USDA: Lake Waco/Bosque River Initiative. Future Growth Projections for the Lake Waco/Bosque River Watershed

Size: px
Start display at page:

Download "USDA: Lake Waco/Bosque River Initiative. Future Growth Projections for the Lake Waco/Bosque River Watershed"

Transcription

1 USDA: Lake Waco/Bosque River Initiative Future Growth Projections for the Lake Waco/Bosque River Watershed Nancy Easterling WP0005 May 2000 Texas Institute for Applied Environmental Research Tarleton State University Box T0410 Tarleton Station Stephenville, Texas FAX

2 Acknowledgements The research on which this report is based was financed by the U.S. Department of Agriculture, Natural Resources Conservation Service. Dr. Larry Hauck, Assistant Director of Research at TIAER, provided guidance and insight in preparing this document. Representatives from cities in the Bosque River watershed met on several occasions to review material needed for this report and provided important feedback. Don Gosdin, Artist Illustrator at TIAER, prepared the map in Figure 1. Tommie Nielsen, former Research Assistant at TIAER, calculated the historical number of cows in Erath and Hamilton counties using milk production data. 2

3 Abstract The Texas Institute for Applied Environmental Research (TIAER) completed future growth projections for the USDA Lake Waco-Bosque River Initiative. A twenty year planning horizon was selected as appropriate for future growth estimates of potential pollution sources in this central Texas watershed. Sectors for which future growth was estimated include wastewater treatment plants (WWTPs), dairy farms, urban growth, and row crops. These sectors represent the watershed s major potential contributors of phosphorus, the pollutant of concern in the Bosque River watershed. Texas Water Development Board estimates of future population growth served as the basis for growth projections of WWTP discharge and urban population. Regression equations based on historical milk production records enabled growth projections for cows in the watershed. Estimates of row crop acreage were based on geographic information system analysis of changes in historical thematic satellite images. Regulatory limits exist for WWTP effluent and dairy cow numbers. The currently permitted maximum amounts of wastewater effluent and dairy cows in the watershed were found to be greater than growth estimates for the year Urban population growth is estimated to increase by 31 percent while row crop production is not expected to increase by the year To accommodate additional growth in the watershed, notably in the municipal and industrial areas, an allotment of 10 percent of the current WWTP discharge is projected. These projections will be used in the modeling efforts and other analyses for the USDA Lake Waco/Bosque River Initiative. 3

4 4

5 Contents Future Growth Projections for the Lake Waco/Bosque River Watershed Introduction Planning Horizons for Future Growth Projections Urban NPS/Population Projections Wastewater Treatment Plant Effluent Projections Projections of Dairy Cow Population in the Bosque River Watershed Method Used to Determine Historical BRW Cow Numbers Method Used to Estimate Current BRW Cow Population Method Used to Predict BRW Cow Numbers Projections of Row Crop Production in the Bosque River Watershed Projections of Unallocated Municipal/Industrial Contributions to the Bosque River Watershed Summary References Appendix A. City of Waco Population and WWTP Projections for the BRW Area Appendix B. WWTP Effluent Projection Calculations Appendix C. Additional Details of Determining Cow Numbers

6 Future Growth Projections for the Lake Waco/Bosque River Watershed 6

7 Tables Table 1: Population Projections, Revisions and Projected Growth Table 2: Daily Average BRW WWTP Discharge Limits Table 3: Estimated Number of Cows in Erath and Hamilton Counties, Table 4: Estimated Number and Annual Growth Rate of BRW Cows in Erath and Hamilton Counties, Table 5: Estimated Number of BRW Cows, Table 6: Projected BRW Cow Numbers Based on Regression Equation Table 7: Changes in BRW Row Crop Acres, 1977 to Table 8: Summary of Future Growth Projections for the BRW Table A-1: WWTP Effluent Discharge Projections for the City of Waco Located in the BRW Table B-1: Population Growth Rate Calculations Table B-2: WWTP Discharge Projections Table C-1: Figures Used in Estimating the Number of BRW Cows in

8 Future Growth Projections for the Lake Waco/Bosque River Watershed 8

9 Figures Figure 1: The Bosque River Watershed and Lake Waco Figure 2: Graph and Regression Equation of Estimated BRW Cow Numbers, Figure 3: Graph and Regression Equation of Estimated BRW Cow Numbers,

10 Future Growth Projections for the Lake Waco/Bosque River Watershed 10

11 Future Growth Projections for the Lake Waco/Bosque River Watershed Introduction The North Bosque River, which flows approximately 125 miles from Erath county, Texas, to Lake Waco, has been included for several years on the Clean Water Act section 303(d) list of impaired water bodies. The river is comprised of two segments, 1226 and 1255, which have been classified by the Texas Natural Resource Conservation Commission (TNRCC). Both segments are cited for nutrient enrichment and other pollutants. The Texas Institute for Applied Environmental Research (TIAER) at Tarleton State University is working with the Bosque River Advisory Committee (BRAC) to consider control or reduction in nutrient loadings in the North Bosque River and to Lake Waco. The research and stakeholder process is occurring through a USDA-funded project entitled the Lake Waco/Bosque River Initiative (USDA Initiative). Factors that can contribute pollutant loads to the system are examined in the USDA Initiative. An important, though difficult, factor in assessments and allocations of nutrient loadings is future contributions. Future contributions are typically estimated by observing historical growth trends in sources and projecting them into the future. Projections of future growth are by definition inexact, with the more distant projections typically representing less accurate estimates. Projections of 20 years are often made, which is the horizon used for future growth projections for the USDA Initiative. Due to concerns about the holistic nature of a watershed s response to environmental influences, the BRAC decided to include the entire Bosque River watershed (BRW) in the future growth projections. This added segment 1246 (the South and Middle Bosque watersheds) and segment 1225 (Lake Waco). Figure 1 shows the cities, major rivers and boundaries of the BRW. The USDA Initiative addresses elevated levels of phosphorus. Data from years of research in the Bosque River watershed indicate that phosphorus is the nutrient that limits (or controls) growth of aquatic plants in the Bosque River watershed. Long term TIAER studies indicate that orthophosphate phosphorus (PO 4 -P) has a stronger statistical relationship with aquatic plant growth in the North Bosque River than does total phosphorus, the other common form of phosphorus measured in the Bosque River system. 11

12 Future Growth Projections for the Lake Waco/Bosque River Watershed Anthropogenically derived sources of PO 4 -P in the watershed include urban nonpoint source runoff, wastewater treatment plants (WWTPs), dairy operations, and row crop production. Effluent from manufacturing and industrial facilities in the watershed is received and treated by local WWTPs. No industrial producers are permitted to independently discharge wastes into the watershed. In addition to wastewater treatment plants and dairies, four other facilities in the Bosque River watershed hold TNRCC permits to dispose of wastes. These facilities include a limestone manufacturing facility, a milk products plant, a small mobile home park and a livestock auction barn. Because these four facilities have no discharge permits and do not represent major potential sources of phosphorus, they are not included in the projections of future contributions of phosphorus. The purpose of this paper is to project future growth of anthropogenic sources that are being considered in phosphorus loading considerations within the USDA Initiative. The future growth projections will be used in the computer model simulations as part of the evaluation process of the project. The conclusions presented in this paper have been agreed to by the BRAC. Figure 1: The Bosque River Watershed and Lake Waco 12

13 Future Growth Projections for the Lake Waco/Bosque River Watershed Future Growth Projections Planning Horizons for Future Growth Projections To provide a basis for future growth projections, a planning horizon must be determined. Often a 20-year planning horizon is used by TNRCC in their wasteload (point source) allocation process. The planning horizon should encompass a reasonable period in which to achieve the desired endpoints (in-stream water quality) and provide ample allowance for future growth to provide for protection of in-stream designated uses in the future. For the USDA Initiative, a 20-year planning horizon was selected. The bases of this 20-year time frame are the following: (1) reduction of elevated phosphorus levels on fields receiving dairy wastes can be a multi-year process and 20 years should provide for substantial reductions in soil phosphorus on these application fields, and (2) this time period represents a reasonable and often used compromise between a projection extending too far into the future and a shortsighted planning horizon which is invalidated by future growth before the endpoints are achieved. Urban NPS/Population Projections Estimates of future population are used to predict urban nonpoint source (NPS) pollution as part of computer modeling efforts. The Texas Water Development Board (TWDB) estimates future population growth for cities and communities throughout Texas in order to predict changes in demand for water. A detailed description of the process used by TWDB to estimate population growth can be found at The mayor, utilities director, and/or other representatives from each of the eight BRW cities were asked to review and provide input on the TWDB population projections. The cities of Clifton and Stephenville submitted revised projections to the BRAC; these revisions have also been submitted to the TWDB. The City of Hico submitted revised population projections to the BRAC based on growth in number of electric meter connections. The City of Waco, only part of which is located within the BRW, provided growth estimates for the BRW portion of its population. Table 1 shows the population estimates for BRW cities for the years 2000, 2010 and

14 Future Growth Projections for the Lake Waco/Bosque River Watershed Table 1: Population Projections, Revisions and Projected Growth City 2000 Populationa 2010 Population 2020 Population Growth Rate ( ) Cliftonb 3,557 3,961 4,268 20% Crawford % Hicob 1,380 1,400 1,417 3% Iredellc % McGregor 5,228 5,670 5,845 12% Meridian 1,504 1,603 1,791 19% Stephenvilleb 16,060 18,638 21,103 31% Valley Mills 1,090 1,107 1,118 3% Wacob,d 34,494 40,965 47,435 38% TOTAL 64,413 74,505 84,190 31% a. Projections were developed by TWDB, except as noted b. Estimates were provided by city representatives c. Estimates for Iredell, not available from TWDB, are based on 1998 Texas Almanac population and TWDB s non-urban growth rate for Bosque county. d. Estimates for the part of Waco within the Lake Waco drainage area; additional details of Waco s population projection are found in Appendix A. Wastewater Treatment Plant Effluent Projections TNRCC records indicate that only municipal wastewater treatment plants (WWTPs) are permitted to discharge in the Bosque River watershed; no industrial facilities hold permits to discharge wastes in the BRW. Estimates of future WWTP effluent are used to predict point source pollution as part of computer modeling efforts. WWTPs are limited by regulation as to the volume of effluent that may be discharged daily and the concentration of key constituents in that effluent. Wastewater discharge is related to the number of people and industrial and manufacturing entities that use the system. The population projections presented in Table 1 were used to estimate the changes in wastewater discharge in the BRW. WWTP effluent from the city of Waco is discharged downstream of BRW and Lake Waco into the Brazos River basin. Waco s effluent thus does not impact the amount of WWTP effluent in the BRW. Several residential developments are expected within the City of Waco s jurisdiction, but are located outside present wastewater collection systems. The City of Waco has already committed funding to connect these planned developments to collection systems that will transport the wastewater out of the 14

15 Future Growth Projections for the Lake Waco/Bosque River Watershed Future Growth Projections watershed to the treatment facility for the City of Waco. Presently it is unlikely that package wastewater treatment plants will be required at these developments. If package wastewater treatment plants are required, they will not be used beyond the year 2002, according to City representatives. Details of potential package WWTPs for Waco are presented in Appendix A. The TNRCC issues permits to WWTPs, designating a daily average effluent discharge limit. Table 2 shows the daily average discharge limit, in million gallons per day (MGD), for each of the eight permitted WWTPs in the BRW. Each WWTP submits to the TNRCC monthly discharge data, including an average of the measured daily discharges for that month. The monthly averages of daily discharges for each WWTP were averaged for the period January 1997 through December 1998 to obtain a daily average discharge for each WWTP. Daily average discharges are shown beside the TNRCC permit flow limit in Table 2. Table 2: Daily Average BRW WWTP Discharge Limits Recent Average Discharges and Estimated 2010 and 2020 Discharges WWTP Facility Daily Avg Discharge Limita (MGD) Recent Daily Average Dischargeb (MGD) Estimated Discharge in 2010 c (MGD) Estimated Discharge in 2020c (MGD) 2020 Discharge as Portion of Discharge Limit Cliftond % Crawford % Hico % Iredell % McGregor % Meridiane % Stephenville % Valley Mills % TOTALf % a. From TNRCC wastewater discharge permits b. Based on self-reporting flow data from 1997 to 1998 c. Based on estimates of population growth rates in Table 1, applied beginning in d. Clifton s discharge limit represents a requested amendment from the current MGD e. Meridian expects a large increase in industrial use f. Total does not include a potential WWTP for Cranfills Gap, which is not permitted and which would impact the 2020 total MGD by less than one percent; see Appendix B for more details The percentage growth projected for each city (Table 1) was applied to that city s wastewater treatment plant effluent, except as noted, in order to predict WWTP efflu- 15

16 Future Growth Projections for the Lake Waco/Bosque River Watershed ent discharge in 2010 and Appendix B contains details of the growth projections for wastewater treatment plant effluent. The TWDB currently projects decreased water use throughout Texas, especially for industrial water users, due to the development and increasing use of water saving devices. Basing future WWTP effluent on changes in water use, in addition to future population growth, would have produced lower effluent projections. In order to allow sufficient growth potential for WWTPs serving BRW municipalities, projections of future WWTP effluent were based on percentage increases in population. City representatives reviewed the WWTP projections and provided input. The city of Clifton is in the process of building a new wastewater treatment plant, and the figures for Clifton reflect the proposed permit limits. The city of Meridian anticipates industrial growth in their region, and therefore had larger estimates than those based on population increases alone. The WWTP effluent projections for 2010 and 2020 are shown in Table 2. In addition, the discharge projected for 2020 is shown in Table 2 as a percentage of the current regulatory discharge limit. For future effluent projections, the greater of the projected WWTP discharge and the permitted WWTP discharge limit should be used. According to these projections, none of the WWTPs in the BRW will exceed their TNRCC permit limit by Therefore, the WWTP effluent projection used will be each WWTP s permitted daily average discharge, which totals MGD. Projections of Dairy Cow Population in the Bosque River Watershed Dairy farming is a major industry in the BRW, potentially contributing a large proportion of the nutrient loading to Lake Waco. Change in the number of dairy cows in the watershed constitutes an important part of future growth projections. Projection of the future BRW dairy cow population is based on the assumption that future growth will proceed at the same rate as previous growth. Analysis of historical cow numbers can be used to produce a regression equation which describes the past growth rate and can be used to predict future growth. The projection estimate requires the following basic steps: (a) determination of historical numbers of BRW cows, (b) determination of the current number of BRW cows, (c) calculation of a regression equation based on historical cow numbers, and (d) application of the equation to the current number of BRW cows for the desired number of years in the future. Neither the historical BRW cow numbers nor the current BRW cow population are available. Estimates of these two data sets were derived from existing data, as explained below. 16

17 Future Growth Projections for the Lake Waco/Bosque River Watershed Future Growth Projections Method Used to Determine Historical BRW Cow Numbers The best available source of long term data on BRW cow numbers is milk production data published monthly in The Milk Market Administrators Report. Cow numbers were estimated by dividing the total pounds of milk produced in the month by the average pounds produced per cow per day (55 pounds of milk per cow per day, according to The Milk Market Administrators Report guidelines) then dividing by the number of days in the month. This approximates the number of lactating cows, which is multiplied by the commonly accepted value of 1.2 to approximate total herd size (lactating and dry cows). See Appendix C for details on this calculation. The cow numbers calculated for each month were averaged to produce the mean number of cows for each year of record. It should be noted that the number of cows on individual dairies fluctuates from day to day and season to season. Therefore, a goal of determining exact cow numbers is not appropriate and is superseded by efforts to estimate average numbers of cows. Milk production data are recorded by county rather than by watershed. Because all but two BRW dairies are located in Erath and Hamilton counties, milk production figures for those two counties were used to estimate the cow population in past years. While reliable milk production data are available for Erath county since at least 1980, complete data for Hamilton county are available only since For this study, 1998 is the latest year with a complete set of data. Table 3 shows the estimated number of cows in both counties, as calculated from milk production data for the period of interest. Table 3: Estimated Number of Cows in Erath and Hamilton Counties, Year # Cowsa Year # Cowsa , , , , , , , , , , , , , ,939 a. Based on milk production data from The Milk Market Administrators Report Many Erath and Hamilton dairies are located outside the BRW in adjacent watersheds, so it was necessary to determine the percentage of the counties cows located within the BRW. This was accomplished by dividing the estimated number of cows in the watershed in 1998, excluding the two dairies outside Erath and Hamilton counties, by the 1998 total for both counties. The number of BRW cows in Erath and Hamilton counties during 1998 was estimated, as explained in the next section, to be 17

18 Future Growth Projections for the Lake Waco/Bosque River Watershed 39,938. This number was divided by the 1998 total number of Hamilton and Erath county cows (97,939, shown in Table 3) to yield the percentage of Hamilton and Erath county cows which are located in the BRW (40.8 percent). While this approach assumes that cows in the BRW represent a constant portion of Erath and Hamilton county cows for each year, there exist insufficient data to make any other assumption. The calculated percentage (40.8 percent) was multiplied by the number of Erath and Hamilton cows for each year of record (from Table 3) to estimate historical numbers of BRW cows in Erath and Hamilton counties. These yearly estimates are presented in Table 4, with the annual growth rate in number of cows. Table 4: Estimated Number and Annual Growth Rate of BRW Cows in Erath and Hamilton Counties, Year Erath & Hamilton Countiesa (# cows) BRW (# cows)b Annual Growth Rate ,733 12, ,648 13,721 6% ,049 16,332 19% ,147 20,857 28% ,068 24,087 15% ,474 27,107 13% ,775 27,638 2% ,412 29,529 7% ,437 33,209 12% ,050 37,537 13% ,644 38,595 3% ,289 40,896 6% ,290 39,266-4% ,939 39,938 2% a. Based on data from The Milk Market Administrator s Report b. Calculated from estimated percentage of Erath and Hamilton cows in the BRW in 1998 (40.8%) Method Used to Estimate Current BRW Cow Population Estimating the current number of cows in the BRW required combining data from different sources. First, all operating dairies in the watershed were identified using a list 18

19 Future Growth Projections for the Lake Waco/Bosque River Watershed Future Growth Projections of dairy addresses compiled by the Texas Department of Health (TDH) for each county, a detailed map of the watershed boundaries, and a considerable amount of ground-truthing. The resulting list of BRW dairies was used to search recent TNRCC dairy inspection reports, which include the actual number of cows present on the inspected dairy. Over one-third of all BRW dairies, however, did not have recent TNRCC inspection reports. TNRCC permits for concentrated animal feeding operations (CAFOs) cannot be used to estimate actual cow numbers because most dairies have fewer cows than the maximum listed on their permit and not all dairies are required to have a permit. (Prior to 1995, dairies with fewer than 250 cows were not required to have a permit; in 1995, that number was lowered to 200 cows.) Therefore, the actual number of cows on any BRW dairy not recently inspected had to be estimated. The percentage of actual cows out of the total allowable number of cows on inspected dairies was calculated and applied to the maximum allowable on the uninspected dairies. The following steps outline the procedure used to estimate cows on uninspected dairies: (1) The number of cows actually present on the dairies inspected from 1997 through 1999 was totaled, using TNRCC inspection reports. The maximum allowable number of cows on those dairies was also totaled. TNRCC CAFO permits provided the maximum allowable number for dairies with permits. For unpermitted dairies, the maximum allowable number of cows was assumed to be either 199 or 249, depending on initial date of operation. The percentage of actual cows out of allowable cows was calculated for the inspected dairies. (2) To estimate the number of actual cows on the uninspected dairies, the percentage calculated above was multiplied by the maximum allowable number of cows for each uninspected dairy. Table 5 presents the data used in estimating the number of BRW cows in The first row of figures in the table presents data for BRW dairies in Erath and Hamilton counties inspected by TNRCC from 1997 through The maximum allowable number of cows was totaled for the 65 inspected dairies. This number had to be adjusted to accommodate dairies located on the boundary between the Bosque and adjacent watersheds. Because some TNRCC permits list total head while other permits list milking head, the figures were also adjusted to represent total cows on all permitted dairies. Appendix C provides details for allocation of cows on the borderline dairies and for adjusting numbers to reflect total cows. The actual number of cows on the first row (27,289) represents the sum from the inspection reports of the 65 inspected dairies, with cow numbers on borderline dairies being appropriately adjusted. Dividing the total of actual cows on those dairies (27,289) by the adjusted maximum number (42,527) yields 64.2 percent. This percentage was applied to the maximum number of cows allowed on the uninspected BRW dairies to estimate their actual cow numbers (second row of Table 5). Four BRW dairies are no longer operating, yet remain on TNRCC s list of permitted dairies. Because they could legally resume operation, they are included in the total for maximum allowable cows. Cow numbers for the two BRW dairies located outside Erath and Hamilton counties, both of which had been inspected, were added to the numbers for the watershed. Recent review of TNRCC permit files show that from January-August 1999, TNRCC issued 19

20 Future Growth Projections for the Lake Waco/Bosque River Watershed permits for one new and two enlarged dairies, adding 1,290 more cows to the total allowable maximum. Although other numbers reflect 1998 conditions, the BRAC decided to include these new cows into the total in order to more accurately reflect the number of cows currently permitted/allowed in the BRW. Table 5: Estimated Number of BRW Cows, 1998 Type of Dairy Maximum Allowable Number of Cowsa Adjusted for Basin & Total Number of Cowsb Actual Number of Cows Actual Compared to Maximum Allowable Inspected BRW dairies in Erath & Hamilton counties Uninspected BRW dairies in Erath & Hamilton counties Out of business permitted dairiesc 42,062 42,527 27, % 22,660 19,712 12,649 2,495 2,495 0 Total in Erath and Hamilton counties 67,217 64,734 39,938 Outside Erath & Hamilton counties 1,050 1, Permitted additions (September 1999) 1,290 1,290 0 Total BRW cows 69,557 67,074 40,483 a. Maximum allowable refers both to TNRCC permit limits and the maximum allowable for unpermitted dairies b. Adjustments include standardizing to total cow numbers and apportioning cows on dairies located only partially within the BRW c. Dairies that are no longer in operation but that are still included on TNRCC s list of permitted dairies. Method Used to Predict BRW Cow Numbers The prediction of BRW cow numbers is based on the application of a regression equation, which describes historical growth in BRW cow numbers, to the current estimated BRW cow population. Estimates of BRW cow populations from 1985 through 1998 were analyzed to produce a regression equation that describes the growth rate from 1985 through A graph of the data (Figure 3) shows a flattening of the growth rate from 1994 through In order to estimate future growth in the BRW cow population, the best information from dairy operators on the BRAC indicated that the more recent flattened trend (Figure 3) is a better representation of expected future growth. The BRAC decided that the projected number of cows based on the regression equation was a more realistic estimate because the earlier period represents an especially dramatic period of growth in the BRW dairy industry which is not likely to be duplicated. 20

21 Future Growth Projections for the Lake Waco/Bosque River Watershed Future Growth Projections Figure 2: Graph and Regression Equation of Estimated BRW Cow Numbers, Note: Does not include the two dairies located outside of Erath and Hamilton counties 50,000 45,000 40,000 Number of Cows 35,000 30,000 25,000 20,000 15,000 10,000 5,000 y = (x-1985)+13, Figure 3: Graph and Regression Equation of Estimated BRW Cow Numbers, Note: Does not include the two dairies located outside of Erath and Hamilton counties 41,500 41,000 40,500 Number of Cows 40,000 39,500 39,000 38,500 38,000 37,500 y = (x-1994) +38,152 37, The regression equation can be used to calculate future numbers of cows (y) from an initial number of cows plus the product of the desired year in the future (x) and a 21

22 Future Growth Projections for the Lake Waco/Bosque River Watershed coefficient derived from analysis which represents growth per year. The terms of the equation are written in the order shown in the equations in Figures 2 and 3. The future growth equation based on BRW data is as follows: y= (x-1998) + 40,483 where x = the year of the desired projection (must be after 1998) 40,483 = estimated number of BRW cows in = coefficient which describes yearly growth rate. Table 6 shows the estimated number of BRW cows in the years 2000, 2010 and 2020 using the equation shown above. Table 6: Projected BRW Cow Numbers Based on Regression Equation Year # cows Growth from ,578 3% ,051 16% ,524 30% Using the regression equation, the projected number of cows in the BRW in 2020 (52,524) is lower than the currently permitted number of cows in the watershed (67,074). Using the larger of the projected and current permitted number of cows, 67,074 total cows are used in the project s considerations for 20 years of future growth. Projections of Row Crop Production in the Bosque River Watershed Approximately 16 percent of the land in the BRW is used for row crops (McFarland and Hauck, 1998). Runoff from crop fields can contain excess fertilizer, which can lead to nutrient over-enrichment. An examination of land use percentages from 1977 and 1996 shows very little change in amount of BRW cropland during the 19 year period. The 1977 land use data were obtained from the USDA Computer-Based Mapping System (CBMS) digital database of aerial photography of Bosque, Coryell, Hamilton and McLennan counties. The 1996 data were developed by USDA Natural Resources Conservation Service from 1996 Landsat TM scenes. The original land use designation combined both row crops and non-row crops, such as improved pasture, into one category termed cropland. In order to identify just the row crops, differentiation in cropland type was assigned based on location in the watershed. Because of soil types and general land use practices, any cropland acres above Hico were considered to be improved pasture, while those below Hico were considered to be row crops. 22

23 Future Growth Projections for the Lake Waco/Bosque River Watershed Future Growth Projections Table 7 presents the number of acres used for row crops in each of the major subwatersheds of the BRW, the percentage of total acreage in the subwatershed used as row crops, and the percentage change from 1977 to The BRAC subcommittee reviewed the data and deemed the amount of change to not be of sufficient magnitude to warrant additional future growth allocation. Table 7: Changes in BRW Row Crop Acres, 1977 to 1996 Row Crop Acres Part of Watershed Used for Row Crops 1977a 1996b Change Entire BRW 168, , % 16.1% <1% North Bosque 44,562 61,582 6% 8% 38% Hog Creek 23,737 20,840 41% 36% -12% Middle Bosque 61,348 53,496 48% 42% -13% South Bosque 29,720 27,539 51% 47% -7% Other 9,007 7,216 30% 23% -20% a. CBMS landuse data b. Landsat TM imagery Projections of Unallocated Municipal/Industrial Contributions to the Bosque River Watershed In order to account for future municipal or industrial growth that generates wastes not treated by existing WWTPs, the BRAC recommended allocating some pollutant loading for unknown industries moving into the watershed. As an initial estimate, approximately 10 percent of the currently permitted WWTP effluent discharge limit is allocated for future municipal and industrial growth. Using the total from Table 2 yields an additional 0.6 MGD of effluent to the river system. 23

24 Future Growth Projections for the Lake Waco/Bosque River Watershed Summary To estimate the future growth of potential pollution sources for the USDA Initiative, areas of potential growth with respect to phosphorus loading in the watershed have been examined. These areas include urban population growth, wastewater treatment plant effluent discharge, numbers of dairy cows, acres of land used for row crop production, and potential municipal and industrial contributions. Projected increases in each area were estimated for an approximate 20-year horizon to the year 2020, with intermediate projections for the year Regulatory limits exist for wastewater treatment plant effluent and dairy cow numbers. Projected growth in neither area equals the current regulatory limits. Because the potential exists for all WWTPs and dairies to increase to their authorized maximum, the sum of the effluent limits for WWTPs and the maximum number of dairy cattle will be used as the projected levels in the year Growth in acres used for row crop production is not anticipated to increase significantly above its current level of 16 percent of the total watershed acres. Currently all effluent from industrial producers in BRW is handled by local WWTPs. In order to allow for additional future growth in the watershed, notably in the municipal and industrial areas, an allotment of 10 percent of the current WWTP effluent is projected. This adds an estimated 0.6 million gallons of effluent per day to the system. Future contributions to be used in the modeling efforts and other analyses for the USDA Lake Waco/Bosque River Initiative project are shown in Table 8. Table 8: Summary of Future Growth Projections for the BRW Component 2020 Projection Change from Current Conditions or Permit Limits Total urban population 84,190 people +19,777 (31%) Total WWTP effluent MGD None Total number of dairy cows 67,074 cows None Total acres of row crops 170,673 acres None Other point source growth 0.6 MGD effluent +0.6 MGD 24

25 References McFarland, Anne and Larry Hauck Stream Water Quality in the Bosque River Watershed, October 1, 1997 through March 15, Report No. PR9705. Stephenville TX: Texas Institute for Applied Environmental Research, Tarleton State University. Ramos, M. and Robert Plocheck eds Texas Almanac Dallas, TX: The Dallas Morning News, Inc. Texas Natural Resource Conservation Commission (TNRCC) State of Texas 1999 Clean Water Section 303(d) List (Draft). Austin, TX: TNRCC State of Texas 1998 Clean Water Section 303(d) List. Austin, TX: TNRCC State of Texas 1996 Clean Water Section 303(d) List. Austin, TX: TNRCC. Texas Water Development Board (TWDB) Water for Texas - Today and Tomorrow, A 1996 Consensus-Based Update to the Texas Water Plan. Vol 3, Water Use Planning Data Appendix. Austin, TX: TWDB. USDA. The Market Administrator s Report: The Texas Marketing Area, New Mexico -West Texas Marketing Area. Monthly editions from January 1985 through December Carrollton, TX: USDA. 25

26 Future Growth Projections for the Lake Waco/Bosque River Watershed 26

27 APPENDIX A City of Waco Population and WWTP Projections for the BRW Area Population Projections Representatives from the City of Waco provided the following population figures for the portion of Waco located within the Bosque River watershed. These projections were prepared for them by The Texas A&M University: Year Population 33,200 44,200 These figures represent an increase of 11,000 people over the 17 year period, or 647 people annually, assuming growth will take place in equal amounts each year. Population projections for 2000, 2010, and 2020 were calculated using equal annual increases in population, as shown below. Year Population 33,200 34,494 40,965 44,200 47,435 Wastewater Treatment Plant Projections Three subdivisions are scheduled to be developed within the City of Waco s jurisdiction. Residences currently located in those areas use onsite septic systems. Permits that would allow package wastewater treatment facilities to discharge into the BRW have been obtained for each of the three residential developments. If the package treatments are installed, they are not anticipated to be used past the year The residential developments will be connected to Waco s wastewater collection system which discharges into the Brazos River watershed. Table A-1 shows combined daily average flow limits, plus the daily average flow and the predicted flow for WWTP discharge from the City of Waco into the BRW. 27

28 Future Growth Projections for the Lake Waco/Bosque River Watershed Table A-1: WWTP Effluent Discharge Projections for the City of Waco Located in the BRW City Daily Avg Flow Limit (MGD) Daily Avg Flow (MGD) Estimated Flow in 2020 (MGD) Percentage Increase 2020 Flow as Percent of Limit Waco % 0.0% 28

29 APPENDIX B WWTP Effluent Projection Calculations WWTP effluent projection calculations are based on population growth in the area served by the WWTP. (a) POPULATION GROWTH RATE: City population estimates for 2000, 2010 and 2020 were obtained from the TWDB web-site or from city representatives. The growth rates in city population were calculated by subtracting one decade s population from the next decade s population and dividing by the first decade s population (Table B- 1). Table B-1: Population Growth Rate Calculations Population Growth City Clifton 3,557 3,961 4, % 7.8% Crawford % -3.2% Hico 1,380 1,400 1, % 1.2% Iredell % 14.3% McGregor 5,228 5,670 5, % 3.1% Meridian 1,504 1,603 1, % 11.7% Stephenville 16,060 18,638 21, % 13.2% Valley Mills 1,090 1,107 1, % 1.0% Waco 34,494 40,965 47, % 15.8% TOTAL 64,413 74,505 84, % 13.0% (b) DAILY AVERAGE DISCHARGE RATE: Monthly averages of daily effluent discharge for each WWTP, obtained from self-reporting data submitted to TNRCC, were averaged across the period of January 1997 through December Because of weather and usage variations, it was felt that two years of data would likely yield a more representative average daily discharge than a single year is the last year 29

30 Future Growth Projections for the Lake Waco/Bosque River Watershed for which complete data are available, so the average daily flows were designated as 1998 averages. Average discharges are shown in Table B-2. (c) DISCHARGE PROJECTIONS: The discharge rate for each WWTP was multiplied by the decade s population growth rate for that city to yield the discharge projection. Two-tenths of the growth rate for was used for the two year period from Projections are shown in Table B-2. Table B-2: WWTP Discharge Projections City 1998 Avg Dischg 2000 Dischg 2010 Dischg 2020 Dischg Clifton Crawford Hico Iredell McGregor Meridiana Stephenville Valley Mills Waco TOTAL a. Representatives from Meridian projected increases larger than those due to population increase alone. That increase and the resulting different totals are reflected in Table 2. Cranfills Gap is a small community located on a tributary to Meridian Creek, which flows to the North Bosque River. Although the town does not currently have a WWTP and TNRCC has not received a permit application for the proposed WWTP, TIAER researchers have been informed that funding has been secured for a Cranfills Gap WWTP. A rough estimate of future wastewater discharges in Cranfills Gap, based on the current number of water meters and the TWDB projected growth rate for nonurban areas of Bosque County, yielded less than a one percent change in total discharge of effluent in In addition, the WWTP would discharge near the headwaters of Meridian Creek, over twelve miles from the North Bosque River, which substantially reduces impacts to the North Bosque River. Therefore, the potential WWTP for Cranfills Gap was not included in effluent discharge projections. 30

31 APPENDIX C Additional Details of Determining Cow Numbers TNRCC wastewater discharge permits for dairies designate a maximum allowable number of cows. Some permits designate milking head; other permits designate total head, while others simply state a number of head. This discrepancy can result in a notable difference in total number of cows. Cows lactate an average of 305 days a year, and are dry the remaining 60 days. Multiplying the number of milking head by 20 percent approximates average number of dry cows. TNRCC permits for all BRW dairies were examined for wording. Cow numbers on permits designating milking cows were increased by 20 percent to accommodate dry cows. Cow numbers for permits designating either total head, head, or cows remained as stated for calculation purposes. This raised the permitted total for the BRW from 67,217 to 70,008 cows. Note: Dairies with fewer than 200 cows (or 250 if they were in operation prior to 1995) are not required to have a TNRCC wastewater discharge permit and, unless otherwise designated, were counted as being "permitted" to have 199 cows (or 249), which is the regulatory allowable number. A number of dairies are located on the boundary of the Bosque River watershed, with acreage in both the Bosque and adjacent watersheds. Whatever proportion of the dairy s waste application fields are located in the BRW is also applied to the cows. For example, if 60 percent of a dairy s waste application fields are located in the BRW, then 60 percent of the cows are counted as BRW cows. This procedure was applied to dairies whose facilities are located in the BRW, with some acreage in adjacent watersheds, as well as dairies whose facilities are located in other watersheds, but have some acreage in the BRW. Dairies that haul manure off their property also are proportioned in this same manner. This adjustment reduced the permitted total for the BRW in Erath and Hamilton counties from 70,008 to 64,734 cows. The number of actual cows, as opposed to a maximum allowable or permitted number of cows, was estimated from TNRCC inspection reports for the years 1997 through 1999 for 67 of the watershed s 107 dairies, including the two dairies outside Erath and Hamilton counties. The TNRCC inspection numbers were revised for dairies whose waste application fields lay only partially within the BRW, just as the permitted numbers were adjusted. Thirty-six dairies, plus four out-of-business dairies, had no TNRCC inspection report on file between 1997 and The number of actual cows on the uninspected dairies was estimated by multiplying the number of permitted cows on those dairies by the ratio of actual-to-permitted cows on the inspected dairies. This ratio was calculated by dividing the actual TNRCC inspection total by the adjusted permitted total for the watershed, excluding the two dairies out- 31

32 Future Growth Projections for the Lake Waco/Bosque River Watershed side Erath and Hamilton counties. The ratio, 0.642, and the other figures are shown in Table C-1, which is an expanded version of Table 4. Dairies included on TNRCC s most current list of permitted dairies, but which are currently out of business, were not used in calculating the permitted to actual cow ratio nor in the regression analyses. However, because those dairies could resume operations, their permitted numbers of cows were included in the total number of permitted cows in the watershed. As noted in the text, a review of TNRCC permit files showed that between January to August 1999, an additional 1,290 cows were permitted in the BRW. These were added to the total permitted number at the request of the BRAC, in order to more accurately estimate the cow population in the watershed. Table C-1: Figures Used in Estimating the Number of BRW Cows in 1998 Type of Dairy # of Dairies Maximum Allowable Permitted Converted to Total Adjusted for Basin Boundaries Estimated Actual Number % of Actual/ Maximum Allowable Inspected Dairies 65 42,062 44,155 42,527 27, Uninspected Dairies 36 22,660 23,358 19,712 12,649 Out-of-Business Permitted Dairies Total in Erath and Hamilton Outside Erath and Hamilton 4 2,495 2,495 2, ,217 70,008 64,734 39, ,050 1,050 1, Permitted in ,290 1,290 1,290 0 TOTAL ,557 72,348 67,074 40,483 32

EXISTING NUTRIENT SOURCES AND CONTRIBUTIONS TO THE BOSQUE RIVER WATERSHED

EXISTING NUTRIENT SOURCES AND CONTRIBUTIONS TO THE BOSQUE RIVER WATERSHED TIAER PR 9911 EXISTING NUTRIENT SOURCES AND CONTRIBUTIONS TO THE BOSQUE RIVER WATERSHED Anne McFarland and Larry Hauck September 1999 Texas Institute for Applied Environmental Research Tarleton State University

More information

Determining Nutrient Contribution by Land Use for the Upper North Bosque River Watershed

Determining Nutrient Contribution by Land Use for the Upper North Bosque River Watershed TIAER PR 98-01 LAKE WACO/BOSQUE RIVER WATERSHED INITIATIVE REPORT: Determining Nutrient Contribution by Land Use for the Upper North Bosque River Watershed Anne McFarland and Larry Hauck January 1998 Revised

More information

USDA Lake Waco-Bosque River Initiative. Fate and Transport of Soluble Reactive Phosphorus in the North Bosque River of Central Texas

USDA Lake Waco-Bosque River Initiative. Fate and Transport of Soluble Reactive Phosphorus in the North Bosque River of Central Texas USDA Lake Waco-Bosque River Initiative Fate and Transport of Soluble Reactive Phosphorus in the North Bosque River of Central Texas Anne McFarland, Larry Hauck, and Richard Kiesling TR0101 February 2001

More information

6. Pollutant Sources in

6. Pollutant Sources in 6. Pollutant Sources in 45 6. Pollutant Sources in the Plum Creek Watershed The LDC analysis for Plum Creek indicates that both point and nonpoint sources contribute pollutants in the watershed. Identifying

More information

Water Resources Element Appendix

Water Resources Element Appendix Appendix Housing Unit Projection Methodology The following assumptions were used to develop the housing unit projections for each Water Resources Element. All projections described in the and this Appendix

More information

MODELING PHOSPHORUS LOADING TO THE CANNONSVILLE RESERVOIR USING SWAT

MODELING PHOSPHORUS LOADING TO THE CANNONSVILLE RESERVOIR USING SWAT MODELING PHOSPHORUS LOADING TO THE CANNONSVILLE RESERVOIR USING SWAT Bryan Tolson 1 & Christine Shoemaker 2 1. PhD Student, 2. Professor School of Civil & Environmental Engineering Cornell University PWT

More information

Water Quality Improvement Through Implementation of a Watershed Protection Plan in the Leon River Watershed

Water Quality Improvement Through Implementation of a Watershed Protection Plan in the Leon River Watershed Water Quality Improvement Through Implementation of a Watershed Protection Plan in the Leon River Watershed HGAC Clean Waters Initiative Houston, Texas September 26, 2017 Agency Role Water Quality Mandate

More information

Nitrate Load Reduction Strategies for the Raccoon and Des Moines Rivers. Keith Schilling, Calvin Wolter Iowa DNR Geological and Water Survey

Nitrate Load Reduction Strategies for the Raccoon and Des Moines Rivers. Keith Schilling, Calvin Wolter Iowa DNR Geological and Water Survey Nitrate Load Reduction Strategies for the Raccoon and Des Moines Rivers Keith Schilling, Calvin Wolter Iowa DNR Geological and Water Survey Outline of Presentation Background of nitrate impairments Nitrate

More information

Lampasas River Watershed Partnership. Ground Rules

Lampasas River Watershed Partnership. Ground Rules Lampasas River Watershed Partnership Ground Rules The signatories to these Ground Rules agree as follows: The following are the Ground Rules for the Lampasas River Watershed Partnership agreed to and signed

More information

Environmental Consideration of Dairy Systems

Environmental Consideration of Dairy Systems Environmental Consideration of Dairy Systems Phosphorus and Water Quality Neil Hansen, Colorado State University neil.hansen@colostate.edu Environmental Issues Agricultural nutrients in surface and ground

More information

Overview of Models for Estimating Pollutant Loads & Reductions

Overview of Models for Estimating Pollutant Loads & Reductions Overview of Models for Estimating Pollutant Loads & Reductions (Handbook Chapter 8.3 8.5) Texas Watershed Planning Short Course Wednesday, June 3, 2008 Larry Hauck hauck@tiaer.tarleton.edu Presentation

More information

Analysis of PL-566 Reservoir Production Responses Along a Nutrient Loading Gradient

Analysis of PL-566 Reservoir Production Responses Along a Nutrient Loading Gradient Analysis of PL-566 Reservoir Production Responses Along a Nutrient Loading Gradient Richard L. Kiesling, Anne M.S. McFarland, and Larry M. Hauck TR0108 August 2001 Texas Institute for Applied Environmental

More information

North Dakota s Nutrient Reduction Strategy. Presented to the 2016 ND Water Quality Monitoring Conference March 4, 2016

North Dakota s Nutrient Reduction Strategy. Presented to the 2016 ND Water Quality Monitoring Conference March 4, 2016 North Dakota s Nutrient Reduction Strategy Presented to the 2016 ND Water Quality Monitoring Conference March 4, 2016 Nutrients Nutrients, in appropriate amounts, are essential to the growth and health

More information

Task 3: Estimation of Nutrient Loading to Falls Lake

Task 3: Estimation of Nutrient Loading to Falls Lake Task 3: Estimation of Nutrient Loading to Falls Lake Prepared for: Upper Neuse River Basin Association Prepared by: Cardno ENTRIX 5400 Glenwood Ave, Suite G03, Raleigh, NC, 27612 Table of Contents Executive

More information

Decision Rationale. Total Maximum Daily Load for Phosphorus for the Sassafras River, Cecil and Kent Counties, Maryland 4/1/2002

Decision Rationale. Total Maximum Daily Load for Phosphorus for the Sassafras River, Cecil and Kent Counties, Maryland 4/1/2002 Decision Rationale I. Introduction Total Maximum Daily Load for Phosphorus for the Sassafras River, Cecil and Kent Counties, Maryland 4/1/2002 The Clean Water Act (CWA) requires a Total Maximum Daily Load

More information

Wisconsin River. Hardest Working River In the Nation

Wisconsin River. Hardest Working River In the Nation Hardest Working River In the Nation Hardest Working River In The Nation Largest Basin In Wisconsin 430 miles in length 20% of Wisconsin, with diverse land use 14,776 mi2 catchment at Prairie du Sac Dam

More information

ALAN PLUMMER ASSOCIATES, INC. ENVIRONMENTAL ENGINEERS - DESIGNERS - SCIENTISTS

ALAN PLUMMER ASSOCIATES, INC. ENVIRONMENTAL ENGINEERS - DESIGNERS - SCIENTISTS Grapevine Lake Watershed Characteristics February 18, 2010 NCTCOG REGIONAL WATERSHED ROUNDTABLE ALAN PLUMMER ASSOCIATES, INC. ENVIRONMENTAL ENGINEERS - DESIGNERS - SCIENTISTS 1 Presentation Overview Geography

More information

ARIZONA CONSERVATION REQUIREMENTS. Management Plans MUNICIPAL CONSERVATION REQUIREMENTS

ARIZONA CONSERVATION REQUIREMENTS. Management Plans MUNICIPAL CONSERVATION REQUIREMENTS ARIZONA CONSERVATION REQUIREMENTS Management Plans The Arizona Groundwater Management Code establishes the legal framework for conserving water in Arizona's most populous areas. To help achieve its goals,

More information

Example Waste Utilization / Nutrient Management Plan. Revised 7/05

Example Waste Utilization / Nutrient Management Plan. Revised 7/05 Example Waste Utilization / Nutrient Management Plan Revised 7/05 Step 1 - Locate Operation Locate on Topo Map first. Note if any named streams or water bodies present within 2000 feet of the application

More information

LAVACA BASIN SUMMARY REPORT

LAVACA BASIN SUMMARY REPORT LAVACA BASIN SUMMARY REPORT July, 2002 Lavaca-Navidad River Authority PO Box 429 Edna, Texas 77957 Paul Price Associates, Inc. 3006 Bee Caves Road, Suite D-230 Austin, Texas 78746 Prepared in cooperation

More information

LIVESTOCK AND THE ENVIRONMENT: A NATIONAL PILOT PROJECT DETAILED PROBLEM STATEMENT Project Task 1.1

LIVESTOCK AND THE ENVIRONMENT: A NATIONAL PILOT PROJECT DETAILED PROBLEM STATEMENT Project Task 1.1 LIVESTOCK AND THE ENVIRONMENT: A NATIONAL PILOT PROJECT DETAILED PROBLEM STATEMENT Project Task 1.1 by Ron Jones and Larry Frarey Texas Institute for Applied Environmental Research Tarleton State University

More information

Draft Wasteload Allocation Report Town of Haworth

Draft Wasteload Allocation Report Town of Haworth Draft Wasteload Allocation Report Town of Haworth Contents 1. Problem Definition... 1 2. Endpoint Identification... 1 3. Source Analysis... 2 3.1. Point Sources... 2 3.2. Non-Point Sources... 2 3.3. Background...

More information

Lisa Prcin Research Associate Watershed Coordinator Texas A&M AgriLife Research at Blackland Research & Extension Center

Lisa Prcin Research Associate Watershed Coordinator Texas A&M AgriLife Research at Blackland Research & Extension Center Lisa Prcin Research Associate Watershed Coordinator Texas A&M AgriLife Research at Blackland Research & Extension Center Watershed: The geographic area that drains to a common body of water Point source

More information

TR Bosque River Environmental Infrastructure Improvement Plan Phase I Final Report By Dr. Raghavan Srinivasan, Spatial Sciences Laboratory

TR Bosque River Environmental Infrastructure Improvement Plan Phase I Final Report By Dr. Raghavan Srinivasan, Spatial Sciences Laboratory TR-312 2008 Bosque River Environmental Infrastructure Improvement Plan Phase I Final Report By Dr. Raghavan Srinivasan, Spatial Sciences Laboratory Sponsored By: Executive Summary The Bosque River and

More information

MARK CREEK DEMONSTRATION PROJECT

MARK CREEK DEMONSTRATION PROJECT MARK CREEK DEMONSTRATION PROJECT OCC Tasks 20 and 21 FY 1990 319(h) Task 210 EPA Grant # C9-006704-90-0 Submitted by: Oklahoma Conservation Commission Water Quality Division 413 NW 12 th Oklahoma City,

More information

Land Application and Nutrient Management

Land Application and Nutrient Management MODULE D Land Application and Nutrient Management Figure 34-13. Relationship between the concentration of dissolved P in subsurface drainage from 30 cm deep lysimeters and the Mehlich-3 extractable soil

More information

Natural Resources & Environmental Stewardship

Natural Resources & Environmental Stewardship Natural Resources & Environmental Stewardship Fundamentals of Nutrient Management Melissa L. Wilson Department of Environmental Science & Technology Ag Nutrient Management Program University of Maryland,

More information

Pennsylvania s Chesapeake Bay Tributary Strategy Implementation Plan for Sewage Facilities Planning

Pennsylvania s Chesapeake Bay Tributary Strategy Implementation Plan for Sewage Facilities Planning The strategy outlined in this guidance document is intended to supplement existing requirements. Nothing in the strategy shall affect regulatory requirements. The information herein is not an adjudication

More information

Grants Pass Water Quality Monitoring

Grants Pass Water Quality Monitoring Grants Pass Water Quality Monitoring 2003-2005 Rogue Valley Council of Governments April 2005 Rogue Valley Council of Governments Natural Resources Department 155 North First Street Central Point, Oregon

More information

Florida s Nitrate + Nitrite Criterion for Springs A Methodology for Predicting What it Would Take to Achieve it at an Impaired Spring

Florida s Nitrate + Nitrite Criterion for Springs A Methodology for Predicting What it Would Take to Achieve it at an Impaired Spring Florida s Nitrate + Nitrite Criterion for Springs A Methodology for Predicting What it Would Take to Achieve it at an Impaired Spring Gregg Jones P.G. Water Resources Technical Director Brandon N. Ashby

More information

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit) CHESAPEAKE BAY TMDL ACTION PLAN (2013 2018 MS4 General Permit) Piedmont Virginia Community College A Plan for Achieving a 5% Reduction of Existing Loads June 30, 2015 Main Campus This plan satisfies the

More information

Wisconsin Wastewater Operators Association. Protecting Our Water Resources: The Future Bill Hafs - NEW Water 10/2014

Wisconsin Wastewater Operators Association. Protecting Our Water Resources: The Future Bill Hafs - NEW Water 10/2014 Wisconsin Wastewater Operators Association Protecting Our Water Resources: The Future Bill Hafs - NEW Water 10/2014 The Fox River Contributes 1/3 of All Nutrients to Lake Michigan APRIL 15, 2011 Photo

More information

Gathering Data to Assess Your Watershed

Gathering Data to Assess Your Watershed Gathering Data to Assess Your Watershed Nikki Dictson Kevin Wagner Presentation Goals: What data do you need? Where do you find the data? How do you get info from TCEQ and other agencies? This session

More information

Phosphorus Rules NR , NR 151 and NR 217 Subchapter III

Phosphorus Rules NR , NR 151 and NR 217 Subchapter III Phosphorus Rules NR 102.06, NR 151 and NR 217 Subchapter III Jim Baumann Wisconsin Department of Natural Resources james.baumann@wisconsin.gov 608/266-9277 Phosphorus 3 Rule Changes S. NR 102.06 phosphorus

More information

An Environmental Accounting System to Track Nonpoint Source Phosphorus Pollution in the Lake Champlain Basin. Year 2 Project Work Plan

An Environmental Accounting System to Track Nonpoint Source Phosphorus Pollution in the Lake Champlain Basin. Year 2 Project Work Plan An Environmental Accounting System to Track Nonpoint Source Phosphorus Pollution in the Lake Champlain Basin Mary Watzin and Lula Ghebremichael University of Vermont, Rubenstein School of Environment and

More information

GUIDELINES FOR PREPARATION OF CAPACITY ANALYSIS REPORTS

GUIDELINES FOR PREPARATION OF CAPACITY ANALYSIS REPORTS GUIDELINES FOR PREPARATION OF CAPACITY ANALYSIS REPORTS Florida Department of Environmental Regulation July 1992 TABLE OF CONTENTS PURPOSE AND APPLICABILITY................... 1 Purpose............................

More information

FINAL. Appendix D: Newport Bay

FINAL. Appendix D: Newport Bay : Newport Bay 1.0 Introduction As described in the main TMDL report, the Coastal Bays are a shallow coastal lagoon system comprised of several individual and distinct waterbodies. The MD 8-Digit Newport

More information

Memorandum of Understanding for an Adaptive Management Pilot Project in the Yahara Watershed

Memorandum of Understanding for an Adaptive Management Pilot Project in the Yahara Watershed Memorandum of Understanding for an Adaptive Management Pilot Project in the Yahara Watershed 1. Background The Wisconsin Department of Natural Resources (WDNR or the department) has developed numeric water

More information

Murky Waters. More Accountability Needed for Agricultural Pollution in the Chesapeake Bay

Murky Waters. More Accountability Needed for Agricultural Pollution in the Chesapeake Bay Murky Waters More Accountability Needed for Agricultural Pollution in the Chesapeake Bay July 14, 2014 About the Environmental Integrity Project The Environmental Integrity Project (EIP) is a nonpartisan,

More information

Strategies for nitrate reduction: The Cedar River Case Study

Strategies for nitrate reduction: The Cedar River Case Study 2010 Integrated Crop Management Conference - Iowa State University 195 Strategies for nitrate : The Cedar River Case Study Matthew J. Helmers, associate professor, Agricultural and Biosystems Engineering,

More information

Regional Ecosystem Analysis Puget Sound Metropolitan Area

Regional Ecosystem Analysis Puget Sound Metropolitan Area Final Report: 7/25/98 Regional Ecosystem Analysis Puget Sound Metropolitan Area Calculating the Value of Nature Report Contents 2 Project Overview and Major Findings 3 Regional Level Analysis 4 Neighborhood

More information

A Summary of Efforts to Reduce Phosphorus in the Red Cedar River Basin

A Summary of Efforts to Reduce Phosphorus in the Red Cedar River Basin A Summary of Efforts to Reduce Phosphorus in the Red Cedar River Basin State Laws to Reduce Phosphorus 1970s - Restriction on phosphorus in laundry detergent 1992 - Limits on point sources with significant

More information

Appendix 12. Pollutant Load Estimates and Reductions

Appendix 12. Pollutant Load Estimates and Reductions Appendix 12. Pollutant Load Estimates and Reductions A pollutant loading is a quantifiable amount of pollution that is being delivered to a water body. Pollutant load reductions can be calculated based

More information

GULF OF MEXICO - SEGMENT 2501

GULF OF MEXICO - SEGMENT 2501 GULF OF MEXICO - SEGMENT 2501 GULF OF MEXICO - SEGMENT 2501 LAND COVER BACTERIA CHLOROPHYLL A Impairment Concern No Impairments or Concerns GULF OF MEXICO - SEGMENT 2501 OTHER IMPAIRMENTS Bays & Estuaries

More information

Ohio s Great Miami River Watershed

Ohio s Great Miami River Watershed Water Quality Credit Trading Ohio s Great Miami River Watershed Water Quality Credit Trading Workshop August 26, 2009 Douglas Dusty Hall The Miami Conservancy District Dayton, Ohio Presentation overview

More information

Environmental Hazard in South Dakota?

Environmental Hazard in South Dakota? ~m Livestock Manure: a Nonpoint Source Environmental Hazard in South Dakota? D.C. ~ a~lorl and D.H. Flicked2 Departments of Economics and Animal and Range Sciences SDSU CAlTLE 95-1 5 Summary This exploratory

More information

Technical Memorandum. 1.0 Introduction

Technical Memorandum. 1.0 Introduction Technical Memorandum To: Jennifer Saran and Christie Kearney, Poly Met Mining, Inc. Project: 23/69-0862.12 100 001 c: Keith Hanson and Tina Pint, Barr Engineering Co. Disclaimer: This is a working document.

More information

Fillmore One to seven million acre-feet in storage depending on calculation assumption; surface area is 20,100 acres.

Fillmore One to seven million acre-feet in storage depending on calculation assumption; surface area is 20,100 acres. Where does the City of Santa Paula obtain its water? Currently, the City of Santa Paula obtains its water supply from the court-adjudicated Santa Paula Groundwater Basin (Basin) and in lieu surface water

More information

EAST TORRANCE SOIL AND WATER CONSERVATION DISTRICT. LONG RANGE PLAN July 1, 2009 June 30, 2019

EAST TORRANCE SOIL AND WATER CONSERVATION DISTRICT. LONG RANGE PLAN July 1, 2009 June 30, 2019 EAST TORRANCE SOIL AND WATER CONSERVATION DISTRICT LONG RANGE PLAN July 1, 2009 June 30, 2019 INTRODUCTION The East Torrance Soil and Water Conservation District covers 1,142,028 acres of land in Torrance

More information

The City of Cocoa (City) is located in east

The City of Cocoa (City) is located in east FWRJ Reclaimed Water and Stormwater: A Perfect Pair to Meet Total Maximum Daily Load Wasteload Allocations? Danielle Honour, James Wittig, John A. Walsh, and Don Stevens Danielle Honour, P.E., D.WRE, and

More information

Mud Lake Lakeshed Assessment

Mud Lake Lakeshed Assessment Mud Lake Lakeshed Assessment The lakeshed vitals table identifies where to focus organizational and management efforts for each lake. Criteria were developed using limnological concepts to determine the

More information

3.2 Estimated Basin Total Phosphorus Amounts Contributed to POTWs and Surface Waters (by Source)

3.2 Estimated Basin Total Phosphorus Amounts Contributed to POTWs and Surface Waters (by Source) 3.2 Estimated Basin Total Phosphorus Amounts Contributed to POTWs and Surface Waters (by Source) This section is intended to present the results of the total phosphorus loading estimates to surface waters

More information

Vernon Township Municipal Build Out Report

Vernon Township Municipal Build Out Report Vernon Township Municipal Build Out Report Prepared by the State of New Jersey Highlands Water Protection and Planning Council in Support of the Highlands Regional Master Plan: Report on the Results of

More information

Pennsylvania s Phase III Watershed Implementation Plan

Pennsylvania s Phase III Watershed Implementation Plan Pennsylvania s Phase III Watershed Implementation Plan Informational Meeting Pennsylvania House and Senate Agriculture and Rural Affairs Committees August 16, 2017 Agenda Why Are We Doing This? Progress

More information

Jordan River Total Maximum Daily Load Study. Presented By: James Harris Utah Division of Water Quality

Jordan River Total Maximum Daily Load Study. Presented By: James Harris Utah Division of Water Quality Jordan River Total Maximum Daily Load Study Presented By: James Harris Utah Division of Water Quality Jordan River Watershed TMDL Study Area No Introduction Necessary A Few Things to Point Out... Lower

More information

COMPREHENSIVE NUTRIENT MANAGEMENT PLAN REVIEW CHECKLIST FOR CERTIFIED CNMP PROVIDERS

COMPREHENSIVE NUTRIENT MANAGEMENT PLAN REVIEW CHECKLIST FOR CERTIFIED CNMP PROVIDERS Customer Name: CNMP Preparer s Name: CNMP Reviewer s Name and Date: COMPREHENSIVE NUTRIENT MANAGEMENT PLAN REVIEW CHECKLIST FOR CERTIFIED CNMP PROVIDERS COMPONENT Yes No NA 1. Overview - Brief statement

More information

Phosphorus Kyle Minks Land and Water Resources Scientist Land Conservation Division

Phosphorus Kyle Minks Land and Water Resources Scientist Land Conservation Division Phosphorus Kyle Minks Land and Water Resources Scientist Land Conservation Division Overview Phosphorus 101 Phosphorus transport What is legacy phosphorus How phosphorus is managed to reduce environmental

More information

Appendix E. Development of Unit Area Load Export Coefficients

Appendix E. Development of Unit Area Load Export Coefficients Appendix E Development of Unit Area Load Export Coefficients DATE: May 30, 2007 Memorandum FROM: PROJECT: TO: Hans Holmberg CLFLWD John Erdmann, Ph.D., P.E. CC: SUBJECT: Penelope Moskus Summary of Recommended

More information

ROUGE RIVER MONITORING FOR E. COLI TMDL IMPLEMENTATION FINAL REPORT GRANT#

ROUGE RIVER MONITORING FOR E. COLI TMDL IMPLEMENTATION FINAL REPORT GRANT# 1 ROUGE RIVER MONITORING FOR E. COLI TMDL IMPLEMENTATION FINAL REPORT GRANT# 2011-0504 FUNDED BY: MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY CLEAN MICHIGAN INITIATIVE CLEAN WATER FUND LANSING, MI PREPARED

More information

Phosphorus Loading to Western Lake Erie: Trends and Sources

Phosphorus Loading to Western Lake Erie: Trends and Sources Phosphorus Loading to Western Lake Erie: Trends and Sources Western Lake Erie Conference Toledo Yacht Club March 13, 28 Dr. David B. Baker National Center for Water Quality Research Heidelberg College

More information

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit) CHESAPEAKE BAY TMDL ACTION PLAN (2013 2018 MS4 General Permit) Central Virginia Community College A Plan for Achieving a 5% Reduction of Existing Loads June 30, 2015 Main Campus This plan satisfies the

More information

Washington State Conference A Perspective on Water Quality Issues across Washington State Strategies and Implementation for Reducing

Washington State Conference A Perspective on Water Quality Issues across Washington State Strategies and Implementation for Reducing 2011 American Water Resources Association Washington State Conference A Perspective on Water Quality Issues across Washington State Strategies and Implementation for Reducing Phosphorus Loading with a

More information

Non-point Source Pollution Assessment of the San Antonio - Nueces Coastal Basin

Non-point Source Pollution Assessment of the San Antonio - Nueces Coastal Basin Non-point Source Pollution Assessment of the San Antonio - Nueces Coastal Basin By David R. Maidment and William K. Saunders Center for Research in Water Resources University of Texas Austin, TX 78712

More information

Elin Betanzo July 14, 2015

Elin Betanzo July 14, 2015 Water Data to Answer Urgent Water Policy Questions: Harmful Algal Blooms, Agriculture, and Lake Erie Elin Betanzo July 14, 2015 Harmful Algal Blooms in Lake Erie Photo: NOAA Satellite Image What Causes

More information

7.10 BRA Sediment Reduction Program

7.10 BRA Sediment Reduction Program 7.10 BRA Sediment Reduction Program 7.10.1 Description of Option The protection of already developed water supplies is a key element of water supply planning. Because Region G s inventory of suitable sites

More information

Eutrophication: Tracing Nutrient Pollution Back to Penns Creek

Eutrophication: Tracing Nutrient Pollution Back to Penns Creek Eutrophication: Tracing Nutrient Pollution Back to Penns Creek Nutrients are substances that life depends on for growth and reproduction. However, when these nutrients enter our planets waterways in excess,

More information

Table 5-1: Availability of Public Sanitary Sewer. Are plans underway to provide Public Sewer?

Table 5-1: Availability of Public Sanitary Sewer. Are plans underway to provide Public Sewer? CHAPTER 5: PUBLIC SANITARY SEWER AND PRIVATE WASTEWATER DISPOSAL; PUBLIC WATER SERVICE AND PRIVATE WELLS Public Sanitary Sewer The presence or absence of public sanitary sewer service is a major factor

More information

FINAL 2012 BACTERIA AND TURBIDITY TOTAL MAXIMUM DAILY LOADS FOR THE RED RIVER, OKLAHOMA (OK311100, OK311200, OK311210, OK311510, OK311600, OK311800)

FINAL 2012 BACTERIA AND TURBIDITY TOTAL MAXIMUM DAILY LOADS FOR THE RED RIVER, OKLAHOMA (OK311100, OK311200, OK311210, OK311510, OK311600, OK311800) FINAL 2012 BACTERIA AND TURBIDITY TOTAL MAXIMUM DAILY LOADS FOR THE RED RIVER, OKLAHOMA (OK311100, OK311200, OK311210, OK311510, OK311600, OK311800) Prepared for: OKLAHOMA DEPARTMENT OF ENVIRONMENTAL QUALITY

More information

IOWA LIVESTOCK ENVIRONMENTAL REGULATIONS & MANURE AGREEMENTS

IOWA LIVESTOCK ENVIRONMENTAL REGULATIONS & MANURE AGREEMENTS IOWA LIVESTOCK ENVIRONMENTAL REGULATIONS & MANURE AGREEMENTS IOWA PORK PRODUCERS ASSOCIATION January 23, 2008 Eldon McAfee ANIMAL CAPACITY Animal weight capacity and animal unit capacity Constructed before

More information

New York State Animal Agriculture Program Assessment

New York State Animal Agriculture Program Assessment New York State Animal Agriculture Program Assessment Final Prepared by: U.S. Environmental Protection Agency Region 2 290 Broadway New York, NY 10007-1866 February 2015 New York Animal Agriculture Program

More information

Manure Management Manual Revisions

Manure Management Manual Revisions Manure Management Manual Revisions Jim Spontak PA DEP Farms In PA 63,136 farms in PA 33813 have livestock Average farm is 124 acres, about 75% under 200 acres Women as the primary farm operator increased

More information

ORDINANCE NO. 1. A large concentrated animal feeding operation as described in Table 1 in Section 3.07.

ORDINANCE NO. 1. A large concentrated animal feeding operation as described in Table 1 in Section 3.07. ORDINANCE NO. AN ORDINANCE OF CLAY COUNTY, SD, AMENDING THE 2013 REVISED ZONING ORDINANCE FOR CLAY COUNTY BY AMENDING ARTICLE 2, DEFINITIONS, ARTICLE 3, GENERAL DISTRICT REGULATIONS AND ARTICLE 4, DISTRICTS

More information

Plum Creek Watershed Partnership Steering Committee Meeting. October 26, 2006 Lockhart, TX

Plum Creek Watershed Partnership Steering Committee Meeting. October 26, 2006 Lockhart, TX Plum Creek Watershed Partnership Steering Committee Meeting October 26, 2006 Lockhart, TX Texas Surface Water Quality Standards Charles Bayer Texas Commission on Environmental Quality Water Quality Assessment

More information

APPENDIX C Technical Approach Used to Generate Maximum Daily Loads

APPENDIX C Technical Approach Used to Generate Maximum Daily Loads APPENDIX C Technical Approach Used to Generate Maximum Daily Loads Summary This appendix documents the technical approach used to define maximum daily loads of TSS consistent with the average annual TMDL,

More information

PERMITTING & CONSTRUCTING ANIMAL FEEDING OPERATIONS IN SOUTH DAKOTA. A whitepaper by:

PERMITTING & CONSTRUCTING ANIMAL FEEDING OPERATIONS IN SOUTH DAKOTA. A whitepaper by: PERMITTING & CONSTRUCTING ANIMAL FEEDING OPERATIONS IN SOUTH DAKOTA A whitepaper by: Nic Rowe, P.E. Pro Ag Engineering 507 Milwaukee St. Lakefield, MN 56150 507-841-3269 nic@proageng.com www.proageng.com

More information

MURPHY DRAIN CATCHMENT

MURPHY DRAIN CATCHMENT The RVCA produces individual reports for 16 catchments in the Lower Rideau subwatershed. Using data collected and analysed by the RVCA through its watershed monitoring and land cover classification programs,

More information

Good Morning! Bruce Gilman Department of Environmental Conservation and Horticulture Finger Lakes Community College 3325 Marvin Sands Drive Canandaigua, New York 14424 585-785- 1255 gilmanba@flcc.edu Northern

More information

Water Quality Study In the Streams of Flint Creek and Flint River Watersheds For TMDL Development

Water Quality Study In the Streams of Flint Creek and Flint River Watersheds For TMDL Development Water Quality Study In the Streams of Flint Creek and Flint River Watersheds For TMDL Development Idris Abdi Doctoral Dissertation Presentation Major Advisor: Dr. Teferi Tsegaye April 18, 2005 Alabama

More information

2.1 Summary of Existing and Future Population Estimates

2.1 Summary of Existing and Future Population Estimates SECTION 2 Demographics This technical memorandum identifies the uncertainties and describes potential future demographics that might affect wastewater facilities in the City of McCall, Idaho (the City).

More information

Chesapeake Bay Pollutant Reduction Plan

Chesapeake Bay Pollutant Reduction Plan Chesapeake Bay Pollutant Reduction Plan Cocalico Creek and Conestoga River Watershed East Cocalico Township, Lancaster County, PA MS4 Permit # PAG133572 April 2015 Prepared for: East Cocalico Township

More information

WATER RESOURCES MANAGEMENT Vol. II - Watershed Modeling For Water Resource Management - D. K. Borah WATERSHED MODELING FOR WATER RESOURCE MANAGEMENT

WATER RESOURCES MANAGEMENT Vol. II - Watershed Modeling For Water Resource Management - D. K. Borah WATERSHED MODELING FOR WATER RESOURCE MANAGEMENT WATERSHED MODELING FOR WATER RESOURCE MANAGEMENT D. K. Borah Borah Hydro-Environmental Modeling, Champaign, Illinois, USA Keywords: Agriculture, agrochemical, BMP, hydrology, long-term continuous model,

More information

MUNICIPAL WATER POLLUTION PREVENTION (MWPP) ANNUAL REPORT

MUNICIPAL WATER POLLUTION PREVENTION (MWPP) ANNUAL REPORT MUNICIPAL WATER POLLUTION PREVENTION (MWPP) ANNUAL REPORT SUBMITTED BY: TREATMENT FACILITY: NPDES #: MUNICIPALITY: COUNTY: CONTACT PERSON: Responsible Official Title Telephone #: Fax #: Email Address:

More information

GRASS VALLEY WASTEWATER TREATMENT INQUIRY

GRASS VALLEY WASTEWATER TREATMENT INQUIRY GRASS VALLEY WASTEWATER TREATMENT INQUIRY REASON FOR INVESTIGATION The 2003-2004 Grand Jury investigated the status of wastewater treatment in unincorporated Nevada County. This year, the Grand Jury investigated

More information

Coastal Stormwater Best Management Practices Guidance. Listening Session ANAHUAC December 9, 2013

Coastal Stormwater Best Management Practices Guidance. Listening Session ANAHUAC December 9, 2013 Coastal Stormwater Best Management Practices Guidance Listening Session ANAHUAC December 9, 2013 Who We Are Dr. Michael Barrett, Ph.D., P.E. University of Texas at Austin CRWR Danica Adams, MSCRP, MSSD

More information

Opportunity: Methane gas recovery Problem: Where to market the power generated?

Opportunity: Methane gas recovery Problem: Where to market the power generated? From Waste to Watts: Methane Recovery for Power Generation Sustainable Biosolids Management in the Future Presented by: Baumgartner Environics, Inc. Bonestroo, Rosene, Anderlik and Associates, Inc. Overlapping

More information

Walnut Creek Watershed Management Authority. Project Kick Off March 18, 2015

Walnut Creek Watershed Management Authority. Project Kick Off March 18, 2015 Walnut Creek Watershed Management Authority Project Kick Off March 18, 2015 Agenda Schedule & Meeting Purpose Meeting Purpose TMDL Raccoon River TMDL Impaired by Nitrate and E.coli Includes Walnut Creek

More information

SECTION 2 CALDWELLL COUNTY CHARACTERISTICS

SECTION 2 CALDWELLL COUNTY CHARACTERISTICS SECTION 2 CALDWELLL COUNTY CHARACTERISTICS 2.1 City Limits and ETJ Boundaries The name Caldwell was given to the county in recognition of an Indian Fighter named Matthew Caldwell, who led a group of militia

More information

2012 Nutrient Regulations Update

2012 Nutrient Regulations Update 2012 Nutrient Regulations Update OWEA Government Affairs Workshop March 1, 2012 Guy Jamesson, PE, BCEE Malcolm Pirnie, The Water Division of ARCADIS Imagine the result Agenda Nutrient impacts Nutrient

More information

Comparison of Annual Costs Associated With Home Ownership in La Crosse County

Comparison of Annual Costs Associated With Home Ownership in La Crosse County Comparison of Annual Costs Associated With Home Ownership in La Crosse County By: Karl Green, Associate Professor Department of Community Development La Crosse County UW-Extension Purpose: The intent of

More information

J. Sargeant Reynolds Community College. Chesapeake Bay TMDL Action Plan

J. Sargeant Reynolds Community College. Chesapeake Bay TMDL Action Plan J. Sargeant Reynolds Community College Prepared for: J. Sargeant Reynolds Community College Parham Road Campus Facilities Management & Planning 1651 E. Parham Road Richmond, VA 23228 June 30, 2015 Revised

More information

Missouri Concentrated Animal Feeding Operation Nutrient Management Technical Standard

Missouri Concentrated Animal Feeding Operation Nutrient Management Technical Standard Missouri Concentrated Animal Feeding Operation Nutrient Management Technical Standard March 4, 2009 Division of Environmental Quality Water Protection Program I Introduction A. Authority and Purpose Missouri

More information

WATERSHED. Maitland Valley. Report Card 201

WATERSHED. Maitland Valley. Report Card 201 Maitland Valley WATERSHED Report Card 201 The Maitland Valley Conservation Authority has prepared this report card as a summary on the state of our forests, wetlands, surface water, and ground water resources.

More information

Title 26 DEPARTMENT OF THE ENVIRONMENT

Title 26 DEPARTMENT OF THE ENVIRONMENT Title 26 ALL NEW RESUBMITTED 11-8-17 DEPARTMENT OF THE ENVIRONMENT Subtitle 08 Water Pollution Chapter 11 Maryland Water Quality Trading Program.01 Purpose. Authority: Environment Article, 9-313, 9-315,

More information

Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan

Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan TR-20 is a computer program for the simulation of runoff occurring from a single storm event. The program develops flood hydrographs from runoff and routes

More information

Dane County Land and Water Resources Land Conservation Division

Dane County Land and Water Resources Land Conservation Division Dane County Land and Water Resources Land Conservation Division 2014 Adaptive Management Phosphorus Reductions Background As part of the 2014 Adaptive Management Pilot Project goals Dane County Land and

More information

Livestock and Poultry Environmental Learning Center Webcast Series June 20, From: G. Albrecht P. Ristow

Livestock and Poultry Environmental Learning Center Webcast Series June 20, From: G. Albrecht P. Ristow Nutrient Management Practices for Small Livestock Farms Dr. Michael L. Westendorf Extension Specialist Rutgers University Fred Kelly New Jersey USDA-Natural Resources Conservation Service Basic Nutrient

More information

Kapil Arora, Carl Pederson, Dr. Matt Helmers, and Dr. Ramesh Kanwar. DATE SUBMITTED: October 23, INDUSTRY SUMMARY

Kapil Arora, Carl Pederson, Dr. Matt Helmers, and Dr. Ramesh Kanwar. DATE SUBMITTED: October 23, INDUSTRY SUMMARY TITLE: Evaluating Nutrient (nitrogen and ortho-phosphate) Export with Subsurface Drainage Water from Spring Applied Swine Manure to Soybean Planted Micro-watersheds - NPB #12-117 INVESTIGATORS: INSTITUTION:

More information

Embedded Energy in Water Studies Study 1: Statewide and Regional Water-Energy Relationship

Embedded Energy in Water Studies Study 1: Statewide and Regional Water-Energy Relationship Embedded Energy in Water Studies Study 1: Statewide and Regional Water-Energy Relationship Prepared by GEI Consultants/Navigant Consulting, Inc. Prepared for the California Public Utilities Commission

More information

Securing and Protecting Water Rights and Uses in Arizona

Securing and Protecting Water Rights and Uses in Arizona Securing and Protecting Water Rights and Uses in Arizona L. William Staudenmaier One Arizona Center 400 East Van Buren Street, Suite 1900 Phoenix, Arizona 85004 2202 602.382.6000 602.382 6070 (fax) www.swlaw.com

More information

Comfort Lake-Forest Lake Watershed District Six Lakes Total Maximum Daily Load Implementation Plan

Comfort Lake-Forest Lake Watershed District Six Lakes Total Maximum Daily Load Implementation Plan Prepared by: for the Comfort Lake-Forest Lake Watershed District and the Minnesota Pollution Control Agency Comfort Lake-Forest Lake Watershed District Six Lakes Total Maximum Daily Load February 16, 2010

More information