ABSTRACT INTRODUCTION

Size: px
Start display at page:

Download "ABSTRACT INTRODUCTION"

Transcription

1 Title: Using Fly Ash to Construct New Ash Pond Containment Dikes at the Wabash River Generating Station Authors: Mr. Keith Brinkman, Mechanical Engineer, Duke Energy Mr. Terry Larson, PE, Project Manager, Burns & McDonnell Date: 2006 Presented at: Coal-Gen 2006 ABSTRACT The existing fly ash ponds at Duke Energy s (formerly Cinergy) Wabash River Generating Station are nearing their useful capacity and site constraints limited the available options for new on-site ash disposal facilities. Ash had to be prepared to optimum moisture and marketed for outside uses to provide sufficient capacity until another ash disposal facility could be constructed. Other site constraints had to be considered in the design of the new facility, including maximizing the use of existing ash materials in the construction of the new facility. Therefore existing ash materials were utilized in the construction of dike structures that will be used for containing ash produced in the future. This paper outlines some of the site constraints and other unique challenges that had to be considered in the design of the new ash pond disposal facility as well as an in depth look at why and how existing ash materials were incorporated into the new disposal facility design. Design considerations to utilize the fly ash in the dike construction include seismic stability, dealing with very moist conditions, and ash placement concerns with respect to removing it from the existing pond, drying to acceptable moisture content, and placing the ash in the dike. Quality assurance testing of the in-place ash also had some unique challenges that will be addressed in this paper. INTRODUCTION The Wabash River Generating Station is located north of Terre Haute, Ind., along the Wabash River and has six coalfired units with a combined generating output of 668 megawatts (MW). Unit 1 s boiler was retired in the 1990s and the steam turbine and generator were repowered using steam from a new coal gasification plant sited northwest of the Wabash River Station. Slag produced from the coal gasification facility is hauled offsite for other uses. Units 2 thru 6 burn a local bituminous coal that produces a Type F fly ash. Fly ash and bottom ash from these five units are sluiced to a common ash disposal pond facility (see Figure 1) located south of the plant. The existing ash pond facility was initially constructed in the mid-1960s. The ash pond was expanded in the 1980s when a new primary disposal cell along with a secondary settling cell were added. The existing pond facilities were nearing their useful capacity and the plant needed to look at construction of a new ash disposal facility and/or identify offsite beneficial uses for the ash material. Page 1 of 5

2 Figure 1: Existing ash disposal pond POND DESIGN PHASE Several design challenges and obstacles had to be overcome in the design of the new ash disposal pond facility. The biggest challenge was keeping the existing pond in-service until the new ash disposal facility could be designed and constructed. As mentioned earlier, the existing pond was already nearing full capacity when the decision to construct a new disposal facility was made. In order to maintain sufficient capacity in the existing pond until a new facility could be constructed, offsite beneficial uses of the ash had to be identified and implemented. Ways to maximize use of available pond storage capacity also had to be incorporated in the overall ash management plan. Cinergy found an ideal beneficial use for the ash. The ash was used as fill material to help reclaim an existing coal strip mine. In order for this beneficial use to occur, the ash had to be dewatered to near optimum moisture before it was loaded onto trucks and hauled to the mine. Cinergy also found other uses for the ash, such as use in highway embankment for bridge approaches. To maximize use of existing pond storage capacity, Cinergy purchased a hydraulic dredge (see Figure 2) to redistribute ash within the pond to fill in dead storage areas in order to maintain sufficient free water surface area and create additional ash storage capacity within the active pond cell for settlement of ash. A dragline was also used to maintain the initial settlement chamber where the ash sluice pipes discharge into the pond. The ash removed by dragline was dewatered by temporarily stacking it above the pond water surface. Then it was loaded onto trucks for beneficial use purposes as discussed previously. Several alternatives were considered for future disposal of ash produced including the following: Raising the earthen dikes of the existing ash pond to provide additional capacity. This alternative was not pursued due to limited space available to raise and widen the existing pond dikes. Constructing internal containment berms within the existing pond dike system. The berms would be constructed out of ponded ash and synthetic geogrid material. However, the cost of stabilizing the in-place ash to provide a suitable base and the cost of installing the geogrid made this alternative economically unattractive. The alternative selected was to construct a new 130 acre HDPE-lined ash disposal pond facility in an open field located immediately south of the existing ash pond facility. Siting the new facility adjacent to the existing pond was beneficial because the existing plant ash conveyance system is operating at maximum capacity and upgrading the existing system Page 2 of 5

3 would be cost prohibitive. Ash will be conveyed to the new ash pond facility by placing a hydraulic dredge in the initial settlement chamber of the existing pond and hydraulically conveying the dredged ash 5,000 feet to the new pond expansion area. Therefore, the existing ash pond will remain in service to receive ash. Effluent from the new pond expansion overflows back through the existing secondary settling cell where it discharges through the existing NPDES permitted outfall. Figure 2: Hydraulic dredge used For moving ash The initial pond design included use of earthen dikes to form the new pond disposal facility. However, the mine reclamation work that used the majority of ash being produced was nearing completion before the new pond could be constructed. Therefore, an additional beneficial use had to be identified. The decision was made to use previously ponded ash as the core material for the new dike system. The new ash pond expansion had to be approved through the Indiana Department of Natural Resources (IDNR). A seismic stability analysis demonstrated the facility would be stable during a seismic event. The stability analysis demonstrated that the ash was structurally suitable for dike construction. CONSTRUCTION PHASE The ash used in dike construction had to be placed in a manner that it was properly contained in the event of a flood condition. The ash dike core is encapsulated by 5 feet of soil so that it is not exposed to the elements. During construction, the outer soil layer was placed sequentially ahead of the inner ash material so that the ash would be protected in the event of a flood event (see Figures 3 and 4). Page 3 of 5

4 Figure 3: Placing ash in core of new pond dike Figure 4: Completed pond dike The construction phase of the project also included several challenges. The biggest challenge was dewatering the ponded ash to an acceptable moisture content range before placement. The ash removal and drying process in the pond had to be conducted sufficiently in advance of the dike construction process to give the ash ample time to dewater and dry before placement. Also, the ash source location impacted the required dewatering time and ash handling requirements since the ash tends to segregate by sediment size across the pond. The coarser ash tends to settle near the ash sluice line discharge, while finer material carries across the pond. The coarser ash will dewater faster and is easier to handle, so this material was typically used for dike construction when available. Another challenge was in-place measurement of ash moisture content during the construction quality control process. Because of the relatively high carbon content of the ash, the nuclear density gage systems used to measure in-place Page 4 of 5

5 density would not accurately measure in-place moisture content of the ash. Consequently, in-place fly ash moisture contents had to be obtained by oven drying methods. After construction of the pond system was in progress, a decision was made to install a center dike in the pond to reduce the HDPE composite lined portion of the pond to 80 acres (see Figure 5). The remaining 60-acre area will remain unlined until future decisions are finalized relative to plant combustion waste disposal needs. SUMMARY The Type F ash produced at the Wabash River Generating Station is an excellent material for use in dike construction and other general fill applications. The biggest challenge to utilizing ash from an ash pond system for fill applications is dewatering the ash to optimum moisture. The ash readily dewaters if it can be stacked above the pond water surface and allowed to sit for several days before using. The coarser ash materials located closer to the ash sluice line discharge point are typically easier to dewater and handle, though the finer material can be used if a longer dewatering time is allotted. Figure 5: Complete pond extension Page 5 of 5

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENTS CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED

More information

David Miller, P.E.- Atlanta. The New Coal Ash Regulations Wednesday, May 6, 2015

David Miller, P.E.- Atlanta. The New Coal Ash Regulations Wednesday, May 6, 2015 David Miller, P.E.- Atlanta The New Coal Ash Regulations Wednesday, May 6, 2015 Overview of CCR Management & Regulations Subtitle D Requirements & Compliance Schedule Non-Utility Boilers Beneficial Reuse

More information

40 CFR Part 257. Rollin M. Schahfer Generating Station

40 CFR Part 257. Rollin M. Schahfer Generating Station Annual CCR Fugitive Dust Control Report in support of 40 CFR Part 257 for Northern Indiana Public Service Company s Rollin M. Schahfer Generating Station Table of Contents Introduction... 3 Requirement

More information

TVA Colbert Fossil Facility Ash Disposal Pond 4

TVA Colbert Fossil Facility Ash Disposal Pond 4 2011 World of Coal Ash (WOCA) Conference May 9-12, 2011 in Denver, CO, USA http://www.flyash.info/ TVA Colbert Fossil Facility Ash Disposal Pond 4 Improving Operations While Preparing for Closure May 10,

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 0200-S3N-R2 AFIN: 32-00042 JANUARY 15, 2016 ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

NAUGHTON POWER PLANT NORTH ASH POND INITIAL CLOSURE PLAN

NAUGHTON POWER PLANT NORTH ASH POND INITIAL CLOSURE PLAN NAUGHTON POWER PLANT NORTH ASH POND INITIAL CLOSURE PLAN Prepared for: PacifiCorp Energy Project Manager: Chad Tomlinson Date: 01 September 2016 Document No.: NP-TR-022 Quality Assurance Statement Office

More information

Closure Plan Brame Fly Ash Pond

Closure Plan Brame Fly Ash Pond Brame Fly Ash Pond CLECO Corporation Rodemacher Unit 2 Project No. 90965 Revision 0 10/14/2016 Brame Fly Ash Pond prepared for CLECO Corporation Rodemacher Unit 2 Rapides Parish, Louisiana Project No.

More information

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS Surface Impoundment Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 2 3. PROPOSED COVER SYSTEM... 2 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 3 5. ESTIMATED

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No Environmental Resources Management January 13, 2017 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0352436 CityCentre Four 840 West Sam Houston Parkway North, Suite 600 Houston,

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO. 0199-S3N-R3 AFIN: 35-00110 JANUARY 15, 2016 ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

Annual Inspection Report Lawrence Energy Center

Annual Inspection Report Lawrence Energy Center Annual Inspection Report Lawrence Energy Center Inactive Units - Ash Pond Area 2, Ash Pond Area 3, and Ash Pond 4 Prepared for: Westar Energy Lawrence Energy Center Lawrence, Kansas Prepared by: CB&I Environmental

More information

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for:

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for: Initial Closure Plan Slag Pond Prepared for: Wisconsin Power and Light Company 11999 County Highway VV Cassville, Wisconsin 53806 Prepared by: SCS ENGINEERS 2830 Dairy Drive Madison, Wisconsin 53718-6751

More information

Inflow Design Flood Control System Plan

Inflow Design Flood Control System Plan Inflow Design Flood Control System Plan R.M. SCHAHFER GENERATING STATION CCR SURFACE IMPOUNDMENT INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN Wheatfield, Indiana Pursuant to 40 CFR 257.82 Submitted To: Northern

More information

HAZARD POTENTIAL CLASSIFICATION REPORT

HAZARD POTENTIAL CLASSIFICATION REPORT HAZARD POTENTIAL CLASSIFICATION REPORT PONDS 1 & 2, JR WHITING PLANT ERIE, MICHIGAN OCTOBER 13, 2016 PREPARED FOR: CONSUMERS ENERGY COMPANY TABLE OF CONTENTS SECTION: PAGE NO.: Certification... i 1.0 Introduction...

More information

CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN. Pursuant to 40 CFR

CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN. Pursuant to 40 CFR Run-On & Run-Off Control System Plan R.M. SCHAHFER GENERATING STATION CCR LANDFILL RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN Wheatfield, Indiana Pursuant to 40 CFR 257.81 Submitted To: Northern Indiana Public

More information

Closure Plan Ash Disposal Area PGE Boardman Power Plant

Closure Plan Ash Disposal Area PGE Boardman Power Plant FIRST ISSUE REVISION 0 Closure Plan Ash Disposal Area PGE Boardman Power Plant Prepared for Portland General Electric September 2015 2020 SW 4th Avenue, Suite 300 Portland, Oregon 97201 This document was

More information

ENVIRONMENTAL ENGINEERING LAND SURVEYING

ENVIRONMENTAL ENGINEERING LAND SURVEYING ENVIRONMENTAL ENGINEERING LAND SURVEYING Inflow Design Flood Control System Plan Bottom Ash Pond Sherburne County Generating Plant Introduction This report presents documentation and certification of the

More information

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI INITIAL PREPARATION DATE: October 11, 2016 TABLE OF CONTENTS 1. CERTIFICATION

More information

CLOSURE PLAN. CFR (b) Document No. GERS Stingy Run Flyash Pond. Gavin Plant Cheshire, Ohio. October, 2016

CLOSURE PLAN. CFR (b) Document No. GERS Stingy Run Flyash Pond. Gavin Plant Cheshire, Ohio. October, 2016 CLOSURE PLAN CFR 257.102(b) Stingy Run Flyash Pond Gavin Plant Cheshire, Ohio October, 2016 Prepared for: AEP Generation Resources Gavin Plant Cheshire, Ohio Prepared by: American Electric Power Service

More information

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT

More information

I. Site Name and Location

I. Site Name and Location HALEY & ALDRICH, INC. 6500 Rockside Road Suite 200 Cleveland, OH 44131 216.739.0555 MEMORANDUM File No. 41938-009 SUBJECT: CCR Fugitive Dust Control Plan - Initial Jeffrey Energy Center St. Marys, Kansas

More information

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY

SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY SMART GYPSUM STACK MANAGEMENT FROM CONCEPT TO REALITY Phong Vo, Manager - Engineering/Gypsum, Mosaic Fertilizer, LLC. 13830 Circa Crossing Drive Lithia, Florida 33547, USA and Ashraf H. Riad, Ph.D., P.E.,

More information

The Impact of Surface Coal Mining on Water Quality in the Northern Great Plains

The Impact of Surface Coal Mining on Water Quality in the Northern Great Plains The Impact of Surface Coal Mining on Water Quality in the Northern Great Plains by Joseph D. Friedlander The North American Coal Corporation Presented at the 2015 National Meeting of the American Society

More information

Steam Electric Power Generating Effluent Guidelines Protecting Surface Water from Power Plant Discharges

Steam Electric Power Generating Effluent Guidelines Protecting Surface Water from Power Plant Discharges Steam Electric Power Generating Effluent Guidelines Protecting Surface Water from Power Plant Discharges EPA Call with the Institute of Clean Air Companies June 22, 2016 Effluent Guidelines Definition

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

BENEFICIAL USE OF COAL COMBUSTION PRODUCTS AN AMERICAN RECYCLING SUCCESS STORY

BENEFICIAL USE OF COAL COMBUSTION PRODUCTS AN AMERICAN RECYCLING SUCCESS STORY BENEFICIAL USE OF COAL COMBUSTION PRODUCTS AN AMERICAN RECYCLING SUCCESS STORY 1 The American Coal Ash Association was established in 1968 as a trade organization devoted to recycling the materials created

More information

FUGITIVE DUST CONTROL PLAN HUNTLEY GENERATION STATION 3500 RIVER ROAD TONAWANDA, NEW YORK. PREPARED FOR: Huntley Power, LLC Tonawanda, New York

FUGITIVE DUST CONTROL PLAN HUNTLEY GENERATION STATION 3500 RIVER ROAD TONAWANDA, NEW YORK. PREPARED FOR: Huntley Power, LLC Tonawanda, New York FUGITIVE DUST CONTROL PLAN HUNTLEY GENERATION STATION 3500 RIVER ROAD TONAWANDA, NEW YORK PREPARED FOR: Huntley Power, LLC Tonawanda, New York PREPARED BY: GZA GeoEnvironmental of New York Buffalo, New

More information

I. Site Name and Location

I. Site Name and Location HALEY & ALDRICH, INC. 6500 Rockside Road Suite 200 Cleveland, OH 44131 216.739.0555 MEMORANDUM 17 April 2017 File No. 129778 005 SUBJECT: CCR Fugitive Dust Control Plan Revision #1 Jeffrey Energy Center

More information

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO 2016 LANDFILL INSPECTION REPORT GERS-16-004 CARDINAL PLANT BRILLIANT, OHIO PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Cardinal Plant Landfill Inspection

More information

FUGITIVE DUST CONTROL PLAN DUNKIRK GENERATION STATION 106 POINT DRIVE NORTH DUNKIRK, NEW YORK. PREPARED FOR: Dunkirk Power, LLC Dunkirk, New York

FUGITIVE DUST CONTROL PLAN DUNKIRK GENERATION STATION 106 POINT DRIVE NORTH DUNKIRK, NEW YORK. PREPARED FOR: Dunkirk Power, LLC Dunkirk, New York FUGITIVE DUST CONTROL PLAN DUNKIRK GENERATION STATION 106 POINT DRIVE NORTH DUNKIRK, NEW YORK PREPARED FOR: Dunkirk Power, LLC Dunkirk, New York PREPARED BY: GZA GeoEnvironmental of New York Buffalo, New

More information

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan) A. B. Brown History of Construction 40 CFR 257.73 (c) (i.) (ii.) (iii.) Owner Name: Southern Indiana Gas and Electric Company dba Vectren Power Supply Owner Address: One Vectren Square, PO Box 209, Evansville,

More information

General Permit No.: OHR Page 53 of 146

General Permit No.: OHR Page 53 of 146 Page 53 of 146 Part 8 Sector-Specific Requirements for Industrial Activity Subpart J Sector J Non-Metallic Mineral Mining and Dressing. You shall comply with Part 8 sector-specific requirements associated

More information

ENERGY SOURCE ESI. A Newsletter published by. The Steam and Power SPECIAL FORCES

ENERGY SOURCE ESI. A Newsletter published by. The Steam and Power SPECIAL FORCES ENERGY SOURCE A Newsletter published by ESI The Steam and Power SPECIAL FORCES Summer 2010 Consider This... Designing a Successful Biomass Material Handling System Part 2 : Material Receiving System Design

More information

Determination of Ash Mixture Properties and Construction of Test Embankment - Part B

Determination of Ash Mixture Properties and Construction of Test Embankment - Part B Final Report FHWA/IN/JTRP-2006/24 Determination of Ash Mixture Properties and Construction of Test Embankment - Part B by Sungmin Yoon and Umashankar Balunaini Graduate Research Assistants Monica Prezzi,

More information

CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN. Prepared for: Tucson Electric Power Company Springerville Generating Station Springerville, Arizona

CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN. Prepared for: Tucson Electric Power Company Springerville Generating Station Springerville, Arizona CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN Prepared for: Tucson Electric Power Company Springerville Generating Station Springerville, Arizona Prepared by: CB&I Environmental & Infrastructure, Inc. Pittsburgh,

More information

Environmental Information Worksheet

Environmental Information Worksheet Environmental Information Worksheet Water System Owner (Attach additional sheets if necessary) Needs and Alternatives Provide a brief narrative that describes: Current drinking water system needs. Project

More information

THE ABATEMENT PLAN. beneficial abatement plan. For the purpose of defining the pollution potential of surface waters

THE ABATEMENT PLAN. beneficial abatement plan. For the purpose of defining the pollution potential of surface waters THE ABATEMENT PLAN GENERAL PLAN Preventing surface waters from entering deep mine workings apparently offers the most beneficial abatement plan. For the purpose of defining the pollution potential of surface

More information

The City of Cocoa (City) is located in east

The City of Cocoa (City) is located in east FWRJ Reclaimed Water and Stormwater: A Perfect Pair to Meet Total Maximum Daily Load Wasteload Allocations? Danielle Honour, James Wittig, John A. Walsh, and Don Stevens Danielle Honour, P.E., D.WRE, and

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any

More information

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. 11-91360-001 ADVERTISED: November 5, 2010 MANDATORY PRE-BID MEETING:

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

LOW LYING AREA FILLING

LOW LYING AREA FILLING LOW LYING AREA FILLING 4.2 Guidelines for Low Laying Area Filling prepared by SPC Board, Odisha in collaboration with C-FARM, New Delhi. Preamble: Generation of large volumes of pulverized fuel ash (PFA)

More information

Fully-dry bottom ash removal system for elimination of ponds

Fully-dry bottom ash removal system for elimination of ponds 2015 World of Coal Ash (WOCA) Conference in Nasvhille, TN - May 5-7, 2015 http://www.flyash.info/ F. Bassetti et al MAC - MAGALDI ASH COOLER Fully-dry bottom ash removal system for elimination of ponds

More information

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce

Lake County Success. support through synergistic local partnerships that not only mitigate, but also produce Lake County Success Generating Environmental Gains With Geothermal Power By Mark Dellinger, Administrator, Lake County (CA) Sanitation District, and Eliot Allen, Principal, Criterion/Planners Engineers

More information

How Dense Slurry Fly Ash Disposal helped Europe's largest Brown Coal Power Station to reduce its Water Consumption by over 90%

How Dense Slurry Fly Ash Disposal helped Europe's largest Brown Coal Power Station to reduce its Water Consumption by over 90% 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ How Dense Slurry Fly Ash Disposal helped Europe's largest Brown Coal Power Station to reduce its Water

More information

In-Situ Coal Combustion Products Impoundment Closure/Remediation Strategy

In-Situ Coal Combustion Products Impoundment Closure/Remediation Strategy 2015 World of Coal Ash (WOCA) Conference in Nasvhille, TN - May 5-7, 2015 http://www.flyash.info/ In-Situ Coal Combustion Products Impoundment Closure/Remediation Strategy Tim Silar 1, John Magee 1 Christopher

More information

LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO S3N AFIN:

LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO S3N AFIN: LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO. 0303-S3N AFIN: 47-00461 OCTOBER 14, 2016 LANDFILL CLOSURE PLAN PLUM POINT ENERGY STATION CLASS 3N CCR LANDFILL PERMIT NO.

More information

Nonrenewable Energy Resources 5.1

Nonrenewable Energy Resources 5.1 Nonrenewable Energy Resources 5.1 I. Energy Some energy resources on Earth are being used faster than nature can replace them these are called nonrenewable energy resources Most of the energy resources

More information

REUSE OF DREDGED SEDIMENTS

REUSE OF DREDGED SEDIMENTS REUSE OF DREDGED SEDIMENTS Lake Erie Waterkeeper Conference W.W. Knight Nature Preserve, Perrysburg, Ohio Friday, March 18, 2016 John H. Hull, P.E., BCEE Hull & Associates, Inc. SEDIMENT ENTERING LAKE

More information

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Updated: November 2010 Directive 74 Appendix C Requirement Approval: 8512D Submitted to SHELL CANADA ENERGY MRM DDA PLAN-UPDATE NOV

More information

OIL SANDS TAILINGS TECHNOLOGY: UNDERSTANDING THE IMPACT TO RECLAMATION. Melinda Mamer, P.Eng

OIL SANDS TAILINGS TECHNOLOGY: UNDERSTANDING THE IMPACT TO RECLAMATION. Melinda Mamer, P.Eng OIL SANDS TAILINGS TECHNOLOGY: UNDERSTANDING THE IMPACT TO RECLAMATION Melinda Mamer, P.Eng Suncor Energy Inc. P.O. Box 4001 Fort McMurray, AB T9H 3E3 ABSTRACT Managing tailings is a critical component

More information

Town of Fortville Utility Street Standards

Town of Fortville Utility Street Standards Town of Fortville Utility Street Standards SECTION 02101 - TEMPORARY EROSION AND DUST CONTROL PART 1 - GENERAL 1.1 DESCRIPTION A. Temporary Erosion and Dust Control measures must meet the current Town

More information

WEFTEC.06. **Cobb County Water System, Marietta, Georgia

WEFTEC.06. **Cobb County Water System, Marietta, Georgia CHEMICALLY ENHANCED PRIMARY TREATMENT FOR A LARGE WATER RECLAMATION FACILITY ON A CONSTRICTED SITE - CONSIDERATIONS FOR DESIGN, START-UP, AND OPERATION ABSTRACT Jeffrey A. Mills, P.E., BCEE,* Roderick

More information

ABERDEEN CITY SUSTAINABLE DRAINAGE SYSTEMS (SUDS) AND FLOOD DEFENCES

ABERDEEN CITY SUSTAINABLE DRAINAGE SYSTEMS (SUDS) AND FLOOD DEFENCES ABERDEEN CITY SUSTAINABLE DRAINAGE SYSTEMS (SUDS) AND FLOOD DEFENCES Countesswells Avenue, Retention Pond A retention ponds function is for water attenuation (storing and slow release) and treatment. The

More information

2013 World of Coal Ash (WOCA) Conference - April 22-25, 2013 in Lexington, KY

2013 World of Coal Ash (WOCA) Conference - April 22-25, 2013 in Lexington, KY 2013 World of Coal Ash (WOCA) Conference - April 22-25, 2013 in Lexington, KY http://www.flyash.info/ Use of Bottom Ash in the Reinforced Zone of a Mechanically Stabilized Earth Wall for the Vertical Expansion

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

New 790-Megawatt Unit. Council Bluffs Energy Center

New 790-Megawatt Unit. Council Bluffs Energy Center New 790-Megawatt Unit Council Bluffs Energy Center JUST THE FACTS Council Bluffs Energy Center s New 790-Megawatt Unit Background To ensure a long-term positive impact on Iowa's economy and a secure supply

More information

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria

Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria Integrated Mine Waste Storage Concept, Krumovgrad Gold Project, Bulgaria Terry Eldridge Golder Associates S.A., Chile Ben Wickland Golder Associates Ltd., Canada Adrian Goldstone Dundee Precious Metals

More information

Nomination for 2014 Hardrock Mining Reclamation Awards Colorado Mined Land Reclamation Board Colorado Mining Association

Nomination for 2014 Hardrock Mining Reclamation Awards Colorado Mined Land Reclamation Board Colorado Mining Association Nomination for 2014 Hardrock Mining Reclamation Awards Colorado Mined Land Reclamation Board Colorado Mining Association Nominee: Permit: Climax Molybdenum Company Climax Mine Highway 91 Fremont Pass Climax,

More information

PENCONSULTING PROMOTES COAL WATER SLURRY APPLICATION TO FUEL POWER GENERATION

PENCONSULTING PROMOTES COAL WATER SLURRY APPLICATION TO FUEL POWER GENERATION PENCONSULTING PROMOTES COAL WATER SLURRY APPLICATION TO FUEL POWER GENERATION PENConsulting has engaged in studies for the commercial application of coal water slurry (CWS) to provide clean coal based

More information

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands

SOUTH FLORIDA WATER MANAGEMENT DISTRICT. Question 13: Wetlands SOUTH FLORIDA WATER MANAGEMENT DISTRICT Question 13: Wetlands 1. The wetland responses and topographical data provided in the ADA for the 520- acre project site are conceptual in nature. The referenced

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

NPDES COMPLIANCE OF COOLING TOWERS BLOWDOWN AT POWER PLANTS WITH RECLAIMED WATER AS SOURCE WATER

NPDES COMPLIANCE OF COOLING TOWERS BLOWDOWN AT POWER PLANTS WITH RECLAIMED WATER AS SOURCE WATER NPDES COMPLIANCE OF COOLING TOWERS BLOWDOWN AT POWER PLANTS WITH RECLAIMED WATER AS SOURCE WATER Nathan Schmaus, P.E. *, Joseph Viciere, P.E., BCEE, CDM Smith CDM Smith, 1715 North Westshore Boulevard,

More information

Coal Combustion Facility Assessment Report. October 20, 2010

Coal Combustion Facility Assessment Report. October 20, 2010 Coal Combustion Facility Assessment Report October 20, 2010 Introduction Stantec Consulting Services Inc. North American Consulting Firm 10,000 Engineers, Geologists, Architects, Scientists and Technicians

More information

Information for File # PRH

Information for File # PRH Information for File # 2016-02602-PRH Applicant Corps Contact Tom Morley Paul Hauser Address 152 Baker Drive, Redwood Falls, MN 56283 E-Mail Paul.R.Hauser@usace.army.mil Phone 651-290-5357 Primary County

More information

10.0 Storm Sewer Systems

10.0 Storm Sewer Systems October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and

More information

A Preliminary Assessment of Potential Impacts of Uranium Mining in Virginia on Drinking Water Sources

A Preliminary Assessment of Potential Impacts of Uranium Mining in Virginia on Drinking Water Sources A Preliminary Assessment of Potential Impacts of Uranium Mining in Virginia on Drinking Water Sources EXECUTIVE SUMMARY January 28, 2011 ES-0 Executive Summary A large uranium reserve, estimated to be

More information

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP

More information

COAL WATER SLURRY FUEL Alternate Fuel for Thailand

COAL WATER SLURRY FUEL Alternate Fuel for Thailand COAL WATER SLURRY FUEL Alternate Fuel for Thailand Power-Gen Asia 2014 Royal Daniel Managing Director RDaniel@roe.com Contents Introduction of POWER Burns and Roe Coal Water Slurry (WS) Fuel in General

More information

The Success of Remining In Pennsylvania

The Success of Remining In Pennsylvania The Success of Remining In Pennsylvania Thomas E. Kovalchuk PA DEP Abstract The Remining Program Staff in Pennsylvania s five district offices successfully worked with the Coal Industry to cooperatively

More information

Dry Stacking of Cycloned Tailings

Dry Stacking of Cycloned Tailings Dry Stacking of Cycloned Tailings W. Lugão - VOGBR, Brazil M. Almeida - VOGBR, Brazil A. Guimarães - VOGBR, Brazil F. Magalhães - VOGBR, Brazil S. Mohallem - ARCELORMITTAL, Brazil Introduction Tailings

More information

Ms. Lynn J. Good, Chairman, President and Chief Executive Officer Duke Energy Corporation 550 South Tryon Street Charlotte, North Carolina 28202

Ms. Lynn J. Good, Chairman, President and Chief Executive Officer Duke Energy Corporation 550 South Tryon Street Charlotte, North Carolina 28202 September 20, 2017 Via Registered Mail Return Receipt Requested Ms. Lynn J. Good, Chairman, President and Chief Executive Officer Duke Energy Corporation 550 South Tryon Street Charlotte, North Carolina

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2013 SENATE BILL 729 RATIFIED BILL

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2013 SENATE BILL 729 RATIFIED BILL GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2013 SENATE BILL 729 RATIFIED BILL AN ACT TO (1) PROHIBIT RECOVERY OF COSTS RELATED TO UNLAWFUL DISCHARGES FROM COAL COMBUSTION RESIDUALS SURFACE IMPOUNDMENTS;

More information

CCR Certification: Initial Structural Stability Assessment (d)

CCR Certification: Initial Structural Stability Assessment (d) Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 47708 Submitted by AECOM 9400 Amberglen Boulevard Austin, Texas 78729 CCR

More information

UPDATE ON THE KEMPER COUNTY IGCC PROJECT Gasification Technologies Conference

UPDATE ON THE KEMPER COUNTY IGCC PROJECT Gasification Technologies Conference UPDATE ON THE KEMPER COUNTY IGCC PROJECT 2012 Gasification Technologies Conference Kemper County IGCC Overview 2x1 Integrated Gasification Combined Cycle (IGCC) 2 Transport Gasifiers 2 Siemens SGT6-5000F

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

High Bridge Combined Cycle Plant

High Bridge Combined Cycle Plant High Bridge Combined Cycle Plant Location: Down town St. Paul, on the Mississippi River Plant Description: High Bridge is a combined cycle generating facility. A combined cycle plant produces electricity

More information

What is FGD Gypsum? Presented By E. Cheri Miller Gypsum Parameters, LLC Tennessee Valley Authority (Retired)

What is FGD Gypsum? Presented By E. Cheri Miller Gypsum Parameters, LLC Tennessee Valley Authority (Retired) What is FGD Gypsum? Presented By E. Cheri Miller Gypsum Parameters, LLC Tennessee Valley Authority (Retired) Flue Gas Desulfurization (FGD) Gypsum Production Processing Disposal Markets WHAT ARE FGD SCRUBBERS?

More information

Dredge Spoils Management for Sustainable Support of U.S. Coast Guard Missions

Dredge Spoils Management for Sustainable Support of U.S. Coast Guard Missions Dredge Spoils Management for Sustainable Support of U.S. Coast Guard Missions Erick Jackson 1, Bethany Gollin 1, Spencer Zwenger 1, Holly Moore 1, Hudson Jackson 2, and Kassim Tarhini 3 1 Ensign, United

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

.. / '\1 r.;... ~ -.. ~ /\ c~v TEXAS COMMISSION ON ENVIRONMENTAL QUALITY. Protecting Texas by Reducing and Preventing Pollution.

.. / '\1 r.;... ~ -.. ~ /\ c~v TEXAS COMMISSION ON ENVIRONMENTAL QUALITY. Protecting Texas by Reducing and Preventing Pollution. B1yan W. Shaw, Ph.D., P.E., Chairman Toby Baker, Commissioner Zak Covar, Commissioner Richard A. Hyde, P.E., Executive Director.. / ~ '\1 r.;... ~ -.. ~ /\ c~v TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

More information

LANDFILL GAS CONTROL SYSTEMS: DESIGN AND CONSTRUCTION CONSIDERATIONS. Mike Bradford, P.E.

LANDFILL GAS CONTROL SYSTEMS: DESIGN AND CONSTRUCTION CONSIDERATIONS. Mike Bradford, P.E. LANDFILL GAS CONTROL SYSTEMS: DESIGN AND CONSTRUCTION CONSIDERATIONS Mike Bradford, P.E. 2 Today s Agenda SOLUTIONS YOU CAN COUNT ON. PEOPLE YOU CAN TRUST. What are we controlling? FOCUS: How do we control

More information

Annex I Lyons Ferry Hatchery Modification Plan

Annex I Lyons Ferry Hatchery Modification Plan Annex I Lyons Ferry Hatchery Modification Plan Table I1 Figure I1 Figure I2 Figure I3 Figure I4 Figure I5 Well Characteristics Lyons Ferry Hatchery Vicinity Map Lyons Ferry Hatchery Site Plan Water Supply

More information

Green Station CCR Surface Impoundment Sebree Generating Station Address: 9000 Highway 2096 Robards, Kentucky 42452

Green Station CCR Surface Impoundment Sebree Generating Station Address: 9000 Highway 2096 Robards, Kentucky 42452 Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Groundwater Monitoring System and Statistical Methods Assessment and Certification

More information

Total Clean System. Taking the lead with your Solids Control Needs!

Total Clean System. Taking the lead with your Solids Control Needs! Total Clean System Taking the lead with your Solids Control Needs! Del Tank & Filtration Systems patented TOTAL CLEAN SYSTEM is used for the removal of solids from slurries that are common in the Dredging,

More information

Sterrett Passive Treatment System Irwin Township Venango County Project Narrative

Sterrett Passive Treatment System Irwin Township Venango County Project Narrative Sterrett Passive Treatment System Irwin Township Venango County Project Narrative Project Overview Project site is located in Irwin Township Venango County. Access to the site will be off of Burns Rd 1

More information

Subject: WUP Integrated Water Use Permit (IWUP) Annual Water Conservation Progress Report (AWCPR)

Subject: WUP Integrated Water Use Permit (IWUP) Annual Water Conservation Progress Report (AWCPR) Kacie Blue Sr. Environmental Specialist Mosaic Fertilizer, LLC 13830 Circa Crossing Drive Lithia, FL 33547 Tel (813) 500-6656 Fax (813) 571-6908 E-mail: kacie.blue@mosaicco.com www.mosaicco.com June 1,

More information

Beneficial Use of Fly Ash for an Airport Safety Way Extension over a Multiple Year Project

Beneficial Use of Fly Ash for an Airport Safety Way Extension over a Multiple Year Project World of Coal Ash (WOCA) Conference - May 9-12, 2011, in Denver, CO, USA http://www.flyash.info/ Beneficial Use of Fly Ash for an Airport Safety Way Extension over a Multiple Year Project John M. Trast,

More information

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC SEPTEMBER 19, 2012 PARR AND FAIRFIELD LOCATIONS Lockhart Neal Shoals Monticello

More information

Gasification Based Biomass Cofiring Project

Gasification Based Biomass Cofiring Project National Energy Technology Laboratory Co-op Agreement No. DE-PS26-00NT 40898 Gasification Based Biomass Cofiring Project Integration of poultry litter gasification with conventional PC fired power plant

More information

Mobile Treatment Units

Mobile Treatment Units Mobile Treatment Units DE-WATERING SEDIMENT CONTROL TECHNIQUE Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils High Flow Rates High Filtration Polluted Soils [1]

More information

Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre

Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre Objectives of Strategic Environmental Review (SER) The European Bank for Reconstruction and Development

More information

EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference. D. Glen Snarr, President & CFO September 21, 2006

EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference. D. Glen Snarr, President & CFO September 21, 2006 EARTH ENERGY RESOURCES INC. Western U.S. Oil Sands Conference D. Glen Snarr, President & CFO glen.snarr@earthenergyresources.com September 21, 2006 ISSUES FACING OIL SAND PRODUCTION Issues Facing Athabasca

More information

CHAPTER 6 DESIGN AND CONSTRUCTION OF DIKES FOR CONTAINMENT OF DREDGED MATERIAL

CHAPTER 6 DESIGN AND CONSTRUCTION OF DIKES FOR CONTAINMENT OF DREDGED MATERIAL CHAPTER 6 DESIGN AND CONSTRUCTION OF DIKES FOR CONTAINMENT OF DREDGED MATERIAL 6-1. Purpose. Containment dikes are retaining structures used to form confined disposal facilities. They consist primarily

More information

Advances in Design of Landfills Over CCR Ponds and Landfills

Advances in Design of Landfills Over CCR Ponds and Landfills Advances in Design of Landfills Over CCR Ponds and Landfills Michael F. Houlihan, P.E., BCCE Geosyntec Consultants Columbia, Maryland 18 October 2012 Overview Current State of Practice Key Design Issues

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

DOWEX UPCORE Ion Exchange Resins Retrofit of Demineralizer with UPCORE System Cuts Chemical Costs by 50%

DOWEX UPCORE Ion Exchange Resins Retrofit of Demineralizer with UPCORE System Cuts Chemical Costs by 50% Case History DOWEX UPCORE Ion Exchange Resins Retrofit of Demineralizer with UPCORE System Cuts Chemical Costs by 50% Site Information Location Indiana, USA Purpose Improve short servicecycle run lengths

More information

Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements

Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements 1 Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements 2 COAL RESOURCE Indonesia has large resources of lower heating value subbituminous coal the resources are

More information

ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION

ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION DURR SYSTEMS, INC. CLEAN TECHNOLOGY SYSTEMS ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION Karl Walby Senior Key Account Manager 734-536-3423, karl.walby@durrusa.com ICAC

More information

Introduction. Upstate New York Power Producers Response to New York Energy Highway Request for Information

Introduction. Upstate New York Power Producers Response to New York Energy Highway Request for Information Introduction The bondholders of AES Eastern Energy are preparing to take ownership of the Somerset and Cayuga power plants following the parent company filing for bankruptcy protection on December 30,

More information