation importance reported onsite and the impacts will only be temporary. The monkeys, which cause damage to the vegetable plantations, will return back when the construction phase is completed. Alien species present might temporarily leave the area, but will return once the human activities cease. Precautions will be taken not to affect watercourses by proper disposal of wastes generated onsite. Sustainable Resource Management Ltd Page 41

12 Electricity Use during Construction Level of significance: 12 (Harmful but ) Activity: Construction Aspect: Excavation and construction of wind turbine foundations, construction of stainless steel huts for installation of transformer, switchgear and power condition devices; laying of overhead distribution cables for connecting to nearby high voltage substation Negative Environmental Impact: Energy consumption 20 kva of electrical power will be drawn from CEB for electrical powering equipment, which is expected to work 10 hours daily, as required during construction phase. Use of electricity during the construction phase is unavoidable. The use of electricity does not require any special mitigation measure as there is no power shortage in Mauritius Change in Land Use and Visual Effects Level of significance: 15 (Harmful but ) Activity: Construction Aspect: Construction of wind turbine foundations, construction of stainless steel huts for installation of transformer, switchgear and power condition devices; laying of overhead distribution cables for connecting to nearby high voltage substation Negative Socio Economic Impact: Change in Land Use and Visual effect 9% of the total area for the proposed project will be deforested during the construction phase. In partial absence of the trees, erection of the wind turbine generators and their respective electric wires and poles will be more visible to Les Mares Road users, from the picnic point and from Mare aux Vacoas Reservoir. Wastes generated onsite may be an eyesore if not properly disposed. Thus, mitigation measures will be needed to reduce visual impact during construction. Sustainable Resource Management Ltd Page 42

13 Emphasis will be laid upon forest conservation during the construction phase where 8,750 m 2 of the forest will be cleared for the 14 wind turbines, each requiring an area of 25 m x 25 m. Upon completion, part of the forest affected by construction works would be re-afforested, that is 7,350 m 2, as each WTG will be occupying a space of only 10 m x 10 m. Hence, the wind farm will have a foot print representing only 0.3% of the total area leased for the project. Eyesores onsite will be minimized by proper housekeeping measures. Wastes generated will be properly disposed of. Thus the impact on the aesthetic view of the site will be reduced Noise and Dust Generation during Construction Level of significance: 20 (Harmful but ) Activity: Construction Aspect: Use of equipment such as crane lorry, hand-held breaker, concrete lorry mixer and vibratory poker Negative Socio Economic and Environmental Impacts: Noise and dust generation The main construction activities associated with the project that may cause noise and dust generation to the nearby areas include: Site preparation - excavation by cutting and filling to form a site platform and construction of concrete footing (2.5 m) for wind turbine foundations; Erection of wind turbines Noise generated during construction shall be within neighborhood noise limits of 60 db(a)l eq from 07:00 to 18:00, 55 db(a)l eq from 18:00 to 21:00 and 45 db(a)l eq from 21:00 to 07:00, as per Environmental Standards for Noise (Amendment) Regulations To minimize the construction noise impact on nearby areas, good site practices and noise management will be adopted as follows: Sustainable Resource Management Ltd Page 43

14 Only well-maintained plant and machinery will be operated on-site and all equipment will be serviced regularly during the construction works; Machines will be used only during normal working hours and never at night; Sound proofing of noisy plant and equipment (such as concrete pumps) will be carried out as far as practical. Noisy plant and equipment required during construction will not interfere with residential areas as the site is situated in a non residential area Solid Waste Generated during Construction Level of significance: 12 (Harmful but ) Activity: Construction Aspect: Removal of fittings of the WTGs from packaging and remaining construction materials Negative Environmental Impact: Solid Waste Generation (packaging and construction waste) It is expected that the construction works will give rise to solid waste production, that is around 1000 kg of construction waste and 90 kg of domestic waste on a daily basis, which unless mitigated can become an environmental nuisance. The quantity of waste materials arising from the construction phase is not expected to be high as most of the construction waste will be used as backfill. All practical measures will be taken to avoid, minimize and recycle wastes. Designated containers for the disposal of solid waste (wooden crates from unpacking of wind farm components) will be provided onsite and these would be sent to Mare Chicose landfill by a licensed waste carrier. A separate area will be designated for storage and monitoring of toxic wastes, like used oil. They will be collected in drums before disposal. Sustainable Resource Management Ltd Page 44

15 6.2.2 Aspects, Impacts and Mitigation Measures related to Transportation Risk of road Accidents and Congestion during Transportation Level of significance: 9 (Mild effect, easily ) Activity: Transport Aspect: Vehicles used to transport the WTGs components from the port (Port Louis) to the wind farm site (Plaine Sophie) Negative Socio Economic Impacts: Risk of Road Accidents and Congestion Large trucks will be used to transport the components of the WTGs. Road accidents and congestions are likely to occur if precautions are not taken by drivers. Drivers will be advised to drive safely when transporting the components of the wind turbine generators and they will be also assisted by police escorts who will be guiding them. Hence, risk of road accidents and congestion will be minimal Air Pollution arising from Transport Vehicles Level of significance: 12 (Harmful but ) Activity: Transport Aspects: Vehicles used to transport WTG components from the port (Port Louis) to the wind farm site (Plaine Sophie); vehicles used onsite for daily inspection of operation of the wind turbines; vehicles used onsite for maintenance of the wind turbines Negative Environmental Impact: Air pollution leading to global warming and increase in carbon footprint Vehicles for transportation will be required during the construction, operation and decommissioning phases of the wind farm. The number of trips during the construction phase is expected to be around 20 trips daily. Well maintained vehicles of appropriate engine capacity will be used for transport of the WTG components from the port to the wind farm site and onsite for daily inspection of Sustainable Resource Management Ltd Page 45

16 operation and maintenance of the wind turbines. Therefore air pollution arising due to transport vehicles will be negligible Aspects, Impacts and Mitigation Measures during Operation Generation and Spillage of small amount of Toxic or Hazardous Materials Level of significance: 12 (Harmful but ) Activity: Operation Aspect: Maintenance of turbines Negative Environmental Impacts: Generation and Spillage of small amount of toxic or hazardous materials (lubricating oils, hydraulic fluids and insulating fluids) Each wind turbine will make use of lubricants and oils such as gearbox oil, hydraulic oil, motor oil, and transformer oil. Spillage of oil during handling or storage, storage tank leakage, overflow or rupture may be expected. Oil spills can cause land contamination, infiltrate in the ground causing heavy aquifer pollution; oil dumped on the soil can contaminate water courses due to the process of infiltration, seepage and percolation. Mitigation measures associated to the respective impact are discussed in the next section. Since only a small amount of toxic/hazardous materials will be used, contamination risks of surface or ground water is hence highly negligible. Consortium Suzlon-Padgreen Company Ltd will take all necessary precautions to avoid leaks through regular and thorough examination of all oil piping systems. Regular maintenance will be carried out to detect any fault in the piping system to avoid leaks. Moreover, a stock of emergency response materials such as sand and/or commercially available absorbent materials will be kept on the project site so as to be ready to contain any waste oil in case of an accidental spill. All personnel will be trained to follow the oil spill containment procedures. Sustainable Resource Management Ltd Page 46

17 Landscape and Visual Impacts Level of significance: 16 (Harmful but ) Activity: Operation Aspect: Visual effects of the wind turbines on the Environment. Negative Socio Economic and Environmental Impact: Landscape and visual impacts The wind turbines will be highly visible since they will be sited in exposed places. The visual impact assessment carried out is as per Annex 10. The impacts relating to the aesthetic effect of the proposed wind farm to the existing environmental views were assessed. They were rated between 1 and 5 according to the landscape components, which were vegetation, land use, land form, viewer activity, and presence of any water course. The visual impacts were caused by the wind turbines and their associated electric wires and poles. From the study, road users were the most likely to be affected because of the change in the views. The overall result (as per Annex 10) obtained was 2.1, revealing a moderate to low visual impact. Visible wind turbines are not necessarily intrusive. Aesthetic issues are by their nature highly subjective. A number of mitigation measures will be considered relating to the consideration of appropriate color (normally white) and finishes of the turbines in order to minimize visual effects. The blade tips have white and red strips so that they are clearly visible as per civil aviation requirements. Also, the turbines would be laid out in a manner to avoid being an eyesore. After reafforestation, the dense plantations together with the site s landscape would reduce the visual impact of the wind turbines. Once fully implemented, it is unlikely that the wind farm would be perceived as an eyesore; rather, their contribution to avoiding GHG emissions would prevail (green energy source) and the same would be accepted by society at large. Sustainable Resource Management Ltd Page 47

18 Reduction of GHG Emissions Level of significance: Nil Activity: Operation Aspect: Generation of electricity from wind turbines Positive Environmental Impact: Reduction of GHG emissions Wind turbines do not use fossil to generate electricity. Hence, no GHG emissions are released to the atmosphere. No mitigation measures would be required with respect to air quality as only reduction of GHG emissions is anticipated Employment Opportunities in the Wind Farm Level of significance: Nil Activity: Operation Aspect: Manpower Positive Socio Economic Impact: Creation of employment The wind farm is expected to produce around 25 employment opportunities during its operation. Around 4 to 5 watchmen, 10 in the control room (24/24 hour basis) and 10 to 12 for maintenance will be required. The project will create employment for around 25 persons. Since this is a positive impact, no mitigation measures are required Noise Generation during Operation of the Wind Farm Level of significance: 16 (Harmful but ) Activity: Operation Aspect: Generation of electricity from the wind turbines, movement of blades Sustainable Resource Management Ltd Page 48

19 Negative Socio Economic and Environmental Impacts: Noise generation The sources of noise emitted from the 14 operating wind turbines include Mechanical noise from gearboxes, generators and transformers; Aerodynamic noise produced during rotation of blades. This noise generally increases with wind speed which leads to an increase in the rotor speed. Aerodynamic broadband noise is typically the largest source of wind turbine noise. A complete noise propagation study has been carried out to gauge the impact of the wind turbine s noise on the neighborhood. At hub height (90 m), the noise level will be db(a)l eq and the noise will be attenuated as distance increases away from the wind turbines. The noise predicted at the nearest inhabited region is less than 45 db(a), which is within neighborhood noise limits of 60 db(a) from 07:00 to 18:00, 55 db(a) from 18:00 to 21:00 and 50 db(a) from 21:00 to 07:00, as shown in Figure 7.1. The full acoustic study report is presented in Annex 9. Results indicate that the predicted noise level will comply with the Environmental Standards for Noise (Amendment) Regulations 2003 at any time, which is 70 db(a)l eq, and therefore the operation of the Wind Farm will not affect the nearby inhabitants of La Marie. Every six month, noise monitoring will be carried out during the operation phase such that if ever the noise level exceeds the permissible noise limit, the turbine operations will be controlled to follow certain speed so that the noise level falls back within the norm. Sustainable Resource Management Ltd Page 49

20 Figure 7.1: Projected Sound from all 14 Turbines operating within an Environmental Wind Speed of 8 m/s at Hub Height Sustainable Resource Management Ltd Page 50

21 Non Ionizing Radiation and Electromagnetic Interference Level of significance: 12 (Relatively harmless) Activity: Operation Aspect: Movement of blades and presence of the tower of the WTGs. Negative Socio Economic and Environmental Impact: Non ionizing radiation and electromagnetic interference Two specific issues relating to Non-Ionizing Radiation have been identified. The first relates to Non-Ionizing Radiation that may be produced by the project and its component, primarily the overhead power lines used to export the power produced. The second relates to the potential for wind turbines to produce electromagnetic interference (EMI) effects. EMI is any type of interference that can potentially disrupt, degrade or interfere with the effective performance of an electronic device like communication network, equipment and aviation. This concern is usually about problems caused by the location of wind turbines in relation to existing radio or television stations and, to possible electromagnetic emissions produced by the turbines. It is a fact that the transmission from radio or television broadcast frequencies (mainly FM broadcast frequencies) is influenced by obstacles between the transmitter and the receiver. Interference can be produced by 3 elements of a wind turbine: the tower, the rotor blades and the generator. The tower and blades may obstruct, reflect or refract the electromagnetic waves. However, the blades are made up of high grade GRP and the tower is coated with polyurethane such that both materials have adequate electromagnetic shielding effect. The region over which the high voltage power lines used for export of power from the wind farm will be only non-residential areas. The effect of non-ionizing radiation will be insignificant and thus does not require any special mitigation measure. Sustainable Resource Management Ltd Page 51

22 Impact on Birds during Operation of the Wind Farm Level of significance: 4 (Relatively harmless) Activity: Operation Aspect: Moving blades of the WTGs Negative Environmental Impact: Bird avoidance of habitat; injuries and deaths of birds During operation, the wind farm project could result in the following impacts on birds and their movement: Habitat avoidance/disturbance due to the noise produced by the WTGs and maintenance work at the wind farm. The birds will tend to displace from the preferred habitat in vicinity of the wind farm and the breeding success rate may be reduced; Reduction or loss of available habitat; Creation of a barrier effect to bird movement; and Bird injuries or death through collision with operating WTGs (blades and towers). The main factors which determine the mortality of birds by collision in wind farms are: landscape topography; direction and strength of local winds; turbine design characteristics (height) and the specific spatial distribution of turbines on the location. The mortality caused by wind farms is very dependent on the season, specific site, species and type of bird activity. From the terrestrial flora and fauna survey carried out (see Annex 11), the impacts of the proposed wind farm were assessed. The plantation onsite consists mainly of pines and of invasive species, and no indigenous plants were recorded. A total of around 41,000 m 2 of forest plantation will have to be cleared out during the construction phase, consisting of erection of the 14 wind turbine generators and access road. 7,350 m 2 will be reafforested, therefore the estimated number of trees that will be cut will be around 2,700 pines assuming that roughly half of the plantation was destroyed during cyclones. But, there will be no loss in terms of plant diversity or animal population. Pigeons, Doves and Song birds present onsite will not be affected as they fly low (below 50 m) and forage on ground. Bird collisions usually occur with birds of prey, migratory birds and bats. However, the only bird of prey in Mauritius is the Mauritius Kestrel, which has never been recorded in the proposed site. The latter is also neither a feeding niche for migratory birds and is not found on their migratory route. The Mauritian Fruit Bat will Sustainable Resource Management Ltd Page 52

23 not be harmed as it is normally found at lower altitudes. Thus, no mitigation measures are required. The Striated Heron which was recorded at Mare aux Vacoas and Mare Longue (3 m away from site) could be potentially threatened. Birds are a major concern of the operational impacts of the wind turbines. Risk of bird collision with blades of the wind turbines, which have a swept area of 7,085 m 2 during operation, is real. The impacts of the turbines on birds (specially the Striated Heron) and their movement are expected to be low and even insignificant. Hence, impacts due to wind turbine bird collision are expected to be minimal as the blades (95 m in diameter) will be rotating at around 15 r.p.m which is slow. Therefore the intensity of the impact due to collision is reduced. Other mitigation measures considered are: The minimum area of plantation will, as far as possible, be cleared for the access road. Thus consideration will be given to pass through the tracks near the vegetable plots to have access to Turbines 11 and 12. The removal of the Fandias, which are protected plant species, will be avoided. Utmost care will be taken not to obstruct water courses within the site. The plants to be used for the restoration work will be mainly endemic and native plant species. A proposed list of these plants is as per Annex 11. The criteria used for selecting the plants are: Plants that are found in the Nature Reserve Perrier which is rich in endemism and is the nearest protected area to the site. Plants that are being propagated in nurseries at the Forestry Service and the National Parks and Conservation Service. Plants that will develop into shrubs and not huge trees because huge trees if broken as a result of cyclones are likely to cause damage to the fence/turbines. Sustainable Resource Management Ltd Page 53

24 Road during Operation Phase Level of significance: 4 (Relatively Harmless) Activity: Operation Aspect: Shadow flicker from rotating blades of the wind turbines Negative Socio Economic Impact: Risk of Road Accidents Shadows of the blades are generated when the sun is shining at a low angle (at dawn and before dusk). Shadow flicker of the rotation blades may cause distraction to the drivers and may cause road accidents. The visual impact study did not reveal any spot or area where the flicker of rotating turbines could become a cause for road accidents. Also, the rotation of the blades (15 r.p.m) will not give rise to flicker and hence NO special mitigation measure is envisaged Aspects, Impacts and Mitigation Measures related to Decommissioning Generation of Scrap Metals during Decommissioning Level of significance: 3 (Relatively harmless) Activity: Decommissioning Aspect: Dismantling of wind turbines Negative Environmental Impact: Generation of scrap metals It is envisaged that at the end of the 20 year lifetime of the wind farm, the latter would be de-commissioned which will generate scrap metal from the components of the wind turbines. Since they do not degrade in the environment, these wastes would occupy space if land filled. Thus, a better option would be to recycle them. The scrap metals (around 3,360 tons) will be sent to recycling facilities during the decommissioning phase. They will comprise cable wires, from which the high value copper conductor materials can be recovered, hubs, nacelles (source of iron) and towers Sustainable Resource Management Ltd Page 54

25 (steel). On the other hand, the transformers can be resold, as it would have little wear and would be valuable for reuse Oils and Lubricants during Decommissioning Level of significance: 15 (Harmful but ) Activity: Decommissioning Aspect: Dismantling of wind turbines Negative Environmental Impact: Oils and lubricants Care will be taken to treat all hazardous/toxic (lubricant oil, hydraulic fluids and insulating fluids) within the best available environmental friendly technologies at the end of the 20 years of operation of the wind farm. Care will be taken to treat all toxic (oils and lubricants, if any) with the then available best environmentally friendly technologies. Precautions will be taken to avoid spillage in the environment and will be properly disposed of Air Pollution arising from Transport Vehicles Level of significance: 20 (Harmful but ) Activity: Transport of WTGs during decommissioning Aspects: Vehicles to transport the metal scraps and used oil to recycling facilities and, the remaining wastes to Mare Chicose Landfill. Negative Environmental Impact: Air pollution from transport during the decommissioning phase. Emissions from the vehicles are unavoidable, but the impacts can be reduced by the use of well maintained vehicles for transport during the decommissioning phase. Hence, air pollution arising from the transport vehicles will be minimized. Sustainable Resource Management Ltd Page 55

26 6.3 Summary of Mitigation Measures Table 6.1 shows a summary of the mitigations measures. Table 6.1: Summary of Mitigation Measures Activity Aspect Impact Mitigation Measures 1.Construction Manpower Unloading of WTG components, and operation of heavy machinery including cranes and concrete pumps Water used by workers Excavation and construction of wind turbine foundations, construction of stainless steel huts for installation of transformer, switchgear and power condition devices; laying of overhead distribution cables for connecting to nearby high voltage substation Creation of employment for 100 workers Injuries to workers during the handling of components of the WTGs, operation of heavy machinery including cranes and concrete pumps Freshwater consumption (25.5 m 3 ) for sanitary, potable and concrete mixing. Ecology: 41,000 m 2 of forest will be lost representing approximately 3,200 pine trees that will be cut down. Energy consumption (200 kwh/day) Change in land use and visual effect - Providing appropriate Personal Protective Equipments (PPEs) to workers Avoid wastage of freshwater onsite 7,350 m 2 of forest will be restored with endemic and native species (around 500 trees) - 7,350 m 2 of forest lost will be re-afforested which will minimize aesthetic impacts of the wind turbines Eyesores onsite will be minimized Sustainable Resource Management Ltd Page 56

27 Activity Aspect Impact Mitigation Measures 1.Construction 2. Transport 3. Operation Use of equipment such as crane lorry, hand-held breaker, concrete lorry mixer and vibratory poker Removal of fittings of the WTGs from packaging and remaining construction materials Vehicles used to transport the WTGs Vehicles used to transport WTGs; vehicles used onsite for daily inspection of operation of the wind turbines; vehicles used onsite for maintenance of the wind turbines Maintenance of turbines Visual effects of the wind turbines on the Environment. Generation of electricity from wind turbines Noise and dust generation 1,090 kg/day solid waste generated (packaging, construction and domestic waste) Risk of road accidents and congestion Air pollution leading to global warming and increase in carbon footprint Generation and spillage of small amount of toxic or hazardous materials (lubricating oils, hydraulic fluids and insulating fluids) Change in landscape and visual impacts with a result of 2.1 (moderate to low) from the visual impact assessment. Reduction of GHG emissions - Noise generated during construction shall be within neighborhood noise limits of: 60 db(a)l eq from 07:00 to 18:00, 55 db(a)l eq from 18:00 to 21:00 and 45 db(a)l eq from 21:00 to 07:00, as per Environmental Standards for Noise (Amendment) Regulations 2003 All practical measures will be taken to avoid, minimize and recycle wastes. Safe driving under speed limitation Police escorts assistance Well maintained vehicles of appropriate engine capacity will be used Necessary precautions to avoid leaks Training on oil spill containment procedures Aesthetic impact will be reduced by re-afforestation with a footprint of only 0.3%. Appropriate color (white) of the turbines Manpower Creation of employment (25) - Sustainable Resource Management Ltd Page 57

28 Activity Aspect Impact Mitigation Measures 3. Operation Generation of electricity from the wind turbines, movement of blades Movement of blades and presence of the tower of the WTGs. Noise generation less than 45 db(a) Non ionizing radiation and electromagnetic interference Within neighborhood noise limits of 60 db(a) from 07:00 to 18:00, 55 db(a) from 18:00 to 21:00 and 50 db(a) from 21:00 to 07:00. Within industrial noise limit of 70 db(a) for power stations at any time. - Moving blades of the WTGs Shadow flicker from rotating blades of the wind turbines Bird avoidance of habitat; injuries and deaths of birds Risk of road accidents Intensity of impact is reduced with slow rotation of 15 r.p.m of the blades (as blades span is 95 m) Slow rotation of blades will not give rise to flicker 4.Decommissioning Dismantling of wind turbines Vehicles to transport the metal scraps and used oil to recycling facilities and, the remaining wastes to Mare Chicose Landfill. Generation of scrap metals from cable wires, hubs, nacelles and towers. Oils and lubricants Air pollution from transport during the decommissioning phase. Around 3,360 tons of scrap metals will be recycled Spillage will be avoided Treat all hazardous/toxic substances within best environmental friendly technologies Well maintained vehicles will be used to reduce air pollution Sustainable Resource Management Ltd Page 58

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

4.0 Predicted Environmental Impacts and Mitigation Measures

4.0 Predicted Environmental Impacts and Mitigation Measures 4.0 Predicted Environmental Impacts and Mitigation Measures 4.1 Introduction This chapter deals with the expected impacts and the respective mitigation measures of the project to the environment during

More information

A clean energy solution from cradle to grave

A clean energy solution from cradle to grave Environmental Product Declaration A clean energy solution from cradle to grave Onshore wind power plant employing SWT-3.2-113 siemens.com / wind 2 Assessing the performance of a wind power plant The environmental

More information

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES SECTION 1601 Wind Energy Installation In any zoning district, a conditional use permit or building permit may be granted to allow a wind energy conversion

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY (ADD TO ARTICLE 2) WIND ENERGY DEFINITIONS: Ambient: Ambient is defined as the sound pressure level exceeded ninety (90) percent of the time. Anemometer:

More information

WIND ENERGY CONVERSION SYSTEMS

WIND ENERGY CONVERSION SYSTEMS CHAPTER 159 WIND ENERGY CONVERSION SYSTEMS 159.01 Purpose and Intent 159.05 Location 159.02 Definitions 159.06 Design and Technical Standards 159.03 General Regulations 159.07 Abandonment and Removal Procedure

More information

KENT BREEZE WIND FARMS

KENT BREEZE WIND FARMS Decommissioning Plan Report MAY 2010 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. DECOMMISSIONING PROCESS DESCRIPTION... 2 3. SITE RESTORATION... 3 4. EXCESS MATERIALS AND WASTE MANAGEMENT... 4 5. MANAGING

More information

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows: SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6

C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6 C O M M E R C I A L W I N D E N E R G Y R E G U L A T I O N S - R E V I S E D : 3 / 3 0 / 1 6 6.6 Small and Commercial Wind Energy Conversion Systems 6.61 Intent: In order to balance the need for clean,

More information

Nance County Zoning Regulations for Wind Energy Conversion Systems

Nance County Zoning Regulations for Wind Energy Conversion Systems Nance County Zoning Regulations for Wind Energy Conversion Systems ARTICLE 1: SMALL / NON-COMMERCIAL WIND ENERGY SYSTEMS Section 1. Purpose It is the purpose of this regulation to promote safe, effective

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

Standards of Performance. Mariane Ewbank Chairperson Standards and Customs WG

Standards of Performance. Mariane Ewbank Chairperson Standards and Customs WG Standards of Performance Mariane Ewbank Chairperson Standards and Customs WG Please hold for instructions to open packs 1 and 2 Can we consider this an official doc???? Second version And this invoice?

More information

U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE

U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE May 11, 2009 STANDARD RECOMMENDATIONS TO AVOID, MINIMIZE AND MITIGATE POTENTIAL IMPACTS OF WIND ENERGY

More information

RENEWABLE AND ALTERNATIVE ENERGIES

RENEWABLE AND ALTERNATIVE ENERGIES RENEWABLE AND ALTERNATIVE ENERGIES Degree in Energy Resources Engineering Academic year 2014-15 Prof. Pablo Castro Description: This is a case study for the development of a small wind farm: Wind farm

More information

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators Page 1 of 5 STREAMLINES A Newsletter for North Carolina Water Supply Watershed Administrators Volume 2, Number 2 May 1997 Non-Point Source (NPS) Pollution This issue of Streamlines provides basic information

More information

What type of radiation transmits heat energy? Complete this sentence. Hotter objects emit infrared radiation than cooler objects.

What type of radiation transmits heat energy? Complete this sentence. Hotter objects emit infrared radiation than cooler objects. Page 1 What type of radiation transmits heat energy? Complete this sentence Hotter objects emit infrared radiation than cooler objects. What type of surfaces are good absorbers and good emitters of infrared

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

Palm Beach County Project, LLC

Palm Beach County Project, LLC Palm Beach County Project, LLC February 9, 2011 Agenda Introductions Wind Capital Group Four basics of a wind farm Why Florida? Environmental Process How we build a wind farm Wind Capital Group Independently

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

it is transmitted easily over distance, through electricity cables it can be used in many ways, for example electric lamps, heaters, motors etc

it is transmitted easily over distance, through electricity cables it can be used in many ways, for example electric lamps, heaters, motors etc 1 of 12 1/24/2013 9:01 AM Science Generating electricity Electricity is a convenient source of energy and can be generated in a number of different ways. You will need to weigh up the advantages and disadvantages

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 The United States Forest Service (USFS), Shawnee National Forest (SNF), is analyzing a request from Ameren Services (Ameren), a group

More information

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Purpose of this Public Information Centre Provide you with an update on Hydro One s infrastructure

More information

V MW. One turbine for one world. vestas.com

V MW. One turbine for one world. vestas.com V112-3.0 MW One turbine for one world vestas.com No. 1 in Modern Energy The world needs ever-greater supplies of clean, sustainable energy. Modern energy that promotes sustainable development and greater

More information

SECTORAL ENVIRONMENTAL ASSESSMENT

SECTORAL ENVIRONMENTAL ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REPUBLIC OF MACEDONIA Regional and Roads Program Support Project SECTORAL ENVIRONMENTAL

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm EXECUTIVE SUMMARY This (SEIS) has been prepared for the proposed Jericho Rise Wind Farm (the Project). LLC (the Applicant), a wholly owned subsidiary of EDP Renewables (EDPR), is proposing to construct

More information

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes MINISTRY OF ENVIRONMENT AND NDU ENVIRONMENTAL GUIDELINE No. 31 Asphalt Plant Set Up Temporarily For The Purposes Of A Project By A Public Department 1.0 Purpose of guideline This environmental guideline

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...

More information

Sample Zoning for Wind Energy Systems April 16, 2008

Sample Zoning for Wind Energy Systems April 16, 2008 Sample Zoning for Wind Energy Systems April 16, 2008 Introduction These guidelines have been developed by the Energy Office, Michigan Dept. of Labor and Economic Growth (DLEG) to assist local governments

More information

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision 1. Intent This program has been developed to reduce the risk of physical injury or property

More information

Noise Assessments for Construction Noise Impacts

Noise Assessments for Construction Noise Impacts Noise Assessments for Construction Noise Impacts Weixiong Wu a AKRF, Inc., 440 Park Avenue, 7th floor, New York, NY, 10016, USA. ABSTRACT Construction noise is one of the most disruptive noise sources

More information

Mechatronics Courses by School Period

Mechatronics Courses by School Period Mechatronics Courses by School Period Year One P1 P1 P2 P3 P3 P3 P4 P4 P4 Integrated Systems Industrial Math (Geometry, Trig, Algebra,) Blueprint Reading Machine Tool I (Hand tools-measuring-saws & Drill

More information

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group Environmental Management System Integrated Pollution Control Document No. 5.2.1 Version no. 1 Origination Date 1 st February 2017 Area: The Group Approval: Group Services & Facilities Last Revision Date

More information

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695]

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695] LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695] 1. Notwithstanding all other permits and clearances, the following clearances shall be obtained prior to

More information

Performance Standard 6 V2

Performance Standard 6 V2 Introduction 1. Performance Standard 6 recognizes that protecting and conserving biodiversity, maintaining ecosystem services, and sustainably managing living natural resources are fundamental to sustainable

More information

7.0 EVALUATION OF REMEDIAL ALTERNATIVES

7.0 EVALUATION OF REMEDIAL ALTERNATIVES 7.0 EVALUATION OF REMEDIAL ALTERNATIVES This section provides a description of the developed remedial alternatives based on viable remedial technologies and process options, as identified in Section 4.0,

More information

Electricity Safety (Electric Line Clearance) Regulations 2010

Electricity Safety (Electric Line Clearance) Regulations 2010 Version No. 001 Electricity Safety (Electric Line Clearance) Regulations 2010 Version as at 29 June 2010 TABLE OF PROVISIONS Regulation Page 1 Objectives 1 2 Authorising provisions 1 3 Commencement 2 4

More information

Safe Handling of Pesticides. Presented by Dr. H. B. Singh

Safe Handling of Pesticides. Presented by Dr. H. B. Singh Safe Handling of Pesticides Presented by Dr. H. B. Singh Transportation of CPPs CPPs spilled on the roadway may: Catch fire or be scattered by passing vehicles Be blown by the wind to nearby area Be washed

More information

Noise Impact Assessment

Noise Impact Assessment APPENDIX C Noise Impact Assessment CBCL Limited Appendices NOISE IMPACT ASSESSMENT PUGWASH WIND FARM, NOVA SCOTIA Client Pugwash Wind Farm Inc. Contact Charles Demond Document No Issue B Status Classification

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

MISSILE DEFENSE AGENCY RECORD OF ENVIRONMENTAL CONSIDERATION

MISSILE DEFENSE AGENCY RECORD OF ENVIRONMENTAL CONSIDERATION MISSILE DEFENSE AGENCY RECORD OF ENVIRONMENTAL CONSIDERATION Project Title: AN/TPY-2 Radar Deployment at the Ted Stevens Marine Research Institute (TSMRI) on the National Oceanic and Atmospheric Administration

More information

USER S MANUAL 400W and 600W

USER S MANUAL 400W and 600W USER S MANUAL 400W and 600W 1108 Summit Avenue, Suite 8 Plano, TX 75074 866-WND-PWRD www.acgreenenergy.com CONTENTS 1. WIND TURBINE INTRODUCTION 2. SITING 3. CHOOSING A SUITABLE WIND TURBINE 4. YOUR WIND

More information

Environmental Assessment Matrix

Environmental Assessment Matrix For FCC Use Only Date: Customer Name: Environmental Assessment Matrix Loan Number: Please complete each question. Some answers may require additional information. Attach additional documentation where

More information

Pesticide Safety Program

Pesticide Safety Program Pesticide Safety Program Environmental Health, Safety and Risk Management Department PO Box 6113, SFA Station Nacogdoches, Texas 75962 Thanks to Texas State University for the use of their pesticide chemical

More information

ALTERNATIVE ENERGY RESOURCES ORDINANCE

ALTERNATIVE ENERGY RESOURCES ORDINANCE ALTERNATIVE ENERGY RESOURCES ORDINANCE Intent The Town of Seven Devils recognizes the progressive and changing needs for alternative energy sources and wishes to illustrate a desire to be proactive in

More information

Introduction. The Need for Wind Energy. Consultation. The Applicant

Introduction. The Need for Wind Energy. Consultation. The Applicant Introduction Peel Wind Farms (UKC) Ltd (Peel) propose to construct a wind farm on an area of land that forms part of the former Asfordby mine and tip site and part of the existing Asfordby Business Park

More information

EIGHT POINT WIND ENERGY CENTER

EIGHT POINT WIND ENERGY CENTER EIGHT POINT WIND ENERGY CENTER Case No. 16 F 0062 1001.11 Exhibit 11 Preliminary Design Drawings Contents Exhibit 11: Preliminary Design Drawings... 1 11(a) Site Plan... 1 11(b) Construction Operations

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

Guidance on the Standards for Storage and Treatment of End-of-life vehicles

Guidance on the Standards for Storage and Treatment of End-of-life vehicles Guidance on the Standards for Storage and Treatment of End-of-life vehicles Introduction This guidance has been prepared by the Environment Agency and the Scottish Environment Protection Agency (SEPA),

More information

Part 3 House Packing Facility

Part 3 House Packing Facility Part 3 House Packing Facility This is a critical area for food safety. Whatever was done to keep the produce safe during harvesting and transportation to the packinghouse can be undone in the packinghouse.

More information

CHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary:

CHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary: 7 Errata CHAPTER 7. ERRATA This chapter addresses errors and corrections to the text of the Phase 1 Draft EIS and is organized by Draft EIS chapter, section, and page number. 1) Chapter 1 Introduction

More information

Eurobitume UK. Site Inspection for Delivery of Bitumen

Eurobitume UK. Site Inspection for Delivery of Bitumen Eurobitume UK Site Inspection for Delivery of Bitumen June 2015 To be used in conjunction with the UK edition of the Eurobitume Guide to Safe Delivery of Bitumen Introduction and Scope This site inspection

More information

Safety and Environmental Orientation and Practices for Contractors

Safety and Environmental Orientation and Practices for Contractors Safety and Environmental Orientation and Practices for Contractors Welcome to the University of California, Irvine. Some University facilities are unique and the practices listed here are for your safety

More information

CHAPTER 28 WIND ENERGY CONVERSION SYSTEMS (WECS)

CHAPTER 28 WIND ENERGY CONVERSION SYSTEMS (WECS) CHAPTER 28 WIND ENERGY CONVERSION SYSTEMS (WECS) SECTION: 10-28-1: Purpose 10-28-2: Application 10-28-3: Declaration of Conditions 10-28-4: Site Plan Drawing 10-28-5: Compliance with State Building Code

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

PROCEDURE FOR IDENTIFICATION OF ENVIRONMENTAL ASPECTS, HAZARDS, EVALUATION OF IMPACTS, RISKS AND DETERMINATION OF CONTROL MEASURES

PROCEDURE FOR IDENTIFICATION OF ENVIRONMENTAL ASPECTS, HAZARDS, EVALUATION OF IMPACTS, RISKS AND DETERMINATION OF CONTROL MEASURES Consolidated Construction Consortium Ltd. PROCEDURE NO. : CSP- 4.3.1 ENVIRONMENTAL ASPECTS, HAZARDS, DETERMINATION OF CONTROL MEASURES REV.NO. 0 DATE: 02-09-2011 PAGE 1 OF 10 ENVIRONMENTAL ASPECTS, HAZARDS,

More information

Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events)

Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events) Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events) TABLE OF CONTENTS 12 HAZARD ANALYSIS AND RISK ASSESSMENT... 12-1 12.1 Introduction... 12-1 12.2 Pipeline Design and Risk... 12-1 12.2.1

More information

Identification and evaluation of environmental aspects

Identification and evaluation of environmental aspects 1.0 Purpose This procedure defines the mechanism for the identification and evaluation of environmental aspects of the operations of KSPH&IDCL in order to determine those aspects that have actual or potential

More information

INVASIVE SPECIES CONTROL PLAN FOR CONSTRUCTION ACTIVITIES AND POST CONSTRUCTION MONITORING

INVASIVE SPECIES CONTROL PLAN FOR CONSTRUCTION ACTIVITIES AND POST CONSTRUCTION MONITORING INVASIVE SPECIES CONTROL PLAN FOR CONSTRUCTION ACTIVITIES AND POST CONSTRUCTION MONITORING INTRODUCTION Black Oak Wind Farm, LLC is proposing to develop a wind-powered electric generating facility (the

More information

A. Provide for the appropriate location and development of antennas and towers within the city;

A. Provide for the appropriate location and development of antennas and towers within the city; Section 1325 - Antennas and Towers 1325.01 Purpose and Intent. In order to accommodate the communication needs of residents and business while protecting the public health, safety and general welfare of

More information

CAL/OSHA ELECTRICAL HIGH VOLTAGE

CAL/OSHA ELECTRICAL HIGH VOLTAGE Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to electrical exposure to high voltage for employees and contractors

More information

OELG Event Categories

OELG Event Categories OELG Event Categories The table below outlines a proposed set of event categories. These have been developed from the MOD event categories and those used previously by the OELG. The aim of the work has

More information

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and Introduction There are many tools that a reviewer of environmental impact assessment documents can use to help determine whether such documents are complete and adequate. Among the powerful tools that

More information

Sub-sectoral Environmental and Social

Sub-sectoral Environmental and Social PROCESS DESCRIPTION This guideline covers the establishment and operation of the terrestrial elements of satellite and cable television networks. It does not cover the manufacture of set top boxes. For

More information

South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48

South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48 South Australia Continuing to Make Room for Wind Farms: Tru Energy Renewable Developments Pty Ltd V Regional Council of Goyder & Ors [2014] SAERDC 48 Claudia Mollina 1 The Environment, Resources and Development

More information

Ensure your own actions reduce risks to health and safety

Ensure your own actions reduce risks to health and safety Ensure your own actions reduce risks to health and safety UNIT SM 1 Area of competence This unit is designed to demonstrate competence in following the health and safety duties required in the workplace

More information

Waste incineration plant authorisation

Waste incineration plant authorisation Waste incineration plant authorisation REC-E1060, Business Environmental Law Kanerva Sunila Some background National Waste Plan (VALTSU) Main targets Prevention of waste Material recycling and biological

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

City of Valparaiso Job Description Water & Sewer Operator

City of Valparaiso Job Description Water & Sewer Operator POSITION TITLE: Water and Sewer Operator DEPARTMENT: Public Works DIVISION: Water and Sewer REPORTS TO: Lead Water and Sewer Operator DEPARTMENT HEAD: Public Works Director STATUS: Non-exempt LAST REVISION:

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Division 8 Intensive Animal Husbandry Code

Division 8 Intensive Animal Husbandry Code Division 8 Intensive Animal Husbry Code 12.8.1 Intensive Animal Husbry Code (1) The provisions in this division comprise the Intensive Animal Husbry Code. (2) They are compliance with the Intensive Animal

More information

COMPLETE COMPLIANCE CHECKLIST

COMPLETE COMPLIANCE CHECKLIST COMPLETE COMPLIANCE CHECKLIST 1. Does your office maintain an active compliance program or plan? 2. Does your office consistently update this plan as new requirements are identified or as new business

More information

Building Permit Applications for new home construction will not be accepted unless the following documentation is included at the time of submission:

Building Permit Applications for new home construction will not be accepted unless the following documentation is included at the time of submission: Building Permit Applications for new home construction will not be accepted unless the following documentation is included at the time of submission: Copy of Alberta Government s New Home Registration

More information

4. Project Description

4. Project Description 4. Project Description 4.1 Introduction This chapter provides information on the principal elements of the proposed redevelopment of St Louis Power Station. A description of the existing site and surrounding

More information

ELECTRICAL SYSTEMS. TEST YOURSELF QUESTIONS: Answer Key. CHAPTER 1: Sustainability in Electrical Systems

ELECTRICAL SYSTEMS. TEST YOURSELF QUESTIONS: Answer Key. CHAPTER 1: Sustainability in Electrical Systems ELECTRICAL SYSTEMS TEST YOURSELF QUESTIONS: Answer Key CHAPTER 1: Sustainability in Electrical Systems 1. What are the benefits of sustainability in green building design? The benefits of sustainability

More information

Non-Renewable Energy Resources: How do dead things power our lives?

Non-Renewable Energy Resources: How do dead things power our lives? Non-Renewable Energy Resources: How do dead things power our lives? Life requires energy it is stored, transferred, and converted Ultimate source of energy for life the Sun For humans, our source of energy

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

COUNTY OF CAPE MAY STATE OF NEW JERSEY ORDINANCE NO ESTABLISHING REGULATIONS FOR SMALL WIND ENERGY SYSTEMS AND SOLAR ENERGY SYSTEMS

COUNTY OF CAPE MAY STATE OF NEW JERSEY ORDINANCE NO ESTABLISHING REGULATIONS FOR SMALL WIND ENERGY SYSTEMS AND SOLAR ENERGY SYSTEMS BOROUGH OF WEST CAPE MAY COUNTY OF CAPE MAY STATE OF NEW JERSEY ORDINANCE NO. 421-09 ESTABLISHING REGULATIONS FOR SMALL WIND ENERGY SYSTEMS AND SOLAR ENERGY SYSTEMS WHEREAS, it is the purpose of this ordinance

More information

Version 26 february Information for product organizations: identifying and evaluating environmental aspects within ISO

Version 26 february Information for product organizations: identifying and evaluating environmental aspects within ISO Information for product organizations: identifying and evaluating environmental aspects within ISO 14001 Information for product organizations: identifying and evaluating environmental aspects within ISO

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Preliminary Hazard Analysis and Risk Assessment for the Wood Centre Development, Southwood Resources - Huon

Preliminary Hazard Analysis and Risk Assessment for the Wood Centre Development, Southwood Resources - Huon Preliminary Hazard Analysis and Risk Assessment for the Wood Centre Development, Southwood Resources - Huon TABLE OF CONTENTS PRELIMINARY HAZARD ANALYSIS AND RISK ASSESSMENT... 4 INTRODUCTION... 4 METHODOLOGY...

More information

+/0'-/12!"&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=!

+/0'-/12!&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=! "#$%&'(&)&$*+,,-,,%-./ +/0'-/12"&21'1/345$1.1/36#''-7-8#9:;&?-/3@1$-2/#$&'#.7A1/0/0-B$#C-2/D&.&7-$&.*>EF-$G1,#$?#$/0-,1/-*1*/0-$1,H&,,-,,%-./?#$/0-.-A+/0'-/12"&21'1/3/0&/ 1,9-1.79E1'/#./0-7$#E.*,#?5$1.1/36#''-7->20##''#2&/-*&/

More information

Questionnaire (Wood Processing)

Questionnaire (Wood Processing) Questionnaire (Wood Processing) QUESTIONNAIRE FOR WOOD PROCESSING (SECTOR-RELATED QUESTIONS) The completion of this questionnaire is voluntary. However, replying to the relevant questions as completely

More information

H 6062 S T A T E O F R H O D E I S L A N D

H 6062 S T A T E O F R H O D E I S L A N D LC001 01 -- H 0 S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 01 A N A C T RELATING TO AGRICULTURE AND FORESTRY - FARM CONSERVATION AND RENEWABLE ENERGY Introduced By: Representative

More information

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC.

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC. BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC www.uk-bar.org CONTENTS Introduction.... 3 Hazards.... 4 Accidents... 5 Working at Height... 6 Dunnage.... 7 Planning for a Safe Delivery....

More information

Hazardous Waste Management

Hazardous Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

AQA GCSE Physics Unit 1 Specification

AQA GCSE Physics Unit 1 Specification P1.1 The transfer of energy by heating processes and the factors that affect the rate at which that energy is transferred Energy can be transferred from one place to another by work or by heating processes.

More information

Aspects of the australian food industry

Aspects of the australian food industry Aspects of the australian food industry H3.1: Investigates operations of ONE organisation within the AFI. - Describe the activities carried out in ONE organisation within the AFI. H1.4: Evaluates the impact

More information

NEVER REMOVE THE SAFETY GUARDS

NEVER REMOVE THE SAFETY GUARDS Page 1 of 5 Name Recommended Use Designed for cutting stumps up to 200 mm above ground and 120 mm below ground. Maximum Stump diameter 300 mm. NOT suitable for stumps surrounded by rocks, stones, concrete

More information