Long Lake Small Hydro Project

Size: px
Start display at page:

Download "Long Lake Small Hydro Project"

Transcription

1 Long Lake Small Hydro Project Minerals North April 2005 Presented by David Carter Regional Power Inc. Stuart Croft - Summit Power Group

2 Project Location 25 km north of Stewart, in northwest B.C. Situated near historic Premier & Big Missouri mining camps Moderated coastal climate and terrain ideal for small hydro Long Lake valley looking south

3 Developer Background Doran-Taylor 5.3 MW Project 40 km west of Port Alberni Premier Power s affiliate company, Summit Power, owns and operates two small hydro developments in southwestern B.C. Soo River Project Whistler - 14 MW commissioned 1994 $18 million Doran-Taylor Project Port Alberni MW commissioned 1996 $8 million

4 Developer Background Regional Power Inc. developer and operator of hydroelectric power plants since developed 3 small hydro plants (2 in BC and 1 in Ontario) and has rehabilitated 3 existing power plants in N Ontario. Regional has 4 hydroelectric development sites under contract representing 93 MW in capacity Bear Creek, Long Lake and Ucona River in BC Anglier in Quebec Near term development prospects with an aggregate capacity of 135 MW. a subsidiary of Manulife Financial

5 Joint Venture Background Doran-Taylor Hydro tailrace (Oct 98) (Fisheries Renewal BC project co-sponsored by Summit Power, DFO, Hupacasath First Nation, MC Wright & Associates) Innovative approach to Project development Identify environmentally and economically sound opportunities Established a favourable, cooperative relationship with government agencies, stakeholders Sechelt Creek Hydro spawn channel (Sep 03) (A cooperative arrangement between Regional Power, DFO, Sechelt First Nation)

6 Project History Several small hydro schemes powered the Premier and Big Missouri mines during 1923 through 1956 Developments on lower Cascade & Fletcher Creeks provided power to nearby Premier mine and townsite

7 Project History Cominco built dam at Long Lake to provide 8500 dam 3 storage for Big Missouri mine power development Long Lake Concrete Arch Dam: length - 30 m height - 12 m built demolished ca 1980 Provided firm power of approx kw year round to mine and townsite

8 Project Background Westmin studied Long Lake hydro scheme to service new 2000 tpd mine in late 1980 s Plans for 7.5 MW hydro power plant shelved when BC Hydro extended transmission line from Aiyansh to Stewart Premier Gold mine operated until mid 1990 s Mine is presently executing closure plant, Boliden seeking to dispose of property

9 Development Background In 1999, Premier Power entered into Agreement with Boliden to acquire facilities & infrastructure, rights-ofway, roads, etc. for Long Lake small hydro development Provides Boliden cost relief, additional security of supply for ongoing water treatment obligations Late 2002: Premier Power and Regional Power formed Long Lake Joint Venture to advance the development Successfully bid into BC Hydro s 2002 CBG power acquisition program and executed EPA in spring 2003

10 Development Concept Reinstate historic development at Long Lake with concept refined from earlier Westmin scheme Develop hydro power scheme to optimize utilization of hydrological resource 16 MW installed capacity 2.83 m 3 /s design flows utilize storage on Long Lake develop 775 m head Utilize existing transmission infrastructure to deliver energy for sale to BC Hydro

11 Feasibility Design 20 m high rockfill dam & intake structure at outlet to Long Lake 1 m buried penstock following Big Missouri haul road 7.5 km to vicinity of Premier Gold mill site Powerhouse with one 16 MW multijet Pelton-type turbine generator unit Automated protection & control system designed for unattended plant operation Power transmission via existing pole line to BC Hydro grid at Stewart Short tailrace to return water to Cascade Creek

12 Feasibility Design Annual generation of approx. 100 GWh Total Capital Cost estimated at $40 million 2 year construction schedule 5.3 MW Pelton turbine (similar to unit proposed for Long Lake)

13 Development Schedule Regulatory Review concludes Spring 2005 Commence construction Summer 2005 Commercial operation Winter 2006 / 2007

14 Benefits Replacement investment and economic stimulus for Stewart, NW BC Sustainable, long term resource development to produce Green Power Maintains valuable infrastructure Affords numerous environmental benefits

15 Long Lake Hydro Back to the Future Excellent small hydro development opportunity hydrology storage infrastructure Benefits to stakeholders Developers Stewart Province of B.C. Working in close cooperation with government, stakeholders and industry to make efficient use of valuable resources FOR MORE INFO... Please contact: Stuart Croft David Carter

Table of Contents. Nov. 2008

Table of Contents. Nov. 2008 Nov. 2008 What is involved? Electrical loads in Yukon are increasing. By 2011, Yukon Energy expects to need additional renewable power to help minimize the use of diesel to generate electricity. As outlined

More information

Soo River Hydro Intake Sediment Management

Soo River Hydro Intake Sediment Management Intake Sediment Management GENERATE 2014 Operators Workshop 15 October 2014 by Stuart Croft Vice President A brief background Soo River Project: 14 MW run-of-river development 15 km north of Whistler on

More information

DEVELOPER AND OPERATOR OF RENEWABLE RESOURCE POTENSIAL

DEVELOPER AND OPERATOR OF RENEWABLE RESOURCE POTENSIAL 182 DA1O.l Projet d'aménagement hydroélectrique à Angliers Abitibi-Témiçcamingue 6211-03-065 WÇIONAL PQmR INC. DEVELOPER AND OPERATOR OF RENEWABLE RESOURCE POTENSIAL Regional Power Inc., a subsidiary of

More information

PROJECT BRIEF for the John Hart Generating Station Replacement Project

PROJECT BRIEF for the John Hart Generating Station Replacement Project PROJECT BRIEF for the John Hart Generating Station Replacement Project Issue Date: March 13, 2012 TABLE OF CONTENTS John Hart Generating Station Replacement Project Page ii of 17 1. INTRODUCTION... 3 1.1

More information

BC Hydro Clean Power Call

BC Hydro Clean Power Call Jamie Creek Project C-Free Power Corp. Gold Bridge 19MW 41GWh/year The Jamie Creek Project is a nameplate 19 MW capacity run-of-river hydroelectric project, located on Jamie Creek, approximately 16 km

More information

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems ABSTRACT Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems By Ron Monk, M.Eng., P.Eng.; Stefan Joyce, P.Eng.; and Mike Homenuke, P.Eng. Kerr Wood Leidal

More information

TRANSFORMING CHALLENGES INTO OPPORTUNITIES

TRANSFORMING CHALLENGES INTO OPPORTUNITIES ... TRETHEWAY CREEK PROJECT TRANSFORMING CHALLENGES INTO OPPORTUNITIES CANADIAN CONSULTING ENGINEERING AWARDS 2017 Natural Resources, Mining, Industry & Energy Category bba.ca Summary The construction

More information

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan EXECUTIVE SUMMARY The consultative process was initiated in April 2000 and completed in November 2001. The consultative process follows the steps outlined in the 1996 provincial government Water Use Plan

More information

FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO )

FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO ) Brookfield Renewable Energy Group Focusing on Renewable Power Generation FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO. 14439) October 2012 HAWKS NEST PROJECT (FERC

More information

Yukon Energy. Rural Generating Facilities

Yukon Energy. Rural Generating Facilities photo : Yukon Energy Yukon Energy Rural Generating Facilities Yukon Energy s Rural Facilities Yukon Energy has three hydro facilities one in Whitehorse on the Yukon River, one located at Aishihik Lake

More information

SYNEX INTERNATIONAL INC. TSX:SXI Since 1987 AUGUST 2016

SYNEX INTERNATIONAL INC. TSX:SXI Since 1987 AUGUST 2016 SYNEX INTERNATIONAL INC. TSX:SXI Since 1987 AUGUST 2016 Our Mission is to provide clean electricity to customers and communities in the province of British Columbia through the design, development and

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project March 2018 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286

More information

More Creek Hydroelectric Project Prefeasibility Study

More Creek Hydroelectric Project Prefeasibility Study Alaska Hydro Corporation More Creek Hydroelectric Project June 2015 E6348 SIGMA ENGINEERING LTD 1444 Alberni Street, 4th Floor, Vancouver, BC, Canada V6G 2Z4 Phone: (604) 688-8271 Fax: (604) 688-1286 TABLE

More information

AEA - Copper Valley Electric Association Allison Creek Hydroelectric Project

AEA - Copper Valley Electric Association Allison Creek Hydroelectric Project Total Project Snapshot Report 2011 Legislature TPS Report 56280v1 Agency: Commerce, Community and Economic Development Grant Recipient: Copper Valley Electric Association, Inc. Project Title: Federal Tax

More information

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project

More information

Pic Mobert First Nation White River Watershed Compensation Flow Management & Development

Pic Mobert First Nation White River Watershed Compensation Flow Management & Development Showcasing Water Innovation Pic Mobert First Nation White River Watershed Compensation Flow Management & Development Pic Mobert Leaders and Members celebrate a water ceremony at the site of the Gitchi

More information

TALTSON HYDROELECTRIC EXPANSION PROJECT

TALTSON HYDROELECTRIC EXPANSION PROJECT TALTSON HYDROELECTRIC EXPANSION PROJECT Prepared for: Yellowknife Scoping Sessions December 7, 2007 Presented by: DEZÉ ENERGY CORPORATION TALTSON HYDROELECTRIC EXPANSION PROJECT Introduction Presentation

More information

Yukon s Hydroelectric Resources Yukon Energy Charrette

Yukon s Hydroelectric Resources Yukon Energy Charrette Yukon s Hydroelectric Resources Yukon Energy Charrette Presented By: Forest Pearson, AECOM March 7-9, 2011 Presentation Overview Hydropower Background Hydropower Resource Capacity in Yukon Hydropower Potential

More information

BC Hydro Contact: Vancouver Island Community Relations Phone:

BC Hydro Contact: Vancouver Island Community Relations Phone: BC Hydro Contact: Vancouver Island Community Relations Phone: 250 755-7173 Project Team: Trade-off Analyst and Facilitator: Tony Wong, Quintry Management Consulting Inc. Resource Valuation Task Manager:

More information

Takatz Lake Project - Alaska

Takatz Lake Project - Alaska BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT SUBMITTED BY: City and Borough of Sitka Electric Department 105 Jarvis Street Sitka, Alaska 99835 June, 2008 Initial Statement

More information

EXHIBIT C CONSTRUCTION SCHEDULE

EXHIBIT C CONSTRUCTION SCHEDULE EXHIBIT C CONSTRUCTION SCHEDULE C.1 CONSTRUCTION SCHEDULE A preliminary construction schedule as shown in Figure C-1 has been developed for the to show the sequencing of principal activities through the

More information

Creating Value Through Operational Excellence

Creating Value Through Operational Excellence Creating Value Through Operational Excellence Kemess North Project Minerals North April 2004 Northgate Exploration Limited Overview BRITISH COLUMBIA based gold mining company Principal asset is the Kemess

More information

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No ) Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides

More information

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

2.16 NAM POT HYDROPOWER PROJECT

2.16 NAM POT HYDROPOWER PROJECT 2.16 NAM POT HYDROPOWER PROJECT Nam Pot is a hydropower project of around 20 to 25 MW located in Xiangkhouang Province. Due to its size, location and economics, Nam Pot project is best suited to a domestic

More information

Inter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal

Inter-office memo. Bear Creek Reservoir. Elliot Headpond. Jordan Generating Tailrace. Diversion Reservoir. Maximum Normal Elevation (m) Minimum Normal Inter-office memo TO: File DATE: 8 November 2007 FROM: Engineering FILE: GENMIS08 NRGPLN SUBJECT: Jordan River Pumped Storage 1.0 Introduction The British Columbia Utility Commission has directed BC Hydro

More information

Grafton Hydro, LLC. 55 Union Street, 4 th Floor Boston, MA, USA Tel: Fax: October 9, 2015

Grafton Hydro, LLC. 55 Union Street, 4 th Floor Boston, MA, USA Tel: Fax: October 9, 2015 Grafton Hydro, LLC 55 Union Street, 4 th Floor Boston, MA, 02108-2400 USA Tel: +617-710-1114 Fax: +617-367-3796 October 9, 2015 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First

More information

Amisk Hydroelectric Project Update

Amisk Hydroelectric Project Update Amisk Hydroelectric Project Update AHP Development Corporation (AHP) is providing an update on the Amisk Hydroelectric Project ( Amisk /the Project ). Amisk is a proposed run-of-river hydroelectric project,

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

ENGINEERING AND ENVIRONMENTAL SERVICES NAM THEUN 2, LAOS 1,074 MW. Down to Earth. Up to the Challenge.

ENGINEERING AND ENVIRONMENTAL SERVICES NAM THEUN 2, LAOS 1,074 MW. Down to Earth. Up to the Challenge. ENGINEERING AND ENVIRONMENTAL SERVICES NAM THEUN 2, LAOS 1,074 MW Down to Earth. Up to the Challenge. Looking for engineering and environmental services to successfully design your hydropower projects?

More information

2008 Long Term Acquisition Plan

2008 Long Term Acquisition Plan 2008 Long Term Acquisition Plan APPENDIX F4b Evaluation of the Jorvic Sewage Reclaim Pipeline Page 1 of 5 1 Introduction In 2004 Vanport Sterilizers Inc. (VPS) submitted a proposal to both the BC Utilities

More information

POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION

POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION WATER POWER ACT LICENCES POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION SUPPORTING DOCUMENTATION Prepared for: Manitoba Sustainable Development 200 Saulteaux Crescent Winnipeg

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE March 12, 2015 THE INTEGRATED RESOURCE PLAN Every 3-5 years BC Hydro develops a flexible, long-term strategic plan

More information

Run-of-River Hydroelectric Resource Assessment for BC

Run-of-River Hydroelectric Resource Assessment for BC Run-of-River Hydroelectric Resource Assessment for BC Small Hydro Engagement Session November 19, 2007 *PRELIMINARY RESULTS* Please note that the results presented here are considered draft results only.

More information

WEST ROSEBUD CREEK, MONTANA

WEST ROSEBUD CREEK, MONTANA Hydropower Project Summary WEST ROSEBUD CREEK, MONTANA MYSTIC LAKE HYDROELECTRIC PROJECT (P-2301) Photo: PPL Montana This summary was produced by the Hydropower Reform Coalition and River Management Society

More information

Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington Revised Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No. 2244 Lewis County, Washington Submitted to P.O. Box 968 Richland, Washington 99352-0968

More information

Discussion on Remote Community Connection Concepts

Discussion on Remote Community Connection Concepts Discussion on Remote Community Connection Concepts February 1, 2012 Presentation Overview 1. Northwest Ontario First Nation Transmission Planning Committee Overview 2. Strategic energy supply options 3.

More information

2.6 NAM FA HYROPOWER PROJECT

2.6 NAM FA HYROPOWER PROJECT 2.6 NAM FA HYROPOWER PROJECT The Nam Fa Project is located in Bokeo Province on the Nam Fa (Nam Pha). The layout of the Project is shown in the attached plan. The project configuration developed for the

More information

Subject Waterpower New Site Release and Development Review

Subject Waterpower New Site Release and Development Review Ontario Ministry of Natural Resources Subject Waterpower New Site Release and Development Review Compiled by Lands and Waters Section Water Resources Policy Draft-March 28, 2004 Date Issued New Replaces

More information

Status Quo and Future Prospects of Hydro Power in Germany

Status Quo and Future Prospects of Hydro Power in Germany Energy Status Quo and Future Prospects of Hydro Power in Germany Renewable Energy Symposium Lima, November 10 th, 2009 Dirk Volkmann www.german-renewable-energy.com content historical development technology

More information

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

2005 Integrated Electricity Plan

2005 Integrated Electricity Plan 2005 Integrated Electricity Plan Regional Workshops Round 1 Kitimat February 22, 2005 Workshop Objectives To provide a forum to learn, share and express regional preferences about future energy options

More information

HPP CEBREN. Prepared by: Development and Investments Department

HPP CEBREN. Prepared by: Development and Investments Department HPP CEBREN Prepared by: Development and Investments Department Skopje, 2017 The partition place Cebren is located at the River Crna Reka, 81 km upstream from its inflow in the River Vardar, near the village

More information

2.29 XE KONG 5 HYDROPOWER PROJECT

2.29 XE KONG 5 HYDROPOWER PROJECT 2.29 XE KONG 5 HYDROPOWER PROJECT The Xe Kong 5 Hydropower Project is located in Kaleum District, Xe Kong Province on the upper reaches of the Xe Kong, immediately upstream of the proposed Xe Kong 4 Hydropower

More information

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC JANUARY 2013 PARR Relicensing Project PARR AND FAIRFIELD LOCATIONS FFPS PARR

More information

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE Q U É B E C S H Y D R O P O W E R R E S O U R C E S P O W E R I N G T H E E M P I R E S TAT E LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE Hydro-Québec, New York s energy partner for decades,

More information

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Ministry of Infrastructure and Transport PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Prepared by : Department of Energy August, 2013 [DOE] 1 Table of Contents Summary... 3 1. Geographical

More information

A. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010.

A. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010. Requests for Information CA-NP-036 NP 2013/2014 GRA 1 2 3 4 5 6 7 8 9 10 11 12 Q. [Decommissioning] Please all workpapers, assumptions, considerations and material reviewed and/or relied upon in developing

More information

Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014

Study on Economic Partnership Projects in Developing Countries in FY2013. Final Report SUMMARY. February 2014 Study on Economic Partnership Projects in Developing Countries in FY2013 Study on the small hydro power project in the province of Lam Dong in Socialist Republic of Vietnam Final Report SUMMARY February

More information

olumbia River Treaty The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct

olumbia River Treaty The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct 2006 1 Presentation Outline Geography of the Pacific Northwest Bonneville Power Administration

More information

2.24 VIENGPHOUKA THERMAL PROJECT

2.24 VIENGPHOUKA THERMAL PROJECT 2.24 VIENGPHOUKA THERMAL PROJECT The Viengphouka Thermal Project is a mine-mouth coal-fired base load power generation project located in Luangnamtha Province. The Consultant has evaluated the Project

More information

Seasonal and Pumped Storage Hydro Opportunity Search in the Carmacks to Faro Road and Power Line Corridor, An Office Study

Seasonal and Pumped Storage Hydro Opportunity Search in the Carmacks to Faro Road and Power Line Corridor, An Office Study Seasonal and Pumped Storage Hydro Opportunity Search in the Carmacks to Faro Road and Power Line Corridor, An Office Study Prepared for Yukon Conservation Society (YCS) June 25, 2015 Prepared by John F.

More information

Hydro Power Technology Overview 2007 September 2008

Hydro Power Technology Overview 2007 September 2008 Hydro Power Technology Overview 27 September 28 1. Hydro introduction 2. Monthly Load Factor plots 3. Seasonal variation and storage capacity 4. Wind and Hydro are weather dependent renewables 5. Micro

More information

Small Hydro based energy generation

Small Hydro based energy generation Workshop on Capacity Development Program for Afghan Women (Clean Energy Access) Small Hydro based energy generation G Anil Head Small Hydro Power Dn., Energy Management Centre, Trivandrum 695017, Kerala,

More information

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April 28 2016 Renewable Energy Systems (RES) In Canada for more than 12 years Family-owned company

More information

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Campbell River System Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation Resource Management Nov 21, 2012 v6 Campbell River System Water Use Plan Page i Table of Contents

More information

LAURIE RIVER #1 GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION

LAURIE RIVER #1 GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION WATER POWER ACT LICENCES LAURIE RIVER #1 GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION SUPPORTING DOCUMENTATION Prepared for: Manitoba Water Stewardship 200 Saulteaux Crescent Winnipeg MB

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions 16 February 2018 1. What is the Highbury Pumped Hydro Energy Storage Project proposal? The proposed project involves the construction of pumped hydro energy storage facility,

More information

If any questions arise concerning this application, please contact us.

If any questions arise concerning this application, please contact us. Cherokee Rivers Company, LLC 390 Timber Laurel Lane Lawrenceville, GA 30043 Office of the Secretary Federal Energy Regulatory Commission Mail Code: DHAC, PJ-12 888 First Street, N.E. Washington, D.C. 20426

More information

Power Plant History of the Pikes Peak Region. Presented by Chris Thompson

Power Plant History of the Pikes Peak Region. Presented by Chris Thompson Power Plant History of the Pikes Peak Region Presented by Chris Thompson Power Timeline 1879 Perfected Arc Lighting System (Cleveland, OH) 1879 First Incandescent Light Bulb (Menlo Park, NJ) 1880 First

More information

IDM Mining Updates Pre-Development Engineering and Optimization at Red Mountain Gold Project

IDM Mining Updates Pre-Development Engineering and Optimization at Red Mountain Gold Project IDM Mining Updates Pre-Development Engineering and Optimization at Red Mountain Gold Project November 30 th, 2017, Vancouver, BC IDM Mining Ltd. (TSX.V:IDM) (OTCQB:IDMMF) ( IDM or the Company ) is pleased

More information

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis Andrew Hamann, Prof. Gabriela Hug Power Systems Laboratory, ETH Zürich February 8, 2017 Future Electric Power Systems and

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

Questions and Answers Electricity Demand and Supply in NL

Questions and Answers Electricity Demand and Supply in NL Questions and Answers Electricity Demand and Supply in NL January 2014 Q1. How many developed generation hydro sites are located on the Island of NL and what is the generation capacity. How many possible

More information

Country Paper on Small Hydro Power ZIMBABWE

Country Paper on Small Hydro Power ZIMBABWE Country Paper on Small Hydro Power ZIMBABWE BY WELLINGTON MAPHOSA PROJECTS ENGINEER,ZIMBABWE POWER COMPANY 1 OVERALL POWER PICTURE IN ZIMBABWE AS AT OCTOBER 2003 TOTAL ELECTRICAL POWER ~70% INTERNAL GENERATION

More information

Dear Ms. Bose, Thank you for the opportunity to comment on the application by Juneau Hydropower Inc. for a

Dear Ms. Bose, Thank you for the opportunity to comment on the application by Juneau Hydropower Inc. for a United States Department of Agriculture Forest Service Alaska Region Tongass National Forest 648 Mission Street Ketchikan, AK 99901 Phone: (907) 225-3101 Fax: (907) 228-6215 File Code: 2770-1 Date: November

More information

Glenfarg Hydropower Development. Hydro-potential in the Glenfarg area

Glenfarg Hydropower Development. Hydro-potential in the Glenfarg area Client: Glenfarg Renewable Energy Association Contract Start Date: May 2014 Report Reference: Contributors: Checked by: MNV/GF001/2011 Dr R C Johnson Rita Day Document Revisions: Status Version Date Final

More information

Appendix 4.4 Industrial Energy and Peak Demand Forecast

Appendix 4.4 Industrial Energy and Peak Demand Forecast Appendix 4.4 Industrial Energy and Peak Demand Forecast 2016-2035 14 November 2016 Contents 1.1 Introduction... 2 1.2 Background... 2 1.3 Source of Information... 2 1.4 Industrial Projects Requirements...

More information

Monitoring Networks for Assessing Small Stream Hydropower Potential, Cosmos Hills, Alaska

Monitoring Networks for Assessing Small Stream Hydropower Potential, Cosmos Hills, Alaska Monitoring Networks for Assessing Small Stream Hydropower Potential, Cosmos Hills, Alaska Michael Lilly, Jeffrey Derry, Austin McHugh, Jeff Murray Geo-Watersheds Scientific David Brailey Brailey Hydrologic

More information

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment

More information

Columbia River Treaty Frequently Asked Questions (FAQs)

Columbia River Treaty Frequently Asked Questions (FAQs) Columbia River Treaty Frequently Asked Questions (FAQs) Spring 2012 Columbia River Treaty 1. What is the Columbia River Treaty? The Columbia River Treaty is a trans-boundary water management agreement

More information

THE CHANGUINOLA DAM & HYDRO ELECTRICAL POWER PLANT

THE CHANGUINOLA DAM & HYDRO ELECTRICAL POWER PLANT THE CHANGUINOLA DAM & HYDRO ELECTRICAL POWER PLANT A large construction project with its own cement and fly ash import operation Ad Ligthart 12-12-2012 2c2i Club des Carriers Industriels Indépendants CONTENTS

More information

Eska Creek Preliminary Feasibility Analysis

Eska Creek Preliminary Feasibility Analysis Introduction Eska Creek Preliminary Feasibility Analysis This report examines the feasibility issues of energy and economics for a 1.8 MW hydroelectric project on Eska Creek (project). The Project is located

More information

Basin-Scale Hydropower and Environmental Opportunity Assessments

Basin-Scale Hydropower and Environmental Opportunity Assessments Basin-Scale Hydropower and Environmental Opportunity Assessments A framework for identifying and evaluating hydropower and environmental opportunities and linkages Simon Geerlofs, Jerry Tagestad, Kyle

More information

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs Project: Sorang Hydro Electric Project - 100 MW Overview: M/s.Himachal Sorang Pvt.Ltd., Hyderabad, is developing the Run of the River Sorang Hydro Electric Project (100MW) in Kinnaur District of Himachal

More information

Meeting held November 8, 2005 at the Coast Bastion Inn in Nanaimo Page 1 of 6

Meeting held November 8, 2005 at the Coast Bastion Inn in Nanaimo Page 1 of 6 Meeting Date and Location November 8, 2005 Coast Bastion Inn 11 Bastion Street, Nanaimo, B.C. 6:30 p.m. 8:30 p.m. Attendees and Interests Name Interest/Organization J. R. Young Gabriola Ratepayers Ed Thompson

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

1. Why is NB Power recommending Life Achievement as the best option?

1. Why is NB Power recommending Life Achievement as the best option? F.A.Q. Mactaquac Generating Station Life Achievement Project December 2016 1. Why is NB Power recommending Life Achievement as the best option? This approach has the lowest cost estimate when compared

More information

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC SEPTEMBER 19, 2012 PARR AND FAIRFIELD LOCATIONS Lockhart Neal Shoals Monticello

More information

Physical Works Terms of Reference

Physical Works Terms of Reference Peace Project Water Use Plan Physical Works Terms of Reference District of Mackenzie Effluent Discharge Feasibility and Design Study GMSWORKS #28a 23 November 2009 Terms of Reference for the Peace Water

More information

Senate Interim Committee on Veterans and Emergency Preparedness

Senate Interim Committee on Veterans and Emergency Preparedness Senate Interim Committee on Veterans and Emergency Preparedness Small-Scale Hydroelectric Power Andy Ginsburg, Assistant Director Energy Planning and Innovation Oregon Department of Energy September 22,

More information

2.32 XESET 2 HYDROPOWER PROJECT

2.32 XESET 2 HYDROPOWER PROJECT 2.32 XESET 2 HYDROPOWER PROJECT The Xeset 2 Hydropower Project is part of the development of the hydropower potential of the Xe Set basin in Saravan Province. It is upstream of the existing 45 MW Xeset

More information

EXECUTIVE SUMMARY. Executive Summary. Introduction to Water Use Planning

EXECUTIVE SUMMARY. Executive Summary. Introduction to Water Use Planning EXECUTIVE SUMMARY Executive Summary Introduction to Water Use Planning Water Use Planning was announced in 1996 to ensure that provincial water management decisions reflect changing public values and environmental

More information

CURRENT STATUS OF THE PEBBLE CREEK (NORTH MEAGER) GEOTHERMAL PROJECT, SOUTHWESTERN BRITISH COLUMBIA

CURRENT STATUS OF THE PEBBLE CREEK (NORTH MEAGER) GEOTHERMAL PROJECT, SOUTHWESTERN BRITISH COLUMBIA CURRENT STATUS OF THE PEBBLE CREEK (NORTH MEAGER) GEOTHERMAL PROJECT, SOUTHWESTERN BRITISH COLUMBIA Mory Ghomshei, Tim Sadlier-Brown and Ferri Hassani McGill University Department of Mining and Materials

More information

Public Meeting, November 3, /3/11

Public Meeting, November 3, /3/11 Public Meeting, November 3, 2011 1 Power Resources needs, direction, investigations Projects Selection Projects Engineering Environmental Baseline existing environment, anticipated impacts and PM&Es Licensing

More information

Northwest Power and Conservation Council

Northwest Power and Conservation Council Northwest Power and Conservation Council Pumped Storage GRAC Meeting Banks Lake Pumped Storage Project (North Dam) FERC Project No. 14329 Portland, Oregon January 27, 2015 Presented by: Lloyd Reed and

More information

Small Hydropower Development 3 rd June, 2018 Hangzhou, China

Small Hydropower Development 3 rd June, 2018 Hangzhou, China 2018 Seminar On Water Resource's Management & Small Hydropower Development for countries along the Belt and Road Kenya Country Report Small Hydropower Development 3 rd June, 2018 Hangzhou, China Presented

More information

FACTS: Max Capacity Nant-y-Moch: million gallons. Nant-y-Moch Dam - Height: Nant-y-Moch Dam - Length: Dinas Dam - Height: Dinas Dam - Length:

FACTS: Max Capacity Nant-y-Moch: million gallons. Nant-y-Moch Dam - Height: Nant-y-Moch Dam - Length: Dinas Dam - Height: Dinas Dam - Length: Welcome to RHEIDOL The Rheidol Hydro Electric scheme is the largest of its kind in England and Wales. Since 1962, the scheme has generated renewable energy by using the rainwater that falls on the surrounding

More information

BACKGROUNDER. Watershed Watch Salmon Society. February 5, 2009 THE BUTE INLET HYDROELECTRIC PROJECT

BACKGROUNDER. Watershed Watch Salmon Society. February 5, 2009 THE BUTE INLET HYDROELECTRIC PROJECT BACKGROUNDER Watershed Watch Salmon Society February 5, 2009 THE BUTE INLET HYDROELECTRIC PROJECT 1 Q: Where will the proposed project take place? A: Bute Inlet is located on the south coast of British

More information

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45 John Hart Generating Station Replacement Project March 2017 Community Construction Update Report #45 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Maroon Creek Small Hydro

Maroon Creek Small Hydro Volume 1 Issue 4 May 2005 creating profit and capacity with employment and entrepreneurship opportunities for Kitsumkalum people Maroon Creek Small Hydro Generating Energy and Revenue he Maroon Creek Small

More information

AEA - Kodiak Electric Association Terror Lake Hydroelectric Facility Expansion

AEA - Kodiak Electric Association Terror Lake Hydroelectric Facility Expansion Total Project Snapshot Report 2011 Legislature TPS Report 55977v2 Agency: Commerce, Community and Economic Development Grant Recipient: Kodiak Electric Association, Inc. Project Title: Federal Tax ID:

More information

A summary Yukon Energy s 2016 Resource Plan

A summary Yukon Energy s 2016 Resource Plan 2016 resource plan YUKON ENERGY A summary Yukon s 2016 Resource Plan June 2017 Imagine what life in Yukon might be like 20 years from now. What s the state of the economy? Are there mines operating here,

More information

Hydropower retrofitted onto existing water infrastructure assets

Hydropower retrofitted onto existing water infrastructure assets Hydropower retrofitted onto existing water infrastructure assets Marco van Dijk Lecturer and Principal Researcher University of Pretoria / Water Research Commission South Africa Presentation Layout How

More information

AUSTMINE. AGL Procurement. June 2015

AUSTMINE. AGL Procurement. June 2015 AUSTMINE 1 AGL Procurement June 2015 Disclaimer 2 The information in this presentation: Is not an offer or recommendation to purchase or subscribe for securities in AGL Energy Limited or to retain any

More information

at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning

at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning Integrated t Resource Planning at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning Today s agenda 1. Our system 2. Integrated Resource Plan 3. Looking forward Our system Generation

More information

Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France

Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France Delivering South Africa s First Project Financed Run of River Hydro Power Plant: The Neusberg Project Outline

More information

TransCanada Pipelines The Company and Its Projects. BC Metis Industry Forum May 10, 2014 Vancouver, B.C.

TransCanada Pipelines The Company and Its Projects. BC Metis Industry Forum May 10, 2014 Vancouver, B.C. TransCanada Pipelines The Company and Its Projects BC Metis Industry Forum May 10, 2014 Vancouver, B.C. TransCanada Corporation (TSX/NYSE: TRP) TransCanada is a leading North American energy infrastructure

More information