Odour and Air Management Studies: Key Tool in Determining Effective Odour Control

Size: px
Start display at page:

Download "Odour and Air Management Studies: Key Tool in Determining Effective Odour Control"

Transcription

1 Odour and Air Management Studies: Key Tool in Determining Effective Odour Control Solutions Yuko Suda, P.Eng., Kerr Wood Leidal Associates Ltd. Ted Steele, P.Eng., Kerr Wood Leidal Associates Ltd A Still Creek Drive, Burnaby, BC Chris Hunniford, P.E., OCTC, A V&A Company 8220 Jones Road, Suite 500, Houston, TX ABSTRACT Sewer odours from pump stations, force main discharge points, and manholes have been a costly problem for many municipalities. Understanding the air and sewer dynamics within the sanitary sewer system is essential to identifying the cause of odour in sewer systems, and to developing cost-effective odour control solutions. Local pressurization of the air space above the sewage in a sewer results in odourous air being expelled at manholes and vents. The conventional solution has been to either seal manholes at these locations or install carbon scrubbers. This, however, increases the pressurization within the overall system and causes air to be expelled elsewhere, potentially shifting the odour problem to a new location. This reactive solution wastes millions of dollars for the municipal wastewater industry because it compounds rather than solves the problem. Completing an odour and air management study is critical in determining the cause of the odour complaints from the sewer system. Once the source or cause is identified there are a number of effective alternative options to address these issues. One such solution is to install active odour control facilities (OCF). Often one or two appropriately sized and well located OCFs are sufficient to address the odour issues for entire sewage areas. The Highbury Interceptor in Metro Vancouver is an example of this. Numerous carbon scrubbers had been installed to address resident complaints; however this method did not resolve the local issues, and was proving to be a costly exercise. An odour and air management study determined the root cause of the odour emissions, and proposed a solution that would eliminate the problems, and reduce the overall operating cost. INTRODUCTION AND BACKGROUND Due to the combination of organic waste material and bacteria in the sewer, generation of hydrogen sulphide and volatile organic compounds (VOCs) are practically unavoidable, especially in large collection systems where detention times can be significant. These odourous compounds exist within the sewer head space to varying degrees, however as long as the air stays within the sewer system no complaints will result. Odourous air is released from the sewer systems as a direct consequence of pressurization in the headspace above the sewage. There are a number of physical mechanisms that result in this pressurization, however the primary mechanism is air movement in the sewer from the effects of friction drag.

2 AIR MOVEMENT IN SEWERS The primary force for air movement in gravity systems is the friction between the sewer headspace air and the moving wastewater below. As the wastewater flows through the pipe, the air-water interface imparts a friction drag force on the air, and thus dragging the air along with the water. The only resistance to air movement in a sewer pipe is friction between the air and the stationary wall of the sewer. Given this set of simple boundary conditions, it is possible to generate a velocity gradient profile for air movement in sewer, similar to that illustrated in Figure 1. As might be anticipated, the velocity of air is at a maximum near the surface of the water and decreases as it gets near the pipe walls. Figure 1. Idealized Air Velocity Contours for a Sewer at Half Full (in Percent of Water Velocity). The friction factor between the water and the air varies depending on the behaviour of the water. More turbulent and rough water surfaces will result in an increase in friction factor, and. conversely, slower moving smooth water surfaces will result in a lower friction factor. The How rate of the air that is conveyed is proportional to the velocity of the air in the headspace and the cross sectional area of the head space. PRESSURIZATION IN SEWER HEAD SPACE Pressurization in the sewer headspace can occur when there are abrupt changes in the rate of air flow in the sewer. Generally, this results from a high flow rate of air from one section of the sewer colliding with air in a subsequent section of pipe that has a lower flow rate. There are two basic cases that results in this change of air flow rates; change in pipe slope and restriction in the air head space. A change in the pipe slope results in a direct change in velocity of sewer. A steeper section of pipe will result in a faster wastewater flow, and thus impart a higher friction drag on the air in the headspace. When the slope of the pipe is less steep, the resulting air velocity will be less as well.

3 Thus when the pipe slope decreases from one section to another, a potential for pressurization exists. A decrease in the cross sectional area of the headspace will result in a decrease of the air flow rate that the pipe can convey as well. There are a number of physical and hydraulic conditions which causes a decrease in the cross sectional area of the headspace including decrease in pipe diameter, increase in water depth (either from a backwatering effect or a sag in the pipe), and a partial or complete inverted siphon (a complete inverted siphon will result in zero head space, and thus zero air flow beyond this point). When the area of pressurization coincides with a manhole or a vent, sewer air will be expelled at that point, which may result in odour complaints. This previous discussion has focused on the simple condition of a pipe flowing partially full, however in a complex system many other factors can contribute to odour ventilation problems. These factors are briefly listed below. A change in barometric pressure (i.e. atmospheric pressure) will cause air movement into or out of sewers depending upon the relative pressures inside and outside the sewers. A decrease in pipe diameter in the downstream direction limits the air carrying capacity and causes a localised pressure zone. A change in ambient temperature (and therefore a change in air density) causes the convection of air into and out of sewers depending upon temperature gradient direction. Opposing or perpendicular flows entering a junction structure or sewer can cause a temporary back up of air resulting in local air pressurization. Strong winds blowing over the top of a manhole or an open standpipe can draw air by eduction out of the sewer. Ventilation effects of sewers are more pronounced when there is limited access to the sewer. Fewer connections to a sewer increases the ventilation effect by limiting the locations through which pressure can be relieved. This is predominantly a deep sanitary sewer phenomenon, but can occur in moderately sized sanitary sewers and deep combined sewers if manholes and tributaries are limited, widely-spaced or sealed for odour control. Ventilation effects can be severe at inverted siphons, full-flowing or surcharged sewers and pump stations. In these situations, all airflow stops although the upstream sewer continues to drag air. This creates high pressures in the sewers which can cause significant odour release from pump stations and sewers, force air upstream in service connections to release on the roof and even blow water out of residential plumbing traps under severe conditions. CONVENTIONAL SOLUTIONS Conventional solutions to these types of problems have been to either bolt the problem manholes down or to place a passive activated carbon scrubber on, in, or adjacent to the manhole. However doing this without due consideration for the cause of the odour coming out of the sewer can lead to more complaints rather than solve the problem.

4 By bolting down the manhole the zone of pressurization is now extended further than it was previously since pressures can no longer be relieved through that manhole. This means that the zone of pressurization may extend to the next set of manholes, sewer laterals or roof vents, effectively moving the problem to another location. The result is odour complaints in an area that previously did not have a problem. Although passive carbon scrubbers allow air to be vented from the sewer they still increase the local pressurization due to the head loss through the carbon system, thus still potentially moving the problem to a new area. Both of these methods require that odour complaints be systematically addressed until there are no more complaints associated with the sewers. This can be an unpredictable exercise and cost much more than initially expected. ODOUR AND AIR MANAGEMENT STUDY An odour and air management study would determine the source or cause of the odour complaints and determine feasible cost-effective solutions. An odour and air management study may include the following components: Monitoring program - which may consist of monitoring hydrogen sulphide concentrations, sampling VOC concentrations, sampling compounds in the wastewater, and monitoring differential pressure (pressure between the atmosphere and the sewer headspace). Ventilation modelling - the model will be used to perform an analysis of the ventilation dynamics within the sewer system to determine the areas of pressurization and the associated air flow rates. Hydraulic modelling - a dynamic hydraulic model will be used to determine whether any displacement effects take place in the sewer. As the water volume in the sewer system increases a similar amount of air must be expelled from the system, either through the vents or through the local sewer systems. Air Management and Odour Control Strategy - based on the above work, an evaluation will be conducted to develop the most effective strategy for mitigating odour emissions. The selection of the preferred strategy will take into consideration such factors as cost, feasibility of implementation, environmental impacts (i.e., presence of hazardous chemicals/by-products, noise, etc.), and overall treatment effectiveness. ACTIVE ODOUR CONTOL FACILITIES An active odour control facility is one solution that can address local pressurizations within the sewer. An active odour control facility draws air from the sewer using a fan, treats it, and releases it to the atmosphere. There are many technologies available that can be used to treat the air, such as biofilters, carbon adsorbers, chemical scrubbers etc. By drawing air in from the sewer with a blower and treating it, an area of negative pressure, also call a zone of influence, can be created in the sewer system around the odour control facility. This area of negative pressure will prevent air from escaping into the atmosphere. Based on the sizing of the facility and the geometry of the local sewer system, a zone of influence extending several kilometres is possible. The advantage of this system is that a single facility can address

5 odour issues in an entire neighbourhood. Although the initial capital cost of an OCF can be high, the overall life cycle cost can be much less compared to multiple carbon scrubbers throughout the system. CASE STUDY - HIGHBURY INTERCEPTOR, METRO VANCOUVER The Highbury Interceptor, owned and operated by Metro Vancouver, is one of the principle trunk sewers in the Vancouver Sewerage Area (VSA), and services the majority of the City of Vancouver and a portion of the City of Burnaby. The sewer is a 6 km long 2,900 mm diameter combined sewer with significant odour and headspace pressurization issues identified along its length. In recent years the number of complaints regarding odour from the interceptor vents have increased. In addition to problems from venting foul air, during winter storms large amounts of air have been observed expelled from manholes and vents, resulting in howling noise. These events are significant enough that manhole covers have been blown off and residents have reported seeing heaving of the asphalt pavement around the interceptor manholes. Ventilation modelling and hydraulic modelling were carried out to simulate the ventilation dynamics within the sewer. Differential pressure monitoring, hydrogen sulphide monitoring and air phase sampling along the sewer was carried out during dry weather periods and wet weather periods as well. The differential pressure data indicated that periods of significant positive pressure occur throughout the Highbury Interceptor. As a result, the potential for odour emissions exists at every point of release along the sewer. While the air pressure within the sewer is relatively moderate under average daily flow conditions, during some storm events pressure in the sewer increases rapidly, exceeding the differential pressure monitor's range. Pressures of this magnitude are considered significant and are rarely seen in sewer systems. Based on the ventilation modelling the peak friction drag airflow condition at the downstream endof the sewer was estimated to be 283 m3/min (10,000 cfm). Since the downstream end of the Highbury Interceptor is a siphon, no air can be conveyed beyond this point, resulting in a significant area of pressurization. In addition to this the dynamic hydraulic revealed that the unique characteristics of the Highbury Interceptor profile resulted in the headspace in the sewer becoming completely isolated from upstream, downstream and tributary sewers under certain flow conditions. This occurs during high sewage flow events, where a backwatering effect cuts off the headspace at the upstream end of the system, and a siphon at the downstream end prevents any entrapped air from escaping. Thus, as the sewage level increases with the storm event, a large amount of the trapped air can only be displaced through the few small vents located along the sewer, resulting in high pressures and high velocities through the vents. The results of the hydraulic model correlated well with the monitoring data, revealing that the extreme pressurization events occurred at the same time as the headspace being isolated. The model calculates that a typical storm can displace as much as 200 m3/min of air. The team's recommendation for the sewer sytsem was to install three well placed active odour control systems along the HI to address both the odour complaints and the pressurization events.

6 The main odour control facility, with a treatment capacity of 283 m3/min, would have a zone of influence of approximately 4.6 km. CONCLUSION Although the Highbury Interceptor would be considered a special case example it illustrates that without a well planned odour and air management study that included both ventilation modelling and hydraulic modelling, the cause ofodours being released into the atmosphere and the extreme pressurization events would not have been identified. The study also identified that one well placed active odour control facility will likely be able to address pressurization events along 80% of its length. Conducting an odour and air management study is key in determining the root cause of odour complaints in a neighbourhood, and developing cost effective solutions. Without a comprehensive study, municipalities can only react to odour complaints and will not be able to develop a cost effective solution that can solve the problem for entire sewerage areas.

Odour and Air Management Studies Key Tool in Determining Effective Odour Control Solutions. Presented by: Wayne Wong, M.A.Sc, EIT

Odour and Air Management Studies Key Tool in Determining Effective Odour Control Solutions. Presented by: Wayne Wong, M.A.Sc, EIT Odour and Air Management Studies Key Tool in Determining Effective Odour Control Solutions Presented by: Wayne Wong, M.A.Sc, EIT Project Team 2 Yuko Suda, P.Eng. Kerr Wood Leidal Associates Ltd. Ted Steele,

More information

Dynamic Sewer Ventilation Modeling

Dynamic Sewer Ventilation Modeling Dynamic Sewer Ventilation Modeling Dynamic Ventilation Modeling 2 Outline Dynamic Ventilation Model Karl City of Burnaby Perspective Ron The Burnaby Model Karl Key Findings - Ron Dynamic Ventilation Modeling

More information

Implementing Vapor Phase Odor Control on Large Diameter Interceptor Systems

Implementing Vapor Phase Odor Control on Large Diameter Interceptor Systems Implementing Vapor Phase Odor Control on Large Diameter Interceptor Systems Biosolids and Odor and Corrosion Conference & Expo 2013 James Joyce, P.E., V&A Consulting Engineers, Inc. Chris Hunniford, P.E.,

More information

Controlling Odour and Corrosion in the Collection System: Region of Peel s Trunk Sewer Odour and Corrosion Control Master Plan

Controlling Odour and Corrosion in the Collection System: Region of Peel s Trunk Sewer Odour and Corrosion Control Master Plan Controlling Odour and Corrosion in the Collection System: Region of Peel s Trunk Sewer Odour and Corrosion Control Master Plan Mark Andrews 1*, P.Eng., Imran Motala 2, P.Eng., Chris Hunniford 3, Jim Joyce

More information

Sewer Ventilation: Factors Affecting Airflow and Modeling Approaches

Sewer Ventilation: Factors Affecting Airflow and Modeling Approaches Sewer Ventilation: Factors Affecting Airflow and Modeling Approaches Scott A. Lowe Manhattan College, Riverdale, New York. Abstract Sewer ventilation modeling and analysis is typically performed as part

More information

Module 2 : System of Sanitation. Lecture 2 : System of Sanitation

Module 2 : System of Sanitation. Lecture 2 : System of Sanitation 1 P age Module 2 : System of Sanitation Lecture 2 : System of Sanitation 2 P age 2.1 BACKGROUND For safe disposal of the sewage generated from a locality efficient collection, conveyance, adequate treatment

More information

1 Metro Vancouver Case Study Vancouver Sewage Area Infrastructure Vulnerability to Climate Change

1 Metro Vancouver Case Study Vancouver Sewage Area Infrastructure Vulnerability to Climate Change 1 Metro Vancouver Case Study Vancouver Sewage Area Infrastructure Vulnerability to Climate Change 1.1 Background Within the First National Engineering Vulnerability Assessment, the Public Infrastructure

More information

Challenges of Designing Wastewater Heat Recovery Systems

Challenges of Designing Wastewater Heat Recovery Systems Challenges of Designing Wastewater Heat Recovery Systems Mike Homenuke, P.Eng. Canadian Geoexchange Coalition National Conference 2013 Outline 2 Wastewater 101 What resources are available? Who is able

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7: Hydraulic Design of Sewers and Storm Water Drains 7.0 HYDRAULIC DESIGN OF SEWERS AND STORM WATER DRAINS 7.1 General Consideration

More information

Wastewater Collection System

Wastewater Collection System WASTEWATER COLLECTION SYSTEM CE 370 1 Wastewater Collection System The function of the collection system is to collect the wastewater from residential, commercial, and industrial areas within the service

More information

GENERAL INFORMATION AND REQUIREMENTS

GENERAL INFORMATION AND REQUIREMENTS GENERAL INFORMATION AND REQUIREMENTS 1.0 BOARD S STANDARD SPECIFICATIONS: Copies of these Standard Specifications for Water Mains, Sanitary Sewers and Sewage Pumping Stations may be purchased from the

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

City of Logan Sanitary Sewer Design Standards

City of Logan Sanitary Sewer Design Standards City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR

More information

Type of Area Density (persons/ha) Large lots 5-7 Small lots, single family 75 Small lots, two family 125 Multistory apartments min.

Type of Area Density (persons/ha) Large lots 5-7 Small lots, single family 75 Small lots, two family 125 Multistory apartments min. Design of Sanitary Sewer System Key components Service connections, Manholes and pump stations Design Flows 1. Infiltration and interflow (71 to 14 m 3 /d/km). Flow from the service connections Type of

More information

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply: SECTION 400 SANITARY SEWER SYSTEM The design of sanitary sewers shall be in conformance with the applicable sections of the State of Washington, Department of Ecology manual, Criteria for Sewage Works

More information

Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel

Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel 5 Surge Analysis for the Proposed OSIS Augmentation Relief Sewer Tunnel M. P. Cherian, Ari Pandian, Karen Ridgway and Gregory Barden The City of Columbus, Ohio, submitted a wet weather management plan

More information

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL INTRODUCTION The District developed a hydraulic model of the sanitary sewer system as part the 2000 Wastewater Comprehensive Plan. The output from this model

More information

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Community Services Department (CSD) standards for: INDEX Designing Gravity Sewer Collection Facilities ( Sewer Design

More information

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS GRAVITY SEWER COLLECTION DESIGN This section of the manual contains the Washoe County Department of Water Resource s (DWR) standards for: Designing Gravity Sewer Collection Facilities ( Sewer Design Standards

More information

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

WASTEWATER & STORM WATER COLLECTION AND REMOVAL CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

Learning objectives. Upon successful completion of this lecture, the participants will be able to: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to: Describe and perform the required step for designing sewer system networks Outline Design

More information

Chapter 5 Existing Wastewater Facilities

Chapter 5 Existing Wastewater Facilities Chapter 5 Existing Wastewater Facilities \\7348101\TOC.doc CHAPTER 5 Existing Wastewater Facilities 5.1 INTRODUCTION Lacey s wastewater utility serves over 21,000 acres (33 square miles) of residential

More information

Wastewater Master Facility Report. (Project Name) (Project Basin Location)

Wastewater Master Facility Report. (Project Name) (Project Basin Location) Wastewater Master Facility Report For (Project Name) (Project Basin Location) The Wastewater Master Facility Report for (Project name) dated (Date); located in the (Basin Name) Basin has been completed

More information

3.9 times the average 3.8 times the average 3.6 times the average

3.9 times the average 3.8 times the average 3.6 times the average ARTICLE VI DESIGN OF SANITARY SEWERS M'RSMIN. VOL.281 JA 2 4 2001 IMAGE; Section 601 Determination of the Amount of Sewage for Sanitary Sewers A. MSD Design Standards for estimating sanitary sewage flow

More information

Technical Memorandum No. 1

Technical Memorandum No. 1 DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY Serving the Public Protecting the Environment Technical Memorandum No. 1 Multi-Jurisdictional Use Facilities Capital Cost Allocation DRAFT April 17, 2013

More information

SECTION TEMPORARY SEWER BYPASS PUMPING

SECTION TEMPORARY SEWER BYPASS PUMPING PART 1 GENERAL 1.1 DESCRIPTION A. The CONTRACTOR shall provide a complete sewer bypassing system including, but not limited to, the following: 1. Developing a sewer bypassing plan 2. Developing a spill

More information

WEF Collection Systems Conference 2017

WEF Collection Systems Conference 2017 Davenport, Iowa 14th District Diversion Study Karol Giokas, P.E., RJN Group Tom Leabhart, P.E., Davenport, IA ABSTRACT The 14 th District sanitary sewer basin in Davenport, Iowa has high levels of inflow

More information

Sanitary Sewer Design. Sanitary Sewers, Page 1

Sanitary Sewer Design. Sanitary Sewers, Page 1 Sanitary Sewer Design Sanitary Sewers, Page 1 Sanitary Sewers, Page 2 Sanitary Sewer Design sanitary sewers collect and transport domestic and industrial wastes via gravity flow the ultimate destination

More information

Effluent Conveyance. Paul Trotta, P.E., Ph.D. Justin Ramsey, P.E. Chad Cooper

Effluent Conveyance. Paul Trotta, P.E., Ph.D. Justin Ramsey, P.E. Chad Cooper Effluent Conveyance Paul Trotta, P.E., Ph.D. Justin Ramsey, P.E. Chad Cooper University Curriculum Development for Decentralized Wastewater Management 1 NDWRCDP Disclaimer This work was supported by the

More information

Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11)

Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11) بسم هللا الرحمن الرحيم Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11) A sewer that drops below the hydraulic gradient to pass under an obstruction, such as a railroad cut,

More information

Water supply components

Water supply components Water supply components Water sources structures (Dams, wells, reservoirs) Surface water Groundewater Pipelines from source Water treatment plant components Pumping stations Storage (elevated tanks) Distribution

More information

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS 2.1. General Requirements Sanitary sewers are to be provided solely for the removal of sanitary waste. Under no circumstances shall any roof drains,

More information

Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change

Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change Andrew Boyland, P.Eng. Kerr Wood Leidal Associates Arash Masbough, M.A.Sc., PMP, P.Eng. Associated Engineering Today s Presentation

More information

Modelling a Combined Sewage and Stormwater Flood Detention Basin

Modelling a Combined Sewage and Stormwater Flood Detention Basin Modelling a Combined Sewage and Stormwater Flood Detention Basin A. Pugh B.E. (Hons), Member A.W.A. Sales and Support Manager, Wallingford Software Pty Ltd, Australia S. Ratcliffe B.Sc(Hons), Grad Dip

More information

USING HYDROXYL RADICALS TO MITIGATE HYDROGEN SULPHIDE AN ODOUR CONTROL STRATEGY AT THE COURTICE WPCP

USING HYDROXYL RADICALS TO MITIGATE HYDROGEN SULPHIDE AN ODOUR CONTROL STRATEGY AT THE COURTICE WPCP USING HYDROXYL RADICALS TO MITIGATE HYDROGEN SULPHIDE AN ODOUR CONTROL STRATEGY AT THE COURTICE WPCP Ray Davis*, Andy Seeley, Regional Municipality of Durham *Regional Municipality of Durham, 100 Osborne

More information

Aerator for Sewer Odor and Corrosion Control

Aerator for Sewer Odor and Corrosion Control Aerator for Sewer Odor and Corrosion Control MUNICIPAL SYSTEMS Sewer Force Main Discharge Sewer Wet Wells & Storage Tanks Irrigation Ponds We build tough products for tough environments A NEW SOLUTION

More information

BE THE CHANGE YOU WANT TO SEE IN THE WORLD

BE THE CHANGE YOU WANT TO SEE IN THE WORLD BE THE CHANGE YOU WANT TO SEE IN THE WORLD COMMON MISTAKES BY CONSULTANTS IN PLANNING OF SEWER NETWORKS AND STP s Col Naresh Sharma Director (PHE), E-in-C s Br PROLOUGE PROLOUGE WATER STRESSED NATION.

More information

Aerator for Sewer Odor and Corrosion Control

Aerator for Sewer Odor and Corrosion Control Aerator for Sewer Odor and Corrosion Control MUNICIPAL SYSTEMS Sewer Force Main Discharge Sewer Wet Wells & Storage Tanks Irrigation Ponds Wastewater Treatment Tanks We build tough products for tough environments

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility

Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility Somerset Raritan Valley Sewerage Authority SSO Abatement and Storm Control Treatment Facility Michael Sanders, P.E., Kleinfelder Collection Systems Specialty Conference NEWEA September 12, 2016 Presentation

More information

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan 4 Capacity Analysis The capacity analysis used the calibrated dry weather and wet weather wastewater collection system model to evaluate

More information

CHAPTER 4 DESIGN CRITERIA

CHAPTER 4 DESIGN CRITERIA CHAPTER 4 DESIGN CRITERIA 4.1 INTRODUCTION This chapter summarizes the basic design criteria necessary to develop options and sizing estimates for the components of centralized wastewater collection systems.

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

HYDRAULIC HYDRODYNAMIC MODELING AS AN EFFECTIVE MANAGEMENT TOOL FOR LARGE COLLECTION SYSTEMS - THE L.A. STORY

HYDRAULIC HYDRODYNAMIC MODELING AS AN EFFECTIVE MANAGEMENT TOOL FOR LARGE COLLECTION SYSTEMS - THE L.A. STORY HYDRAULIC HYDRODYNAMIC MODELING AS AN EFFECTIVE MANAGEMENT TOOL FOR LARGE COLLECTION SYSTEMS - THE L.A. STORY Fernando Gonzalez, Adel Hagekhalil, Bryan Trussell, City of Los Angeles Bureau of Sanitation

More information

The Shades Valley Transfer Line (SVT) in Jefferson County, Ala., is only 24 years

The Shades Valley Transfer Line (SVT) in Jefferson County, Ala., is only 24 years The Shades Valley Transfer Line (SVT) in Jefferson County, Ala., is only 24 years old, but high hydrogen sulfide conditions early in its operation have its owners concerned about its overall condition.

More information

Appendix J: Storm Conveyance Design Parameters

Appendix J: Storm Conveyance Design Parameters Appendix J: Storm Conveyance Design Parameters Drain Commissioner 39 February 2005 STORM DRAINAGE DESIGN CRITERIA A. STORM SEWERS 1. The required discharge capacity shall be determined by the Rational

More information

SEWAGE TREATMENT AND DISPOSAL

SEWAGE TREATMENT AND DISPOSAL SEWAGE TREATMENT AND DISPOSAL QUANTITY OF SANITARY SEWAGE AND STORM WATER Zerihun Alemayehu Unpolluted cooling water Intercept or sewer Sources of Sewage Residential and commercial sewage Industrial wastewater

More information

Using Sanitary Sewer I/I Field Data to Calibrate a Storm Sewer Model

Using Sanitary Sewer I/I Field Data to Calibrate a Storm Sewer Model 15 Using Sanitary Sewer I/I Field Data to Calibrate a Storm Sewer Model Josh A. Reinicke, Marc A. Lehmann and C. Timothy Fallara Since 1992, the City of Columbus Division of Sewerage and Drainage (DOSD)

More information

Design and Construction of Local Public and Private Sewers and Ancillary Facilities

Design and Construction of Local Public and Private Sewers and Ancillary Facilities Chapter 2 Design and Construction of Local Public and Private Sewers and Ancillary Facilities Subchapter I - General 2.101 Purpose...1 2.102 Applicability...1 2.103 Electronic data...1 2.104 Effect of

More information

4 EXISTING FACILITIES EVALUATION

4 EXISTING FACILITIES EVALUATION 4 EXISTING FACILITIES EVALUATION The City is served by a combination of wastewater collection, conveyance, and treatment systems. The City owns and operates the collection system that collects wastewater

More information

MCBERNS ZC SERIES ODOUR FILTERS STANDARD SPECIFICATION

MCBERNS ZC SERIES ODOUR FILTERS STANDARD SPECIFICATION MCBERNS ZC SERIES ODOUR FILTERS STANDARD SPECIFICATION 1 INTRODUCTION The McBerns ZC series odour filters are designed for sewage pump stations, trunk sewerage systems, storage tanks, sewer air release

More information

Dynamic Pump Design of Complex Rising Main Injector Systems

Dynamic Pump Design of Complex Rising Main Injector Systems Dynamic Pump Design of Complex Rising Main Injector Systems Morten Just Kjølby 1, Arne Møller 1 1 DHI Denmark. (Presenter: Morten Just Kjølby mjk@dhigroup.com) Abstract In low laying coastal areas sewerage

More information

Design of Underground Sewerage System for Kalapatti, East Zone Coimbatore

Design of Underground Sewerage System for Kalapatti, East Zone Coimbatore Design of Underground Sewerage System for Kalapatti, East Zone Coimbatore A. Kothai, R. Muthu priya, A. Rajkumar Department of Civil Engineering, PSG College of Technology, Coimbatore, India E-Mail: kothaiarjunan@gmail.com,

More information

DEALING WITH H 2 S CORROSION IN THE GORDON TRUNK SEWER

DEALING WITH H 2 S CORROSION IN THE GORDON TRUNK SEWER North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper C-3-03 DEALING WITH H 2 S CORROSION IN THE GORDON TRUNK SEWER Ashley Rammeloo 1 1 Environmental

More information

CHAPTER 6. Sanitary Sewer

CHAPTER 6. Sanitary Sewer CHAPTER 6 Sanitary Sewer A. Introduction All proposed developments, subdivisions, and buildings must have a properly designed and constructed sanitary sewer collection system. The system shall provide

More information

Sunnyside Heights (Grandview Heights Area #2) Neighbourhood Concept Plan (NCP) - Engineering Servicing and Financial Strategies

Sunnyside Heights (Grandview Heights Area #2) Neighbourhood Concept Plan (NCP) - Engineering Servicing and Financial Strategies CORPORATE REPORT NO: R236 COUNCIL DATE: November 15, 2010 REGULAR COUNCIL TO: Mayor & Council DATE: November 10, 2010 FROM: General Manager, Engineering FILE: 6520-20 (GH#2) SUBJECT: Sunnyside Heights

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

Foul Water Drainage Strategy Monkton Road Minster CT12 4EE

Foul Water Drainage Strategy Monkton Road Minster CT12 4EE 66-68 Monkton Road Minster CT12 4EE RMB Consultants (Civil Engineering) Ltd May 2016 RMB Consultants (Civil Engineering) Ltd 39 Cossington Road Canterbury Kent CT1 3HU Tel 01227 472128 www.rmbconsultants.co.uk

More information

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Attachment 1 Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Sanitary Sewer System Master Plan Summary Points - City s sanitary system

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

A. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards General 11 a. Future Extensions 11

A. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards General 11 a. Future Extensions 11 A. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards 11 1. General 11 a. Future Extensions 11 b. Design Calculations 11 c. Easements and Property 12

More information

Rehabilitating a 105-inch Interceptor Innovations and Lessons Learned

Rehabilitating a 105-inch Interceptor Innovations and Lessons Learned Rehabilitating a 105-inch Interceptor Innovations and Lessons Learned Pipe User Group Northern California March 13, 2018 Tim Karlstrand and Gary Warren Agenda System Overview Project Need Video Lessons

More information

Metro Vancouver I&I Reduction Measures

Metro Vancouver I&I Reduction Measures ,000 DETERMINATION OF RELATIONSHIP BETWEEN I&I RATE AND SANITARY SEWER AGE 5 to 100 Year Age-of-Sewer 5-Year 24-Hour I&I Rate,000,000 y = 6770.2e 0.0323x,000,000,000,000,000 y = 1104.3x - 20729,000,000

More information

Sewer Capacity Assessment

Sewer Capacity Assessment Sewer Capacity Assessment Wainlode Lane, Norton, Gloucestershire DE-1607-722 Version 2 Date: 10 th February 2017 Black & Veatch Ltd. 60 High Street Redhill Surrey RH1 1SH Sewer Capacity Assessment Summary

More information

Development in the City of Toronto

Development in the City of Toronto Development in the City of Toronto Water Infrastructure Challenges and Opportunities Graham Harding, P.Eng. Toronto Water, City of Toronto Urban Land Institute Leadership Program February 16, 2017 Toronto

More information

DIVISION 3: SEWER. Improvement Design Standards City of Dundee Oregon. Division 3 : Sewer Page 1

DIVISION 3: SEWER. Improvement Design Standards City of Dundee Oregon. Division 3 : Sewer Page 1 DIVISION 3: SEWER 3.1 DESIGN CRITERIA A. APPLICABILITY 1. These Design Standards shall govern all construction and upgrading of public sanitary sewer facilities in the City of Dundee and applicable work

More information

2. DEFINITIONS. American Association of State Highway and Transportation Officials.

2. DEFINITIONS. American Association of State Highway and Transportation Officials. 2. DEFINITIONS 2.010 Definitions [See Amendment 2] In addition to words and terms that may be defined elsewhere in this manual, the following words and terms shall have the meanings defined below: AASHTO:

More information

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter X X X Adopt Entire Chapter as amended (amended sections listed below) X X X X X X

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter X X X Adopt Entire Chapter as amended (amended sections listed below) X X X X X X CALIFORNIA PLUMBING CODE MATRIX ADOPTION TABLE CHAPTER 9 - VENTS (Matrix Adoption Tables are non-regulatory, intended only as an aid to the user. See Chapter 1 for state agency authority and building application.)

More information

Hydraulic Modeling of Deep Tunnel Provides Cost Savings

Hydraulic Modeling of Deep Tunnel Provides Cost Savings 5 Hydraulic Modeling of Deep Tunnel Provides Cost Savings Taymour El-Hosseiny, Karen Reinhart and M. P. Cherian In 2005, the City of Columbus, Ohio submitted a plan to the Ohio Environmental Protection

More information

Welcome South London Wastewater Servicing Study. Municipal Class Environmental Assessment Master Plan Public Information Centre.

Welcome South London Wastewater Servicing Study. Municipal Class Environmental Assessment Master Plan Public Information Centre. Welcome South London Wastewater Servicing Study Municipal Class Environmental Assessment Master Plan Public Information Centre February 26, 2018 The purpose of this Public Information Centre (PIC) is to:

More information

PRESSURE SEWER SYSTEMS PLANNING AND DESIGN GUIDELINE JUNE 2018 VERSION: 1.0 VERSION: 2.0

PRESSURE SEWER SYSTEMS PLANNING AND DESIGN GUIDELINE JUNE 2018 VERSION: 1.0 VERSION: 2.0 PRESSURE SEWER SYSTEMS PLANNING AND DESIGN GUIDELINE JUNE 2018 VERSION: 1.0 VERSION: 2.0 Contents 1 General... 4 1.1 Introduction... 4 1.2 Background... 4 2 Can pressure sewer be investigated?... 5 2.1

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE Project Background As part of the Seaterra Program, Clover A new conveyance pipe (forcemain) Pump Station will be upgraded and will run

More information

A Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond.

A Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond. Engineering Page 3-1 3.0 STORM DRAINAGE 3.1 GENERAL Good drainage is vital to flat urban areas such as Lulu Island. It is essential that every storm sewer must be designed accurately minimizing conflicts

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

Improved Inflow & Infiltration (I&I) Monitoring Program

Improved Inflow & Infiltration (I&I) Monitoring Program City of Abbotsford Improved Inflow & Infiltration (I&I) Monitoring Program Submission For 2009 UBCM Community Excellence Awards Best Practices City of Abbotsford Improved Inflow & Infiltration (I&I) Monitoring

More information

Facilities Development Manual

Facilities Development Manual State of Wisconsin Department of Transportation Facilities Development Manual ORIGINATOR Director, Bureau of Highway Development PROCEDURE 13-25-35 CHAPTER 13 Drainage SECTION 25 Storm Sewer Design SUBJECT

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Project Identification Project Name: Elyria East Side Relief Sewer Phase 1B South (CS390337-0018), Phase 1C (CS390337-0014), Phase 1D (CS390337-0017) Applicant: The Honorable Holly

More information

Sanitary Sewer 101. Jan. 12, 2016 Keith Fisher, P.E. Director of Public Works

Sanitary Sewer 101. Jan. 12, 2016 Keith Fisher, P.E. Director of Public Works Sanitary Sewer 101 Jan. 12, 2016 Keith Fisher, P.E. Director of Public Works What We Will Cover -What is Sanitary Sewer? -Components -History -What types of systems are there? -What types of materials

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

Course: Wastewater Management

Course: Wastewater Management Course: Wastewater Management Prof. M. M. Ghangrekar Questions 1 1. Describe advantages and disadvantages offered by the water carriage system. 2. What are the possible adverse effects when untreated or

More information

GRAVITY CALIBRATION: A SIGNATURE ACCOMPLISHMENT

GRAVITY CALIBRATION: A SIGNATURE ACCOMPLISHMENT GRAVITY CALIBRATION: A SIGNATURE ACCOMPLISHMENT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 ABSTRACT Virginia Beach,

More information

CHAPTER 4 SYSTEM DESIGN CRITERIA

CHAPTER 4 SYSTEM DESIGN CRITERIA INTRODUCTION CHAPTER 4 SYSTEM DESIGN CRITERIA Adequate design of the District s wastewater conveyance facilities requires the determination of the quantity of wastewater from contributing sources. The

More information

The Corporation of Delta COUNCIL REPORT Regular Meeting. South Delta Sanitary Sewer Capacity

The Corporation of Delta COUNCIL REPORT Regular Meeting. South Delta Sanitary Sewer Capacity The Corporation of Delta COUNCIL REPORT Regular Meeting F.02 To: Mayor and Council File No.: 5440-30/SD From: Engineering Department Date: July 6, 2012 South Delta Sanitary Sewer Capacity The following

More information

Chapter 9 Sanitary Sewers

Chapter 9 Sanitary Sewers Chapter 9 Sanitary Sewers I:\AD\030\U30\U30009.docx 4-8-16 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow 9-1 9.4 Facility Design

More information

Technical Memorandum. 1. Introduction. 2. Background. 2.1 Lakeside Creek System. DATE: July 10, 2012 TO:

Technical Memorandum. 1. Introduction. 2. Background. 2.1 Lakeside Creek System. DATE: July 10, 2012 TO: Technical Memorandum DATE: July 10, 2012 TO: Heather Beresford, Resort Municipality of Whistler James Hallisey, P.Eng., Resort Municipality of Whistler FROM: Erica Ellis, M.Sc., P.Geo. RE: LAKESIDE CREEK

More information

Vancouver Area Sewer Systems

Vancouver Area Sewer Systems November 17, 2009 Vancouver Area Sewer Systems Brent Burton, M.A.Sc., P.Eng. Metro Vancouver Andrew Boyland, P.Eng. Kerr Wood Leidal Assoc. Ltd Metro Vancouver case study Host: Metro Vancouver (Legal Name:

More information

Vancouver Area Sewer Systems

Vancouver Area Sewer Systems November 17, 2009 Vancouver Area Sewer Systems Brent Burton, M.A.Sc., P.Eng. Metro Vancouver Andrew Boyland, P.Eng. Kerr Wood Leidal Assoc. Ltd Metro Vancouver case study Host: Metro Vancouver (Legal Name:

More information

Rowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project. TACWA Meeting

Rowlett Cottonwood Transfer Sewer: 60 RCP Sanitary Sewer Rehabilitation Project. TACWA Meeting Rowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project TACWA Meeting September 25, 2009 North Texas Municipal Water District Project Background 1. Rowlett-Cottonwood Transfer

More information

MANAGING AND MAINTAINING SEWER RISING MAINS LESSONS LEARNT. Julian Vivoli. Gold Coast Water

MANAGING AND MAINTAINING SEWER RISING MAINS LESSONS LEARNT. Julian Vivoli. Gold Coast Water MANAGING AND MAINTAINING SEWER RISING MAINS LESSONS LEARNT Paper Presented by: Julian Vivoli Author: Julian Vivoli, Asset Project Officer, Gold Coast Water 41st Annual WIOA Queensland Water Industry Operations

More information

RECOMMENDATION PREVIOUS REPORTS PERTINENT TO THIS MATTER STRATEGIC PLAN

RECOMMENDATION PREVIOUS REPORTS PERTINENT TO THIS MATTER STRATEGIC PLAN TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON NOVEMBER 21, 2017 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES & CITY ENGINEER WASTEWATER

More information

Wasting Resources Evaluating Heat & Water Recovery Opportunities in Wastewater Systems

Wasting Resources Evaluating Heat & Water Recovery Opportunities in Wastewater Systems Wasting Resources Evaluating Heat & Water Recovery Opportunities in Wastewater Systems Chris Johnston, PEng Kerr Wood Leidal Associates Erik Lindquist, PEng DEC Design Mechanical Consultants 1 Outline

More information

DELGANY INTERCEPTOR AND SOUTH PLATTE RIVER STUDY

DELGANY INTERCEPTOR AND SOUTH PLATTE RIVER STUDY DELGANY INTERCEPTOR AND SOUTH PLATTE RIVER STUDY ALTERNATIVES ANALYSIS APPENDICES A C Prepared for City and County of Denver Department of Public Works June 28, 2017 6200 South Quebec Street Greenwood

More information

Infiltration and Inflow. Michael Sassaman Phone

Infiltration and Inflow. Michael Sassaman Phone Infiltration and Inflow Michael Sassaman msassaman@entecheng.com Phone 610-373-3345 Inflow and Infiltration PA DEP Learning Objectives Do you have Excessive I/I? Sources of Inflow and Infiltration I/I

More information

Section 3 Modeling and Capacity Analysis

Section 3 Modeling and Capacity Analysis Section 3 Modeling and Capacity Analysis The capacity of the existing DSRSD wastewater collection system and the future capacity requirements of the system were determined through hydraulic modeling. This

More information

Section 8 System Evaluation and Capacity Assurance Plan (SECAP)

Section 8 System Evaluation and Capacity Assurance Plan (SECAP) System Evaluation and Capacity Assurance Plan (SECAP) The WDR requires owners and operators of sewer collection systems to have a (SECAP). This component involves preparing and implementing a Capital Improvement

More information

Chapter 6 STEP System Force Main Velocity Evaluation

Chapter 6 STEP System Force Main Velocity Evaluation Chapter 6 STEP System Force Main Velocity Evaluation \\7348101\TOC.doc CHAPTER 6 STEP System Force Main Velocity Evaluation 6.1 INTRODUCTION The City s existing STEP (septic tank effluent pump) pumps currently

More information

FORM 1 S Design Certification List - Wastewater Agreements

FORM 1 S Design Certification List - Wastewater Agreements FORM 1 S Design Certification List - Wastewater Agreements Job Description Location Developer / Owner Developer / Owner Contact Details Consultant Gippsland Water Drawing Numbers Notes: 1 Where the word

More information