Presentation to DMR and Minutes of Meeting
|
|
- Isaac Robbins
- 6 years ago
- Views:
Transcription
1 Annex C16 Presentation to DMR and Minutes of Meeting ENVIRONMENTAL RESOURCES MANAGEMENT SOUTH DEEP SOLAR PV EIA REPORT
2 Meeting Minutes Subject/Ref Venue Date of Meeting 02 October South Deep Solar PV EIA Presentation DMR Offices, 78 De Korte Street, Johannesburg Environmental Resources Management Building 32 1 st Floor The Woodlands Office Park Woodlands Drive Woodmead, 2148 T: F: Present Distribution Alan Cochran (AC) (ERM, Environmental Consultant) Puseletso Matete (PM) (South Deep, Project Proponent) Ravisha Ajodhapersadh (RA) (EGP, Project Developer) Mantwa Mathebula (MM) (EGP, Project Developer) Christinah Ramoelo (CR) (DMR, Case Developer) Musa Mangobe (MMe) (DMR, oversight) As above Date 11 October 2017 MINUTES 1. Welcome and Introductions a. AC welcomed all present. b. All introduced themselves 2. Health & Safety Moment a. AC noted the emergency exits and the procedures to be followed in case of emergency. 3. Objectives of the Meeting a. AC outlined the objectives of the meeting were to i. Present the findings of the Environmental Impact Assessment to the DMR. ii. Provide a platform for the DMR to ask questions about the project. 4. South Deep Solar EIA Presentation a. AC presented the EIA (See Annex A). Issues and questions were addressed as the presentation progressed; these are listed in item 5 below. 5. EIA Questions and Discussions a. MMe noted that the proponent should be accurate with the Listed Activities that are applied for as these will be audited by the Department once the project has been authorised. b. CR will need to conduct a site visit of the proposed project location once the final EIA has been submitted. It was also suggested that CR join a site visit to an operating Solar PV Facility in early November. Invitation is to be sent to the regional Manager suggesting CR attend. c. Detailed discussion of the site selection and alternatives analysis process. This has been outlined in detail in the EAI report. ACTION Proponent to double check Listed Activities applied for. EGP to invite CR to attend site visit to operating Solar PV Facility. Invitation to be sent to DMR Regional Manager requesting CR attendance. Note.
3 Meeting Minutes d. AC noted the project will not be constructed with a wetland / water course. However, the project will be within 500m of a watercourse and thus the necessary Water Use Licence Application process has been initiated. e. MMe noted that GDARD have Gazetted a new Environmental Management Framework (EMF) and that this should be consulted for the project f. Terrestrial Ecology: The areas designated by GDARD as Important and Ecological Support are not 100% accurate, but serve as a guide to the specialist terrestrial ecologist. The terrestrial ecologist has thus mapped areas which are Natural Habitat and Modified Habitat. The areas that are defined as Natural Habitat are of concern and the developer is working on way to optimise the project layout and reduce the impact on these areas. Additionally the developer and proponent are looking at developing Additional Conservation Actions (ACA s) to account for the potential residual impact on the Natural Habitat (Important areas). g. There are 20 mine employees that have an agreement with the mine to graze their cattle on the land earmarked for the proposed project. Thus the mine is in discussions with these people on alternative locations to graze their cattle. h. There are several Cultural heritage features identified. Most of these are of low heritage significance. There is a grave on the proposed site. The developer has optimized the project layout to avoid the grave as well as provide access to the grave for family members. i. Financial Provisions: The draft EIA includes Financial Provisions for decommissioning and closure. This must be updated based on the optimised layout. MMe noted that ERM should double check that the latest DMR calculation sheet has been used to generate this and that he would send ERM the latest calculation sheet. It may be useful to have the financial provisions independently audited prior to submission. DMR informed the Proponent and Project Developer that prior to any issuance of an Environmental Authorisation (EA), the financial provision in terms of closure and rehabilitation will be requested in writing by the DMR to the Proponent. Additionally the Proponent will need to enact payment of the financial provision prior to issuance of the EA and the EA will not be issued without the financial provisions being in place. MMe noted that the Proponent and the Developer should ensure that it is covered under their contractual agreement. j. In terms of consultation of key authorities, MMe noted that as long as the proponent has proof of submission of the Draft Scoping Report and the Draft EIA to the various key commenting Note. Proponent to consult the new GDARD EMF. Note. Note. Note. Proponent to check Financial Provisions calculation sheet is the latest one and to update in accordance with the optimized site layout. MMe to share the latest financial provisions calculation sheet with ERM. Proponent to consider having the updated financial provisions independently audited prior to submission. Note. Proponent to include proof of delivery of reports
4 Meeting Minutes authorities / departments (DAFF, DWS, GDARD, and Municipality) then this is sufficient. k. Mining Charter is not applicable to this project. This needs to be explained in the Comments and Responses Report. 6. Discussion: Transfer of Environmental Authorisation and requirement for Section 102 Amendment to Mining Right. a. Transfer of the Environmental Authorisation from South Deep to EGP should be straight forward. Proponent should make use of the NEMA (DEA) form for this. b. EGP await DMR Regional Director (RD) response to letter regarding Section 102. MMe suggested setting up a meeting with the RD to discuss this issue. in PPP chapter annexes. Note. Note. RA and MM to request meeting with DMR Regional Director. Annexes Annex A: _DMR EIA Presentation_ pdf
5 Environmental Impact Assessment for the South Deep Solar PV Power Plant DMR Meeting 2 October 2017 Insert then choose Picture select your picture. Right click your picture and Send to back. Copyright 2017 by ERM Worldwide Group Limited and/or its affiliates ( ERM ). All Rights Reserved. No part of The The business world s leading of sustainability sustainability consultancy this work may be reproduced or transmitted in any form or by any means, without prior written permission of ERM.
6 Presentation Outline Welcome and Introductions Health & Safety Moment Objectives of the Meeting Introductions About the Project The EIA Process Environmental & Social Baseline Potential Impacts Key Impacts and Mitigation Measures Environmental Management Programme Report Public Consultation Process The Way Forward Water Use Licence Application (WULA) Notice Questions, Comments, and Discussion 2
7 Objectives of the Meeting Present the findings of the Environmental Impact Assessment to the DMR. Provide a platform for the DMR to ask questions about the project. 3
8 Introductions Project Proponent Project Developer Global producer of gold with operations in Australia, Ghana, Peru and South Africa. Gold Fields in collaboration with Enel Green Power is proposing to develop a 40MW Solar PV Plant at the South Deep Gold Mine near Westonaria, Gauteng Independent Consultant Global Sustainability Consultancy. Independent Environmental Assessment Practitioner (EAP). Responsible for conducting the EIA and public participation process. Leader in the renewable energy sector with operations in Europe, Americas, Asia, Oceania and Africa 4
9 Project Need and Desirability The PV facility is desired to: Supplement the Mine s power supply with green/ clean energy Diversify the Mine s energy mix to reduce the mines reliance on fossil fuels and include renewable energy Contribute to the Mine s strategic objective to reduce energy costs and decrease the environmental footprint of the mine Why Solar PV? Well established technology Economic return on investment time (two years on a year life span) Construction process is simple Small land-take footprint when compared to other similar technologies Good sighting options as they can be constructed on sloping landscapes 5
10 Project Location The site is within the existing South Deep mining right, adjacent to existing mining operations: 6
11 Activity and Technology Alternatives Activity alternatives considered included other power generation options: Diesel fired power plant Gas-fired power plant Wind farm facility Solar power plant Solar was found to be the best suited generation alternative. Within solar the following technologies were considered: Concentrated Solar Power (CSP) Concentrated Photovoltaic (CPV) Photovoltaic panels (PV) Photovoltaic panels were found to be the preferred technology alternatives. 7
12 Site Alternatives 8
13 Motivation for Proposed Site The site is a mixture of modified and natural habitat and is currently used for grazing Located next to the mine s main access road The entire project footprint (40MW) can be accommodated The site is comparatively flat Ease of interconnection with Mine network The site is close to existing Mine infrastructure 9
14 Project Description 40MW Solar PV Plant occupying a maximum area of 130 ha (1.3 km 2 ) consisting of: Single axis tracking Solar PV panels/modules arranged in arrays PV module mountings DC-AC current inverters and transformers Substation and connection to Mine s 11kV distribution line Underground cabling On-site buildings (including an operational control centre, office, ablutions and guard house) Access roads and internal road network 10
15 Project Description Electrical Transformer Typical PV Arrays 11 Typical Substation
16 Project Layout 12
17 The EIA Process The Project requires full Scoping and EIA Processes in terms of National Environmental Management Act, 1998, (Act No. 107 of 1998), as amended (NEMA). 13
18 Environmental Baseline: Soils & Land Capability 94.8 ha has Class VI grazing land capability: it has the ability to support livestock farming (grazing) 26.6 ha has Class IV land capability: arable but with severe climate and terrain limitations that restrict crop yield. 9.5 ha has Class III land capability: suitable for crop production but with climate limitations that restrict yield. According to this classification system, the project site is therefore most suitable to light and moderate grazing, forestry and wildlife as an agricultural or ecological land use. 14
19 Environmental Baseline: Wetlands Two main wetland systems are associated with the project site: Channelled valley bottom wetland to the west and an unchannelled valley bottom to the east. Both wetlands have a present Ecological Status Score of C (the impact of the modifications on the hydrological integrity is identifiable but limited). The Loopspruit flanks the footprint to the west and the Kariegaspruit to the east. 15
20 Environmental Baseline: Terrestrial Ecology The vegetation type is Rocky Highveld Grassland, of which a total of 60% is transformed and only 1.38% is conserved. Natural grassland 68 ha (52%), Modified grasslands 62 ha (48%) Gauteng Conservation Plan: Important Area 70 ha (54%) Ecological Support 13 ha (10%) 16
21 Social Baseline: Socio-Economic Gauteng Provincia l Governm West ent Rand District Municipa Rand lity West City Local Municipa lity Ward 30 Administrative Structure Percent Demographics West Rand District Municipality Randfontein Local Municipality Westonaria 17 Percent 80% 70% 60% 50% 40% 30% 20% 10% 0% Mining and Quarrying General Wholesale and government and retail, trade personal services Economic Activities Finance and business services Manufacturing Construction Transport and communication Westonaria Randfontein Local Municipality West Rand District Municipality Electricity, gas and water Agriculture, fishing and forestry
22 Social Baseline: Socio-economic Employment Education Health Unemployment in WRDM: 26.7% 30% over age 20 in WRDM have completed secondary School. There are clinics located in most of the urban centres within Westonaria, including Thusanang. Unemployment rate for females in Westonaria was 48% in 2011, significantly higher than that of the male population (19%). reflects the higher demand for male labour by the mining sector. Within the RWC Local Municipality, the number of people completing secondary school has increased from 30 percent to approximately 35 percent between 2011 and Overall, prevalence the HIV/ AIDS has been quite stable in the WRDM, decreasing from 7.9% in 2003 to 7.6% by 2013 in the Randfontein Local Municipality and decreasing from 10.3% to 10.09% in the Westonaria Local Municipality over that same period 18
23 Social Baseline: Cultural Heritage 19 Built Environment (Section 34 of the NHRA) Feature 1: ephemeral stone wall foundations (GP.C). Feature 2: remains of a rectangular stone walled house (GP.C). Feature 3: Ruins of old Farm house (GP.C). Feature 4: Large stone cattle kraal (GP.B). Feature 5: ephemeral rectangular stone packed foundations (GP.C). Feature 6: Remains of old farm house (GP.C). Archaeological and palaeontological resources (Section 35 of the NHRA) No archaeological sites of significance were recorded during the survey. Burial Grounds and Graves (Section 36 of the NHRA) Feature 3: The grave is that of Elisabeth Gezina Prinsloo, born on the 12th of October 1879 and who passed away on the 30th June The site is of high social significance (GP.A). Field Rating Key Grade Significance Recommended Mitigation National Significance (NS) Grade 1 - Conservation; national site nomination Provincial Significance (PS) Grade 2 - Conservation; provincial site nomination Local Significance (LS) Grade 3A High significance Conservation; mitigation not advised Local Significance (LS) Grade 3B High significance Mitigation (part of site should be retained) Generally Protected A (GP.A) - High/medium significance Mitigation before destruction Generally Protected B (GP.B) - Medium significance Recording before destruction Generally Protected C (GP.C) - Low significance Destruction
24 Social Baseline: Visual Resource A Class IV Visual objective was assigned to the two landscapes of the proposed development area. This was due to the Low Scenic Quality of the resource as well as the anticipated Low Receptor Sensitivity to landscape change. The main findings: The two broad brush landscape types are similar in character. The overall site Scenic Quality is graded Low, predominantly due to the lack of uniqueness of the site, the homogeneity of the vegetation and the degraded adjacent mine landscapes. Scenic Quality Receptor Sensitivity Visual Resources A= scenic quality rating of 19; B = rating of 12 18, C= rating of 11 H = High; M = Medium; L = Low VRM NAME Landform Vegetation Water Colour Scarcity Adjacent Landscape Cultural Modifications Sum Rating Type of Users Amount of Use Public Interest Adjacent Land Uses Special Areas Rating Class Rand Highveld Grassland C M H L L L L IV Transformed Rand Highveld Grassland C M H L L L L IV 20 SUM (Avg) C M H L L L L
25 Potential Impacts There were 25 potential impacts identified. Embedded controls considered and mitigation measures developed. Impact significance before mitigation and after mitigation (residual impact) assessed. Topic Impact Statement Significance (Premitigation) Residual Impact Significance (Postmitigation) Surface Water & Wetlands Chemical pollution of surface water due to solar PV power plant construction and operational activities Minor (-ve) Negligible (-ve) Surface Water & Wetlands Altered surface hydrology due to the construction and operation of the solar PV power plant Negligible (-ve) Negligible (-ve) Surface Water & Wetlands Increased sediment load in surface water systems due to construction and operation of the solar PV power plant Negligible (-ve) Negligible (-ve) Terrestrial Eosystems Loss of natural terrestrial grassland habitat due to the construction of the solar PV power plant Moderate (-ve) Moderate (-ve) Terrestrial Eosystems Increased risk of invasive alien plant encroachment due to clearing of grassland vegetation Moderate (-ve) Minor (-ve) Terrestrial Eosystems Loss and disruption of ecosystem services due to clearing of grassland vegetation Minor (-ve) Negligible (-ve) Soils and Land Capability Susceptibility to erosion due to solar PV power plant construction activities Minor (-ve) Negligible (-ve) Soils and Land Capability Susceptibility to erosion due to solar PV power plant operational activities Negligible (-ve) Negligible (-ve) Soils and Land Capability Chemical pollution of soils due to solar PV power plant construction activities Moderate (-ve) Minor (-ve) Soils and Land Capability Chemical Pollution of soils due to solar PV power plant operational activities Negligible (-ve) Negligible (-ve) Soils and Land Capability Loss of land capability due to construction of the solar PV power plant Moderate (-ve) Moderate (-ve) Socio-economic Increased employment, local business opportunities, and skills enhancement due to the construction and decommissioning of the solar PV power plant Positive (+ve) Positive (+ve) Socio-economic Increased employment, local business opportunities, and skills enhancement due to the operation of the solar PV power plant Positive (+ve) Positive (+ve) Socio-economic Increased socio-economic spending during the operation of the PV power plant Positive (+ve) Positive (+ve) Socio-economic Loss of access to grazing land due to the construction and operation of the solar PV power plant Minor (-ve) Minor (-ve) Socio-economic Reduced community health and safety due to the presence of temporary construction workforce and additional job seekers Moderate (-ve) Moderate (-ve) Socio-economic Increased incidence of crime due to the increased activity associated with the construction of the solar PV power plant Moderate (-ve) Minor (-ve) Socio-economic Increased incidence of nuisance factors (noise, dust, and traffic) due to the construction of the solar PV power plant Moderate (-ve) Minor (-ve) Socio-economic Increased risk to worker rights, health, and safety due to construction and operation of the solar PV power plant Minor (-ve) Minor (-ve) Cultural Heritage Loss of cultural heritage resources due to construction of the solar PV power plant Negligible (-ve) Negligible (-ve) Cultural Heritage Damage or destruction of a grave site due to the construction of the solar PV power plant Moderate (-ve) Moderate (-ve) Visual Resources Reduction in visual resources for the Northern Receptors due to the construction of the solar PV power plant Minor (-ve) Minor (-ve) Visual Resources Reduction in visual resources for the Western Receptors due to the construction of the solar PV power plant Moderate (-ve) Moderate (-ve) Visual Resources Reduction in visual resources for the Southern Receptors due to the construction of the solar PV power plant Negligible (-ve) Negligible (-ve) Visual Resources Degradation of the landscape to due to the construction and operation of the solar PV power plant Minor (-ve) Minor (-ve) 21
26 Key Impacts and Mitigation Measures Loss of natural terrestrial grassland habitat due to the construction of the solar PV power plant: The proponent to set aside an area of natural grassland, that supports the same vegetation as within the site, on the edge of the site that will be protected from construction activities and any future development and that will be used to translocate plant species when construction commences. In order to achieve No Net Loss it is recommended that the proponent, in consultation with the Gauteng Department of Agriculture and Rural Development (GDARD) and any relevant stakeholders, identify feasible conservation actions designed to compensate for residual adverse biodiversity impacts arising from the proposed project development and persisting after appropriate avoidance, minimization and restoration measures have been taken. The conservation action must be designed to conserve the same biodiversity values that are being impacted by the project. These conservation actions must be measurable conservation outcomes for biodiversity and must be demonstrated in situ (on-the-ground), on an appropriate geographic scale (e.g., local, landscape-level, national, regional) and be implemented for the lifetime of the solar project. 22
27 Key Impacts and Mitigation Measures Loss of access to grazing land due to the construction and operation of the solar PV power plant: The proponent to engage with the cattle owners to inform them that the land will no longer be available for grazing and to investigate the possibility of providing suitable alternative land to graze cattle. Loss of cultural heritage resources due to construction of the solar PV power plant AND Damage or destruction of a grave site due to the construction of the solar PV power plant: The proponent to engage the Heritage and other relevant authorities in a timely manner to obtain the necessary permits for the destruction of heritage resources and the relocation of the grave. 23
28 EMPr Environmental Management Programme Report (EMPr) Environmental and Social Management System (ESMS) Planning Environmental and Social Commitments Management Plans and Procedures Implementation Roles and Responsibilities Training and Awareness Communication Documentation Managing Changes to Project Activities or Project Setting Stakeholder Engagement Grievance Mechanism Pre-construction Management and Monitoring Measures Terrestrial Ecosystems Socio-economic Cultural Heritage Construction Management and Monitoring Measures Surface Water and Wetlands Terrestrial Ecosystems Soils and Land Capability Management Socio-Economic Cultural Heritage Visual and Landscape Operational Management and Mitigation Measures Surface Water and Wetlands Terrestrial Ecosystems Soils and land Capability Socio-Economic Decommissioning Management and Monitoring Measures 24 Specific Management Plans and Procedures 1. Waste Management Plan 2. Stormwater Management Plan 3. Traffic Management Plan 4. Emergency Response Plan 5. Grievance Mechanism 6. Cultural Heritage Chance Finds Procedure 7. Alien Invasive Plant Management Plan 8. Plant Rescue and Protection Plan 9. Construction Revegetation and Rehabilitation Plan 10. Decommissioning, Closure, and Rehabilitation Plan
29 Public Consultation Process: Scoping Phase Site Notices; News paper adverts; Stakeholder database development; Calling and ing BID; Project website; 30 day comment period from 22 May 2017 to 27 June 2017 Key Stakeholder Meetings: DMR 8 March 2017 Rand West Stakeholders Forum 17 May 2017 Adjacent Land Owners 27 June 2017 Cattle Owners Committee Representative 27 June 2017) Public Meeting / Open Day 7 June 2017 Hard copy of Draft Scoping Report (DSR) submitted to: DMR, DAFF, DWS, GDARD, WRDM. Hard copy of DSR made available at Westonaria, Carletonville, and Fochville Libraries. 25
30 Public Consultation Process: EIA Phase Notifying Stakeholders (Calls, s, sms s, website); 30 day comment period from 28 August 2017 to 27 September 2017 Public Meeting 13 September 2017 Hard copy distribution of Draft EIA Report to: DMR, DAFF, DWS, GDARD, WRDM. Report uploaded to project website; Hard copy of Draft EIA made available at Westonaria, Carletonville, and Fochville Libraries. 26
31 Main Stakeholder Questions & Concerns Skills Development Recruitment Process Mining Charter Applicability Stakeholder Communication Employment Opportunities Local SMME s (procurement process) Community Development / Investment 27
32 Way Forward Finalise EIA & EMPr: Week 2-6 October Submit to DMR: Week 9-13 October DMR Review Environmental Authorisation 28
33 Water Use Licence Application (WULA) The following activities apply for the project in terms of the National Water Act, 1998 (NWA) (Act No 36 of 1998): Section 21(c): Impeding or diverting the flow of water in a water course Section 21(i): Altering the bed, banks, course or characteristics of a watercourse The application phase to authorise these activities has commenced with the Department of Water-affairs. 29
34 Questions, Comments, & Discussion CONTACT DETAILS: ERM Johannesburg Office Tel: Fax: Postnet Suite 624, Private Bag x29, Gallo Manor, 2052 Project Website: ERM Ref Number: Thank you 30
Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017
Annesley Andalusite Mine: Section 24G Rectification Process Consultation with community members 15 June 2017 AGENDA Welcome and introduction Meeting protocol Purpose of the meeting Project background Project
More informationPROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.
ENVIRONMENTAL IMPACT ASSESSMENT (EIA), MINING RIGHT APPLICATION AND OTHER ANCILLARY LICENSING PROCESSES: PROPOSED PLATINUM GROUP METALS MINE & ASSOCIATED INFRASTRUCTURE PROPOSED VOLSPRUIT MINE, MOKOPANE
More informationOttawa-Trussler Area Sewage Facility Class Environmental Assessment
Welcome to the Ottawa-Trussler Area Sewage Facility Class Environmental Assessment Public Open House May 7, 2013 September 25, 2013 Welcome The purpose of this second Public Open House is to: Present the
More informationWIND ENERGY AND YOUR LAND
WIND ENERGY AND YOUR LAND WIND FARMS & your land Wind turbines and farmland can work very well together, but choosing the right partner is critical. RES works with landowners, farmers and estate managers
More informationComprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:
Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment
More informationC&B Alberta Solar Development ULC
Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by
More informationFULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS
FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Agricultural Expansion on Portion 2 of Farm 92, Tregaron, known as Sylvania, Sundays River Valley Municipality BACKGROUND INFORMATION DOCUMENT,
More informationPOSTMASBURG SOLAR PV ENERGY FACILITY 2 (PTY) LIMITED
(Solar International, 2013) POSTMASBURG SOLAR PV ENERGY FACILITY 2 (PTY) LIMITED Final EIR Technical Layout Development Report, March 2015 Prepared for: Mr D. Holder Cape EAPrac dale@cape eaprac.co.za
More informationNxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015
Nxuba Wind Farm NERSA PUBLIC HEARINGS 10 September 2015 1 Nxuba Wind Farm has been appointed as a Preferred Bidder in the Fourth Round of the Department of Energy s (DoE) Renewable Energy IPP Procurement
More informationLeaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood
Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood Purpose of this Public Information Centre Provide you with an update on Hydro One s infrastructure
More informationLESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006
LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 AGENDA Opening and Welcome Introduction of Consultants Profile of Izwelisha Consortium Explanation of the EMF process Environmental
More information8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION)
8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION) In order to manage the construction phase impacts associated with the establishment of the Compilation Yard and the Common User
More informationNatural Systems Planning Primer
Natural Systems Planning Primer Lise.Guevremont@ottawa.ca Amy.Macpherson@ottawa.ca Land Use and Natural Systems Unit Planning and Growth Management November 2015 1 Welcome Policy Framework Development
More informationViridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton
Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management
More informationShell Quest Carbon Capture and Storage Project. Shell Canada Limited
SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries
More information4 PROJECT ALTERNATIVES
4 PROJECT ALTERNATIVES 4.1 Introduction In terms of the EIA Regulations published in Government Notice R543 of 2 August 2010 in terms of Section 24 of the National Environmental Management Act (Act No.
More informationAppendix General Environmental Risk Analysis
Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified
More informationDraft Scoping Report. Delivering sustainable solutions in a more competitive world
Draft Scoping Report Proposed 90 MW Drennan Photovoltaic (PV) Power Facility, Eastern Cape Solaire Direct Southern Africa (Pty) Ltd DEA Ref: 14/12/16/3/3/2/359 November 2012 www.erm.com Delivering sustainable
More informationEnvironmental Management Programme: Langhoogte Wind Farm, Western Cape
SAGIT Energy Ventures Environmental Management Programme: Langhoogte Wind Farm, Western Cape Version 1 February 2013 J30284A Head Office 14 Eglin Road, Sunninghill 2191 Johannesburg, South Africa Tel:
More informationBasic Assessment for the Vopak Efficiency (Growth 4) Project, Durban, South Africa
Basic Assessment for the Vopak Efficiency (Growth 4) Project, Durban, South Africa Open House Public Meeting Insert then choose Picture select your picture. 30 June 2016 Right click your picture and Send
More informationAddition to Section 4 - Special Use Regulations
Large-Scale Ground-Mounted Solar Photovoltaic Installations Addition to Section 4 - Special Use Regulations 4.4 Large Scale Ground-Mounted Solar Photovoltaic Installations 4.4.1 Purpose The purpose of
More informationSevern Sun Solar Project. Invenergy LLC Public Community Meeting August 6, 2015
Severn Sun Solar Project Invenergy LLC Public Community Meeting August 6, 2015 Invenergy LLC is a Qualified Applicant Invenergy LLC qualified to participate in the IESO Large Renewable Procurement - Request
More informationBackground Information Document and Invitation to Comment
Background Information Document and Invitation to Comment Environmental Impact Assessment for the Proposed Drennan Photovoltaic (PV) Solar Power Plant, Cradock, Eastern Cape Province Scoping/EIA DEA Ref
More informationDRAFT BASIC ASSESSMENT REPORT
DRAFT BASIC ASSESSMENT REPORT Basic Assessment for the proposed expansion of a pig production and vegetable enterprise on Portion 56 of the Farm Houtpoort 392 in Heidelberg, Gauteng Basic Assessment for
More informationC&B Alberta Solar Development ULC
Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017
More informationANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:
ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not
More information5600. LARGE-SCALE GROUND-MOUNTED SOLAR PHOTOVOLTAIC INSTALLATIONS
To Wit: To see if the Town will vote to amend the Town of Westborough Zoning Bylaws, Article 2, District Regulations, Section 2300, Use Regulations Schedule; and to amend Article 4, Special Regulations
More informationProvincial Policy Statement 2014 Training Aid
This job aid has been developed for education and training purposes as a high-level summary of the policy changes in the PPS 2014. It should not be relied upon as a substitute for specialized legal or
More informationChapter 17 Cumulative Impacts
Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...
More informationCanadian Solar Developers Ltd.
Canadian Solar Developers Ltd. Type of Document Draft Report Project Name Proposed Ground Mount Solar Facility L.P #5 8338 Scotchmere Drive, Strathroy, ON OPA FIT Program: FIT-FL67GB5 Project Number V00002250-00
More informationAssessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture
Assessment of Landfill Footprint Alternatives Figure 422 99 Option #4 Impact on Agriculture The net effects with respect to continued service to customers, the optimized site life/ capacity is 65 million
More informationDarial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP
Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation
More informationESIA for the proposed Baynes Hydropower Project:
ESIA for the proposed Baynes Hydropower Project: Public Scoping Meeting: Windhoek Special Arrangements Visitors from Kunene Region Liaison Officer will translate for them. Meeting filmed. Microphones to
More informationENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass
ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT
More informationAnnex F Scoping Checklist
Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve
More information6 Risk assessment methodology
Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management
More informationNOTICE OF PREPARATION AND SCOPING MEETING
April 9, 2013 NOTICE OF PREPARATION AND SCOPING MEETING SUBJECT: Notice of preparation of a Draft Environmental Impact Report (DEIR) for the California Flats Solar Project. The County of Monterey will
More informationC&B Alberta Solar Development ULC
Decision 22447-D01-2017 Vauxhall Solar Power Plant July 4, 2017 Alberta Utilities Commission Decision 22447-D01-2017 Vauxhall Solar Power Plant Proceeding 22447 Application 22447-A001 July 4, 2017 Published
More informationStrategic Environmental Assessments (SEAs) for large scale infrastructure projects
Strategic Environmental Assessments (SEAs) for large scale infrastructure projects 1 Presented by: Lydia Cape (Pr. Sci. Nat. Environmental Sciences) Council for Scientific and Industrial Research, South
More informationNew York Community Solar Facility Decommissioning Plan
New York Community Solar Facility Decommissioning Plan July 2017 Prepared For: Town of Dryden, NY Delaware River Solar 33 Irving Place, Suite 1090 New York, NY 10003 Table of Contents Page 1. Introduction
More informationImplementing the Mitigation Hierarchy
Implementing the Mitigation Hierarchy Presented by National Biodiversity and Business Network IUCN De Beers Group of Companies 10 August 2016 Objectives for the day Provide an overview of the overall framework
More informationEAST-WEST TIE TRANSMISSION PROJECT
EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you
More informationSummary of Preparatory Study
Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic
More informationConservation and Reclamation INFORMATION LETTER. Environmental Protection Guidelines for Oil Production Sites - Revised January 2002
March 2002 Conservation and Reclamation INFORMATION LETTER C&R/IL/02-1 Environmental Protection Guidelines for Oil Production Sites - Revised January 2002 CHANGES TO THE INFORMATION LETTER This Information
More informationSection 75J of the Environmental Planning & Assessment Act 1979
Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 I approve the project application referred to in schedule 1, subject to the conditions in schedule 2. These conditions are
More informationEIA Screening Tool Sensitivity Theme for Reporting
EIA Screening Tool Sensitivity Theme for Reporting 13 th National Biodiversity Planning Forum 8 June 2016 Environmental Advisory Services Nicolene Fourie Chief GIS Specialist: GIS Operations Directorat:
More informationENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA DEA Reference Number: 12/12/20/2175 BACKGROUND INFORMATION
More informationUkraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre
Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre Objectives of Strategic Environmental Review (SER) The European Bank for Reconstruction and Development
More informationCONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5
CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey
More informationCoire Glas Pumped Storage Scheme
About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,
More informationGUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK
PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the
More informationClifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary
Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474
More information407 TRANSITWAY. Planning & Preliminary Design
FROM EAST OF HIGHWAY 400 TO KENNEDY ROAD GWP #252-96-00 Public Information Centre #2 June 24 th and 29 th, 2010 Purpose of Public Information Centre #2 The first Public Information Centre (PIC #1) was
More informationAugust. RE Capital 11 (Pty) Ltd. Solar farm development. August. Scoping Engineering Report
RE Capital 11 (Pty) Ltd. Solar farm development. August August Engineering overview and summary pertaining to environmental aspects of the RE Capital 11 (Pty) Ltd. Solar Development. Compiled by Solek
More informationHydropower Sustainability Assessment Protocol Section III Trail ESKOM. Ingula Pumped Storage Scheme. November 2009
Hydropower Sustainability Assessment Protocol Section III Trail ESKOM Ingula Pumped Storage Scheme November 2009 Assessor: Rob Griffin Date: 2009-11-25 Table of Contents 1 Introductory Information... 3
More informationAPPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval
APPENDIX 2 Nova Scotia Department of Environment and Labour Terms and Conditions for Approval Approval Approval Date: March 14, 2007 Keltic Petrochemicals Inc. LNG and Petrochemical Plant Facilities Keltic
More informationNERSA Public Hearing Dyason s Klip 1 (Pty) Ltd
Scatec Solar ASA NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd Presented by Jan Fourie Business Development Manager September 2015 Project Company-General Information Dyason s Klip 1 (Pty) Ltd (formerly
More informationReport for Agenda Item: 2
QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage
More informationCMPDI. 4.6 Mine Closure Plan
4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.
More informationEWA ENVIRONMENTAL AFFAIRS
326 National Environmental Management Act (107/1998): Amendments to the Environmental Impact Assessment Regulations, 2014 40772 STAATSKOERANT, 7 APRIL 2017 No. 40772 211 DEPARTMENT OF ENVIRONMENTAL AFFAIRS
More informationDraft Queensland solar farm guidelines: Guidance for local governments
Draft Queensland solar farm guidelines: Guidance for local governments March 2018 State of Queensland, March 2018. Published by the Department of State Development, Manufacturing, Infrastructure and Planning,
More informationOPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME
OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen
More informationNOVEMBER 2016 REVISION 0. Prepared by: JG AFRIKA (PTY) LTD
DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT & ENVIRONMENTAL MANAGEMENT PROGRAMME REPORT: PROPOSED ESTABLISHMENT OF A STAGED MOBILE CRUSHING PLANT WITHIN THE CURRENT FOOTPRINT OF THE AMASUNDU GRAVEL CC
More informationChapter 10 Natural Environment
Chapter 10 Natural Environment Existing Conditions The Natural Environment Element addresses the protection, conservation, preservation, and restoration of the natural resources the Bayview Ridge Subarea,
More informationH 6062 S T A T E O F R H O D E I S L A N D
LC001 01 -- H 0 S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 01 A N A C T RELATING TO AGRICULTURE AND FORESTRY - FARM CONSERVATION AND RENEWABLE ENERGY Introduced By: Representative
More informationCottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:
Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by
More informationCornwall Solar Project Renewable Energy Approval Modification Report
Cornwall Solar Project Renewable Energy Approval Modification Report Algonquin Power Co 2845 Bristol Circle Oakville ON, L6H 7H7 Contents Contents... 1 Introduction... 2 Summary and Rational for Minor
More informationFINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE
FINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE OURAY RANGER DISTRICT OURAY COUNTY, COLORADO BACKGROUND The Owl Creek Gravel Pit, also known as the Spruce Ridge Pit,
More informationENVIRONMENTAL IMPACT ASSESSMENT EIA PHASE
ENVIRONMENTAL IMPACT ASSESSMENT EIA PHASE PROPOSED ESTABLISHMENT OF THE PUMPED STORAGE SCHEME AND ASSOCIATED INFRASTRUCTURE IN THE STEELPOORT AREA, LIMPOPO AND MPUMALANGA PROVINCES FINAL MINUTES OF THE
More informationPollution & Environmental Harm
Pollution & Environmental Harm Fact Sheet 27 Updated December 2010 An introduction to Pollution and Environmental Harm There are a large range of activities that can lead to pollution or cause environmental
More informationAnnex K. Environmental and Social Management Programme (EMPr)
Annex K Environmental and Social Management Programme (EMPr) CONTENTS ABBREVIATIONS 1 DEFINITIONS AND TERMINOLOGY 1 1 BACKGROUND TO PROJECT 4 1.1 REGULATORY REQUIREMENT FOR THE EMPR 4 1.2 OBJECTIVES OF
More informationRE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS
6 October 2016 Dear Stakeholder, RE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS As indicated in our previous notification dated 12 February 2016, Consol Glass (Pty) Limited ( Consol
More information18 Cumulative Impacts and Interaction of Effects
18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly
More information06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards
06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards THE APPLICATION Planning permission is sought for the construction of a noise attenuation
More informationGRAND NIAGARA Proposed Secondary Plan
GRAND NIAGARA Proposed Secondary Plan Public Open House #3 January 17. 2017 scope + process BUILT Grand Niagara Secondary Plan The Grand Niagara Secondary Plan will establish a framework for the future
More informationGeneral Certificate of Education Advanced Level Examination January 2012
General Certificate of Education Advanced Level Examination January 2012 Geography GEOG3 Unit 3 Contemporary Geographical Issues Monday 30 January 2012 1.30 pm to 4.00 pm For this paper you must have:
More informationApplications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments
Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June
More information9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:
SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities
More informationGaliuro Exploration Drilling Project
Galiuro Exploration Drilling Project Range and Noxious Weeds Report Prepared by: Gwen Dominguez Range Staff for: Safford Ranger District Coronado National Forest Date September 2, 2016 Forest Plan/Policy
More informationHigh Speed Rail (London- West Midlands)
High Speed Rail (London- West Midlands) Draft Environmental Minimum Requirements Annex 4: Draft Environmental Memorandum November 2013 ESA 4.2 High Speed Rail (London- West Midlands) Draft Environmental
More informationNoront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017
Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach October 2017 (Simulated FPF) INTRODUCTION Noront is proposing to develop a Ferrochrome Production Facility (FPF) in Northern
More informationPortbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009
Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted
More information1 ENVIRONMENTAL MANAGEMENT PROGRAMME 1.1 INTRODUCTION
1 ENVIRONMENTAL MANAGEMENT PROGRAMME 1.1 INTRODUCTION This section presents the Draft Management Programme (EMPr) for the Proposed Acetylene Gas Manufacturing Plant, located in Daleside (hereafter referred
More informationProject Briefing. Community Consultative Committee
Project Briefing Community Consultative Committee 5 th October 2017 Contents Goldwind - Overview Coppabella Wind Farm Project Overview Modification Application Host Landowners and Neighbours Community
More informationDRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT
Portion 1 and Portion 4 of Cape Farm 1183 (Erf 277), Western Cape Scoping and Environmental Impact Assessment for the proposed Atlantis Gas-to-Power facility on Cape Farm 1183-4-1 (Erf 277), Western Cape
More informationTimber harvesting in native State forests
OCTOBER 2008 PRIMEFACT 693 Timber harvesting in native State forests Forest Management There are approximately 2 million hectares of native State forests in NSW. In managing these areas, Forests NSW aims
More informationIntroduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and
Introduction There are many tools that a reviewer of environmental impact assessment documents can use to help determine whether such documents are complete and adequate. Among the powerful tools that
More informationThe Effluent Permitting Process under the Environmental Management Act. An Overview for Mine Project Applicants
The Effluent Permitting Process under the Environmental Management Act An Overview for Mine Project Applicants APRIL 2013 Disclaimer This document does not replace the Environmental Management Act or its
More informationChapter 13 of Agenda 21
Chapter 13 of Agenda 21 What is Agenda 21? Agenda 21 is the global plan of action that was adopted at the United Nations Conference on Environment and Development (UNCED) held in Rio de Janeiro, Brazil,
More informationDISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS
DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver
More informationDistrict of North Vancouver Construction Traffic Management Plan Guidelines
District of North Vancouver Construction Traffic Management Plan Guidelines The District of North Vancouver is committed to ensuring that the disruptions to the community and traffic associated with construction
More informationKENT BREEZE WIND FARMS
Decommissioning Plan Report MAY 2010 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. DECOMMISSIONING PROCESS DESCRIPTION... 2 3. SITE RESTORATION... 3 4. EXCESS MATERIALS AND WASTE MANAGEMENT... 4 5. MANAGING
More informationSHAMS MA AN SOLAR PV POWER PLANT PROJECT (50MW) NON-TECHNICAL SUMMARY IN ENGLISH
SHAMS MA AN SOLAR PV POWER PLANT PROJECT (50MW) NON-TECHNICAL SUMMARY IN ENGLISH 21 October 2014 TABLE OF CONTENT Table of Content... i 1. Introduction... 1 1.1 Project Alternatives... 2 2. Project Description...
More informationEnvironmental Impact Report for the proposed establishment of a New Coal-Fired Power Station in the Lephalale Area, Limpopo Province
3. SCOPE OF ENVIRONMENTAL INVESTIGATIONS 3.1. Approach to Undertaking the Study An Environmental Scoping Study for the proposed establishment of a new coalfired Power Station, in Lephalale, was undertaken
More informationApplications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments
Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December
More informationPublic Information Centre No. 2
Public Information Centre No. 2 Wednesday April 20, 2011 4:00 pm to 7:00 pm City of Welland City Hall Area 2 Welland, Pelham, and Port Colborne Welcome to Public Information Centre No. 2 Please sign in
More informationTrenches combined with living hedges or grass lines Rwanda - Imiringoti
Trenches combined with living hedges or grass lines Rwanda - Imiringoti Trenches combined with living hedges or grass lines are slow-forming terraces to control soil erosion by changing the length of the
More informationAPPLICATION FOR A GENERATOR AND A SUPPLY CONNECTION AT THE SAME POINT OF SUPPLY TO THE ESKOM NETWORK. Revision September 13 July 2016
E Ph APPLICATION FOR A GENERATOR AND A SUPPLY CONNECTION AT THE SAME POINT OF SUPPLY TO THE ESKOM NETWORK Revision 08 01September 13 July 2016 Introduction (This form should be completed if the generator
More informationChapter 13 Management and Implementation
Chapter 13 Management and Implementation TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Overview of AGT Region Operating Management System... 13-1 13.3 Construction
More informationEnvironmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)
Checklist:. 10.Ports and Harbors (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders (3) Examination of Alternatives (1) Air Quality (2) Water
More information