1 Date ISDS Prepared/Updated: 01/26/2011 I. BASIC INFORMATION A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC6042 Country: South Asia Project ID: P Project Name: India-Nepal and India-Bangladesh Cross Border Transmission and Trade Project Task Team Leader: Raghuveer Y. Sharma Estimated Appraisal Date: January 25, Estimated Board Date: March 29, Managing Unit: SASDE Lending Instrument: Adaptable Program Loan Sector: Power (60%);Renewable energy (40%) Theme: Analysis of economic growth (67%);Climate change (33%) IBRD Amount (US$m.): 0.00 IDA Amount (US$m.): GEF Amount (US$m.): 0.00 PCF Amount (US$m.): 0.00 Other financing amounts by source: BORROWER/RECIPIENT Financing Gap B. Project Objectives [from section 2 of PCN] The objective of the Proposed India-Nepal Cross-Border Transmission Project is to enable electricity trade to meet deficits in Nepal and export electricity to India along commercial principles. C. Project Description [from section 3 of PCN] The Proposed Project would comprise, design, construction and operation of: a) In India, a 100 km 400 kv double circuit transmission line between Muzaffarpur and the Nepal border to be owned by a joint venture comprising Power Grid Corporation of India (PGCIL), Sutlej Jal Vidyut Nigam, IL&FS (all from India) and Nepal Electricity Authority (NEA); b) In Nepal, a 40 kilometer 400 kv double circuit transmission line and concomitant substation at Dhalkebar to be owned a joint venture of NEA, IL&FS and PGCIL; and

2 c) In Nepal, a 325 km 400 kv double circuit Hetouda-Duhabi transmission line to be owned and operated by Nepal Electricity Authority (NEA). These transmission lines would be operated as part of the India-Nepal synchronous system, for which PGCIL and NEA will be responsible. The construction of sections of the Hetouda-Duhaby line is part of the Butwal-Dhalkebar- Duhabi 465 km transmission system and would enable the project to deliver the imported electricity to load centers; and bring the exportable electricity to Dhalkebar substation. Part of this additional line, Hetauda-Bharatpur (70 km) section is already under implementation with World Bank financing; and for Bharatpur-Bardghat (70 km) section, World Bank financing has been secured. D. Project location (if known) The most extensive portion of the project # the Hetauda-Dhalkebar-Duhabi 400 KV transmission line, would pass through southern Nepal, mostly Terai flat lands, but also substantial stretches would pass through the Siwalik Hills. The Koshi River, north of its entry into India, would be the most significant water body to be crossed. While the land-use along the line is most likely to be agriculture in the eastern portion, it would also traverse several stretches of forests in the western portion. The Dhalkebar-Bittamod-Muzaffarpur (in India) would pass through almost flat lands with few known sensitive environmental receptors. The proposal for the 400 KV substations would include a new site at Duhabi/Inurawa, a pre-identified site in Hetauda, as well as augmentation or new location of the Dhalkebar. On the India side, the existing substation at Muzaffarpur would be used to transfer power between Nepal and India. E. Borrower s Institutional Capacity for Safeguard Policies [from PCN] NEA has some recent experience of implementing environmental management for transmission projects conforming to the World Bank#s safeguards policies. It is currently implementing its largest project with Bank assistance # construction of 220 KV lines and substations in the Bharatpur-Bardaghat, Bharatpur-Hetauda, and Khimti-Dhalkebar lines, some of which are in the same area as the proposed project. The increased emphasis on the rejuvenation of the power sector in Nepal has meant that the capacity of the NEA#s environmental and social team is being stretched. This would be strengthened as part of this project preparation to include 400 KV transmission lines and substations, which is being attempted for the first time to boost power transfer and trade with India # importing about 150 MW for the short term and then connecting with the hydro projects being developed in Nepal for export after these come on-stream. F. Environmental and Social Safeguards Specialists Mr Chaohua Zhang (SASDS) Mr Gaurav D. Joshi (SASDI) II. SAFEGUARD POLICIES THAT MIGHT APPLY Safeguard Policies Triggered Yes No TBD Environmental Assessment (OP/BP 4.01) The project will involve construction of new 400 KV transmission lines and substations. Though transmission has few direct adverse impacts in the operation stage, planning and

3 Safeguard Policies Triggered Yes No TBD construction of these facilities could require mitigation/enhancement measures to ensure that there is little adverse impact of these important facilities. Impacts pertaining to alignment/route selection across sensitive stretches like forests, siting of sub-stations and ensuring appropriate drainage in the vicinity of their locations, occupational health and safety of construction workers as well as staff, would be some of the key areas of attention. Natural Habitats (OP/BP 4.04) The current proposals for the lines do not pass through any recognized critical natural habitats. However, the during the project preparation phase the assessment will specifically verify, on the stretches through the forest areas in the western portion and across the Koshi river in the east, the extent to which any natural habitats, not recognized currently as critical, may get impacted. Forests (OP/BP 4.36) A substantial portion of the main East-West (Duhabi-Hetauda) line is likely to pass through the Forest Areas in the Siwaliks. The project will identify the extent of impacts, suggest adequate mitigation measures in line with GoN rules, and Bank policy, and put in place appropriate institutional arrangements to ensure their timely implementation. Pest Management (OP 4.09) Physical Cultural Resources (OP/BP 4.11) Since civil works are involved, impacts on #chance finds# at work sites are likely impacts that would have to be managed. Adverse impacts on locally important cultural properties would be examined, if any, for appropriate mitigation during planning and implementation stages. Indigenous Peoples (OP/BP 4.10) TBD Involuntary Resettlement (OP/BP 4.12) TBD Safety of Dams (OP/BP 4.37) Projects on International Waterways (OP/BP 7.50) Projects in Disputed Areas (OP/BP 7.60) Environmental Category: A - Full Assessment III. SAFEGUARD PREPARATION PLAN A. Target date for the Quality Enhancement Review (QER), at which time the PAD-stage ISDS would be prepared: 02/01/2011 B. For simple projects that will not require a QER, the target date for preparing the PAD-stage ISDS: N/A

4 C. Time frame for launching and completing the safeguard-related studies that may be needed. The specific studies and their timing 1 should be specified in the PAD-stage ISDS. Detailed Environmental Impacts Assessment (EIA), called Initial Environmental Examination or IEE in Nepal, and concomitant Social Impact Assessment (SIA) which would include the mitigation and management plans would be prepared before appraisal of the proposed project. Under the on-going Power Development Project, a transmission master planning exercise will be undertaken, which will also have an environmental and social component. The results of this study would also help streamline the procedures for environmental management and social development within the NEA with a view to have its own ESPP as the project progresses. IV. APPROVALS Signed and submitted by: Task Team Leader: Mr Raghuveer Y. Sharma 01/24/2011 Approved by: Regional Safeguards Coordinator: Mr Sanjay Srivastava 01/25/2011 Comments: The PCN stage ISDS is cleared with Category A. Please follow the disclosure requirements and submit the same through the operations portal. Sector Manager: Mr Malcolm Cosgrove-Davies 01/24/2011 Comments: 1 Reminder: The Bank s Disclosure Policy requires that safeguard-related documents be disclosed before appraisal (i) at the InfoShop and (ii) in-country, at publicly accessible locations and in a form and language that are accessible to potentially affected persons.

5

India-Nepal and India-Bangladesh Cross Border Transmission and Trade Project Region. Bangladesh-India-Nepal Sector

India-Nepal and India-Bangladesh Cross Border Transmission and Trade Project Region. Bangladesh-India-Nepal Sector Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6310 (The report # is

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated:

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC1974. Date ISDS Prepared/Updated: 02/06/2006 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC1974. Date ISDS Prepared/Updated: 02/06/2006 I. BASIC INFORMATION. A. Basic Project Data Date ISDS Prepared/Updated: 02/06/2006 I. BASIC INFORMATION A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC1974 Country: Africa Project ID: P094916 Project Name: WAPP

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC4437. Date ISDS Prepared/Updated: 08/18/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC4437. Date ISDS Prepared/Updated: 08/18/2009 I. BASIC INFORMATION. A. Basic Project Data Date ISDS Prepared/Updated: 08/18/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC4437 Country: Papua New Guinea Project ID: P116521 Project

More information

C. Project Description [from section 3 of PCN] The proposed project would comprise of the following three components:

C. Project Description [from section 3 of PCN] The proposed project would comprise of the following three components: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 02/17/2012 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Report No.: 38582 Date ISDS Prepared/Updated: 16 January 2007 I. BASIC INFORMATION A.

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832 Country: Uruguay Project ID: P110965 Project Name: Sustainable

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3947. Date ISDS Prepared/Updated: 04/20/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3947. Date ISDS Prepared/Updated: 04/20/2009 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 04/20/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3763. Date ISDS Prepared/Updated: 07/11/2008 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3763. Date ISDS Prepared/Updated: 07/11/2008 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 07/11/2008 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC6530. Date ISDS Prepared/Updated: 03/14/2012 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC6530. Date ISDS Prepared/Updated: 03/14/2012 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 03/14/2012 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 07/27/2011 1. Basic Project Data Original

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2668. Date ISDS Prepared/Updated: 02/09/2007 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2668. Date ISDS Prepared/Updated: 02/09/2007 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 02/09/2007 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: October 21, 2004 I. BASIC INFORMATION A. Basic Project Data Country: Western Africa Project Name: Africa Emergency Locust Project

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/24/2007 INTEGRATED SAFEGUARDS DATASHEET

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli Transmission Project

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli Transmission Project Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Kabeli Transmission Project Report No.: AB6289 Region SOUTH ASIA Sector Power (50%);Renewable energy (50%) Project ID P112893 Borrower(s)

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5623. Date ISDS Prepared/Updated: 09/22/2010 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5623. Date ISDS Prepared/Updated: 09/22/2010 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 09/22/2010 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

I Managing Unit: EASRE

I Managing Unit: EASRE Date ISDS PreparedNpdated: 08/06/07 I. BASIC INFORMATION INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE A. Basic Project Data I Country: Indonesia I Project ID: PI04022 Project Name: Makassar Landfill

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 12-Feb-2014

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: June 10, 2004 I. BASIC INFORMATION A. Basic Project Data Country: Brazil Project Name: Brasilia Environmentally Sustainable Pro

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5229. Date ISDS Prepared/Updated: 04/15/2010 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5229. Date ISDS Prepared/Updated: 04/15/2010 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 04/15/2010 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated: 04/13/2006 INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Report No.: AC2194 1. Basic Project Data Country: Burkina Faso Project ID: P098956 Project Name: Post-Primary

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE. I. Basic Information Date prepared/updated: 07/13/2009 Report No.: 49497

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE. I. Basic Information Date prepared/updated: 07/13/2009 Report No.: 49497 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated:

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: 47875 INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: February 6, 2008 I. BASIC INFORMATION A. Basic Project Data Country: Brazil Project ID: P096337 Additional Project

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 23-Jul-2014

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 09/26/2008 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: November 14, 2003 I. BASIC INFORMATION A. Basic Project Data Country: China Project Name: LIUZHOU ENVIRONMENT MANAGEMENT PROJECT

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 10/28/2009 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/14/2011 1. Basic Project Data Original

More information

Financing (In USD Million) Financing Source

Financing (In USD Million) Financing Source Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 05-Aug-2012 I. BASIC INFORMATION 1. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Date prepared/updated: January 13, 2017 Report No.:

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Date prepared/updated: January 13, 2017 Report No.: INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Date prepared/updated: January 13, 2017 Report No.: 112247 I. Basic Information 1. Basic Project Data Country: Republic of Zambia Project ID: P157943 Additional

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: September 13, 2004 I. BASIC INFORMATION A. Basic Project Data Country: Mali Project Name: Second Transport Sector Project Estimated

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA638 Project Name Kali Gandaki A Hydropower Plant Rehabilitation Project (KGAHPRP) (P132289) Region SOUTH ASIA Country Nepal Sector(s)

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 06/05/2006 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated: 03/08/2007 INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Report No.: AC2566 1. Basic Project Data Country: Lesotho Project ID: P088544 Project Name: Private

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: August 2, 2003 I. BASIC INFORMATION A. Basic Project Data Country: Peru Project ID: P082625 Project Name: Vilcanota Valley Task

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2501. Date ISDS Prepared/Updated: 03/01/2007 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2501. Date ISDS Prepared/Updated: 03/01/2007 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 03/01/2007 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB6384 NEPAL-INDIA

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/03/2006 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 13-Dec-2012

More information

INTEGRATED SAFEGUARDS DATA SHEET INITIATION/CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET INITIATION/CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET INITIATION/CONCEPT STAGE Report.: 121880 Date ISDS Prepared/Updated: 4 December 2017 Public Disclosure Authorized Public Disclosure Authorized

More information

INTEGRATED SAFEGUARDS DATA SHEET. Costa Rica FCPF READINESS PREPARATION GRANT CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET. Costa Rica FCPF READINESS PREPARATION GRANT CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET Costa Rica FCPF READINESS PREPARATION GRANT CONCEPT

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated:

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 04-Dec-2014

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 05/18/2006 INTEGRATED SAFEGUARDS DATASHEET

More information

Report No.: ISDSA1037

Report No.: ISDSA1037 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 0 o INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Date ISDS Prepared/Updated: 07-May-2015

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 30-May-2013

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: PIDC32071 Project Name 24x7

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 23-Jul-2012

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 07/15/2015 INTEGRATED SAFEGUARDS DATASHEET

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5136 Project Name

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5136 Project Name PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5136 Project Name Luhri Hydro Electric Project Region SOUTH ASIA Sector Power (50%); Renewable energy (50%) Project ID P102843 Borrower(s)

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: ISDSC13230 Date ISDS Prepared/Updated: 13-Jul-2015 Date ISDS Approved/Disclosed: 14-Jul-2015 I. BASIC INFORMATION A. Basic Project Data Country:

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.:47622 Project Name Rural

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 05/09/2011 1. Basic Project Data Original

More information

Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS)

Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS) Public Disclosure Authorized The World Bank Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet Identification / Concept Stage (ISDS) Concept Stage Date ISDS Prepared/Updated:

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.:45460 Project Name Rural Electrification and Transmission Interconnection Project (RETP) Region EAST ASIA AND PACIFIC Sector Energy Project ID

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 05/29/2008 INTEGRATED SAFEGUARDS DATASHEET

More information

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date prepared/updated: 10/09/12 I. Basic Information INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5868. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5868. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Report No.: 89787 Date prepared/updated: July 28, 2014 I. Basic Information 1. Basic

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC4308. Date ISDS Prepared/Updated: 01/11/2010 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC4308. Date ISDS Prepared/Updated: 01/11/2010 I. BASIC INFORMATION. A. Basic Project Data INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC4308 Date ISDS Prepared/Updated: 01/11/2010 I. BASIC INFORMATION A. Basic Project Data Country: Africa Project ID: P113138 Project Name: Lake

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: April 12, 2006 1. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 10/14/2010 INTEGRATED SAFEGUARDS DATASHEET

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet (ISDS) Section I Basic Information Date ISDS Prepared/Updated:

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE,2 Date ISDS Prepared/Updated: 22-Jul-2015 Report.: ISDSC13452 Date ISDS Approved/Disclosed: 06-Aug-2015 Public Disclosure Authorized

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 23-Mar-2015 Report No.: ISDSC 12226 Date ISDS Approved/Disclosed: 06-Apr-2015 Public Disclosure Authorized

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Report No.: ISDSA3140

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Report No.: ISDSA3140 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET Date ISDS Prepared/Updated: July 30, 2013 I. BASIC INFORMATION

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated: 11/14/2009 Report.: AC4826 1. Basic Project Data Country: Sudan Project ID: P111061 Project Name: Southern Sudan

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 28-Jul-2013

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 02-Nov-2011 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 05/29/2007 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 29-Sep-2015 Report No.: ISDSC14538 Date ISDS Approved/Disclosed: 15-Oct-2015 Public Disclosure Authorized

More information

Safeguard Requirements And the Framework Process

Safeguard Requirements And the Framework Process Safeguard Requirements And the Framework Process The World Bank Europe & Central Asia Region Biskek,Tblisi March/April 2008 1 Role of Bank and Borrower Bank Screens and Sets EA Category Advises Borrower

More information

Terms of Reference. Conflict Management and Mitigation for Energy Projects in Nepal

Terms of Reference. Conflict Management and Mitigation for Energy Projects in Nepal Terms of Reference Conflict Management and Mitigation for Energy Projects in Nepal Background Nepal is a land-locked country that is facing major development challenges. With 27.8 million people, Nepal

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 11-Jun-2014 Report No.: ISDSC9465 Date ISDS Approved/Disclosed: 09-Dec-2014 Public Disclosure Authorized

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 10-Feb-2015 Report No.: ISDSC 141 Date ISDS Approved/Disclosed: 18-Feb-2015 Public Disclosure Authorized

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE,2 Date ISDS Prepared/Updated: 03-Sep-2015 Report No.: ISDSC14552 Date ISDS Approved/Disclosed: 04-Sep-2015 Public Disclosure

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date PreparedlUpdated: July 272009 A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE. 10-Oct-2014

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE. 10-Oct-2014 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: I BASIC INFORMATION A Basic Project Data INTEGRATED SAFEGUARDS

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 11/15/2010 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Project ID:

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Project ID: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Public Disclosure Copy Date ISDS Prepared/Updated: 05-Mar-2014

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 12-Nov-2014 Report No.: ISDSC9631 Date ISDS Approved/Disclosed: 06-Dec-2014 Public Disclosure Authorized

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized o Date ISDS Prepared/Updated: 19-Jan-2016 INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 03/21/2011 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 11-Jul-2014

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA982. Project Name. Region. Country

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA982. Project Name. Region. Country Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA982 Project Name Electric

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA Project Name. Region. Country

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA Project Name. Region. Country Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA54793 Project Name

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2388. Date ISDS Prepared/Updated: 07/12/2006 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2388. Date ISDS Prepared/Updated: 07/12/2006 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 07/12/2006 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 01/21/2011 INTEGRATED SAFEGUARDS DATASHEET

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 23-Mar-2014 INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 20-Apr-2015

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Peru Second Rural Electrification

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Peru Second Rural Electrification Project Name Region Sector Project ID GEF Focal Area Global Supplemental ID Borrower(s) Implementing Agency PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Peru Second Rural Electrification Latin America

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3842. Date ISDS Prepared/Updated: 03/09/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3842. Date ISDS Prepared/Updated: 03/09/2009 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 03/09/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4319 WAPP APL 3 (1 ST PHASE INTER-ZONAL TRANSMISSION HUB) Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4319 WAPP APL 3 (1 ST PHASE INTER-ZONAL TRANSMISSION HUB) Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4319 WAPP

More information

Integrated Safeguards Data Sheet (Initial)

Integrated Safeguards Data Sheet (Initial) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet (Initial) Report No: AC124 Section I - Basic Information

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Project Name CBF Sidi Daoud Wind Farm

More information

Integrated Safeguards Data Sheet (Initial)

Integrated Safeguards Data Sheet (Initial) THE WORLD BANK GROUP U---- _ InfoShop Date Prepared/Updated: 02/24/2003 Section I - Basic Information A. Basic Project Data Country: BRAZIL Project: RF Support of Scientific Research for the Amazon II

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: PIDC54374 Project Name National

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: PIDC779 Project Name WAPP

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Date prepared/updated: 09/10/2013 / 10/05/2013

More information