1 John Hart Generating Station Replacement Project February 2018 Community Construction Update Report #56 Prepared by: Stephen Watson, BC Hydro (O) or (C)

2 Project Status Surface Works: Work on the control room for the intake (downstream of the dam) progressing, including floors, walls, roof and more; Surge tank earthfill backfilling continues about 70% complete; Excavation of the blast rock at the tailrace now complete; and Preparation work for pole installation that will connect the powerhouse to the substation. Underground Works: Installation of powerhouse suspended ceiling continues; Powerhouse office complex moving forward with electrical and drywall installations; Shotcrete touch-ups of the power tunnel continues, with lighting and other services being removed as the work moves towards the powerhouse; The rock trap, which is located just before the power tunnel manifold where water will enter the water bypass or generators, is now complete; and Generator installation work continues.

3 Project Schedule Early March: Permanently shutting down Generator 3 within the old generating station (moved from early February); Late March: Water Intake water up or water filling; Late March: Tailrace tunnel water up; April: Power tunnel water up; April 30: Reopening of Brewster Lake Road access across the John Hart dam (was closed for three years); May: Generating unit testing; June: First generating unit begins to generate electricity into the power grid; October: Commissioning of completed facility. Our anticipated water releases down Elk Falls Canyon (base flow 4 m3/s) in March: March 1-4: 10 m3/s March 5-9: 45 m3/s March 10-31: m3/s Flows are subject to change based on weather and available generators.

4 Construction Pictures John Hart Dam Feb 27 4

5 The same vantage point: a May 2017 photo on the left, and this month s picture on the right. 5

6 On the downstream side of the dam, the valves for water releases down Elk Falls Canyon. Construction Pictures John Hart Dam 6

7 The low level outlet on the left and the yearly fish habitat flow release valve on the right. Construction Pictures John Hart Dam 7

8 Final shotcrete touch-ups within the power tunnel. Construction Pictures John Hart Dam 8

9 9 The surge tank that connects to the power tunnel. The earthen area is being backfilled.

10 The surge shaft that connects to the surge tank 100 metres above. Power tunnel. 10

11 11 Entrance to the power tunnel manifold. The rock trap in the foreground is now complete.

12 12 View down the power tunnel manifold, with the water bypass inlets on the left and the turbine inlets further down.

13 13 The end of the power tunnel manifold with the water inlets to two turbines/generators.

14 Powerhouse view with the office space complex in the background. 14

15 15 Another vantage of the powerhouse. The circular turbine/generator pits are in the foreground.

16 A big focus now is pulling cable through the cable trays. 16

17 17 Pulling cable.

18 18 View down the service tunnel towards the powerhouse. The power cable civil work is being placed along the invert (floor) to connect the powerhouse to the substation.

19 19 View from main access tunnel into the powerhouse area.

20 Main access tunnel, taken from this location. Gate gallery. Entry into the powerhouse. 20

21 21 Gate gallery on the downstream side of the powerhouse.

22 22 Water bypass outlet into the surge chamber, located below the gate gallery.

23 View of the water outlets into the surge chamber, with water flows to turn 90 degrees and flow down the tailrace tunnel in the background. 23

24

25 Campbell River Community Liaison Committee Annual Tour The second group of committee members took a tour on Feb 2.

26 City of Campbell River Council And Senior Staff Annual Tour Feb 5

27 People Profile Chad Saunders About Chad Background: Chad drove logging trucks for six years until he switched careers to work in electrical. He s now a journeyman electrician and an 80-ton crane certified operator. He s been with FMI for almost 11 years (five years as a supervisor). Chad s experience involves work on many substations, such as the isolated phase bus upgrades at GM Shrum and other types of BC Hydro substation work, to mill shut downs. Home: Chad was born and raised in Lantzville, where he currently lives. Working on a project close to home is a rare and wonderful change for himself and his family. Hobbies: In his off-time Chad spends time with his family; his two boys Jack and Wyatt, and his wife Kelly. When he s not at work, you ll find him camping, hunting, and fishing. Project Responsibility: Chad works as a deputy project manager for FMI. His day-today involves construction planning, pricing and scheduling. I look forward to seeing the day-to-day progress at the site, overcoming the challenges that are put forth, and seeing everyone go home safe at the end of the day. Working on a project this complex is a challenge a fun challenge.

28 Construction Point Of Interest Each month, BC Hydro and InPower BC will provide a construction fact, occurrence, or situation. Watering up the new underground facility, step by step. The project is nearing another milestone with water being introduced in stages to the underground facility. While water up may sound as simple as turning on a tap or pulling a plug, it s actually a carefully done process. Step 1: The water intake and valves: First, we will have water from the new intake at the dam fill the water intake structure. Second, with water from the intake structure, we will then commission the two water release valves that will provide the water flow down Elk Falls Canyon. Step 2: Tailrace and power tunnel: To add water in tailrace tunnel, we will pull the metal stop logs at the tunnel outlet and slowly allow water to enter the tunnel. This may take a day. To fill the power tunnel, the large operating gate within the water intake structure will be opened in stages. There are seven steps for watering up the power tunnel and it may take two weeks to complete. Step 3: Start commissioning/wet testing: Once all the water is in, we will begin preparing for operation of the generators and water bypass facility.

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47 John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8 John Hart Generating Station Replacement Project December 2013 - January 2014 Community Construction Update Report #8 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16

John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16 John Hart Generating Station Replacement Project October 2014 Community Construction Update Report #16 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Campbell River System Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation Resource Management Nov 21, 2012 v6 Campbell River System Water Use Plan Page i Table of Contents

More information

PROJECT BRIEF for the John Hart Generating Station Replacement Project

PROJECT BRIEF for the John Hart Generating Station Replacement Project PROJECT BRIEF for the John Hart Generating Station Replacement Project Issue Date: March 13, 2012 TABLE OF CONTENTS John Hart Generating Station Replacement Project Page ii of 17 1. INTRODUCTION... 3 1.1

More information

Lower Mattagami River Project

Lower Mattagami River Project Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added

More information

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants Head Office Augustaanlage 62-64 D-68165 Mannheim Germany Reinhold Metzler Project manager Tel: +49-7531 3620 882 email: metzler@enerm.de RAIFFEISEN BANK SH.A. ALBANIA entecag Consulting & Engineering Bahnhofstr.

More information

Ingula Pumped Storage Scheme: Project Management Case Study

Ingula Pumped Storage Scheme: Project Management Case Study Ingula Pumped Storage Scheme: Project Management Case Study Colin Logan Project Manager Gibb Engineering & Science South Africa BRAAMHOEK CONSULTANTS JOINT VENTURE Definition of Project Management Planning,

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

WORKING WITH BC HYDRO GENERATION 10 YEAR CAPITAL PLAN

WORKING WITH BC HYDRO GENERATION 10 YEAR CAPITAL PLAN WORKING WITH BC HYDRO GENERATION 10 YEAR CAPITAL PLAN The main purpose of this document is to provide our suppliers insight into the upcoming Capital Plan at BC Hydro s dams and generating facilities.

More information

CASE STUDY OF INGULA AND LIMA PUMPED STORAGE SCHEMES

CASE STUDY OF INGULA AND LIMA PUMPED STORAGE SCHEMES CASE STUDY OF INGULA AND LIMA PUMPED STORAGE SCHEMES Frans Louwinger Engineering Department (Hydro), Eskom Enterprises Division, PO Box 1091, Johannesburg, 2000 SOUTH AFRICA, frans.louwinger@eskom.co.za

More information

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K)

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K) ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT Project Location State District River Vicinity Latitude Longitude Nearest Railhead; Udhapur (J&K) Hiachal Pradesh Chaba Chenab River Luj village

More information

KANAWHA RIVER, WEST VIRGINIA

KANAWHA RIVER, WEST VIRGINIA Hydropower Project License Summary KANAWHA RIVER, WEST VIRGINIA LONDON-MARMET HYDROELECTRIC PROJECT (P-1175) Photo: US Army Corps of Engineers This summary was produced by the Hydropower Reform Coalition

More information

North and South Dams Project Overview

North and South Dams Project Overview North and South Dams Project Overview Construction performed by Barnard Pennecon LP Mobilized in late-2015 Anticipated Completion in mid-2019 Major Features of Our Contract Include: Diversion of Churchill

More information

Introduction. General Description

Introduction. General Description Introduction General Description The 3-Gorges project is a vitally important and backbone project in the development and harnessing of the Yangtze River (Changjiang River). The dam site is situated at

More information

CHAPTER 9 BASIC DESIGN

CHAPTER 9 BASIC DESIGN CHAPTER 9 BASIC DESIGN TABLE OF CONTENTS Chapter 9 Basic Design 9.1 General...9-1 9.2 Maximum Allowable Vibration due to Blasting against Existing Structures...9-3 9.2.1 Characteristics of Vibration due

More information

Long Lake Small Hydro Project

Long Lake Small Hydro Project Long Lake Small Hydro Project Minerals North 2005 29 April 2005 Presented by David Carter Regional Power Inc. Stuart Croft - Summit Power Group Project Location 25 km north of Stewart, in northwest B.C.

More information

Micro Hydroelectricity Installer Skills Assessment

Micro Hydroelectricity Installer Skills Assessment Micro Hydroelectricity Installer Skills Assessment Philip V. Hofmeyer August 2011 Page 1 Overview: This document contains an extensive skills assessment for renewable energy professionals who intend to

More information

JOBS AROUND THE WORLD

JOBS AROUND THE WORLD PILE DRIVERS AND THE U.S. SUPREME COURT: A STORIED FOUNDATION OF CONSTRUCTION LAW EST. 1984 THE INTERNATIONAL PILE DRIVERS, DEEP FOUNDATIONS & MARINE CONTRACTOR S MAGAZINE PILE BUCK PRESENTS 2013 VOLUME

More information

Previous Tunnel News

Previous Tunnel News Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above

More information

BOARD BRIEFING DAM SAFETY QUARTERLY REPORT

BOARD BRIEFING DAM SAFETY QUARTERLY REPORT EXECUTIVE SUMMARY The purpose of this report is to update the Capital Projects Committee of the Board of Directors on key dam risk management activities during the period from July 1, 2015 to September

More information

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM 1. PROJECT INFORMATION Intoduction: Tamakoshi V Hydroelectric Project The Tamakoshi-V Hydropower Project is a cascade development

More information

The Use of the Roof The Upper Level Company

The Use of the Roof The Upper Level Company The Use of the Roof The Upper Level Company GTA - Your competent partner GTA made the upper level working By cooperation with the mining industry GTA have acquired vast experience in underground mining

More information

HOLDING TANK PLANNING & INSTALLATION GUIDELINES

HOLDING TANK PLANNING & INSTALLATION GUIDELINES HOLDING TANK PLANNING & INSTALLATION GUIDELINES Under no circumstances is sewage from a holding tank to be discharged onto the surface of the ground or into groundwater or surface waters. TABLE OF CONTENTS

More information

Ardnacrusha Generating Station

Ardnacrusha Generating Station Ardnacrusha Generating Station Contents Part 1 Electricity for an expanding economy Part 2 The Shannon Scheme Part 3 ESB and hydro-generation power Part 4 How hydro-generation works Part 5 Looking into

More information

BC Hydro 2016 Carbon Neutral Action Report

BC Hydro 2016 Carbon Neutral Action Report BC Hydro 2016 Carbon Neutral Action Report May 2017 This Carbon Neutral Action Report for the period January 1, 2016 to December 31, 2016 summarizes our emissions profile, the total offsets to reach net-zero

More information

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation

More information

FACTS: Max Capacity Nant-y-Moch: million gallons. Nant-y-Moch Dam - Height: Nant-y-Moch Dam - Length: Dinas Dam - Height: Dinas Dam - Length:

FACTS: Max Capacity Nant-y-Moch: million gallons. Nant-y-Moch Dam - Height: Nant-y-Moch Dam - Length: Dinas Dam - Height: Dinas Dam - Length: Welcome to RHEIDOL The Rheidol Hydro Electric scheme is the largest of its kind in England and Wales. Since 1962, the scheme has generated renewable energy by using the rainwater that falls on the surrounding

More information

ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION

ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION DURR SYSTEMS, INC. CLEAN TECHNOLOGY SYSTEMS ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION Karl Walby Senior Key Account Manager 734-536-3423, karl.walby@durrusa.com ICAC

More information

Refurbishment of the Pant yr Afon Hydro Scheme By Matt Palmer and John Howarth, Dulas Ltd. September 2007

Refurbishment of the Pant yr Afon Hydro Scheme By Matt Palmer and John Howarth, Dulas Ltd. September 2007 Refurbishment of the Pant yr Afon Hydro Scheme By Matt Palmer and John Howarth, Dulas Ltd. September 2007 Abstract Pant yr Afon was one of the first hydroelectric stations in North Wales, originally commissioned

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Presentation Outline. Review of CEATI Background Conventional Hydro Program Update

Presentation Outline. Review of CEATI Background Conventional Hydro Program Update Presented to: Presentation Outline Review of CEATI Background Conventional Hydro Program Update CEATI Interest Groups: CEATI currently operates 14 focused Interest Groups Generation & Utilization Hydraulic

More information

Voith s StreamDiver solution for decentralized low head hydropower plant operations

Voith s StreamDiver solution for decentralized low head hydropower plant operations Voith s StreamDiver solution for decentralized low head hydropower plant operations Stefan Reich Joerg Lochschmidt, Mandar Pachegaokar Voith Hydro Holding GmbH & Co. KG Voith Hydro Holding GmbH & Co. Voith

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

BC Hydro Contact: Vancouver Island Community Relations Phone:

BC Hydro Contact: Vancouver Island Community Relations Phone: BC Hydro Contact: Vancouver Island Community Relations Phone: 250 755-7173 Project Team: Trade-off Analyst and Facilitator: Tony Wong, Quintry Management Consulting Inc. Resource Valuation Task Manager:

More information

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet Project Description Canadian Niagara Power Inc. ( CNP ) proposes to replace two existing lattice steel towers (Queen Street

More information

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements

More information

Water. Power. HYDROMATRIX

Water. Power. HYDROMATRIX Water. Power. HYDROMATRIX HYDROMATRIX An innovative way to hydropower generation Conventional HYDROMATRIX Ø 6+ m Ø 1.3+ m An array ( Matrix ) of small turbines instead of conventional sized turbines Best

More information

Rio Algom Limited & Denison Mines Inc. Community Newsletter 2015

Rio Algom Limited & Denison Mines Inc. Community Newsletter 2015 Rio Algom Limited & Denison Mines Inc. Community Newsletter 2015 Strong, Effective Regulation Helps Improve Elliot Lake Site Environment What does the CNSC do? The Canadian Nuclear Safety Commission (CNSC)

More information

GUIDELINES to the MINING ACT

GUIDELINES to the MINING ACT GUIDELINES to the MINING ACT PART I Format Requirements Reports 1. All reports required to be submitted to the minister by the Mining Act or regulations shall (a) be bound in a folder; (b) be a typewritten

More information

This document also describes the basis on which building permit fees should be calculated.

This document also describes the basis on which building permit fees should be calculated. 1/6 1.0 PURPOSE This specification outlines when a Building Permit is required pursuant to the Building Code Act and its Regulations. The Building Code Act prescribes that each municipality is responsible

More information

Engineering Design & Power Training Institute

Engineering Design & Power Training Institute Engineering Design & Power Training Institute Recognition & Approvals Association of Power & Design Engineers (APDE) An ISO 9001: 2008 Certified Institute Courses P G Diploma in Piping Design & Details

More information

MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY

MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY MONTH: DECEMBER, 2012 A: IMPLEMENTATION OF WATER SECTOR DEVELOPMENT PROGRAMME (WSDP) PROJECTS Introduction Under Water Sector Development Programme,

More information

K_`j `e]fidxk`fe `j Yifl^_k kf pfl Yp Fncj?Xcc <em`ifed\ekxc nfib`e^ `e gxike\ij_`g n`k_ BcXi^\jk\i gif[lzkj% '/+, *., (/'(

K_`j `e]fidxk`fe `j Yifl^_k kf pfl Yp Fncj?Xcc <em`ifed\ekxc nfib`e^ `e gxike\ij_`g n`k_ BcXi^\jk\i gif[lzkj% '/+, *., (/'( Excellent Treatment PD0064, Issue 1 INSTALLATION INSTRUCTIONS FOR N3 to N5 NITRIFICATION BIODISCS Introduction PD0064, Issue 1 Klargester BioDiscs are manufactured in Glass Fibre Reinforced Polyester (GRP).

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Site 15: Gresgarth Hall, Caton

Site 15: Gresgarth Hall, Caton Site 15: Gresgarth Hall, Caton Site Assessment Report Title Figure 1 Map showing general layout This mill is thought to have been built between 1770 and 1790 as a corn mill, becoming a threshing mill in

More information

1 Small Hydro Power Plants Wetzmann

1 Small Hydro Power Plants Wetzmann 5 th Bulgarian-Austrian Seminar SMALL DAMS AND HPP 30 March 2012, Sofia R.9 REFURBISHMENT OF TWO SMALL HYDRO POWER PLANTS IN AUSTRIA P. Tschernutter Abstract: A weir at the River Gail, which was used for

More information

NEC 2014 Code Changes

NEC 2014 Code Changes NEC 2014 Code Changes Articles 280.21-300.50 CHANGES FROM 2011 TO 2014 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 280 Surge Arresters, Over 1000 volts II. Instillation III. Connecting Surge

More information

Annex I Lyons Ferry Hatchery Modification Plan

Annex I Lyons Ferry Hatchery Modification Plan Annex I Lyons Ferry Hatchery Modification Plan Table I1 Figure I1 Figure I2 Figure I3 Figure I4 Figure I5 Well Characteristics Lyons Ferry Hatchery Vicinity Map Lyons Ferry Hatchery Site Plan Water Supply

More information

NUMERICAL SIMULATION DOWNSTREAM ATTRACTION FLOW AT DANUBE WEIR DONAUWÖRTH

NUMERICAL SIMULATION DOWNSTREAM ATTRACTION FLOW AT DANUBE WEIR DONAUWÖRTH 9 th ISE 2012, Vienna NUMERICAL SIMULATION DOWNSTREAM ATTRACTION FLOW AT DANUBE WEIR DONAUWÖRTH MARKUS GRÜNZNER TECHNISCHE UNIVERSITÄT MÜNCHEN DEPARTMENT OF HYDRAULIC ENGINEERING 80333 MUNICH, BAVARIA,

More information

Appendix B. Construction Method Statement

Appendix B. Construction Method Statement Garmony Hydro Scheme Appendix B. Construction Method Statement 282515/TGD/TGC/1/B December 2011 http://pims01/pims/llisapi.dll?func=ll&objaction=overview&objid=1473533573 54 Garmony Hydropower Scheme Construction

More information

PEND OREILLE RIVER, WASHINGTON

PEND OREILLE RIVER, WASHINGTON Hydropower Project Summary PEND OREILLE RIVER, WASHINGTON BOUNDARY HYDROELECTRIC PROJECT (P-2144) Photo: Rich Bowers, HRC This summary was produced by the Hydropower Reform Coalition and River Management

More information

Construction of Dariali HEPP. Reinstatement Plan

Construction of Dariali HEPP. Reinstatement Plan Construction of Dariali HEPP Reinstatement Plan 2016 Table of Content 1. Introduction... 3 2. Site Clean-up... 4 3. Headwork Site Reinstatement... 4 4. Reinstatement Of The Pipeline Corridor.9 5. Cable

More information

National Hydropower Association Operational Excellence Event Report. Environmental

National Hydropower Association Operational Excellence Event Report. Environmental 1) Submitting Organization: Redacted 2) Name of Preparer, Phone & Email: Redacted 3) Report Number (OE Internal Use): To Be Supplied Later 4) Date & Time of Event: 5) Duration of Event: 6) Functional Area:

More information

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

TUG - Institute of Hydraulic Engineering and Water Resources Management 1 Large Dams Design, Construction and Performance Gerald Zenz Graz - University of Technology 1 Dam Structures & Geotechnique Design Construction / Observation Operation / Monitoring Cooperation & Transfer

More information

consulting engineers hydraulic steel structures

consulting engineers hydraulic steel structures consulting engineers hydraulic steel structures Floating Sector Gate at Yeonsang Front cover Five of the seven rising sector gates at the Gangchon bridge and weir at Yeoju on the Han River in central Korea.

More information

GUIDE TO WATER SERVICE APPLICATIONS

GUIDE TO WATER SERVICE APPLICATIONS How To Apply Please contact our Call Center at 1-800-272-1325 with your site specifics, including block and lot information. Your information will be reviewed to determine preliminary service availability.

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

2012 Joint Water Use Plan for the Capilano and Seymour Watersheds

2012 Joint Water Use Plan for the Capilano and Seymour Watersheds ATTACHMENT 1 2012 Joint Water Use Plan for the Capilano and Seymour Watersheds Greater Vancouver Water District - 33 Joint Water Use Plan for the Capilano and Seymour Watersheds OCTOBER 2012 Greater Vancouver

More information

CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS

CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS 1 CEIS Working Group Civil Engineering, Infrastructure and Siting Core Disciplines: Civil

More information

Technical and economic comparison of Taivalkoski, Ossauskoski, Petäjäskoski and Valajaskoskifish pass alternatives

Technical and economic comparison of Taivalkoski, Ossauskoski, Petäjäskoski and Valajaskoskifish pass alternatives MIGRATORY FISH AND FISHWAY SYMPOSIUM OF THE NORTH 8 9 October 2013 Technical and economic comparison of Taivalkoski, Ossauskoski, Petäjäskoski and Valajaskoskifish pass alternatives Dr. Kenneth MacDougall

More information

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources Division. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act)

MINISTRY OF ENERGY AND MINES Mines and Mineral Resources Division. REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) MINISTRY OF ENERGY AND MINES Mines and Mineral Resources Division REPORT OF GEOTECHNICAL INSPECTOR (Issued pursuant to Section 15 of the Mines Act) Name of Property: Permit No.: M-29 Mine Manager: Don

More information

Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair

Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair Memorandum Number MERL 2011-34 Evaluation of New Concrete Shrinkage Reducing Additive for Glen Elder Dam Spillway Inlet Slab Repair Missouri River Basin Project Solomon Division Glen Elder Unit - Kansas

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

MEKONG SITE VISIT TO LAOS FIRST TWO MAINSTREAM DAM PROJECTS. Letters from the EXECUTIVE SUMMARY OF THE SECOND LETTERS FROM THE MEKONG ISSUE BRIEF

MEKONG SITE VISIT TO LAOS FIRST TWO MAINSTREAM DAM PROJECTS. Letters from the EXECUTIVE SUMMARY OF THE SECOND LETTERS FROM THE MEKONG ISSUE BRIEF Letters from the MEKONG SITE VISIT TO LAOS FIRST TWO MAINSTREAM DAM PROJECTS EXECUTIVE SUMMARY OF THE SECOND LETTERS FROM THE MEKONG ISSUE BRIEF by Richard Cronin and Courtney Weatherby JANUARY 2015 1

More information

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME 1 Introduction and Background To meet its environmental and social obligations and commitments, the Lesotho Highlands Development

More information

Power Capacity. Jobs. Effects on Water, Land and Wildlife. predetermine the pace, scale and nature of development in the region for decades to come.

Power Capacity. Jobs. Effects on Water, Land and Wildlife. predetermine the pace, scale and nature of development in the region for decades to come. PRIMER E N E R G Y, M I N I N G A N D S U S T A I N A B I L I T Y I N N W B R I T I S H C O L U M B I A F E B R U A R Y 2 0 0 8 Sustainable Energy Solutions Sizing It Up Scenarios for Powering Northwest

More information

SINKING THE PIT SINCE THE SECOND WORLD WAR

SINKING THE PIT SINCE THE SECOND WORLD WAR SINKING THE PIT Betws New Drift Mine John Dorian Evans BA, BA Hons, MA, MED, PHD, PGCE Text of a talk delivered at The Archaeology and History Society (Ammanford and District) On 18 th September 2006 Betws

More information

Tazi Twé Hydroelectric Project. Environmental Assessment Report

Tazi Twé Hydroelectric Project. Environmental Assessment Report Tazi Twé Hydroelectric Project Environmental Assessment Report July 2015 Cover photo credited to Ross Phillips, Golder Associates Ltd. Her Majesty the Queen in Right of Canada, represented by the Minister

More information

USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS

USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS Tractebel Energia S.A. GDF SUEZ 1 Contents Introduction 3 Objectives 5 Development 6 Methodology 8

More information

MIKE ASHEY PRODUCTIONS PRESENTS MIKE ASHEY S PHASE-II HOBBY ROOM EXPANSION

MIKE ASHEY PRODUCTIONS PRESENTS MIKE ASHEY S PHASE-II HOBBY ROOM EXPANSION MIKE ASHEY PRODUCTIONS PRESENTS MIKE ASHEY S PHASE-II HOBBY ROOM EXPANSION The area above our garage was an unfinished room so years ago I decided to close in about half of it and make it my hobby room.

More information

3- Hydropower. Energy conversion and hydropower principles

3- Hydropower. Energy conversion and hydropower principles 3- Hydropower The hydraulic power is one of the oldest energy sources of the mankind, namely for irrigation and industry. Nowadays, small hydro is one of the most valuable answers to the question of how

More information

Member Service Electric Wiring Guidelines

Member Service Electric Wiring Guidelines Member Service Electric Wiring Guidelines Table of Contents A. Definitions... 2 B. Member Service Wiring Guidelines... 2 C: Meter located on the house from an underground source - pad transformer or j-box....

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Drinking Water Audit Report

Drinking Water Audit Report Drinking Water Audit Report County: Offaly County Council Date of Audit: 18/11/16 Plant(s) visited: Tullamore Public Water Supply Clonaslee WTP Date of issue of Audit Report: File Reference: 23/11/16 DW2007/343

More information

Hydropower & Dams Services

Hydropower & Dams Services Hydropower & Dams Services We represent a world-class concentration of hydropower and dam expertise. Since 1920, we have designed hundreds of new hydropower and dams globally, producing clean reliable

More information

Irrigation System. BWCDD Zanjero Training 2/13/2008

Irrigation System. BWCDD Zanjero Training 2/13/2008 Irrigation System BWCDD Zanjero Training Session #7 2/13/2008 Irrigation System The (main) intake structure t directs water from the source of supply, such as a reservoir or a river, into the irrigation

More information

ENGINEERING AND ENVIRONMENTAL SERVICES NAM THEUN 2, LAOS 1,074 MW. Down to Earth. Up to the Challenge.

ENGINEERING AND ENVIRONMENTAL SERVICES NAM THEUN 2, LAOS 1,074 MW. Down to Earth. Up to the Challenge. ENGINEERING AND ENVIRONMENTAL SERVICES NAM THEUN 2, LAOS 1,074 MW Down to Earth. Up to the Challenge. Looking for engineering and environmental services to successfully design your hydropower projects?

More information

THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN

THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN 14 DE JULHO HPP MONTE CLARO HPP CASTRO ALVES HPP Authors: Marco Aurélio Fernandes, Vendolino Fischer and Marcelo Wood Chiarello THE ANTAS RIVER HYDROPOWER COMPLEX

More information

SECTION 5.0 ACTION 4 - ENGLEBRIGHT DAM REMOVAL

SECTION 5.0 ACTION 4 - ENGLEBRIGHT DAM REMOVAL SECTION 5.0 ACTION 4 - ENGLEBRIGHT DAM REMOVAL This Section presents facilities design and cost information for Englebright Dam Removal Action (Action 4). Action 4 includes improvements to Daguerre Point

More information

Engineering for SH Operations Voith s new StreamDiver technology. StreamDiver B Murtha, NWHA Sisters Oregon

Engineering for SH Operations Voith s new StreamDiver technology. StreamDiver B Murtha, NWHA Sisters Oregon Engineering for SH Operations Voith s new StreamDiver technology 1 97% of existing dams in the US are not used for hydropower and similarly with 85% worldwide. Today the investment costs and projected

More information

VANCOUVER ISLAND SUNSHINE COAST COMMUNITY RELATIONS 2014 ANNUAL REPORT

VANCOUVER ISLAND SUNSHINE COAST COMMUNITY RELATIONS 2014 ANNUAL REPORT BC Hydro Trucks enroute to Quatsino VANCOUVER ISLAND SUNSHINE COAST COMMUNITY RELATIONS 2014 ANNUAL REPORT MESSAGE FROM JESSICA MCDONALD I had the good fortune to join BC Hydro as President and CEO in

More information

Lesson 5 Energy. OAA Science Lesson 5 52

Lesson 5 Energy. OAA Science Lesson 5 52 Lesson 5 Energy OAA Science Lesson 5 52 Name Date Period Student Lesson 5: Energy Reference Sheet: Energy - is the ability to do work or cause change - can be changed from one form to another - cannot

More information

Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary.

Report. Engineering Services Group. Capital Investment Plan (CIP) Quarterly Report for the period ending September Summary. Report Engineering Services Group Capital Investment Plan (CIP) Quarterly Report for the period ending September 2012 Summary This report provides a summary of fiscal year accomplishments, capital expenditures

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Horizontal Directional Drilling

Horizontal Directional Drilling Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social

More information

EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION

EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION EXHIBIT B PROJECT OPERATION AND RESOURCE UTILIZATION B.1 ALTERNATIVE SITES CONSIDERED In developing the proposed configuration of the Project the following

More information

Bridge River Power Development Water Use Plan. Revised for Acceptance for the Comptroller of Water Rights

Bridge River Power Development Water Use Plan. Revised for Acceptance for the Comptroller of Water Rights Bridge River Power Development Water Use Plan Revised for Acceptance for the Comptroller of Water Rights March 17, 2011 Bridge River WUP March 17, 2011 Page i Bridge River Power Development Water Use Plan

More information

International Fish Screening Conference Southampton March 2011

International Fish Screening Conference Southampton March 2011 International Fish Screening Conference Southampton 29-30 March 2011 Downstream bypass facilities for salmon and eel at small hydro power plants in France F. Travade M. Larinier EDF R&D ONEMA 6, quai Watier

More information

Ash River Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Ash River Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Ash River Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 4 October 24 B Ash River Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation

More information

Tsunami Countermeasures at Hamaoka Nuclear Power Station

Tsunami Countermeasures at Hamaoka Nuclear Power Station Tsunami Countermeasures at Hamaoka Nuclear Power Station Reference Reactor No. 5 Reactor No. 4 Reactor No. 3 Reactor No. 2 Reactor No. 1 March 16, 2012 2011 Chubu Electric Power Co., Inc. All rights reserved.

More information

Performance Testing of The Robert Moses Niagara Power Plant and Sir Adam Beck Generating Station

Performance Testing of The Robert Moses Niagara Power Plant and Sir Adam Beck Generating Station Performance Testing of The Robert Moses Niagara Power Plant and Sir Adam Beck Generating Station By Albert F. Mikhail, P.Eng., Ontario Power Generation and Robert J. Knowlton, P.E., New York Power Authority

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

Three Gorges Project. A Project with Tremendous Benefits and in Favour of Environmental Improvement. By Cao Guangjing May 22, 2004

Three Gorges Project. A Project with Tremendous Benefits and in Favour of Environmental Improvement. By Cao Guangjing May 22, 2004 Three Gorges Project A Project with Tremendous Benefits and in Favour of Environmental Improvement By Cao Guangjing May 22, 2004 Contents 1. Brief Introduction 2. Why Should TGP Be Built? 3. Investment

More information

Working with BC Hydro. Capital Infrastructure Project Delivery

Working with BC Hydro. Capital Infrastructure Project Delivery Working with BC Hydro Capital Infrastructure Project Delivery 1 Introduction We have planned work of varying sizes and complexity all over the province. Our external partners are an essential part of the

More information