M51 Kliplev Sønderborg motorvejen

Size: px
Start display at page:

Download "M51 Kliplev Sønderborg motorvejen"

Transcription

1 M51 Kliplev Sønderborg motorvejen A motorway project to be carried out as a Public Private Partnership 1

2 2

3 PART 1 Project description 3

4 Facts about the project The project compromises: 26 km of four-lane motorway between the E45 at Kliplev and the Alssund Bridge at Sønderborg 7 intersections 10 minor roads to be led under/over the motorway 18 km of minor roads to be modified 4

5 Facts 2,90 Mio. m³ Earthworks (mass balance) 0,35 Mio. m³ soft soil 0,90 Mio. m³ Stabilisation 0,90 Mio. m² base layer stabilisation t asphalt (0,80 Mio. m²) t cement & lime m dewatering pipes (PP and Concrete) m slot drain (in-situ) 5

6 Actual Status of the Project Largest Road Construction Side in Scandinavia 350 Skilled Employees >225 Major Construction Machines (20-75to) Works all over the project ongoing Earthworks capacity m³ per day Earthworks will be finished in April 2011 (2,9 Mio. m³) First Intersections is handed over in December 2010 Focus 2011 on Road Crust, CS, Asphalt, Slot Drain Motorway will be definitly finished in spring

7 PART 2 Life Cycle Management Approach 7

8 Functional Design / LCA 8

9 Interfaces Sensitivity Principle of gear wheels 9

10 Process of Pavement Design 10 Process for finding optimum pavement construction is based on holistic approach Collection of relevant data and information Traffic information Climatic information Availability of materials and construction methods Bearing capacity of subgrade and foundation etc. Pavement construction alternatives (draft design) Life Cycle Cost Analysis Investment costs Costs for maintenance Costs for unavailability Performance requirements and prediction Economic assessment and optimization etc. Detailed design of optimum pavement construction(s) 10

11 Pavement Management Process 11 Basics for strategic decisions Inventory Netdata Pavement Traffic Condition Others INPUT OUTPUT Models and requirements Performance prediction Treatments Requirements (framework conditions) Time frame and intervals Basics for recommended construction program 11

12 LCC - Analysis 12 LCC-analysis is state of the art process for managing motorways Finding optimum solution Maximize benefit (monetary, nonmonetary) Minimize costs Maximize savings (in user costs) Maintenance Treatments in accordance with Pavement design Flexible pavement Rigid pavement Semi rigid pavement Requirements 12

13 Life time consideration -> responsibilty M51 Project showed several different approaches LCA must me optimized over all gear wheels it must be sure that the taken design is be best solution for the given system (95%) the system contain not only the pavement: Dewatering, Geometry, Road Furniture, Subsoil works must be taken in consideration not the cheapest solution is the best over the lifetime 13

14 4 major benefits of LCA: evaluation of competing options in purchasing; improved awareness of total costs; more accurate forecasting of cost profiles; and performance trade-off against cost. 14

15 Prioritization Methods 15 Prioritization Methods Subjective prioritization Prioritization according to technical criteria Prioritization according to economic criteria Optimization Method ( Modern PMS ) Characterized by: Performance prediction of pavement condition Combination of different maintenance strategies Optimization of on target value under given preconditions 15

16 LCC-Analysis - Prognosis 16 Core of a modern PMS Prognosis of single technical parameters (PIs) Condition? Cond. Time Use of deterministic and/or probabilistic performance prediction models 16

17 Maintenance Strategies 17 + Pavement Condition - Do-Nothing-Strategy Strategy 1 Strategy 2 Reconstruction Overlay Overlay Age [Year] 17

18 LCC Costs optimisation 18 Assessment of possible design and maintenance strategies during LCC-analysis Bearing capacity (e.g. residual life) Overlay 20 Inlay Bearing capacity (e.g. residual life) 20 Reinforcement 5 Threshold 5 Threshold Time Time Pavement condition (e.g. rutting) Overlay Inlay 20 Threshold Pavement condition (e.g. rutting) Reinforcement 20 Threshold Time Time 18

19 Pavement Management Software 19 19

20 PART 3 Technical Execution M51 20

21 Technical parameters Cross section Homogenius crossfall 30 Overall width Green middle strip (2m) will be a water tight construction 35 cm thick layer of compacted clay with mineral additives. Pavement Design 2.5 cm bitumen-concrete SMA 6+ (with noise reducing surface) 4 cm bituminous binding course ABB 11 8 cm bituminous bearing course GAB cm cement stabilized sand layer 40.5 cm compacted sand layer BL II xx cm lime stabilisation (incl. subsoil grade) Dewatering System In-situ casted slot drain (2 Paradell systems to collect all water) 21

22 Cross Section 22

23 Principles of execution All elements are optimized and crosschecked To improve quality innovative documentation systems are used (2way communication) To improve accuaracy all elements are build in with highest precision (UTS/Totalstation mm) CS Slot Drain Pavement 23

24 Soil Stabilisation 24

25 Logistical System for Cement & Lime 25

26 Dewatering - Slot Drain 26

27 Dewatering - Slot Drain Indikator Enhed Referencesystem Slidserende Differenceværdi Rørledningslængde pr. meter af motorvej [m/m] 3,60 1,75 49% Installationer pr. meter af motorvej [Antal/m] 0,11 0,04 34% Byggeomkostninger pr. meter af motorvej [DKK/m] 4490, ,00 91% Indikator enhed 26 år 50 år Referencesystem [Mio. DKK] 156,97 202,27 Slidserende [Mio. DKK] 140,37 179,67 27

28 Cement Stabilitation CS (hydrophobic) 28

29 Compact Asphalt 29

30 Documentation System Asphalt GPS Mixing Plant (A) Transport (B) Paving (C) 30

31 Documentation System CS Spreader are equipped with weighting systems Spreading information (kg/m²) are combined via GPS to georeferenced datas Output are georeferenced maps and quality control documents Simplification of documentation 31

32 Summary Innovative pavement design is an interdisciplinary issue All elements must be investigated and analyzed Cost saving approach Development of new pavement and construction methods High investments during tender stage Objective Risk Management Use of new and innovative technologies on side 32

Table of Contents. Chapter 1 : Introduction 1. Chapter 2 : Structure and design 15

Table of Contents. Chapter 1 : Introduction 1. Chapter 2 : Structure and design 15 Table of Contents Chapter 1 : Introduction 1 1-1 Overview of Japan 1 1-1-1 Topography 1 1-1-2 Climate 1 1-1-3 Population 3 1-1-4 Economy 3 1-2 History and current status of roads in Japan 5 1-2-1 Road

More information

AUSTRIAN PAVEMENT DESIGN METHOD A CRITICAL REVIEW. FLEXIBLE PAVEMENT DESIGN WORKSHOP Ljubljana, Ljubljana, 2012

AUSTRIAN PAVEMENT DESIGN METHOD A CRITICAL REVIEW. FLEXIBLE PAVEMENT DESIGN WORKSHOP Ljubljana, Ljubljana, 2012 FLEXIBLE PAVEMENT DESIGN WORKSHOP Ljubljana, 2012 AUSTRIAN PAVEMENT DESIGN METHOD A CRITICAL REVIEW FLEXIBLE RONALD PAVEMENT BLAB & BERNHARD DESIGN HOFKOWORKSHOP Ljubljana, 2012 INSTITUTE OF TRANSPORTATION

More information

EINRIP. Specification and Construction Issues

EINRIP. Specification and Construction Issues EINRIP Specification and Construction Issues There are a significant number of changes in the Specification Not all issues can be discussed here A more detailed list of changes will be provided with bid

More information

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP INFRASTRUCTURE SERVICES Page 1 of 7 1.0 GRANULAR BASE AND SUB-BASE 1.1 DESCRIPTION.1 This section specifies requirements for supplying, producing, hauling placing and compacting processed gravel or quarried

More information

FULL - DEPTH RECYCLING OF ASPHALT PAVEMENTS WITH PORTLAND CEMENT

FULL - DEPTH RECYCLING OF ASPHALT PAVEMENTS WITH PORTLAND CEMENT FULL - DEPTH RECYCLING OF ASPHALT PAVEMENTS WITH PORTLAND CEMENT Dick Martin Pavement Recycling Specialist Road Recycling Council New England Region What is Full Depth Reclamation? FDR is the rehabilitation

More information

Advantages of Full Depth Recycling

Advantages of Full Depth Recycling Definition of FDR re-use existing asphalt, base and subgrade material 6 12 (150 300 mm) to produce a new base course a new wearing surface is applied a stabilizer can be incorporated Advantages of Full

More information

Cutting-edge Wirtgen technology in successful operation on Interstate 81

Cutting-edge Wirtgen technology in successful operation on Interstate 81 Cold recycling: pioneering, economical, resource-efficient. Cutting-edge Wirtgen technology in successful operation on Interstate 81 JOBREPORTS ANDREFERENCES 02 03 Cold recycling Leading technology in

More information

SOM August 2009 Alaska

SOM August 2009 Alaska Asphalt Rubber Finishing Course (ARFC) The end of the road for the tire. The beginning of the road for a quieter, smoother Pavement. SOM August 2009 Alaska Jim Delton, State Materials Engineer, Arizona

More information

concrete upper layer George Vorobieff Head to Head International Presented by:

concrete upper layer George Vorobieff Head to Head International Presented by: Two layer paving with porous concrete upper layer Presented by: George Vorobieff Member, ASCP & ISCP Head to Head International Disclaimer: The opinions expressed in this presentation are those of the

More information

SEMINAR ON CEMENT AND CONCRETE APPLICATIONS ROADS 1 2 AUGUST 2018 JKR CREATE, MELAKA COLD IN PLACE RECYCLING (CIPR)

SEMINAR ON CEMENT AND CONCRETE APPLICATIONS ROADS 1 2 AUGUST 2018 JKR CREATE, MELAKA COLD IN PLACE RECYCLING (CIPR) SEMINAR ON CEMENT AND CONCRETE APPLICATIONS ROADS 1 2 AUGUST 2018 JKR CREATE, MELAKA COLD IN PLACE RECYCLING (CIPR) Empowered by science, inspired by humans CONTENTS : GENERAL DEFINATION WHERE TO USE PROCESS

More information

Roads and Transport Department Pavement Design 3 rd Year TYPES OF PAVEMENT FLEXIBLE AND RIGID PAVEMENT

Roads and Transport Department Pavement Design 3 rd Year TYPES OF PAVEMENT FLEXIBLE AND RIGID PAVEMENT TYPES OF PAVEMENT FLEXIBLE AND RIGID PAVEMENT There are two types of pavements based on design considerations i.e. flexible pavement and rigid pavement. Difference between flexible and rigid pavements

More information

MNDOT PAVEMENT DESIGN MANUAL

MNDOT PAVEMENT DESIGN MANUAL MNDOT PAVEMENT DESIGN MANUAL Chapter 9 truction and Rehabilitation Alternates MnDOT Pavement Engineer Date Contents Introduction... 1 900 Existing Pavement-Types... 2 910 Rehabilitation with HMA Overlay

More information

Revision of EU Green Public Procurement Criteria for Road Construction

Revision of EU Green Public Procurement Criteria for Road Construction Revision of EU Green Public Procurement Criteria for Road Construction Proposal of product scope and definition Elena Garbarino, Oliver Wolf (JRC IPTS Seville) Linda Høibye, Frans Christensen (COWI) March

More information

MAINTENANCE OF CRACKED PAVEMENTS WITHIN THE FORMAT PROJECT

MAINTENANCE OF CRACKED PAVEMENTS WITHIN THE FORMAT PROJECT MAINTENANCE OF CRACKED PAVEMENTS WITHIN THE FORMAT PROJECT M.L. Antunes 1, A. van Dommelen 2, P. Sanders 3, J.M. Balay 4 and E.L. Gamiz 5 (1) Laboratório Nacional de Engenharia Civil, Portugal (2) Rijkswaterstaat,

More information

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS 219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,

More information

Széchenyi István University Faculty of Architecture, Civil Engineering and Transport Sciences Department of Transport Infrastructure.

Széchenyi István University Faculty of Architecture, Civil Engineering and Transport Sciences Department of Transport Infrastructure. Széchenyi István University Faculty of Architecture, Civil Engineering and Transport Sciences Department of Transport Infrastructure Pavement failures Themes of lecture Failure types of pavements Different

More information

PAVEMENT ASSET MANAGEMENT PRACTICE IN AUSTRIA TOLL ROAD NETWORK. Christian Honeger ASFINAG Service Ltd Tokyo, 1. November 2017

PAVEMENT ASSET MANAGEMENT PRACTICE IN AUSTRIA TOLL ROAD NETWORK. Christian Honeger ASFINAG Service Ltd Tokyo, 1. November 2017 PAVEMENT ASSET MANAGEMENT PRACTICE IN AUSTRIA TOLL ROAD NETWORK Christian Honeger ASFINAG Service Ltd Tokyo, 1. November 2017 Content ASFINAG organisation and figures Approach in pavement management AUSTRIA

More information

ROAD AND RAILWAY CONSTRUCTION

ROAD AND RAILWAY CONSTRUCTION MSC COURSE 2016/2017 AUTUMN SEMESTER ROAD AND RAILWAY CONSTRUCTION PAVING TECHNOLOGIES SZÉCHENYI ISTVÁN UNIVERSITY Dr. Péter FÜLEKI assistant professor 7th lecture s theme Paving technologies Earthwork

More information

An Overview of Low Cost Pavement Alternatives in Canada

An Overview of Low Cost Pavement Alternatives in Canada An Overview of Low Cost Pavement Alternatives in Canada Venkat Lakkavalli P. Eng., M. Sc. Leader, Pavement Engineering The City of Calgary Alberta, Canada Acknowledgement Acknowledge Authors, Co-authors

More information

7.1 Flexible Pavement Design. 7.2 Rigid Pavement Design TRANSPORTATION SYSTEM ENGINEERING 1, 61360

7.1 Flexible Pavement Design. 7.2 Rigid Pavement Design TRANSPORTATION SYSTEM ENGINEERING 1, 61360 7.1 Flexible Pavement Design 7.2 Rigid Pavement Design 1 Highway pavements are divided into two main categories: Flexible -Bituminous concrete Rigid -Portland cement concrete- Flexible pavements usually

More information

The Danish Pavement Design Guide. Gregers Hildebrand, Danish Road Directorate

The Danish Pavement Design Guide. Gregers Hildebrand, Danish Road Directorate The Danish Pavement Design Guide Gregers Hildebrand, Danish Road Directorate New Danish design guide Modern tool based on sound scientific principles Designs for roads at all levels Designs in three ways:

More information

HAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003

HAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003 HAWAII DEPARTMENT OF TRANSPORATION HIGHWAYS DIVISION PAVEMENT PREVENTIVE MAINTENANCE GUIDELINES JUNE 2003 Reviewed and accepted by FHWA on September 29, 2003 Note: Guidelines was revised on to correct

More information

Dr. Kieran Feighan PMS Pavement Management Services Ltd. October 9, 2013

Dr. Kieran Feighan PMS Pavement Management Services Ltd. October 9, 2013 Guidelines for Development of Pavement Improvement/Renewal Schemes Dr. Kieran Feighan PMS Pavement Management Services Ltd. October 9, 2013 Pavement Management System dtims Data Repository Condition Data

More information

GEOSYNTHETICS AND. Design and Construction of Pavements Using Geosynthetics-II

GEOSYNTHETICS AND. Design and Construction of Pavements Using Geosynthetics-II GEOSYNTHETICS AND REINFORCED SOIL STRUCTURES Design and Construction of Pavements Using Geosynthetics-II P f K R j l Prof K. Rajagopal Department of Civil Engineering IIT Madras, Chennai 600 036 e-mail:

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 00252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous

More information

TYPES OF PAVEMENT FLEXIBLE AND RIGID PAVEMENT

TYPES OF PAVEMENT FLEXIBLE AND RIGID PAVEMENT TYPES OF PAVEMENT FLEXIBLE AND RIGID PAVEMENT There are two types of pavements based on design considerations i.e. flexible pavement and rigid pavement. Difference between flexible and rigid pavements

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

ROAD CONSTRUCTION AND

ROAD CONSTRUCTION AND Unit ID 1137 Domain ROAD CONSTRUCTION AND MAINTENANCE - INSPECTION Title: Demonstrate knowledge of road construction and maintenance methods as an Inspector Level: 3 Credits: 10 Purpose This unit standard

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

STRESS RELIEVING FUNCTION OF PAVING FABRICS WHEN USED IN NEW ROAD CONSTRUCTION

STRESS RELIEVING FUNCTION OF PAVING FABRICS WHEN USED IN NEW ROAD CONSTRUCTION STRESS RELIEVING FUNCTION OF PAVING FABRICS WHEN USED IN NEW ROAD CONSTRUCTION E. Ramberg Steen Fibertex A/S, Constructions, Aalborg, Denmark Abstract In order to increase the bearing capacity of roadbases

More information

ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING

ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING AFTER NOVEMBER 1, 2008 ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous

More information

Althon slot channels Althon

Althon slot channels Althon Effectively innovative. Althon slot channels - the solid drainage system! Althon slot channels Althon Drainage systems Althon slot channels high resilience high performance! The Althon slot channel is

More information

100 Pavement Requirements Pavement Design Concepts 200-1

100 Pavement Requirements Pavement Design Concepts 200-1 Table of Contents 100 Pavement Requirements 100-1 101 Design Responsibility 100-1 102 Structural Design Period 100-1 102.1 Priority System Design Period... 100-1 102.2 General System Design Period... 100-2

More information

DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL. Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents

DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL. Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents DESIGN BULLETIN #77/2013 AMENDMENTS TO PAVEMENT DESIGN MANUAL Re: Updated Requirements for Agency Practice, Design Inputs and Design Report Contents Introduction This design bulletin provides a number

More information

Full Depth Reclamation

Full Depth Reclamation Full Depth Reclamation FDR Has Been Around A While 2 3 What is Full Depth Reclamation (FDR)? Full Depth Reclamation is a pavement rehabilitation technique in which the full flexible pavement section and

More information

Introduction to Pavement Overlays

Introduction to Pavement Overlays Introduction to Pavement Overlays Course No: C02-046 Credit: 2 PDH J. Paul Guyer, P.E., R.A., Fellow ASCE, Fellow AEI Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980

More information

VDOT Pavement Recycling Initiative. Andy Babish, P.E. State Materials Engineer

VDOT Pavement Recycling Initiative. Andy Babish, P.E. State Materials Engineer Andy Babish, P.E. State Materials Engineer Pavement Recycling Initiative Background Goal and Key Components Going Forward 2 Initiative Background - 2008: 3 Full Depth Reclamation trial sections constructed

More information

Ania M. Anthony, M.Sc., P. Eng. Senior Surfacing Engineer Saskatchewan Ministry of Highways and Infrastructure

Ania M. Anthony, M.Sc., P. Eng. Senior Surfacing Engineer Saskatchewan Ministry of Highways and Infrastructure Techniques for Low Volume Roads in Saskatchewan Ania M. Anthony, M.Sc., P. Eng. Senior Surfacing Engineer Saskatchewan Ministry of Highways and Infrastructure The Western Canada Pavement Workshop Feb 1-2,

More information

Job Reports WR 240 / WR 240 i. Performing to highest quality standards whatever the job

Job Reports WR 240 / WR 240 i. Performing to highest quality standards whatever the job Job Reports WR 240 / WR 240 i Performing to highest quality standards whatever the job Construction of a dam for effective fl ood control Job description In the event of floods, a dam of up to 6 m in height

More information

Airport Pavement Rehabilitation 2015 Minnesota Airports Conference

Airport Pavement Rehabilitation 2015 Minnesota Airports Conference Airport Pavement Rehabilitation 2015 Minnesota Airports Conference St. Cloud, Minnesota April 16, 2015 David L. Rettner, P. E. American Engineering Testing, Inc. Pavement Life Cycle Routine Maintenance

More information

A Surveying Design of Overlay Thickness of Rigid Pavements Using Road Software

A Surveying Design of Overlay Thickness of Rigid Pavements Using Road Software A Surveying Design of Overlay Thickness of Rigid Pavements Using Road Software Priya M S 1, Nithil 2 J S Vishwas 3 P.G. Student, Department of Civil Engineering, JNN College of Engineering, Shimoga, India

More information

Passionate about fibres. Stabilizing asphalt: TECHNOCEL TOPCEL. Cellulose fibres. Pellets

Passionate about fibres. Stabilizing asphalt: TECHNOCEL TOPCEL. Cellulose fibres. Pellets Passionate about fibres Stabilizing asphalt: TECHNOCEL Cellulose fibres TOPCEL Pellets TECHNOCEL TOPCEL SMA - A Long Life Pavement leads the way Stone Mastic Asphalt (SMA) was developed in Germany 30 years

More information

Pavement Management Techniques to Improve Network Performance

Pavement Management Techniques to Improve Network Performance Pavement Management Techniques to Improve Network Performance Jeremy Gregory and CSHub Research Team Ohio Transportation Engineering Conference October 10, 2017 The US is not sufficiently investing in

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 90P-270 Sheet 1 of 5 SECTION PAVEMENT PATCHING Page 591, Section. Delete the Section and replace with

More information

Highway construction C 5

Highway construction C 5 Highway construction C 5 Contents Equipments used in Highway Construction Construction of Earth Roads Gravel Roads Water Bound Macadam Roads Bituminous Pavements Cement Concrete Pavements Equipment used

More information

Stabilisation. Definition In Situ Soil Stabilisation. Today s Discussion. Benefits of Stabilisation Lime & cement has been found in the Roman Roads

Stabilisation. Definition In Situ Soil Stabilisation. Today s Discussion. Benefits of Stabilisation Lime & cement has been found in the Roman Roads Definition In Situ Soil Stabilisation In- Situ process of mixing addi onal material to improve the physical or chemical proper es of pavement materials to suit par cular pavement design or construc on

More information

ST. TAMMANY PARISH COUNCIL ORDINANCE

ST. TAMMANY PARISH COUNCIL ORDINANCE ST. TAMMANY PARISH COUNCIL ORDINANCE ORDINANCE CALENDAR NO: 5563 COUNCIL SPONSOR: DEAN/BRISTER INTRODUCED BY: MR. BELLISARIO ORDINANCE COUNCIL SERIES NO: PROVIDED BY: DEVELOPMENT SECONDED BY: MR. STEFANCIK

More information

Cold-in-Place Recycling

Cold-in-Place Recycling Design Manual Chapter 5 - Roadway Design 5J - Pavement Rehabilitation Program 5J-2 Cold-in-Place Recycling A. General Cold-in-place recycling (CIR) is the process of recycling an asphalt pavement in-place

More information

1.01 The work shall consist of spreading and compacting crushed and pugmilled aggregate on a prepared surface.

1.01 The work shall consist of spreading and compacting crushed and pugmilled aggregate on a prepared surface. 3505 - SPECIFICATION FOR GRANULAR BASE COURSE 3505 - l DESCRIPTION 1.01 The work shall consist of spreading and compacting crushed and pugmilled aggregate on a prepared surface. 1.02 The following definitions

More information

SLURRYPAVER AND NOVASEALER COLD ASPHALT SLURRY APPLICATION MACHINERY

SLURRYPAVER AND NOVASEALER COLD ASPHALT SLURRY APPLICATION MACHINERY SLURRYPAVER AND NOVASEALER COLD ASPHALT SLURRY APPLICATION MACHINERY Cold asphalt slurries: a modern solution to road maintenance Cold asphalt slurries have been in constant progress for the past 30 years.

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

ROADEX RESEARCH PROJECT: Road Widening

ROADEX RESEARCH PROJECT: Road Widening ROADEX RESEARCH PROJECT: Road Widening Petri Varin Roadscanners Oy Research Project: Widening of Roads Background: The cost effective widening of roads is a major issue facing the ROADEX Partners. State-of-the-art

More information

BEHAVIOUR OF AN OLD EPS LIGHT-WEIGHT FILL AT VAMMALA, FINLAND. Seppo Saarelainen 1 and Heikki Kangas 2

BEHAVIOUR OF AN OLD EPS LIGHT-WEIGHT FILL AT VAMMALA, FINLAND. Seppo Saarelainen 1 and Heikki Kangas 2 BEHAVIOUR OF AN OLD EPS LIGHT-WEIGHT FILL AT VAMMALA, FINLAND Seppo Saarelainen 1 and Heikki Kangas 2 ABSTRACT Characteristics of a pavement and its EPS compensation fill were investigated in the fall

More information

SECTION STORM DRAIN

SECTION STORM DRAIN PART 1 - GENERAL 1-01 SECTION INCLUDED A. Furnishing and installing storm drainage facilities, including pipe, cleanout, manhole structures and inlet structures. 1-02 RELATED SECTIONS A. Division 00 Contract

More information

PAVEMENT MANAGEMENT SYSTEM

PAVEMENT MANAGEMENT SYSTEM PAVEMENT MANAGEMENT SYSTEM IMPORTANCE OF PAVEMENT MANAGEMENT SYSTEM Road System Deficient to Meet the Traffic Demand Improper Planning Deficiencies in Road Geometrics Poor Construction and Maintenance

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

Over-coming differential settlement in soft grounds using Floating Semi-Rigid Pavement

Over-coming differential settlement in soft grounds using Floating Semi-Rigid Pavement 14 th REAAA Conference 2013, 26 28 March 2013, Kuala Lumpur, Malaysia Over-coming differential settlement in soft grounds using Floating Semi-Rigid Pavement Dato Ir Dr Safry Kamal Ahmad, Dr Wu DQ, Francis

More information

Special track. Jarosław Zwolski, PhD CE. 1. Slab track. 2. Track on bridges

Special track. Jarosław Zwolski, PhD CE. 1. Slab track. 2. Track on bridges Special track 1. Slab track 2. Track on bridges Jarosław Zwolski, PhD CE Genesis 1. Requirement of plastic deformation elimination in track. 2. Elimination of the ballast layer as the most flexible element

More information

Item P-219 Recycled Concrete Aggregate Base Course

Item P-219 Recycled Concrete Aggregate Base Course Item P-219 Recycled Concrete Aggregate DESCRIPTION 219-1.1 This item consists of a base course composed of recycled concrete aggregate, crushed to meet a particular gradation, constructed on a prepared

More information

Select Subgrade Material, Compacted

Select Subgrade Material, Compacted 314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.

More information

MICROSURFACING ON CONCRETE PAVEMENT

MICROSURFACING ON CONCRETE PAVEMENT EMULSION BITUMEN APPLICATIONS MICROSURFACING ON CONCRETE PAVEMENT S.SOLIMAN Dr.Engineer Senior Technical Advisor INGEVITY Almaty 16 & 17 of August 2018. Summary : - Reminder Emulsion applications - Slurry

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

asphalt applications Asphalt surfacings for high stress areas mpa asphalt Asphalt Information Service Mineral Products Association

asphalt applications Asphalt surfacings for high stress areas mpa asphalt Asphalt Information Service Mineral Products Association asphalt applications 6 Asphalt surfacings for high stress areas Asphalt Information Service mpa asphalt November 2009 Mineral Products Association Introduction Information Sheet 2 in this series, Construction

More information

Concrete Pavements Tour of European Practice

Concrete Pavements Tour of European Practice Concrete Pavements Tour of European Practice Hermann Sommer Vienna, Austria Salina, KS October 15-16, 2008 Roundabouts Urban roads Agricultural roads Minor roads Main application: heavy duty motorways

More information

Sustainable Pavement Design in Christchurch Southern Motorway

Sustainable Pavement Design in Christchurch Southern Motorway Sustainable Pavement Design in Christchurch Southern Motorway Dr Bryan Pidwerbesky General Manager Technical Fulton Hogan Ltd, PO Box 39185, Christchurch 8545, New Zealand Tel: +64 3 357 0615 email: bryan.pidwerbesky@fultonhogan.com

More information

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material

More information

B HOT MIX, HOT LAID ASPHALTIC CONCRETE OPSS 313

B HOT MIX, HOT LAID ASPHALTIC CONCRETE OPSS 313 B 313-1 OPSS 313 313-1.1 GENERAL HL,, Mixture, and/or Mix, is hot mixed, hot laid asphaltic concrete, used for pavement construction and other uses. 1. HL 1 This dense graded surface course mix is used

More information

SEMI-FLEXIBLE PAVEMENT SYSTEMS FOR HEAVY DUTY PAVEMENT SECTIONS

SEMI-FLEXIBLE PAVEMENT SYSTEMS FOR HEAVY DUTY PAVEMENT SECTIONS SEMI-FLEXIBLE PAVEMENT SYSTEMS FOR HEAVY DUTY PAVEMENT SECTIONS Pavement Design Methodology January 2002 Job 2426002 Ref.No. RP001.doc Prepd. JHH Edition 1 Checked JSU Date 2002-01-31 Appd. JHH RAMBØLL

More information

313-1 HOT MIX ASPHALT - OPSS.PROV 313

313-1 HOT MIX ASPHALT - OPSS.PROV 313 313-1 - OPSS.PROV 313 313-1.1 GENERAL Hot mix asphalt consists of several mix types, which are grouped into two categories: Stone Mastic Asphalt and Superpave as detailed below. The type of hot mix asphalt

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3 CITY OF TORONTO TS 3.70 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS 3.70.01 SCOPE...3 TS

More information

GENERAL NOTES ROADWAY CONSTRUCTION RD0001-1A ISSUED:2017 REVISED: --

GENERAL NOTES ROADWAY CONSTRUCTION RD0001-1A ISSUED:2017 REVISED: -- ROADWAY CONSTRUCTION NOTES 1. ALL RIGHT-OF-WAY OTHER THAN ROADWAY AREAS SHALL BE SODDED. ALL SLOPE STEEPER THAN 6:1 SHALL REQUIRE SODDING. THE CITY RESERVES THE RIGHT TO REQUIRE SODDING IN SPECIAL AREAS

More information

Pavement Maintenance in Japan

Pavement Maintenance in Japan Pavement Maintenance in Japan Kazuyuki Kubo Head, Pavement and Earthworks Division National Institute for Land and Infrastructure Management Ministry of Land, Infrastructure, Transport and Tourism 1. Present

More information

Cold Foam In-Place Recycling (CIR)

Cold Foam In-Place Recycling (CIR) Cold Foam In-Place Recycling (CIR) FONSECA/McELROY GRINDING CO., INC. Cold Foam CIR CIR Method/Foamed Asphalt Cold In-Place Recycling Foamed Asphalt Hot Bitumen Water Air Foamed Asphalt The larger surface

More information

SECTION BITUMINOUS CONCRETE PAVING

SECTION BITUMINOUS CONCRETE PAVING PART 1 GENERAL 1.1 SECTION INCLUDES: SECTION 02400 BITUMINOUS CONCRETE PAVING A. The intent of this specification section is to provide requirements for materials, equipment, and methods for constructing

More information

Pavement Rehabilitation Options in Indiana. Dave Holtz Tommy E. Nantung Lisa Egler-Kellems Indiana Department of Transportation

Pavement Rehabilitation Options in Indiana. Dave Holtz Tommy E. Nantung Lisa Egler-Kellems Indiana Department of Transportation Pavement Rehabilitation Options in Indiana Dave Holtz Tommy E. Nantung Lisa Egler-Kellems Indiana Department of Transportation Decision to select treatment options Rehabilitation Treatment Overview Objectives

More information

Implementing An effective Airport Pavement Management System

Implementing An effective Airport Pavement Management System Implementing An effective Airport Pavement Management System Hazim M Abdulwahid 13 th, MSC, MBA International O&M Conference in the Arab Countries,17-19 Nov 2015 1 Content What is Pavement Engineering

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 02222 - EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES PART 1 - GENERAL 1.01 SECTION INCLUDES A. Excavating trenches for the installation of utilities and stormwater detention facilities. B.

More information

Spectrum of Axles Approach

Spectrum of Axles Approach Spectrum of Axles Approach Typical Axle Load Spectrum Axle Load (kn) Single Number of Axles Tandem Tridem Quad 50 60 5,000 400 100 5 61 80 3,000 2,000 500 10 81 100 200 5,000 800 30 101 120 50 4,000 1,000

More information

Design Criteria and Testing for Cold In-Place Recycling. Todd Thomas Technical Services Engineer Colas Solutions, Inc.

Design Criteria and Testing for Cold In-Place Recycling. Todd Thomas Technical Services Engineer Colas Solutions, Inc. Design Criteria and Testing for Cold In-Place Recycling Todd Thomas Technical Services Engineer Colas Solutions, Inc. August 29, 2012 Presentation Topics CIR description Project selection criteria for

More information

NZQA registered unit standard version 1 Page 1 of 5. Demonstrate knowledge of equipment and processes for constructing slurry surfacings

NZQA registered unit standard version 1 Page 1 of 5. Demonstrate knowledge of equipment and processes for constructing slurry surfacings Page 1 of 5 Title Demonstrate knowledge of equipment and processes for constructing slurry surfacings Level 4 Credits 6 Purpose People credited with this unit standard are able to demonstrate knowledge

More information

Revision Date Prepared By Reviewed By Approved By Remarks. Draft Jan 07 Paul Weedon Tim Neville Draft

Revision Date Prepared By Reviewed By Approved By Remarks. Draft Jan 07 Paul Weedon Tim Neville Draft SOUTH IMPROVEMENT ALLIANCE DOCUMENT TYPE: REQUEST FOR WAIVER APPROVAL PROJECT DETAIL: PASSING LANE STRUCTURAL FILL MATERIAL LOCATION: NSW PASSING LANES PL13 TO PL17 DOC NUMBER: ART-PL16-REF-NM535-DES-TS-2000-D01

More information

Rehabilitation of Highway Pavements an Engineering Challenge

Rehabilitation of Highway Pavements an Engineering Challenge Rehabilitation of Highway Pavements an Engineering Challenge G eorge W. M ca lpin Transportation Consultant Rye, New Hampshire IN T R O D U C T IO N There is no question that our country is currently confronted

More information

Thomas Bennert, Rutgers University Robert Sauber, NJDOT (Retired) CAIT RUTGERS. NEAUPG October 6-7th, 2010 Saratoga Springs, NY

Thomas Bennert, Rutgers University Robert Sauber, NJDOT (Retired) CAIT RUTGERS. NEAUPG October 6-7th, 2010 Saratoga Springs, NY Thomas Bennert, Rutgers University Robert Sauber, NJDOT (Retired) NEAUPG October 6-7th, 2010 Saratoga Springs, NY Reconstruction of I295 consisting of old PCC Rubblization used for speed and cost Constructed

More information

COLD IN-PLACE RECYCLING (CIR) Starting with what is there i.e. in situ materials

COLD IN-PLACE RECYCLING (CIR) Starting with what is there i.e. in situ materials COLD IN-PLACE RECYCLING (CIR) Starting with what is there i.e. in situ materials Definitions: ARRA (Asphalt Recycling/Reclaiming Ass.) Cold In-Place Recycling (CIR) is the on-site recycling process to

More information

8.01. SUB TOTAL 1 1,168, ADD 16% VAT 187, TOTAL 1,356, Total Carried Forward to Form of Tender:

8.01. SUB TOTAL 1 1,168, ADD 16% VAT 187, TOTAL 1,356, Total Carried Forward to Form of Tender: Contract No WARD NAM AINAMOI WARD ROAD NAME 3.30 KM SUMMARY Bill No. Description Amount Preliminary and General Items 1.01 Allow a prime cost sum of Ksh.20,000 for Engineer's miscellaneous account and

More information

NEW AND INNOVATIVE MATERIALS FOR LONG LASTING ROAD INFRASTRUCTURE

NEW AND INNOVATIVE MATERIALS FOR LONG LASTING ROAD INFRASTRUCTURE NEW AND INNOVATIVE MATERIALS FOR LONG LASTING ROAD INFRASTRUCTURE MODIFIED BINDERS FOR IMPROVED PERFORMANCE OF HIGHWAYS TYPES OF POLYMERS Plastomers High stiffness - low ductility Typical kinds - LDPE,

More information

Concrete Roads. Environmental aspects Economic aspects Social benefits Other sustainable applications of cement & concrete.

Concrete Roads. Environmental aspects Economic aspects Social benefits Other sustainable applications of cement & concrete. John Nichols Concrete Roads Environmental aspects Economic aspects Social benefits Other sustainable applications of cement & concrete www.eupave.eu A4 30 pages Environmental aspects of concrete roads

More information

TOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION. June 1984

TOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION. June 1984 1 TOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION June 1984 1. DEFINITIONS APPROVAL, APPROVED, ACCEPTED OR WORDS OR TERMS OF SIMILAR MEANING: Written approval of the Highway Superintendent. BASE

More information

Published in Roading Geotechnics 98, Institute of Professional Engineers, Auckland (1998), pp

Published in Roading Geotechnics 98, Institute of Professional Engineers, Auckland (1998), pp APPLICATIONS OF MECHANISTIC PAVEMENT DESIGN IN NEW ZEALAND (II) Case Histories Comparing Design Prediction with Post Construction Measurement and Analysis Graham Salt, Tonkin & Taylor Ltd William Gray,

More information

Flexible pavement thickness design by Haryati Yaacob (fka, utm)

Flexible pavement thickness design by Haryati Yaacob (fka, utm) Flexible pavement thickness design by Haryati Yaacob (fka, utm) Flexible pavement thickness design Flexible Pavement Structure Factors to be Considered in Designing Flexible Pavement Thickness Thickness

More information

National AustStab Guidelines Pavement design guide for a cement stabilised base layer for light traffic [Version B 31 July 2012]

National AustStab Guidelines Pavement design guide for a cement stabilised base layer for light traffic [Version B 31 July 2012] National AustStab Guidelines Pavement design guide for a cement stabilised base layer for light traffic [Version B 31 July 2012] The Association is a non-profit organisation sponsored by organisations

More information

REHABILITATION OF RUNWAY 11/29 AT CFB BAGOTVILLE. Presented by: Marla Hughesman CAPTG Sunday Workshop 12 September 2010

REHABILITATION OF RUNWAY 11/29 AT CFB BAGOTVILLE. Presented by: Marla Hughesman CAPTG Sunday Workshop 12 September 2010 REHABILITATION OF RUNWAY 11/29 AT CFB BAGOTVILLE Presented by: Marla Hughesman CAPTG Sunday Workshop 12 September 2010 CFB BAGOTVILLE Located approximately 400 km NE of Montreal One of the Canadian Forces

More information

TRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA

TRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA 2008/09 $52.0 M 85% SELF-PERFORMED Widen 12 miles of Interstate 10 to six lanes including the reconstruction

More information

Cement Stabilized Aggregate Base

Cement Stabilized Aggregate Base Supplemental Technical Specification for June 2, 2008 Cement Stabilized Aggregate Base SCDOT Designation: SC-M-308 (06/08) 1. SCOPE 1.1. Cement Stabilized Aggregate Base (CSAB) consists of aggregate, Portland

More information

Tasman Retaining Wall System

Tasman Retaining Wall System Tasman Retaining Wall System The Tasman Retaining Wall System incorporates purpose made corners and capping units to provide classical reconstructed stone retaining walls for any landscape situation. From

More information

Fiji Roads Authority GUIDE to PAVEMENT DESIGN. Supplement to the AUSTROADS Guide to the Structural Design of Road Pavements

Fiji Roads Authority GUIDE to PAVEMENT DESIGN. Supplement to the AUSTROADS Guide to the Structural Design of Road Pavements Fiji Roads Authority GUIDE to PAVEMENT DESIGN Supplement to the AUSTROADS Guide to the Structural Design of Road Pavements TA-8777 FIJI 1 VERSION 2 June 2018 TA-8777 FIJI 2 VERSION 2 June 2018 1.0 Introduction

More information

Asphalts in road construction. Edited by Dr Robert N. Hunter. Thomas Telford, London

Asphalts in road construction. Edited by Dr Robert N. Hunter. Thomas Telford, London Asphalts in road construction Edited by Dr Robert N. Hunter Thomas Telford, London Contents 1. Assessing aggregates for use in asphalts 1 1.1. 1.2. Preamble Why test aggregates? 1 2 1.3. Classifying aggregates

More information

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL )

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL ) MINIMUM RATE 1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to

More information

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL )

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL ) 1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to top of fill starting

More information